Professional Documents
Culture Documents
Attachment No.
Attachment No. of Pages
JOB PMTS
PURPOSE Prepared Checker Approved
REV DATE NAME NAME NAME
REVISION REVISION
SHEET SHEET
A B C 0 A B C 0
1
2 X
3 X
4 X
5 X X
6 X
7 X
8 X
9 X
10 X
11 X
12 X
13 X X
14 X X
15 X X X
16 X X X
17 X
18 X
19 X
20 X
ELECTRICAL DESIGN BASIS Doc. No.: SNO-E-DB-543-
001
Rev. 0 Page 3 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
REVISION SUMMARY
Table of Contents
ELECTRICAL DESIGN BASIS Doc. No.: SNO-E-DB-543-
001
Rev. 0 Page 4 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
1.0 GENERAL....................................................................................................................... 5
1.1 Scope.......................................................................................................................... 5
1.2 Definitions................................................................................................................... 5
1.3 Abbreviations.............................................................................................................. 4
2.0 REFERENCE DOCUMENTS, CODES AND STANDARDS.............................................6
2.1 International/National Codes and Standards...............................................................6
2.2 Project Documents......................................................................................................6
2.3 Voltage and Frequency Variations...............................................................................6
2.3.1 Frequency Variations.......................................................................................6
2.3.2 Switchboard Voltage Variations........................................................................7
2.3.3 Motor Terminal Voltages...................................................................................7
2.4 Design Margins........................................................................................................... 7
2.5 Switchgear Short Circuit Ratings.................................................................................7
2.6 Cable Sizing and Selection..........................................................................................7
3.0 ELECTRICAL SUBSTATIONS........................................................................................9
3.1 General....................................................................................................................... 9
4.0 GENERAL..................................................................................................................... 12
5.0 MAIN POWER SUPPLY................................................................................................13
5.1 Alternator Sizing Criteria............................................................................................13
6.0 BACK UP POWER GENERATION................................................................................14
6.1 General..................................................................................................................... 14
6.2 Generator Ratings.....................................................................................................14
6.3 Alternator Impedances..............................................................................................15
7.0 ELECTRICAL POWER CONSUMPTION LIST.............................................................16
8.0 INTERFACE TO DISTRIBUTED CONTROL SYSTEM (DCS).......................................18
9.0 LIGHTNING PROTECTION...........................................................................................19
ELECTRICAL DESIGN BASIS Doc. No.: SNO-E-DB-543-
001
Rev. 0 Page 5 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
1.0 GENERAL
The operating Joint Operating Body Pertamina – Medco E&P (JOB PMTS) will be developing
the Senoro gas field, located onshore near the coast of Senoro-Toili Block on the eastern arm of
Sulawesi Island, Indonesia. Senoro Central Processing Plant through common 30” main gas
pipeline will deliver 55 MMscfd of sales gas to Ammonia Plant while others to existing LNG
Plant.
To be able to deliver sales gas for Ammonia PPLN Plant, PLN Gas Metering Station developed
to measure total sales gas while existing Gas Metering Station already dedicated to existing
Buyer. The facility for PLN Gas Metering Station project will consist Sales Gas Separator SNO-
V-5301, 2 x 100% Sales Gas Filter SNO-F-5302A/B, 2 x 100% Main UltrasonicSenior Orifice
Metering, and Instrument/Utility Air System.
1.1 Scope
This document describes the minimum technical requirements for the design and engineering
of electrical facilities for onshore Oil & Gas metering station Plants. This document, together
with all additional detailed Company Engineering Standards for major electrical equipment, shall
form the project Electrical Design Standards.
The term of minimum requirement is the minimum requirement which is mandatory to follow by
CONTRACTOR, but during detail design, COMPANY has the right to add some requirement
without any impact.
This document describes the requirements for the following aspects of the Electrical systems:
- Design Margin
- Electrical Substation
- Power Supply
- Interface to DCS
1.2 Definitions
Rev. 0 Page 6 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
SKID EDGE Skid edge is defined as a zone within two (2) inches of a
skid’s outside perimeter as set by the skid’s main
support. When the skid is covered by enclosure, skid
edge is defined as the outside surface of the enclosure.
1.3 Abbreviations
AC Alternating Current
AVR Automatic Voltage Regulator
CAT Conventional Air Terminal
CB Circuit Breaker
CT Current Transformer
DC Direct Current
DCS Distributed Control System
DOL Direct On Line
ESD Emergency Shut Down
ETAP Electrical Transient Analyzer Program
F&G Fire & Gas
FEED Front End Engineering and Design
FVMS Fused Vacuum Contactor Motor Starter
HV High Voltage
HVAC Heating, Ventilation and Air Conditioning
IP Ingress Protection
IS Intrinsically Safe
LCS Local Control Station
LV Low Voltage
MAT Modern Air Terminal
MCB Miniature Circuit Breaker
ELECTRICAL DESIGN BASIS Doc. No.: SNO-E-DB-543-
001
Rev. 0 Page 7 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
Rev. 0 Page 8 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
SNO-R-CC-543-005 Process Specification and Sizing Calculation for Diesel Storage Tank
The power system frequency shall be maintained within ± 2.5% of the nominal value for
steady-state and within ± 5% of the transient conditions including motor starting.
ELECTRICAL DESIGN BASIS Doc. No.: SNO-E-DB-543-
001
Rev. 0 Page 9 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
Switchboard voltages shall be maintained within ± 5% of the nominal value for steady-state
conditions.
Switchboard voltages shall be maintained ± 15% of the nominal value for transient conditions
including motor starting, however the terminal voltage at the motor being started shall be as
per 2.3.3 below.
As the electrical loads are determined based on the conceptual design, the design load is
calculated using a design margin of 25% to allow for changes during design detail development.
Following completion of detailed design, the design margin may be reduced to 10% to allow for
future modifications.
Consideration shall be given to providing a single short-circuit rating across all switchboards of
common voltage, irrespective of system location or transformer rating.
All conductors shall be sized taking into account the following factors:
Rev. 0 Page 10 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
All externally routed cables shall be provided with galvanized steel wire armouring. Non-
armoured cables may be specified if confined to buildings and are provided with adequate
means of mechanical protection.
Low voltage multicore power and control cables shall include an integral dedicated earth
conductor within the cable.
Where cables are installed within hydrocarbon liquid containment bunds and below the level of
the bund wall, an oil-tight lead sheath shall be provided.
Any cables installed buried underground shall have an oil-tight lead sheath, except perimeter
lighting, street lighting or other areas not susceptible to hydrocarbon liquid contamination.
The maximum permissible voltage drop along the length of the cable with reference to the
nominal supply voltage shall be as follows:
Motors 5% running at full load15 % on starting
Feeders 5% at full load between the MCC and the load terminals
2% between MCC and a distribution board
Lighting 3% between lighting distribution board and most distant lighting fixture
ELECTRICAL DESIGN BASIS Doc. No.: SNO-E-DB-543-
001
Rev. 0 Page 11 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
3.1 General
Substation shall be located in non-hazardous area classification (safe area).
Electrical distribution equipment shall be installed within an Electrical Switchroom at the PLN
Metering station. The Electrical Switchroom will be air-conditioned to provide a clean and dry
environment.
ELECTRICAL DESIGN BASIS Doc. No.: SNO-E-DB-543-
001
Rev. 0 Page 12 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
2.0 GENERAL
Normal power generation at PLN Gas Metering station will be at 400 V, 3-phase 50 Hz and shall
have a solid earthed neutral.
Emergency power generation at all facilities gas metering station will be at 400 V, 3-phase 50
Hz and shall have a solidly earthed neutral.
ELECTRICAL DESIGN BASIS Doc. No.: SNO-E-DB-543-
001
Rev. 0 Page 13 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
B
ELECTRICAL DESIGN BASIS Doc. No.: SNO-E-DB-543-
001
Rev. 0 Page 14 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
4.1 General
PLNLN Gas Metering Station shall have a single 400 V, 50 Hz emergency generator connected
to the LV Switchgear.
Emergency power will be provided for services which can tolerate an interruption in the power
supply but which require restoration of the supply within a relatively short period of time. The
emergency power supply will provide power to process services; these facilities able to operate
with normal production under emergency power generation.
Under normal operating conditions, all users will be supplied from DSLNGPLN main power
generation. On loss of voltage at LV switchboards, the switchgear shall automatically
disconnect from the normal supply and the switchgear will be supplied from the emergency
generator.
.The emergency generator shall be designed for plant black start ( after normal operation and
not for initial start up plant ) and will be provided with dedicated battery systems to supply the
diesel engine starter motor and generator protection and control system.
The emergency generator shall be a diesel engine driven generator with integral fuel storage
(day tank) and with a facility to receive diesel fuel from other source to permit extended
operation. The emergency generator shall be a self contained unit capable of starting and
running without the need for external services.
The back up power generator shall be suitable for parallel operation with the normal power
system.
Emergency generator shall be in accordance with SNO-E-TES-534-002 Specification For Diesel
Engine Generator.
Continuous power output suitable to cater for 110% of the l design loading as per SNO-
E-CC-534-001 Load Calculation and Summaries
Of suitable rating to maintain steady state and transient frequency within acceptable
limits for starting of the largest motor loads.
CONTRACTOR shall provide the calculation and simulation of biggest motor starting at the
worst case condition for sizing the EDG during Engineering and purchasing stage.
Alternator’s rated output is specified in terms of apparent power (kVA) and rated power factor.
The rated power factor for the alternator is specified as 0.8, under full load conditions. Load
studies shall confirm that the overall system power factor is not less than this value, or
otherwise measures shall be taken to improve the system power factor.
Apparent power is selected according to the rated power factor and the highest overload output
active power capability of the diesel engine driver, normally specified as 125% of the rated
continuous output.
In general the minimum requirements shall be specified as per the above, however the actual
equipment rating shall be in line with manufacturer’s standard products.
ELECTRICAL DESIGN BASIS Doc. No.: SNO-E-DB-543-
001
Rev. 0 Page 15 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
Transient reactance selected to maintain transient voltages at the downstream bus within
acceptable limits for starting of large loads
Three-phase and three-phase to earth short circuit studies shall be performed to determine the
prospective initial short circuit levels (Ik”) at the LV switchboards under the worst case scenario,
with all main power generators on-line including any standby machines, as well as considering
on-line testing of the diesel engine driven generators. This value will determine the selected LV
switchboard rating with the following considerations:
Considering total capacity from all generators on-line
1
Vendor Data
B
ELECTRICAL DESIGN BASIS Doc. No.: SNO-E-DB-543-
001
Rev. 0 Page 16 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
The electrical load is classified according to its service or criticality as Normal Loads and
Emergency Loads.
Normal Loads – loads typically related to production, and those of which the loss of
supply would not create an unsafe condition or result in damage to equipment. The
loads prevail under normal operating conditions.
Emergency Loads – these are typically loads which must be maintained continuously in
order to prevent the development of an unsafe condition. These typically include control
and safety systems and telecommunications systems. Such loads are typically supplied
via battery backed power supplies. During main generator shutdown, emergency diesel
generator will be started.
The electrical load is determined for the following electrical load calculation cases:
Total Load is determined as total loads into the switchboard based on operation of continuous,
intermittent and standby loads, without any design margins applied.
B
ELECTRICAL DESIGN BASIS Doc. No.: SNO-E-DB-543-
001
Rev. 0 Page 17 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
• Phase over-current
• Short-circuit
• Restricted earth fault
• Backup earth fault
• Differential (where greater than 1250kVA)
• Over-temperature
• Overpressure
Low Voltage Motors
• Thermal Overload.
• Stall/locked rotor
• Short circuit
• Earth fault (using core-balance CTs for motors 30kW to 75kW)
• Over current (motors 90kW and above)
• Negative sequence current (motors 90kW and above)
• Motors 90kW and above shall be provided with electronic motor protection relays
Bus-Tie CBs (If Any)
• Phase over-current protection
• Synchronism check protection (where applicable)
Incomers
• Over-current
• Short circuit
• Earth fault
• Under-voltage
Outgoing feeders
• Over-current
• Short circuit
• Earth fault (by residual CT connection)n and trip circuit supervision).
ELECTRICAL DESIGN BASIS Doc. No.: SNO-E-DB-543-
001
Rev. 0 Page 18 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017
Rev. 0 Page 19 of 19
EPC FASILITAS PENGUKURAN
GAS SENORO-PLN
Rev. Date: 13-Jun-201610
Oct 2017