CRONOGRAMA DE UTILIZACION DEL RECURSO MANO DE OBRA

ENTIDAD: MUNICIPALIDAD DISTRITAL CORONEL GREGORIO ALBARRACIN LANCHIPA


PROYECTO: CREACION DE LOS SERVICIOS MUNICIPALES DE INHUMACION EN EL SECTOR VIÑANI, DISTRITO DE GREGORIO ALBARRACIN LANCHIPA - TACNA-TACNA

PRESUPUESTO PROGRAMADO
DESCRIPCION UND
CANTIDAD PRECIO TOTAL Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17
TOPOGRAFO hh 141.76 19.40 2,746.56 2,746.56
CAPATAZ hh 4,173.73 21.34 89,140.12 9,904.46 9,904.46 9,904.46 9,904.46 9,904.46 9,904.46 9,904.46 9,904.46 9,904.46
OPERARIO hh 32,740.43 19.40 634,918.99 12,698.38 31,745.95 63,491.90 95,237.85 114,285.42 95,237.85 95,237.85 95,237.85 31,745.95
OFICIAL hh 16,268.60 15.86 257,731.32 0.00 12,886.57 25,773.13 25,773.13 38,659.70 38,659.70 51,546.26 38,659.70 25,773.13
PEON hh 41,897.69 14.22 595,967.92 29,798.40 47,677.43 71,516.15 89,395.19 107,274.23 107,274.23 59,596.79 59,596.79 23,838.72
TOTAL 1,580,504.91 55,147.79 102,214.41 170,685.64 220,310.63 270,123.80 251,076.23 216,285.36 203,398.80 91,262.26
PROGRAMADO MENSUAL 3.49% 6.47% 10.80% 13.94% 17.09% 15.89% 13.68% 12.87% 5.77%
PROGRAMADO ACUMULADO 3.49% 9.96% 20.76% 34.70% 51.79% 67.67% 81.36% 94.23% 100.00%
CRONOGRAMA DE ADQUISICION DE MATERIALES
ENTIDAD: MUNICIPALIDAD DISTRITAL CORONEL GREGORIO ALBARRACIN LANCHIPA

PROYECTO: “MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA I.E.I. N° 446 EN LA ASOC. VIV. VILLA VIÑANI - VIÑANI II ETAPA, EN EL DISTRITO CRNL. GREGORIO ALBARRACIN LANCHIPA - TACNA - TACNA”

PRESUPUESTO Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17
ITEM DESCRIPCION UND Total
CANTIDAD PRECIO PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL

1 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 kg 78,840.49 3.25 256,231.59 11,826.07 38,434.74 7,884.05 25,623.16 7,884.05 25,623.16 15,768.10 51,246.32 15,768.10 51,246.32 19,710.12 64,057.90 - - - 256,231.59
2 ACERO LISO DE 3/8" m 260.35 4.50 1,171.58 - - - - - 260.35 1,171.58 - - - 1,171.58
3 ADAPTADOR DE 1'' pza 36.00 3.80 136.80 - - - 36.00 136.80 - - - - - 136.80
4 ADAPTADOR DE 1 1/2'' pza 36.00 6.50 234.00 - - - 36.00 234.00 - - - - - 234.00
5 ADAPTADOR DE 2'' pza 36.00 9.50 342.00 - - - 36.00 342.00 - - - - - 342.00
6 ADITIVO CURADOR gln 953.54 29.00 27,652.66 - 953.54 27,652.66 - - - - - - - 27,652.66
7 ADITIVO IMPERMEABILIZANTE X 20 LT bal 72.75 105.50 7,675.13 - 72.75 7,675.13 - - - - - - - 7,675.13
8 ADOCESPED DE CONCRETO m2 45.15 45.00 2,031.75 - - - - - - 45.15 2,031.75 - - 2,031.75
9 AFIRMADO m3 1,181.54 44.00 51,987.76 - - 1,181.54 51,987.76 - - - - - - 51,987.76
10 AGUA m3 3,297.31 8.00 26,378.45 3,297.31 26,378.45 - - - - - - - - 26,378.45
11 AGUA PARA CONSUMO HUMANO X 20 LTS und 210.00 13.56 2,847.60 210.00 2,847.60 - - - - - - - - 2,847.60
12 ALAMBRE NEGRO N°16 kg 4,861.69 4.00 19,446.76 2,430.85 9,723.38 - - 2,430.85 9,723.38 - - - - - 19,446.76
13 ALAMBRE NEGRO N°8 kg 3,834.21 4.00 15,336.84 1,917.11 7,668.42 - - 1,917.11 7,668.42 - - - - - 15,336.84
14 ANGULO 2" X 2" X 3/16" pza 2.00 35.00 70.00 - - - - - - 2.00 70.00 - - 70.00
15 ANGULO 1"x1"x3/16" x6m pza 5.88 18.00 105.84 - - - - - - 5.88 105.84 - - 105.84
16 ANGULO DE FIERRO 1 1/2" X 1 1/2" X 3/16" pza 0.50 39.00 19.50 - - - - - - 0.50 19.50 - - 19.50
17 ANGULO DE FIERRO 2" X 2" X 2.5mm pza 18.00 40.00 720.00 - - - - - - 18.00 720.00 - - 720.00
18 ANGULO DE FIERRO 2" X 2" X 3/16" pza 0.50 56.00 28.00 - - - - - - 0.50 28.00 - - 28.00
19 ANILLO DE CERA CON GUIA und 33.00 5.93 195.69 - - - - - - 33.00 195.69 - - 195.69
20 ARAUCARIA EXCELSA und 5.00 60.80 304.00 - - - - - - - 5.00 304.00 - 304.00
21 ARENA FINA m3 367.24 50.00 18,362.13 - - - 367.24 18,362.13 - - - - - 18,362.13
22 ARENA GRUESA m3 1,079.66 38.00 41,027.08 539.83 20,513.54 - - 539.83 20,513.54 - - - - - 41,027.08
23 ARENA GRUESA 3/8" m3 33.44 38.00 1,270.72 - - - - - 33.44 1,270.72 - - - 1,270.72
24 ARNES DE SEGURIDAD C/LINEA DE ENGANCHE pza 30.00 90.00 2,700.00 30.00 2,700.00 - - - - - - - - 2,700.00
25 ARTEFACTO DE EMERGENCIA CON EQUIPO Y LAMPARA DE und 14.00 150.00 2,100.00 - - - - 14.00 2,100.00 - - - - 2,100.00
26 2x20 W
ARTEFACTO TIPO BRAQUET 2x20W, PARA ALUMBRADO EN und 5.00 45.00 225.00 - - - - 5.00 225.00 - - - - 225.00
27 PARED
ARTEFACTO TIPO GALAXIE PARA ADOSAR CON 02 und 72.00 55.00 3,960.00 - - - - 72.00 3,960.00 - - - - 3,960.00
28 LAMPARAS FLUORESCENTE
ARTEFACTO DE 2x18W
TIPO GEOTEC PARA EMPOTRAR EN PISO, CON und 5.00 1,102.00 5,510.00 - - - - 5.00 5,510.00 - - - - 5,510.00
29 LAMPARA
ARTEFACTODETIPO
150WGEOTEC PARA EMPOTRAR EN PISO, CON und 3.00 1,035.00 3,105.00 - - - - 3.00 3,105.00 - - - - 3,105.00
30 LAMPARA DETIPO
ARTEFACTO 70W RAS PARA ADOSAR CON 02 LAMPARAS und 24.00 140.00 3,360.00 - - - - 24.00 3,360.00 - - - - 3,360.00
31 FLUORESCENTE
ARTEFACTO TIPODE 2x36W
RES PARA EMPOTRAR CON 02 LAMPARAS und 57.00 140.00 7,980.00 - - - - 57.00 7,980.00 - - - - 7,980.00
32 FLUORESCENTE
ASFALTO RC-250 DE 2x36W gln 312.52 18.00 5,625.36 312.52 5,625.36 - - - - - - - - 5,625.36
33 BIODIGESTOR AUTOLIMPIABLE 7000 LITROS INC/ und 1.00 10,500.00 10,500.00 - - - - - - 1.00 10,500.00 - - 10,500.00
34 ACCESORIOS
BISAGRA ALUMINIZADA 3 1/2"x3 1/2" und 6.00 2.60 15.60 - - - - - - - 6.00 15.60 - 15.60
35 BISAGRA DE FIERRO DE 1/4" x 6" und 18.00 10.00 180.00 - - - - - - - 18.00 180.00 - 180.00
36 BISAGRAS ALUMINIZADAS DE 4" x 2" pza 115.00 3.00 345.00 - - - - - - - 115.00 345.00 - 345.00
37 BISAGRAS DE FIERRO DE 3" X 1/4" pza 84.00 10.00 840.00 - - - - - - - 84.00 840.00 - 840.00
38 BISAGRAS DE FIERRO PESADA DE 6" pza 6.00 30.00 180.00 - - - - - - - 6.00 180.00 - 180.00
39 BLOQUEADOR SOLAR cja 10.00 56.00 560.00 10.00 560.00 - - - - - - - - 560.00
40 BOTAS DE JEBE CAÑA ALTA PAR 50.00 29.00 1,450.00 50.00 1,450.00 - - - - - - - - 1,450.00
41 BOTIQUIN DE PRIMEROS AUXILIOS (EQUIPADO) und 1.00 200.00 200.00 1.00 200.00 - - - - - - - - 200.00
42 BROCHA DE 4" und 26.82 22.00 590.04 26.82 590.04 - - - - - - - - 590.04
43 BUGANVILLA und 7.00 30.00 210.00 - - - - - - - 7.00 210.00 - 210.00
44 BUZON DE CONCRETO PARA RED DE B.T. 0.8 x 0.8 x 1.0 m und 20.00 128.00 2,560.00 - - - 20.00 2,560.00 - - - - - 2,560.00
45 BUZÓN DE CONEXIONES ELÉCTRICAS GLB 11.00 120.00 1,320.00 - - - 11.00 1,320.00 - - - - - 1,320.00
46 CABLE 1-1x10 mm2 N2XOH+1x10/N mm2 N2XOH m 340.00 12.00 4,080.00 - - - - - 340.00 4,080.00 - - - 4,080.00
47 CABLE 2-1x4 mm2 NHX-90+1x4/T mm2 NHX-90 m 90.00 6.00 540.00 - - - - - 90.00 540.00 - - - 540.00
48 CABLE 3-1x10 mm2 N2XOH+1x10/N mm2 N2XOH m 190.00 24.00 4,560.00 - - - - - 190.00 4,560.00 - - - 4,560.00
49 CABLE 3-1x35 mm2 N2XOH+1x35/N mm2 N2XOH m 20.00 65.00 1,300.00 - - - - - 20.00 1,300.00 - - - 1,300.00
50 CABLE 3-1x50 mm2 N2XOH+1x50/N mm2 N2XOH m 120.00 80.00 9,600.00 - - - - - 120.00 9,600.00 - - - 9,600.00
51 CABLE 3-1x6 mm2 N2XOH+1x6/N mm2 N2XOH+1x6/T mm2 m 160.00 17.00 2,720.00 - - - - - 160.00 2,720.00 - - - 2,720.00
52 N2XOH
CABLE 3-1x70 mm2 N2XOH+1x70/N mm2 N2XOH m 250.00 120.00 30,000.00 - - - - - 250.00 30,000.00 - - - 30,000.00
53 CABLE NH-80, 1x2.5 mm2 m 2,243.00 1.10 2,467.30 - - - - - 2,243.00 2,467.30 - - - 2,467.30
54 CABLE NH-80, 1x4 mm2 m 1,944.00 1.60 3,110.40 - - - - - 1,944.00 3,110.40 - - - 3,110.40
55 CABLE UTP AMP SÓLIDO 4P, CATEGORIA 6, 23AWG LSZH m 120.00 2.68 321.60 - - - - - 120.00 321.60 - - - 321.60
56 CAJA DE CONCRETO P/MEDIDOR AGUA und 36.00 35.00 1,260.00 - - - 36.00 1,260.00 - - - - - 1,260.00
57 CAJA DE PASO METALICA C/TAPA 150 X 150 X 75 mm. und 5.00 14.00 70.00 - - - 5.00 70.00 - - - - - 70.00
58 CAJA DE PASO METALICA C/TAPA 250 X 250 X 200 mm. und 3.00 17.00 51.00 - - - 3.00 51.00 - - - - - 51.00
59 CAJA DE REGISTRO CON TAPA PARA POZO DE PUESTA A und 4.00 30.00 120.00 - - - 4.00 120.00 - - - - - 120.00
60 TIERRA
CAJA GALV. OCTOGONAL SAP 100mm x 55mm und 174.00 5.00 870.00 - - - 174.00 870.00 - - - - - 870.00
61 CAJA GALV. RECTANGULAR SAP 100mm x 50mm x 55mm und 263.00 5.00 1,315.00 - - - 263.00 1,315.00 - - - - - 1,315.00
62 CAJA TIPO FACE PLATE und 8.00 5.00 40.00 - - - 8.00 40.00 - - - - - 40.00
63 CALAMINA GALVANIZADA DE 0.80 m x 3.60 m x 0.21 mm. pln 64.80 25.00 1,620.00 64.80 1,620.00 - - - - - - - - 1,620.00
64 CAMILLA DE AUXILIO und 1.00 480.00 480.00 1.00 480.00 - - - - - - - - 480.00
65 CAMISA DE SEGURIDAD und 120.00 38.00 4,560.00 120.00 4,560.00 - - - - - - - - 4,560.00
66 CANASTILLA DE BRONCE 1 1/2" und 2.00 30.00 60.00 2.00 60.00 - - - - - - - - 60.00
67 CANASTILLA DE BRONCE 1" und 2.00 25.00 50.00 2.00 50.00 - - - - - - - - 50.00
68 CANDADO 2'' und 13.00 48.00 624.00 13.00 624.00 - - - - - - - - 624.00
69 CARTELES DE SEÑALIZACION und 6.00 35.00 210.00 6.00 210.00 - - - - - - - - 210.00
70 CASCO DE SEGURIDAD P/PERSONAL OBRERO und 120.00 16.00 1,920.00 120.00 1,920.00 - - - - - - - - 1,920.00
PRESUPUESTO Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17
ITEM DESCRIPCION UND Total
CANTIDAD PRECIO PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL

71 CASUARINA, PINO AUSTRALIANO und 3.00 3.00 9.00 3.00 9.00 - - - - - - - - 9.00
72 CELOSIA und 8.00 3.00 24.00 8.00 24.00 - - - - - - - - 24.00
73 CEMENTO CONDUCTIVO 25 KG bol 8.00 80.00 640.00 8.00 640.00 - - - - - - - - 640.00
74 CEMENTO PORTLAND TIPO I (42.5KG) BOL 16.60 21.80 361.88 16.60 361.88 - - - - - - - - 361.88
75 CEMENTO PORTLAND TIPO IP (42.5KG) BOL 15,888.55 21.80 346,370.39 1,588.86 34,637.04 - 14,299.70 311,733.35 - - - - - - 346,370.39
76 CERAMICO DE 30CMX30CM m2 2.88 35.00 100.80 - - - 2.88 100.80 - - - - - 100.80
77 CERAMICO DE 60CMX60CM m2 1,119.91 46.00 51,515.86 - - - 1,119.91 51,515.86 - - - - - 51,515.86
78 CERRADURA EXTERIOR DE DOS GOLPES und 13.00 70.00 910.00 - - - 13.00 910.00 - - - - - 910.00
79 CERRADURA TIPO PERILLA P/INTERIORES pza 29.00 35.50 1,029.50 - - - 29.00 1,029.50 - - - - - 1,029.50
80 CHALECO DE SEGURIDAD und 120.00 24.00 2,880.00 120.00 2,880.00 - - - - - - - - 2,880.00
81 CINTA AISLANTE m 4,400.00 4.00 17,600.00 - - - 4,400.00 17,600.00 - - - - - 17,600.00
82 CINTA AISLANTEAUTOFUNDENTE 3/4" Ø (600 V.) und 117.00 33.00 3,861.00 - - - 117.00 3,861.00 - - - - - 3,861.00
83 CINTA DE PELIGRO rll 6.00 45.00 270.00 6.00 270.00 - - - - - - - - 270.00
84 CINTA DE SEGURIDAD ROLLO DE 5KG und 6.00 35.00 210.00 6.00 210.00 - - - - - - - - 210.00
85 CINTA SEÑALIZADORA DE BAJA TENSION m 1,287.00 0.60 772.20 1,287.00 772.20 - - - - - - - - 772.20
86 CINTA TEFLON rll 544.70 1.10 599.17 544.70 599.17 - - - - - - - - 599.17
87 CINTA VULCANIZANTE rll 3.50 30.00 105.00 3.50 105.00 - - - - - - - - 105.00
88 CIPRES und 25.00 40.00 1,000.00 - - - - - - - 25.00 1,000.00 - 1,000.00
89 CLAVELINA und 22.00 3.00 66.00 - - - - - - - 22.00 66.00 - 66.00
90 CLAVOS CON CABEZA PROMEDIO kg 2.00 2.97 5.94 2.00 5.94 - - - - - - - - 5.94
91 CLAVOS PARA CALAMINA kg 64.80 6.78 439.34 64.80 439.34 - - - - - - - - 439.34
92 CLAVOS PARA MADERA CON CABEZA 3" kg 1,843.96 4.00 7,375.84 1,843.96 7,375.84 - - - - - - - - 7,375.84
93 CODO F° GALV. DE 1/2" X 90° pza 33.00 2.50 82.50 - - - 33.00 82.50 - - - - - 82.50
94 CODO PVC SAL 1"X90º und 24.00 1.50 36.00 - - - 24.00 36.00 - - - - - 36.00
95 CODO PVC SAL 2"X90° und 129.45 1.70 220.07 - - - 129.45 220.07 - - - - - 220.07
96 CODO PVC SAL 3"X90° und 6.00 3.75 22.50 - - - 6.00 22.50 - - - - - 22.50
97 CODO PVC SAL 4"X90° und 15.00 5.80 87.00 - - - 15.00 87.00 - - - - - 87.00
98 CODO PVC SAL 6"X90º und 9.00 35.00 315.00 - - - 9.00 315.00 - - - - - 315.00
99 CODO PVC SAP 1 1/2" X 90° pza 2.00 6.00 12.00 - - - 2.00 12.00 - - - - - 12.00
100 CODO PVC SAP 1" X 45° pza 3.00 3.50 10.50 - - - 3.00 10.50 - - - - - 10.50
101 CODO PVC SAP 1" X 90° pza 6.00 3.50 21.00 - - - 6.00 21.00 - - - - - 21.00
102 CODO PVC SAP 2" X 90° pza 18.00 9.00 162.00 - - - 18.00 162.00 - - - - - 162.00
103 CODO PVC SAP 1/2" X 90° und 56.00 1.80 100.80 - - - 56.00 100.80 - - - - - 100.80
104 CODO PVC SAP 3/4"X45º und 1.00 6.00 6.00 - - - 1.00 6.00 - - - - - 6.00
105 CODO PVC SAP 3/4"X90° pza 11.00 2.80 30.80 - - - 11.00 30.80 - - - - - 30.80
106 CODOS PVC SAL 2" X 45° pza 89.25 1.70 151.73 - - - 89.25 151.73 - - - - - 151.73
107 CODOS PVC SAL 4" X 45° pza 25.20 36.00 907.20 - - - 25.20 907.20 - - - - - 907.20
108 COLUMNA PREFABRICADA DE CONCRETO ARMADO (SEGUN und 184.00 127.12 23,390.08 - - - - - 184.00 23,390.08 - - - 23,390.08
109 DISEÑO).15X.15X3.20 M
CONDUCTOR DE CU BIPLASTOFLEX 2X2.5 MM2 m 112.00 3.80 425.60 - - - - - 112.00 425.60 - - - 425.60
110 CONDUCTOR DE CU. BLANDO DE 16 mm. m 60.00 10.00 600.00 - - - - - 60.00 600.00 - - - 600.00
111 CONECTORES DE COBRE TIPO A/B und 4.00 9.00 36.00 - - - - - 4.00 36.00 - - - 36.00
112 CONEXIONES PVC-SAP 20 mm ELECTRICAS und 765.00 1.70 1,300.50 - - - - - 765.00 1,300.50 - - - 1,300.50
113 CONEXIONES PVC-SAP ELECTRICA (1") 25 mm. und 20.00 1.90 38.00 - - - - - 20.00 38.00 - - - 38.00
114 CONFITILLO m3 50.96 85.00 4,331.60 - - - 50.96 4,331.60 - - - - - 4,331.60
115 CONO DE SEGURIDAD DE PVC H=0.90M und 4.00 70.00 280.00 4.00 280.00 - - - - - - - - 280.00
116 CONTACTOR und 1.00 80.00 80.00 1.00 80.00 - - - - - - - - 80.00
117 CONTACTOR 3x20 A und 4.00 160.00 640.00 4.00 640.00 - - - - - - - - 640.00
118 CORDEL m 291.68 0.42 122.51 291.68 122.51 - - - - - - - - 122.51
119 CORDEL m 1,053.00 0.17 179.01 1,053.00 179.01 - - - - - - - - 179.01
120 CORDON DE POLIETILENO P/RELLENO DE JUNTA m 221.04 3.90 862.06 221.04 862.06 - - - - - - - - 862.06
121 CORTACIRCUITO BIPOLAR 15 A und 28.00 16.00 448.00 - - - 28.00 448.00 - - - - - 448.00
122 CRUCETA PARA CERAMICO DE 5MM. bls 104.61 5.50 575.36 - - - 104.61 575.36 - - - - - 575.36
123 CUMBRERA P/PERFIL G-ONDA pza 1.85 19.80 36.63 - - - 1.85 36.63 - - - - - 36.63
124 CURVA PVC SAP 20 mm, Diam. und 765.00 1.00 765.00 - - - 765.00 765.00 - - - - - 765.00
125 CURVA PVC SAP 25 mm, Diam. und 29.00 1.50 43.50 - - - 29.00 43.50 - - - - - 43.50
126 CURVA PVC SAP 40 mm, Diam. und 50.00 3.50 175.00 - - - 50.00 175.00 - - - - - 175.00
127 CURVA PVC SAP 50 mm, Diam. und 21.00 4.50 94.50 - - - 21.00 94.50 - - - - - 94.50
128 CURVA PVC SAP 80 mm, Diam. und 37.00 12.00 444.00 - - - 37.00 444.00 - - - - - 444.00
129 DIPLADENIA und 13.00 25.00 325.00 - - - 13.00 325.00 - - - - - 325.00
130 DISCO DE CORTE pza 11.99 16.95 203.23 - - - 11.99 203.23 - - - - - 203.23
131 DISCO DE CORTE DE P/ACERO7" und 221.21 8.25 1,824.98 - - - 221.21 1,824.98 - - - - - 1,824.98
132 DISOLVENTE D3 gln 10.75 12.50 134.38 - - - - 10.75 134.38 - - - - 134.38
133 DISOLVENTE XILOL gln 55.72 45.00 2,507.40 - - - - 55.72 2,507.40 - - - - 2,507.40
134 DISPENSADOR DE TOALLA DE CERAMICA und 8.00 33.90 271.20 - - - - 8.00 271.20 - - - - 271.20
135 DUCHA CROMADA INC.GRIF 1 LLAVE und 2.00 95.00 190.00 - - - - 2.00 190.00 - - - - 190.00
136 DUCTO DE CONCRETO DE 2 VIAS pza 30.00 26.00 780.00 - - - - 30.00 780.00 - - - - 780.00
137 ELECTROBOMBA DE 1.0HP INC./ACCESORIOS und 3.00 700.00 2,100.00 - - - - 3.00 2,100.00 - - - - 2,100.00
138 ELECTROBOMBA DE 2.0HP INC./ACCESORIOS und 1.00 800.00 800.00 - - - - 1.00 800.00 - - - - 800.00
139 EMULSION ASFALTICA CSS 1HP gln 1,968.62 18.00 35,435.16 - - - - - 1,968.62 35,435.16 - - - 35,435.16
140 EMULSION PARA IMPRIMACION gln 441.65 18.50 8,170.53 - - - - - 441.65 8,170.53 - - - 8,170.53
141 ESPEJO CON MARCO DE ALUMINIO m2 12.11 171.50 2,076.87 - - - - - - 12.11 2,076.87 - - 2,076.87
142 ESPONJA DE 1" pln 31.09 12.71 395.15 31.09 395.15 - - - - - - - - 395.15
143 EXTINTOR DE POLVO QUIMICO DE 10 KG und 2.00 150.00 300.00 2.00 300.00 - - - - - - - - 300.00
144 FAROLA CONICA MODELO SPC-70-E27 PHILIPS und 28.00 420.00 11,760.00 - - - - - 28.00 11,760.00 - - - 11,760.00
145 FERTILIZANTE kg 78.96 2.45 193.45 - - - - - 78.96 193.45 - - - 193.45
146 FIERRO CORRUGADO F'Y=4200 KG/CM2 GRADO 60 kg 28.24 2.65 74.84 28.24 74.84 - - - - - - - - 74.84
147 FORMADOR DE EMPAQUETADURA und 138.30 7.00 968.10 138.30 968.10 - - - - - - - - 968.10
PRESUPUESTO Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17
ITEM DESCRIPCION UND Total
CANTIDAD PRECIO PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL

148 FRAGUA DE COLOR kg 208.41 6.00 1,250.46 - - - - 208.41 1,250.46 - - - - 1,250.46


149 FUSIBLE TIPO C, 5 AMP. und 56.00 1.50 84.00 - - - - 56.00 84.00 - - - - 84.00
150 GASOLINA 84 OCTANOS gln 244.45 11.90 2,908.96 244.45 2,908.96 - - - - - - - - 2,908.96
151 GIGANTOGRAFIA DE 3.60X2.40M. und 1.00 350.00 350.00 1.00 350.00 - - - - - - - - 350.00
152 GRIFO DE BRONCE 1/2" und 33.00 18.00 594.00 33.00 594.00 - - - - - - - - 594.00
153 GUANTES DE CUERO PAR 50.00 10.00 500.00 50.00 500.00 - - - - - - - - 500.00
154 GUANTES DE JEBE PAR 50.00 9.50 475.00 50.00 475.00 - - - - - - - - 475.00
155 HOJA DE SIERRA pza 13.65 2.97 40.54 13.65 40.54 - - - - - - - - 40.54
156 HORMIGON m3 678.75 38.00 25,792.50 339.38 12,896.25 - - 339.38 12,896.25 - - - - - 25,792.50
157 HUMUS m3 8,133.34 0.90 7,320.01 - - - - - - - 8,133.34 7,320.01 - 7,320.01
158 IMPRIMANTE gln 389.51 25.00 9,737.75 - - - - - - - 389.51 9,737.75 - 9,737.75
159 INODORO TQUE. BAJO NORMAL BLANCO INCLUYE und 33.00 220.00 7,260.00 - - - - - 33.00 7,260.00 - - - 7,260.00
160 ACCESORIOS
INTERRUPTOR DE CONMUTACION und 7.95 18.00 143.10 - - - - - 7.95 143.10 - - - 143.10
161 INTERRUPTOR DIFERENCIAL 2x25 A, 30 mA und 2.00 75.00 150.00 - - - - - 2.00 150.00 - - - 150.00
162 INTERRUPTOR DIFERENCIAL 3x25 A, 30 mA und 3.00 250.00 750.00 - - - - - 3.00 750.00 - - - 750.00
163 INTERRUPTOR DIFERENCIAL 3x40 A, 30 mA und 1.00 270.00 270.00 - - - - - 1.00 270.00 - - - 270.00
164 INTERRUPTOR DOBLE und 30.80 14.00 431.20 - - - - - 30.80 431.20 - - - 431.20
165 INTERRUPTOR HORARIO und 1.00 100.00 100.00 - - - - - 1.00 100.00 - - - 100.00
166 INTERRUPTOR SIMPLE und 128.20 12.00 1,538.40 - - - - - 128.20 1,538.40 - - - 1,538.40
167 INTERRUPTOR TERMOMAGNETICO 2x16 A und 16.00 20.00 320.00 - - - - - 16.00 320.00 - - - 320.00
168 INTERRUPTOR TERMOMAGNETICO 2x20 A und 10.00 20.00 200.00 - - - - - 10.00 200.00 - - - 200.00
169 INTERRUPTOR TERMOMAGNETICO 2x25 A und 4.00 23.00 92.00 - - - - - 4.00 92.00 - - - 92.00
170 INTERRUPTOR TERMOMAGNETICO 3x125 A und 1.00 200.00 200.00 - - - - - 1.00 200.00 - - - 200.00
171 INTERRUPTOR TERMOMAGNETICO 3x20 A und 2.00 50.00 100.00 - - - - - 2.00 100.00 - - - 100.00
172 INTERRUPTOR TERMOMAGNETICO 3x25 A und 14.00 60.00 840.00 - - - - - 14.00 840.00 - - - 840.00
173 INTERRUPTOR TERMOMAGNETICO 3x32 A und 15.00 65.00 975.00 - - - - - 15.00 975.00 - - - 975.00
174 INTERRUPTOR TERMOMAGNETICO 3x40 A und 2.00 65.00 130.00 - - - - - 2.00 130.00 - - - 130.00
175 INTERRUPTOR TERMOMAGNETICO 3x63 A und 2.00 70.00 140.00 - - - - - 2.00 140.00 - - - 140.00
176 INTERRUPTOR TERMOMAGNETICO 3x80 A und 2.00 160.00 320.00 - - - - - 2.00 320.00 - - - 320.00
177 INTERRUPTOR TRIPLE und 15.40 20.00 308.00 - - - - - 15.40 308.00 - - - 308.00
178 JACARANDA und 26.00 25.00 650.00 - - - - - - - 26.00 650.00 - 650.00
179 JACK R-J45 PARA VOZ Y/O DATA und 16.00 12.00 192.00 - - - - - - - 16.00 192.00 - 192.00
180 JUNTA INPER WATER STOP NEOPRENE 6" m 38.54 1.00 38.54 - - - - - - - 38.54 38.54 - 38.54
181 KIT DE EMPALME RECTO Y/O DERIVACION, PARA CABLE und 35.00 28.00 980.00 - - - - 35.00 980.00 - - - - 980.00
182 N2XOH B.T
LACA DESMOLDANTE + SOLVENTE gln 52.59 144.07 7,576.64 52.59 7,576.64 - - - - - - - - 7,576.64
183 LADRILLO DE ARCILLA HERCULES I DE 24x14x10 CM. pza 140,784.62 1.50 211,176.93 28,156.92 42,235.39 - - 112,627.70 168,941.54 - - - - - 211,176.93
184 LADRILLO P/TECHO DE 15x30x30 CM 8 HCOS. und 3,277.30 3.30 10,815.09 - - - 3,277.30 10,815.09 - - - - - 10,815.09
185 LADRILLO PASTELERO 24X 24X3 CM und 5,373.60 2.90 15,583.44 - - - 5,373.60 15,583.44 - - - - - 15,583.44
186 LAMPARA DE CONTROL DE BOMBA O RELE TERMICO und 8.00 30.00 240.00 - - - - - 8.00 240.00 - - - 240.00
187 LAVATORIO DE PARED C/BLANCO INC./ACCESORIOS pza 12.00 145.00 1,740.00 - - - - - 12.00 1,740.00 - - - 1,740.00
188 LENTES DE PROTECCION und 100.00 3.50 350.00 100.00 350.00 - - - - - - - - 350.00
189 LIJA und 425.46 1.70 723.28 425.46 723.28 - - - - - - - - 723.28
190 LIJA DE CONCRETO hja 41.37 2.00 82.74 41.37 82.74 - - - - - - - - 82.74
191 LIJA PARA MADERA und 5.36 1.45 7.77 5.36 7.77 - - - - - - - - 7.77
192 LLAVE PARA URINARIOS und 8.00 38.00 304.00 - - - - - 8.00 304.00 - - - 304.00
193 MADERA TORNILLO p2 45,622.32 5.90 269,171.69 11,405.58 67,292.92 - - 34,216.74 201,878.77 - - - - - 269,171.69
194 MALLA ARPILLERA m 1,003.18 7.00 7,022.26 1,003.18 7,022.26 - - - - - - - - 7,022.26
195 MALLA COCADA DE ALAMBRE GALVANIZADO #12 X 2" m2 728.44 10.00 7,284.40 - - - - - - 728.44 7,284.40 - - 7,284.40
196 MALLA PLASTICA DE 60 GR 0.5x45M rll 6.00 60.00 360.00 6.00 360.00 - - - - - - - - 360.00
197 MARGARITA und 36.00 3.00 108.00 - - - - - - - 36.00 108.00 - 108.00
198 MARIGOLD und 20.00 3.00 60.00 - - - - - - - 20.00 60.00 - 60.00
199 MASCARA ANTIPOLVO CON FILTRO und 100.00 7.00 700.00 100.00 700.00 - - - - - - - - 700.00
200 MASILLA kg 13.58 6.78 92.07 - - - 13.58 92.07 - - - - - 92.07
201 MATERIAL CLASIFICADO PARA BASE m3 250.78 50.00 12,539.00 - - - 250.78 12,539.00 - - - - - 12,539.00
202 NIPLE DE Fº GALV. DE 1 1/2" X 1 1/2" pza 12.00 35.00 420.00 - - - - 12.00 420.00 - - - - 420.00
203 NIPLE DE FºGº DE 3/4''x3/4" und 18.00 15.00 270.00 - - - - 18.00 270.00 - - - - 270.00
204 NIPLE REDUCTOR DE 1 1/2X1/2'''' pza 36.00 4.50 162.00 - - - - 36.00 162.00 - - - - 162.00
205 NIPLE REDUCTOR DE 1X1/2'''' pza 396.00 1.50 594.00 - - - - 396.00 594.00 - - - - 594.00
206 NIPLE REDUCTOR DE 2X1/2'''' pza 36.00 5.00 180.00 - - - - 36.00 180.00 - - - - 180.00
207 OCRE kg 7.49 10.17 76.17 7.49 76.17 - - - - - - - - 76.17
208 OVALIN DE LOSA BLANCA pza 33.00 145.00 4,785.00 - - - - - 33.00 4,785.00 - - - 4,785.00
209 PALMERA PHOENIX (DACTYLIFERA) und 14.00 50.00 700.00 - - - - - - 14.00 700.00 - - 700.00
210 PALO DE EUCALIPTO DE 3" x 3.0m und 334.39 15.00 5,015.85 334.39 5,015.85 - - - - - - - - 5,015.85
211 PANTALON DE SEGURIDAD und 120.00 38.00 4,560.00 120.00 4,560.00 - - - - - - - - 4,560.00
212 PAPELERA DE LOSA BLANCA ADOSADA pza 8.00 18.00 144.00 - - - - - 8.00 144.00 - - - 144.00
213 PARANTE DE MADERA EUCALIPTO TRATADA H=3.0M und 133.00 15.00 1,995.00 133.00 1,995.00 - - - - - - - - 1,995.00
214 PEGAMENTO PARA CERAMICO X 25 KG BOL 262.36 15.00 3,935.40 - - - - - 262.36 3,935.40 - - - 3,935.40
215 PEGAMENTO PARA PVC gln 62.58 105.00 6,570.90 - - - - - 62.58 6,570.90 - - - 6,570.90
216 PEGAMENTO PARA PVC gal 2.88 84.50 242.94 - - - - - 2.88 242.94 - - - 242.94
217 PEGAMENTO PARA PVC AGUA FORDUIT gln 0.07 20.00 1.40 - - - - - 0.07 1.40 - - - 1.40
218 PEGAMENTO PVC 1/4 GALON und 0.11 20.00 2.20 - - - - - 0.11 2.20 - - - 2.20
219 PENSAMIENTO und 58.00 3.00 174.00 - - - - - - - 58.00 174.00 - 174.00
220 PERFIL "L" FIERRO 1 1/2" x 1/4" und 1.00 68.00 68.00 - - - - - - 1.00 68.00 - - 68.00
221 PERFIL GRAN ONDA 3.05mx1.10m x5mm pza 238.58 68.60 16,366.59 - - - - - - 238.58 16,366.59 - - 16,366.59
222 PERNO DE ANCLAJE P. ENCOF. 1/2"x0.50 m. pza 3.90 1.69 6.59 - - - - - - 3.90 6.59 - - 6.59
223 PERNO HEXAGONAL DE 5/16" X 3/4" pza 10.00 1.50 15.00 - - - - - - 10.00 15.00 - - 15.00
224 PERNOS DE FIJACION und 4,329.38 0.68 2,943.98 - - - - - - 4,329.38 2,943.98 - - 2,943.98
PRESUPUESTO Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17
ITEM DESCRIPCION UND Total
CANTIDAD PRECIO PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL

225 PIEDRA CHANCADA 1/2" m3 0.74 85.00 62.90 0.74 62.90 - - - - - - - - 62.90
226 PIEDRA CHANCADA DE 1/2" m3 365.29 85.00 31,049.65 182.65 15,524.83 - - 182.65 15,524.83 - - - - - 31,049.65
227 PIEDRA DE CANTO RODADO D=1/2"-1" m3 87.58 40.00 3,503.20 87.58 3,503.20 - - - - - - - - 3,503.20
228 PIEDRA GRANDE DE 6" m3 197.34 40.00 7,893.60 197.34 7,893.60 - - - - - - - - 7,893.60
229 PIEDRA GRANDE DE 8" T.M. m3 20.28 40.00 811.20 20.28 811.20 - - - - - - - - 811.20
230 PIEDRA MEDIANA DE 3" m3 17.97 40.00 718.80 17.97 718.80 - - - - - - - - 718.80
231 PIEDRA ZARANDEADA DE 1/2" m3 541.52 40.00 21,660.80 - - - 541.52 21,660.80 - - - - - 21,660.80
232 PILON CROMADO TEMPORIZADO und 45.00 130.00 5,850.00 - - - - 45.00 5,850.00 - - - - 5,850.00
233 PINTURA ANTICORROSIVA gln 107.66 42.00 4,521.72 - - - - 107.66 4,521.72 - - - - 4,521.72
234 PINTURA BARNIZ gln 5.36 45.00 241.20 - - - - 5.36 241.20 - - - - 241.20
235 PINTURA DE TRAFICO gln 72.62 55.00 3,994.10 - - - - 72.62 3,994.10 - - - - 3,994.10
236 PINTURA ESMALTE gln 143.57 45.00 6,460.65 - - - - 143.57 6,460.65 - - - - 6,460.65
237 PINTURA IMPRIMANTE gln 5.28 21.19 111.88 - - - - 5.28 111.88 - - - - 111.88
238 PINTURA LATEX MATE gln 460.82 32.00 14,746.24 - - - - 460.82 14,746.24 - - - - 14,746.24
239 PLACA PREMOLDEADA DE CONCRETO ARMADO TIPO und 1,494.65 50.85 76,002.95 - - - - - 1,494.65 76,002.95 - - - 76,002.95
240 LADRILLO DE
PLANCHA 5X50X242
ACEROCM
1.20m x 2.40m (e=1/16") pln 1.96 50.00 98.00 - - - - 1.96 98.00 - - - - 98.00
241 PLANCHA DE ACERO 1.20m x 2.40m (e=3/16") pln 0.24 240.00 57.60 - - - - 0.24 57.60 - - - - 57.60
242 PLANCHA DE ACERO 1.20m x2.40m (e=1/32") pln 21.60 50.00 1,080.00 - - - - 21.60 1,080.00 - - - - 1,080.00
243 PLANCHA DE ACERO 1.20m x2.40m (e=1/4") pln 0.05 150.00 7.50 - - - - 0.05 7.50 - - - - 7.50
244 PLANCHA DE ACERO 1.20m x2.40m (e=1/8") pln 9.45 160.00 1,512.00 - - - - 9.45 1,512.00 - - - - 1,512.00
245 PLANCHA DE ACERO 1.20m x2.40m (e=3/8") pln 1.56 460.00 717.60 - - - - 1.56 717.60 - - - - 717.60
246 PLANCHA DE ACERO 1.20m x2.40m x 2 mm pln 17.10 75.00 1,282.50 - - - - 17.10 1,282.50 - - - - 1,282.50
247 PLANCHA DE ACERO ESTRIADA DE 1.20X2.40 e=3/16'' pln 2.00 310.00 620.00 - - - - 2.00 620.00 - - - - 620.00
248 PLANCHA DE ACERO INOXIDABLE 1.20m x 2.40m (e=1/16") pln 1.75 240.00 420.00 - - - - 1.75 420.00 - - - - 420.00
249 PLANCHA DE TECKNOPORT DE 1" X 4' X8' und 17.85 14.00 249.90 - - - - 17.85 249.90 - - - - 249.90
250 PLANCHA GALVANIZADA DE 4' X 8' E=3/32" pln 12.71 60.00 762.60 - - - - 12.71 762.60 - - - - 762.60
251 PLANCHA METALICA DE 1/32" pln 4.08 50.00 204.00 - - - - 4.08 204.00 - - - - 204.00
252 PLANCHA METALICA DE 3.5 MM. pln 1.60 200.00 320.00 - - - - 1.60 320.00 - - - - 320.00
253 PLANCHA METALICA ESTRIADA DE 3/16" pln 5.23 240.00 1,255.20 - - - - 5.23 1,255.20 - - - - 1,255.20
254 PLATINA DE 1" X 3/16" pza 2.00 18.00 36.00 - - - - 2.00 36.00 - - - - 36.00
255 PLATINA DE ACERO 1" X 3/16" X 6M. pza 28.46 18.00 512.28 - - - - 28.46 512.28 - - - - 512.28
256 PLATINA DE FIERRO 3" X 3/16" pza 1.25 70.00 87.50 - - - - 1.25 87.50 - - - - 87.50
257 PONCIANA REGIA und 6.00 40.00 240.00 - - - - 6.00 240.00 - - - - 240.00
258 POSTE DE F°G° 4.5 m und 28.00 450.00 12,600.00 - - - - 28.00 12,600.00 - - - - 12,600.00
259 PRUEBA HIDRAULICA DE ESTANQUEIDAD GLB 2.00 500.00 1,000.00 - - - - - 2.00 1,000.00 - - - 1,000.00
260 PRUEBA HIDRAULICA DE SISTEMA DE AGUA GLB 1.00 500.00 500.00 - - - - - 1.00 500.00 - - - 500.00
261 PULSADOR TIPO HONGO und 8.00 40.00 320.00 - - - - - - 8.00 320.00 - - 320.00
262 RED DE SEGURIDAD GLB 1.00 780.00 780.00 1.00 780.00 - - - - - - - - 780.00
263 REDUCCION PVC SAL 3" A 2" pza 23.00 4.50 103.50 - - - - 23.00 103.50 - - - - 103.50
264 REDUCCION PVC SAL 4" A 2" pza 14.00 5.00 70.00 - - - - 14.00 70.00 - - - - 70.00
265 REDUCCION PVC SAL 4" A 3" pza 6.00 6.00 36.00 - - - - 6.00 36.00 - - - - 36.00
266 REDUCCION PVC SAP 2" A 1" pza 1.00 6.00 6.00 - - - - 1.00 6.00 - - - - 6.00
267 REDUCCION PVC SAP 3/4" A 1/2" pza 41.00 1.50 61.50 - - - - 41.00 61.50 - - - - 61.50
268 REDUCCION PVC SAP 1 1/2" A 1" pza 11.00 4.00 44.00 - - - - 11.00 44.00 - - - - 44.00
269 REDUCCION PVC SAP 1 1/2" A 3/4" pza 6.00 4.00 24.00 - - - - 6.00 24.00 - - - - 24.00
270 REDUCCION PVC SAP 1" A 1/2" pza 4.00 1.90 7.60 - - - - 4.00 7.60 - - - - 7.60
271 REDUCCION PVC SAP 1" A 3/4" pza 8.00 2.00 16.00 - - - - 8.00 16.00 - - - - 16.00
272 REDUCCION PVC SAP 2" A 1 1/2" pza 7.00 5.00 35.00 - - - - 7.00 35.00 - - - - 35.00
273 REDUCCION PVC SAP 2" A 1" pza 2.00 5.00 10.00 - - - - 2.00 10.00 - - - - 10.00
274 REDUCCION PVC SAP 2" A 3/4" pza 3.00 8.00 24.00 - - - - 3.00 24.00 - - - - 24.00
275 REGISTRO ROSCADO DE BRONCE DE 4" pza 47.00 18.00 846.00 - - - - 47.00 846.00 - - - - 846.00
276 REGLA DE MADERA p2 3,509.43 5.90 20,705.64 3,509.43 20,705.64 - - - - - - - - 20,705.64
277 RELE TERMICO und 4.00 158.00 632.00 - - - - - 4.00 632.00 - - - 632.00
278 RODOPLAST PARA BORDE DE CERAMICOS m 329.18 3.50 1,152.13 - - - - - 329.18 1,152.13 - - - 1,152.13
279 SAUCE LLORON und 45.00 15.20 684.00 - - - - - 45.00 684.00 - - - 684.00
280 SELLADOR PARA TERRAZOS gln 0.94 306.00 287.64 - - - - - 0.94 287.64 - - - 287.64
281 SELLO ELASTOMERICO DE POLIURETANO gln 21.46 35.00 751.10 - - - - - 21.46 751.10 - - - 751.10
282 SEMILLA DE GRAS AMERICANO kg 78.96 85.00 6,711.60 - - - - - 78.96 6,711.60 - - - 6,711.60
283 SILICONA und 36.02 11.02 396.94 - - - - - 36.02 396.94 - - - 396.94
284 SOLDADURA kg 141.87 13.50 1,915.25 - - - - 141.87 1,915.25 - - - - 1,915.25
285 SOMBRERO DE VENTILACION PVC SAL 2" und 5.00 4.00 20.00 - - - - 5.00 20.00 - - - - 20.00
286 SUMIDERO CROMADO DE 2" und 44.00 5.50 242.00 - - - - 44.00 242.00 - - - - 242.00
287 TABLERO METALICO TRIFASICO, 12 SALIDAS und 4.00 700.00 2,800.00 - - - - 4.00 2,800.00 - - - - 2,800.00
288 TABLERO METALICO TRIFASICO, 24 SALIDAS und 3.00 800.00 2,400.00 - - - - 3.00 2,400.00 - - - - 2,400.00
289 TABLERO METALICO TRIFASICO, 6 SALIDAS und 3.00 600.00 1,800.00 - - - - 3.00 1,800.00 - - - - 1,800.00
290 TANQUE ELEVADO DE POLIETILENO DE 1,100 LTS und 3.00 550.00 1,650.00 - - - - 3.00 1,650.00 - - - - 1,650.00
291 INC./ACCESORIOS
TAPA C/MARCO FºFº DE AGUA 12"X12" pza 36.00 28.00 1,008.00 - - - - 36.00 1,008.00 - - - - 1,008.00
292 TAPA C/MARCO FºFº DE DESAGUE 12" X 24" pza 18.00 38.00 684.00 - - - - 18.00 684.00 - - - - 684.00
293 TAPA GANG und 8.00 7.00 56.00 - - - - 8.00 56.00 - - - - 56.00
294 TAPON R/H DE PVC 1" pza 13.00 5.00 65.00 - - - - 13.00 65.00 - - - - 65.00
295 TAPONES AURICULARES und 100.00 3.50 350.00 100.00 350.00 - - - - - - - - 350.00
296 TEE PVC SAL 1 1/2" X 1 1/2" pza 6.00 2.00 12.00 - - - - 6.00 12.00 - - - - 12.00
297 TEE PVC SAL 1" X 1" pza 6.00 2.00 12.00 - - - - 6.00 12.00 - - - - 12.00
298 TEE PVC SAL 4" X 4" pza 47.00 8.00 376.00 - - - - 47.00 376.00 - - - - 376.00
299 TEE PVC SAP 1 1/2" pza 23.00 10.00 230.00 - - - - 23.00 230.00 - - - - 230.00
300 TEE PVC SAP 1" pza 68.00 3.80 258.40 - - - - 68.00 258.40 - - - - 258.40
301 TEE PVC SAP 1/2" pza 83.00 3.00 249.00 - - - - 83.00 249.00 - - - - 249.00
PRESUPUESTO Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17
ITEM DESCRIPCION UND Total
CANTIDAD PRECIO PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL

302 TEE PVC SAP 2" pza 24.00 14.00 336.00 - - - - 24.00 336.00 - - - - 336.00
303 TEE PVC SAP 3/4" pza 7.00 3.80 26.60 - - - - 7.00 26.60 - - - - 26.60
304 TEE SANITARIA SIMPLE PVC SAL 2" X 2" pza 2.00 5.80 11.60 - - - - 2.00 11.60 - - - - 11.60
305 TEE SANITARIA SIMPLE PVC SAL 4" X 2" pza 10.00 9.00 90.00 - - - - 10.00 90.00 - - - - 90.00
306 TEE SANITARIA SIMPLE PVC SAL 4" X 4" pza 10.00 12.00 120.00 - - - - 10.00 120.00 - - - - 120.00
307 TEMPLADOR PLATINA 2''X3/16" und 31.00 5.00 155.00 - - - - 31.00 155.00 - - - - 155.00
308 TENSOR DE 3/8" und 11.10 45.00 499.50 - - - - 11.10 499.50 - - - - 499.50
309 TERMINAL R/M DE 1'' pza 36.00 3.50 126.00 - - - - 36.00 126.00 - - - - 126.00
310 TERMINAL R/M DE 1 1/2'' pza 36.00 6.00 216.00 - - - - 36.00 216.00 - - - - 216.00
311 TERMINAL R/M DE PVC 1" pza 10.00 5.00 50.00 - - - - 10.00 50.00 - - - - 50.00
312 TERRAZO PREMEZCLADO GRANO 23 COLOR BLANCO BLS BOL 231.87 60.00 13,912.20 - - - - 231.87 13,912.20 - - - - 13,912.20
313 40 KG
THINER gln 121.75 17.00 2,069.75 121.75 2,069.75 - - - - - - - - 2,069.75
314 TIERRA DE CHACRA m3 1,974.11 30.00 59,223.30 - - - - - - 1,974.11 59,223.30 - - 59,223.30
315 TIERRA DE CULTIVO m3 8.00 25.00 200.00 - - - - - - 8.00 200.00 - - 200.00
316 TILLANDSIA und 22.00 10.00 220.00 - - - - - - 22.00 220.00 - - 220.00
317 TIZA kg 42.12 1.50 63.18 42.12 63.18 - - - - - - - - 63.18
318 TIZA EN POLVO kg 4.14 1.27 5.26 4.14 5.26 - - - - - - - - 5.26
319 TOMACORRIENTE DOBLE CON LINEA A TIERRA und 96.00 14.00 1,344.00 - - - 96.00 1,344.00 - - - - - 1,344.00
320 TRAMPA "P" PVC SAL DE 2" und 44.00 12.00 528.00 - - - 44.00 528.00 - - - - - 528.00
321 TRAMPA PVC TIPO BOTELLA P/LAVATORIO pza 45.00 9.50 427.50 - - - 45.00 427.50 - - - - - 427.50
322 TRIPLAY DE 4'x8'x 10 mm pln 84.45 65.00 5,489.25 - - - 84.45 5,489.25 - - - - - 5,489.25
323 TRIPLAY DE 4'x8'x 4 mm pln 97.20 27.00 2,624.40 - - - 97.20 2,624.40 - - - - - 2,624.40
324 TRIPLAY LUPUNA DE 4'x8'x 10 mm pln 23.84 57.63 1,373.90 - - - 23.84 1,373.90 - - - - - 1,373.90
325 TUB. PVC SAP PRESION C-10 C/R. 1" x 5m und 168.75 24.00 4,050.00 - - - 168.75 4,050.00 - - - - - 4,050.00
326 TUB. PVC SAP PRESION C-10 C/R. 1/2" x 5m und 30.30 10.00 303.00 - - - 30.30 303.00 - - - - - 303.00
327 TUB. PVC SAP PRESION C-10 C/R. 3/4" x 5m und 179.29 18.00 3,227.22 - - - 179.29 3,227.22 - - - - - 3,227.22
328 TUB. PVC SAP PRESION C-10 EC 1 1/2" x 5m und 89.00 42.00 3,738.00 - - - 89.00 3,738.00 - - - - - 3,738.00
329 TUBERIA PVC SAL 1" x 3m pza 17.15 8.00 137.20 - - - 17.15 137.20 - - - - - 137.20
330 TUBERIA PVC SAL 2" PERFORADA und 7.35 19.00 139.65 - - - 7.35 139.65 - - - - - 139.65
331 TUBERIA PVC SAL 2" x 3m pza 227.29 11.00 2,500.19 - - - 227.29 2,500.19 - - - - - 2,500.19
332 TUBERIA PVC SAL 3" PERFORADA und 1.05 33.00 34.65 - - - 1.05 34.65 - - - - - 34.65
333 TUBERIA PVC SAL 3" x 3m pza 47.33 17.00 804.61 - - - 47.33 804.61 - - - - - 804.61
334 TUBERIA PVC SAL 4" PERFORADA und 21.00 45.00 945.00 - - - 21.00 945.00 - - - - - 945.00
335 TUBERIA PVC SAL 4" x 3m pza 296.49 22.00 6,522.78 - - - 296.49 6,522.78 - - - - - 6,522.78
336 TUBERIA PVC SAL 6"X6m m 47.08 129.00 6,073.32 - - - 47.08 6,073.32 - - - - - 6,073.32
337 TUBERIA PVC SAP 20mm, Diam und 2,040.00 1.50 3,060.00 - - - 2,040.00 3,060.00 - - - - - 3,060.00
338 TUBERIA PVC SAP 25mm, Diam und 147.50 5.20 767.00 - - - 147.50 767.00 - - - - - 767.00
339 TUBERIA PVC SAP 40mm, Diam und 175.00 12.50 2,187.50 - - - 175.00 2,187.50 - - - - - 2,187.50
340 TUBERIA PVC SAP 50mm, Diam und 73.50 13.50 992.25 - - - 73.50 992.25 - - - - - 992.25
341 TUBERIA PVC SAP 80mm, Diam und 129.50 32.00 4,144.00 - - - 129.50 4,144.00 - - - - - 4,144.00
342 TUBERIA PVC SAP PRESION C-10 EC. 2" X 5m und 176.25 52.00 9,165.00 - - - 176.25 9,165.00 - - - - - 9,165.00
343 TUBO ABAS.CU.FLEX.TERM/M-H 1/2"x1/2"30cm und 45.00 12.00 540.00 - - - - - 45.00 540.00 - - - 540.00
344 TUBO ABAS.CU.FLEX.TERM/M-H 1/2"x7/8"30cm und 33.00 12.00 396.00 - - - - - 33.00 396.00 - - - 396.00
345 TUBO CIRCULAR D= 1"X3 mm und 5.19 45.00 233.55 - - - - - 5.19 233.55 - - - 233.55
346 TUBO CIRCULAR D= 1/2"X1.8 mm und 7.82 18.00 140.76 - - - - - 7.82 140.76 - - - 140.76
347 TUBO CIRCULAR D= 2"X3 mm und 9.75 155.00 1,511.25 - - - - - 9.75 1,511.25 - - - 1,511.25
348 TUBO CUADRADO DE FIERRO NEGRO 1 1/2" X 1 1/2" X 1.5 und 9.56 38.00 363.28 - - - - - 9.56 363.28 - - - 363.28
349 mm
TUBO CUADRADO DE FIERRO NEGRO 1 1/4" X 1 1/4" X 1.5 und 9.56 32.00 305.92 - - - - - 9.56 305.92 - - - 305.92
350 mm
TUBO CUADRADO DE FIERRO NEGRO 1" X 1" X 1.5 mm und 9.56 25.00 239.00 - - - - - 9.56 239.00 - - - 239.00
351 TUBO CUADRADO DE FIERRO NEGRO 1" X 1" X 2 mm und 39.00 32.00 1,248.00 - - - - - 39.00 1,248.00 - - - 1,248.00
352 TUBO CUADRADO DE FIERRO NEGRO 2" X 2" X 2 mm und 47.11 60.00 2,826.60 - - - - - 47.11 2,826.60 - - - 2,826.60
353 TUBO CUADRADO DE FIERRO NEGRO 2" X 2" X 3 mm und 83.33 90.00 7,499.70 - - - - - 83.33 7,499.70 - - - 7,499.70
354 TUBO CUADRADO DE FIERRO NEGRO 3" X 2" X 3 mm und 83.92 135.00 11,329.20 - - - - - 83.92 11,329.20 - - - 11,329.20
355 TUBO CUADRADO DE FIERRO NEGRO 4" X 2" X 2 mm und 3.68 90.00 331.20 - - - - - 3.68 331.20 - - - 331.20
356 TUBO DE FIERRO NEGRO DE 1 1/2" X 1.5 MM. und 0.70 65.00 45.50 - - - - - 0.70 45.50 - - - 45.50
357 TUBO DE FIERRO NEGRO DE 1"X1'' X 1.2 MM. und 37.80 25.00 945.00 - - - - - 37.80 945.00 - - - 945.00
358 TUBO DE FIERRO NEGRO DE 2"X2'' X 2.0 MM. und 1.06 65.00 68.90 - - - - - 1.06 68.90 - - - 68.90
359 TUBO DE FIERRO NEGRO DE 4" X 2.0 MM. m 43.30 90.00 3,897.00 - - - - - 43.30 3,897.00 - - - 3,897.00
360 TUBO DE FIERRO NEGRO DE 4''X2" X 2.5MM. und 6.74 75.00 505.50 - - - - - 6.74 505.50 - - - 505.50
361 TUBO DE FIERRO NEGRO DE 4''X2" X 3MM. und 11.40 105.00 1,197.00 - - - - - 11.40 1,197.00 - - - 1,197.00
362 TUBO NEGRO DE 1 1/2" X 1 1/2" X 3mm und 18.83 40.00 753.20 - - - - - 18.83 753.20 - - - 753.20
363 TUBO NEGRO DE 2" X 2" X 3mm und 16.26 90.00 1,463.40 - - - - - 16.26 1,463.40 - - - 1,463.40
364 TUBO NEGRO DE 3" X 3" X 3mm und 9.75 145.00 1,413.75 - - - - - 9.75 1,413.75 - - - 1,413.75
365 TUBO RECTANGULAR DE FIERRO NEGRO DE 2" X 3" X 4 mm und 46.20 168.00 7,761.60 - - - - - 46.20 7,761.60 - - - 7,761.60
366 TUBO RECTANGULAR DE FIERRO NEGRO DE 4" X 4" X 3 mm und 8.20 140.00 1,148.00 - - - - - 8.20 1,148.00 - - - 1,148.00
367 TUBO RECTANGULAR DE FIERRO NEGRO DE 6" X 4" X 2 mm und 12.90 125.00 1,612.50 - - - - - 12.90 1,612.50 - - - 1,612.50
368 TUBO REDONDO DE FIERRO NEGRO 2" X 2 mm und 99.60 90.00 8,964.00 - - - - - 99.60 8,964.00 - - - 8,964.00
369 TUERCA GALVANIZADA DE 1/2" pza 80.00 0.50 40.00 - - - - - 80.00 40.00 - - - 40.00
370 TUERCA GALVANIZADA DE 3/8" pza 31.00 0.50 15.50 - - - - - 31.00 15.50 - - - 15.50
371 UNION PR PVC SAP P/AGUA DE 1 1/2" und 47.35 5.00 236.75 - - - 47.35 236.75 - - - - - 236.75
372 UNION PR PVC SAP P/AGUA DE 1" und 89.78 3.00 269.34 - - - 89.78 269.34 - - - - - 269.34
373 UNION PR PVC SAP P/AGUA DE 1/2" und 9.98 1.50 14.97 - - - 9.98 14.97 - - - - - 14.97
374 UNION PR PVC SAP P/AGUA DE 2" und 93.77 8.00 750.16 - - - 93.77 750.16 - - - - - 750.16
375 UNION PR PVC SAP P/AGUA DE 3/4" und 53.87 2.30 123.90 - - - 53.87 123.90 - - - - - 123.90
376 UNION PVC SAP 20 mm, Diam. und 765.00 1.00 765.00 - - - 765.00 765.00 - - - - - 765.00
377 UNION PVC SAP 25 mm, Diam. und 51.50 1.50 77.25 - - - 51.50 77.25 - - - - - 77.25
378 UNION PVC SAP 40 mm, Diam. und 175.00 3.50 612.50 - - - 175.00 612.50 - - - - - 612.50
PRESUPUESTO Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17
ITEM DESCRIPCION UND Total
CANTIDAD PRECIO PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL

379 UNION PVC SAP 50 mm, Diam. und 73.50 4.50 330.75 - - - 73.50 330.75 - - - - - 330.75
380 UNION PVC SAP 80 mm, Diam. und 129.50 7.20 932.40 - - - 129.50 932.40 - - - - - 932.40
381 UNION UNIVERSAL DE PVC SAP 1 1/2" und 30.00 13.00 390.00 - - - 30.00 390.00 - - - - - 390.00
382 UNION UNIVERSAL DE PVC SAP 1" und 25.00 8.00 200.00 - - - 25.00 200.00 - - - - - 200.00
383 UNION UNIVERSAL DE PVC SAP 1/2" und 108.00 3.00 324.00 - - - 108.00 324.00 - - - - - 324.00
384 UNION UNIVERSAL DE PVC SAP 2" und 30.00 25.00 750.00 - - - 30.00 750.00 - - - - - 750.00
385 UNION UNIVERSAL DE PVC SAP 3/4" und 27.00 5.00 135.00 - - - 27.00 135.00 - - - - - 135.00
386 UÑAS PARA LAVATORIO pza 12.00 4.00 48.00 - - - 12.00 48.00 - - - - - 48.00
387 URINARIO PICO COLOR BLANCO INC./ACCES. und 8.00 170.00 1,360.00 - - - 8.00 1,360.00 - - - - - 1,360.00
388 VALVULA CHECK DE BRONCE DE 1 1/2" und 10.00 65.00 650.00 - - - 10.00 650.00 - - - - - 650.00
389 VALVULA CHECK DE BRONCE DE 1" und 13.00 49.00 637.00 - - - 13.00 637.00 - - - - - 637.00
390 VALVULA CHECK DE BRONCE DE 2" und 4.00 150.00 600.00 - - - 4.00 600.00 - - - - - 600.00
391 VALVULA CHECK DE BRONCE DE 3/4" und 9.00 35.00 315.00 - - - 9.00 315.00 - - - - - 315.00
392 VALVULA COMPUERTA DE BRONCE DE 1 1/2" und 4.00 55.00 220.00 - - - 4.00 220.00 - - - - - 220.00
393 VALVULA COMPUERTA DE BRONCE DE 1" und 10.00 48.00 480.00 - - - 10.00 480.00 - - - - - 480.00
394 VALVULA COMPUERTA DE BRONCE DE 1" und 4.00 35.00 140.00 - - - 4.00 140.00 - - - - - 140.00
395 VALVULA COMPUERTA DE BRONCE DE 1/2" und 18.00 28.00 504.00 - - - 18.00 504.00 - - - - - 504.00
396 VALVULA COMPUERTA DE BRONCE DE 2" und 10.00 100.00 1,000.00 - - - 10.00 1,000.00 - - - - - 1,000.00
397 VALVULA COMPUERTA DE BRONCE DE 3/4" und 9.00 35.00 315.00 - - - 9.00 315.00 - - - - - 315.00
398 VALVULA DE COMPUERTA DE BRONCE DE 1 1/2'' und 6.00 55.00 330.00 - - - 6.00 330.00 - - - - - 330.00
399 VARILLA DE COBRE DE 3/4" X 2.40 m und 4.00 155.00 620.00 - - - 4.00 620.00 - - - - - 620.00
400 VILCA und 6.00 25.00 150.00 - - - 6.00 150.00 - - - - - 150.00
401 WINCHA METALICA DE 50 m und 1.05 40.00 42.12 - - - 1.05 42.12 - - - - - 42.12
402 YEE PVC SAL DE 2" X 2" pza 36.00 4.50 162.00 - - - 36.00 162.00 - - - - - 162.00
403 YEE PVC SAL DE 4" X 2" pza 42.00 6.50 273.00 - - - 42.00 273.00 - - - - - 273.00
404 YEE PVC SAL DE 4" X 4" pza 41.15 10.50 432.08 - - - 41.15 432.08 - - - - - 432.08
405 YEE PVC SAL DE 6" X 2" pza 4.00 32.00 128.00 - - - 4.00 128.00 - - - - - 128.00
406 YEE PVC SAL DE 6" X 4" pza 5.00 35.00 175.00 - - - 5.00 175.00 - - - - - 175.00
407 YESO (12KG) BOL 88.60 6.00 531.60 88.60 531.60 - - - - - - - - 531.60
408 ZAPATOS DE SEGURIDAD (PUNTA DE ACERO) PAR 100.00 75.00 7,500.00 100.00 7,500.00 - - - - - - - - 7,500.00

COSTO DIRECTO 2,267,324.39 394,729.33 60,950.94 389,344.27 737,285.06 176,802.37 383,696.02 103,095.50 21,420.90 - 2,267,324.39
AVANCE PORCENTUAL % 17.41% 2.69% 17.17% 32.52% 7.80% 16.92% 4.55% 0.94% 0.00% 100.00
AVANCE PORCENTUAL % 17.41% 20.10% 37.27% 69.79% 77.59% 94.51% 99.06% 100.00% 100.00%
CRONOGRAMA DE UTILIZACION DE MAQUINARIA Y EQUIPOS
ENTIDAD: MUNICIPALIDAD DISTRITAL CORONEL GREGORIO ALBARRACIN LANCHIPA

PROYECTO: CREACION DE LOS SERVICIOS MUNICIPALES DE INHUMACION EN EL SECTOR VIÑANI, DISTRITO DE GREGORIO ALBARRACIN LANCHIPA - TACNA-TACNA

PRESUPUESTO Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17
ITEM DESCRIPCION UND Total
CANTIDAD PRECIO TOTAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL

1 HERRAMIENTAS MANUALES %MO 1.00 47,326.43 47,326.43 0.80 37,861.14 - - 0.20 9,465.29 - - - - - 47,326.43
2 PRISMA hm 70.88 10.00 708.80 70.88 708.80 - - - - - - - - 708.80
3 EQUIPO DE PINTURA hm 657.57 4.24 2,788.10 - - - - - - - 657.57 2,788.10 - 2,788.10
4 VOLQUETE DE 15 M3 hm 730.50 150.00 109,575.00 365.25 54,787.50 - - 365.25 54,787.50 - - - - - 109,575.00
5 CAMION CISTERNA (AGUA) 2,500 gl hm 47.10 140.00 6,594.00 18.84 2,637.60 - - 28.26 3,956.40 - - - - - 6,594.00
6 CAMION BARANDA 4 TON. hm 48.00 106.00 5,088.00 - - 48.00 5,088.00 - - - - - - 5,088.00
7 EQUIPO DE SOLDAR hm 644.84 8.47 5,461.79 - - - - - - - 644.84 5,461.79 - 5,461.79
8 MOCHILA PULVERIZADORA hm 614.76 4.24 2,606.58 - - 92.21 390.99 92.21 390.99 122.95 521.32 92.21 390.99 92.21 390.99 61.48 260.66 61.48 260.66 2,606.58
9 ANDAMIO METALICO hm 9,263.15 3.50 32,421.03 - - 926.32 3,242.10 926.32 3,242.10 1,852.63 6,484.21 1,852.63 6,484.21 1,852.63 6,484.21 926.32 3,242.10 926.32 3,242.10 32,421.03
10 CIZALLA PARA CORTE DE FIERRO hm 1,023.89 3.60 3,686.00 - - 307.17 1,105.80 102.39 368.60 307.17 1,105.80 307.17 1,105.80 - - - 3,686.00
11 COMPRESORA NEUMATICA 150 HP 380-590 PCM hm 12.05 105.93 1,276.46 12.05 1,276.46 - - - - - - - - 1,276.46
12 COMPRESORA NEUMATICA 125 HP hm 9.33 50.00 466.50 9.33 466.50 - - - - - - - - 466.50
13 COMPACTADOR VIBR. TIPO PLANCHA 8 HP hm 1,300.40 13.00 16,905.20 - - - - - 390.12 5,071.56 390.12 5,071.56 260.08 3,381.04 260.08 3,381.04 16,905.20
14 RODILLO LISO VIBR AUTOP 70-100 HP 7-9 T. hm 47.10 180.00 8,478.00 - - - - - - - 47.10 8,478.00 - 8,478.00
15 RODILLO TANDEM VIB.AUTOP 111-130HP 9-11T hm 6.63 180.00 1,193.40 - - - - - - - 6.63 1,193.40 - 1,193.40
RODILLO NEUMATICO AUTOPROPULSADO 126 HP
16 hm 9.33 180.00 1,679.40 - - - - - - - 9.33 1,679.40 - 1,679.40
10 ton
17 TRACTOR SOBRE LLANTAS DE 200-250 HP hm 292.74 180.00 52,693.20 292.74 52,693.20 - - - - - - - - 52,693.20
18 CARGADOR FRONTAL DE 3M3 hm 190.86 180.00 34,354.80 95.43 17,177.40 95.43 17,177.40 - - - - - - - 34,354.80
19 BARREDORA MECANICA 10-20 HP 7 P.LONG. hm 4.46 117.00 521.82 - - - - - - - 4.46 521.82 - 521.82
20 MARTILLO NEUMATICO DE 24 Kg. hm 12.05 20.00 241.00 12.05 241.00 - - - - - - - - 241.00
21 VIBRADOR DE CONCRETO 4 HP 1.5" hm 1,145.27 13.00 14,888.51 - - 171.79 2,233.28 171.79 2,233.28 171.79 2,233.28 171.79 2,233.28 229.05 2,977.70 114.53 1,488.85 114.53 1,488.85 14,888.51
22 MOTONIVELADORA DE 125 HP hm 76.64 180.00 13,795.20 - - - - - - - 76.64 13,795.20 - 13,795.20
23 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 hm 1,347.52 20.00 26,950.40 - - 202.13 4,042.56 202.13 4,042.56 202.13 4,042.56 202.13 4,042.56 269.50 5,390.08 134.75 2,695.04 134.75 2,695.04 26,950.40
24 WINCHE DE DOS BALDES (350KG)M.E. 3.6HP hm 147.09 15.00 2,206.35 - - - - 36.77 551.59 36.77 551.59 36.77 551.59 36.77 551.59 - 2,206.35
25 CAMION IMPRIMADOR DE 2300 gl hm 4.46 180.00 802.80 - - - - - - - 4.46 802.80 - 802.80
26 CAMION GRUA (BRAZO ARTICULADO) hm 652.70 101.69 66,373.06 - - - 652.70 66,373.06 - - - - - 66,373.06
27 ESTACION TOTAL hm 141.76 20.00 2,835.20 141.76 2,835.20 - - - - - - - - 2,835.20
28 PULIDORA DE TERRAZOS hm 58.45 20.00 1,169.00 - - - - - 58.45 1,169.00 - - - 1,169.00
29 LUXOMETRO he 8.00 40.00 320.00 - - - - - - 8.00 320.00 - - 320.00
30 TELUROMETRO he 8.00 60.00 480.00 - - - - - - 8.00 480.00 - - 480.00
31 MEGOMETRO he 8.00 70.00 560.00 - - - - - - 8.00 560.00 - - 560.00
32 MULTIMETRO he 8.00 10.00 80.00 - - - - - - 8.00 80.00 - - 80.00
33 COMPACTADORA VIBRATORIA TIPO PLANCHA 7 HP hm 94.77 17.00 1,611.12 - - - - - 94.77 1,611.12 - - - 1,611.12

COSTO DIRECTO 466,137.16 170,684.80 17,177.40 16,102.73 144,859.78 14,938.75 22,660.10 22,306.12 46,339.79 11,067.69 466,137.16
AVANCE PORCENTUAL % 36.62% 3.69% 3.45% 31.08% 3.20% 4.86% 4.79% 9.94% 2.37% 100.00
AVANCE ACUMULADO % 36.62% 40.30% 43.76% 74.83% 78.04% 82.90% 87.68% 97.63% 100.00%
CRONOGRAMA DE REALIZACION DE SERVICIOS Y/O SUBCONTRATOS
ENTIDAD: MUNICIPALIDAD DISTRITAL CORONEL GREGORIO ALBARRACIN LANCHIPA

PROYECTO: “MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA I.E.I. N° 446 EN LA ASOC. VIV. VILLA VIÑANI - VIÑANI II ETAPA, EN EL DISTRITO CRNL. GREGORIO ALBARRACIN LANCHIPA - TACNA - TACNA”

PRESUPUESTO PROGRAMADO
ITEM DESCRIPCION UND Total
CANTIDAD PRECIO PARCIAL Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17
1 SUMINISTRO E INSTALACION DE DIVISIONES DE m2 82.30 211.86 17,436.08 17,436.08 S/. 17,436.08
2 ALUMINIO
SC CON PANELES
ELABORACION DE MELAMINA
DEL PLAN DE 18MM
DE SEGURIDAD Y SALUD EN SERV 1.00 2,523.00 2,523.00 2,523.00 S/. 2,523.00
INC/PUERTAS
EL TRABAJO
3 SC CAPACITACION EN SEGURIDAD Y SALUD mes 10.00 700.00 7,000.00 777.78 777.78 777.78 777.78 777.78 777.78 777.78 777.78 777.78 S/. 7,000.00
4 SC MATERIALES DE TRABAJO PARA CAPACITACION SERV 9.00 150.00 1,350.00 150.00 150.00 150.00 150.00 150.00 150.00 150.00 150.00 150.00 S/. 1,350.00
5 SC ALQUILER DE EQUIPO PARA CAPACITACION SERV 9.00 300.00 2,700.00 300.00 300.00 300.00 300.00 300.00 300.00 300.00 300.00 300.00 S/. 2,700.00
6 SC REVISION MECANICA DEL CORRECTO SERV 9.00 300.00 2,700.00 900.00 900.00 900.00 S/. 2,700.00
7 FUNCIONAMIENTO DE LOS
SC ASIENTO DE MADERA EQUIPOS
E=2" CON ACABADO E und 20.00 500.00 10,000.00 10,000.00 S/. 10,000.00
8 INSTALADO
SC CERCO METALICO SEGUN DISEÑO m2 35.63 400.00 14,252.00 14,252.00 S/. 14,252.00
9 SC LETRAS DE ACERO QUIRURGICO CON BASE und 2.00 9,500.00 19,000.00 19,000.00 S/. 19,000.00
10 METALICA
SC SERVICIOS HIGIENICOS QUIMICOS PORTATILES und 27.00 350.00 9,450.00 1,050.00 1,050.00 1,050.00 1,050.00 1,050.00 1,050.00 1,050.00 1,050.00 1,050.00 S/. 9,450.00
11 SUM. E INST. DE MAMPARA VIDRIO TEMPLADO E=8mm m2 46.36 223.00 10,338.28 10,338.28 S/. 10,338.28
12 SC BASURERO METALICO REVESTIDO DE MADERA INC. und 8.00 430.00 3,440.00 3,440.00 S/. 3,440.00
13 INST.
SUM. E INST. DE VENTANA TIPO SISTEMA CON VIDRIO m2 74.27 190.00 14,111.30 14,111.30 S/. 14,111.30
14 TEMPLADO
SC 6MM Y MARCO
CONSTRUCCION DE METALICA,
DE CRUZ ALUMINIO SEGUN DISEÑO und 1.00 6,549.50 6,549.50 6,549.50 S/. 6,549.50
15 A TODO
SC COSTO DE ESCULTURA ANGEL (SEGUN
ELABORACION SERV 1.00 8,000.00 8,000.00 8,000.00 S/. 8,000.00
16 DISEÑO)
SC ELABORACION DE ESCULTURA VIRGEN (SEGUN SERV 1.00 17,000.00 17,000.00 17,000.00 S/. 17,000.00
17 DISEÑO)
SC ELABORACION DE ESCULTURA 2 ANGELES (SEGUN SERV 1.00 4,000.00 4,000.00 4,000.00 S/. 4,000.00
18 DISEÑO)
SC FALSO CIELO RASO CON PLANCHA SUPERBOARD m2 412.80 53.00 21,878.40 21,878.40 S/. 21,878.40
19 E=4MM
SC PUERTA DE MADERA CEDRO MACHIEMBRADA SIMPLE m2 4.77 450.00 2,146.50 2,146.50 S/. 2,146.50
20 SC TABIQUE SISTEMA DRYWALL CON PLACA DE YESO m2 44.81 119.80 5,368.24 5,368.24 S/. 5,368.24
21 SC VENTANA DE VIDRIO TEMPLADO 0.6X1.85M INC. und 6.00 250.00 1,500.00 1,500.00 S/. 1,500.00
22 ACCES. Y COLOCACION
SC VENTANA DE VIDRIO TEMPLADO 0.35X1.0 M INC. und 46.00 135.00 6,210.00 6,210.00 S/. 6,210.00
23 ACCES. Y COLOCACION
SC MAMPARA DE VIDRIO TEMPLADO 4.35X2.30 M INC. und 2.00 3,100.00 6,200.00 6,200.00 S/. 6,200.00
24 ACCES.
SC Y COLOCACION
MAMPARA DE VIDRIO TEMPLADO 5.27X2.30 M INC. und 2.00 3,700.00 7,400.00 7,400.00 S/. 7,400.00
25 ACCES. Y COLOCACION
SC MAMPARA DE VIDRIO TEMPLADO M-1(INCLUYE und 1.00 2,750.00 2,750.00 2,750.00 S/. 2,750.00
26 ACCESORIOS
SC MAMPARA DE A TODO COSTO)
VIDRIO TEMPLADO M-2(INCLUYE und 1.00 2,850.00 2,850.00 2,850.00 S/. 2,850.00
27 ACCESORIOS
SC MAMPARA DE A TODO COSTO)
VIDRIO TEMPLADO M-3 (INCLUYE und 1.00 3,320.00 3,320.00 3,320.00 S/. 3,320.00
28 ACCESORIOS
SC MAMPARA DE A TODO COSTO)
VIDRIO TEMPLADO M-4 (INCLUYE und 1.00 1,500.00 1,500.00 1,500.00 S/. 1,500.00
29 ACCESORIOS A TODODRYWALL
SC TABIQUE SITEMA COSTO) CON PLANCHA m2 58.67 109.00 6,395.03 6,395.03 S/. 6,395.03
30 FIBROCEMENTO
SC E=8MM YADOSADO
LOGOTIPO METALICO LANA DE VIDRIO
A MURO SEGUN und 2.00 123.00 246.00 246.00 S/. 246.00
31 DETALLE
SC ELABORACION DE CRUZ DE MADERA (SEGUN SERV 1.00 280.00 280.00 280.00 S/. 280.00
32 DISEÑO)
SC CRUZ METALICA EN CAPILLA (SEGUN DISEÑO) SERV 1.00 343.38 343.38 343.38 S/. 343.38
33 SC LOGOTIPO METALICO EN CREMATORIO (SEGUN SERV 1.00 123.00 123.00 123.00 S/. 123.00
34 DISEÑO)
SC PANEL INFORMATIVO DE MADERA (SEGUN DISEÑO) und 1.00 2,500.00 2,500.00 2,500.00 S/. 2,500.00
35 SC SEÑAL INFORMATIVA METALICA SIMPLE (SEGUN und 9.00 400.00 3,600.00 3,600.00 S/. 3,600.00
36 DISEÑO)
SC SEÑAL INFORMATIVA METALICA DOBLE (SEGUN und 3.00 500.00 1,500.00 1,500.00 S/. 1,500.00
37 DISEÑO)
SC PUERTA CONTRAPLACADA CON MARCO DE MADERA m2 15.05 350.00 5,267.50 5,267.50 S/. 5,267.50
38 SIMPLE
SC PUERTA CONTRAPLACADA MARCO DE MADERA CON m2 56.24 350.00 19,684.00 19,684.00 S/. 19,684.00
39 VENTANA
SERVICIO DE EXAMEN MEDICO und 80.00 250.00 20,000.00 20,000.00 S/. 20,000.00
40 ENERGIA ELECTRICA PROVICIONAL GLB 9.00 300.00 2,700.00 300.00 300.00 300.00 300.00 300.00 300.00 300.00 300.00 300.00 S/. 2,700.00
41 INSTALACION DE RED PRIMARIA GLB 1.00 258,641.88 258,641.88 86,213.96 86,213.96 86,213.96 S/. 258,641.88

COSTO DIRECTO 532,254.09 5,100.78 22,577.78 89,691.74 99,259.98 91,291.74 3,477.78 35,079.56 119,476.36 66,298.39 532,254.09
AVANCE PORCENTUAL % 0.96% 4.24% 16.85% 18.65% 17.15% 0.65% 6.59% 22.45% 12.46% 100.00%
AVANCE PORCENTUAL % 0.96% 5.20% 22.05% 40.70% 57.85% 58.51% 65.10% 87.54% 100.00%
CRONOGRAMA DE ADQUISICION DE BIENES PARA EQUIPAMIENTO
ENTIDAD: MUNICIPALIDAD DISTRITAL CORONEL GREGORIO ALBARRACIN LANCHIPA

PROYECTO: “MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA I.E.I. N° 446 EN LA ASOC. VIV. VILLA VIÑANI - VIÑANI II ETAPA, EN EL DISTRITO CRNL. GREGORIO ALBARRACIN LANCHIPA - TACNA - TACNA”

PRESUPUESTO Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17
ITEM DESCRIPCION UND Total
CANTIDAD PRECIO PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL

1 ANAQUELES DE ANGULOS RANURADOS 1.50X0.30X1.80 und 11.00 800.00 8,800.00 - - - - - - 11.00 8,800.00 - - 8,800.00
2 ARMARIO DE MELAMINE 1.20X0.40X1.80 und 10.00 700.00 7,000.00 - - - - - - 10.00 7,000.00 - - 7,000.00
3 BANQUETA DE 03 ASIENTOS FIBRA DE VIDRIO und 12.00 600.00 7,200.00 - - - - - - 12.00 7,200.00 - - 7,200.00
4 1.43X0.46X0.78
CAMARA DE CONSERVACION DE CADAVERES DE 4 und 1.00 37,881.00 37,881.00 - - - - - - 1.00 37,881.00 - - 37,881.00
5 COMPARTIMIENTOS
CAMILLA PARA EXAMEN (TOPICO) und 1.00 1,200.00 1,200.00 - - - - - - 1.00 1,200.00 - - 1,200.00
6 COMPUTADORA CON PROCESADOR CORE I5 4TA und 2.00 3,500.00 7,000.00 - - - - - - 2.00 7,000.00 - - 7,000.00
7 GENERACIONDE MELAMINA TIPO 02 1.20X0.60X0.75
ESCRITORIO und 5.00 600.00 3,000.00 - - - - - - 5.00 3,000.00 - - 3,000.00
8 ESCRITORIO DE MELAMINE TIPO 01 1.50X1.30X0.81 und 3.00 800.00 2,400.00 - - - - - - 3.00 2,400.00 - - 2,400.00
9 GARRUCHA MOVIL CON CAPACIDAD DE 120kg pza 48.00 140.00 6,720.00 - - - - - - 48.00 6,720.00 - - 6,720.00
10 HORNO CREMATORIO ECOLOGICO und 1.00 251,677.50 251,677.50 - - - - - - 1.00 251,677.50 - - 251,677.50
11 IMPRESORA MULTIFUNCIONAL A TINTA CON SISTEMA und 3.00 650.00 1,950.00 - - - - - - 3.00 1,950.00 - - 1,950.00
12 CONTINUO
MESA DE MADERA TIPO 01 2.00X0.45X0.90 und 1.00 1,200.00 1,200.00 - - - - - - 1.00 1,200.00 - - 1,200.00
13 MESON DE METAL 2.00X0.64X0.70 und 1.00 800.00 800.00 - - - - - - 1.00 800.00 - - 800.00
14 SILLA DE MADERA 4.00X0.46X0.80 und 21.00 1,200.00 25,200.00 - - - - - - 21.00 25,200.00 - - 25,200.00
15 SILLA GERENCIAL 0.52X0.42X1.08 und 3.00 300.00 900.00 - - - - - - 3.00 900.00 - - 900.00
16 SILLA TAPIZADA 0.46X0.42X0.78 und 21.00 150.00 3,150.00 - - - - - - 21.00 3,150.00 - - 3,150.00
17 TANQUE DE GAS 500 GL und 1.00 10,000.00 10,000.00 - - - - - - 1.00 10,000.00 - - 10,000.00

COSTO DIRECTO 376,078.50 - - - - - - 376,078.50 - - 376,078.50


AVANCE PORCENTUAL % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 100.00
AVANCE PORCENTUAL % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 100.00% 100.00%
CUADRO RESUMEN DE UTILIZACION DE RECURSOS

OBRA: " CREACION DE LOS SERVICIOS MUNICIPALES DE INHUMACION EN EL SECTOR VIÑANI, DISTRITO DE GREGORIO ALBARRACIN LANCHIPA - TACNA - TACNA"

RESIDENTE: ING. NADIA ELMA JUAREZ PACHECO

MES: OCTUBRE 2016

RESUMEN

OBSERVACION: RECURSOS PROGRAMADOS MENSUALIZADO

PLAZO APROBADO
RECURSOS SEGÚN
DESCRIPCIÓN
EXPEDIENTE TECNICO Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17

COSTO DIRECTO 5,222,299.05 625,662.70 202,920.53 665,824.37 1,201,715.44 553,156.66 660,910.13 752,845.04 390,635.84 168,628.34

COMPONENTE 01: INFRAESTRUCTURA


MANO DE OBRA - PERSONAL OBRERO 1,580,504.91 55,147.79 102,214.41 170,685.64 220,310.63 270,123.80 251,076.23 216,285.36 203,398.80 91,262.26
MATERIALES 2,267,324.39 394,729.33 60,950.94 389,344.27 737,285.06 176,802.37 383,696.02 103,095.50 21,420.90 0.00
SERVICIOS - MAQUINARIA 466,137.16 170,684.80 17,177.40 16,102.73 144,859.78 14,938.75 22,660.10 22,306.12 46,339.79 11,067.69
SERVICIOS - TERCEROS 532,254.09 5,100.78 22,577.78 89,691.74 99,259.98 91,291.74 3,477.78 35,079.56 119,476.36 66,298.39

COMPONENTE 02: EQUIPAMIENTO


MOBILIARIO Y EQUIPAMIENTO 376,078.50 0.00 0.00 0.00 0.00 0.00 0.00 376,078.50 0.00 0.00

GASTOS GENERALES 626,675.89 75,079.52 24,350.46 79,898.92 144,205.85 66,378.80 79,309.22 90,341.41 46,876.30 20,235.40

TOTAL DE RECURSOS EMPLEADOS S/. 5,848,974.94 S/. 700,742.22 S/. 227,270.99 S/. 745,723.30 S/. 1,345,921.29 S/. 619,535.45 S/. 740,219.35 S/. 843,186.45 S/. 437,512.14 S/. 188,863.74

% 100.00% 11.98% 3.89% 12.75% 23.01% 10.59% 12.66% 14.42% 7.48% 3.23%