Route 5:

Information Assessment Application


Q Terrain and landform Terrain classification for slope instability
evaluation - The grade is 2.2% and classified as flat
- According to REAM terrain.
Standard, The natural Area & Cost Amount of Cut & Fill Activities:
ground cross slopes (i.e., - Cut Area: 20479.9076 sqm
perpendicular to natural - Fill Area : 3630.87694 sqm
ground contours) in a flat - Total Cost : RM9860740.169
terrain are generally below 3%
- Evaluation of
Earthwork cost
Crossing over rivers/streams Identify route plan
- By referencing Google - The length of the route is 7.76 km and
Earth Application, the route - Two major rivers is cross by the route
crossing over river can be with 700m and 100m length.
determine.
Land use To conduct multicriteria analysis
- By referencing to the land - To propose route with minimum
use map from Dewan impact towards social, economic,
Bandaraya Kota Kinabalu terrain, environment, cost and time
Geological Map Landform and soil material To identify the geological formation
parent rock - The route is laid over moderate hill and
- By referencing to the minor valley floors, tidal swamp and very
geological map from high hills
Jabatan Tanah
Route 3:

Information Assessment Application


Topographic Terrain and landform Terrain classification for slope instability
Map evaluation - The grade is 3.8% and classified as
- According to REAM rolling terrain
Standard, the natural Area & Cost Amount of Cut & Fill Activities:
ground cross slopes in - Cut Area: 28221.59754 spm
a rolling terrain are - Fill Area : 1204.52383 sqm
generally between 3% - Total Cost : RM12163659.42
to 25%
- Evaluation of
Earthwork cost
Crossing over rivers/streams Identify route plan
By referencing Google Earth - The length of the route is 6.48 km and
Application, the route crossing two river is cross by the route with 600m
over river can be determine. and 2km length.

Land use To conduct multicriteria analysis


By referencing to the land use To propose route with minimum impact
map from Dewan Bandaraya towards social, economic, terrain,
Kota Kinabalu environment, cost and time
Geological Map Landform and soil material To identify the geological formation
parent rock - The route is laid over beaches,
- By referencing to the floodplains and very high hills.
geological map from
Jabatan Tanah
Route 8:

Information Assessment Application


Topographic Map Terrain and landform Terrain classification for slope instability
evaluation - The grade is 5.3% and classified as
- According to REAM rolling terrain
Standard, the natural Area & Cost Amount of Cut & Fill Activities:
ground cross slopes in - Cut Area: 34435.54493 sqm
a mountainous terrain - Fill Area : 10799.90654 sqm
are generally above - Total Cost : RM14371750.45
25%
- Evaluation of Earthwork
cost
Crossing over rivers/streams Identify route plan
By referencing Google Earth - The length of the route is 6.10 km
Application, the route crossing and two river is cross by the route with
over river can be determine. 800m and 1km length.

Land use To conduct multicriteria analysis


By referencing to the land use To propose route with minimum impact
map from Dewan Bandaraya towards social, economic, terrain,
Kota Kinabalu environment, cost and time
(Approximate area for each land
zone)
Geological Map Landform and soil material To identify the geological formation
parent rock - The route is laid over very high hills,
- By referencing to the flood plains and beaches
geological map from (Approximate area in each
Jabatan Tanah geological formation)