What does “Effort driven” option in Microsoft


Project do?

January 11, 2016September 16, 2016 /

You may wonder what does “Effort driven” option in Task Detail Form do?

https://doduykhuong.com/2016/01/11/what-does-effort-driven-option-in-microsoft-project-do/ 1/5
3/25/2018 What does “Effort driven” option in Microsoft Project do? – Do Duy Khuong Blog

(h ps://doduykhuong.files.wordpress.com/2016/01/13.png)

Here I have 2 tasks.

Task A doesn’t have Effort driven check. When I assign 2 resources to it, the Work unit for each resource
doesn’t change (80h for each resource). No ma er how many resource I assign, each resource will get
80h.

(h ps://doduykhuong.files.wordpress.com/2016/01/23.png)

Now, Task B have Effort driven check. When I assign resource to it, the Work unit for each resource
change (with 2 resource assign it will get 40h for each resource). And activity duration reduce to 5 days.
The more resource you assign, the less unit each resource will get.

https://doduykhuong.com/2016/01/11/what-does-effort-driven-option-in-microsoft-project-do/ 2/5
3/25/2018 What does “Effort driven” option in Microsoft Project do? – Do Duy Khuong Blog

(h ps://doduykhuong.files.wordpress.com/2016/01/33.png)

SUMMARY

So, when you have kind of activity which can be reduced duration by adding more resource, use “Effort
driven” option.

https://doduykhuong.com/2016/01/11/what-does-effort-driven-option-in-microsoft-project-do/ 3/5
3/25/2018 What does “Effort driven” option in Microsoft Project do? – Do Duy Khuong Blog

Advertisements

Gestión de Proyectos
Pasos para el éxito del proyecto:
pruebe Wrike, organízate, cumpla
con los plazos.

Report this ad

Report this ad

Published by Khuong Do

Khuong Do is a Project Planner / Construction Claims Consultant / Delay Analyst in Civil,


Transportation and Oil & Gas Industry. He has worked as a Primavera Consultant Specialist since 2006 .
He holds a Civil Engineering degree and a Bachelor of Information Management System. Now he is
working in SGC company, providing Delay Analysis service. They have offices in Beijing – China and
Dubai – UAE. View all posts by Khuong Do

2 Comments

1. elvin says:February 13, 2016 at 6:43 PM


You can choose activity type “fixed work” and get the same result.

https://doduykhuong.com/2016/01/11/what-does-effort-driven-option-in-microsoft-project-do/ 4/5
3/25/2018 What does “Effort driven” option in Microsoft Project do? – Do Duy Khuong Blog

Reply
1. kelvinkirby says:September 29, 2016 at 4:42 AM
Yes that’s correct. Fixed Work and Effort Driven mean the same thing in this context. In fact if you
select Fixed Work, it automatically puts a tick in the effort driven check box and grey’s it out. :-).
But you can have effort driven selected (or not) for Fixed duration and Fixed Unit tasks. In either
of these cases the behaviour can be different.