Professional Documents
Culture Documents
You may wonder what does “Effort driven” option in Task Detail Form do?
https://doduykhuong.com/2016/01/11/what-does-effort-driven-option-in-microsoft-project-do/ 1/5
3/25/2018 What does “Effort driven” option in Microsoft Project do? – Do Duy Khuong Blog
(h ps://doduykhuong.files.wordpress.com/2016/01/13.png)
Task A doesn’t have Effort driven check. When I assign 2 resources to it, the Work unit for each resource
doesn’t change (80h for each resource). No ma er how many resource I assign, each resource will get
80h.
(h ps://doduykhuong.files.wordpress.com/2016/01/23.png)
Now, Task B have Effort driven check. When I assign resource to it, the Work unit for each resource
change (with 2 resource assign it will get 40h for each resource). And activity duration reduce to 5 days.
The more resource you assign, the less unit each resource will get.
https://doduykhuong.com/2016/01/11/what-does-effort-driven-option-in-microsoft-project-do/ 2/5
3/25/2018 What does “Effort driven” option in Microsoft Project do? – Do Duy Khuong Blog
(h ps://doduykhuong.files.wordpress.com/2016/01/33.png)
SUMMARY
So, when you have kind of activity which can be reduced duration by adding more resource, use “Effort
driven” option.
https://doduykhuong.com/2016/01/11/what-does-effort-driven-option-in-microsoft-project-do/ 3/5
3/25/2018 What does “Effort driven” option in Microsoft Project do? – Do Duy Khuong Blog
Advertisements
Gestión de Proyectos
Pasos para el éxito del proyecto:
pruebe Wrike, organízate, cumpla
con los plazos.
Report this ad
Report this ad
Published by Khuong Do
2 Comments
https://doduykhuong.com/2016/01/11/what-does-effort-driven-option-in-microsoft-project-do/ 4/5
3/25/2018 What does “Effort driven” option in Microsoft Project do? – Do Duy Khuong Blog
Reply
1. kelvinkirby says:September 29, 2016 at 4:42 AM
Yes that’s correct. Fixed Work and Effort Driven mean the same thing in this context. In fact if you
select Fixed Work, it automatically puts a tick in the effort driven check box and grey’s it out. :-).
But you can have effort driven selected (or not) for Fixed duration and Fixed Unit tasks. In either
of these cases the behaviour can be different.
Reply
https://doduykhuong.com/2016/01/11/what-does-effort-driven-option-in-microsoft-project-do/ 5/5