R&B DIVISION VALSAD

Constructing a Bridge across Margo Creek near Village Nargol on Nargol - Dehri Gowada Road up to Maharashtra
Name of Work :
state border C.H. 6 Dist. Valsad (Approaches)
Contractor : AVADH INFRASTRUCTURE PVT. LTD.
Agreement No. : B-2 / 8 OF 2009-2010
CORE, CUTTER Method (Test Method :- IS 2720 - 1975, Part - 29)
Location: 30 to 90 Date of Testing :- 7-Oct-09
Type Of Material Soil Sample No 1 to 6
M.D.D. : 1.67 O.M.C. :- 19
Chainage in Mtrs
S.
Determaination 35 45 55 65 75 85
No.
1st Test 2nd Test 3rd Test 4th Test 5th Test 6th Test
M.D.D. : 1.67 O.M.C. :- 19
S.
Determaination 1st Test 2nd Test 3rd Test 4th Test 5th Test 6th Test
No.
1 Wt. of wet Soil + Core cutter (W1) 2823 2901 2888 2830 2944 2892

2 Wt. of Core cutter (W2) 883 955 947 903 1014 946

3 Wt. of wet Soil [(W1 - W2)=W3] 1940 1946 1941 1927 1930 1946

4 Volume of core cutter (V1) 1013 1013 1017 1000 1017 1013

5 Wet Density of Soil (W3/V1) = YD(Wet) 1.915 1.921 1.908 1.927 1.897 1.921

6 Moisture contant of Soil = m1 17 18 16 18 15 18

7 Dry Density = Yd/(1+m)/100=Yd(dry) 1.637 1.628 1.645 1.633 1.650 1.628

Percentage of compaction = Yd(dry)/


8 98 97.5 98.5 97.8 98.8 97.5
(MDD)x100
Sign. Of Contractor's Reprensative Sign. Of Consultant's Reprensative Sign. Of Client's Reprensative