FISH TOWN - HARPER ROAD PROJECT PHASE 1

Paving of Harper - Karloken (50km) and


Maintenance of Karloken to Fish Town (80km)

TEST SUMMARY

Sample Source: Date:Bpit Quality


Crushed Stone Base, CREC Yard, 24/10/2017
Control
Sample Designation: Km 2+040 - 2+120 RHS
Sample Description: Base Layer Along

Intended Use: Base Subbase Fill


X

Sieve Analysis
Sieve Size 50 37.5 18.75 4.75 0.425 0.075
Test 1 100 100 63 35 12 2
Test 2 100 100 67 36 14 3
Average 100 100 65 35 13 3
Lower Limit 100 80 60 30 8 2
Upper Limit 100 100 80 60 25 5
Max 17%

Specification
Sieve Analysis Results Obtained Base
Passing 0.075 3 Max 17%
Percentage passing 0.425mm 13
Fraction passing 0.075/0.425 0.20 Max 0.66

Atterberg Limits
Liquid Limit (%) - Max 25
Plastic Limit (%) -
Plasticity Index (%) NON-PLASTIC Max 4

Califonia Bearing Ratio


@ 98% of MDD 142.0
@ 95% of MDD 124.0 Min 80
@ 93% of MDD 104.0
Organic Content 0.0 Max 2%

Moisture Density Relationship


Maximum Dry Density (kg/m3) 2.21
Optimum Moisture Content (%) 3.2

Flakiness Index 14.9 Max 35%


Elongation Index 10.3 not specified

Los Angeles Abrasion 40.3 Max 50%

Aggregate Crushing Value 26.1 not specified

Ten Percent Fines (Dry) 100.7 not specified

Ten Percent Fines (Wet/Dry) 94.4 not specified

Remarks:

Contractor's Materials Engineer Engineers Materials Engineer


FISH TOWN - HARPER ROAD PROJECT PHASE 1
Paving of Harper - Karloken (50km) and
Maintenance of Karloken to Fish Town (80km)
MOISTURE DENSITY RELATIONSHIP

Sample Source: Crushed Stone Base, CREC Yard, Bpit Quality Control Date: 19/10/2017
Sample Designation: Km 2+040 - 2+120 RHS
Sample Description: Base Layer Along
Mass air - dry sample ( g ) 5000 5000 5000 5000 5000
Mass Water added (g ) 100 125 150 200 250
Percent water added ( % ) 2.0 2.5 3.0 4.0 5.0
Estimated air - dry MC. ( % ) 0.0 0.0 0.0 0.0 0.0
Est. compaction MC. (%) 2.0 2.5 3.0 4.0 5.0
Mould Number. 1 1 1 1 1
Volume of Mould 2177 2177 2177 2177 2177
Mass of Mould (g) 4447 4447 4447 4447 4447
Mass Mould + Wet Soil. (g) 9180 9268 9420 9244 9166
Mass Wet Soil. (g) 4733 4821 4973 4797 4719
Wet Density. Kg/cu. M. 2.174 2.215 2.284 2.203 2.168
APPROX. Dry Density 2.131 2.161 2.218 2.119 2.064
Moisture Content Determination
Oven - Pan Number. 1 2 3 4 5
Mass Oven - Pan. (g) 215.0 216.0 217.0 218.0 219.0
Mass Oven - Pan + Wet Soil. (g) 984.6 1111.7 1184.9 984.9 895.4
Mass Oven - Pan + Dry Soil. (g) 968.0 1089.0 1154.0 954.0 862.0
Mass of water. (g) 16.6 22.7 30.9 30.9 33.4
Mass Dry Soil (g). 753.0 873.0 937.0 736.0 643.0
Moisture Content (%) 2.2 2.6 3.3 4.2 5.2
Back Calc. Air dry M.C. (%) 0.2 0.1 0.3 0.2 0.2
Dry Density 2.127 2.158 2.211 2.115 2.061

Contractor's Materials Engineer Engineers Assistant Materials Engineer


ESTIMATED DRY DENSITY/ ESTIMATED MOISTURE CONTENT

Est. Dry Density 2.131 2.161 2.218 2.119 2.064


Est. Moisture Content 2.0 2.5 3.0 4.0 5.0

GRAPH OF ESTIMATED DRY DENSITY/ ESTIMATED MOISTURE CONTENT


2.240
2.220
2.200
APPROX. DRY DENSITY ( kg/m3)

2.180
2.160
2.140
2.120
2.100
2.080
2.060
2.040
0.0 1.0 2.0 3.0 4.0 5.0 6.0
MOISTURE CONTENT ( % )

DRY DENSITY/ MOISTURE CONTENT

Dry Density 2.127 2.158 2.211 2.115 2.061


Moisture Content 2.2 2.6 3.3 4.2 5.2
M.D.D 2.210
O.M.C 3.2
GRAPH OF DRY DENSITY/ MOISTURE CONTENT
2.220

2.200

2.180
DRY DENSITY ( kg/m3 )

2.160

2.140

2.120

2.100

2.080

2.060

2.040
0.0 1.0 2.0 3.0 4.0 5.0 6.0
MOISTURE CONTENT ( % )

Contractor's Materials Engineer Engineers Assistant Materials Engineer


FISH TOWN - HARPER ROAD PROJECT PHASE 1 Paving of
Harper - Karloken (50km) and Maintenance of
Karloken to Fish Town (80km)

SIEVE ANALYSIS (1377-2) WASHED GRADING

Sample Source: Crushed Stone Base, CREC Yard, Bpit Quality Control Date: 19/10/2017
Sample Designation: Km 2+040 - 2+120 RHS
Material Description: Base Layer Along

Oven Dry Mass Before Washing (g): 4877 Dry Weight (g): 4867
Oven Dry Mass After Washing (g): 4819

Percentage Percnentage Specification


Sieve Size (mm) Mass Retained (g) Passing
Retained (%) Passing (%)
Upper Lower
50.00 0.0 0.0 100.0 100 100 100

37.50 0.0 0.0 100.0 100 80 100

18.75 1800.9 37.0 63.0 63 60 80

4.75 1362.8 28.0 35.0 35 30 60

0.43 1109.7 22.8 12.2 12 8 25

0.075 491.6 10.1 2.1 2 2 5 Max 17%

Pan 53.9
2.1
Wash Loss 48.3

Total 4867.3

PARTICLE SIZE ANALYSIS


100

90

80

70

60
Passing (%)

50

40

30

20

10

0
0.01 0.10 1.00 10.00 100.00
Sieve (mm)

Contractor's Materials Engineer Engineers Assistant Materials Engineer


FISH TOWN - HARPER ROAD PROJECT PHASE 1 Paving of
Harper - Karloken (50km) and Maintenance of
Karloken to Fish Town (80km)

SIEVE ANALYSIS (1377-2) WASHED GRADING

Sample Source: Crushed Stone Base, CREC Yard, Bpit Quality Control Date: 19/10/2017
Sample Designation: Km 2+040 - 2+120 RHS
Material Description: Base Layer Along

Oven Dry Mass Before Washing (g): 4419 Dry Weight (g): 4410
Oven Dry Mass After Washing (g): 4365

Percentage Percnentage Specification


Sieve Size (mm) Mass Retained (g) Passing
Retained (%) Passing (%)
Upper Lower
50.00 0.0 0.0 100.0 100 100 100

37.50 0.0 0.0 100.0 100 80 100

18.75 1468.6 33.3 66.7 67 60 80

4.75 1358.3 30.8 35.9 36 30 60

0.43 957.0 21.7 14.2 14 8 25

0.075 485.1 11.0 3.2 3 0 2 Max 17%

Pan 95.9
3.2
Wash Loss 45.2

Total 4410.2

PARTICLE SIZE ANALYSIS


100

90

80

70

60
Passing (%)

50

40

30

20

10

0
0.01 0.10 1.00 10.00 100.00
Sieve (mm)

Contractor's Materials Engineer Engineers Assistant Materials Engineer


FISH TOWN - HARPER ROAD PROJECT PHASE 1
Paving of Harper - Karloken (50km) and Maintenance of Karloken to
Fish Town (80km)

DETERMINING THE LIQUID LIMIT & PLASTICITY INDEX &LINEAR SHRINKAGE OF SOILS

Sample Source: Crushed Stone Base, CREC Yard, Bpit Quality Control Date: 19-Oct-17
Sample Designation: Km 2+040 - 2+120 RHS
Material Description: Base Layer Along

LIQUID LIMIT PLASTIC LIMIT


Container number
Number of blows
Wt.of Container +Wet soil (g)
Wt.of Container +Dry soil (g)
Wt.of water (g)
Wt.of Container weight (g)
Wt.of Dry soil (g)
Moisture content (%)
Average ( %) — — — — -

41

40.5

40

39.5
Moisture content %

39

38.5

38

37.5

37

36.5

36
0 5 10 15 20 25 30
No. of blows

SIEVE ANALYSIS LINEAR SHRINKAGE

Sieve size Wt/Rt %Pass Mould number — —

No.10 2.00 mm — — Initial length L0(mm) — —

No.40 0.425 mm — — Oven-dried length LD(mm) — —

No.200 0.075 mm — —
Linera Shrinkage,LS=100(1-
— —
LD/L0) (%)
Liquid Limit -

Plastic Limit - Average %

Plasticity Index NON-PLASTIC

Group Index
Soil Classification

Contractor's Materials Engineer Engineers Assistant Materials Engineer


FISH TOWN - HARPER ROAD PROJECT PHASE 1
Paving of Harper - Karloken (50km) and Maintenance of Karloken to
Fish Town (80km)

DETERMINING THE LIQUID LIMIT & PLASTICITY INDEX &LINEAR SHRINKAGE OF SOILS

Sample Source: Crushed Stone Base, CREC Yard, Bpit Quality Control Date: 19-Oct-17
Sample Designation: Km 2+040 - 2+120 RHS
Material Description: Base Layer Along

LIQUID LIMIT PLASTIC LIMIT


Container number
Number of blows
Wt.of Container +Wet soil (g)
Wt.of Container +Dry soil (g)
Wt.of water (g)
Wt.of Container weight (g)
Wt.of Dry soil (g)
Moisture content (%)
Average ( %) — — — — -

41

40.5

40

39.5
Moisture content %

39

38.5

38

37.5

37

36.5

36
0 5 10 15 20 25 30
No. of blows

SIEVE ANALYSIS LINEAR SHRINKAGE

Sieve size Wt/Rt %Pass Mould number — —

No.10 2.00 mm — — Initial length L0(mm) — —

No.40 0.425 mm — — Oven-dried length LD(mm) — —

No.200 0.075 mm — —
Linera Shrinkage,LS=100(1-
— —
LD/L0) (%)
Liquid Limit -

Plastic Limit - Average %

Plasticity Index NON-PLASTIC

Group Index
Soil Classification

Contractor's Materials Engineer Engineers Assistant Materials Engineer


FISH TOWN - HARPER ROAD PROJECT PHASE 1
Paving of Harper - Karloken (50km) and Maintenance of Karloken to
Fish Town (80km)

DETERMINING THE LIQUID LIMIT & PLASTICITY INDEX &LINEAR SHRINKAGE OF SOILS

Sample Source: Crushed Stone Base, CREC Yard, Bpit Quality Control Date: 19-Oct-17
Sample Designation: Km 2+040 - 2+120 RHS
Material Description: Base Layer Along

LIQUID LIMIT PLASTIC LIMIT


Container number
Number of blows
Wt.of Container +Wet soil (g)
Wt.of Container +Dry soil (g)
Wt.of water (g)
Wt.of Container weight (g)
Wt.of Dry soil (g)
Moisture content (%)
Average ( %) — — — — -

41

40.5

40

39.5
Moisture content %

39

38.5

38

37.5

37

36.5

36
0 5 10 15 20 25 30
No. of blows

SIEVE ANALYSIS LINEAR SHRINKAGE

Sieve size Wt/Rt %Pass Mould number — —

No.10 2.00 mm — — Initial length L0(mm) — —

No.40 0.425 mm — — Oven-dried length LD(mm) — —

No.200 0.075 mm — —
Linera Shrinkage,LS=100(1-
— —
LD/L0) (%)
Liquid Limit -

Plastic Limit - Average %

Plasticity Index NON-PLASTIC

Group Index
Soil Classification

Contractor's Materials Engineer Engineers Assistant Materials Engineer


FISH TOWN - HARPER ROAD PROJECT PHASE 1
Paving of Harper - Karloken (50km) and
Maintenance of Karloken to Fish Town (80km)

CBR COMPACTION

Sample Source: Crushed Stone Base, CREC Yard, Bpit Quality Control
Date: 19/10/2017
Sample Designation: Km 2+040 - 2+120 RHS
Sample Description: Base Layer Along

C.B.R.

56 BLOWS 25 BL0WS 10 BLOWS


Crushed Stone Base, CREC Yard, Bpit Quality Control
Mass air - dry sample ( g ) 5000 5000 5000
Mass Water added (g ) 150.0 150.0 150.0
Percent water added ( % ) 3.0 3.0 3.0
Estimated air - dry MC. ( % ) 0.2 0.2 0.2
Est. compaction MC. (%) 3.2 3.2 3.2
Mould Number. 3 2 1
Volume of Mould 2177 2177 2177
Mass of Mould (g) 4338 4317 4281
Mass Mould + Wet Soil. (g) 9344 9018 8894
Mass Wet Soil. (g) 5006 4701 4613
Wet Density. Kg/cu. M. 2.299 2.159 2.119
APPROX. Dry Density 2.228 2.092 2.053
Moisture Content Determination
Oven - Pan Number. 3 2 1
Mass Oven - Pan. (g) 183.5 188.3 188.7
Mass Oven - Pan + Wet Soil. (g) 755.6 1105.8 486.1
Mass Oven - Pan + Dry Soil. (g) 735.5 1074.3 475.7
Mass of water. (g) 20.1 31.5 10.4
Mass Dry Soil (g). 552.0 886.0 287.0
Moisture Content (%) 3.7 3.6 3.6
Back Calc. Air dry M.C. (%) 0.5 0.4 0.4
Dry Density 2.219 2.085 2.045

Contractor's Materials Engineer Engineers Assistant Materials Engineer


FISH TOWN - HARPER ROAD PROJECT PHASE 1
Paving of Harper - Karloken (50km) and Maintenance of
Karloken to Fish Town (80km)

CBR PENETRATION DATA

Sample Source: Crushed Stone Base, CREC Yard, Bpit Quality Control Date: 23/10/2017
Sample Designation: Km 2+040 - 2+120 RHS
Sample Description: Base Layer Along

CBR LOAD RING NUMBER LOAD RING FACTOR:(KN/DIV ) = 0.2182


STANDARD LOAD: 0.1 mm = 13.24
13.34 STANDARD LOAD: 0.2mm = 19.96
MOULD NO.
NO. OF BLOWS 10 25 56
CALIFORNIA BEARING RATIO

CALIFORNIA BEARING RATIO

CALIFORNIA BEARING RATIO


CORRECTED FORCE KN

CORRECTED FORCE KN

CORRECTED FORCE KN
STANDARD FORCE KN

FORCE READING KN

FORCE READING KN

FORCE READING KN
PENETRATION(mm)

0.00 0 0 0 0.00 0 0 0
0.50 9 14 22 0.50 9 14 2
1.00 20 28 27 1.00 20 28 2
1.50 28 36 47
2.00 39 47 68
2.50 13.34 46 46 75.2 59 59 96.5 80 80 130.9
3.00 54 69 92
3.50 67 79 105
4.00 77 86 119
4.50 85 96 132
5.00 19.96 91 91 99.5 109 109 119.2 144 144 157.4
5.50 97 117 159
6.00 102 128 172
6.50 111 142 186

200
190 56 blows
180
170 25 blows
160
150
140
130
120
CBR ( % )

110
100 10 blows
90
80
70
60
50
40
30
20
10
0
0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00

PLUNGER PENETRATION ( mm )
Contractor's Materials Engineer Engineers Assistant Materials Engineer
FISH TOWN - HARPER ROAD PROJECT PHASE 1
Paving of Harper - Karloken (50km) and
Maintenance of Karloken to Fish Town (80km)
CBR DATA

Sample Source: Crushed Stone Base, CREC Yard, Bpit Quality Control Date: 23/10/2017
Sample Designation: Km 2+040 - 2+120 RHS
Sample Description: Base Layer Along

CBR DATA FORM OPERATOR :

MODIFIED COMPACTION. MDD : = 2.21 OMC : = 3.2


MOULD NUMBER M27 M28 M5
NO. OF LAYERS 5 5 5
NO OF BLOWS PER LAYER 56 25 10
CONDITION COMPACTED SOAKED COMPACTED SOAKED COMPACTED SOAKED

MASS OF MOULD (g) 4338 4338 4317 4317 4281 4281

MASS OF MOULD + WET SOIL (g) 9344 9207 9018 8915 8894 8752

MASS OF WET SOIL (g) 5006 4869 4701 4598 4613 4471

COMPACTION MOISTURE CONTENT (%) 3.2 3.2 3.2

MASS DRY SOIL (g) 4851 4555 4470

MC AFTER SOAKING (g) 0.4 0.9 0.0

SWELL

INITIAL READING, ( mm ) 0 0 0
FINAL READING AFTER 4 DAY SOAK, (
mm ) 0 0 0

SWELL : mm / % 0 0 0

CBR

COMPACTED DRY DENSITY 2.219 2.085 2.045

RELATIVE COMPATION, %MDD. 100 94 93

CBR @ 0.1 PENETRATION. 131 97 75

CBR @ 0.2 PENETRATION. 157 119 99

Contractor's Materials Engineer Engineers Assistant Materials Engineer


FISH TOWN - HARPER ROAD PROJECT PHASE 1
Paving of Harper - Karloken (50km) and
Maintenance of Karloken to Fish Town (80km)

GRAPH OF CBR AGAINST RELATIVE DENSITY


180.0

160.0

140.0

120.0

100.0
CBR ( % )

80.0

60.0

40.0

20.0

0.0
83 85 87 89 91 93 95 97 99 101 103

RELATIVE COMPACTION ( % )

MDD @
CBR @ 98% M.D.D = 142 2.166 100 94 93
CBR @ 95% M.D.D = 124 2.100 157.4 119.2 99.5
CBR @ 93% M.D.D = 104 2.055

Contractor's Materials Engineer Engineers Assistant Materials Engineer


FISH TOWN - HARPER ROAD PROJECT PHASE 1
Paving of Harper - Karloken (50km) and
Maintenance of Karloken to Fish Town (80km)

ORGANIC CONTENT DETERMINATION

Sample Source: Crushed Stone Base, CREC Yard, Bpit Quality Control Date: 23/10/2017
Sample Designation: Km 2+040 - 2+120 RHS
Sample Description: Base Layer Along
Test 1 Test 2
Porcelaine no 1 2
Mass of container (g) 584 584
Mass of container plus oven dry sample (g) 1729 1223
Mass of container plus muffled furnace sample (g) 1729 1223
organic content (%) 0.0 0.0
Average Organic Content (%) 0.0

Contractor's Materials Engineer Engineers Assistant Materials Engineer