Due to the limited quantity of GRE pipes for the ditch water supply & in order to be insure
that all parts of east side ditch can be filled by water, We suggest to extend the GRE pipe in
DESCRIPTION
east side of CPF1 by using 650 m UPVC pipes DN 150 as highlighted in the attached design
drawings.
ACTION PROPOSED To insure that all parts of east side ditch can be filled by water
Signature
PMC/PMT Response:
Indicate Potential Impact:
- The FDC is accepted.
- CONTRACTOR to use the 150 rating at least, and granted the proper connection between the GRE and UPVC
at the tie-in point.
- The change shall be marked and updated in the as-built stage.
SOW Change , Cost , Schedule, Re-Hazop (if Yes, need Project Change Order Request (additional Cost or Reduction Cost)
PMC
Engineer
PMC Engineering Manager F/ PMC Project Manager
Signature
*(NOTE): Field Engineer at Site to capture the accepted changes on latest IFC document for as built marking.
490 ML
120 ML
1200 ML