Professional Documents
Culture Documents
• Approach channel
• Ramp
• Tunnel Intake
• Tunnel
• Surge Shaft
• DT Tunnels
• Pump House
• Delivery mains
• Cistern
Package - 23
J Chokka Rao Devadula Lift Irrigation Scheme
Kaleswaram Lift Irrigation Scheme
P.V. Narasimha Rao Kanthanapally
Sujala Sravanthi Project
Jyothi Rao Pule Dummugudem Nagarjuna
Sagar Sujala Sravanthi (Link Canal)
Indira Sagar Rudramkota Lift Irrigation
Scheme
Rajiv Dummugudem Lift Irrigation Scheme
Rajiv Dummugudem Lift Irrigation Scheme
Chagalnadu Lift Irrigation Scheme
Venkatanagaram Pumping Scheme
Thota Venkatachalam Pushkara L.I.S.
Thota Venkatachalam Pushkara L.I.S.
Tadipudi Lift Irrigation Scheme
Tadipudi Lift Irrigation Scheme
Rajiv Bheema Lift Irrigation Scheme
Rajiv Bheema Lift Irrigation Scheme
Rajiv Bheema Lift Irrigation Scheme
Jawahar Nettempadu L.I.S.
Mahatma Gandhi Kalwakurthi L.I.S.
Mahatma Gandhi Kalwakurthi L.I.S.
Koil Sagar L.I.S.
Anantha Venkata Reddy Hundri Neeva
Sujala Sravanthi Project L.I.S.
Anantha Venkata Reddy Hundri Neeva
Sujala Sravanthi Project L.I.S.
Status of work:
Total length of canal under Phase – I : 251.750 Km
Phase – I :
Completed water is let out in to Jeedipally Resorvoir.
Siddapuram L.I.S.
Gandikota L.I.S.
Gandikota C.B.R. L.I.S.
Gandikota C.B.R. L.I.S.
Gandikota C.B.R. L.I.S.
C.B.R. Right Canal L.I.S.
C.B.R. Right Canal L.I.S.
C.B.R. Right Canal L.I.S.
Guru Raghavendra L.I.S.
Reasons for Opting L.I.Schemes
• Spatial and temporal distribution of rainfall variation
leads for construction of storage reservoirs for
Irrigation needs and for Water supply.
• For the regions which are situated at higher altitudes
where gravity system of canals is not feasible.
• Prevailing situation is widening the socioeconomic
conditions between regions creating imbalance.
• Certain site conditions of source do not permit
construction of dams/barrages.
• Lift irrigation system has gained great significance in
the changed scenario as provision of conventional
irrigation structures is exhausted.
Limitation of the conventional Irrigation
structures namely Dams and Barrages
• Submersion
• Rehabilitation
• Land Acquisition
• Environmental Clearance
• Interstate Disputes and also
• They consume much time / more no. of
years
• Requires huge financial support and estimated
costs gets multiplied due to delay in
completion of projects and due to escalation of
prices.
• Even after completion of projects such as
major dams in the vicinity certain uplands still
unable to get Water for Example:
Priyadarshini Jurala Project, Srisailam and
Nagarjuna Sagar which promoted to take up
the projects like AMRP, Kalwakurthy,
Nettempadu, Bheema, Koilsagar, AVRHNSS
Need for lift Irrigation Schemes
• In the present circumstances, lift irrigation
schemes assumed greater significance and
seems to be the only viable solution to meet the
aspirations of the upland people for the
following reasons :
• Speedy Completion of the Scheme
• Lesser initial Cost
• No need of extensive time for investigation
• Flexibility of Location of Head works
• Minimal foundation problems
• Environmental friendly
• Absence of many problems in dams such as
Submersion, Environment, Rehabilitation,
Land Acquisition and Inter-state Disputes.
• Though lift irrigation schemes have some
drawbacks and costly, in the prevailing
situation, they are inevitable since the situation
demands them in the contemporary irrigation
planning, but ought to be taken up judiciously.
Objectives of L.I.Schemes
Diversion of flood water to upland areas can be done by:
• Supplying water to needy regions located far away from
source
• Feeding tanks for future needs
• Effective usage of water stored in reservoirs
• Optimum utilization of water by supplying designed
quantity
• Interlinking of rivers
• Transfer of surplus water from reservoirs to the required
regions.
ADVANTAGES OF LIFT
IRRIGATION SCHEMES
• Service Bay
Width = 0.7 – 2.5 x unit spacing
Height = Main hook level + clearances
II ) Electro-Mechanical and
III) Hydro-Mechanical
I) Civil Structure &
Associated components /
provisions
• Approach Canal on U/S of Pump
house
• Intake/Sump/Forebay/Surge pool
• Sub structure / sump
• Super structure to accommodate
Pumps & Motors
• Balancing Reservoirs / tanks
• Delivery Cistern
• Gravity Canal with CM & CD
works on delivery side
II) Electro Mechanical
• Pumps & Motors
• Control Panels
• SCADA
• Dewatering Pumps
• Fire water Pumps
• EOT crane for Pumps
• HOPDV / NRV /
EOPDV etc within
pump house
• Transformers & Sub
station
III) Hydro – Mechanical
• Pressure mains with design
dia and thickness
• Surge Protection Devices
• Valves such as air valves at
regular intervals
• Stoplogs & trashracks
• Manifold connecting
delivery pipes of pumps and
pressure mains
• Semi Portal crane for
Stoplogs & Trash racks
Planning & Design of LIS Comprises The
Following
1. Hydrology
2. Finalisation of Alignment
- Length of Gravity Canals
- Length of Pressure mains
- Number of Lifts
- Balancing Reservoirs Utilization/Introduction -
Pump Houses Location
3. Hydraulic Particulars
- Discharge
- Pumping Head
4. Design of Pumps
- Type of Pumps
- Number of Pumps
- Capacity of Pumps
5. Design of Pump House
- Approach Canal / Tunnel
- Intake / sump / Forebay
- Sub Structure
- Super Structure
6. Design of Pressure mains
- Type / Material
- Diameter of Pipes and
- Number of rows
- Pipe Laying & Compaction of refill
- Surge Analysis And Protection System
- CM & CD Works for Pipe crossings
7. Delivery Cistern / Out fall structure
8. SCADA
9. Canal networking system
1). HYDROLOGY
Water Required to be assessed based on
• Ayacut to be served
• Type of Crops
• Quantity of water
• Period of operation
• Drinking water requirement for enroute habitations.
• Pipe thickness
• Capital cost
Fixing of Pump House Location
Pump house location shall be
located such a way that it needs :
• Smaller length of approach canal
• Smaller length of approach bridge
from TBL
Utilization of Tanks / Balancing
Reservoirs
Presence of intermediate tanks
or BRs in the alignment
makes scheme economical
as well as efficient because :
• High reliability.
• Design simplicity.
• Superior operating performance.
• Low submergence.
• Lowest maintenance cost.
• Delivery size up to 60,000 mm
• Capacity up to 1,20,000 Cubic m per hour.
• Heading up to 200 m.
TYPICAL PUMP HOUSE DRAWING CONCRETE
VOLUTE PUMP / VERTICAL TURBINE PUMP
TECHNICAL COMPARISION OF CONCRETE VOLUTE
PUMP AND VERTICAL WET PIT PUMP
Typ Concrete Volute Vertical
e Pump Casing Pump
Metal
Dry – pit Wet –
Intake · Hydraulic Design ·pit Sump or Pit
· No dead water area · Dead water area
· No vortices · Chance of vortices
· No Micro/Macro · Micro/macro fouling
Fouling · Sand/silt deposit
· No Deposit · Irregular flow pattern
· Stream lined flow
pattern
Bearing · Out of water : no wear · Submerged bearing
· Oil lubricated bushes
· Easy temperature · Possible setbacks
check · Less reliability
· Minimum 10 years life · Difficult – expensive
· Simplified to maintain
maintenance
Shaft · Dry, no water contact · Inwater, subjected to
· No corrosion, long life irregular stresses and
· No vibrations problems
· Possible vibrations
and cracks
TECHNICAL COMPARISION OF CONCRETE VOLUTE
PUMP AND VERTICAL WET PIT PUMP
• Low maintenance
• Full accessibility
• High reliability
• Design simplicity
• Specific Speed
• Type of pumps
Where
d = Diameter of column assembly
D = Diameter of bowl assembly
which is usually in the range 1.5d
to 1.8d
T = Thickness of baffle wall / pier
Good features: