Professional Documents
Culture Documents
The PoA is operated and implemented by PT. Blue World Indonesia (hereinafter referred to as “BWC”).
BWC is the “Coordinating / Managing Entity” (hereinafter referred to as “CME”).
The CPA complies with the following project scenario(s) (referred to as scenario throughout this
document) as described in the PoA-DD:
Table I.A.3.1 - Description of the small-scale CDM programme activity technology scenario
Project Scenario Description of scenario
1 Biogas plants installed at new (Greenfield) facilities
2 Biogas plants installed at existing facilities
E Utilization of biogas for grid connected power generation (in combination with
scenario 1 or 2)
CPA that utilize biogas for the production of electricity can optionally select scenario E to be able to
claim the emission reduction due to exported of electricity to the grid.
The CPA will contribute to climate change mitigation efforts through the reduction of Green House
Gases (GHG) emissions through introduction of technology that captures and subsequently utilizes or
destroys methane released during wastewater treatment. In the baseline situation the methane would be
released into the atmosphere.
In addition to the above, CPA that also select project scenario E implement the following measure:
Technology / measures employed: a new small-scale renewable power plant.
Type: renewable energy projects
Category: I.D: “Grid connected renewable electricity generation”; Version 17, EB 61, Sectoral Scope
01.
The CPA will contribute to climate change mitigation efforts through the reduction of Green House
Gases (GHG) emissions through displacement from of more carbon intensive power generation in the
grid.
The CME has considered the CPA in the PoA. For inclusion it has obtained the mandate from the CPA
Implementer.
(a) A list and the arrangement of the main manufacturing/production technologies, systems
and equipment involved.
The proposed CPA project activity will convert the existing effluent treatment system into one efficient
covered bio digester with methane collection point. An enclosed flare will be installed to combust the
biogas for the first year and will combust the excess gas when the biogas could not be used for electricity
generation in the second year onwards. The biogas run gensets for a total capacity of 1 MW will be
installed to generate electricity to be exported to the nearest grid (Sumatera Grid).
Item Type/Brand
Cover Geo Membrane HDPE
Base lining Geo Membrane HDPE
Flare system + additional Kobar Flare / KF-GF-XX
Sistem monitoring MARIS
Gas engine + additional *) MARIS
Lifetime of the equipment 15 years
Overhaul of Gas Engine/Flare 8000 hour
UNFCCC/CCNUCC
(b) Energy and mass flows and balances of the systems and equipment included in the CPA;
The specifications of the main equipment for wastewater treatment that are implemented under the
project activity are as follows:
(d) Facilities, systems and equipment in operation under the existing scenario prior to the
implementation of the CPA;
The existing situation on baseline scenario is using the open lagoon as the conventional wastewater
treatment at palm oil mill in Indonesia.
In the baseline, the wastewater is treated in an open lagoon system where methane is emitted as a result
of anaerobic digestion. The palm oil mill and open lagoon system are existing facilities.
The baseline scenario for power generation is grid connected electricity generation in the Thai national
grid. The CPA will displace electricity generation in the baseline.
3
Unit Dimensions Volume (M )
The baseline scenario is a continuation of current practice, thus identical to the scenario existing prior to
the implementation of the CPA.
A.6. Party(ies)
Private and/or public
Indicate if the Party involved
Name of Party involved (host) entity(ies) CPA
wishes to be considered as
indicates a host Party implementer(s)
CPA implementer (Yes/No)
(as applicable)
Private Entity: PT. Blue World
Indonesia (host) No
Indonesia
Private Entity: Blue World
Netherlands No
Carbon SEA Pte Ltd
As per PoA section C, the identification parameters as per table I.A.7.1 are required for each CPA.
Confirmation that the start date of this CPA is not before DD/MM/YYYY (date of commencement of
PoA validation).
It has been demonstrated that this CPA included in the PoA is not a debundled component of another
CDM Programme of Activities or another CDM Project activity. The following approach has been
applied as per the guidance for determining the occurrence of de bundling under a Programme of
Activities (EB 54, Annex 13):
Para 8. For the purposes of registration of a Programme of Activities (PoA)1 a proposed small-scale
CPA of a PoA shall be deemed to be a de-bundled component of a large scale activity if there is already
an activity2, which satisfies both conditions (a) and (b) below:
(a) Has the same activity implementer as the proposed small scale CPA or has a Coordinating or
Managing entity, which also manages a large scale PoA of the same technology/measure, and;
Substantiation: Neither the CPA Implementer (PT. Maris Sustainable Indonesia) nor the CME (BWC)
have implemented a large scale PoA/CDM Project activity of the same technology/measure.
(b) The boundary is within 1 km of the boundary of the proposed small-scale CPA, at the closest point.
Substantiation: As the CPA implementer and the CME have not implemented a large scale PoA/CDM
Project activity of the same technology/measure this condition is not applicable.
Substantiation: As the CPA implementer and the CME have not implemented a PoA/CDM Project
activity of the same technology/measure this condition is not applicable.
Para 10. If each of the independent subsystems/measures (e.g. biogas digester, solar home system)
included in the CPA of a PoA is no larger than 1% of the small scale thresholds defined by the
methodology applied 4 , than that CPA of PoA is exempted from performing de-bundling check i.e.
considered as being not a de-bundled component of a large scale activity.
Substantiation: Not applicable to this CPA as the measure is larger than 1% of the small scale thresholds
defined by the methodology applied.
1
Only those POAs need to be considered in determining de-bundling that are: (i) in the same geographical area; and (ii) use the
same methodology; as the POA to which proposed CPA is being added
2
Which may be a (i) registered small-scale CPA of a PoA, (ii) an application to register another small-scale CPA of a PoA or
(iii) another registered CDM Project activity
3
Limits have been revised as set in paragraph 28 of decision 1/CMP.2
4
i.e. 450 kW thermal installed capacity
UNFCCC/CCNUCC
Based on the above description, the proposed small scale CPA under PoA is not deemed to be de-bundled
component of a large-scale activity, therefore is eligible to use the simplified modalities and procedures
for small-scale project activities. The CPA implementer PT. Maris Sustainable Indonesia has given a
declaration to CME that the Project activity is not a debundled component of large scale Project.
The CME confirms that the CPA is not a de-bundled component of large scale Project activity.
Environmental impacts of the biogas project are expected to occur in different stages from pre-
construction, construction stage, operational and post-operational stage. In pre-construction stage, no
significant impact is expected. The company will have to engage employees and people living nearby to
communicate the project idea, the benefit of electricity supply it will bring and possible negative impacts.
Construction stage will give positive impact to the community for it creates job opportunities. Some of
the local villagers will be involved during this phase. It is expected that members of the local community
will be employed as unskilled workers during the construction phases of the project.
Transportation of equipment and material might cause damage to the roads surrounding the project
location. The magnitude of the construction is small and therefore the impact is considered smaller or
insignificant. Transportation activity might also emit pollutants, dust and noise. The scale of the impact
is considered minor. Construction of biogas plant and its facilities might also emit pollutants, dust and
noise. It is considered significant notably to construction workers, mill and estate workers and their
family who live in the surrounding. The company will have to control and monitor these impacts on a
regular basis.
Operational stage of the project will include the activities of methane capture, operation of biogas plant,
power generation.
Possible impact that might occur is gas leakage and explosion. The company has to carefully control and
monitor the safety procedures to prevent leakage and explosion. All operation and maintenance of the
biodigester will be undertaken by trained personnel working for the technology provider. This will ensure
optimal operation.
Additional small number of employees involved in power plant operation will not give significant
impact. The impact from maintenance activity is also considered insignificant.
UNFCCC/CCNUCC
A presentation was delivered by CDM Consultant (BWC), Project Owner (PT. MSI), Manager Mill
(PTPN VII) during the meeting on the CDM, sustainability criteria and an overview of the Kyoto
Protocol, Technical aspects of the biogas project were also described together with the methane recovery
details for the mill. It was also described how the implementation of the project can save GHG emissions
by avoiding the usage of diesel for power generation and can also create job opportunities for local
people. Representatives of the local government believed that the project will reduce GHG emission
globally and locally improve the working conditions at the mill and claimed that, together with the
private sector and local communities, they are ready to further support national programs that reduce
GHG emissions locally.
Answer:
- OK, we take into consideration of this suggestion.
- Thank you for all of suggestion and supporting for the project.
5
The number in front of each paragraph indicates the respective paragraph of AMS.III.H Version 16.
6
Other technologies in Table 6.3 of Chapter 6: Wastewater Treatment and Discharge of 2006 IPCC Guidelines for
National Greenhouse Gas Inventories are included.
UNFCCC/CCNUCC
7
Source: “Sekilas Lintas Kabupaten Lampung Tengah” page 6
8
For example combusted in a prime mover such as an engine coupled to a machine such as grinding machine.
UNFCCC/CCNUCC
Projects that have selected scenario E (utilization of biogas as fuel for power generation and export to the
grid) shall also comply with the applicability conditions of AMS.I.D Version 17. Demonstration of the
applicability or a typical CPA is described below:
9
The number in front of each paragraph indicates the respective paragraph of AMS.I.D Version 17.
10
Refer to EB 23, annex 18 or the definition of renewable biomass.
11
AMS-I.D “Grid connected renewable electricity generation”, AMS-I.F “Renewable electricity generation for
captive use and mini-grid” and AMS-I.A “Electricity generation by the user”
12
A capacity addition is an increase in the installed power generation capacity of an existing power plant through:
(i) The installation of a new power plant besides the existing power plant/units; or (ii) The installation of new
power units, additional to the existing power plant/units. The existing power plant/units continue to operate after
the implementation of the project activity.
13
Retrofit (or rehabilitation or refurbishment). It involves an investment to repair or modify an existing power
plant/unit, with the purpose to increase the efficiency, performance or power generation capacity of the plant,
without adding new power plants or units, or to resume the operation of closed (mothballed) power plants. A
retrofit restores the installed power generation capacity to or above its original level. Retrofits shall only include
measures that involve capital investments and not regular maintenance or housekeeping measures.
14
Replacement. It involves investment in a new power plant or unit that replaces one or several existing unit(s) at
the existing power plant. The installed capacity of the new plant or unit is equal to or higher than the plant or unit
that was replaced.
UNFCCC/CCNUCC
§5: If the new unit has both renewable and non- the installed capacity generator of the
renewable components (e.g. a wind/diesel unit), the project activity is 1 MW
eligibility limit of 15 MW for a small-scale CDM Hence meet the criteria
project activity applies only to the renewable
component. If the new unit co-fires fossil fuel, the
capacity of the entire unit shall not exceed the limit of
15 MW.
§6: Combined heat and power (co-generation) The project activity producing power only
systems are not eligible under this category.
Hence meet the criteria
§7: In the case of project activities that involve the The project activity is new facility of
addition of renewable energy generation units at an generating unit
existing renewable power generation facility, the Hence meet the criteria
added capacity of the units added by the project
should be lower than 15 MW and should be
physically distinct from the existing units.
§8: In the case of retrofit or replacement, to qualify as The project activity is new facility of
a small-scale project, the total output of the retrofitted generating unit.
or replacement unit shall not exceed the limit of 15 Hence meet the criteria
MW.
§25: In the specific case of biomass project activities Not applicable to the proposed CPA
the applicability of the methodology is limited to
either project activities that use biomass residues only
or biomass from dedicated plantations complying
with the applicability conditions of AM0042.
§26: In the specific case of biomass project activities Not Applicable to the proposed CPA
the determination of leakage shall be done following
15
A reservoir is a water body created in valleys to store water generally made by the construction of a dam.
16
A reservoir is to be considered as an “existing reservoir” if it has been in operation for at least three years before
the implementation of the project activity.
UNFCCC/CCNUCC
Table I.D.3.1 Emission sources and gases included in the SSC-CPA boundary
Source Gas Included Justification
Decay emissions from CO2 No Excluded for simplification.
the baseline wastewater CH4 Yes Major emission source in case of wastewater
treatment system treatment plants.
N2O No Excluded for simplification.
Decay emissions from CO2 No Excluded for simplification.
the baseline sludge CH4 No Sludge treatment is not included in the boundary
Baseline Scenario
treatment system
N2O No Excluded for simplification.
Emissions on account CO2 Yes May be an important source of emission if the
of electricity or fossil baseline involves the use of electricity or fossil
fuel used fuels.
CH4 No Excluded for simplification.
N2O No Excluded for simplification.
Emissions from the CO2 No Excluded for simplification.
discharge of the effluent CH4 Yes Major emission source in case of wastewater being
into river/lake/sea discharged to sea/river/lake.
N2O No Excluded for simplification.
Emissions from CO2 No Excluded for simplification.
17
Available on <http://cdm.unfccc.int/methodologies/SSCmethodologies/approved.html>.
UNFCCC/CCNUCC
The emission sources and gases below only need to be included in the boundary for CPA that comply
with technology scenario E (Utilization of biogas for grid connected power generation):
The CPA complies with technology scenario E, the tables below have been completed
The CPA does not comply with technology scenario E, the tables below have not been completed.
According to “Indicative simplified baseline and monitoring methodologies for selected small scale
CDM project activity categories, AMS-I.D., Version 17, EB 61, 3 June 2011, the spatial extent of the
CPA its project boundary includes the physical and geographical site of the renewable generation source
that includes the biogas power plant as well as the sub-station connection to the relevant electricity grid
(a regional grid system). Figure E.3.1 shows the project flowchart and its boundaries.
Table E.3.2 Emission sources and gases included in the SSC-CPA boundary for scenario E
Source Gas Included? Justification / Explanation
UNFCCC/CCNUCC
Baseline CO2 emission from electricity CO2 Included Main emission source
generation in fossil fuel fired CH4 Excluded Minor emission source.
power plants that are N2O Excluded Minor emission source.
displaced due to the project
activity
CO2 Included May be an important emission
CPA Projgrame
Treated wastewater
In the baseline scenario of the existing palm oil mill the wastewater is treated in an open anaerobic
lagoon system. Hence, based on the paragraph above, the baseline is continuation of the existing open
lagoon system with associated methane emissions.
The baseline scenario is in compliance with host country regulations for wastewater treatment and the
CPA implementer is not
Since the CPA also applies technology scenario E the baseline shall be also defined as follows:
In accordance with AMS-I.D version 17, paragraph 10, the baseline scenario is that the electricity
delivered to the grid by the project activity would have otherwise been generated by the operation of
grid-connected power plants and by the addition of new generation sources into the grid.
The compliance of the CPA with the eligibility criteria is outlined in the table below:
18
To be confirmed at CPA level by the CME
UNFCCC/CCNUCC
P. Confirmation on the crediting period of the Confirmation described in the SSC-CPA-DD Yes Confirmation of the same has
SSC-CPA which shall not exceed the length that states that the crediting period of the SSC- been indicated in the CPA-
of the PoA (28 years) regardless of the time CPA shall not exceed the length of the PoA. No DD.
of inclusion of CPA in the PoA
Q. The CPA shall not involve biomass storage The following document shall be provided: Yes As per information provided in
under anaerobic conditions. Declaration from the CPA Implementer that the FSR the project does not
the CPA does not involve biomass storage No involve storage of biomass in
under anaerobic conditions. any case.
The eligibility criteria below only need to be completed for CPA that comply with technology scenario E (Utilization of biogas for grid connected power
generation):
The CPA complies with technology scenario E, the tables below have been completed
The CPA does not comply with technology scenario E, the tables below have not been completed.
UNFCCC/CCNUCC
>>
The assessment and demonstration of additionality of the CPA has been based on the criteria
mentioned in the section E.5.1 of the PoA-DD. The Additionality for the CPA is demonstrated by:
As prescribed in the simplified modalities and procedures of small scale CDM Project activities, the
Project can demonstrate the additionality as per any of the prescribed approaches. Therefore, the
approach(es) selected above shall be completed below for the specific CPA and the remaining
approach(es) does not have to be completed.
The additionality for the SSC-CPA is demonstrated by Approach [B], applicable for the Project
activity.
All small scale projects may follow the approaches defined in Attachment A to Appendix B to Annex
II of 4/CMP.1 (“Attachment A”) to prove additionality. Herein all CPAs will have to demonstrate the
presence of an investment barrier, i.e. a financially more viable alternative to the project activity
would have led to higher emissions
The detailed investment calculation, indicating all assumptions will be provided to the DOE at time of
inclusion of the CPA.
The investment analysis will be based on the project details considered by the board when
approving the investment in the project. Therefore, the inputs to the investment analysis will be
considered relevant to the timing of the investment decision.
2. Apply Benchmark Analysis: Sub Step 2b: Step 2b Option III (Benchmark Analysis) of the
Option III of the Tool for the demonstration and Tool for the Demonstration and assessment of
assessment of additionality. additionality, Version 6.0.0 will be applied.
UNFCCC/CCNUCC
3. Identify the financial/economic indicator, such as The CPA will apply the Project IRR
IRR, most suitable for the project type and decision
context.
4. Determine financial benchmark The benchmark for Project IRR is calculated as per
Guidance on the Assessment of Investment
Analysis Version 05, the default value for the
expected return on equity shown below are
calculated after taxes in Indonesia for group 1
(waste handling and disposal and energy industries.
The benchmark is 12.5%.
5. Present a clear comparison of the financial indicator As per financial analysis the IRR of the project is
and the financial benchmark. If the CDM project 2.30%, which is lower than the benchmark of
activity has a less favourable indicator (e.g. lower 12.5%.
IRR) than the benchmark, then the CDM project
activity cannot be considered as financially
attractive.
6. Include a Sensitivity Analysis to show that the Please refer to table B.5.7 – investment analysis
conclusions regarding the financial/economic outcome for the sensitivity analysis.
attractiveness are robust to reasonable variations in
the critical assumptions. After the sensitivity
analysis, it must be concluded that the proposed
CDM project activity is unlikely to be
financially/economic attractive.
7. Determine sources of data for calculating the The benchmark for Project IRR is calculated as per
benchmark Guidance on the Assessment of Investment
Analysis Version 05, the default value for the
expected return on equity shown below are
calculated after taxes in Indonesia for group 1
(waste handling and disposal and energy industries.
8. Calculation and comparison of financial indicators The investment analysis is based on the information
provided in the FSR of the project and describes the
method of calculation in a transparent manner.
Key criteria and data required for assessing the additionality of the CPA are summarised below.
2. Yearly Methane Nm3/year 1.328.262 Nm3/year. Based on available data at the time of
Production (Optional) investment decision. This is based on the Third Feasibility
Study.
3. Yearly Electricity MWh/year 3,699,034 kWh/year. Based on available data at the time of
Production (Optional) investment decision. This is based on the Third Feasibility
Study.
4. Percentage of Biogas % 0%. Based on available data at the time of investment decision.
Flared This is based on the Third Feasibility Study.
8. Residual value of IDR Base on national accounting practices for depreciation, where
equipment the equipment is fully depreciated by the end of the lifetime of
the asset, the value is zero.
11. Conversion Rate €/IDR dan € 1 = Rp 11.000 (exchange rate that was applied in
feasibility study report)
12. CPI (O&M escalation % This may include one of the following:
rate) (a) Estimates of national CPI
(b) Investment Memorandum
(c) Escalation as agreed in contract
13. Percentage of Debt % Debt portion 50.0%
Financing
16. Total Operation and IDR 1,061,387,500 IDR/year (Third Party feasibility study)
Maintenance Cost
17. Operational Lifetime Years 15 years (Third Party feasibility study)
(Supply Period)
The PoA investment spread sheet template is applied to the CPA to demonstrate that the project
is not financially feasible without the revenue from CERs. The outcomes of the financial analysis
spread sheet are shown below:
Table B.5.7 – investment analysis outcome
The results of the financial analysis spreadsheet demonstrate that the project is not financially
feasible without the revenue from CERs. The financial analysis is robust to reasonable variations of
+10% and -10% in the critical assumptions, as is shown in the table below:
UNFCCC/CCNUCC
For CPA that generate electricity from biogas with an installed capacity of 10 MW or less, the power
tariff is affected by MEMR No.31/2009, identified as an E- policy. Hence, according the EB 65
(annex 5) paragraph 44, the power tariff applied for the purpose of the investment analysis is selected
to accurately reflect the Host Country regulations that were in effect as of 11/11/2001 and shall
exclude the introduction of the identified E- policy. On that basis, CPAs under this PoA with less than
10 MW installed capacity have the option to not account for the impacts of MEMR No.31/2009 and
conduct all analysis as if the policy did not exist.
As an approach in determining the power tariff in the hypothetical case without the E- policy in place
the following methodology is applied: The power tariff is determined on the basis of available
empirical data of similar biogas power plants that supply power to the same regional electricity
system as the CPA
Documentation relevant to substantiation of the investment barrier shall be provided to the DOE at
time of inclusion
Conclusion
In accordance with the benchmark analysis, if the financial indicators (such as the IRR) of a project
are lower than the benchmark, the project is not considered to be financially attractive. From the table
above it is clear that the project activity is not financially viable with only the cost savings arising
from diesel and shell consumption as the IRR for the project activities calculated over a period of 15
years without CDM benefit is 2.3%. This is lower than the chosen benchmark (10.94%) and therefore
the proposed project is not financially attractive.
Based on the above analysis it can be concluded that the specific CPA titled “CPA 1.1 – Maris –
PTPN VII Biogas Project” is therefore additional and eligible for inclusion as per eligibility criteria
specified in the registered PoA-DD.
Baseline Emissions
UNFCCC/CCNUCC
Baseline emissions will include greenhouse gas (GHG) emissions associated with the following
sources:
(a) Emissions associated with electricity or fuel consumption in the baseline wastewater treatment
system- The CPA will follow the “Tool to calculate baseline, project and/or leakage emissions for
electricity consumption” and/or “Tool to calculate project or leakage emissions for fossil fuel
combustion” for calculating emissions associated with electricity or fuel consumption.
(b) Emissions associated with baseline wastewater treatment not equipped with a biogas recovery
system and which is affected by the project activity treatment system- organic content in the
wastewater will be decomposed in the baseline treatment system and would result in generation of
methane. Since the baseline wastewater system is not equipped with methane recovery system, it will
result in GHG emissions into the atmosphere. Baseline emissions will account for this source of
emissions.
(c) Emissions associated with discharge of treated wastewater into sea/river/lake- this is in relation to
the amount of chemical oxygen demand (COD) present in the wastewater even after being treated by
the baseline wastewater system. If such treated wastewater is discharged to downstream such as
sea/river/lake, baseline emissions to account for the un-removed COD in the treated wastewater.
(d) Emissions associated with anaerobic decay of final sludge- if in the baseline scenario, the sludge
is allowed to decay under anaerobic conditions it will result in generation of methane which will be
emitted into the atmosphere, baseline emissions will account for this source of emissions.
In determining the baseline emissions, past historic records (e.g. COD removal efficiency of the
wastewater treatment systems, the amount of dry matter in sludge, power and electricity consumption
per m3 of wastewater treated, the amount of final sludge generated per tonne of COD removed) of at
least one year prior to the project implementation shall be used. If the historical data is not available
or for the case of Greenfield projects and capacity addition projects, a baseline measurement
campaign should be undertaken for at least 10 days before project implementation. The average
values from the measurement campaign shall be multiplied by 0.89 to account for the uncertainty
range (30% to 50%) and used for estimating emissions associated with the prevailing baseline.
For the existing plant without the historical data, the baseline emissions in year y are taken as the
minimum between the result of:
(a) All the available data in determining the required parameters, and
(b) Ex-ante calculation from the aforementioned measurement campaign.
The approach (e.g. past historic records, 10-day measurement campaign, value from
manufacturer/designer) and the associated data which are selected and applied in determining the
baseline emissions shall be recorded under Annex 3 of the CPA-DD.
UNFCCC/CCNUCC
Unit -
Description Methane correction factor for baseline wastewater treatment system i
Source of data Table III.H.1 of AMS-III.H (version 16)
Value(s) applied 0.8
Choice of data In line with the requirement of the baseline and monitoring methodology
or
Measurement
methods and
procedures
Purpose of data The data is used to estimate the baseline emission.
Additional comment
Data / Parameter F
Unit -
Description Fraction of CH4 in biogas
Source of data IPCC default value as per paragraph 22 of AMS-III.H version 16
Value(s) applied 0.5
Choice of data In line with the requirement of the baseline and monitoring methodology
or
Measurement
methods and
procedures
Purpose of data The data is used to estimate the project emission.
Additional comment
Data / Parameter DF
Unit -
Description 10-day measurement campaign factor to account for the uncertainty range
(30% to 50%)
Source of data As per AMS-III.H (version 16) paragraph 27
Value(s) applied 0.89
Choice of data In line with the requirement of the baseline monitoring methodology
or
Measurement
methods and
procedures
Purpose of data The data is used to estimate the baseline emission.
Additional comment
UNFCCC/CCNUCC
Total emission reductions of the CPA will be calculated as a sum of emission reductions from
methane recovery in wastewater treatment (technology scenario 1 and 2) and optionally emission
reduction obtained through combustion of recovered methane for electricity generation (scenario E).
Where:
ERy = Total emission reductions of the project in year y (tCO2e/year)
ERgrid,y = Emission reductions from electricity generation in year y (tCO2e/year)
ERmethane,y = Emission reductions from methane recovery in wastewater treatment in year y
(tCO2e/year)
Below are the methodological choices used for calculating emission reductions baseline and
monitoring methodology AMS-III.H “Methane Recovery in Wastewater Treatment” (version 16).
Provide explanation in case the emission source is excluded and indicate respective emissions as 0.
Included? Parameter Explanation Value Unit
BE methane, y Baseline emissions from methane recovery in 18,533 tCO2e/yr
wastewater treatment in year y
Yes 0 tCO2e/yr
BE power, y Baseline emissions from electricity or fuel
NO consumption in year y.
Yes 18,533 tCO2e/yr
BE ww,treatment, y Baseline emissions of the wastewater treatment
NO systems affected by the project activity in year y
Yes 0 tCO2e/yr
BE s ,treatment, y Baseline emissions of the sludge treatment
NO systems affected by the project activity in year y.
Provide explanation in case the emission source is
excluded.
Yes 0 tCO2e/yr
BE ww,discharge,y Baseline methane emissions from degradable
NO organic carbon in treated wastewater discharged
into sea/river/lake in year y. The wastewater will
be discharged to Land Application
Yes 0 tCO2e/yr
BE s , final, y Baseline methane emissions from anaerobic decay
NO of the final sludge produced in year y. Provide
explanation in case the emission source is
UNFCCC/CCNUCC
excluded.
ii. Methane emissions from baseline wastewater treatment systems (BE ww,treatment,y );
Methane emissions from the baseline wastewater treatment systems affected by the project
(BEww,treatment,y) are determined using the COD removal efficiency of the baseline plant. The baseline
for the CPA is [description of the baseline. As such baseline emissions are calculated as follows:
The COD removal efficiency has been calculated as simple average value based on historic records
from the existing baseline system.
iii. Methane emissions from baseline sludge treatment systems (BE s,treatment,y );
Methane emissions from the baseline sludge treatment systems affected by the project activity are
determined using the methane generation potential of the sludge treatment systems:
UNFCCC/CCNUCC
To determine CODww,discharge,BL,y: if the baseline treatment system(s) is different from the treatment
system(s) in the project scenario, the monitored values of the COD inflow during crediting period will
be used to calculate the baseline emissions ex post. The outflow COD of the baseline systems will be
estimated using the removal efficiency of the baseline treatment systems, estimated as per paragraphs
26, 27 or 28 of AMS.III.H. A description of this will be provided here and if applicable also in annex
3 of the CPA-DD.
v. Methane emissions from the decay of the final sludge generated by the baseline
treatment systems (BE s,final,y ).
In case this baseline source is excluded/disregarded: Therefore: BE s,final,y = 0 tCO2e
Where:
Included? Parameter Description Value Unit
PE methane, y Project activity emissions from methane 3,465 tCO2e/yr
recovery in wastewater treatment in the year y
Yes PE power, y Emissions from electricity or fuel consumption 0 tCO2e/yr
NO in the year y
Yes PEww,treatment, y Methane emissions from wastewater treatment 0 tCO2e/yr
NO systems affected by the project activity, and
not equipped with biogas recovery, in year y
Yes PEs ,treatment, y Methane emissions from sludge treatment 0 tCO2e/yr
NO systems affected by the project activity, and
not equipped with biogas recovery, in year y.
Yes PEww,discharge, y Methane emissions from degradable organic 0 tCO2e/yr
NO carbon in treated wastewater in year y
Yes PE s , final, y Methane emissions from anaerobic decay of 0 tCO2e/yr
NO the final sludge produced in year y.
Yes PE fugitive, y Methane emissions from biogas release in 2,166 tCO2e/yr
NO capture systems in year y
Yes PE flaring, y Methane emissions due to incomplete flaring 1,299 tCO2e/yr
NO in year y.
Yes PEbiomass, y Methane emissions from biomass stored under 0 tCO2e/yr
NO anaerobic conditions
(i) CO2 emissions from electricity and fuel used by the project facilities ( PE power, y );
In case electricity is generated with biogas:
PE power,y = 0 tCO2e
Description of the determination for the emission factor EFEL,j,y and for the Average technical
transmission and distribution losses for providing electricity to source j in year y(TDLjy), CPAs of the
PoA shall consider the default value as mentioned in the tool and provide justification here.
(ii) Methane emissions from wastewater treatment systems affected by the project
activity, and not equipped with biogas recovery in the project scenario
( PEww,treatment, y );
As described above the project activity affects systems of the baseline wastewater treatment plant.
This thus is thus irrelevant. For these the project emissions are calculated as:
UNFCCC/CCNUCC
(iii) Methane emissions from sludge treatment systems affected by the project
activity, and not equipped with biogas recovery in the project situation
( PEs ,treatment, y );
The project activity does not affect systems of the baseline wastewater treatment plant as
described above. This thus is thus irrelevant.
(v) Methane emissions from the decay of the final sludge generated by the project
activity treatment systems ( PEs , final, y );
Project activity emissions from methane release in capture systems are determined as follows: This
emission source is relevant to any project scenario as it applies to any installed biogas digester
generating biogas. The calculation of this emission source is as follows:
For the ex-ante emission calculation the following formula will be applied:
PE fugitive, y PE fugitive,ww, y PE fugitive,s , y
Parameter Description Value Unit
PEfugitive,y Fugitive emissions through capture inefficiencies 2,166 tCO2e
PEfugitive,ww,y Fugitive emissions through capture inefficiencies in 2,166 tCO2e
the anaerobic wastewater treatment systems
PEfugitive,s,y Fugitive emissions through capture inefficiencies in [Value] tCO2e
the anaerobic sludge treatment systems
Methane may be released as a result of incomplete combustion in the flare. To calculate project
emissions from flaring of the biogas (PEflare), the “Tool to determine project emissions from flaring
gases containing methane” (version 01 approved at EB28) is applied.
For determination of the flare efficiency, a default value of 90% will be used for the calculation of
project emissions from flaring gases if the CPA uses since an enclosed will be employed by the CPA.
Step 1: Determination of the mass flow rate of the residual gas that is flared
This step calculates the residual gas mass flow rate in each hour h, based on the volumetric flow rate
and the density of the residual gas. The density of the residual gas is determined based on the
volumetric fraction of all components in the gas.
This step calculates the residual gas mass flow rate in each hour h, based on the volumetric flow rate
and the density of the residual gas. The density of the residual gas is determined based on the
volumetric fraction of all components in the gas. Alternatively, the tool provides a simplified
approach to only measure the volumetric fraction of methane and to consider the deference to 100%
as being nitrogen. The proposed project activity adopts this simplified approach.
Step 2 is not applicable because of the simplified approach taken where only the volumetric fraction
of methane is measured.
Steps 3 & 4 are only applicable if the combustion efficiency of the flare is continuously monitored
and are therefore not considered.
Step 5: Determination of methane mass flow rate in the residual gas on a dry basis
The quantity of methane in the residual gas flowing into the flare is the product of the volumetric flow
rate of the residual gas (FVRG,h), the volumetric fraction of methane in the residual gas (fvCH4,RG,h) and
the density of methane (CH4,n,h) in the same reference conditions (normal conditions and dry or wet
basis).
Where:
Parameter Description Unit Source
Mass flow rate of methane in Flaring tool
TMRG,h kg/h
the residual gas in the hour h Equation 13
To be
Volumetric flow rate of the residual gas in dry basis at monitored
FVRG,h m3/h
normal conditions in the hour h after project
implementation
To be
Volumetric fraction of methane
monitored
fvCH4,RG,h in the residual gas on dry basis m3/h
after project
in hour h
implementation
Flaring tool
CH4,n Density of methane at normal conditions kg/m3
The CPA uses an enclosed flare, the flare efficiency in the hour h (ηflare,h) according to the tool is:
0% if the temperature in the exhaust gas of the flare (Tflare ) is below 500 °C for more than 20
minutes during the hour h .
50%, if the temperature in the exhaust gas of the flare (Tflare ) is above 500 °C for more than
40 minutes during the hour h, but the manufacturer’s specifications on proper operation of the
flare are not met at any point in time during the hour h.
90%, if the temperature in the exhaust gas of the flare (Tflare ) is above 500 °C for more than
40 minutes during the hour h and the manufacturer’s specifications on proper operation of the
flare are met continuously during the hour h.
Project emissions from flaring are calculated as the sum of emissions from each hour h, based on the
methane flow rate in the residual gas (TMRG,h) and the flare efficiency during each hour h (flare,h), as
follows:
1 flare,h
8760
GWPCH 4
PEflare,y = TM
h 1
RG ,h
1000
Eq. 15 of Flaring Tool Version 01
Where:
Parameter Description Unit Source
Project emissions from flaring of Flaring tool
PEflare,y tCO2e/yr
the residual gas stream in year y Equation 15
To be
Mass flow rate of the methane in monitored
TMRG,h kg/h
the residual gas in the hour h after project
implementation
ηflare,h Flare efficiency in hour h fraction Flaring tool
UNFCCC/CCNUCC
PEbiomass,y = 0 tCO2e
Leakage (AMS-III.H)
If the technology is using equipment transferred from another facility, leakage effects at the site of
the other activity are to be considered and estimated (LEy).
Otherwise:
LEy = 0 tCO2e
The emission reduction calculations below need to be completed for CPA that comply with
technology scenario E (Utilization of biogas for grid connected power generation). If this scenario is
not applicable, then BE grid, y = 0 t CO2
Where:
BE grid, y Baseline Emissions for electicity generation from biogas that 4,718 (t CO2)
is exported to the grid in year y
EG BL , y Quantity of net electricity supplied to the grid as a result of 7008 MWh
the implementation of the CDM project activity in year y
EFCO2, grid, y CO2 emission factor of the grid in year y 0.748 t
CO2/M
Wh
Baseline Emission
Project emissions Leakage
Year emissions reductions
(t CO2e) (t CO2e)
(t CO2e) (t CO2e)
Year 1 18,533 3,465 0 15,068
Year 2 18,533 2,296 0 16,237
Year 3 18,533 2,296 0 16,237
Year 4 18,533 2,296 0 16,237
Year 5 18,533 2,296 0 16,237
Year 6 18,533 2,296 0 16,237
Year 7 18,533 2,296 0 16,237
Year 8 18,533 2,296 0 16,237
Year 9 18,533 2,296 0 16,237
Year 10 18,533 2,296 0 16,237
Total 185,331 24,127 0 161,204
Total number 10
of crediting
years
Annual 18,533 2,413 - 16,120
average over
the crediting
period
UNFCCC/CCNUCC
Below are the combined ex-ante estimates of emission reduction for AMS.III.H and AMS.I.D:
Baseline Emission
Project emissions Leakage
Year emissions reductions
(t CO2e) (t CO2e)
(t CO2e) (t CO2e)
Year 1 18,533 3465 0 15,068
Year 2 21,300 2296 0 19,004
Year 3 21,300 2296 0 19,004
Year 4 21,300 2296 0 19,004
Year 5 21,300 2296 0 19,004
Year 6 21,300 2296 0 19,004
Year 7 21,300 2296 0 19,004
Year 8 21,300 2296 0 19,004
Year 9 21,300 2296 0 19,004
Year 10 21,300 2296 0 19,004
Total 210,233 24127 0 186,106
Total number of 10
crediting years
Annual average 21,023 2,413 - 18,611
over the
crediting period
UNFCCC/CCNUCC
D.7. Application of the monitoring methodology and description of the monitoring plan
D.7.1. Data and parameters to be monitored
(Copy this table for each data and parameter.)
Unit m³/month
Description The flow of wastewater
Source of data Onsite measurements
Value(s) applied 12,600
Measurement Measurements are undertaken by using flow meter at inlet to the project
methods and activity wastewater treatment system.
procedures
Details e.g. location, configuration, accuracy, class of the measurement
device are to be provided in the CPA-DD.
Monitoring
frequency
QA/QC procedures The measurements will be monitored continuously (at least hourly
measurements will be undertaken, if less confidence/ precession level of
90/10 shall be attained). Calibration of the flow meters will also be
conducted as specified by vendor.
Purpose of data Calculation of baseline emissions;
Calculation of project emissions;
Additional comments At the time of the CPA inclusion, for each of the relevant wastewater flow
meter separate tables shall be provided.
UNFCCC/CCNUCC
The data will be archived electronically and kept for minimum of two years
after the end of the crediting period or the last issuance of CERs for the
project activity, whichever occurs later.
be ignored. The parameter will not be monitored for this particular CPA.]
The data will be archived electronically and kept for minimum of two years
after the end of the crediting period or the last issuance of CERs for the
UNFCCC/CCNUCC
If the methane emissions from anaerobic decay of the final sludge are to be
neglected because the sludge is controlled combusted, disposed of in a
landfill with methane recovery, or used for soil application, then the end-use
of the final sludge will be monitored during the crediting period.
This table is not relevant to the project activity because sludge treatment is
not part of the project activity and can thus be ignored. The parameter will
not be monitored for this particular CPA.
UNFCCC/CCNUCC
Data / Parameter FE
Unit Fraction
Description Flare efficiency in year y (fraction).
Source of data --
Value(s) applied 90%
Measurement As per the “Tool to determine project emissions from flaring gases
methods and containing methane”
procedures Regular maintenance shall be carried out to ensure optimal operation of
flares
Data / Parameter T
o
Unit C
Description Temperature of the biogas recovered
Source of data Measurements from the temperature indicator
Value(s) applied To be monitored during operation.
Measurement The temperature of the biogas is required to determine the density of the
methods and methane combusted. If the biogas flow meter employed measures flow,
procedures pressure and temperature and displays or outputs the normalised flow
of biogas, then there is no need for separate monitoring of pressure
and temperature of the biogas.
Data / Parameter P
Unit Pa
Description Pressure of the biogas
Source of data Pressure measurement device
Value(s) applied To be monitored during operation.
Measurement The pressure of the biogas is required to determine the density of the
methods and methane combusted. The pressure will be measured continuously. If the
procedures biogas flow meter employed measures flow, pressure and temperature and
displays or outputs the normalised flow of biogas, then there is no need for
separate monitoring of pressure and temperature of the biogas.
The pressure of the biogas will be measured at the same time when methane
content in biogas (wCH4,y) is measured.
Monitoring Continues
frequency
QA/QC procedures Calibration of the meter will be as per vendor’s specifications.
Purpose of data Calculation of project emissions;
Additional The data will be archived electronically and kept for minimum of two years
UNFCCC/CCNUCC
comments after the end of the crediting period or the last issuance of CERs for the
project activity, whichever occurs later.
The data will be archived electronically and kept for minimum of two years
after the end of the crediting period or the last issuance of CERs for the
project activity, whichever occurs later.
after the end of the crediting period or the last issuance of CERs for the
project activity, whichever occurs later.
The data will be archived electronically and kept for minimum of two years
UNFCCC/CCNUCC
after the end of the crediting period or the last issuance of CERs for the
project activity, whichever occurs later.
Unit -
Description Average technical transmission and distribution losses for providing
electricity to source j/k in year y
Source of data As per “Tool to calculate the emission factor for an electricity system”.
Value(s) applied 20%
Measurement As per “Tool to calculate the emission factor for an electricity system”.
methods and
procedures
Monitoring ----
frequency
QA/QC procedures ----
Purpose of data Calculation of project emissions;
Calculation of baseline emissions;
Additional comments At the time of the CPA inclusion, for each of the relevant TDL separate
tables shall be provided.
The data will be archived electronically and kept for minimum of two years
after the end of the crediting period or the last issuance of CERs for the
project activity, whichever occurs later.
This table is not relevant to the project activity because no fossil fuel is used
and can thus be ignored. The parameter will not be monitored for this
UNFCCC/CCNUCC
particular CPA.
This table is not relevant to the project activity because no fossil fuel is used
and can thus be ignored. The parameter will not be monitored for this
particular CPA.
UNFCCC/CCNUCC
Measurement Any of the four data source in preferential order as mentioned in the Tool to
methods and calculate project or leakage CO2 emissions from fossil fuel combustion”. For
procedures option a) and b): Measurements should be undertaken in line with national or
international fuel standards.
Monitoring To be defined for each CPA at time of inclusion
frequency
QA/QC procedures To be defined for each CPA at time of inclusion
Purpose of data Calculation of project emissions;
Additional comments At the time of the CPA inclusion, for each of the relevant fossil fuel separate
tables shall be provided.
The data will be archived electronically and kept for minimum of two years
after the end of the crediting period or the last issuance of CERs for the
project activity, whichever occurs later.
This table is not relevant to the project activity because no fossil fuel is used
and can thus be ignored. The parameter will not be monitored for this
particular CPA.
In order to ensure all CPAs are monitored and verified as per the applied monitoring methodology, the
CME has prepared a comprehensive monitoring plan for all the CPAs to be included in the PoA.
Furthermore, the CME will conduct periodical inspection of units randomly at any given time in a
year. For this purpose the CME will deploy trained monitoring personnel who will visit the CPAs
sites, review their records and take corrective actions if required. The monitoring personnel would
duly attest the records as a mark of satisfactory inspection. The CME would randomly check the visits
of monitoring personnel in order to ensure due compliance of registered monitoring plan.
Templates (as a part of monitoring manual) are made to record the data to be monitored. The
monitoring personnel of the CME would be provided with such templates. In-house training shall be
imparted to plant personnel (at the CPA site) for the efficient monitoring/recording of the data and to
translate the same into the computation of emission reductions.
The key considerations for developing monitoring plans in individual CPAs are discussed below.
1. Introduction
The Monitoring Plan (MP) would present a plan to meet the requirements for the collection,
processing and reporting of data. It will describe the management systems and procedures to be
implemented by CME upon implementation of each CPA in order to ensure consistency between the
UNFCCC/CCNUCC
project operation as well as monitoring, processing and reporting of data required for the
calculation of emission reductions (ERs).
2. Obligations of CME
It will be the responsibility of the CME to develop and implement a management and operational
system for a CPA that will meet the requirements of the MP.
1. Description of the primary source of data from where the information pertaining to the data
parameter will be collected
2. Description of the data collection process
3. Description of the data recording process
4. Description of the measurement instruments, in case a given parameter is to be measured (
for e.g. meters used for measuring energy consumption, operating hours)
5. Calibration requirement of the measurement instrument
6. Description of data storage process
7. Other information, if required
The other relevant data will be recorded by the CPA owners and would be provided on quarterly basis
to the CME. The data received will be archived electronically for computations of emission
reductions on annual basis. Such archived data will be kept until two years after the end of the
crediting period or the issuance of CERs whichever is later. Each small scale CPA shall follow all the
provision of the PoA including that related to monitoring. Only those CPA implementers who confirm
to sign an agreement in this context shall be included in the PoA, as this is a part of eligibility criteria
should include a check if the number of project activity equipment distributed by the project and
the number of scrapped equipment correspond with each other. For this purpose scrapped
equipment should be stored until such correspondence has been checked. The scrapping of
replaced equipment should be documented and independently verified
7. Procedures for emergency preparedness for cases where emergencies cause unintended
emissions:
For each CPA an emergency preparedness procedure will be developed which takes into account:
Procedures to avoid unintended emissions during operation and maintenance
General procedures to avoid unintended emissions due to activities near the biogas plan.
Inspection procedures to ensure integrity of the biogas plant
Monitoring requirements for technology scenario E (Utilization of biogas for grid connected
power generation):
The monitoring plan applies to CPA that comply with technology scenario E (Utilization of biogas for
grid connected power generation) and can the text can be deleted if scenario E is not applicable.
The proposed CPA is connected to the Public Power Grid through one or more on-site transformer
stations. The project will be connected to nearest Substation through available power lines and might
in the future also connect to the grid through other main power lines. The CPA may furthermore be
connected to a back-up power line to provide emergency power in case the project is not operational.
An indicative grid connection diagram is provided in figure E.7.2.1. The solid lines indicate
connection lines that are currently intended with the dotted lines indicating potential future additions.
The grid connection diagram indicates the principles for positioning of metering instruments that will
be used in the monitoring of emission reductions. A separate detailed grid connection diagram will be
prepared which is updated on the basis of the actual implementation of the project’s grid connection
and which will serve as the basis for periodic verification. The CPA implementer will ensure that the
actual implementation of grid connection will not deviate from the procedures outlined in this section.
UNFCCC/CCNUCC
M2a M2b
Back-up power line
M2c
Project Boundary
M1a M1b M1c
M3
The CPA implementer will meter electric power according to the following principles:
Power received through back-up power lines: As indicated in Figure B.7.2.1 the project
may be connected by a back-up emergency power line (indicated in brown) which delivers
UNFCCC/CCNUCC
power from the grid to the project in case of emergencies or when the turbines of the
proposed CPA are not in operation. Net power received from the grid is metered as below:
o Grid company:
The grid company will meter the power supplied to the project with its own metering
equipment in accordance with national regulations.
o Calibration:
Calibrations are carried out by the grid company or by a certified company.
The CPA will collect the sales receipts for power supplied to the grid and billing receipts for power
received from the grid as evidence. The net supply (i.e. gross supply minus supply by the grid to the
project) will be used in the calculations. In case of discrepancies between the metering instruments of
the grid company and the CPA, the readings of the grid company will prevail. All records of power
delivered to the grid, sales receipts and the results of calibration will be collated in a central place by
the CPA.
Net electricity supplied to the grid by the project (EGBL,y in section E.7.1.) is calculated on a monthly
basis as:
Equation B.13
EGBL , y ES y ED y
With:
ESy, electricity supplied by the project through the main power line(s) (in MWh) metered by
the grid company (evidenced by monthly sales receipts) and cross-checked against the
readings of metering instruments of the CPA Implementer.
EDy, electricity delivered to the project through possible back-up power line(s) metered by the
grid company (evidenced by monthly billing receipts).
UNFCCC/CCNUCC
19
The CPA Implementer intends to log the readings of meters M1x and M1x manually in daily logs, but these logs
will not form a formal requirement during verification. The ACM0002 methodology only requires hourly
electronic measurement and these manual log records will only be maintained for back-up purposes. The CPA
Implementer may deviate from this procedure during actual operation of the project.
UNFCCC/CCNUCC
The project entity will furthermore document all efforts taken to restore normal monitoring procedures.
Emergencies:
In case of emergencies, the project entity will not claim emission reductions due to the project activity
for the duration of the emergency. The project entity will follow the below procedure for declaring the
emergency period to be over:
1. The project entity will ensure that all requirements for monitoring of emission reductions have
been re-established.
2. The monitoring officer and the head of operations of the power station will both sign a statement
declaring the emergency situation to have ended and normal operations to have resumed.
The monitoring officer who will be responsible for verification of the measurement, collection of sales
receipts, collection of billing receipts of the power supplied by the grid to the power plant and the
calculation of the emissions reductions. The monitoring officer will prepare operational reports of the
project activity, recording the daily operation of the power station including operating periods, power
delivered to the grid, equipment defects, etc. The selection procedure, tasks and responsibilities of the
monitoring officer are described in detail in Annex 4. Finally, the monitoring reports will be reviewed by
Blue World Carbon.
UNFCCC/CCNUCC
Monitoring officer:
Verification of
measurement &
calculation of emission
reductions
-----
UNFCCC/CCNUCC
No public funding is used to implement this small scale CDM Programme of Activity (CPA).
N
o Parameter Unit Value Source Comment
Baseline
Information
FSR/Mill Minutes of Starting
1 Mill Capacity tph 60 Meetings 2013
2 operational day day/year 300 FSR
operational
hours hour 14 FSR / historical data
Wastewater
Generation
3 Factor m3/tFFB 0.6 FSR
UNFCCC/CCNUCC
Wastewater
Volume m3/year 151,200 Calculated
Should be
multiply by
COD of POME 0.89 as per
entering the Meth AMS
anaerobic 10 days Campaign result III H Ver 16
4 lagoon #1 mg/l 35,824 report Para 27
COD of POME Should be
Final Discharge multiply by
to Land 0.89 as per
Application exit Meth AMS
from anaerobic 10 days Campaign result III H Ver 16
5 lagoon #4 mg/l 3,033 report Para 28
COD Removal of
6 The Lagoon % 92 Calculated
Project
Information
Type of
technology to be
1 applied Covered Lagoon
Project digester
COD treatment CIGAR
2 efficiency % 85 FSR Efficiency
COD Level out
from the
3 digester mg/l 5,374 Calculated
Biogas
production
4 potential m3/kgCOD 0.6 FSR
Biogas
5 Production m3/year 2,762,482 FSR
Fraction of
methane in m3 CH4/m3
6 biogas biogas 0.6
Methane
content in
7 biogas m3 CH4 / year 1,657,489
Electricity
8 Production kWh/year 3,699,034 FSR FSR
No additional information
No additional information
-----
UNFCCC/CCNUCC