You are on page 1of 12

JULY 2011

JCT NEWS
THE JCT CONTRACTS UPDATE FOR THE CONSTRUCTION PROFESSIONAL

WORLD HERITAGE SITE UNDERGOES


WORK USING A JCT CONTRACT
A JCT Constructing Excellence (CE) contract HRP chose the CE contract as it was in
has been used by the Historic Royal Palaces accordance with its partnering approach to
(HRP) for the first phase of conservation procurement – the contract is specifically
works at the Devereux Tower at the Tower designed to promote partnership working and
of London. The works were completed has been used by HRP on other projects. It
by the Chichester stone and conservation enabled HRP to engage CWO as part of the
specialists, Cathedral Works Organisation design team, allowing it to receive input from
(CWO) in collaboration with architects Carden CWO from the outset, and gain the benefit
& Godfrey, English Heritage and Oxford of preliminary works, obtaining samples and
Archaeology. The works are part of a four- enabling works being carried out before the
year programme to conserve the inner curtain contract for the conservation works were
wall on the Devereux Tower. finalised.
The Devereux Tower project involved
assessing the current level of deterioration
of the stone, to slow the rate of decay and
to preserve the fabric of the building using
traditional materials and methods with as
little intervention as possible. It also included
preparing the wall walk ready for visitors.
The project was particularly complicated as
it involved a building subjected to numerous
alterations over its 800 year history, all of
Tower of London which were of historic interest and had to be
Tower of London
preserved where possible. The tower was
originally only two storeys high (it is now three)
The tower was built between 1238 and Peter Hibberd, JCT chairman, said: “It is
and the roof was used as a gun platform.
1272 by King Henry III. It was named after pleasing to see that as JCT celebrates
Robert Devereux, the Earl of Essex, who Works, which required Scheduled Ancient its 80th birthday, as the country’s oldest
was imprisoned in the tower prior to being Monument Consent from English Heritage, established contract drafting body, one
executed for treason by Elizabeth I in 1601 were completed in eight months, with the of JCT’s newest forms of contract has
following his attempted uprising. cladding and scaffolding being removed late been used on one of the country’s oldest
last year. buildings.”

3 6 8 10 11 12
The Architecture of Ode to the JCT Working North of Can insurance ever Education and JCT News Flash
Austerity Measured Term the Border – Key catch up? Training Initiative
Contract Differences between Bill Gloyn - Partner, announced, as JCT
Richard Saxon CBE JCT and SBCC
Patricia Nathan- Jardine Lloyd Thompson celebrates landmark
Amissah - Charles Contracts European Real Estate; 80th Anniversary
Russell LLP Shona Frame - Immediate Past-President,
MacRoberts City Property Association

SWEET & MAXWELL


JCT NEWS
2 EDUCATION AND TRAINING NOT
EDUCATION VERSUS TRAINING
At JCT’s 80th birthday celebrations held at the RIBA The UK has some excellent ‘sandwich degrees’ and
in April I had the privilege to announce the JCT’s other forms of placement within construction courses
education and training initiative. This initiative is timely but their existence is always severely threatened when
because it comes at a time when the country and industry stops growing or faces higher than average
the construction industry in particular are faced with levels of risk. So rather than see growth in ways of
significant challenges. Education and training is and bridging the gap we tend to see a decline. Somehow
always has been recognised as the most important we need to further encourage and facilitate the
of issues. We are all aware of the saying ‘education, conversion of knowledge acquired through academic
education, education’ but does the way it is delivered study into a skill that can be used in the workplace –
meet the needs of individuals and the communities in learning by doing being the most obvious. Part time
Peter Hibberd
which they live? courses were a traditional approach and many still offer

Chairman’s
the potential for bridging the gap between knowledge
In 2006 Don McKinnon at the World Teachers’ Day
accumulation and its application. However, it should
Conference said education is the key to everything
Letter and is the key to billions of human beings fulfilling
their unique potential. One would not disagree with
neither be left entirely to academia nor entirely to
business to ensure the conversion takes place; it must
be a joint effort and despite the extent of dialogue that
that but one can always question the form and nature
exists in some areas this must not only be extended but
of education. Education has to do more than fulfil a
more importantly acted upon.
human’s potential, it must also ultimately provide a
benefit to the community through the workplace: no In order to train for the workplace one must be clear
one is an island. This point touches on the education what you want people to accomplish and JCT is making
versus training debate – where education is acquiring the case that wherever you might be placed in the
knowledge, whereas training is acquiring skills by the supply chain a working understanding of construction
application of that knowledge. JCT throughout its long contracts is an essential component in the efficient
existence has always been about education, not just running of a project. JCT’s initiative therefore is,
education but also training and it wants to do more by amongst other things, aimed at not only encouraging
emphasising training throughout the supply chain and the accumulation of knowledge of construction
by further reducing the learning curve. procurement and of construction contracts but
importantly the application of that knowledge through
I have heard it said that today’s younger generation
training.
of employees want to be trained, not educated and I
have also heard it said that many employers are less We believe that this will not only lead to a more efficient
than satisfied with the ability of graduates to perform construction industry but will also stimulate wider
in the workplace. If these are valid observations then interest in the industry and what it has to offer both
it says something about the relationship of universities individuals and the communities in which they live.
and colleges with the workplace or indeed our
Peter Hibberd
understanding of what that should be. Survey data
Chairman of JCT
published by the Centre for Higher Education Research
and Information at The Open University in 2009 indicate
that the UK has one of the lowest rates of participation
in work placements in Europe, at around 30 per cent
as compared with France where it was over 80%. This,
to some extent, may help explain why some employers
hold the view that many people lack the appropriate
skills to operate within the workplace.

SWEET & MAXWELL


3 THE ARCHITECTURE OF AUSTERITY
RICHARD SAXON CBE

Architecture had a bull run in the UK from 1993 to 2008.


The profession had a sharply rising workload, eventually
drawing in thousands of professionals from overseas to
meet the demand. The quality and reputation of British
architecture boomed also, raising public awareness
through the media and the RIBA Stirling Prize and
winning work all over the world. CABE was formed to
promote better architecture. Architecture was named by
the government as a leading part of the newly identified
Creative Industries and architects earned £3 billion in
annual fees out of £14b for the whole construction
professional service sector in the 2007 survey by the
Construction Industry Council.
However, the cost of building rose inexorably faster than
RPI throughout the period, stretching affordability and
making substitutes like information technology more
attractive. Reports on the reform of the industry from
Latham (1994) through Egan (1998) to Morrell (2010) all
attacked its cost and wastefulness. Both Latham and
Egan thought that a 30% reduction in cost was possible
from improved process alone. Whilst some leading
clients did make big savings, the mainstream showed
little effect from those reports and the industry struggles Richard Saxon CBE
with ever-rising materials costs and regulatory burdens.
The latest load is that of reaching low carbon-dioxide
emission targets. Estimates of the cost of getting to To a profession where LC used to be shorthand for
zero-carbon (whatever that turns out to mean) vary up radical modernist Le Corbusier, it must now mean Low
to an extra 30% over the regulations of 2000. Carbon and Low Cost.

The coalition government has recently been blaming So how can we avoid an era of banality and cramped
architects for this situation. The education minister shoddiness in what little building gets done? Are there
castigates architects for extravagant design in BSF ways to reduce cost whilst increasing value and keeping
schools and a free-school champion says that relevant quality?
architects add no value and should be avoided. And
The conventional response to tight budgets has
there have been some very expensive examples as
always been to favour refurbishment over new build,
well as some great outcomes. Even the government’s
to lower the quality of specification and to minimise
Chief Construction Advisor says that we should be
the size of the building. Refurbishment scores well
softening the message that ‘good design’ is vital.
on the low carbon agenda, saving embodied carbon,
‘Good-enough design’ is all we need and can afford,
waste and cost, but the result may underperform.
says former CABE Commissioner Paul Morrell. He also
Lower specification can push up whole-life costs or
calls for a cut in construction costs sufficient to make
it can be a worthwhile simplification. Smaller area
low-carbon buildings cost no more than conventional
can be reasonable with new ways of working, or it
buildings. Thus the link has been made in the public
can be a false economy. The iron triangle, Area times
mind between expressive architecture and avoidable
Specification equals Cost, rules some cost consultants’
cost. ‘Good design’ in the sense that the now-gutted
minds. The Latham/Egan reformers saw however that
CABE has promoted becomes a ‘nice-to-have’ option.
the way we work adds major cost. We have some of the
Austerity architecture is what is wanted.
JCT NEWS
4 • Using Building Information Modelling (BIM) to
reduce risk. BIM is a multi-dimensional CAD model
of the project which all participants share and
which reduces errors enormously by coordinating
designers and rehearsing construction. It can save
more than the cost of design on a job and goes on
helping the owner run the building over its life. It’s a
basic part of IPD.
• Reducing over-specification. We use belt and braces
in the UK, especially for M&E design. Over-regulation
needs to be reviewed as well.
• Using a smaller range of standard products and never
specials. Europe has ten times the range of products
available compared to the USA and many have small
orders but raise whole industry costs. Standard
Fig 1: Opening Space between Value, Price and Cost.
Prof. Hennes de Ridder assemblies and even building elements, like school
toilets and hotel bathrooms, can reduce cost.
most expensive buildings in Europe whilst paying low • Building Offsite. Design for manufacture cuts waste,
wages and salaries to participants. UK productivity and time and risk. Elements can be manufactured directly
profitability in construction is low and many clients pay a from BIM data. Higher air-tightness and insulation is
high price for low risk. Why is our lowest-tender system achievable and the building can start earning sooner.
producing such high prices?
New ways to raise value:
The way ahead surely lies in both taking cost out of
Better client leadership. Most public and many private
the process and creating more value in the product.
clients are inexperienced and risk-averse. Bringing
Professor de Ridder’s graph (Fig 1) suggests a utopia
suitable client advisers on board at the earliest stage
where buyers see value well above the price they pay
reaps rewards by defining the project well and buying
and suppliers keep costs well below price. Both do well.
design and construction intelligently. The RIBA now has
The Toyota system called Lean Thinking suggests that
a cohort of accredited Client Advisers to offer, bringing
concentrating on what customers really value allows
strategic thinking to bear so that the right product is
cost to be taken out, making both margins grow. This
asked for and the right process used.
has to be our roadmap, raking out wasted effort whilst
increasing client satisfaction. • Defining whole-life best value: A building costs more
to run over 20 years than it costs to build. And it
New ways to cut costs include:
houses activity worth many times more. A good
• Using design-build teamwork to reach low-cost value-seeking process optimises the outcomes for
solutions; not ‘here’s my design, what’s your price?’ the owner and occupier, sets acceptable operating
but ‘here’s our goal, what’s your idea to get there?’ cost and then the capital budget to achieve those
Teams formed early and incentivised to collaborate goals.
and to beat a reasonable benchmark showed in the
• Spending more up front to spend less on building.
Building-Down-Barriers (BDB) experiment in 1996-9
Ships, cars and aeroplanes all have more elaborate
that they could cut whole-life costs and get well paid
design stages than they used to do in order to have
for it. The American Integrated Project Delivery (IPD)
lower build and operating costs. Only construction
concept is prospering now, with client-led teams
tries to save on preparation as an aim in itself,
delivering more for less.
condemning it to repeat old errors. A thorough
briefmaking and design process, with BIM and
constructor involvement, redistributes cost but can
cut it overall. As a current US slogan has it: “Pre-
work, not Re-work”.

SWEET & MAXWELL


5

Fig 2: Nurture Future School: a low-carbon, low-cost system by Tarmac and Cartwright Pickard Architects

• Commission well and operate to learn. Buildings The initial strategy-making for a project can cost less
don’t work as well as designers and constructors than 1% of construction cost or 1/3000 of the value
expect, and they don’t know why because they delivered in the building over 20 years. The chance to
are off the scene. A leap in customer satisfaction leverage high performance is large. We need cost-
and supplier understanding follows if you use effective buildings, not just cheap ones.
‘Soft Landings’, the commissioning and feedback
Perhaps UK architects’ iconic buildings will
convention developed by consultants and
increasingly be in the Gulf and in Asia. Let’s focus here
Cambridge University and now available from BSRIA.
in the UK on understated value.
For low-carbon building it’s an essential step.

Austerity architecture could turn out to be elegant


and long-lasting. No one will thank us for dropping Richard Saxon CBE is an accredited RIBA Client
unsympathetic standard schools onto sites as if they Adviser at www.saxoncbe.com. Formerly chairman
were McDonalds. But we don’t need to go there (see of BDP and of Be, Collaborating for the Built
Fig 2). Low cost, low carbon architecture could be Environment, president of the BCO and vice-
high whole-life value through excellence in the process, president of the RIBA. He was also inaugural Povey
choice of simple strategies over complex ones, flexible Lecturer for the JCT.
space working hard and a building made of standard
components and recycled elements of the former
building on the site. The last thing we should do is cut
down on the thinking.
JCT NEWS
6 ODE TO THE JCT MEASURED TERM CONTRACT
PATRICIA NATHAN-AMISSAH - CHARLES RUSSELL LLP

Maintenance contracts differ from other forms of more commonly used main forms of JCT contract.
procurement. The contract length can often be for As its title suggests, the JCT MTC is designed for use
periods of between 3 to 5 years which, in these where there is “a regular flow of maintenance and
difficult times, can offer contractors much needed minor works, including improvements, to be carried
continuity of work and income. The form of contract out by a single contractor over a specified period
needs to cater for the ebbs and flows of work type, under a single contract”. Consequently other forms
volume and pricing. Choosing the appropriate may be better suited if the volume of work is not large
JCT contract for maintenance work needs careful enough or where the work can be fully designed and
consideration and often choices can be fettered by completed in less than a year.
the comfort regular users of JCT contracts may have
Patricia Nathan-Amissah The JCT MTC consists of over 40 pages of printed
with traditional lump sum contracts.
conditions, many of which would be familiar to users
Generally, Measured Term Contracts or Framework of other JCT contracts. The JCT MTC refers solely
Agreements are best suited for maintenance, to the Contract Administrator (as opposed to the
improvement and in some cases minor works. Architect). The Contract Administrator is usually a
surveyor engaged by the Employer and is intended
So how do Measured Term Contracts work? Usually
to be someone who is experienced and skilled in
a contractor undertakes to carry out a series of works
construction procurement. The Contract Administrator
orders placed over a period of years within a defined
is responsible for administering the terms of the
geographical area – the work is then measured and
contract in an impartial manner.
valued using rates in a pre-priced Schedule of Rates
or hourly rates which usually include a negotiated The latest JCT MTC Revision 2, as with other JCT
contract percentage, applied to the relevant work. contracts, includes provisions relating to
To encourage economies of scale one contractor • collaborative working
may be appointed, however as the administration
of Connaught PLC shows, there is a benefit to • health and safety
spreading the risk. To reduce the effect of contractor • cost savings and value improvements
insolvency two or more contractors may be appointed
to undertake the work required under a term • sustainable development and environmental
agreement. This also has the benefit of enabling direct considerations
comparisons to be made and facilitating benefit of • performance Indicators and monitoring, and
common supply chains.
• notification and negotiation of disputes.
Many major clients such as registered landlords, local
authorities, churches, universities, care homes and There are other amendments to the text but generally
other large property owners, often use inappropriate the contract remains unchanged from Revision 1.
bespoke contracts or the wrong form of JCT contract. The Articles, Recitals and Contract Particulars set
out the Contract Period (usually at least a year),
Forms of Measured Term Contracts
the Contract Area and the work types in respect
Contracts let on a term basis often use the JCT of which orders may be given. Unless otherwise
Measured Term Contract 2006 (JCT MTC), which was agreed between the Contractor and the Contract
first published in 1989 and is considered “tried and Administrator orders will be of a size consistent
tested”. The latest version of the JCT MTC is Revision with the minimum or maximum orders stated in the
2 2009. There are other forms of term contracts Contract Particulars, as long as they are reasonably
published by the NEC (NEC3 Term Service Contract capable of being carried out within the Contract
published in 2005) and the TPC 2005 ACA Standard Period. The Contract Particulars also include an
Form of Term Contract for Term Partnering – amended anticipated value of work but there is no guarantee of
2008. work nor are there any provisions in the standard form
for exclusivity.
JCT Measured Term Contract Revision 2
The JCT MTC is not written about or reported as often Not only does the contract include termination
as other JCT contracts and its use is dwarfed by the provisions it also contains break notice provisions

SWEET & MAXWELL


7

which allow either party to reduce the duration of the


Contract Period by giving the other party at least 13 weeks
notice (or such shorter period of notice set out in the
Contract Particulars). The notice may expire at any time
not less than 6 months after the date of commencement of
the Contract Period. Consequently the break mechanism
cannot be used to reduce the Contract Period to less than
6 months but the period of notice required can be specified
as less than 13 weeks. The guidance notes suggest that
such break clauses are rarely used in practice.
The contract is designed for use where the Employer does
not commit to minimum order levels or to any degree of
exclusive dealings so the level of orders may fall below
expectation or where there is an unexpected and material
change in market rates or prices.
The JCT MTC makes no provision for liquidated damages
as the implementation of such clauses in term contracts
gives rise to difficulties in terms of a genuine pre-estimate
of loss, either with reference to individual orders or orders
collectively. The contractor will be liable to pay unliquidated
damages for a material delay or disruption in carrying out
any order.

JCT Framework Agreement 2007


The JCT Framework Agreement, which is a two party
agreement between the Employer and the “Provider”, is
designed for use as an umbrella agreement for underlying
contracts such as the JCT Design and Build Contract and
the Minor Works Building Contracts. Individual tasks are
instructed as required, subject to the pre-agreed terms of
the underlying contract. The Framework Agreement aims
to encourage the parties to work with all those involved in
an open, co-operative and collaborative manner and “in a
spirit of mutual trust” to achieve the objectives set out in the
Framework Agreement.

Conclusion
The JCT MTC is a stand-alone contract appropriate for
use by Employers who have a regular flow of maintenance
and minor works, whereas the JCT Framework allows
Employers to call off discrete contracts, which may be quite
diverse in nature. Both forms of contract can be used to
foster the collaborative and long term relationships with
suppliers that are now recognised as best practice.
If you require any further information arising from
this article, please contact Patricia Nathan-Amissah
at Charles Russell LLP by email at patricia.nathan-
amissah@charlesrussell.co.uk or by telephone on 01483
252638.
JCT NEWS
WORKING NORTH OF THE BORDER –
8
KEY DIFFERENCES BETWEEN JCT AND
SBCC CONTRACTS
SHONA FRAME - MACROBERTS

The aim of the Scottish Building Contract Committee Contractor’s Council and Scottish Building
(SBCC) in its standard form contracts is to create as Federation. The Arbitrator nominating bodies are
much uniformity across the UK as possible, adopting the the Chairman or Vice Chairman of the board of the
JCT forms wherever possible. However, it remains the Scottish Building Contract Committee Limited and
case that because of the different legal system north of the Chairman or Vice Chairman of the Chartered
the border, there are certain key differences in approach. Institute of Arbitrators (Scottish Branch).
The SBCC standard forms have made the changes • Off site materials and goods – JCT clause 2.25
required to the JCT forms to bring them in line with provides that where a payment is made under the
Scots law and terminology but they do not change the contract of the value of the off-site materials, the
risk profile or make other substantive amendments. They materials will become the property of the client
follow the JCT colour coding, section headings and notwithstanding that delivery has not been made.
clause numbering and, as far as possible, follow the JCT This is not contained in the SBCC contract because
names and dates. in Scotland, under a building or engineering contract,
ownership of property can only pass when there
The SBCC forms are now published in one
is both an intention to transfer ownership and
amalgamated document so that it is no longer necessary
delivery. This can be achieved when the property is
(as was the case with the JCT 80 and 98 forms) to read
incorporated into the works. It may also be achieved
a separate Scottish supplement into the JCT form. The
when the materials are delivered to site and then
consolidated approach is one that users will find easier
paid for by the Employer by inclusion in an interim
to read.
certificate. However, where the contract can be
Key differences are: characterised as a contract of sale, it will be subject
to the Sale of Goods Act 1979 and ownership of the
• Arbitration – Like the JCT form, the default dispute property may pass, by agreement, on payment being
resolution method is Court as opposed to Arbitration. made rather than on delivery. The way this is dealt
Where arbitration applies, the applicable legislation is with is for the client to enter into a separate contract
the Arbitration (Scotland) Act 2010 which came into for the purchase of the materials from the contractor
force on 7 June 2010. The Arbitration Act 1996 does or sub-contractor so that the materials will no longer
not apply in Scotland. The Arbitration (Scotland) Act form part of their contract. This is provided for within
2010 is relatively brief, consisting of 37 sections, but SBCC clause 4.17. It is in quite different terms from
supplemented by 84 Rules contained in Schedule 1, the equivalent JCT clause and provides that the
the Scottish Arbitration Rules. It can apply equally to Employer may enter into a separate contract for the
domestic, inter-UK or international arbitrations. The purchase of materials or goods prior to their delivery
Scottish Arbitration Rules are stated to govern every to site. If such a contract is entered into, the purchase
arbitration seated in Scotland. Some of the Rules of the materials or goods is excluded altogether from
are mandatory meaning they cannot be modified or the building contract.
disapplied and some are non-mandatory (referred to
as the “default rules”). The default rules apply unless • Trust – A trust cannot be effectively created in
the parties have agreed to modify or disapply them. It Scotland unless the parties divest control of the
is possible to disapply a rule in whole or in part. The relevant assets to the trustee. This means that most
appointment of the arbitrator is dealt with by “Arbitral trust mechanisms in English standard form contracts,
Appointments Referees” which are bodies authorised e.g. in respect of retention, will be ineffective under
by the Scottish Ministers to act in this role. Scots law.

• Adjudication – the Rules of the Scottish Scheme are • Signing – In Scotland the law in relation to the
applied. formalities of the execution of contracts is contained
in the Requirements of Writings (Scotland) Act 1995.
• Nominating bodies – the Adjudicator nominating To be validly executed a document requires to be
bodies are the Royal Incorporation of Architects properly subscribed by each of the parties on its last
in Scotland, The Royal Institution of Chartered page. At least part of the written document must
Surveyors in Scotland, National Specialist appear on the page which is signed, and that page

SWEET & MAXWELL


requires to be signed by at least one of the be subsequently issued means that any default. If the person who suffered the
parties. It is not appropriate for the parties arbitral award under the contract can be loss, injury or damage was not aware and
to sign on a blank page that is merely enforced without the need to go to court for could not, exercising reasonable diligence,
attached to the document to be executed. enforcement. have become aware of its occurrence at
The proper method of subscription the time it occurred, then the period runs
• Third Party Rights – the Contracts (Rights
depends on the nature of the party signing. from the date the person became aware
of Third Parties) Act 1999 does not apply
A document may be executed in such a or could, exercising reasonable diligence,
in Scotland. The equivalent right in Scots
way as to make it self-proving. The 1995 have become aware. The long negative
law derives from the Scottish common
Act also sets out rules for the incorporation prescription is twenty years which acts
law doctrine of jus quaesitum tertio. This
of schedules and other attachments as a longstop. This runs from the date of
allows a third party who is not party to the
to a document. Schedules should be the act, neglect or default rather than the
contract to obtain and enforce rights under
referred to in the document itself and each date of discovery of the defect. Relevant
the contract. It is necessary to identify the
schedule should be identified on its face proceedings (broadly court action or
third party in the contract by name, as a
as being the schedule that is referred to arbitration) need to be commenced prior
member of a class or as answering to a
in the contract. There is no need generally to the deadline date otherwise the claim is
particular description. It is also necessary to
for a schedule to be signed unless it is a extinguished.
show that the contracting parties intended
contract which “relates to land”. There is no
to benefit the third party. The third party In general terms, the similarities between the
Scottish equivalent to the English rule on
rights procedure is not commonly used. JCT and SBCC forms by far outweigh the
counterparts or exchange of contract.
Collateral warranties remain the preferred differences but it is important to bear in mind
• Registration for preservation and option in Scotland. the key differences above if contracting north
execution – In Scotland the parties of the border.
• Prescription & Limitation – The law in
may agree to have the contract, and
Scotland on prescription and limitation of Shona Frame is a Partner at MacRoberts
more particularly any arbitration clause,
claims is to be found in the Prescription LLP. She is accredited by the Law Society of
registered in the Books of Council and
and Limitation (Scotland) Act 1973 and the Scotland as a Specialist in Construction Law.
Session in Edinburgh. Registration for
case law regarding its interpretation and She can be contacted on shona.frame@
preservation means the document is kept
application. The short negative prescriptive macroberts.com
safe in the Register so it does not get lost.
period is five years. This period runs
Registration of the contract for execution
from the date any loss, injury or damage
together with any decree arbitral that may
occurred as a result of an act, neglect or
JCT NEWS
CAN INSURANCE EVER CATCH UP?
10 BILL GLOYN - PARTNER, JARDINE LLOYD THOMPSON EUROPEAN REAL ESTATE; IMMEDIATE PAST-PRESIDENT,
CITY PROPERTY ASSOCIATION

Fortunately, at least for those that can effect Where reinsurers do object to a particular risk
insurance, most serious disasters are covered. one often sees standard exclusions from most
The UK has a very mature market that has policies. One such risk is the legal liability that
seen, and responded to, most of the dangers might arise from working with asbestos. There,
that nature – and fellow humans – can throw of course, the insurance market has suffered
at us. enormously from the industrial disease claims
that started flowing during the 1970’s but
Occasionally something new comes along
which reached a peak some 20 years after. It
and, after a while, insurance usually steps
is not possible to estimate how much insurers
up to the plate and provides protection. A
will have to pay out but a recent estimate of
classic example was terrorism. After two
the total cost in the US alone put the potential
major bombings in London in the early 1990’s,
figure at over $200 billion. The relatively low
individual insurers, and their reinsurers, felt
premiums that these losses related to had
unable to shoulder the burden of another
often been collected decades earlier and
attack under the normal arrangements.
forgotten about, and so the volume of claims
However, with the support of H M Government
There are some changes afoot to the that hit the insurance market posed a severe
acting as re-insurers of last resort, the whole
insurance obligations in clauses 6.11 and threat to its stability. Fortunately, the situation
market got together and formed a mutual
6.12 (and associated Contract Particulars) was managed and now seems under control.
insurance company – the Pool Re – that
of the proposed 2011 version of the Design
enabled insurance to be offered. First this Not surprising that there is now a reluctance to
and Build contract. These relate to the
was against the risk of fire and explosion get involved with asbestos exposures. There is
requirement to include cover for asbestos
only but, after the atrocities of 9/11 – with a similar reluctance to get involved with toxic
and toxic fungal mould within the Professional
the world market removing any cover for mould; not yet a major problem in the UK but
Indemnity insurance that the contractor has
damage and subsequent losses arising out one that has reportedly led to some 30,000
to effect. Having been put there in the 2009
of an act of terrorism – the extent of the claims in the United States – at a cost of over
amendments, it is now planned to remove
protection was extended to an “all risks” basis, $500million. The fear, confirmed by an RICS
them as the required cover has proved difficult
including radioactive, chemical and biological commissioned report which estimated that
to obtain.
contamination. some 3 million homes in the UK are potentially
This change led me to think about the reason affected by it, is that toxic strains of mould are
That makes the cover available in the UK
for insurance being an integral part of the becoming more prevalent in the UK and may
arguably the widest anywhere in the world. We
obligations of both parties in the first place – to eventually lead to the volume of death, illness
are the envy of many other countries, giving
provide a financially secure way of transferring and property damage/valuation claims seen in
comfort to the many overseas investors that
risk. Insurance is a vital ingredient of relation to asbestos.
have put their money into the UK over the past
commerce; without it the risk that a business
decade. So, insurance does respond when No wonder that claims from mould are also
would fail in the event of a disaster would be
needed. becoming a widespread exclusion from
too great for many transactions to go ahead.
many types of policy – including professional
Reinsurers, mentioned earlier, are basically a
Risk is a moving target. As many people and indemnity. Also, understandable is JCT’s view
global group of mega insurance companies
businesses have found out over the past few that insurance against claims arising from
who insure the primary insurer – the one that
years, areas previously unaffected by flooding asbestos and toxic mould should therefore
issues the policy – against catastrophic losses
have experienced devastating damage and not form part of the standard contract
that would otherwise affect their financial
subsequent consequential losses. And that requirements.
stability. Consequently, reinsurers have
ignores the human tragedy often involved.
considerable power in dictating underwriting However, insurers do respond to demand.
Tragically, the catastrophic events in Japan
policy. Sometimes reinsurers take a particular Perversely, just as the requirement is being
seem to have been largely uninsured, due to
dislike to a certain risk and, being a basically removed a fledgling market has emerged
a lack of underwriting capacity for earthquake
unregulated global grouping, they can among specialist underwriters. So, anyone
and tsunami exposures.
therefore take decisions in concert – unlike who wants to retain the requirement for wider
direct insurers who must act so as not to cover may find it, that is if they look hard
offend anti-competitive legislation. enough and are not fobbed off by assertions
that it is not available.

SWEET & MAXWELL


11 EDUCATION AND TRAINING INITIATIVE ANNOUNCED,
AS JCT CELEBRATES LANDMARK 80TH ANNIVERSARY
JCT used its recent 80th birthday 80 years and counting...
celebration to announce plans of its new
“The announcement of the initiative marks
Education and Training Initiative.
another exciting period for JCT, which enters
Professor Peter Hibberd, JCT chairman, its 80th year at the forefront of the industry,
introduced the initiative in his speech at a setting standards for construction contracts,”
special event held at the Royal Institute of commented Neil Gower, JCT chief executive
British Architects (RIBA) in London.
“Throughout its history JCT has been an
Hibberd will be championing education and example of effective collaboration in the
training throughout the year with a phased construction industry. It was, and remains a
roll-out, aimed at improving understanding consensus-based organisation serving every
of the construction industry, and in part of the construction supply chain. Through
particular, procurement and construction the support of its members and the industry
contracts. as a whole, JCT continues to provide real
benefits. Its wide portfolio of construction
Plans for the Education and Training contracts is estimated to be used on 80% of
Initiative include: construction projects.”
• The JCT Academic Box Set, a The continued impact of JCT’s work across
comprehensive tool for education
the industry was reflected in the warm and
providers which includes the full set The Jive Aces: celebrating success with JCT
lively celebration at the RIBA on 12 April.
of JCT contracts as well as a range
of benefits via membership of JCT’s
Education and Training Provider Group.
Recognition of JCT’s achievements was echoed across the industry:
• Closer collaboration with institutions
providing construction-related courses, “When it was established, JCT was revolutionary, [...] saving huge amounts
with the creation of a bespoke JCT of time and money. [...] JCT has built on its leadership in the industry with
module to enhance the understanding of the recent introduction of provisions and guidance on sustainability and fair
procurement and contracts.
payment.”
• A competition for students with the Mark Frisk MP, construction minister
chance to win bursaries towards the
funding of courses. “[...] It is a tribute to its success that it is now both the UK’s leading construction
• A dedicated area of the JCT website. contract authoring body and provides the largest portfolio of standard form
contracts in the world.”
Peter Hibberd explained: “Many of the
Ruth Reed, RIBA president
industry’s problems could be addressed
through better education and training. “JCT is also a superb demonstration of the industry resolving its own issues. [...]
“...if trades and subcontractors had a better
This consensus remains today, with all new and revised JCT contracts being
understanding of contractual objectives, approved by all sides of the industry before publication.”
contract provisions, and the impact of their Tony Bingham, leading construction barrister and arbitrator
actions, many of the problems and disputes
“JCT is proof if ever it was needed that whilst the world of commerce changes,
which escalate up the supply chain could
good ideas last. [...] It is worth reflecting on the man-hours the JCT saves our
be avoided.
sector each year through its sterling work on standardisation.”
“This is not just about skills; it is also Liz Peace, BPF chief executive
about understanding the industry, about
educating those within the industry, and “Our Contracts in Use Survey showed them [JCT] to be leading the market in
those entering it.” contract use. [...] Clearly the market sees the JCT contract as the mainstay of
the construction industry in the UK.”
Robert Peto, RICS president
JCT NEWS FLASH
NEW SERVICES AND PRODUCTS FROM JCT

JCT CONTRACTS 2011 START YOUR TRANSITION • Design and Build Contract 2011 Tracked
Change Document
EDITION TO JCT 2011 WITH JCT
• Intermediate Building Contract 2011
NEW ACT, NEW EDITION TRACKED CHANGE Tracked Change Document
The new edition of JCT Contracts – JCT 2011, DOCUMENTS • Intermediate Building Contract with
will cover the new payment legislation and THE CHANGES TRACKED FOR YOU contractor’s design 2011 Tracked Change
other updates. Currently, the Department for Document
Business, Innovation & Skills (BIS) are working To help make the move to the new edition of
JCT Contracts as smooth as possible, the JCT • Minor Works Building Contract 2011
towards an implementation date of October this
have produced the JCT Contracts Tracked Tracked Change Document
year for the new Construction Act.
Change Documents that show the tracked • Minor Works Building Contract with
If implementation is confirmed by mid July changes to the existing JCT 2005 contracts contractor’s design 2011 Tracked Change
for October, JCT 2011 will be published in that will form the JCT 2011 suite of contracts. Document
September, to give you time to make the
transition to the new suite. Especially helpful for professional advisers All other contracts are available through
who have requested advance notice of the Docdel by emailing: sweetandmaxwell.
The JCT 2005 suite will remain available for changes so that they can advise their clients, Docdel@thomson.com.
nine months after the implementation date and the Tracked Change Documents are available
will be labelled to show they no longer comply in hard copy only. When you purchase a Tracked Change
with the current legislation. Document through Docdel, you will receive
HOW TO GET THE TRACKED CHANGE an unbound hardcopy print out of the PDF
If you are a current subscriber to JCT’s Digital DOCUMENT YOU NEED version.
Contracts Service, you will receive your CD in
early September. The following Tracked Change Documents are

Watch the press and your JCT News for more


available to order in bound hardcopy from your JCT EDUCATION AND
local stockist.
details. Email stanform@jctltd.co.uk to sign TRAINING
up to receive the paper or E version. • Standard Building Contract with Quantities
2011 Tracked Change Document The JCT Education and Training Provider
Pack includes a set of highly beneficial tools
JCT CONTRACTS • Standard Building Contract with and support for academic institutions and
Approximate Quantities 2011 Tracked
COMPLETE WORKS Change Document
other education and training providers.

JCT 2011 Complete Works comprises of E-mail us today at stanform@jctltd.co.uk to


• Standard Building Contract without find out more and register your interest.
a full set of JCT documents, in JCT branded
Quantities 2011 Tracked Change Document
binders, for your library or office.
Pre-order from your local stockist today.
JCT 2011COMPLETE WORKS
ISBN: 978-0-414-04793-8

You can find full pricing and a list of


stockists at jctcontracts.com

MAKE SURE YOU RECEIVE EVERY


ISSUE OF THE JCT NEWS
Please email us at stanform@jctltd.co.uk to add
yourself, colleagues or your organisation to the JCT
News mailing list, or to amend your contact details.

SWEET & MAXWELL

You might also like