You are on page 1of 1

16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1

L
Existing CDSP Structure with rail L

K
Sheet Pilling K

Pile cap casted


J J

Pile cap yet Load test for


not casted compression
load 84.1
I
tons is I

Cutting in slope
pending

H
Pile caps H

Sheet Pilling
casted Digitally signed by Neeraj
Dwivedi
APPROVED DN: cn=Neeraj Dwivedi,
A Releasedistributionprints.

o=STEAG Energy Services India
 Pvt. Ltd., ou,
G  email=nk.dwivedi@steag.in, c=IN G
Date: 2017.10.27 17:16:06
+05'30'

Sheet Pilling ETG043-DUCON-5-C-17-282

F F

E E

D D

OWNER

OWNER'S ENGINEER
C
C
STEAG ENERGY SERVICES (INDIA) PVT. LTD.
TR-2

PROJECT
MATERIAL HANDLING SYSTEM FOR 80 TPH PET-COKE
FIRED CFBC BOILER AT GUWAHATI REFINERY
CONSULTANT
B DUCON TECHNOLOGIES (I) PVT. LTD.
B

A A

16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
Size A1