SEJIRAM MILL 80 TPH PROJECT

  08-Dec-17 17:37

# Activity ID Activity Name Dur % OD Start Finish Calendar 2017 2018 2019 2020
Complete Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
09-Jan-20, SEJIRAM MILL 80 TPH PROJECT
1
SEJIRAM MILL 80 TPH PROJECT 0% 915d 09-Jan-17 09-Jan-20

2 FEASIBILITY PHASE 0% 120d 09-Jan-17 23-Jun-17 5 Working Day 23-Jun-17, FEASIBILITY PHASE
3 SJRM10000 Request Palm Oil Facility (POF) 0% 0d 09-Jan-17 5 Working Day Request Palm Oil Facility (POF), 09-Jan-17
4 SJRM10010 Feasibility report 0% 90d 20-Feb-17 23-Jun-17 5 Working Day Feasibility report
5 DEVELOPMENT PHASE 0% 243d 24-Jun-17 05-Apr-18 05-Apr-18, DEVELOPMENT PHASE
6 Project Design Requirement 0% 0d 11-Oct-17 11-Oct-17 5 Working Day 11-Oct-17, Project Design Requirement
7 SJRM10020 Receive Project Design Requirement (PDR) 0% 0d 11-Oct-17 5 Working Day Receive Project Design Requirement (PDR),
8 Project Management Activities 0% 45d 25-Sep-17 24-Nov-17 5 Working Day 24-Nov-17, Project Management Acti vities
9 SJRM10030 Develop time schedule (Level 3 for the Development phase) 0% 10d 16-Oct-17 27-Oct-17 5 Working Day Develop time schedule (Level 3 for the Development phase)
10 SJRM10040 Prepare time schedule (level 2) & milestone list for the execution0%
phase 10d 30-Oct-17 10-Nov-17 5 Working Day Prepare time schedule (level 2) & milestone list for the execution phase
11 SJRM10050 Develop the Quality Mananagement Plan 0% 45d 25-Sep-17 24-Nov-17 5 Working Day Develop the Quality Mananagement Plan
12 Site selection & topography 0% 60d 04-Sep-17 24-Nov-17 5 Working Day 24-Nov-17, Site selection & topography
13 SJRM10060 Topography study 0% 20d 30-Oct-17 24-Nov-17 5 Working Day Topography study
14 SJRM10070 Conduct Soil Investigation 0% 60d 04-Sep-17 24-Nov-17 5 Working Day Conduct Soil Investigation
15 Permiting & certificates 0% 243d 24-Jun-17 05-Apr-18 05-Apr-18, Permiting & certificates
16 SJRM10080 Location Permitt 0% 50d 24-Jun-17 21-Aug-17 6 Working Day Location Permitt
17 SJRM10090 Obtain AMDAL / UKL / UPL 0% 66d 22-Aug-17 21-Nov-17 5 Working Day Obtain AMDAL / UKL / UPL
18 SJRM10100 HO Permit 0% 24d 22-Nov-17 19-Dec-17 6 Working Day HO Permit
19 SJRM10110 Start IMB Process (required to start construction) 0% 66d 01-Dec-17 06-Mar-18 5 Working Day Start IMB Process (required to start construction)
20 SJRM10120 Obtain BKPM Permit 0% 22d 07-Mar-18 05-Apr-18 5 Working Day Obtain BKPM Permit
21 Conceptual/Basic Design 0% 36d 12-Oct-17 30-Nov-17 5 Working Day 30-Nov-17, Conceptual/Basic Design
22 Engineering 0% 4d 27-Nov-17 30-Nov-17 5 Working Day 30-Nov-17, Engineering
23 SJRM10130 Receive Building Layout of SKSM 0% 0d 27-Nov-17 5 Working Day Receive Building Layout of SKSM, 27-Nov-17
24 SJRM10140 Develop SJRM Site Plan/Layout 0% 4d 27-Nov-17 30-Nov-17 5 Working Day Develop SJRM Site Plan/Layout
25 Cost Estimating review 0% 34d 12-Oct-17 28-Nov-17 5 Working Day 28-Nov-17, Cost Estimating review
26 SJRM10150 Prepare Basis of Estimate 0% 23d 12-Oct-17 13-Nov-17 5 Working Day Prepare Basis of Estimate
27 SJRM10160 Create the Cost Break Down schedule 0% 2d 14-Nov-17 15-Nov-17 5 Working Day Create the Cost Break Down schedule
28 SJRM10170 CAPEX Cost Estimate (-10% / + 15%) 0% 7d 16-Nov-17 24-Nov-17 5 Working Day CAPEX Cost Estimate (-10% / + 15%)
29 SJRM10180 Conduct alternatives analyses (CAPEX / OPEX) 0% 2d 27-Nov-17 28-Nov-17 5 Working Day Conduct alternatives analyses (CAPEX / OPEX)
30 Procurement 0% 12d 09-Nov-17 24-Nov-17 5 Working Day 24-Nov-17, Procurement
31 Procurement Strategy 0% 12d 09-Nov-17 24-Nov-17 5 Working Day 24-Nov-17, Procurement Strategy
32 SJRM10190 Define tender packages contractors & propietary items & other items
0% 5d 09-Nov-17 15-Nov-17 5 Working Day Define tender packages contractors & propietary items & other items
33 SJRM10200 Develop the procurement plan & strategy 0% 5d 16-Nov-17 22-Nov-17 5 Working Day Develop the procurement plan & strategy
34 SJRM10210 Define the project Distribution & Logistics 0% 2d 23-Nov-17 24-Nov-17 5 Working Day Define the project Distribution & Logistics
35 Review 0% 3d 27-Nov-17 29-Nov-17 5 Working Day 29-Nov-17, Review
36 SJRM10220 Cost estimating review 0% 1d 29-Nov-17 29-Nov-17 5 Working Day Cost estimating review
37 SJRM10230 Schedule estimating review 0% 1d 28-Nov-17 28-Nov-17 5 Working Day Schedule estimating review
38 SJRM10240 Procurement & Expediting Schedule review 0% 1d 27-Nov-17 27-Nov-17 5 Working Day Procurement & Expediting Schedule review
39 SJRM10250 Permitting & Licenses Schedule review 0% 1d 28-Nov-17 28-Nov-17 5 Working Day Permitting & Licenses Schedule review
40 Project Data Book 0% 41d 17-Oct-17 12-Dec-17 5 Working Day 12-Dec-17, Project Data Book
41 SJRM10260 Prepare the Project Data Book (PDB) 0% 30d 17-Oct-17 27-Nov-17 5 Working Day Prepare the Project Data Book (PDB)
42 SJRM10270 Review the PDB 0% 5d 28-Nov-17 04-Dec-17 5 Working Day Review the PDB
43 SJRM10280 Submit PDB for approval 0% 1d 05-Dec-17 05-Dec-17 5 Working Day Submit PDB for approval
44 SJRM10290 Approval of the PDB (final Go / No Go decision) 0% 0d 12-Dec-17 5 Working Day Approval of the PDB (final Go / No Go decision),
45 EXECUTING,MONITORING AND CONTROL PHASE 0% 897d 09-Jan-17 18-Dec-19 18-Dec-19, EXECUTING,MONITORING AND CONTROL P
46 Project Management Activities 0% 31d 28-Nov-17 12-Jan-18 5 Working Day 12-Jan-18, Project Management Acti vities
47 SJRM10300 Develop Project Management Plan 0% 20d 28-Nov-17 26-Dec-17 5 Working Day Develop Project Management Plan
48 SJRM10310 Review Project Management Plan 0% 5d 27-Dec-17 03-Jan-18 5 Working Day Review Project Management Plan
49 SJRM10320 Submit Project Management Plan 0% 1d 04-Jan-18 04-Jan-18 5 Working Day Submit Project Management Plan
50 SJRM10330 Approval Project Management Plan 0% 0d 12-Jan-18 5 Working Day Approval Project Management Plan, 12-Jan-18
51 Detail Design 0% 109d 01-Dec-17 04-May-18 5 Working Day 04-May-18, Detail Design
52 Engineering 0% 84d 01-Dec-17 30-Mar-18 5 Working Day 30-Mar-18, Engineering
53 General 0% 84d 01-Dec-17 30-Mar-18 5 Working Day 30-Mar-18, General
54 Civil Structure 0% 34d 01-Dec-17 19-Jan-18 5 Working Day 19-Jan-18, Civil Structure
55 SJRM10340 Finalized SJRM Site Plan/Layout 0% 5d 01-Dec-17 07-Dec-17 5 Working Day Finalized SJRM Site Plan/Layout
56 SJRM10350 Building Section 0% 5d 08-Dec-17 14-Dec-17 5 Working Day Building Section
57 SJRM10360 Building Elevation 0% 5d 15-Dec-17 21-Dec-17 5 Working Day Building Elevation
58 Cut & Fill 0% 6d 01-Dec-17 08-Dec-17 5 Working Day 08-Dec-17, Cut & Fill
59 Road & Drainage 0% 18d 11-Dec-17 05-Jan-18 5 Working Day 05-Jan-18, Road & Drainage
60 Pilling 0% 18d 26-Dec-17 19-Jan-18 5 Working Day 19-Jan-18, Pilling
61 Mech-Piping 0% 2d 29-Mar-18 30-Mar-18 5 Working Day 30-Mar-18, Mech-Piping
62 Intrumentation 0% 2d 07-Feb-18 08-Feb-18 5 Working Day 08-Feb-18, Intrumentation
63 Electrical 0% 2d 07-Feb-18 08-Feb-18 5 Working Day 08-Feb-18, Electrical
64 Process Building 0% 20d 17-Jan-18 13-Feb-18 5 Working Day 13-Feb-18, Process Building
65 Civil Structure 0% 20d 17-Jan-18 13-Feb-18 5 Working Day 13-Feb-18, Civil Structure
66 Main Building Substructure & Superstructure 0% 10d 17-Jan-18 30-Jan-18 5 Working Day 30-Jan-18, Main Building Substructure & Superstructure
67 Process Building Substructre & Superstructure 0% 10d 31-Jan-18 13-Feb-18 5 Working Day 13-Feb-18, Process Building Substructre & Superstructure
68 Ancillary Building 0% 5d 28-Feb-18 07-Mar-18 5 Working Day 07-Mar-18, Anci llary Buildi ng
69 Loading Ramp Station (01) 0% 2d 26-Dec-17 27-Dec-17 5 Working Day 27-Dec-17, Loading Ramp Station (01)
70 Sterilizer (02) 0% 2d 31-Jan-18 01-Feb-18 5 Working Day 01-Feb-18, Sterilizer (02)
71 Thresshing (03) 0% 2d 26-Dec-17 27-Dec-17 5 Working Day 27-Dec-17, Thresshing (03)
72 Pressing Station (04) 0% 2d 14-Feb-18 15-Feb-18 5 Working Day 15-Feb-18, Pressing Station (04)
73 Clarification (05) 0% 2d 14-Feb-18 15-Feb-18 5 Working Day 15-Feb-18, Clarification (05)
74 Palm Oil Storage (06) 0% 2d 14-Feb-18 15-Feb-18 5 Working Day 15-Feb-18, Palm Oil Storage (06)
75 Nut & Kernel (07) 0% 2d 07-Mar-18 08-Mar-18 5 Working Day 08-Mar-18, Nut & Kernel (07)
76 Boiler Station (08) 0% 2d 31-Jan-18 01-Feb-18 5 Working Day 01-Feb-18, Boiler Station (08)
77 Power House (09) 0% 2d 31-Jan-18 01-Feb-18 5 Working Day 01-Feb-18, Power House (09)
78 Water Treatment Plant (10) 0% 2d 31-Jan-18 01-Feb-18 5 Working Day 01-Feb-18, Water Treatment Plant (10)
79 Effluent Treatm ent Plant (11) 0% 2d 07-Feb-18 08-Feb-18 5 Working Day 08-Feb-18, Effluent Treatment Plant (11)

Project ID : 16STP2019 Actual Level of Effort Critical Remaining Work TASK filter: All Activities
Revison .0, 08-Dec-17 Actual Work Milestone © Oracle Corporation
Status      : 1st Issued
Remaining Work summary
 
SEJIRAM MILL 80 TPH PROJECT
  08-Dec-17 17:37

# Activity ID Activity Name Dur % OD Start Finish Calendar 2017 2018 2019 2020
Complete Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
80 Fire Fighting System (12) 0% 2d 07-Mar-18 08-Mar-18 5 Working Day 08-Mar-18, Fire Fighting System (12)
81 Compressed Air System (13) 0% 2d 06-Feb-18 07-Feb-18 5 Working Day 07-Feb-18, Compressed Air Sys tem (13)
82 Fuel Oil System (14) 0% 2d 14-Feb-18 15-Feb-18 5 Working Day 15-Feb-18, Fuel Oil System (14)
83 Hot Water Syst em (15) 0% 2d 07-Mar-18 08-Mar-18 5 Working Day 08-Mar-18, Hot Water System ( 15)
84 Hydraulic Unit (16) 0% 1d 11-Dec-17 11-Dec-17 5 Working Day 11-Dec-17, Hydraulic Unit (16)
85 Boiler Feed Water Treatment Plant (17) 0% 10d 11-Dec-17 22-Dec-17 5 Working Day 22-Dec-17, Boiler Feed Water Treatment Plant (17)
86 Compile Document Package 0% 78d 08-Dec-17 30-Mar-18 5 Working Day 30-Mar-18, Compile Document Package
87 Contractor Document Package 0% 78d 08-Dec-17 30-Mar-18 5 Working Day 30-Mar-18, Contractor Document Package
88 SJRM10820 Cut & Fill Doc's 0% 0d 08-Dec-17 5 Working Day Cut & Fill Doc's,
89 SJRM10830 Road & Drainage Doc's 0% 0d 05-Jan-18 5 Working Day Road & Drainage Doc's,
90 SJRM10840 Pilling Doc's 0% 0d 19-Jan-18 5 Working Day Pilling Doc's,
91 SJRM10850 Main Building Sub & Superstructure Doc's 0% 0d 30-Jan-18 5 Working Day Main Building Sub & Superstructure Doc's,
92 SJRM10860 Process Building Substructure & Superstructure Doc's 0% 0d 13-Feb-18 5 Working Day Process Building Substructure & Superstructure Doc's,
93 SJRM10870 Ancillary Building Doc's 0% 0d 07-Mar-18 5 Working Day Ancillary Building Doc's,
94 SJRM10880 MEP Package Doc's 0% 0d 30-Mar-18 5 Working Day MEP Package Doc's,
95 Vend or Packag e 0% 39d 08-Dec-17 05-Feb-18 5 Working Day 05-Feb-18, Vendor Package
96 SJRM10890 Steam Boiler 30 TPH (at 32 barg) & Deaerator 60 TPH 0% 0d 08-Dec-17 5 Working Day Steam Boiler 30 TPH (at 32 barg) & Deaerator 60 TPH,
97 SJRM10900 Steam Turbo Alternator 1600 kW at 30 barg 0% 0d 08-Dec-17 5 Working Day Steam Turbo Alternator 1600 kW at 30 barg,
98 SJRM10910 Steam Make Up System 0% 0d 08-Dec-17 5 Working Day Steam Make Up System,
99 SJRM10920 Indexer System 0% 0d 08-Dec-17 5 Working Day Indexer System,
100 SJRM10930 Boiler Feed Water Treatment Plant 0% 0d 05-Feb-18 5 Working Day Boiler Feed Water Treatment Plant,
101 SJRM10940 Overhead crane in Main Process Building 0% 0d 08-Dec-17 5 Working Day Overhead crane in Main Process Building,
102 Prop Item Package Document 0% 35d 27-Dec-17 15-Feb-18 5 Working Day 15-Feb-18, Prop Item Package Document
103 SJRM10950 Big Diesel Generating Set & Small Diesel Genset 0% 0d 08-Feb-18 5 Working Day Big Diesel Generating Set & Small Diesel Genset,
104 SJRM10960 Road Weighbridge 0% 0d 18-Jan-18 5 Working Day Road Weighbridge,
105 SJRM10970 Cages (capacity 10 Tons FFB) 0% 0d 25-Jan-18 5 Working Day Cages (capacity 10 Tons FFB),
106 SJRM10980 Trans fer Carriage 0% 0d 27-Dec-17 5 Working Day Trans fer Carriage,
107 SJRM10990 Tippler (2 x @10 tons FFB cages) 0% 0d 27-Dec-17 5 Working Day Tippler (2 x @10 tons FFB cages),
108 SJRM11000 Bunch Hopper & Gate Bunch Feeder (2 x 10 tons FFB) 0% 0d 01-Feb-18 5 Working Day Bunch Hopper & Gate Bunch Feeder (2 x 10 tons FFB),
109 SJRM11010 Crane Grapple 0% 0d 08-Feb-18 5 Working Day Crane Grapple,
110 SJRM11020 Digesters (4,000 ltr) 0% 0d 27-Dec-17 5 Working Day Digesters (4,000 ltr),
111 SJRM11030 Screw Press (P-20) 0% 0d 15-Feb-18 5 Working Day Screw Press (P-20),
112 SJRM11040 Screw Press Power Pack 0% 0d 15-Feb-18 5 Working Day Screw Press Power Pack,
113 SJRM11050 Crude Oil Vibrating Screen 0% 0d 15-Feb-18 5 Working Day Crude Oil Vibrating Screen,
114 SJRM11060 Sludge Vibrating Screen 0% 0d 15-Feb-18 5 Working Day Sludge Vibrating Screen,
115 SJRM11070 Sludge Centrifuge 12000 ltr/hr 0% 0d 25-Jan-18 5 Working Day Sludge Centrifuge 12000 ltr/hr,
116 SJRM11080 Air Compressor, Air dryer & Air Receiver 3000L 0% 0d 18-Jan-18 5 Working Day Air Compressor, Air dryer & Air Receiver 3000L,
117 SJRM11090 Sterilizer Autom atic Control 0% 0d 15-Feb-18 5 Working Day Sterilizer Autom atic Control,
118 SJRM11100 Self Separating Bunch Crusher 0% 0d 15-Feb-18 5 Working Day Self Separating Bunch Crusher,
119 SJRM11110 Vacuum Oil Dryer c/w Vac uum Pump 15 m 3/hr 0% 0d 15-Feb-18 5 Working Day Vacuum Oil Dryer c/w Vac uum Pump 15 m 3/hr,
120 SJRM11120 Oil Transfer Pump / Dried Oil Pump 0% 0d 15-Feb-18 5 Working Day Oil Transfer Pump / Dried Oil Pump,
121 SJRM11130 Sludge Flow meter 0% 0d 15-Feb-18 5 Working Day Sludge Flow meter,
122 SJRM11140 Ripple Mill 0% 0d 15-Feb-18 5 Working Day Ripple Mill,
123 SJRM11150 Claybath Vibrating Screen 0% 0d 15-Feb-18 5 Working Day Claybath Vibrating Screen,
124 SJRM11160 Sludge Flow meter w/o recorder 0% 0d 15-Feb-18 5 Working Day Sludge Flow meter w/o recorder,
125 BOQ & Cost Estimation 0% 105d 07-Dec-17 04-May-18 5 Working Day 04-May-18, BOQ & Cost Estimation
126 Bill of Quantity 0% 95d 07-Dec-17 20-Apr-18 5 Working Day 20-Apr-18, Bill of Quantity
127 SJRM11170 Cut & Fill Package 0% 6d 07-Dec-17 14-Dec-17 5 Working Day Cut & Fill Package
128 SJRM11180 Pilling Package 0% 5d 22-Jan-18 26-Jan-18 5 Working Day Pilling Package
129 SJRM11190 CSA Package 0% 10d 01-Mar-18 14-Mar-18 5 Working Day CSA Package
130 SJRM11200 MEP Package 0% 15d 02-Apr-18 20-Apr-18 5 Working Day MEP Package
131 Cost Estimation 0% 99d 15-Dec-17 04-May-18 5 Working Day 04-May-18, Cost Estimation
132 SJRM11210 Cut & Fill Package 0% 5d 15-Dec-17 21-Dec-17 5 Working Day Cut & Fill Package
133 SJRM11220 Pilling Package 0% 5d 29-Jan-18 02-Feb-18 5 Working Day Pilling Package
134 SJRM11230 CSA Package 0% 10d 15-Mar-18 28-Mar-18 5 Working Day CSA Package
135 SJRM11240 MEP Package 0% 10d 23-Apr-18 04-May-18 5 Working Day MEP Package
136 Procurement 0% 380d 21-Nov-17 21-Feb-19 21-Feb-19, Procurement
137 General 0% 17d 28-Nov-17 20-Dec-17 5 Working Day 20-Dec-17, General
138 SJRM11250 Update tender packages strategy 0% 7d 28-Nov-17 06-Dec-17 5 Working Day Update tender packages strategy
139 SJRM11260 Prepare the Contract Term s and Requirem ents 0% 10d 07-Dec-17 20-Dec-17 5 Working Day Prepare the Contract Term s and Requirem ents
140 Procurement 0% 380d 21-Nov-17 21-Feb-19 21-Feb-19, Procurement
141 Pre-qualification 0% 24d 21-Nov-17 22-Dec-17 5 Working Day 22-Dec-17, Pre-qualification
142 SJRM11270 Set up Bidder list 0% 2d 21-Nov-17 22-Nov-17 5 Working Day Set up Bidder list
143 SJRM11280 Conduct Pre-Qualification 0% 20d 23-Nov-17 20-Dec-17 5 Working Day Conduct Pre-Qualification
144 SJRM11290 Select final bidders 0% 2d 21-Dec-17 22-Dec-17 5 Working Day Select final bidders
145 Tender 0% 369d 04-Dec-17 21-Feb-19 21-Feb-19, Tender
146 Vend or Package 0% 363d 11-Dec-17 21-Feb-19 21-Feb-19, Vendor Package
147 Steam Boiler 30 TPH (at 32 barg) & Deaerator 60 TPH 0% 347d 11-Dec-17 02-Feb-19 02-Feb-19, Steam Boiler 30 TPH (at 32 barg) & Deaerator 60 T PH
148 SJRM11300 Tender Call (send RFQ) 0% 1d 11-Dec-17 11-Dec-17 5 Working Day Tender Call (send RFQ)
149 SJRM11310 1st Proposal Submission 0% 7d 12-Dec-17 20-Dec-17 5 Working Day 1st Proposal Submission
150 SJRM11320 1st Technic al Bi d Evaluation 0% 7d 21-Dec-17 02-Jan-18 5 Working Day 1st Technic al Bi d Evaluation
151 SJRM11330 1st Technic al Cl arific ation 0% 7d 03-Jan-18 11-Jan-18 5 Working Day 1st Technic al Cl arific ation
152 SJRM11340 2nd Proposal Submission 0% 2d 12-Jan-18 15-Jan-18 5 Working Day 2nd Proposal Submission
153 SJRM11350 Commercial Bid Evaluation 0% 5d 16-Jan-18 22-Jan-18 5 Working Day Commercial Bid Evaluation
154 SJRM11360 Negotiation 0% 2d 23-Jan-18 24-Jan-18 5 Working Day Negotiation
155 SJRM11370 QCF Approval 0% 7d 25-Jan-18 02-Feb-18 5 Working Day QCF Approval
156 SJRM11380 Issuing LoA 0% 1d 05-Feb-18 05-Feb-18 5 Working Day Issuing LoA
157 SJRM11390 Expediting 0% 270d 06-Feb-18 28-Dec-18 6 Working Day Expediting

Project ID : 16STP2019 Actual Level of Effort Critical Remaining Work TASK filter: All Activities
Revison .0, 08-Dec-17 Actual Work Milestone © Oracle Corporation
Status      : 1st Issued
Remaining Work summary
 
SEJIRAM MILL 80 TPH PROJECT
  08-Dec-17 17:37

# Activity ID Activity Name Dur % OD Start Finish Calendar 2017 2018 2019 2020
Complete Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
158 SJRM11400 Receive 1st Tender Docum ent 0% 0d 28-Feb-18 6 Working Day Receive 1st Tender D ocum ent,
159 SJRM11410 Inspection (FAT) 0% 0d 23-Nov-18 6 Working Day Inspection (FAT),
160 SJRM11420 Trans port 0% 30d 29-Dec-18 02-Feb-19 6 Working Day Trans port
161 SJRM11430 ROS(Requested on Site) 0% 0d 02-Feb-19 6 Working Day ROS(Requested on Site),
162 Steam Turbo Alternator 1600 kW at 30 barg 0% 347d 11-Dec-17 02-Feb-19 02-Feb-19, Steam Turbo Alternator 1600 kW at 30 barg
163 SJRM11440 Tender Call (send RFQ) 0% 1d 11-Dec-17 11-Dec-17 5 Working Day Tender Call (send RFQ)
164 SJRM11450 1st Proposal Submission 0% 7d 12-Dec-17 20-Dec-17 5 Working Day 1st Proposal Submission
165 SJRM11460 1st Technic al Bi d Evaluation 0% 7d 21-Dec-17 02-Jan-18 5 Working Day 1st Technic al Bi d Evaluation
166 SJRM11470 1st Technic al Cl arific ation 0% 7d 03-Jan-18 11-Jan-18 5 Working Day 1st Technic al Cl arific ation
167 SJRM11480 2nd Proposal Submission 0% 2d 12-Jan-18 15-Jan-18 5 Working Day 2nd Proposal Submission
168 SJRM11490 Commercial Bid Evaluation 0% 5d 16-Jan-18 22-Jan-18 5 Working Day Commercial Bid Evaluation
169 SJRM11500 Negotiation 0% 2d 23-Jan-18 24-Jan-18 5 Working Day Negotiation
170 SJRM11510 QCF Approval 0% 7d 25-Jan-18 02-Feb-18 5 Working Day QCF Approval
171 SJRM11520 Issuing LoA 0% 1d 05-Feb-18 05-Feb-18 5 Working Day Issuing LoA
172 SJRM11530 Expediting 0% 270d 06-Feb-18 28-Dec-18 6 Working Day Expediting
173 SJRM11540 Receive 1st Tender Docum ent 0% 0d 28-Feb-18 6 Working Day Receive 1st Tender D ocum ent,
174 SJRM11550 Inspection (FAT) 0% 0d 23-Nov-18 6 Working Day Inspection (FAT),
175 SJRM11560 Trans port 0% 30d 29-Dec-18 02-Feb-19 6 Working Day Trans port
176 SJRM11570 ROS(Requested on Site) 0% 0d 02-Feb-19 6 Working Day ROS(Requested on Site),
177 Steam Make Up System 0% 227d 11-Dec-17 13-Sep-18 13-Sep-18, Steam Make Up System
178 SJRM11580 Tender Call (send RFQ) 0% 1d 11-Dec-17 11-Dec-17 5 Working Day Tender Call (send RFQ)
179 SJRM11590 1st Proposal Submission 0% 7d 12-Dec-17 20-Dec-17 5 Working Day 1st Proposal Submission
180 SJRM11600 1st Technic al Bi d Evaluation 0% 7d 21-Dec-17 02-Jan-18 5 Working Day 1st Technic al Bi d Evaluation
181 SJRM11610 1st Technic al Cl arific ation 0% 7d 03-Jan-18 11-Jan-18 5 Working Day 1st Technic al Cl arific ation
182 SJRM11620 2nd Proposal Submission 0% 2d 12-Jan-18 15-Jan-18 5 Working Day 2nd Proposal Submission
183 SJRM11630 Commercial Bid Evaluation 0% 5d 16-Jan-18 22-Jan-18 5 Working Day Commercial Bid Evaluation
184 SJRM11640 Negotiation 0% 2d 23-Jan-18 24-Jan-18 5 Working Day Negotiation
185 SJRM11650 QCF Approval 0% 7d 25-Jan-18 02-Feb-18 5 Working Day QCF Approval
186 SJRM11660 Issuing LoA 0% 1d 05-Feb-18 05-Feb-18 5 Working Day Issuing LoA
187 SJRM11670 Expediting 0% 150d 06-Feb-18 09-Aug-18 6 Working Day Expediting
188 SJRM11680 Receive 1st Tender Docum ent 0% 0d 28-Feb-18 6 Working Day Receive 1st Tender D ocum ent,
189 SJRM11690 Inspection (FAT) 0% 0d 06-Jul-18 6 Working Day Inspection (FAT),
190 SJRM11700 Trans port 0% 30d 10-Aug-18 13-Sep-18 6 Working Day Trans port
191 SJRM11710 ROS(Requested on Site) 0% 0d 13-Sep-18 6 Working Day ROS(Requested on Site),
192 Indexer System 0% 347d 11-Dec-17 02-Feb-19 02-Feb-19, Indexer System
193 SJRM11720 Tender Call (send RFQ) 0% 1d 11-Dec-17 11-Dec-17 5 Working Day Tender Call (send RFQ)
194 SJRM11730 1st Proposal Submission 0% 7d 12-Dec-17 20-Dec-17 5 Working Day 1st Proposal Submission
195 SJRM11740 1st Technic al Bi d Evaluation 0% 7d 21-Dec-17 02-Jan-18 5 Working Day 1st Technic al Bi d Evaluation
196 SJRM11750 1st Technic al Cl arific ation 0% 7d 03-Jan-18 11-Jan-18 5 Working Day 1st Technic al Cl arific ation
197 SJRM11760 2nd Proposal Submission 0% 2d 12-Jan-18 15-Jan-18 5 Working Day 2nd Proposal Submission
198 SJRM11770 Commercial Bid Evaluation 0% 5d 16-Jan-18 22-Jan-18 5 Working Day Commercial Bid Evaluation
199 SJRM11780 Negotiation 0% 2d 23-Jan-18 24-Jan-18 5 Working Day Negotiation
200 SJRM11790 QCF Approval 0% 7d 25-Jan-18 02-Feb-18 5 Working Day QCF Approval
201 SJRM11800 Issuing LoA 0% 1d 05-Feb-18 05-Feb-18 5 Working Day Issuing LoA
202 SJRM11810 Expediting 0% 270d 06-Feb-18 28-Dec-18 6 Working Day Expediting
203 SJRM11820 Receive 1st Tender Docum ent 0% 0d 28-Feb-18 6 Working Day Receive 1st Tender D ocum ent,
204 SJRM11830 Inspection (FAT) 0% 0d 23-Nov-18 6 Working Day Inspection (FAT),
205 SJRM11840 Trans port 0% 30d 29-Dec-18 02-Feb-19 6 Working Day Trans port
206 SJRM11850 ROS(Requested on Site) 0% 0d 02-Feb-19 6 Working Day ROS(Requested on Site),
207 Boiler Feed Water Treatment Plant 0% 316d 06-Feb-18 21-Feb-19 21-Feb-19, Boiler Feed Water Treatment Plant
208 SJRM11860 Tender Call (send RFQ) 0% 1d 06-Feb-18 06-Feb-18 5 Working Day Tender Call (send RFQ)
209 SJRM11870 1st Proposal Submission 0% 7d 07-Feb-18 15-Feb-18 5 Working Day 1st Proposal Submission
210 SJRM11880 1st Technic al Bi d Evaluation 0% 7d 16-Feb-18 26-Feb-18 5 Working Day 1st Technic al Bi d Evaluation
211 SJRM11890 1st Technic al Cl arific ation 0% 7d 27-Feb-18 07-Mar-18 5 Working Day 1st Technic al Cl arific ation
212 SJRM11900 2nd Proposal Submission 0% 2d 08-Mar-18 09-Mar-18 5 Working Day 2nd Proposal Submission
213 SJRM11910 Commercial Bid Evaluation 0% 5d 12-Mar-18 16-Mar-18 5 Working Day Commercial Bid Evaluation
214 SJRM11920 Negotiation 0% 2d 19-Mar-18 20-Mar-18 5 Working Day Negotiation
215 SJRM11930 QCF Approval 0% 7d 21-Mar-18 29-Mar-18 5 Working Day QCF Approval
216 SJRM11940 Issuing LoA 0% 1d 30-Mar-18 30-Mar-18 5 Working Day Issuing LoA
217 SJRM11950 Expediting 0% 240d 31-Mar-18 17-Jan-19 6 Working Day Expediting
218 SJRM11960 Receive 1st Tender Docum ent 0% 0d 24-Apr-18 6 Working Day Receive 1st Tender Docum ent, 24-Apr-18
219 SJRM11970 Inspection (FAT) 0% 0d 12-Dec-18 6 Working Day Inspection (FAT),
220 SJRM11980 Trans port 0% 30d 18-Jan-19 21-Feb-19 6 Working Day Trans port
221 SJRM11990 ROS(Requested on Site) 0% 0d 21-Feb-19 6 Working Day ROS(Requested on Site),
222 Overhead crane in Main Process Building, Workshop & Tranfer Carriage 0% 317d 11-Dec-17 28-Dec-18 28-Dec-18, Overhead crane in Main Process Building, Workshop & Tranfer Carriage
223 SJRM12000 Tender Call (send RFQ) 0% 1d 11-Dec-17 11-Dec-17 5 Working Day Tender Call (send RFQ)
224 SJRM12010 1st Proposal Submission 0% 7d 12-Dec-17 20-Dec-17 5 Working Day 1st Proposal Submission
225 SJRM12020 1st Technic al Bi d Evaluation 0% 7d 21-Dec-17 02-Jan-18 5 Working Day 1st Technic al Bi d Evaluation
226 SJRM12030 1st Technic al Cl arific ation 0% 7d 03-Jan-18 11-Jan-18 5 Working Day 1st Technic al Cl arific ation
227 SJRM12040 2nd Proposal Submission 0% 2d 12-Jan-18 15-Jan-18 5 Working Day 2nd Proposal Submission
228 SJRM12050 Commercial Bid Evaluation 0% 5d 16-Jan-18 22-Jan-18 5 Working Day Commercial Bid Evaluation
229 SJRM12060 Negotiation 0% 2d 23-Jan-18 24-Jan-18 5 Working Day Negotiation
230 SJRM12070 QCF Approval 0% 7d 25-Jan-18 02-Feb-18 5 Working Day QCF Approval
231 SJRM12080 Issuing LoA 0% 1d 05-Feb-18 05-Feb-18 5 Working Day Issuing LoA
232 SJRM12090 Expediting 0% 240d 06-Feb-18 22-Nov-18 6 Working Day Expediting
233 SJRM12100 Receive 1st Tender Docum ent 0% 0d 01-Mar-18 6 Working Day Receive 1st Tender D ocum ent, 01-Mar-18
234 SJRM12110 Inspection (FAT) 0% 0d 19-Oct-18 6 Working Day Inspection (FAT),

Project ID : 16STP2019 Actual Level of Effort Critical Remaining Work TASK filter: All Activities
Revison .0, 08-Dec-17 Actual Work Milestone © Oracle Corporation
Status      : 1st Issued
Remaining Work summary
 
SEJIRAM MILL 80 TPH PROJECT
  08-Dec-17 17:37

# Activity ID Activity Name Dur % OD Start Finish Calendar 2017 2018 2019 2020
Complete Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
235 SJRM12120 Trans port 0% 30d 23-Nov-18 28-Dec-18 6 Working Day Trans port
236 SJRM12130 ROS(Requested on Site) 0% 0d 28-Dec-18 6 Working Day ROS(Requested on Site),
237 Prop Item Package Document 0% 269d 28-Dec-17 17-Nov-18 17-Nov-18, Prop Item Package Document
238 Big Diesel Generating Set & Small Diesel Generating Set 0% 227d 09-Feb-18 10-Nov-18 10-Nov-18, Big Diesel Generating Set & Small Diesel Generating Set
239 SJRM12140 Tender Call (send RFQ) 0% 1d 09-Feb-18 09-Feb-18 5 Working Day Tender Call (send RFQ)
240 SJRM12150 1st Proposal Submission 0% 7d 12-Feb-18 20-Feb-18 5 Working Day 1st Proposal Submission
241 SJRM12160 1st Technic al Bi d Evaluation 0% 7d 21-Feb-18 01-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
242 SJRM12170 1st Technic al Cl arific ation 0% 7d 02-Mar-18 12-Mar-18 5 Working Day 1st Technic al Cl arific ation
243 SJRM12180 2nd Proposal Submission 0% 2d 13-Mar-18 14-Mar-18 5 Working Day 2nd Proposal Submission
244 SJRM12190 Commercial Bid Evaluation 0% 5d 15-Mar-18 21-Mar-18 5 Working Day Commercial Bid Evaluation
245 SJRM12200 Negotiation 0% 2d 22-Mar-18 23-Mar-18 5 Working Day Negotiation
246 SJRM12210 QCF Approval 0% 7d 26-Mar-18 03-Apr-18 5 Working Day QCF Approval
247 SJRM12220 Issuing LoA 0% 1d 04-Apr-18 04-Apr-18 5 Working Day Issuing LoA
248 SJRM12230 Expediting 0% 150d 05-Apr-18 06-Oct-18 6 Working Day Expediting
249 SJRM12240 Receive 1st Tender Docum ent 0% 0d 28-Apr-18 6 Working Day Receive 1st Tender Docum ent, 28-Apr-18
250 SJRM12250 Inspection (FAT) 0% 0d 03-Sep-18 6 Working Day Inspection (FAT),
251 SJRM12260 Trans port 0% 30d 08-Oct-18 10-Nov-18 6 Working Day Trans port
252 SJRM12270 ROS(Requested on Site) 0% 0d 10-Nov-18 6 Working Day ROS(Requested on Site),
253 Road Weighbridge 0% 227d 19-Jan-18 20-Oct-18 20-Oct-18, Road Weighbridge
254 SJRM12280 Tender Call (send RFQ) 0% 1d 19-Jan-18 19-Jan-18 5 Working Day Tender Call (send RFQ)
255 SJRM12290 1st Proposal Submission 0% 7d 22-Jan-18 30-Jan-18 5 Working Day 1st Proposal Submission
256 SJRM12300 1st Technic al Bi d Evaluation 0% 7d 31-Jan-18 08-Feb-18 5 Working Day 1st Technic al Bi d Evaluation
257 SJRM12310 1st Technic al Cl arific ation 0% 7d 09-Feb-18 19-Feb-18 5 Working Day 1st Technic al Cl arific ation
258 SJRM12320 2nd Proposal Submission 0% 2d 20-Feb-18 21-Feb-18 5 Working Day 2nd Proposal Submission
259 SJRM12330 Commercial Bid Evaluation 0% 5d 22-Feb-18 28-Feb-18 5 Working Day Commercial Bid Evaluation
260 SJRM12340 Negotiation 0% 2d 01-Mar-18 02-Mar-18 5 Working Day Negotiation
261 SJRM12350 QCF Approval 0% 7d 05-Mar-18 13-Mar-18 5 Working Day QCF Approval
262 SJRM12360 Issuing LoA 0% 1d 14-Mar-18 14-Mar-18 5 Working Day Issuing LoA
263 SJRM12370 Expediting 0% 150d 15-Mar-18 15-Sep-18 6 Working Day Expediting
264 SJRM12380 Receive 1st Tender Docum ent 0% 0d 07-Apr-18 6 Working Day Receive 1st Tender Docum ent, 07-Apr-18
265 SJRM12390 Inspection (FAT) 0% 0d 13-Aug-18 6 Working Day Inspection (FAT),
266 SJRM12400 Trans port 0% 30d 17-Sep-18 20-Oct-18 6 Working Day Trans port
267 SJRM12410 ROS(Requested on Site) 0% 0d 20-Oct-18 6 Working Day ROS(Requested on Site),
268 Cages (capacity 10 Tons FFB) 0% 227d 26-Jan-18 27-Oct-18 27-Oct-18, Cages (capacity 10 Tons FFB)
269 SJRM12420 Tender Call (send RFQ) 0% 1d 26-Jan-18 26-Jan-18 5 Working Day Tender Call (send RFQ)
270 SJRM12430 1st Proposal Submission 0% 7d 29-Jan-18 06-Feb-18 5 Working Day 1st Proposal Submission
271 SJRM12440 1st Technic al Bi d Evaluation 0% 7d 07-Feb-18 15-Feb-18 5 Working Day 1st Technic al Bi d Evaluation
272 SJRM12450 1st Technic al Cl arific ation 0% 7d 16-Feb-18 26-Feb-18 5 Working Day 1st Technic al Cl arific ation
273 SJRM12460 2nd Proposal Submission 0% 2d 27-Feb-18 28-Feb-18 5 Working Day 2nd Proposal Submission
274 SJRM12470 Commercial Bid Evaluation 0% 5d 01-Mar-18 07-Mar-18 5 Working Day Commercial Bid Evaluation
275 SJRM12480 Negotiation 0% 2d 08-Mar-18 09-Mar-18 5 Working Day Negotiation
276 SJRM12490 QCF Approval 0% 7d 12-Mar-18 20-Mar-18 5 Working Day QCF Approval
277 SJRM12500 Issuing LoA 0% 1d 21-Mar-18 21-Mar-18 5 Working Day Issuing LoA
278 SJRM12510 Expediting 0% 150d 22-Mar-18 22-Sep-18 6 Working Day Expediting
279 SJRM12520 Receive 1st Tender Docum ent 0% 0d 14-Apr-18 6 Working Day Receive 1st Tender D ocum ent, 14-Apr-18
280 SJRM12530 Inspection (FAT) 0% 0d 20-Aug-18 6 Working Day Inspection (FAT),
281 SJRM12540 Trans port 0% 30d 24-Sep-18 27-Oct-18 6 Working Day Trans port
282 SJRM12550 ROS(Requested on Site) 0% 0d 27-Oct-18 6 Working Day ROS(Requested on Site),
283 Transfer C arriage 0% 227d 28-Dec-17 29-Sep-18 29-Sep-18, Transfer Carriage
284 SJRM12560 Tender Call (send RFQ) 0% 1d 28-Dec-17 28-Dec-17 5 Working Day Tender Call (send RFQ)
285 SJRM12570 1st Proposal Submission 0% 7d 29-Dec-17 09-Jan-18 5 Working Day 1st Proposal Submission
286 SJRM12580 1st Technic al Bi d Evaluation 0% 7d 10-Jan-18 18-Jan-18 5 Working Day 1st Technic al Bi d Evaluation
287 SJRM12590 1st Technic al Cl arific ation 0% 7d 19-Jan-18 29-Jan-18 5 Working Day 1st Technic al Cl arific ation
288 SJRM12600 2nd Proposal Submission 0% 2d 30-Jan-18 31-Jan-18 5 Working Day 2nd Proposal Submission
289 SJRM12610 Commercial Bid Evaluation 0% 5d 01-Feb-18 07-Feb-18 5 Working Day Commercial Bid Evaluation
290 SJRM12620 Negotiation 0% 2d 08-Feb-18 09-Feb-18 5 Working Day Negotiation
291 SJRM12630 QCF Approval 0% 7d 12-Feb-18 20-Feb-18 5 Working Day QCF Approval
292 SJRM12640 Issuing LoA 0% 1d 21-Feb-18 21-Feb-18 5 Working Day Issuing LoA
293 SJRM12650 Expediting 0% 150d 22-Feb-18 25-Aug-18 6 Working Day Expediting
294 SJRM12660 Receive 1st Tender Docum ent 0% 0d 17-Mar-18 6 Working Day Receive 1st Tender Docum ent, 17-Mar-18
295 SJRM12670 Inspection (FAT) 0% 0d 23-Jul-18 6 Working Day Inspection (FAT),
296 SJRM12680 Trans port 0% 30d 27-Aug-18 29-Sep-18 6 Working Day Trans port
297 SJRM12690 ROS(Requested on Site) 0% 0d 29-Sep-18 6 Working Day ROS(Requested on Site),
298 Tippler (2 x @10 tons FFB cages) 0% 227d 28-Dec-17 29-Sep-18 29-Sep-18, Tippler (2 x @10 tons FFB cages)
299 SJRM12700 Tender Call (send RFQ) 0% 1d 28-Dec-17 28-Dec-17 5 Working Day Tender Call (send RFQ)
300 SJRM12710 1st Proposal Submission 0% 7d 29-Dec-17 09-Jan-18 5 Working Day 1st Proposal Submission
301 SJRM12720 1st Technic al Bi d Evaluation 0% 7d 10-Jan-18 18-Jan-18 5 Working Day 1st Technic al Bi d Evaluation
302 SJRM12730 1st Technic al Cl arific ation 0% 7d 19-Jan-18 29-Jan-18 5 Working Day 1st Technic al Cl arific ation
303 SJRM12740 2nd Proposal Submission 0% 2d 30-Jan-18 31-Jan-18 5 Working Day 2nd Proposal Submission
304 SJRM12750 Commercial Bid Evaluation 0% 5d 01-Feb-18 07-Feb-18 5 Working Day Commercial Bid Evaluation
305 SJRM12760 Negotiation 0% 2d 08-Feb-18 09-Feb-18 5 Working Day Negotiation
306 SJRM12770 QCF Approval 0% 7d 12-Feb-18 20-Feb-18 5 Working Day QCF Approval
307 SJRM12780 Issuing LoA 0% 1d 21-Feb-18 21-Feb-18 5 Working Day Issuing LoA
308 SJRM12790 Expediting 0% 150d 22-Feb-18 25-Aug-18 6 Working Day Expediting
309 SJRM12800 Receive 1st Tender Docum ent 0% 0d 17-Mar-18 6 Working Day Receive 1st Tender Docum ent, 17-Mar-18
310 SJRM12810 Inspection (FAT) 0% 0d 23-Jul-18 6 Working Day Inspection (FAT),
311 SJRM12820 Trans port 0% 30d 27-Aug-18 29-Sep-18 6 Working Day Trans port

Project ID : 16STP2019 Actual Level of Effort Critical Remaining Work TASK filter: All Activities
Revison .0, 08-Dec-17 Actual Work Milestone © Oracle Corporation
Status      : 1st Issued
Remaining Work summary
 
SEJIRAM MILL 80 TPH PROJECT
  08-Dec-17 17:37

# Activity ID Activity Name Dur % OD Start Finish Calendar 2017 2018 2019 2020
Complete Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
312 SJRM12830 ROS(Requested on Site) 0% 0d 29-Sep-18 6 Working Day ROS(Requested on Site),
313 Bunch Hopper & Gate Bunch Feeder (2 x 10 tons FFB) 0% 227d 02-Feb-18 03-Nov-18 03-Nov-18, Bunch Hopper & Gate Bunch Feeder (2 x 10 tons FFB)
314 SJRM12840 Tender Call (send RFQ) 0% 1d 02-Feb-18 02-Feb-18 5 Working Day Tender Call (send RFQ)
315 SJRM12850 1st Proposal Submission 0% 7d 05-Feb-18 13-Feb-18 5 Working Day 1st Proposal Submission
316 SJRM12860 1st Technic al Bi d Evaluation 0% 7d 14-Feb-18 22-Feb-18 5 Working Day 1st Technic al Bi d Evaluation
317 SJRM12870 1st Technic al Cl arific ation 0% 7d 23-Feb-18 05-Mar-18 5 Working Day 1st Technic al Cl arific ation
318 SJRM12880 2nd Proposal Submission 0% 2d 06-Mar-18 07-Mar-18 5 Working Day 2nd Proposal Submission
319 SJRM12890 Commercial Bid Evaluation 0% 5d 08-Mar-18 14-Mar-18 5 Working Day Commercial Bid Evaluation
320 SJRM12900 Negotiation 0% 2d 15-Mar-18 16-Mar-18 5 Working Day Negotiation
321 SJRM12910 QCF Approval 0% 7d 19-Mar-18 27-Mar-18 5 Working Day QCF Approval
322 SJRM12920 Issuing LoA 0% 1d 28-Mar-18 28-Mar-18 5 Working Day Issuing LoA
323 SJRM12930 Expediting 0% 150d 29-Mar-18 29-Sep-18 6 Working Day Expediting
324 SJRM12940 Receive 1st Tender Docum ent 0% 0d 21-Apr-18 6 Working Day Receive 1st Tender Docum ent, 21-Apr-18
325 SJRM12950 Inspection (FAT) 0% 0d 27-Aug-18 6 Working Day Inspection (FAT),
326 SJRM12960 Trans port 0% 30d 01-Oct-18 03-Nov-18 6 Working Day Trans port
327 SJRM12970 ROS(Requested on Site) 0% 0d 03-Nov-18 6 Working Day ROS(Requested on Site),
328 Crane Grapple 0% 227d 09-Feb-18 10-Nov-18 10-Nov-18, Crane Grapple
329 SJRM12980 Tender Call (send RFQ) 0% 1d 09-Feb-18 09-Feb-18 5 Working Day Tender Call (send RFQ)
330 SJRM12990 1st Proposal Submission 0% 7d 12-Feb-18 20-Feb-18 5 Working Day 1st Proposal Submission
331 SJRM13000 1st Technic al Bi d Evaluation 0% 7d 21-Feb-18 01-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
332 SJRM13010 1st Technic al Cl arific ation 0% 7d 02-Mar-18 12-Mar-18 5 Working Day 1st Technic al Cl arific ation
333 SJRM13020 2nd Proposal Submission 0% 2d 13-Mar-18 14-Mar-18 5 Working Day 2nd Proposal Submission
334 SJRM13030 Commercial Bid Evaluation 0% 5d 15-Mar-18 21-Mar-18 5 Working Day Commercial Bid Evaluation
335 SJRM13040 Negotiation 0% 2d 22-Mar-18 23-Mar-18 5 Working Day Negotiation
336 SJRM13050 QCF Approval 0% 7d 26-Mar-18 03-Apr-18 5 Working Day QCF Approval
337 SJRM13060 Issuing LoA 0% 1d 04-Apr-18 04-Apr-18 5 Working Day Issuing LoA
338 SJRM13070 Expediting 0% 150d 05-Apr-18 06-Oct-18 6 Working Day Expediting
339 SJRM13080 Receive 1st Tender Docum ent 0% 0d 28-Apr-18 6 Working Day Receive 1st Tender Docum ent, 28-Apr-18
340 SJRM13090 Inspection (FAT) 0% 0d 03-Sep-18 6 Working Day Inspection (FAT),
341 SJRM13100 Trans port 0% 30d 08-Oct-18 10-Nov-18 6 Working Day Trans port
342 SJRM13110 ROS(Requested on Site) 0% 0d 10-Nov-18 6 Working Day ROS(Requested on Site),
343 Digesters (4,000 ltr) 0% 227d 28-Dec-17 29-Sep-18 29-Sep-18, Digesters (4,000 ltr)
344 SJRM13120 Tender Call (send RFQ) 0% 1d 28-Dec-17 28-Dec-17 5 Working Day Tender Call (send RFQ)
345 SJRM13130 1st Proposal Submission 0% 7d 29-Dec-17 09-Jan-18 5 Working Day 1st Proposal Submission
346 SJRM13140 1st Technic al Bi d Evaluation 0% 7d 10-Jan-18 18-Jan-18 5 Working Day 1st Technic al Bi d Evaluation
347 SJRM13150 1st Technic al Cl arific ation 0% 7d 19-Jan-18 29-Jan-18 5 Working Day 1st Technic al Cl arific ation
348 SJRM13160 2nd Proposal Submission 0% 2d 30-Jan-18 31-Jan-18 5 Working Day 2nd Proposal Submission
349 SJRM13170 Commercial Bid Evaluation 0% 5d 01-Feb-18 07-Feb-18 5 Working Day Commercial Bid Evaluation
350 SJRM13180 Negotiation 0% 2d 08-Feb-18 09-Feb-18 5 Working Day Negotiation
351 SJRM13190 QCF Approval 0% 7d 12-Feb-18 20-Feb-18 5 Working Day QCF Approval
352 SJRM13200 Issuing LoA 0% 1d 21-Feb-18 21-Feb-18 5 Working Day Issuing LoA
353 SJRM13210 Expediting 0% 150d 22-Feb-18 25-Aug-18 6 Working Day Expediting
354 SJRM13220 Receive 1st Tender Docum ent 0% 0d 17-Mar-18 6 Working Day Receive 1st Tender Docum ent, 17-Mar-18
355 SJRM13230 Inspection (FAT) 0% 0d 23-Jul-18 6 Working Day Inspection (FAT),
356 SJRM13240 Trans port 0% 30d 27-Aug-18 29-Sep-18 6 Working Day Trans port
357 SJRM13250 ROS(Requested on Site) 0% 0d 29-Sep-18 6 Working Day ROS(Requested on Site),
358 Screw Press (P-20) 0% 227d 16-Feb-18 17-Nov-18 17-Nov-18, Screw Press (P-20)
359 SJRM13260 Tender Call (send RFQ) 0% 1d 16-Feb-18 16-Feb-18 5 Working Day Tender Call (send RFQ)
360 SJRM13270 1st Proposal Submission 0% 7d 19-Feb-18 27-Feb-18 5 Working Day 1st Proposal Submission
361 SJRM13280 1st Technic al Bi d Evaluation 0% 7d 28-Feb-18 08-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
362 SJRM13290 1st Technic al Cl arific ation 0% 7d 09-Mar-18 19-Mar-18 5 Working Day 1st Technic al Cl arific ation
363 SJRM13300 2nd Proposal Submission 0% 2d 20-Mar-18 21-Mar-18 5 Working Day 2nd Proposal Submission
364 SJRM13310 Commercial Bid Evaluation 0% 5d 22-Mar-18 28-Mar-18 5 Working Day Commercial Bid Evaluation
365 SJRM13320 Negotiation 0% 2d 29-Mar-18 30-Mar-18 5 Working Day Negotiation
366 SJRM13330 QCF Approval 0% 7d 02-Apr-18 10-Apr-18 5 Working Day QCF Approval
367 SJRM13340 Issuing LoA 0% 1d 11-Apr-18 11-Apr-18 5 Working Day Issuing LoA
368 SJRM13350 Expediting 0% 150d 12-Apr-18 13-Oct-18 6 Working Day Expediting
369 SJRM13360 Receive 1st Tender Docum ent 0% 0d 05-May-18 6 Working Day Receive 1st Tender D ocum ent, 05-May-18
370 SJRM13370 Inspection (FAT) 0% 0d 10-Sep-18 6 Working Day Inspection (FAT),
371 SJRM13380 Trans port 0% 30d 15-Oct-18 17-Nov-18 6 Working Day Trans port
372 SJRM13390 ROS(Requested on Site) 0% 0d 17-Nov-18 6 Working Day ROS(Requested on Site),
373 Screw Press Power Pack 0% 227d 16-Feb-18 17-Nov-18 17-Nov-18, Screw Press Power Pack
374 SJRM13400 Tender Call (send RFQ) 0% 1d 16-Feb-18 16-Feb-18 5 Working Day Tender Call (send RFQ)
375 SJRM13410 1st Proposal Submission 0% 7d 19-Feb-18 27-Feb-18 5 Working Day 1st Proposal Submission
376 SJRM13420 1st Technic al Bi d Evaluation 0% 7d 28-Feb-18 08-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
377 SJRM13430 1st Technic al Cl arific ation 0% 7d 09-Mar-18 19-Mar-18 5 Working Day 1st Technic al Cl arific ation
378 SJRM13440 2nd Proposal Submission 0% 2d 20-Mar-18 21-Mar-18 5 Working Day 2nd Proposal Submission
379 SJRM13450 Commercial Bid Evaluation 0% 5d 22-Mar-18 28-Mar-18 5 Working Day Commercial Bid Evaluation
380 SJRM13460 Negotiation 0% 2d 29-Mar-18 30-Mar-18 5 Working Day Negotiation
381 SJRM13470 QCF Approval 0% 7d 02-Apr-18 10-Apr-18 5 Working Day QCF Approval
382 SJRM13480 Issuing LoA 0% 1d 11-Apr-18 11-Apr-18 5 Working Day Issuing LoA
383 SJRM13490 Expediting 0% 150d 12-Apr-18 13-Oct-18 6 Working Day Expediting
384 SJRM13500 Receive 1st Tender Docum ent 0% 0d 05-May-18 6 Working Day Receive 1st Tender D ocum ent, 05-May-18
385 SJRM13510 Inspection (FAT) 0% 0d 10-Sep-18 6 Working Day Inspection (FAT),
386 SJRM13520 Trans port 0% 30d 15-Oct-18 17-Nov-18 6 Working Day Trans port
387 SJRM13530 ROS(Requested on Site) 0% 0d 17-Nov-18 6 Working Day ROS(Requested on Site),
388 Crude Oil Vibrating Screen 0% 227d 16-Feb-18 17-Nov-18 17-Nov-18, Crude Oil Vibrating Screen

Project ID : 16STP2019 Actual Level of Effort Critical Remaining Work TASK filter: All Activities
Revison .0, 08-Dec-17 Actual Work Milestone © Oracle Corporation
Status      : 1st Issued
Remaining Work summary
 
SEJIRAM MILL 80 TPH PROJECT
  08-Dec-17 17:37

# Activity ID Activity Name Dur % OD Start Finish Calendar 2017 2018 2019 2020
Complete Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
389 SJRM13540 Tender Call (send RFQ) 0% 1d 16-Feb-18 16-Feb-18 5 Working Day Tender Call (send RFQ)
390 SJRM13550 1st Proposal Submission 0% 7d 19-Feb-18 27-Feb-18 5 Working Day 1st Proposal Submission
391 SJRM13560 1st Technic al Bi d Evaluation 0% 7d 28-Feb-18 08-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
392 SJRM13570 1st Technic al Cl arific ation 0% 7d 09-Mar-18 19-Mar-18 5 Working Day 1st Technic al Cl arific ation
393 SJRM13580 2nd Proposal Submission 0% 2d 20-Mar-18 21-Mar-18 5 Working Day 2nd Proposal Submission
394 SJRM13590 Commercial Bid Evaluation 0% 5d 22-Mar-18 28-Mar-18 5 Working Day Commercial Bid Evaluation
395 SJRM13600 Negotiation 0% 2d 29-Mar-18 30-Mar-18 5 Working Day Negotiation
396 SJRM13610 QCF Approval 0% 7d 02-Apr-18 10-Apr-18 5 Working Day QCF Approval
397 SJRM13620 Issuing LoA 0% 1d 11-Apr-18 11-Apr-18 5 Working Day Issuing LoA
398 SJRM13630 Expediting 0% 150d 12-Apr-18 13-Oct-18 6 Working Day Expediting
399 SJRM13640 Receive 1st Tender Docum ent 0% 0d 05-May-18 6 Working Day Receive 1st Tender D ocum ent, 05-May-18
400 SJRM13650 Inspection (FAT) 0% 0d 10-Sep-18 6 Working Day Inspection (FAT),
401 SJRM13660 Trans port 0% 30d 15-Oct-18 17-Nov-18 6 Working Day Trans port
402 SJRM13670 ROS(Requested on Site) 0% 0d 17-Nov-18 6 Working Day ROS(Requested on Site),
403 Sludge Vibrating Screen 0% 227d 16-Feb-18 17-Nov-18 17-Nov-18, Sludge Vibrating Screen
404 SJRM13680 Tender Call (send RFQ) 0% 1d 16-Feb-18 16-Feb-18 5 Working Day Tender Call (send RFQ)
405 SJRM13690 1st Proposal Submission 0% 7d 19-Feb-18 27-Feb-18 5 Working Day 1st Proposal Submission
406 SJRM13700 1st Technic al Bi d Evaluation 0% 7d 28-Feb-18 08-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
407 SJRM13710 1st Technic al Cl arific ation 0% 7d 09-Mar-18 19-Mar-18 5 Working Day 1st Technic al Cl arific ation
408 SJRM13720 2nd Proposal Submission 0% 2d 20-Mar-18 21-Mar-18 5 Working Day 2nd Proposal Submission
409 SJRM13730 Commercial Bid Evaluation 0% 5d 22-Mar-18 28-Mar-18 5 Working Day Commercial Bid Evaluation
410 SJRM13740 Negotiation 0% 2d 29-Mar-18 30-Mar-18 5 Working Day Negotiation
411 SJRM13750 QCF Approval 0% 7d 02-Apr-18 10-Apr-18 5 Working Day QCF Approval
412 SJRM13760 Issuing LoA 0% 1d 11-Apr-18 11-Apr-18 5 Working Day Issuing LoA
413 SJRM13770 Expediting 0% 150d 12-Apr-18 13-Oct-18 6 Working Day Expediting
414 SJRM13780 Receive 1st Tender Docum ent 0% 0d 05-May-18 6 Working Day Receive 1st Tender D ocum ent, 05-May-18
415 SJRM13790 Inspection (FAT) 0% 0d 10-Sep-18 6 Working Day Inspection (FAT),
416 SJRM13800 Trans port 0% 30d 15-Oct-18 17-Nov-18 6 Working Day Trans port
417 SJRM13810 ROS(Requested on Site) 0% 0d 17-Nov-18 6 Working Day ROS(Requested on Site),
418 Sludge Centrifuge 12000 ltr/hr 0% 227d 26-Jan-18 27-Oct-18 27-Oct-18, Sludge Centrifuge 12000 ltr/hr
419 SJRM13820 Tender Call (send RFQ) 0% 1d 26-Jan-18 26-Jan-18 5 Working Day Tender Call (send RFQ)
420 SJRM13830 1st Proposal Submission 0% 7d 29-Jan-18 06-Feb-18 5 Working Day 1st Proposal Submission
421 SJRM13840 1st Technic al Bi d Evaluation 0% 7d 07-Feb-18 15-Feb-18 5 Working Day 1st Technic al Bi d Evaluation
422 SJRM13850 1st Technic al Cl arific ation 0% 7d 16-Feb-18 26-Feb-18 5 Working Day 1st Technic al Cl arific ation
423 SJRM13860 2nd Proposal Submission 0% 2d 27-Feb-18 28-Feb-18 5 Working Day 2nd Proposal Submission
424 SJRM13870 Commercial Bid Evaluation 0% 5d 01-Mar-18 07-Mar-18 5 Working Day Commercial Bid Evaluation
425 SJRM13880 Negotiation 0% 2d 08-Mar-18 09-Mar-18 5 Working Day Negotiation
426 SJRM13890 QCF Approval 0% 7d 12-Mar-18 20-Mar-18 5 Working Day QCF Approval
427 SJRM13900 Issuing LoA 0% 1d 21-Mar-18 21-Mar-18 5 Working Day Issuing LoA
428 SJRM13910 Expediting 0% 150d 22-Mar-18 22-Sep-18 6 Working Day Expediting
429 SJRM13920 Receive 1st Tender Docum ent 0% 0d 14-Apr-18 6 Working Day Receive 1st Tender D ocum ent, 14-Apr-18
430 SJRM13930 Inspection (FAT) 0% 0d 20-Aug-18 6 Working Day Inspection (FAT),
431 SJRM13940 Trans port 0% 30d 24-Sep-18 27-Oct-18 6 Working Day Trans port
432 SJRM13950 ROS(Requested on Site) 0% 0d 27-Oct-18 6 Working Day ROS(Requested on Site),
433 Air Compressor, Air dryer & A ir Receiver 3000L 0% 227d 19-Jan-18 20-Oct-18 20-Oct-18, Air Compressor, Air dryer & Air Receiver 3000L
434 SJRM13960 Tender Call (send RFQ) 0% 1d 19-Jan-18 19-Jan-18 5 Working Day Tender Call (send RFQ)
435 SJRM13970 1st Proposal Submission 0% 7d 22-Jan-18 30-Jan-18 5 Working Day 1st Proposal Submission
436 SJRM13980 1st Technic al Bi d Evaluation 0% 7d 31-Jan-18 08-Feb-18 5 Working Day 1st Technic al Bi d Evaluation
437 SJRM13990 1st Technic al Cl arific ation 0% 7d 09-Feb-18 19-Feb-18 5 Working Day 1st Technic al Cl arific ation
438 SJRM14000 2nd Proposal Submission 0% 2d 20-Feb-18 21-Feb-18 5 Working Day 2nd Proposal Submission
439 SJRM14010 Commercial Bid Evaluation 0% 5d 22-Feb-18 28-Feb-18 5 Working Day Commercial Bid Evaluation
440 SJRM14020 Negotiation 0% 2d 01-Mar-18 02-Mar-18 5 Working Day Negotiation
441 SJRM14030 QCF Approval 0% 7d 05-Mar-18 13-Mar-18 5 Working Day QCF Approval
442 SJRM14040 Issuing LoA 0% 1d 14-Mar-18 14-Mar-18 5 Working Day Issuing LoA
443 SJRM14050 Expediting 0% 150d 15-Mar-18 15-Sep-18 6 Working Day Expediting
444 SJRM14060 Receive 1st Tender Docum ent 0% 0d 07-Apr-18 6 Working Day Receive 1st Tender Docum ent, 07-Apr-18
445 SJRM14070 Inspection (FAT) 0% 0d 13-Aug-18 6 Working Day Inspection (FAT),
446 SJRM14080 Trans port 0% 30d 17-Sep-18 20-Oct-18 6 Working Day Trans port
447 SJRM14090 ROS(Requested on Site) 0% 0d 20-Oct-18 6 Working Day ROS(Requested on Site),
448 Sterilizer Automatic Con trol 0% 227d 16-Feb-18 17-Nov-18 17-Nov-18, Sterilizer Autom atic Control
449 SJRM14100 Tender Call (send RFQ) 0% 1d 16-Feb-18 16-Feb-18 5 Working Day Tender Call (send RFQ)
450 SJRM14110 1st Proposal Submission 0% 7d 19-Feb-18 27-Feb-18 5 Working Day 1st Proposal Submission
451 SJRM14120 1st Technic al Bi d Evaluation 0% 7d 28-Feb-18 08-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
452 SJRM14130 1st Technic al Cl arific ation 0% 7d 09-Mar-18 19-Mar-18 5 Working Day 1st Technic al Cl arific ation
453 SJRM14140 2nd Proposal Submission 0% 2d 20-Mar-18 21-Mar-18 5 Working Day 2nd Proposal Submission
454 SJRM14150 Commercial Bid Evaluation 0% 5d 22-Mar-18 28-Mar-18 5 Working Day Commercial Bid Evaluation
455 SJRM14160 Negotiation 0% 2d 29-Mar-18 30-Mar-18 5 Working Day Negotiation
456 SJRM14170 QCF Approval 0% 7d 02-Apr-18 10-Apr-18 5 Working Day QCF Approval
457 SJRM14180 Issuing LoA 0% 1d 11-Apr-18 11-Apr-18 5 Working Day Issuing LoA
458 SJRM14190 Expediting 0% 150d 12-Apr-18 13-Oct-18 6 Working Day Expediting
459 SJRM14200 Receive 1st Tender Docum ent 0% 0d 05-May-18 6 Working Day Receive 1st Tender D ocum ent, 05-May-18
460 SJRM14210 Inspection (FAT) 0% 0d 10-Sep-18 6 Working Day Inspection (FAT),
461 SJRM14220 Trans port 0% 30d 15-Oct-18 17-Nov-18 6 Working Day Trans port
462 SJRM14230 ROS(Requested on Site) 0% 0d 17-Nov-18 6 Working Day ROS(Requested on Site),
463 Self Separating Bunch Crusher 0% 227d 16-Feb-18 17-Nov-18 17-Nov-18, Self Separating Bunch Crusher
464 SJRM14240 Tender Call (send RFQ) 0% 1d 16-Feb-18 16-Feb-18 5 Working Day Tender Call (send RFQ)
465 SJRM14250 1st Proposal Submission 0% 7d 19-Feb-18 27-Feb-18 5 Working Day 1st Proposal Submission

Project ID : 16STP2019 Actual Level of Effort Critical Remaining Work TASK filter: All Activities
Revison .0, 08-Dec-17 Actual Work Milestone © Oracle Corporation
Status      : 1st Issued
Remaining Work summary
 
SEJIRAM MILL 80 TPH PROJECT
  08-Dec-17 17:37

# Activity ID Activity Name Dur % OD Start Finish Calendar 2017 2018 2019 2020
Complete Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
466 SJRM14260 1st Technic al Bi d Evaluation 0% 7d 28-Feb-18 08-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
467 SJRM14270 1st Technic al Cl arific ation 0% 7d 09-Mar-18 19-Mar-18 5 Working Day 1st Technic al Cl arific ation
468 SJRM14280 2nd Proposal Submission 0% 2d 20-Mar-18 21-Mar-18 5 Working Day 2nd Proposal Submission
469 SJRM14290 Commercial Bid Evaluation 0% 5d 22-Mar-18 28-Mar-18 5 Working Day Commercial Bid Evaluation
470 SJRM14300 Negotiation 0% 2d 29-Mar-18 30-Mar-18 5 Working Day Negotiation
471 SJRM14310 QCF Approval 0% 7d 02-Apr-18 10-Apr-18 5 Working Day QCF Approval
472 SJRM14320 Issuing LoA 0% 1d 11-Apr-18 11-Apr-18 5 Working Day Issuing LoA
473 SJRM14330 Expediting 0% 150d 12-Apr-18 13-Oct-18 6 Working Day Expediting
474 SJRM14340 Receive 1st Tender Docum ent 0% 0d 05-May-18 6 Working Day Receive 1st Tender D ocum ent, 05-May-18
475 SJRM14350 Inspection (FAT) 0% 0d 10-Sep-18 6 Working Day Inspection (FAT),
476 SJRM14360 Trans port 0% 30d 15-Oct-18 17-Nov-18 6 Working Day Trans port
477 SJRM14370 ROS(Requested on Site) 0% 0d 17-Nov-18 6 Working Day ROS(Requested on Site),
478 Vacuum O il Dryer c/w Vacuum Pump 15 m3/hr 0% 227d 16-Feb-18 17-Nov-18 17-Nov-18, Vacuum Oil Dryer c/w Vacuum Pum p 15 m3/hr
479 SJRM14380 Tender Call (send RFQ) 0% 1d 16-Feb-18 16-Feb-18 5 Working Day Tender Call (send RFQ)
480 SJRM14390 1st Proposal Submission 0% 7d 19-Feb-18 27-Feb-18 5 Working Day 1st Proposal Submission
481 SJRM14400 1st Technic al Bi d Evaluation 0% 7d 28-Feb-18 08-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
482 SJRM14410 1st Technic al Cl arific ation 0% 7d 09-Mar-18 19-Mar-18 5 Working Day 1st Technic al Cl arific ation
483 SJRM14420 2nd Proposal Submission 0% 2d 20-Mar-18 21-Mar-18 5 Working Day 2nd Proposal Submission
484 SJRM14430 Commercial Bid Evaluation 0% 5d 22-Mar-18 28-Mar-18 5 Working Day Commercial Bid Evaluation
485 SJRM14440 Negotiation 0% 2d 29-Mar-18 30-Mar-18 5 Working Day Negotiation
486 SJRM14450 QCF Approval 0% 7d 02-Apr-18 10-Apr-18 5 Working Day QCF Approval
487 SJRM14460 Issuing LoA 0% 1d 11-Apr-18 11-Apr-18 5 Working Day Issuing LoA
488 SJRM14470 Expediting 0% 150d 12-Apr-18 13-Oct-18 6 Working Day Expediting
489 SJRM14480 Receive 1st Tender Docum ent 0% 0d 05-May-18 6 Working Day Receive 1st Tender D ocum ent, 05-May-18
490 SJRM14490 Inspection (FAT) 0% 0d 10-Sep-18 6 Working Day Inspection (FAT),
491 SJRM14500 Trans port 0% 30d 15-Oct-18 17-Nov-18 6 Working Day Trans port
492 SJRM14510 ROS(Requested on Site) 0% 0d 17-Nov-18 6 Working Day ROS(Requested on Site),
493 Oil Transf er Pu mp / Dried Oil Pump 0% 227d 16-Feb-18 17-Nov-18 17-Nov-18, Oil Transfer Pump / Dried Oil Pump
494 SJRM14520 Tender Call (send RFQ) 0% 1d 16-Feb-18 16-Feb-18 5 Working Day Tender Call (send RFQ)
495 SJRM14530 1st Proposal Submission 0% 7d 19-Feb-18 27-Feb-18 5 Working Day 1st Proposal Submission
496 SJRM14540 1st Technic al Bi d Evaluation 0% 7d 28-Feb-18 08-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
497 SJRM14550 1st Technic al Cl arific ation 0% 7d 09-Mar-18 19-Mar-18 5 Working Day 1st Technic al Cl arific ation
498 SJRM14560 2nd Proposal Submission 0% 2d 20-Mar-18 21-Mar-18 5 Working Day 2nd Proposal Submission
499 SJRM14570 Commercial Bid Evaluation 0% 5d 22-Mar-18 28-Mar-18 5 Working Day Commercial Bid Evaluation
500 SJRM14580 Negotiation 0% 2d 29-Mar-18 30-Mar-18 5 Working Day Negotiation
501 SJRM14590 QCF Approval 0% 7d 02-Apr-18 10-Apr-18 5 Working Day QCF Approval
502 SJRM14600 Issuing LoA 0% 1d 11-Apr-18 11-Apr-18 5 Working Day Issuing LoA
503 SJRM14610 Expediting 0% 150d 12-Apr-18 13-Oct-18 6 Working Day Expediting
504 SJRM14620 Receive 1st Tender Docum ent 0% 0d 05-May-18 6 Working Day Receive 1st Tender D ocum ent, 05-May-18
505 SJRM14630 Inspection (FAT) 0% 0d 10-Sep-18 6 Working Day Inspection (FAT),
506 SJRM14640 Trans port 0% 30d 15-Oct-18 17-Nov-18 6 Working Day Trans port
507 SJRM14650 ROS(Requested on Site) 0% 0d 17-Nov-18 6 Working Day ROS(Requested on Site),
508 Sludge Flow meter 0% 227d 16-Feb-18 17-Nov-18 17-Nov-18, Sludge Flow meter
509 SJRM14660 Tender Call (send RFQ) 0% 1d 16-Feb-18 16-Feb-18 5 Working Day Tender Call (send RFQ)
510 SJRM14670 1st Proposal Submission 0% 7d 19-Feb-18 27-Feb-18 5 Working Day 1st Proposal Submission
511 SJRM14680 1st Technic al Bi d Evaluation 0% 7d 28-Feb-18 08-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
512 SJRM14690 1st Technic al Cl arific ation 0% 7d 09-Mar-18 19-Mar-18 5 Working Day 1st Technic al Cl arific ation
513 SJRM14700 2nd Proposal Submission 0% 2d 20-Mar-18 21-Mar-18 5 Working Day 2nd Proposal Submission
514 SJRM14710 Commercial Bid Evaluation 0% 5d 22-Mar-18 28-Mar-18 5 Working Day Commercial Bid Evaluation
515 SJRM14720 Negotiation 0% 2d 29-Mar-18 30-Mar-18 5 Working Day Negotiation
516 SJRM14730 QCF Approval 0% 7d 02-Apr-18 10-Apr-18 5 Working Day QCF Approval
517 SJRM14740 Issuing LoA 0% 1d 11-Apr-18 11-Apr-18 5 Working Day Issuing LoA
518 SJRM14750 Expediting 0% 150d 12-Apr-18 13-Oct-18 6 Working Day Expediting
519 SJRM14760 Receive 1st Tender Docum ent 0% 0d 05-May-18 6 Working Day Receive 1st Tender D ocum ent, 05-May-18
520 SJRM14770 Inspection (FAT) 0% 0d 10-Sep-18 6 Working Day Inspection (FAT),
521 SJRM14780 Trans port 0% 30d 15-Oct-18 17-Nov-18 6 Working Day Trans port
522 SJRM14790 ROS(Requested on Site) 0% 0d 17-Nov-18 6 Working Day ROS(Requested on Site),
523 Ripple Mill 0% 227d 16-Feb-18 17-Nov-18 17-Nov-18, Ripple Mill
524 SJRM14800 Tender Call (send RFQ) 0% 1d 16-Feb-18 16-Feb-18 5 Working Day Tender Call (send RFQ)
525 SJRM14810 1st Proposal Submission 0% 7d 19-Feb-18 27-Feb-18 5 Working Day 1st Proposal Submission
526 SJRM14820 1st Technic al Bi d Evaluation 0% 7d 28-Feb-18 08-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
527 SJRM14830 1st Technic al Cl arific ation 0% 7d 09-Mar-18 19-Mar-18 5 Working Day 1st Technic al Cl arific ation
528 SJRM14840 2nd Proposal Submission 0% 2d 20-Mar-18 21-Mar-18 5 Working Day 2nd Proposal Submission
529 SJRM14850 Commercial Bid Evaluation 0% 5d 22-Mar-18 28-Mar-18 5 Working Day Commercial Bid Evaluation
530 SJRM14860 Negotiation 0% 2d 29-Mar-18 30-Mar-18 5 Working Day Negotiation
531 SJRM14870 QCF Approval 0% 7d 02-Apr-18 10-Apr-18 5 Working Day QCF Approval
532 SJRM14880 Issuing LoA 0% 1d 11-Apr-18 11-Apr-18 5 Working Day Issuing LoA
533 SJRM14890 Expediting 0% 150d 12-Apr-18 13-Oct-18 6 Working Day Expediting
534 SJRM14900 Receive 1st Tender Docum ent 0% 0d 05-May-18 6 Working Day Receive 1st Tender D ocum ent, 05-May-18
535 SJRM14910 Inspection (FAT) 0% 0d 10-Sep-18 6 Working Day Inspection (FAT),
536 SJRM14920 Trans port 0% 30d 15-Oct-18 17-Nov-18 6 Working Day Trans port
537 SJRM14930 ROS(Requested on Site) 0% 0d 17-Nov-18 6 Working Day ROS(Requested on Site),
538 Claybath Vibrating Screen 0% 227d 16-Feb-18 17-Nov-18 17-Nov-18, Claybath Vibrating Screen
539 SJRM14940 Tender Call (send RFQ) 0% 1d 16-Feb-18 16-Feb-18 5 Working Day Tender Call (send RFQ)
540 SJRM14950 1st Proposal Submission 0% 7d 19-Feb-18 27-Feb-18 5 Working Day 1st Proposal Submission
541 SJRM14960 1st Technic al Bi d Evaluation 0% 7d 28-Feb-18 08-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
542 SJRM14970 1st Technic al Cl arific ation 0% 7d 09-Mar-18 19-Mar-18 5 Working Day 1st Technic al Cl arific ation

Project ID : 16STP2019 Actual Level of Effort Critical Remaining Work TASK filter: All Activities
Revison .0, 08-Dec-17 Actual Work Milestone © Oracle Corporation
Status      : 1st Issued
Remaining Work summary
 
SEJIRAM MILL 80 TPH PROJECT
  08-Dec-17 17:37

# Activity ID Activity Name Dur % OD Start Finish Calendar 2017 2018 2019 2020
Complete Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
543 SJRM14980 2nd Proposal Submission 0% 2d 20-Mar-18 21-Mar-18 5 Working Day 2nd Proposal Submission
544 SJRM14990 Commercial Bid Evaluation 0% 5d 22-Mar-18 28-Mar-18 5 Working Day Commercial Bid Evaluation
545 SJRM15000 Negotiation 0% 2d 29-Mar-18 30-Mar-18 5 Working Day Negotiation
546 SJRM15010 QCF Approval 0% 7d 02-Apr-18 10-Apr-18 5 Working Day QCF Approval
547 SJRM15020 Issuing LoA 0% 1d 11-Apr-18 11-Apr-18 5 Working Day Issuing LoA
548 SJRM15030 Expediting 0% 150d 12-Apr-18 13-Oct-18 6 Working Day Expediting
549 SJRM15040 Receive 1st Tender Docum ent 0% 0d 05-May-18 6 Working Day Receive 1st Tender D ocum ent, 05-May-18
550 SJRM15050 Inspection (FAT) 0% 0d 10-Sep-18 6 Working Day Inspection (FAT),
551 SJRM15060 Trans port 0% 30d 15-Oct-18 17-Nov-18 6 Working Day Trans port
552 SJRM15070 ROS(Requested on Site) 0% 0d 17-Nov-18 6 Working Day ROS(Requested on Site),
553 Sludge Flow meter w/o recorder 0% 227d 16-Feb-18 17-Nov-18 17-Nov-18, Sludge Flow meter w/o recorder
554 SJRM15080 Tender Call (send RFQ) 0% 1d 16-Feb-18 16-Feb-18 5 Working Day Tender Call (send RFQ)
555 SJRM15090 1st Proposal Submission 0% 7d 19-Feb-18 27-Feb-18 5 Working Day 1st Proposal Submission
556 SJRM15100 1st Technic al Bi d Evaluation 0% 7d 28-Feb-18 08-Mar-18 5 Working Day 1st Technic al Bi d Evaluation
557 SJRM15110 1st Technic al Cl arific ation 0% 7d 09-Mar-18 19-Mar-18 5 Working Day 1st Technic al Cl arific ation
558 SJRM15120 2nd Proposal Submission 0% 2d 20-Mar-18 21-Mar-18 5 Working Day 2nd Proposal Submission
559 SJRM15130 Commercial Bid Evaluation 0% 5d 22-Mar-18 28-Mar-18 5 Working Day Commercial Bid Evaluation
560 SJRM15140 Negotiation 0% 2d 29-Mar-18 30-Mar-18 5 Working Day Negotiation
561 SJRM15150 QCF Approval 0% 7d 02-Apr-18 10-Apr-18 5 Working Day QCF Approval
562 SJRM15160 Issuing LoA 0% 1d 11-Apr-18 11-Apr-18 5 Working Day Issuing LoA
563 SJRM15170 Expediting 0% 150d 12-Apr-18 13-Oct-18 6 Working Day Expediting
564 SJRM15180 Receive 1st Tender Docum ent 0% 0d 05-May-18 6 Working Day Receive 1st Tender D ocum ent, 05-May-18
565 SJRM15190 Inspection (FAT) 0% 0d 10-Sep-18 6 Working Day Inspection (FAT),
566 SJRM15200 Trans port 0% 30d 15-Oct-18 17-Nov-18 6 Working Day Trans port
567 SJRM15210 ROS(Requested on Site) 0% 0d 17-Nov-18 6 Working Day ROS(Requested on Site),
568 Contractor Package 0% 137d 04-Dec-17 28-Jun-18 5 Working Day 28-Jun-18, Contractor Package
569 Cut & Fill Package 0% 49d 04-Dec-17 12-Feb-18 5 Working Day 12-Feb-18, Cut & Fill Package
570 SJRM15220 Tender Call for Contractors 0% 0d 04-Dec-17 5 Working Day Tender Call for Contractors,
571 SJRM15230 Project Briefing 0% 1d 07-Dec-17 07-Dec-17 5 Working Day Project Briefing
572 SJRM15240 1st Proposal Submission 0% 0d 22-Dec-17 5 Working Day 1st Proposal Submission,
573 SJRM15250 1st Technic al & Com merc ial Ev aluation 0% 5d 26-Dec-17 02-Jan-18 5 Working Day 1st Technic al & Com merc ial Ev aluation
574 SJRM15260 1st Clarification 0% 2d 03-Jan-18 04-Jan-18 5 Working Day 1st Clarification
575 SJRM15270 2nd Proposal Submission 0% 0d 12-Jan-18 5 Working Day 2nd Proposal Submission,
576 SJRM15280 2nd Technical & Com mer cial Evaluation 0% 5d 15-Jan-18 19-Jan-18 5 Working Day 2nd Technical & Com mer cial Evaluation
577 SJRM15290 Negotiation 0% 3d 24-Jan-18 26-Jan-18 5 Working Day Negotiation
578 SJRM15300 QCF Approval 0% 7d 01-Feb-18 09-Feb-18 5 Working Day QCF Approval
579 SJRM15310 Issuing LoA Contractor Package 0% 0d 12-Feb-18 5 Working Day Issuing LoA Contractor Package,
580 SJRM15320 Confirmation of Tenderers Parti cipati on 0% 2d 05-Dec-17 06-Dec-17 5 Working Day Confirmation of Tenderers Parti cipati on
581 SJRM15330 Site Visit 0% 2d 12-Dec-17 13-Dec-17 5 Working Day Site Visit
582 SJRM15340 1st BOQ Release to Bidder 0% 0d 15-Dec-17 5 Working Day 1st BOQ Release to Bidder,
583 SJRM15350 3rd Final Quotation Submission 0% 1d 29-Jan-18 29-Jan-18 5 Working Day 3rd Final Quotation Submission
584 SJRM15360 Unit Price Evaluation 0% 2d 30-Jan-18 31-Jan-18 5 Working Day Unit Price Evaluation
585 SJRM15370 2nd Clarification 0% 2d 22-Jan-18 23-Jan-18 5 Working Day 2nd Clarification
586 Pilling Package 0% 53d 21-Dec-17 08-Mar-18 5 Working Day 08-Mar-18, Pilling Package
587 SJRM15380 Tender Call for Contractors 0% 0d 21-Dec-17 5 Working Day Tender Call for Contractors,
588 SJRM15390 Project Briefing 0% 1d 27-Dec-17 27-Dec-17 5 Working Day Project Briefing
589 SJRM15400 1st Proposal Submission 0% 0d 12-Jan-18 5 Working Day 1st Proposal Submission,
590 SJRM15410 1st Technic al & Com merc ial Ev aluation 0% 10d 15-Jan-18 26-Jan-18 5 Working Day 1st Technic al & Com merc ial Ev aluation
591 SJRM15420 1st Clarification 0% 5d 29-Jan-18 02-Feb-18 5 Working Day 1st Clarification
592 SJRM15430 2nd Proposal Submission 0% 0d 09-Feb-18 5 Working Day 2nd Proposal Submission,
593 SJRM15440 2nd Technical & Com mer cial Evaluation 0% 3d 12-Feb-18 14-Feb-18 5 Working Day 2nd Technical & Com mer cial Evaluation
594 SJRM15450 Negotiation 0% 3d 19-Feb-18 21-Feb-18 5 Working Day Negotiation
595 SJRM15460 QCF Approval 0% 7d 27-Feb-18 07-Mar-18 5 Working Day QCF Approval
596 SJRM15470 Issuing LoA Contractor Package 0% 0d 08-Mar-18 5 Working Day Issuing LoA Contractor Package,
597 SJRM15480 Confirmation of Tenderers Parti cipati on 0% 1d 22-Dec-17 22-Dec-17 5 Working Day Confirmation of Tenderers Parti cipati on
598 SJRM15490 Site Visit 0% 3d 03-Jan-18 05-Jan-18 5 Working Day Site Visit
599 SJRM15500 1st BOQ Release to Bidder 0% 0d 27-Dec-17 5 Working Day 1st BOQ Release to Bidder,
600 SJRM15510 3rd Final Quotation Submission 0% 1d 22-Feb-18 22-Feb-18 5 Working Day 3rd Final Quotation Submission
601 SJRM15520 Unit Price Evaluation 0% 2d 23-Feb-18 26-Feb-18 5 Working Day Unit Price Evaluation
602 SJRM15530 2nd Clarification 0% 2d 15-Feb-18 16-Feb-18 5 Working Day 2nd Clarification
603 CSA Package 0% 53d 07-Mar-18 21-May-18 5 Working Day 21-May-18, CSA Pack age
604 SJRM15540 Tender Call for Contractors 0% 0d 07-Mar-18 5 Working Day Tender Call for Contractors,
605 SJRM15550 Project Briefing 0% 1d 12-Mar-18 12-Mar-18 5 Working Day Project Briefing
606 SJRM15560 1st Proposal Submission 0% 0d 27-Mar-18 5 Working Day 1st Proposal Submission,
607 SJRM15570 1st Technic al & Com merc ial Ev aluation 0% 10d 28-Mar-18 10-Apr-18 5 Working Day 1st Technic al & Com merc ial Ev aluation
608 SJRM15580 1st Clarification 0% 5d 11-Apr-18 17-Apr-18 5 Working Day 1st Clarification
609 SJRM15590 2nd Proposal Submission 0% 0d 24-Apr-18 5 Working Day 2nd Proposal Submission,
610 SJRM15600 2nd Technical & Com mer cial Evaluation 0% 3d 25-Apr-18 27-Apr-18 5 Working Day 2nd Technical & Com mer cial Evaluation
611 SJRM15610 Negotiation 0% 3d 02-May-18 04-May-18 5 Working Day Negotiation
612 SJRM15620 QCF Approval 0% 7d 10-May-18 18-May-18 5 Working Day QCF Approval
613 SJRM15630 Issuing LoA Contractor Package 0% 0d 21-May-18 5 Working Day Issuing LoA Contractor Package,
614 SJRM15640 Confirmation of Tenderers Parti cipati on 0% 1d 08-Mar-18 08-Mar-18 5 Working Day Confirmation of Tenderers Parti cipati on
615 SJRM15650 Site Visit 0% 3d 16-Mar-18 20-Mar-18 5 Working Day Site Visit
616 SJRM15660 1st BOQ Release to Bidder 0% 0d 12-Mar-18 5 Working Day 1st BOQ Release to Bidder,
617 SJRM15670 3rd Final Quotation Submission 0% 1d 07-May-18 07-May-18 5 Working Day 3rd Final Quotation Submission
618 SJRM15680 Unit Price Evaluation 0% 2d 08-May-18 09-May-18 5 Working Day Unit Price Evaluation
619 SJRM15690 2nd Clarification 0% 2d 30-Apr-18 01-May-18 5 Working Day 2nd Clarification

Project ID : 16STP2019 Actual Level of Effort Critical Remaining Work TASK filter: All Activities
Revison .0, 08-Dec-17 Actual Work Milestone © Oracle Corporation
Status      : 1st Issued
Remaining Work summary
 
SEJIRAM MILL 80 TPH PROJECT
  08-Dec-17 17:37

# Activity ID Activity Name Dur % OD Start Finish Calendar 2017 2018 2019 2020
Complete Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
620 MEP Package 0% 54d 30-Mar-18 28-Jun-18 5 Working Day 28-Jun-18, MEP Package
621 SJRM15700 Tender Call for Contractors 0% 0d 30-Mar-18 5 Working Day Tender Call for Contractors,
622 SJRM15710 Project Briefing 0% 1d 04-Apr-18 04-Apr-18 5 Working Day Project Briefing
623 SJRM15720 1st Proposal Submission 0% 0d 19-Apr-18 5 Working Day 1st Proposal Submission,
624 SJRM15730 1st Technic al & Com merc ial Ev aluation 0% 10d 23-Apr-18 04-May-18 5 Working Day 1st Technic al & Com merc ial Ev aluation
625 SJRM15740 1st Clarification 0% 5d 07-May-18 11-May-18 5 Working Day 1st Clarification
626 SJRM15750 2nd Proposal Submission 0% 0d 18-May-18 5 Working Day 2nd Proposal Submission,
627 SJRM15760 2nd Technical & Com mer cial Evaluation 0% 3d 21-May-18 23-May-18 5 Working Day 2nd Technical & Com mer cial Evaluation
628 SJRM15770 Negotiation 0% 3d 28-May-18 30-May-18 5 Working Day Negotiation
629 SJRM15780 QCF Approval 0% 7d 05-Jun-18 27-Jun-18 5 Working Day QCF Approval
630 SJRM15790 Issuing LoA Contractor Package 0% 0d 28-Jun-18 5 Working Day Issuing LoA Contractor Package,
631 SJRM15800 Confirmation of Tenderers Parti cipati on 0% 1d 02-Apr-18 02-Apr-18 5 Working Day Confirmation of Tenderers Parti cipati on
632 SJRM15810 Site Visit 0% 3d 10-Apr-18 12-Apr-18 5 Working Day Site Visit
633 SJRM15820 1st BOQ Release to Bidder 0% 0d 04-Apr-18 5 Working Day 1st BOQ Release to Bidder,
634 SJRM15830 3rd Final Quotation Submission 0% 1d 31-May-18 31-May-18 5 Working Day 3rd Final Quotation Submission
635 SJRM15840 Unit Price Evaluation 0% 2d 01-Jun-18 04-Jun-18 5 Working Day Unit Price Evaluation
636 SJRM15850 2nd Clarification 0% 2d 24-May-18 25-May-18 5 Working Day 2nd Clarification
637 Review 0% 259d 09-Jan-17 08-Jan-18 5 Working Day 08-Jan-18, Review
638 Construction 0% 468d 04-Jan-18 29-Jul-19 29-Jul-19, Construction
639 Cut & Fill 0% 280d 04-Jan-18 19-Oct-18 7 Working Day 19-Oct-18, Cut & Fill
640 SJRM15910 Mill Footprint 0% 90d 22-Jan-18 21-Apr-18 7 Working Day Mill Footprint
641 SJRM15920 Effluent Pond #1 0% 30d 21-Feb-18 22-Mar-18 7 Working Day Effluent Pond #1
642 SJRM15930 Effluent Pond #2 0% 30d 23-Mar-18 21-Apr-18 7 Working Day Effluent Pond #2
643 SJRM15940 Effluent Pond #3 0% 30d 22-Apr-18 21-May-18 7 Working Day Effluent Pond #3
644 SJRM15950 Reservoir 0% 52d 29-Aug-18 19-Oct-18 7 Working Day Reservoir
645 SJRM15960 Mobilization & Marking 0% 60d 04-Jan-18 04-Mar-18 7 Working Day Mobilization & Marking
646 SJRM15970 Road (Subbase) & Drainage (temporary) 0% 60d 23-Mar-18 21-May-18 7 Working Day Road (Subbase) & Drainage (temporary)
647 SJRM15980 Effluent Pond #4 0% 30d 22-May-18 29-Jun-18 7 Working Day Effluent Pond #4
648 SJRM15990 Effluent Pond #5 0% 30d 30-Jun-18 29-Jul-18 7 Working Day Effluent Pond #5
649 SJRM16000 Effluent Pond #6 0% 30d 30-Jul-18 28-Aug-18 7 Working Day Effluent Pond #6
650 Pilling Works 0% 122d 16-Mar-18 24-Jul-18 7 Working Day 24-Jul-18, Pilling Works
651 SJRM16010 Main Production Building 0% 25d 12-May-18 05-Jun-18 7 Working Day Main Production Building
652 SJRM16020 CPO Storage Tanks 0% 30d 06-Jun-18 14-Jul-18 7 Working Day CPO Storage Tanks
653 SJRM16030 Weighbridge & Loading Ramp 0% 10d 15-Jul-18 24-Jul-18 7 Working Day Weighbridge & Loading Ramp
654 SJRM16040 Fabrication 0% 35d 16-Mar-18 19-Apr-18 7 Working Day Fabrication
655 SJRM16050 Delivery 0% 14d 20-Apr-18 03-May-18 7 Working Day Delivery
656 Mill & Facilities 0% 375d 22-Apr-18 29-Jul-19 29-Jul-19, Mill & Facilities
657 Preliminary Works 0% 209d 28-May-18 03-Jan-19 7 Working Day 03-Jan-19, Preliminary Works
658 CSA Package Works 0% 180d 28-May-18 03-Dec-18 7 Working Day 03-Dec-18, CSA Pack age Works
659 SJRM16060 Kick Off Meeting with CSA Contractor 0% 0d 28-May-18 7 Working Day Kick Off Meeting with CSA Contractor,
660 SJRM16070 Mobilization 0% 90d 29-May-18 04-Sep-18 7 Working Day Mobilization
661 SJRM16080 Temporary Facility 0% 30d 07-Jul-18 05-Aug-18 7 Working Day Temporary Facility
662 Fabrication 0% 150d 07-Jul-18 03-Dec-18 7 Working Day 03-Dec-18, Fabrication
663 MEP Package Works 0% 180d 06-Jul-18 03-Jan-19 7 Working Day 03-Jan-19, MEP Package Work s
664 SJRM16110 Kick Off Meeting with MEP Contractor 0% 0d 06-Jul-18 7 Working Day Kick Off Meeting with MEP Contractor, 06-Jul-18
665 SJRM16120 Mobilization 0% 90d 06-Jul-18 03-Oct-18 7 Working Day Mobilization
666 SJRM16130 Temporary Facility 0% 30d 05-Aug-18 03-Sep-18 7 Working Day Temporary Facility
667 Fabrication 0% 180d 06-Jul-18 03-Jan-19 7 Working Day 03-Jan-19, Fabrication
668 CPO Storage Tanks 0% 329d 05-Jul-18 08-Jun-19 7 Working Day 08-Jun-19, CPO Storage Tanks
669 CSA Works 0% 61d 05-Jul-18 03-Sep-18 7 Working Day 03-Sep-18, CSA Works
670 CPO Storage-1 0% 40d 05-Jul-18 13-Aug-18 7 Working Day 13-Aug-18, CPO Storage-1
671 CPO Storage-2 0% 44d 15-Jul-18 27-Aug-18 7 Working Day 27-Aug-18, CPO Storage-2
672 Oil Loading Shed & Dispatch Pump House 0% 23d 12-Aug-18 03-Sep-18 7 Working Day 03-Sep-18, Oil Loading Shed & Dispatch Pump House
673 MEP Works 0% 208d 03-Nov-18 08-Jun-19 7 Working Day 08-Jun-19, MEP Wor ks
674 CPO Storage -1 0% 118d 03-Nov-18 02-Mar-19 7 Working Day 02-Mar-19, CPO Storage -1
675 CPO Storage -2 0% 118d 03-Feb-19 08-Jun-19 7 Working Day 08-Jun-19, CPO Storage -2
676 Loading Ramp 0% 233d 25-Jul-18 16-Mar-19 7 Working Day 16-Mar-19, Loading Ramp
677 Main Production Building 0% 306d 22-Jul-18 29-Jul-19 29-Jul-19, Main Production Building
678 Main Building 0% 212d 22-Jul-18 20-Feb-19 7 Working Day 20-Feb-19, Main Building
679 Pressing Station 0% 157d 06-Jan-19 22-Jun-19 7 Working Day 22-Jun-19, Pressing Station
680 Clarification Station 0% 194d 06-Jan-19 29-Jul-19 7 Working Day 29-Jul-19, Clarification Station
681 Tippler Station 0% 109d 06-Jan-19 24-Apr-19 7 Working Day 24-Apr-19, Tippler Station
682 Transfer Carriage St ation 0% 80d 19-Feb-19 09-May-19 7 Working Day 09-May-19, Transfer Carriage Station
683 Sterilization Station 0% 79d 19-Feb-19 08-May-19 7 Working Day 08-May-19, Sterilization Station
684 Threshing Station 0% 122d 10-Feb-19 22-Jun-19 7 Working Day 22-Jun-19, Threshing Station
685 Nut & Kernel Station including KSB 0% 110d 10-Mar-19 08-Jul-19 7 Working Day 08-Jul-19, Nut & Kernel Station including KSB
686 Boiler Station 0% 120d 03-Feb-19 05-Jul-19 05-Jul-19, Boiler Station
687 Power House 0% 59d 28-Mar-19 25-May-19 7 Working Day 25-May-19, Power House
688 Water Treatment Plant 0% 71d 26-Mar-19 15-Jun-19 7 Working Day 15-Jun-19, Water Treatment Plant
689 Boiler Wat er Treatment Plant 0% 51d 16-Apr-19 16-Jun-19 7 Working Day 16-Jun-19, Boiler Water Treatment Plant
690 Empty Bunch Station 0% 106d 12-Mar-19 06-Jul-19 7 Working Day 06-Jul-19, Empty Bunch Station
691 Office, Laboratory & Control Room 0% 148d 06-Jan-19 13-Jun-19 7 Working Day 13-Jun-19, Office, Laboratory & Control Room
692 Workshop & Warehouse 0% 57d 08-Mar-19 04-May-19 7 Working Day 04-May-19, Workshop & Warehouse
693 Weightbridge 0% 38d 08-Mar-19 14-Apr-19 7 Working Day 14-Apr-19, Weightbridge
694 Ancillary Building 0% 159d 06-Jan-19 24-Jun-19 7 Working Day 24-Jun-19, Anci llary Buildi ng
695 Infrastructure 0% 389d 22-Apr-18 26-May-19 7 Working Day 26-May-19, Infrastructure
696 Commissioning 0% 170d 02-Jul-19 18-Dec-19 7 Working Day 18-Dec-19, Commissioning
697 Early Construction Phase (preparation & Pre-commissioning) 0% 60d 02-Jul-19 30-Aug-19 7 Working Day 30-Aug-19, Early Construction Phase (preparation & Pre-commissioning)
698 SJRM19780 Installation Validation & Check List 0% 30d 02-Jul-19 31-Jul-19 7 Working Day Installation Validation & Check List
699 SJRM19790 Initial Plan for Functional Testing 0% 20d 02-Jul-19 21-Jul-19 7 Working Day Initial Plan for Functional Testing
700 SJRM19795 Mechanical Completion 0% 0d 31-Jul-19 7 Working Day Mechanical Completion,

Project ID : 16STP2019 Actual Level of Effort Critical Remaining Work TASK filter: All Activities
Revison .0, 08-Dec-17 Actual Work Milestone © Oracle Corporation
Status      : 1st Issued
Remaining Work summary
 
SEJIRAM MILL 80 TPH PROJECT
  08-Dec-17 17:37

# Activity ID Activity Name Dur % OD Start Finish Calendar 2017 2018 2019 2020
Complete Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
701 SJRM19800 Functional Testi ng 0% 30d 01-Aug-19 30-Aug-19 7 Working Day Functional Testi ng
702 Later Construction Phase (actual commissioning) 0% 60d 31-Aug-19 29-Oct-19 7 Working Day 29-Oct-19, Later Construction Phase (actual commissioning)
703 SJRM19820 Functional Performance Test 0% 60d 31-Aug-19 29-Oct-19 7 Working Day Functional Performance Test
704 Turn Over Phase (post commissioning) 0% 50d 30-Oct-19 18-Dec-19 7 Working Day 18-Dec-19, Turn Over Phase (post commissioning)
705 SJRM19830 Systems Manuals 0% 10d 30-Oct-19 08-Nov-19 7 Working Day Systems Manuals
706 SJRM19840 Trainning Sessi ons & Reports 0% 5d 09-Nov-19 13-Nov-19 7 Working Day Trainning Sessi ons & Reports
707 SJRM19850 Issue Log Completion 0% 5d 14-Nov-19 18-Nov-19 7 Working Day Issue Log Completion
708 SJRM19860 Commissioning Process Summary Report 0% 10d 19-Nov-19 28-Nov-19 7 Working Day Commissioning Process Summary Report
709 SJRM19870 Final Commissioning Report 0% 5d 29-Nov-19 03-Dec-19 7 Working Day Final Commissioning Report
710 SJRM19880 Lessons Learned Workshop & Report 0% 10d 04-Dec-19 13-Dec-19 7 Working Day Lessons Learned Workshop & Report
711 SJRM19890 Commsissioning Documents Control 0% 5d 14-Dec-19 18-Dec-19 7 Working Day Commsissioning Documents Control
712 PROJECT CLOSING PHASE 0% 26d 04-Dec-19 09-Jan-20 5 Working Day 09-Jan-20, PROJECT CLOSING PHASE
713 SJRM19900 Close Outstanding Punch List items 0% 10d 04-Dec-19 17-Dec-19 5 Working Day Close Outstanding Punch List items
714 SJRM19910 Quality Project Close Out Report 0% 10d 18-Dec-19 01-Jan-20 5 Working Day Quality Project Close Out Report
715 SJRM19920 Lessons Learned Workshop & Report 0% 5d 02-Jan-20 08-Jan-20 5 Working Day Lessons Learned Workshop & Report
716 SJRM19930 Hand over all documents, (as built) drawings, operating manuals,0%
spare part1d
list etc 09-Jan-20
to operations.09-Jan-20 5 Working Day Hand over all documents, (as built) drawings, operati
717 SJRM19940 Approval of the Project Close Out Report 0% 0d 09-Jan-20 5 Working Day Approval of the Project Close Out Report,

Project ID : 16STP2019 Actual Level of Effort Critical Remaining Work TASK filter: All Activities
Revison .0, 08-Dec-17 Actual Work Milestone © Oracle Corporation
Status      : 1st Issued
Remaining Work summary
 