You are on page 1of 2

Project : BADR Phase 01

Employer : M/s Dubai Islamic Bank


Engineer : M/s LACASA Architects & Engineering Consultants
Main Contractor : M/s Engineering Contracting Co. L.L.C.
MEP Contractor : M/s Al Arabia Electromechanical Contracting L.L.C.

Rate Derivation for Bidet-Wall Hung with Bracket


BOQ Rate (Bidet-Floor Standing, rate ref. B1/QA1/Item G) used as basis.

Bidet-Floor Standing Bidet-Wall Hung with Bracket


SI. No. Description
BoQ rate % Factor (Assumed)
Amount Amount
[A] [B] [D]

1 Material and Accessories - - - - -

1 Skilled Labor x 3.8 Hrs 2 Skilled Labor x 6 Hrs


76.00 240.00
@AED 20/Hrs @AED 20/Hr
2 Unskilled Labor x 3.8 Hrs 2 Unskilled Labor x 6 Hrs
2 Labor 121.60 192.00
@AED 16/Hr @AED 16/Hr

79.04% 197.60 Total Labor 432.00


250.00
3 Plant & Tools (10% of items 2) 7.90% 19.76 43.20

4 OH & P (15% of items 2 & 3) 13.04% 32.60 71.28

5 Rest of OHP 0.01% 0.04 1.00 0.04

Total 100.00% 100.00% 250.00 546.52


RBU-BD-01

Wall Hung with Bracket

Remarks

Cost of 1 Skilled Labor = AED 20/Hr

Cost of 1 Unskilled Labor= AED


16/Hr

Plant & Tools is calculated as 10% of


items 2
OH & P is calculated as 15% of items
2&3
Factor assumed as same as in Bidet-
Floor Standing