Professional Documents
Culture Documents
Schedule:
2014: Detailled design / Demolition / Ground preparations
2015: Foundation works / Framework / Enveloping
2017: Scheduled completion Q2
• Strategy
- An as lean project as possible in design and construction.
- Lean on all levels and in all phases.
• Tools
- BiM
- dRofus (room functional database)
GENERAL PROJECT PRINCIPALS
«LEVEL 2 & 3»
KEYPOINTS (NEW)
PROCESSES (7)
Everyone developed the PCP-level-1-map together.
Everyone’s «on the same page».
Everyone has «the same mind».
Everyone has the same objectives.
CONTINOUS FLOW
TO THE VIRTUAL
BUILDING (BIM) AND
THE PHYSICAL
BUILDING
TOPICS WITH
ISSUSES & OWNERS
SLICING THE ELEPHANT: MINOR PIECES / TOPICS
DEADLINE
«PRODUCT»/OUTPUT
ISSUES:
- RESOURCES
- TIME
- INPUT
OWNER
TOPIC
«TAKT and TRAIN»
2-WEEK «TAKT»
INCL.
3-DAYS BIG-ROOM
CO-LOCATION
2 WEEK TAKT /
WORK PROCEDURE
KHIB LEAN STEP BY STEP
1) Pre-Seminar
Discussing and preparing a lean construction strategy.
Getting to know the building.
2) Product Creation Process (w/ Porsche Consulting)
Project top level overview.
Mindshifting.
3) Now what ..? A design train and takt ..?
4) Developing and improving the lean design process
«Unfamiliar territory!»
5) Extended use of lean takt planning and construction with contractors.
- Contract review.
- Contract handover (from design to contractors).
- Frontloading (putting the puzzle together).
- Lean construction.
6) Lessons learned
COMBINING THE LEVELS
LEVEL 2 PROJECT
DESIGNPLAN
(TOPIC OVERVIEW)
PROCESSES (7)
3-DAYS BIG-ROOM CO-LOCATION
TOPIC
OWNER
(If time…)
Hans Thomas Holm / Statsbygg
• Projectmanager with Statsbygg since 2007.
• Projectmanager for KHiB since June 2013.
• Email: htho@statsbygg.no
• Cell-phone: +47 - 915 73 626