CHECKLIST OF MEP INSTALLATION

DISCOVERY & CONVENTION HOTEL ANCOL PROJECT

No Job Description ROOM................


A. ELECTRICAL
1 MCB BOX
2 BREAKER 20A
3 BREAKER 16A
4 BREAKER 10A
5 BREAKER 6A
6 KONTAKTOR
7 ELCB 16A
8 RELAY MY4
9 Terminal Kasuga TR 20
10 Terminal Box 200X200X100
11 Piping Conduit 20mm for Socket and Lighting
12 Piping Conduit 25mm For cable Feeder
13 Wiring cable 3x2,5mm for Socket & Lighting
14 Wiring FEEDER 3X4mm
15 Wiring Cable AWG 16 FOR Thermostat
16 Wiring NYMHY 2X1,5mm for Relay to Thermostat
17 Wiring NYA 5X2,5mm FCU to Terminal Box
18 Installation Keytag
19 Installation Thermostat
20 Continuity test
21 Megger Test
22 Testing Commisioning / Function Test

Mark [√] if done

Approved by, Acknowledged by, Prepared by,


PT Skemanusa Consultama Teknik Discovery Hotel & Convention Ancol PT Hamanroko

(...............................) (................................) (................................)


Date : ……………… Date : ………………. Date :……………….
CHECKLIST OF MEP INSTALLATION
DISCOVERY & CONVENTION HOTEL ANCOL PROJECT

No Job Description ROOM.................


A. HVAC
1 Pemasangan FCU
2 Pemasangan Supply Air Ducting
3 Pemasangan Return Air Ducting
4 Pemasangan Grill Return
5 Pemasangan Grill Supply
6 Pemasangan Dumper Duct FA
7 Pemasangan Round Duct FA
8 Pemasangan Flexible FA
9 Pemasangan Exhaust Toilet
10
11
12
13
14
15
16
17
18
19
20

Mark [√] if done

Approved by, Acknowledged by, Prepared by,


PT Skemanusa Consultama Teknik Discovery Hotel & Convention Ancol PT Hamanroko

(...............................) (................................) (................................)


Date : ……………… Date : ………………. Date :……………….
CHECKLIST OF MEP INSTALLATION
DISCOVERY & CONVENTION HOTEL ANCOL PROJECT

No Job Description ROOM....................


A. PLUMBING
1 Bongkar Closet Existing
2 Bongkar Wastapel Existing
3 Bongkar Riser Existing
4 Instalasi C.W
5 Instalasi Pipa H.W
6 Isolasi Hot Water
7 Instalasi Pipa CHWS
8 Instalasi Pipa CHWR
9 Ciping Dinding
10 Sapouting
11 Relokasi Pipa Air Bongkar
12 Testing
13 Isolasi Pipa CHWS / CHWR
14 Instal Asesoris Pipa FCU
15
16
17
18
19
20
21
22
23
24
25
Mark [√] if done

Approved by, Acknowledged by, Prepared by,


PT Skemanusa Consultama Teknik Discovery Hotel & Convention Ancol PT Hamanroko

(...............................) (................................) (................................)


Date : ……………… Date : ………………. Date :……………….