You are on page 1of 5

EX:ercise in craftsmanship

Building
a
concrete
spiral
staiway Sandblasted architectural concrete stairway ar fhe new
Cedar Rapids Public Library. Complex cu&es called for
time-consuming and ingenious formwork.

Eight man-mo,nths of skilled labor in the formwork paid off for the
contractor. His own satisfaction of accomplishment was heightened by
enthusiastic approval from the owner and architect,

THE CHALLENGE: A spiral staircase in architectural This article details some of the five months of forming
concrete, with a broad, curved landing three steps up and and placing operations required for successful comple-
a larger boat-shaped landing half way to the second floor. tion of the stairs.
Monolithic sidewalls supporting a polished brass hand-
rail end in scrolling curves with a 1-foot radius. With a BUILDING THE FORMS
skylight above and overhanging cast-m-place planter box- Complexity of the drawings provided a good early
es at the upper landing level, the stairway is planned as warning for the form builders. After development of the
the dramatic focal point of a new public library. The concept, the architect had kept one man busy two months
buiider has signed a fixed-price agreement based on es- preparing the design drawing alone. The contractor
timates which, he realixes al1 too late, didn’t allow ade- received 2V8 large sheets showing the layout and details..
quately for the complexity of the stairway work. What F’rom this starting point, two men worked four months
to do? constructing the forms. The formwork had to be finished
THE RESPONSE: Do the best possible work regard- almost as carefully as cabinet work, and strong and rigid
less of unusual costs. The contractor wisely recognixed enough to hold the fresh concrete and the men placing it.
that the stairway would be the center of attention. ‘Ib Structural support for the stairs is provided by 304nch
build it properly would require the fin& craftsmanship, round caissons, which extend 20 feet below the ground
and no effort could be spared. Anything less might have floor to rock. The first landing, up three steps, is support-
prejudiced acceptance of the whole job. ed directly on one of .these caissons. A second~landing,
CONCRETE CONSTRUCTION / FEBRUARY 1995 181
A. After &whm a
full-scale plan ,f the
stalm on the concrY)te
slab, carpenters
erected a metal
column which wouhi
ptvvkle center suppcft
for rbrmwork. steel
plates w3rr3 ~3lded tc
the post in line with
the face of each trwd.

C Soffit form for the staim was made of two /ayers of


plywood suppotted on 2x10s. This view of the inside of the
form shows outside Wall sheathing in place. Three thin
layers of plywood wem used to permit bending to the
design curva

Then began the task of forming the warped surface


of the underside of the spiral stairs. Steel plates were weld-
ed to the post in line with the position of each tread face
Wood studs were set up at the outside of the 27-foot cir-
cle Then 2x10s were placed under each tread location,
supported by the studs and bolted to plates on the center
post (Photo B). The edges of the 2x10s were next planed
cdy by hand to define the contour of the helical soffit
of the stair slab. Over this support, the soffit was formed
with two layers of plywood- Ve inch on the bottom and
V, inch above @‘hoto C). Thicker plywood could not have
been warped to the desired curvature With two layers,
it also was possible to offset joints and reduce the possi-
bility of leakage through the form.
Sidewalls for the stalnxse~
R Wood studs wem set up at the outslde of the 2%
foot clrcle. Then 2x10s set bekw the location of.each stair The stairs have exposed concrete sidewalls 3’1% feet high
tmad WBT~ supported on the studs and on the steel plates above the treads, with a formed recess for the polished
attached to the center metal post. Edges of the 2x10s wem brass handrail. Form ties used in these 8-inch walls had
planed carefully to define the contour of the helical soffit. plastic cones which left 2-inch-deep mcesses that became
a visual feature of the sandblasted concrete.
The walls were to be placed monolithically with the
half way to the second floor, fs carried by curving columns stair soffit in a continuous pour. There were no control
about 8 feet high, resting on two other caissons. joints and no construction joints. The contractor elected
to place about 12 inches of the concrete soffit in this con-
tinuous pour and then come back later to complete the
Forming the sofftt stair treads. This would leave no visible joints and be
The stairway and its sidewalls lie within a 27-foot- much more convenient for the finishers. Stair tread con-
diameter circle The upper landing and planters have crete was doweled to the sidewalls.
their own radiuses as do the lower landing and the scroll- Outer forms for the sidewalls were made of three lay-
ing curve with which the sidewalls end. To build all these ers of V,-inch plywood to facilitate precision curving to
intersecting curwxl surfaces, the carpenter foreman decid- the necessary radiuses-about 7 feet on one side and 13
ed to start with a full-scale layout which he drew on the feet on the other side of the stairs (Photo C). They were
steel troweled floor slab. After creating this full plan of backed up by supporting curved wood wales. Joints in
the stairway, he set up a lo-inch-diameter steel post (Pho- the forms were carefully sealed with plastic caulk.
to A), which was braced to the main framing beams of The outer wall formscould be supported on studs and
the library’s second floor. joined to the soffit form at the bottom. The inner wall
CONCRETE CONSTRUCTION / FEBRUARY 1985 193
D. Forms for the two Inner faces of stahway sidewalls
were suspended from these wood 1’s made of two
2x10s. Forty-six job-built curved panels needed to make the
inner form had to be held above the soffit form to permit
monolithic casting of walls and soffit.

E. Curved forms for the inner wa// faces. Note gap


between form panel and soffit form to permit monolithic
casting.

forms presented a different problem because they had to


be suspended to permit continuous placing of soffit slab
and wall. The builders devised a set of inverted wood T’s
made of pairs of 2x6s which they could support on the
outside wall forms (Photo D). From these T’s they hung
the 46 job-built curved panels needed for the inner face
of the stair walls (Photo E). These panels were carefully
hung and fitted, then dismantled for placing the rein-
forcing bars, and suspended again with special attention
to joints between them. Slots were routed in the butting
edges of the panels, and sheet metal strips 1 inch wide
were inserted to hold the panels in alignment and to help
prevent leakage
Difficult details
A continuous recess running the length of ,the inside
wall form was needed to accommodate the brass hand-
rail. This recess was formed with blockouts made of six
layers of hardboard, hand sculpted to the cm-ved contour,
smoothed with gypsum plaster, and coated with shellac.
The blockouts were mounted on the curved inside wall
form panels. In effect, this reduced the wall thickness
from 8 to 5Ve inches at the top, adding to the difficulty
of placing concrete
Even greater problems faced the form builders at the
bottom of the stairs where the wall ended in a curve with
12-inch radius, which could not be formed like the rest
of the wall (Photo F). Expanded metal lath, coated with
gypsum plaster provided part of the solution, where the

E Stairway railings ended in a curve with l-foot radius,


requiring unorthodox forming. This vio, looking down
into the form, shows externa/ bracing required because ties
could not be installed here.

handrail recess assumed a more complex shape. The car-


penter foreman had to work within narrow confines to
caulk joints where this piece joined with the other forms.
Here it was impossible to use form ties, and heavy exter-
nal bracing was required to resist the concrete pressure.

PLACING THE CONCRETE


The concrete, much of which would be exposed and
sandblasted, had a design strength of 4006 psi. Local river
grave1 of 3/,-inch maximum size in varied colors was used
as toarse aggregate. The Portland cement was standard
gray Type 1. Slump was held to 3 inches, and a retarder
was used for al1 but the first load delivered.
Form planning had started in January, but concrete
wasn’t placed until May when the temperature was
around 66 degrees E The surrounding building frame had
been completed by then, and artificial heating was not
needed for stairway pours.
Because of cramped spaces and the critica1 nature of
the work, a rehearsal was conducted for laborers han-
dling the concrete and the vibrators before any concrete
was delivered. Wo vibrators were used, a regular 2-inch
spud and a 3/r-inch pencil vibrator. Concrete was con-
veyed in a bucket with elephant trunk by crane from the
Street through a skylight.
The monolithic stair soffit and walls were concreted
slowly over a ô-hour period. The total pour was 35 cubic
ya&, and deliveries were made in 3-yard batches to ac-
commodate the crew working carefully in tight spaces
to prevent honeycombing that would disfigure the archi-
0. Stair steps wem placed in a second Iift on top of the 12-lnch soffit
slab poured monolithlcally wlth sidewalls. Dow& anchored this lift to fhe
walls. Steel truweled treads were later covered with carpeting.

tectural surfaces. Fortunately, the tribute to the architectural effect.


ready mix plant was just across the With carpeting and polished hand-
Street so delivery could be carefully rail added on the stairs, plants over-
controlled. hanging the planter boxes, and a ’
The 8-inch walls, which narrowed flood of light from the skylight
to only 5Ve inches at the leve1 of the above, the treasured focal point of
handrail, had #8 bars near the top. the library has been completed.
To help improve, access for placing A concrete stairway whose cost
the concrete below, those final bars goes well above $1299 per cubic yard
were not set into place until the form has paid off for the constructor who .
had been filled to that level. After the spared no effort in building it. When
wall forms had been stripped, a sec- the completed building was tumed
ond concrete placement was made to over to the library board in Decem-
complete the stair steps (Photo G). ber 1984, the architect, the board,
The tread surfaces were steel trow- and the public had lavish praise for
eled for later installation of carpet- the finished job.
ing. Planter boxes at the upper land-
Acknowledgment:
ing were cast several weeks after the Thanks to Gordon Gates of Gates and Sons,
rest of the stairway work, bringing Denver, and to Steve Chmelar of Carroll Dis-
the final total of concrete to about tributing and Construction Supply in Ottum-
49 cubic yards. wa, Iowa for alerting CONCRETE CONSTRUC
Careful detailing and sealing of TION to this story.
joints left forms so tight that the Credlts:
builder says “less than a quart” of ce- Architects: Brown Healey Bock FC. and
McConnell Steveley Anderson RC., Cedar
ment paste leaked during the entire Flapids, Iowa
pour.
Engineers: Shive-Hattety and Associates, Ce
THE HAPPY ENDINO dar Rapids, Iowa
General Contractor: Knutson Construction
Form stripping revealed a highly Company, Minneapolis; Superlntendent: Ar-
successful piece of work, which has thur J. Rinderknecht; Carpenter Poreman:
since been sandblasted to a depth of Jon A. Rinderknecht
Ve to ‘Is inch, like the exposed con- Owner: Cedar Rapids Public Librar-y, Cedar
crete in the building around it. Sec- Rapids, Iowa
ond floor and roof waffle slabs as Fcr photo ackncwledgments
well as beams and columns al1 con- ses page 230.

You might also like