Fortnightly Progress Report No 3

Progress report of Teesta III in respect of Gates and Hoists


dated 16-10-2009
Sr. no Description Engineering Fabrication
Target Actual Target

1 - 3 - 2009 to
A Diversion Tunnel
3 - 3 - 2010

(i) Stoplogs
a) 2nd stage embedded parts completed

b) Stoplog Leaves 8 nos completed 30-9-2009

d) Lifting beam 1 no. completed 30-9-2009

c) Monorail crane supporting


structure 8 columns and crane completed 30-9-2009
beam

( ii ) Spillway Radial gate

a) 2nd stage embedded parts In progress 31-08-210

b) Radiaal gate
In Progress
c) Hydraulic Hoist.

( ii ) Stoplogs Spillway Radial gate 31-08-210

a) 2nd stage embedded parts

b) Stoplog Leaves 8 nos To be


started in
the month
d) Lifting beam 1 no. of Nov.09

c) Gantry crane for operation

B Order for Main Gates and Hoists

(i) Technical evaluation 31 - 8 - 2009 Comleted

( ii ) Placement of Order 30 - 9 - 2009 Commercial bids under evaluat

C Order for Butterfly Valves


(i) Calling of tenders 15 - 9 - 2009 Tenders called from 5 manufactur

( ii ) Technical Evaluation 25 - 11- 2009 Under progres

( iii ) Placement of Order 20-12-2009


ct of Gates and Hoists Progress report o

Fabrication Supply Erection Sr. no


Actual Target Actual Target Actual

(i)
15-9-2009 13-9-2009 15-10-2009

7nos. completed 26-10-2009

80% completed

( ii )

30-9-2010 31-12-2010

30-9-2010 31-12-2010 ( ii )

(i)

Commercial bids under evaluation with Abir. ( ii )

C
Tenders called from 5 manufacturers (i)

Technical offer received from two manufacturers. ( ii )

( iii )
Fortnightly Progress Report No 4
Progress report of Teesta III in respect of Gates and Hoists
dated 16-10-2010
Description Engineering Fabrication Supply Erection
Target Actual Target Actual Target Actual Target Actual
2-3-
2009 to
Diversion Tunnel
3-3-
2010
Stoplogs
a) 2nd stage embeddecompleted 15-9-2010 13-9-2010 15-10-2010

b) Stoplog Leaves 8 ncompleted 30-9-2009


7nos. completed
26-10-2010

c)
d) Lifting beam 1 no. completed 30-9-2009 -
Monorail
crane
supportin
g completed 30-9-2009
80% completed
structure
8 columns
and crane
Spillway
beamRadial gate

a) 2nd stage embeddeIn progress 31-08-210 30-9-2010 31-12-2010

b) Radiaal gate
In Progress
c) Hydraulic Hoist.

Stoplogs Spillway Radial gate 31-08-210 30-9-2010 31-12-2010

a) 2nd sta

b) Stoplog Leaves 8 n To be
started in
the month
d) Lifting beam 1 no. of Nov.10

c) Gantry
crane for
operation

Order for Main Gates and Hoists

Technical e32 - 8 - 2009Comleted

Placement of Order
30 - 9 - 2009 Commercial bids under evaluation with Abir.

Order for Butterfly Valves


Calling of tenders
15 - 9 - 2009 Tenders called from 5 manufacturers

Technical Evaluation
26 - 11- 2009 Under progres Technical offer received from two manufacturers.

Placement of Order
20-12-2010
Fortnightly Progress Report No 4
Progress report of Teesta III in respect of Gates and Hoists-HM Equipment.
Dated 16-10-2009
Sr. no Description Engineering Fabrication
Target Actual Target Actual
A Diversion Tunnel
(i) Stoplogs
a) 2nd stage embedded parts completed

All 8nos.
b) Stoplog Leaves 8 nos completed 30-9-2009
1 - 3 -2009 completed
to
d) Lifting beam 1 no. 31 - 07 - 2009 completed 30-9-2009 In progress

c) Monorail crane supporting


structure 8 columns and crane completed 30-9-2009
beam

( ii ) Spillway Radial gate

a) 2nd stage embedded parts In progress 31-08-2010


1 - 3 - 2009
to
b) Radiaal gate 3-3-
2010 In Progress
c) Hydraulic Hoist.

( ii ) Stoplogs Spillway Radial gate 31-08-210

a) 2nd stage embedded parts


To be
started in
b) Stoplog Leaves 8 nos
the month
of Nov.09
d) Lifting beam 1 no.

c) Gantry crane for operation

B Order for Main Gates and Hoists

(i) Technical evaluation 31 - 8 - 2009 Completed

Commercial bids under evaluation with Abir. Placement of


( ii ) Placement of Order 30 - 9 - 2009
for 20th Nov. 2009
C Order for Butterfly Valves

(i) Calling of tenders 15 - 9 - 2009 Completed Tenders called from 5 manufacturers

( ii ) Technical Evaluation 25 - 11- 2009 Under progres Technical off

( iii ) Placement of Order 20-12-2009


M Equipment.

Supply Erection Remarks


Target Actual Target Actual

Erection to start along with civil


15-9-2009 13-9-2009 15-10-2009
structures

Shall be despatched after issue of


26-10-2009
MDCC by 5th Nov. 2009

To be completed by 10-11-2009

Completed except two columns.


Completion by 10th Nov. 2009

30-9-2010 31-12-2010

30-9-2010 31-12-2010

tion with Abir. Placement of order now targeted


or 20th Nov. 2009
m 5 manufacturers

Technical offer received from two manufacturers under evaluation..


Fortnightly Progress Report No 5
Progress report of Teesta III in respect of Gates and Hoists-HM Equipment.
Dated 16-11-2009
Engineering Fabrication
Sr. no Description
Target Actual Target Actual
A Diversion Tunnel
(i) Stoplogs
a) 2nd stage embedded parts completed

All 8nos.
b) Stoplog Leaves 8 nos completed 30-9-2009
1 - 3 -2009 completed
to
d) Lifting beam 1 no. 31 - 07 - 2009 completed 30-9-2009 In progress

c) Monorail crane supporting


structure 8 columns and crane completed 30-9-2009 completed
beam

( ii ) Spillway Radial gate

a) 2nd stage embedded parts In progress 31-08-2010


1 - 3 - 2009
to
b) Radiaal gate 3-3-
2010 In Progress
c) Hydraulic Hoist.

( ii ) Stoplogs Spillway Radial gate 31-08-2010

a) 2nd stage embedded parts


To be
started in
b) Stoplog Leaves 8 nos
the month
of Nov.09
d) Lifting beam 1 no.

c) Gantry crane for operation

B Order for Main Gates and Hoists

(i) Technical evaluation 31 - 8 - 2009 Completed

Commercial bids under evaluation with Abir. Placement of


( ii ) Placement of Order 30 - 9 - 2009
for 30th Nov. 2009
C Order for Butterfly Valves

(i) Calling of tenders 15 - 9 - 2009 Completed Tenders called from 5 manufacturers

( ii ) Technical Evaluation 25 - 11- 2009 Under progres Technical offe

( iii ) Placement of Order 20-12-2009


M Equipment.

Supply Erection
Remarks
Target Actual Target Actual

Material shall be available at site on


15-9-2009 13-9-2009 15-10-2009
site by 17.11.09

8 panels shall be dispatched to site


26-10-2009
on 16.11.09

Shall be completed by 17.11.09

15-11-09 Material dispatched on 15.11.09

30-9-2010 31-12-2010
Design and engineering inhold for
finalising Civil structure.

30-9-2010 31-12-2010

tion with Abir. Placement of order now targeted


or 30th Nov. 2009
Out of three commercial pricebids
from two suppliers to be received
m 5 manufacturers

Technical offer received from Three manufacturers under evaluation..


Fortnightly Progress Report No 6
Progress report of Teesta III in respect of Gates and Hoists-
Dated 30-11-2009
Engineering Fabrication
Sr. no Description
Target Actual Target
A Diversion Tunnel
(i) Left Bank Diversion Tunnel Stoplogs
a) 2nd stage embedded parts completed 30.08.09

b) Stoplog Leaves 8 nos completed 30-9-2009


01-03-2009
to
c) Lifting beam 1 no. 31-07-2009 completed 30-9-2009

Monorail crane supporting structure 8


d) completed 30-9-2009
columns and crane beam

( ii ) Left Bank Diversion Tunnel -1 Spillway Radial gate 31-08-2010


a) 2nd stage embedded parts 01 - 03 - 2009 In progress
to
b) Radial gate 03 In progress
c) Hydraulic Hoist. - 03 - 2010 In Progress

( ii ) Left Bank Diversion Tunnel -1 Stoplogs for Spillway Radial gate 31-08-2010
a) 2nd stage embedded parts
b) Stoplog Leaves 8 nos
--------------
c) Lifting beam 1 no.
d) Gantry crane for operation

B Main Order for Gates and Hoists


(i) Technical evaluation 31 - 8 - 2009 Completed
( ii ) Placement of Order 30 - 9 - 2009 in Progress Offers evaluation completed.Order yet
Negotiation with

C Order for Butterfly Valves


(i) Calling of tenders 15 - 9 - 2009 Completed Tenders called from 7 manufacturers
( ii ) Technical Evaluation 25 - 11- 2009 Under progres
( iii ) Placement of Order 30-12-2009
ortnightly Progress Report No 6
esta III in respect of Gates and Hoists-HM Equipment.
Dated 30-11-2009
Fabrication Supply Erection
Remarks
Actual Target Actual Target Actual

Completed 15.09.2009 Completed 12.11.2009 In Progress Both sill beams erected


2 Nos
All 8 nos leaves Dispatched to site
Completed 26-10-2009 leaves 26.11.09 ----------
on 20.11.09
reached site
Material in
Completed 26-10-2009 26.11.09 ---------- Dispatched to site on 20.11.09
transit
Material in All the material Dispatched to site on
completed 26-10-2009 26.11.09 ----------
transit 20.11.09

30-9-2010 31-12-2010
Design and engineering shall start
after finalising of Civil structure,
which in progress for firming up size
and no of gates.

30-9-2010 31-12-2010
Design and engineering shall start
after finalising of Civil structure,
which in progress for firming up size
and no of gates.

Offers evaluation completed.Order yet to be place by Abir Infrastructure Pvt Ltd


Negotiation with firms in progress.

Tenders called from 7 manufacturers


Technical offer received from Three manufacturers under evaluation..
Fortnightly Progress Report No 7
Progress report of Teesta III in respect of Gates and Hoi
Dated 16-12-2009
Engineering Fabrication
Sr. no Description
Target Actual Target
A Diversion Tunnel
(i) Left Bank Diversion Tunnel Stoplogs

a) 2nd stage embedded parts completed 30.08.09

b) Stoplog Leaves 8 nos 01-03-2009 completed 30-9-2009


to
c) Lifting beam 1 no. 31-07-2009 completed 30-9-2009

Monorail crane supporting structure 8


d) completed 30-9-2009
columns and crane beam

( ii ) Left Bank Diversion Tunnel -1 Spillway Radial gate 31-08-2010


a) 2nd stage embedded parts 01 - 03 - 2009 In progress
to
b) Radial gate 03 In progress
c) Hydraulic Hoist. - 03 - 2010 In Progress

( ii ) Left Bank Diversion Tunnel -1 Stoplogs for Spillway Radial gate 31-08-2010
a) 2nd stage embedded parts
b) Stoplog Leaves 8 nos
--------------
c) Lifting beam 1 no.
d) Gantry crane for operation

B Main Order for Gates and Hoists


(i) Technical evaluation 31 - 8 - 2009 Completed
( ii ) Placement of Order 30 - 9 - 2009 in Progress Offers evaluation completed.Order yet
Negotiation with

C Order for Butterfly Valves


(i) Calling of tenders 15 - 9 - 2009 Completed Tenders called from 7 manufacturers
( ii ) Technical Evaluation 25 - 11- 2009 Under progres
( iii ) Placement of Order 30-12-2009

Note:
Manufacturers of Butterfly Valve.

1 FOURESS ENGINEERING(INDIA) LIMITED


2 Taihe Electric (Hongkong) Limited {CIF Mumbai}
3 Jyoti Ltd
4 Andritz Hydro Pvt.Ltd
5 VAG - Valves(India) Pvt. Ltd
6 ALSTOM
7 BHEL.
Fortnightly Progress Report No 7
Teesta III in respect of Gates and Hoists-HM Equipment.
Dated 16-12-2009
Fabrication Supply Erection
Actual Target Actual Target Actual

Completed 15.09.2009 Completed 12.11.2009 In Progress

Completed 26-10-2009 Completed 26.11.09 ----------


Completed 26-10-2009 Completed 26.11.09 ----------

completed 26-10-2009 In Progress 26.11.09 ----------

30-9-2010 31-12-2010

30-9-2010 31-12-2010

Offers evaluation completed.Order yet to be place by Abir Infrastructure Pvt Ltd


Negotiation with firms in progress.

Tenders called from 7 manufacturers


Technical offer received from Four manufacturers under evaluation.

IA) LIMITED
ed {CIF Mumbai}
Remarks

Erection of sill l beam in both bays


completed.7m roller track erected out of
54m,14m side seal seat erected out of
54m,7m side guide erected out of 72m.
Material at site
Material at site
Monorail Crane Hoist has been dispatched
from Ludhiana(Pilot Engineers) on 12-12-
2009 by dedicated truck.Expected delivery
at site 20-12-2009

Design and engineering shall start after


finalising of Civil structure drawings, which
is in progress for firming up size and no of
gates.

Design and engineering shall start after


finalising of Civil structure drawings, which
in progress for firming up size and no of
gates.

evaluation.
Fortnightly Progress Report No 8
Progress report of Teesta III in respect of Gates and Hoists-HM Equipment.
Dated 31 -12-2009
Engineering Fabrication Supply Erection
Sr. no Description Remarks
Target Actual Target Actual Target Actual Target Actual
A Diversion Tunnel
(i) Left Bank Diversion Tunnel Stoplogs

Erection of sill l beam in both bays


completed. 41.2 m roller track erected out of
a) 2nd stage embedded parts completed 30.08.09 Completed 15.09.2009 Completed 12.11.2009 In Progress
54m; 28 m side seal seat erected out of
54m; 40m side guide erected out of 72m.

Material at site Seals fited in units to be


b) Stoplog Leaves 8 nos completed 30-9-2009 Completed 26-10-2009 Completed 26.11.09 ----------
used for dry testing
c) Lifting beam 1 no. 01-03-2009 completed 30-9-2009 Completed 26-10-2009 Completed 26.11.09 ---------- Material at site
to
31-07-2009
Monorail crane supporting structure 8
d) completed 30-9-2009 completed 26-10-2009 Completed 26.11.09 ----------
columns and crane beam

Monorail Crane Hoist has been dispatched


from Ludhiana(Pilot Engineers) on 12-12-
e) Monorail crane Hoist completed 30-9-2009 completed 26-10-2009 In progress.
2009 by dedicated truck. Reached Siliguri
on 27-12-2009

( ii ) Left Bank Diversion Tunnel -1 Spillway Radial gate 31-08-2010 30-9-2010 31-12-2010 The earlier order of the radial gates kept on hold. Against
this order 1st stage anchor rods and yoke girder
a) 2nd stage embedded parts 01 - 03 - 2009 In progress fabricated and despatched to site. Are surplus to revised
to scheme.
03
b) Radial gate In progress Design and engineering shall start after
- 03 - 2010
c) Hydraulic Hoist. In Progress finalising of Civil structure drawings, which
is in progress for firming up size and no of
( iii) Left Bank Diversion Tunnel -1 Stoplogs for Spillway Radial gate 31-08-2010 30-9-2010 31-12-2010 gates.
a) 2nd stage embedded parts Design and engineering shall start after
b) Stoplog Leaves 8 nos finalising of Civil structure drawings, which
--------------
c) Lifting beam 1 no. in progress for firming up size and no of
d) Gantry crane for operation gates.

B Main Order for Gates and Hoists


(i) Technical evaluation 31 - 8 - 2009 Completed
( ii ) Placement of Order 30 - 9 - 2009 in Progress Offers evaluation completed.Order yet to be place by Abir Infrastructure Pvt Ltd
Negotiation with firms in progress.

C Order for Butterfly Valves


(i) Calling of tenders 15 - 9 - 2009 Completed Tenders called from 7 manufacturers
Technical offer received from five manufacturers under evaluation. Technical evaluation to be finalised by 15th
( ii ) Technical Evaluation 25 - 11- 2009 Under progres
Jan.2010
( iii ) Placement of Order 30-12-2009

Note:
Manufacturers of Butterfly Valve.

1 FOURESS ENGINEERING(INDIA) LIMITED


2 Taihe Electric (Hongkong) Limited {CIF Mumbai}
3 Jyoti Ltd
4 Andritz Hydro Pvt.Ltd
5 VAG - Valves(India) Pvt. Ltd
6 ALSTOM
7 BHEL.
Fortnightly Progress Report No 9
Progress report of Teesta III in respect of Gates and Hois
Dated 15-01-2010
Engineering Fabrication
Sr. no Description
Target Actual Target Actual
A Diversion Tunnel
(i) Left Bank Diversion Tunnel Stoplogs

a) 2nd stage embedded parts completed 30.08.09 Completed

b) Stoplog Leaves 8 nos 01-03-2009 completed 30-9-2009 Completed


c) Lifting beam 1 no. to completed 30-9-2009 Completed
31-07-2009
Monorail crane supporting structure 8
d) completed 30-9-2009 completed
columns and crane beam

e) Monorail crane Hoist completed 30-9-2009 completed

( ii ) Left Bank Diversion Tunnel -1 Spillway Radial gate 31-08-2010

a) 2nd stage embedded parts 01 - 03 - 2009 In progress


to
03
b) Radial gate In progress
- 03 - 2010
c) Hydraulic Hoist. In Progress

( iii) Left Bank Diversion Tunnel -1 Stoplogs for Spillway Radial gate 31-08-2010
a) 2nd stage embedded parts
b) Stoplog Leaves 8 nos
--------------
c) Lifting beam 1 no.
d) Gantry crane for operation

B Main Order for Gates and Hoists


(i) Technical evaluation 31 - 8 - 2009 Completed
( ii ) Placement of Order 30 - 9 - 2009 LOI placed upon GMW on 13th Jan. 2010

C Order for Butterfly Valves


(i) Calling of tenders 15 - 9 - 2009 Completed Tenders called from 7 manufacturers
Technical offer received fro
( ii ) Technical Evaluation 25 - 11- 2009 Under progres
yet to be furnished by VAG
( iii ) Placement of Order 30-12-2009

Note:
Manufacturers of Butterfly Valve.

1 FOURESS ENGINEERING(INDIA) LIMITED


2 Taihe Electric (Hongkong) Limited {CIF Mumbai}
3 Jyoti Ltd
4 Andritz Hydro Pvt.Ltd
5 VAG - Valves(India) Pvt. Ltd
6 ALSTOM
7 BHEL.
rogress Report No 9
spect of Gates and Hoists-HM Equipment.
d 15-01-2010
Supply Erection
Remarks
Target Actual Target Actual

Erection of sill l beam, roller track side and


top seals in both the bays completed. 41.2
m roller track erected out of 54m; 40m side
15.09.2009 Completed 12.11.2009 In Progress
guide erected out of 72m. Dummy Stoplog
fabricted and tested in both bays. The
rever diverted on 15-01-2010

26-10-2009 Completed 26.11.09 ---------- remarks


26-10-2009 Completed 26.11.09 ---------- Material at site

26-10-2009 Completed 26.11.09 ----------

26-10-2009 In progress. Monorail Crane Hoist available at site.

30-9-2010 31-12-2010 The earlier order of the radial gates kept on hold. Against
this order 1st stage anchor rods and yoke girder
fabricated and despatched to site. Are surplus to revised
scheme.

Design and engineering shall start after


finalising of Civil structure drawings, which
is in progress for firming up size and no of
30-9-2010 31-12-2010 gates.

Design and engineering shall start after


finalising of Civil structure drawings, which
in progress for firming up size and no of
gates.

on 13th Jan. 2010

om 7 manufacturers
chnical offer received from five manufacturers under evaluation. Technical offer and price for dismentling joint
to be furnished by VAG . Technical evaluation completion targeted for 22nd Jan.2010
Fortnightly Progress Report No 10
Progress report of Teesta III in respect of Gates and Hoists-HM Equipment.
Dated 31-01-2010
Engineering Fabrication Supply Erection
Sr. no Description Remarks
Target Actual Target Actual Target Actual Target Actual
A Diversion Tunnel
(i) Left Bank Diversion Tunnel Stoplogs

The diversion tunnel water running through both


bays.Sill beams,Top and side seal seats,roller
a) 2nd stage embedded parts completed 30.08.09 Completed 15.09.2009 Completed 12.11.2009 In Progress track erected.Balance erection of 2nd stage
embedded parts is in progress as per civil front
availability.60m side guide erected out of 72m.

b) Stoplog Leaves 8 nos completed 30-9-2009 Completed 26-10-2009 Completed 26.11.09 ---------- Material at site
c) Lifting beam 1 no. 01-03-2009 completed 30-9-2009 Completed 26-10-2009 Completed 26.11.09 ---------- Material at site
to
31-07-2009
Monorail crane supporting structure 8
d) completed 30-9-2009 completed 26-10-2009 Completed 26.11.09 ---------- Material at site
columns and crane beam

e) Monorail crane Hoist completed 30-9-2009 completed 26-10-2009 In progress. Material at site

( ii ) Left Bank Diversion Tunnel -1 Spillway Radial gate 31-08-2010 30-9-2010 31-12-2010
The earlier order of the radial gates kept on
hold. Against this order 1st stage anchor rods
a) 2nd stage embedded parts 01 - 03 - 2009 In progress and yoke girder fabricated and dispatched to
to site, are surplus to revised scheme.
03
b) Radial gate - 03 - 2010 In progress Design and engineering shall start after
c) Hydraulic Hoist. In Progress finalising of Civil structure drawings, which is in
progress for firming up size and no of gates.
Four alternatives of radial gate profiles sent for
( iii) Left Bank Diversion Tunnel -1 Stoplogs for Spillway Radial gate 31-08-2010 30-9-2010 31-12-2010 finalisation by civil dept.
a) 2nd stage embedded parts
Design and engineering shall start after
b) Stoplog Leaves 8 nos
-------------- finalising of Civil structure drawings, which in
c) Lifting beam 1 no. progress for firming up size and no of gates.
d) Gantry crane for operation

B Main Order for Gates and Hoists


(i) Technical evaluation 31 - 8 - 2009 Completed GMW site visit on 8th Feb-2010.Kick off
meeting scheduled for 12th Feb-2010.
( ii ) Placement of Order 30 - 9 - 2009 LOI placed upon GMW on 13th Jan. 2010

C Order for Butterfly Valves


(i) Calling of tenders 15 - 9 - 2009 Completed Tenders called from 7 manufacturers
( ii ) Technical Evaluation 25 - 11- 2009 Under progres Technical evaluation completed. Commercial evaluation is in progress.
( iii ) Placement of Order 30-12-2009

Note:
Manufacturers of Butterfly Valve.

1 FOURESS ENGINEERING(INDIA) LIMITED


2 Taihe Electric (Hongkong) Limited {CIF Mumbai}
3 Jyoti Ltd
4 Andritz Hydro Pvt.Ltd
5 VAG - Valves(India) Pvt. Ltd
6 ALSTOM
7 BHEL.
Fortnightly Progress Report No 11
Progress report of Teesta III in respect of Gates and Hoists-HM Equipment.
Dated 15-02-2010
Engineering Fabrication Supply Erection
Sr. no Description Remarks
Target Actual Target Actual Target Actual Target Actual
A Diversion Tunnel
(i) Left Bank Diversion Tunnel Stoplogs

The diversion tunnel water running through both


bays.Sill beams,Top and side seal seats,roller
a) 2nd stage embedded parts completed 30.08.09 Completed 15.09.2009 Completed 12.11.2009 In Progress track erected.Balance erection of 2nd stage
embedded parts is in progress as per civil front
availability.60m side guide erected out of 72m.

b) Stoplog Leaves 8 nos completed 30-9-2009 Completed 26-10-2009 Completed 26.11.09 ---------- Material at site
c) Lifting beam 1 no. 01-03-2009 completed 30-9-2009 Completed 26-10-2009 Completed 26.11.09 ---------- Material at site
to
31-07-2009 Material at site. The erection of the coloumn
Monorail crane supporting structure 8
d) completed 30-9-2009 completed 26-10-2009 Completed 26.11.09 ---------- base and anchors shall be done after
columns and crane beam
completion of the civil structure.

e) Monorail crane Hoist completed 30-9-2009 completed 26-10-2009 In progress. Material at site

( ii ) Left Bank Diversion Tunnel -1 12x7.7m Spillway Radial gate 31-08-2010 30-9-2010 31-12-2010
The earlier order of the radial gates kept on
hold. Against this order 1st stage anchor rods
a) 2nd stage embedded parts 01 - 03 - 2009 In progress and yoke girder fabricated and dispatched to
to site, are surplus to revised scheme.
03
b) Radial gate - 03 - 2010 In progress
c) Hydraulic Hoist. In Progress
The civil structure drawings for providing one no
Radial gate and 1 no. fixed wheel maintenance
gate for Diversion Tunnel no. 1 finalised.
( iii) Left Bank Diversion Tunnel -1 12x11.2m Fixed wheel maintenance gat 31-08-2010 30-9-2010 31-12-2010 Technical specifications under progress.Revised
specifications shall be sent to Abir by 20th
a) 2nd stage embedded parts Feb.10 for revision of order on PES Engineers.
b) Stoplog Leaves 8 nos
--------------
c) Lifting beam 1 no.
d) Gantry crane for operation

Left Bank Diversion Tunnel -2 11x14 m Fixed wheel maintenance The civil structure drawings for providing one no
( iv) 31-08-2010 30-9-2010 31-12-2010 Radial gate and 1 no. fixed wheel maintenance
gate for Spillway Radial gate
gate for spillway Diversion Tunnel no. 2
finalised . Technical specifications under
progress.Revised specifications shall be sent to
Left Bank Diversion Tunnel -2 11x14 m Fixed wheel maintenance Abir by 20th Feb.10 for calling offer and
( v) 31-08-2010 30-9-2010 31-12-2010
gate for Spillway Radial gate placement of order on GMW.

B Main Order for Gates and Hoists


(i) Technical evaluation 31 - 8 - 2009 Completed GMW visited site from 9th Feb-2010. to 11th
Feb. 2010. Kick off meeting scheduled for
( ii ) Placement of Order 30 - 9 - 2009 LOI placed upon GMW on 13th Jan. 2010 22nd Feb.2010.

C Order for Butterfly Valves


(i) Calling of tenders 15 - 9 - 2009 Completed Tenders called from 7 manufacturers
( ii ) Technical Evaluation 25 - 11- 2009 Under progres Technical evaluation completed. Commercial evaluation is in progress.
( iii ) Placement of Order 30-12-2009

Note:
Manufacturers of Butterfly Valve Technical Offers under consideration commercially
specifications sent to.
1 FOURESS ENGINEERING(INDIA) LIMITED 1 FOURESS ENGINEERING(INDIA) LIMITED
2 Taihe Electric (Hongkong) Limited {CIF Mumbai} 2 Taihe Electric (Hongkong) Limited {CIF Mumbai}
3 Jyoti Ltd 3 Andritz Hydro Pvt.Ltd
4 Andritz Hydro Pvt.Ltd 4 VAG - Valves(India) Pvt. Ltd
5 VAG - Valves(India) Pvt. Ltd
6 ALSTOM
7 BHEL.
Fortnightly Progress Report No 12
Progress report of Teesta III in respect of Gates and Hoists-HM Equipment.
Dated 28-02-2010
Engineering Fabrication Supply Erection
Sr. no Description Remarks
Target Actual Target Actual Target Actual Target Actual
A Diversion Tunnel
(i) Left Bank Diversion Tunnel Stoplogs

The diversion tunnel water running through both


a) 2nd stage embedded parts completed 30.08.09 Completed 15.09.2009 Completed 12.11.2009 In Progress
bays. All 2nd stage embedded parts erected . .
b) Stoplog Leaves 8 nos completed 30-9-2009 Completed 26-10-2009 Completed 26.11.09 ---------- Material at site
c) Lifting beam 1 no. 01-03-2009 completed 30-9-2009 Completed 26-10-2009 Completed 26.11.09 ---------- Material at site
to
Monorail crane supporting structure 8 31-07-2009 Material at site.The column bolts and base
d) completed 30-9-2009 completed 26-10-2009 Completed 26.11.09 ----------
columns and crane beam plates erected.

e) Monorail crane Hoist completed 30-9-2009 completed 26-10-2009 In progress. Material at site

( ii ) Left Bank Diversion Tunnel -1 12x7.7m Spillway Radial gate 31-08-2010 30-9-2010 31-12-2010
The earlier order of the radial gates kept on
hold. Against this order 1st stage anchor rods
a) 2nd stage embedded parts 01 - 03 - 2009 In progress and yoke girder fabricated and dispatched to
to site, are surplus to revised scheme.
03
b) Radial gate - 03 - 2010 In progress
c) Hydraulic Hoist. In Progress The Mechanical drawings and Specifications for
providing one no Radial gate and 1 no. fixed
wheel maintenance gate for Diversion Tunnel
no. 1 finalised.Technical specifications
( iii) Left Bank Diversion Tunnel -1 12x11.2m Fixed wheel maintenance gat31-08-2010 30-9-2010 31-12-2010 completed.Revised specifications shall be sent
to Abir by 2nd Mar.10 for revision of order on
a) 2nd stage embedded parts PES Engineers.
b) Maintenance Gate --------------
d) Rope Drum Hoist for operation

Left Bank Diversion Tunnel -2 11x14 m Fixed wheel maintenance The civil structure drawings for firming the sizes
( iv) 31-08-2010 30-9-2010 31-12-2010
gate for Spillway Radial gate of one no Radial gate and 1no. fixed wheel
maintenance gate for spillway Diversion
Tunnel no. 2 yet to be finalised.Technical
specifications and drawings under progress
Left Bank Diversion Tunnel -2 11x14 m Fixed wheel maintenance shall be finalised after gate sizes are firmed by
( v) 31-08-2010 30-9-2010 31-12-2010
gate for Spillway Radial gate civil after model study results.

B Main Order for Gates and Hoists


(i) Technical evaluation 31 - 8 - 2009 Completed Kick of Meeting with GMW held on 22nd Feb-
10 in EIPL, Gurgaon. Engineering started for
( ii ) Placement of Order 30 - 9 - 2009 LOI placed upon GMW on 13th Jan. 2010 designs of gates and hoists.

C Order for Butterfly Valves


(i) Calling of tenders 15 - 9 - 2009 Completed Tenders called from 7 manufacturers
( ii ) Technical Evaluation 25 - 11- 2009 Under progres Technical evaluation completed. Commercial evaluation is in progress.

( iii ) Placement of Order 30-12-2009 Under Finalisation

Note:
Manufacturers of Butterfly Valve Technical Offers under consideration commercially
specifications sent to.
1 FOURESS ENGINEERING(INDIA) LIMITED 1 FOURESS ENGINEERING(INDIA) LIMITED
2 Taihe Electric (Hongkong) Limited {CIF Mumbai} 2 Taihe Electric (Hongkong) Limited {CIF Mumbai}
3 Jyoti Ltd 3 Andritz Hydro Pvt.Ltd
4 Andritz Hydro Pvt.Ltd 4 VAG - Valves(India) Pvt. Ltd
5 VAG - Valves(India) Pvt. Ltd
6 ALSTOM
7 BHEL.
Fortnightly Progress Report No 13
Progress report of Teesta III in respect of Gates,Hoists and Penstocks-HM Equipment.
Dated 15-03-2010
Engineering Fabrication Supply Erection
Sr. no Description Remarks
Target Actual Target Actual Target Actual Target Actual
A Diversion Tunnel
(i) Left Bank Diversion Tunnel Stoplogs

The diversion tunnel water running through both


a) 2nd stage embedded parts completed 30.08.09 Completed 15.09.2009 Completed 12.11.2009 In Progress
bays. All 2nd stage embedded parts erected . .
b) Stoplog Leaves 8 nos completed 30-9-2009 Completed 26-10-2009 Completed 26.11.09 ---------- Material at site
c) Lifting beam 1 no. 01-03-2009 completed 30-9-2009 Completed 26-10-2009 Completed 26.11.09 ---------- Material at site
to
Monorail crane supporting structure 8 31-07-2009 Material at site.The column bolts and base
d) completed 30-9-2009 completed 26-10-2009 Completed 26.11.09 ----------
columns and crane beam plates erected.

e) Monorail crane Hoist completed 30-9-2009 completed 26-10-2009 In progress. Material at site

( ii ) Left Bank Diversion Tunnel -1 12x7.7m Spillway Radial gate 31-08-2010 30-9-2010 31-12-2010
The earlier order of the radial gates kept on
hold. Against this order 1st stage anchor rods
a) 2nd stage embedded parts 01 - 03 - 2009 In progress and yoke girder fabricated and dispatched to
to site, are surplus to revised scheme.
03
b) Radial gate - 03 - 2010 In progress
c) Hydraulic Hoist. In Progress The Mechanical drawings and Specifications for
providing one no Radial gate and 1 no. fixed
wheel maintenance gate for Diversion Tunnel
( iii) Left Bank Diversion Tunnel -1 12x11.2m Fixed wheel maintenance gate for Sp 31-08-2010 30-9-2010 31-12-2010 no. 1 finalised.Technical specificationsand
drawings sent to Abir on 2nd Mar.10 for
revision of order on PES Engneers.
a) 2nd stage embedded parts
b) Maintenance Gate --------------
d) Rope Drum Hoist for operation

Left Bank Diversion Tunnel -2 11x14 m Fixed wheel maintenance gate for The civil structure drawings for firming the sizes
( iv) 31-08-2010 30-9-2010 31-12-2010
Spillway Radial gate of one no Radial gate and 1no. fixed wheel
maintenance gate for spillway Diversion Tunnel
no. 2 yet to be finalised.Technical specifications
and drawings under progress shall be finalised
Left Bank Diversion Tunnel -2 11x14 m Fixed wheel maintenance gate for after gate sizes are firmed by civil after model
( v) 31-08-2010 30-9-2010 31-12-2010
Spillway Radial gate study results.

B Main Order for Gates and Hoists


(i) Technical evaluation 31 - 8 - 2009 Completed Designs and general arrangement drawing
work in progress.
( ii ) Placement of Order 30 - 9 - 2009 LOI placed upon GMW on 13th Jan. 2010

C Order for Butterfly Valves


(i) Calling of tenders 15 - 9 - 2009 Completed Tenders called from 7 manufacturers Placement of order has been finalized to Taihe
( ii ) Technical Evaluation 25 - 11- 2009 Completed Electric (Hongkong) Limited on 09-03-2010.
Transportation of valve methodology being
( iii ) Placement of Order 30-12-2009 Completed taken up with Transportater and Taihe
Engineers.

D Buried Penstock:

Kick of Meeting with PES held on 8th and 9th


March-10 in EIPL, Gurgaon. Regarding setting
Placement of Order 30 - 10 - 2009 Work order for Fabrication and Erection for Buried Penstock placed upon PES on 30-10-2009
of workshop shifting of machinery and start of
fabrication.by 1st.MAY 2010

E Steel Plates:
Steel Plates for 1st Consignment
(i)
(253Plates-1556 tons):
Steel Plates for 2nd Consignment
( ii ) Total plates available at site 485 out of 722.
(218Plates-1540.19 tons):
Steel Plates for 3rd Consignment
( iii )
(251Plates-1546.8 tons):
Steel Plates for 4th Consignment
( iv)
(261Plates-1560.44 tons):

i) Excavation and stone soiling of 20


foundations has been Completed out of 22.
Construction status of Fabrication ii) PCC work for 14 foundations has
F 22/01/2010 24/04/2010
Workshop: been completed.
iii) Pedestal Concrete for 8
foundations has been completed.

Machinery Required for rolling of


G
Ferrules
Bending Machine(Suitableto roll plates
(i) The bending rmacchine to be transported from Parbati . Transportaytion to start from April 1st. 2010
94mm thick and 3m width.)
( ii ) 14 ton Hydra Shifting to be
( iii ) DG Set completed by Accepted by PES Engineers
( iv) EOT Crane 24-04-2010
(v) Chain Pulley
( ivi) SAW Machine