You are on page 1of 1

Legally Bound gulfconstructionworldwide.

com

New Red Book, a lengthy read


STUART JORDAN* analyses the newly released Red Book and indicates that he
does not anticipate immediate adoption of the new forms in the Gulf.

I
HAVE previously mentioned the longer, covering some 106 pages instead changed. Contract administration, how-
slow-paced rewriting of the Fidic of 60. Much of this increase is due to ever, has changed almost completely.
(International Federation of Con- more prescriptive contract Much of this is wel-
sulting Engineers) main contract suite, administration, on every- come and follows mod-
which was last updated in 1999. This thing from early warning ern practice. The provi-
exercise has been trailed for years and and variations to time/ sions on programmes
many of us thought it would never hap- money claims and dis- and extensions of time
pen. putes. The highlights in- will drive clarity and
Well, last month Fidic released three clude: certainty of outcome, so
new contracts: the 2017 Second Edition, • An obligation on the reducing the scope for
comprising the Conditions of Contract contractor to price and disputes. Other changes
for Construction (Red Book); the Condi- programme in full detail appear to be unnecessar-
tions of Contract for Plant and Design- any proposed variation. ily intrusive and will add
Build (Yellow Book); and the Conditions • An indemnity from the to overall cost. We can
of Contract for EPC/Turnkey Projects contractor, should defects expect users in the Gulf
(Silver Book). in contractor design cause Jordan ... the 2017 forms will to delete the new provi-
This is big news, given the dominance of the works not to be fit for take a while to bed in. sions on DAABs, just as
Fidic forms in the Middle East – espe- purpose. As with the earli- the existing equivalent
cially the main contracts. In this article, er Red Book, the contract can call for con- provisions are now.
we’ll look just at the Red Book, which is tractor design. Whilst fitness for purpose This makes the second question easier to
subtitled “For Building and Engineering is a normal Fidic feature, the indemnity is answer. There will be no immediate adop-
Works Designed by the Employer”. This new and the reason for making this even tion of these new forms in the Gulf region.
is the simplest of the suite and the best tougher on contractors, is not immedi- The first reason is this new process-driv-
from which to assess the general approach ately obvious. en approach to contract administration.
taken by the writers. • Programmes are required to be more de- There is responsibility on both parties
So, are the new forms an improvement, tailed – to show activity float, to be log- for proactive engagement and there are
and will they be used any time soon in ic-linked and to show critical path. The consequences on both sides in default of
the Gulf region? On the first question, contractor’s programmes must be updated meeting those obligations. This is the op-
we should consider why the publishers and shall be accepted by the engineer if posite of the more reactive Middle East-
thought the rewrite was necessary. What they comply with contract requirements. ern approach to contract administration,
were the obvious deficiencies? Which • Also on time management, the parties in which the engineer’s main job is simply
contract terms were routinely deleted, are directed to agree a position on how to hold the contractor to account.
changed or inserted by users, or required to deal with concurrent delay. There is no The bigger reason though is habit: the
by funders? prescription on how to deal with it – to al- Fidic 1995 Orange Book is still popular
In terms of both market share and mar- low or to disallow an extension of time in in this region; even some 1987 forms are
ket perception, we might conclude that that situation – but it has to be addressed. still used. In this environment, where even
there wasn’t a lot to fix. Compared to oth- • There are more detailed requirements on the 1999 editions are a little bit too new
er international published contracts, the devising and operating quality manage- for some users, the 2017 forms will take a
1999 First Edition forms are short, simple ment and verification systems. while to bed in!
and user-friendly. Yes, in many ways too • Contractual claims for time and money We’ll look at the new Yellow and Silver
simple; lacking in some essential detail have been separated from the disputes books separately. n
needed for modern complex projects and provisions, and the time bar is softened
to achieve bankability. This necessitates with a route of appeal for late claims. * Stuart Jordan is a partner in the Global
some lengthy amendments but I have not • There is to be a standing Dispute Avoid- Projects group of Baker Botts, a leading in-
noted any perception that the forms are ance/Adjudication Board (DAAB) which ternational law firm. Jordan’s practice focuses
inadequate as a starting point. Anyway, it can give both informal non-binding views on the oil, gas, power, transport, petrochemi-
is fair to say that a very different approach on an issue and interim-binding deci- cal, nuclear and construction industries. He
has been taken with the new forms. sions. has extensive experience in the Middle East,
For a start, the conditions are much Overall, the basic risk profile has not Russia and the UK.

46 Gulf Construction, February 2018

You might also like