CCP REPLACING ROOF METHODE


PT.ROYAL CILEGON ABADI

Methods of work of the loading plug the roof SMP CCP ADH Type 650

A. Checking and measuring


1. Checking the very necessary because once the results of the checking can be a quiz to work
unloading the tide due to the much needed accurate data in order to make a request for production
cutting list or forming, also for making the system work in security sop and the JSA.
Colorsheet Roofing overlap joint

overlap
Gutter purlin
2. The creation of the system of job safety analyst (JSA) and standard operational procedure (SOP)
can be made after the team checked into a location that will be done, and can be analyzed the way
the safe way to do the job, this can be done along with team safety.
B. work of forming roof material settings ADH 650
1. after checking the team get the data is accurate, then the result is given to the engineering team to
made cutting list according to needs that are needed in work site
2. Forming this job done must install in site given the needed materials very length 22.5 meters, and
also facilitate the transfer of material from the production of forming to the lay down area under the
CCP places the Rapture material the roof over the height of 40 meters.
Material out Forming machine
22,5 Meters

conveyor

Handling

3. At the time of production or forming length 25.5 metress we need labor about 30 people
including operators, supervisors, foreman because at the time. handling of forming machine
we do manually (using human power).
4
CCP REPLACING ROOF METHODE
PT.ROYAL CILEGON ABADI

4. At the time of adoption of the roof materials using 160 T crane, at this stage we need AIDS
spyder, labrang and Til to ease at the time of execution of the increase or decrease of roofing
material.
5. At the time of appointment is only allowed 12 sheets of up to 15 sheets of roofing material.
6. Storage of material the roof above should only be placed above the rafters, due to the weight of
the roof material bias causes the destruction of the old roof surfaces and arranged in such a way
that the heavy weights are divided on one not fulcrum.

B. Demolition type ADH 650


1. the method of demolition of the roof
On the implementation of this work requires one way or method must be really accurate and safe for
workers above or the workers who were under.
at the time of the demolition there are several processes that must be performed are:

 Cutting grinding machine using a seaming bun.


 Cutting the length of the roof as an example of long 25.5 meters to 5 sections each of
length is the meter which is a 5.125 former material that should be lowered, and the cutting was
done using the engine gerida.

 Key for opening key ring using roofing clips/pas. In this process it takes effort about 15 people
because at the time of the demolition
Cutting Seaming

5.125 22.5

There is also a team that brings the material to the former.


process of dismantling can only do per three (3) pieces of the roof after three
4
CCP REPLACING ROOF METHODE
PT.ROYAL CILEGON ABADI

(3) pieces of the roof were open the next need to install a new roof because considering the rainy
season that the time has come, that at the time of execution of the demolition could be
immediately closed if it rains dating and usable keys while the clip or seaming manual.
New Roof

3 sheet

Existing Roof

Prepare tarps are broken down according to maintain if it rains suddenly.

C.Install roof type adh 650


On the implementation of the installation of a new roof there are some important things to do are:
a. Placement of new roofing material corresponding cutting lists that have been approved by the
owner and engineering.
New roof
exist existing

b. signs lap down and over the roof of each of each connection.
overlap
4
CCP REPLACING ROOF METHODE
PT.ROYAL CILEGON ABADI

c. System locking clip and seaming.


Seaming
Klip Bolt

d. pull and installation of a new roof using human labor (manual), must be done carefully because
there is a job given altitude and supple material and length.

5. finishing work is done after the roof material installed everything and checking all the clips lock
well also limit signs and over lap just right according to what was ordered.

6. seaming work is done at the end of the job and should be done for every roof connection is an end
point of a series lockdown roof to roof one another.