Dear: Arch.

Benny June,

We are formally submitted here with our offer for the demolition of your old house.
Please review the following requirements of our demolition.

Subject : Demolition of 2 storey apartment (3 units) with clearing

Location : Fernando St. Corner A. Roxas St. Vito Cruz Manila

Demolition services shall be in exchange of:

A.) Your company will pay the amount of (P 119,000 pesos) for demolishing your 2 storey
concrete house with clearing.
B.) Down payment of P 69,000 pesos must be given before the start day of demolition work.
should only be 20-30% dp
C.) And for the final payment, P 50,000 pesos shall be given upon 100% accomplishment of
the said demolition works.

Bank Details:

Account name: Jeffrey Q. Angeles


Account number: 9739-1077-73
Bank : BPI

• All materials such as Roof & Lumber will be recovered by the contractor’s side.
All salvageable materials such as wires/cables, embedded deformed bars & scrap metals, etc.
will be recovered by the demolition contractor/buyer’s side.

• -- COMPLETE SET – Cutting Torch Kit & Tank

Torch Handle
Oxygen Attachment
Oxygen Regulator & Tank
Acetylene Regulator & Tank
Welding Nozzles (Nos. 3, 5, & 7)
Mixer
Cutting Nozzle
Twin Hose: 15ft x 1/4" C/W Fittings
Tip Cleaner
Goggles Spark Lighter

• Demolition Tools

Tactical Pry Bar & Crowbar


Sledgehammer
Nail Set
Framing Hammer
Phillips & Straight Flat Screwdrivers
Demolition Maul
Chisels
Crosscut Saw
Shovel
Demolition Rope 30ft. long 2pcs.
Demolition Hammer
demolition heavy equipments?

Scope of Work:

a.) Complete demolition of all standing structure.


should include
b.) Dismantling of house up to ground floor level only. excavation of
foundations and
c.) Hauling out of all retrievable materials. tie beams

d.) With clearing and hauling.

e.) Dismantling of firewall.

f.) Demolition of perimeter fence.

permits?

Terms and conditions:

a.) Mobilization of manpower, necessary tools and equipment shall be provided by the
contractor. We can already start working on the demolition of the said house within the day after
receiving your approval and procurement of the necessary demolition and barangay permits.
b.) The existing rules and regulation being implemented by the village/barangay shall be strictly
followed by the contractor while on the course of demolition works.

c.) Any untoward incidents/ accidents to workers or third party inside the property or within the
peripheral of the demolition area that may occur on the course of demolition works shall be for
the demolition contractor’s sole liability.

d.) Erection of safety signs, barriers, nets, etc shall be for demolition company expense.

e.) Duration of work must be completed within maximum of (14) days, and shall commence
effectively, procurement of the necessary barangay and demolition permits and after receiving
the owner notice to proceed. another 7 days should be alloted for excavation

f.) All the retrievable materials shall have a designated area of stockpile.

g.) The demolition contractor shall not be held liable for any delays caused by “force majure” or
deemed as act of God. Hence an extension of time may be granted by the owner.

h.) Request for additional time shall be subject to owner’s approval for clarification and may
only be granted by the owner through agreed terms and condition acceptable to both parties

i.) Homeowner to provide Utilities access during the course of demolition and said bills incurred
shall be for demolition contractor’s expenses.

Arch. Benny June Jheff Angeles

Owner/Authorized Personnel Proprietor


A.D. TORRES TRADING
6553 E. RAMOS STREET MAKATI CITY
CONTACT NUMBER: 09173234989/09207709901
EMAIL; adtorrestrading@yahoo.com

March 13, 2018

Attention: Architect Benny June Nacion


Subject: Ground Level Demolition Of Old House Located At Fernando St>
Paco Manila

Dear Sir,
I would like to formalize a bid proposal for the Ground level Demolition Of Old House
located at Fernando St. Paco Manila . Please find the details of our offer as follow

DEMOLITION COST -------------------------------------------- Php 340,000.00


Less Recovery Items ------------------------------------------ Php 200,000.00
Total Payable To Be Contractor = Php 140,000.00
excavation not included

TERMS OF PAYMENT:
1. 30% down payment of total demolition cost upon mobilization to the demolition site .
2. Remaining balance of 70% upon completion of the project .

SCOPE OF WORK:
1. Demolition of whole structure to the ground level. should expose natural grade line
2. Use of equipment’s or machineries to speed up demolition procedure with the help of manual
man power.
3. Clearing and hauling of all debris and garbage’s to its appropriate dumping site except soil.

CONDITIONS:
1. All salvageable items (wood, concrete, steel, glass, lighting fixtures, wiring, tiles, and all other
salvageable items inside the structure, will be for the account of the demolition contractor.
2. Insurance, wages and coverage of all workers that will undergo the demolition services for the
account of the contractor.
3. All government permits necessary for the demolition of the said structure, are for the account
of the contractor.
4. Project duration is thirty (30) working days upon issuance of demolition permit.
target date should be 14-21 days only with
excavation

Should you have any questions/clarifications on the above matter, please feel free to contact us
and we will be more than willing to serve you.
ZAAM Demolition Contractor
Demolition· Dismantling, Etc
Dealer of assorted scrap materials · Trucking ·
Address: Block 1 Lot 12 Ursing Street, Saint Joseph Subd, Pulang Lupa Dos, Las Piñas City
Email Add: marc_andaya14@yahoo.com

March 5, 2018
Fernando st Corner A.Roxas
Vitocuz Manila

Attention : Architect Benny Nacion

Sir,
Submitted herewith is our proposal to render demolition services concerning your two and a a
half storey residential house, located at Fernado St, Corner A. Roxas Vitocruz Manila
Demolition services shall be ONE HUNDRED TWENTY SEVEN THOUSAND PESOS ONLY (Php:
127,000.00). In-addition,all salvageable materials such as wires/cables, woods/lumbers,
plywoods, purlins, trusses, joists, doors and jambs, embedded deformed bars in CHB walls,
columns and beams, scrap metals, etc., shall be granted to the demolition contractor.

Scope of Works:
• Breaking of all CHB walls and its vertical structures.
• Complete dismantling of floorings and existing posts.
• Extraction of foundations, footings and tie beams.
• Hauling and clearing of garbage, debris and salvageable materials. However, all soil
materials shall be left in place for back filling.
• Erection of temporary fence using blue sheets along enclosing shelves of the house. The
firewall shall be remained intact. firewall should be demolished
Terms and conditions:
• Mobilization of manpower, necessary tools and equipment’sshall be provided by the
contractor a day after receiving your notice to proceed and down payment.
• Mode of Payment shall be:
1. 30% Down Payment
2. 50% Progressive payment prior for mobilization of heavy equipment
(Backhoe / breaker) and ten-wheelerdump trucks.
3. 20% Upon Project Completion
4. All payments shall be made cash or check prior to this contract agreement shall be
paid only to the demolition contractor who is Mr. Mark Anthony Andaya.
• Securing of all pertinent documents such as barangay clearance, village association
bond and (demolition permit coming from the city hall if necessary) shall be
shouldered and provided by the owner.
• The existing rules and regulation being implemented by the village/barangay shall be
strictly followed by the contractor while on the course of demolition works.
• Any untoward incidents/ accidents that may occur on the course of demolition
works the contractor shall be held liable.
• Duration of work must becompleted within twenty five (25) working days and shall
commence effectively two days after receiving the owner notice to proceed and
down payment. we will try to target 21 days, but 25 is acceptable
• All the retrievable materials shall have a designated area of stockpile.
• The demolition contractor shall not be held liable for any delays caused by “force
majure” or deemed as act of God. Hence an extension of time may be granted by
the owner.
• Request for additional time shall be subject to owner’s approval for clarification and
may only be granted by the owner through agreed terms and condition acceptable
to both parties. can be deducted to the original contract, per day
delayed

Rest assured that the undersigned will comply to any of your further demands necessary to
finish the aforesaid project.

Respectfully Yours,

Mr. Mark Anthony B. Andaya


Demolition Contractor
Thank you very much for giving us this opportunity to offer our services and we hope to have a
long lasting business relationship with your prestigious company.

TOTAL BREAKDOWN

Hauling of Debris ------------------------------------------ Php 90,000.00


Rental Backhoe ---------------------------------------------- Php 50,000.00
Labor Expenses ---------------------------------------------- Php 80,000.00
Cutting Tools Expenses ---------------------------------- Php 15,000.00
Demolition Permit ------------------------------------------ Php 75,000.00
Expenses ------------------------------------------------------- Php 30,000.00
Total Breakdown -------------------------------------------- Php 340,000.00

Your’s Truly,

ANTONIO DORIO TORRES


Proprietor
Hi, Arch Benny

A pleasant day to you.

Thank you for taking my call earlier. As discussed over the phone, attached is ADTorres' revised
proposal for the demolition of the house. The scope are as follows:

1. Processing of demolition permit


2. Demolition of house (scrap sales shall be under the ownership of the demolition contractor)
3. Clearing and hauling of debris (up to ground zero - floor slab will be left)

As mentioned, the reason why their initial proposal was high ( inclusive of 2m depth excavation) is
that they will be outsourcing the excavation services to a specialty contractor and will be filing for
an excavation permit. Since ADTorres specialty is demolition and not excavation, I suggest you
consider to award the excavation to your gencon as part of their scope of works or consider hiring
a excavation trade contractor directly to save cost. By packaging the excavation works with the
general civil works contractor, you will be in a better position to haggle costs as they will also be
considering the other scope of works assigned to them when they submit their proposed
discounted prices. If you go with the latter proposal which is awarding the excavation directly to
an excavation trade contractor, the demolition contractor's overhead and mark up costs will be
eliminated thus you will be only charged by the excavation contractor's actual cost. excavation should be
included to advance soil
Feel free to call my attention for any clarification or questions regarding the proposal.testing

Thanks
BART FLORES

March 13, 2018

Archt. Benny

San Fernando St. Corner A Roxas, Vito Cruz Manila

This is referring to our quotation on your house demolition

1. Before we start the demolition, we are putting a temporary fence on the square area
of your lot.

2. The demolition of your house will be totally knocked down with hauling and removal
of broken concrete and clearing of all debris and waste materials.

3. Removal of post including putting and breaking the floor area.

4. All salvage materials “such as BAKAL “YERO “KAHOY” and others will be
pertaining to demolition contractor.

5. That in case accident, injuries, death, damage, petty problems happened during
the work the owner of the property will not be liable of any kind.

6. Supply all labor, tools and equipment like backhoe/ breaker and dump truck to
perform the work specified to be shouldered by the demolition contractor

7. All demolition permit will be shouldered by the demolition contractor.

8. The owner of the house will pay the amount of Php 370,000 pesos to the
demolition contractor changed to 300,000 pesos
project duration should be included
Scope of work;
1. Hauling of debris and waste materials
2. Removal of post including putting and breaking floor area
3. Complete demolition permit

Terms:
A. 50% - Down Payment 20 - 30% percent is acceptable
B. 40% - Progress Billing
C. 10% - Full Payment (Project Accomplished)

Thank you for the opportunity to accept our quotation


Very truly yours,
____________________
Orlando “BART” Flores
(Demolition Contractor)
Cel.0917-360-3679
Cel.0915-522-8554
INFINITE VENTURE DEMOLITION SERVICE
Demolition· Excavation and Earth Moving, Etc
Dealer of scrap paper · Paper trimmings · Assorted scrap materials · Trucking ·Address:
Office Address: 6892 Washington St., Makati City *
Email Add: abeth.nueva@gmail.com*
Tel Nos: 8172089 *CP# 09192825261 *09059631205

March 16,2018

Attention : Arch. Benny Nacion

Sir,

Submitted herewith is our proposal to render demolition and hauling services of your dilapidated
two storey- house located at A. Roxas corner Fernando Sts., City of Manila. The best price we can
offer for the said rendered demolition and hauling services is One Hundred Fifty Thousand Pesos
Only (Php.: 150,000.00) VAT EXCLUSIVE.

Scope of Works:
a.) Complete dismantling, demolition and breaking of your dilapidated two-storey houses
including the concrete slabs or finished grade line.
b.) Breaking of all CHB walls and its vertical structures. includes fire walls
c.) After breaking the concrete slabs or finish grade-line, the exposed or the resulting natural
grade line shall be the reference point of elevation throughout the entire area.
d.) Extraction of the foundation.
e.) Installation of blue sheets thru its enclosing shelves of the said residential house.
f.) Hauling of all retrievable materials as well as debris and stockpile of unsuitable materials.
g.) Spreading evenly the top soil throughout the entire area to obtain the average point of
elevation.
without building permit
Terms and conditions:
a.) Mobilization of manpower, necessary tools and equipment shall be provided by the
contractors a day after receiving your company notice of award and notice to proceed.
b.) To compensate for the cost of equipment, hauling of debris, manpower, etc. All
retrievable materials that were left over shall be granted in favor of the contractors.
c.) Demolition permit and Barangay clearance shall be provided by our company.
d.) CARI Insurance and Individual insurance of workers shall be in the account of the
contractors.
e.) The contractors shall bear all liabilities arising from any untoward incidents that may
occur while on the course of demolition works.
f.) Heavy equipment to be used ¾ backhoe and ten wheeler dump trucks and mini dump
trucks.
g.) Duration of work must be completed within forty (40) working days. target is 14-25 days
h.) The demolition contractor shall not be held liable for any delays caused by “force
majure” or deemed as act of God. Hence an extension of time may be granted by your
company.
i.) Request for additional time shall be subject for approval and clarification that may
only be granted by your company through agreed terms and condition acceptable to
both parties. can be deducted to the total package, per
day lost
Billing Progress:
a.) Initial down payment of Thirty percent (30%) upon receiving your company notice of
award and notice to proceed for mobilization of manpower, tool, temporary
installation of perimeter fence.
b.) Secondary payment of Thirty percent (30%) shall be made by your company for
mobilization of backhoe and for the incurring costs of dump trucks. If all the top
portion of the dilapidated houses and stripping of doors, windows, partitions, ceilings,
etc have been done by the contractors.
c.) Tertiary payment of Thirty percent (30%) shall be made by your company for the
extraction of foundations and incurring cost of dump trucks for clearing of all the
accumulated debris.
d.) Retention of Ten percent (10%) shall be settled only by your company upon
completion of works.

Rest assured that the undersignees will comply to any further demands of your company
necessary to finish the aforesaid project.

Respectfully Yours,

Mrs. Elizabeth Nueva


Project Manager

Noted By:

Engr. Salvador Andaya


IVDS - President