Professional Documents
Culture Documents
Energy Cost
Climate Change
SITUATIONER
2010 ENERGY CONSUMPTION BY SECTOR
AFF
1%
INDUSTRY
26% BUILDINGS
36%
53-70% of a
building’s
energy
consumption is
due to cooling
4
MITIGATION IMPERATIVE
Climate Vulnerability
…. pursuing
climate change
mitigation as a
Resource efficiency function of
and security adaptation
…. improve
Shared Responsibility bottomline
Why GO green
Green Building provides a window of opportunity to
prevent being locked in a high carbon economy.
Economics
Urbaniation
Climate Change
Green
Building?
What?
Why?
How?
…the State has adopted the Philippine Agenda
21 framework which espouses sustainable
development, to fulfill human needs while
maintaining the quality of the natural environment for
current and future generations.
Materials Water
Market Analysis
Sensitivity Analysis
Green Building
Recommendations
• Energy
16
Efficiency
• Water Efficiency 3
• Material
BUILDING TECHNOLOGIES & PRACTICES (SHDA) – Ar Emelito C Punsalan, PGBI, Sept. 17, 2015
Sustainability
1
• Solid Waste 1
Management
• Site 2
Sustainability
• Indoor
Environmental 2
Quality
25 GB Measures
COVERAGE AND APPLICATION
Minimum Total Gross Floor Area (TGFA) coverage
USE / OCCUPANCY TGFA
Hotel 10,000 sqm
Mall 15,000 sqm
Office 10,000 sqm
UILDING TECHNOLOGIES & PRACTICES (SHDA) – Ar Emelito C Punsalan, PGBI, Sept. 17, 2015
Residential Condominium 20,000 sqm
School 10,000 sqm
Hospital 10,000 sqm
Mixed Occupancy 10,000 sqm
3. Natural Ventilation
- Use of operable windows
5. Roof insulation
- Reduction of heat transfer through the roof
ENERGY EFFICIENCY
EFFICIENCY OF MECHANICAL SYSTEMS
1. Daylighting Provision
- Harvest natural daylighting
4. Occupancy Sensors
- Controlled use of artificial
lighting due to demand
ENERGY EFFICIENCY
EFFICIENCY OF ELECTRICAL SYSTEMS
6. Transformers
- Use of highly-efficient
transformers
1. Rainwater Harvesting
- Re-use of rainwater reduces use of
potable water and slows down
stormwater surface run-off
2. Water Recycling
- Resulting water from sewage treatment
plants (STP) can be re-used
- Cooling Tower / Irrigation
MATERIAL SUSTAINABILITY
NON-TOXIC MATERIALS
Material resource with least impact
to the environment and
to human beings
SOLID WASTE MANAGEMENT
UILDING TECHNOLOGIES & PRACTICES (SHDA) – Ar Emelito C Punsalan, PGBI, Sept. 17, 2015
USD 864 Million Costs expected to be
avoided
25
Green Building Voluntary
Code Rating Systems
Number of buildings
26
The evaluation of Bldg
Permit Docs
Including the GB Code
measures under the
appropriate disciplines
GB Measures
embedded in
Technical Drawings
& Specifications
Ocula
a Sealed window and door assemblies Bay wall sections
Ve
Enlarged details of
building envelope
b Sealed utility services Applies to all building occupancies showing required air Pro
except building and spaces without air- tightness & moisture
conditioning system protection elements
Building elevations &
c Sealed walls Brochu
sections
Architectural Reflected
a Building LPD within maximum LPD W/m2 W/m2 Ceiling Plan w/ LEGEND
requirements Box
Electrical Lighting Layout
a.1 Residential Dwelling 10.8
w/ LEGEND Box
Building Lighting Power
a.2 Hotel/Resort 10.8
Density Table
Ocu
a.3 Educational: School Applies to all building occupancies 12.9 ver
a.4 Institutional: Hospital without exceptions 12.9 la
a.5 Business: Office 10.8 na
a.6 Mercantile:Mall (excl accent lighting) 16.1 sho
a.7 Exterior facade 2.15 Technical specifications
a.8 Active entrance (pedestrian conveyance) 98.4 of light fixtures
Inactive entrance (normally
a.9 65.6
locked/inactive)
a.10 Covered Parking 3.2
a.11 Open Parking 1.6
Applies to all building occupancies Required? Complied?
10.6.4 Occupancy Sensors
except hospitals and malls Yes/No Yes/No
Provisions for emergency and security Architectural Reflected
a Occupancy sensors in lighting system
lighting are exempted Ceiling Plan
Ocu
Occupancy sensors in covered parking ver
b Electrical Lighting layout
lighting system - at least 60% of lighting la
Occupancy Sensing na
System Confirmation sho
Air-conditioning &
(Equipment 2)
Ventilation Layout Ocul
Technical Specifications verifi
(Equipment 3) of the various AC lab
(Equipment 4) nam
(Equipment 5) shopd
b
(Equipment 6)
(Equipment 7)
(Equipment 8)
Applies to all building occupancies
Required
except building with no water heating Efficiency
10.5.2 Water Heating System Efficiency
Factor
system and buildings using solar water Factor
heating and/or heat pump for water
a Efficient water heater (Equipment 1) Equipment Schedule
Plumbing & Electrical Ocul
(Equipment 2) verifi
power layout
lab
Technical Specifications nam
(Equipment 3)
of Water Heating system shopd
(Equipment 4) b
(Equipment 5)
Applies to all building occupancies.
Non-centralized air-conditioning
Variable Speed Drives and High Efficiency systems in buildings are not required to Efficiency Efficiency
10.5.3 Factor Factor
Motors employ variable speed controllers;
and kitchen ventilation fans are exempt
from this requirement.
Building Envelope
BUILDING PERMIT PROCESS
Applicability
This measure applies to all building occupancies as
indicated in Table 1. of the GB Code
Exceptions
Buildings and spaces without provisions for air conditioning
systems are exempt.
Building Envelope
BUILDING PERMIT PROCESS
Design Application & Documentation
Design Documents needed are the following:
1. Bay Wall Sections, showing details or air leakage control & water barrier
at roof joints; roof/gutter joints; roof/wall joints; ceiling/wall joints;
window/wall joints, door/wall joints, and wall/floor joints;
2. Enlarged details, showing flashing & counter-flashing; membrane; sealant &
tape applications; fenestration (window & door) weatherstripping, gaskets
and door bottom sweeps;
3. Building Elevations & Sections with call-outs specifying moisture
protection material;
4. Technical Specifications of moisture protection (moisture barrier for walls,
waterproofing membrane, flashings), sealants, gaskets, weatherstripping to
be used
Building Envelope
BUILDING PERMIT PROCESS
Air Tightness & Moisture Protection
Building Envelope
OCCUPANCY CLEARANCE PROCESS
• Application form from the Office of the Local
Application Building Official
Building Envelope
OCCUPANCY CLEARANCE PROCESS
Construction Application & Documentation
Building Envelope
OCCUPANCY CLEARANCE PROCESS
Construction Application & Documentation
Shopdrawings & As-built plans
Building Envelope
OCCUPANCY CLEARANCE PROCESS
Air-Conditioning Equipment
Exceptions
No exceptions
Mechanical Systems
OCCUPANCY CLEARANCE PROCESS
Design Application & Documentation
Design Documents needed are the following:
Mechanical Systems
OCCUPANCY CLEARANCE PROCESS
Air-Conditioning Equipment
AC & Ventilation Layout
Mechanical Systems
OCCUPANCY CLEARANCE PROCESS
Construction Application & Documentation
Actions needed are the following:
Building Envelope
OCCUPANCY CLEARANCE PROCESS
Construction Application & Documentation
Ocular Inspection
Mechanical Systems
OCCUPANCY CLEARANCE PROCESS
Construction Application & Documentation
Product labels & nameplate rating Brochures & catalogs
Mechaical Systems
BUILDING PERMIT PROCESS
a Sealed window and door assemblies Requi red Compl i ed Bay wall sections Yes Yes
a Sealed window and door assemblies Requi red Compl i ed Bay wall sections Yes Yes
MRF with minimum floor area as per Table Architectural floor plans
a 19.29 25.00
15 & site development plan Yes Yes
b MRF fully enclosed & easily accessible Applies to all Required Complied showing location of MRF
building
Solid waste containers for 4 types of
occupancies MRF Floor Area
c waste; compostable; non-recyclable; without exceptions Required
Complied Yes Yes
Computation Table
recyclable; special
For hospitals, isolated bins for hazardous Technical specifications
d Not RequiredNot Applicable
wastes for the MRF
MRF with minimum floor area as per Table Architectural floor plans
a 19.29 25.00
15 & site development plan Yes Yes
b MRF fully enclosed & easily accessible Applies to all Required Complied showing location of MRF
building
Solid waste containers for 4 types of
occupancies MRF Floor Area
c waste; compostable; non-recyclable; without exceptions Required
Complied Yes Yes
Computation Table
recyclable; special
For hospitals, isolated bins for hazardous Technical specifications
d Not RequiredNot Applicable
wastes for the MRF
Document
10.6.3 Lighting Power Density (LPD) LPD Calculator Design Value Documentation needed Design Specification Relevant
Provided?
Architectural Reflected
a Building LPD within maximum LPD W/m2 W/m2 Ceiling Plan w/ LEGEND Yes Yes
requirements Box
Electrical Lighting Layout
a.1 Residential Dwelling 10.8 2.25 Yes Yes
w/ LEGEND Box
Building Lighting Power
a.2 Hotel/Resort 10.8 0.00 Yes Yes
Density Table
a.3 Educational: School Applies to all building occupancies 12.9 0.00
a.4 Institutional: Hospital without exceptions 12.9 0.00
a.5 Business: Office 10.8 0.00
a.6 Mercantile:Mall (excl accent lighting) 16.1 0.00 Technical specifications of
lights is different from lamp
a.7 Exterior facade 2.15 0.00 Technical specifications
Yes No fixtures indicated in LEGEND
a.8 Active entrance (pedestrian conveyance) 98.4 0.00 of light fixtures
BOX of Electrical Lighting
Inactive entrance (normally Layout
a.9 65.6 0.00
locked/inactive)
a.10 Covered Parking 3.2 0.00
a.11 Open Parking 1.6 0.00
EVALUATION SIMULATION NO. 3
Design Compliance
Philippine Green Building Code Required Design
Item Applicability Document
Requirement value Value Documentation needed Design Specification Relevant
Provided?
Document
10.6.3 Lighting Power Density (LPD) LPD Calculator Design Value Documentation needed Design Specification Relevant
Provided?
Architectural Reflected
a Building LPD within maximum LPD W/m2 W/m2 Ceiling Plan w/ LEGEND Yes Yes
requirements Box
Electrical Lighting Layout
a.1 Residential Dwelling 10.8 2.25 Yes Yes
w/ LEGEND Box
Building Lighting Power
a.2 Hotel/Resort 10.8 0.00 Yes Yes
Density Table
a.3 Educational: School Applies to all building occupancies 12.9 0.00
a.4 Institutional: Hospital without exceptions 12.9 0.00
a.5 Business: Office 10.8 0.00
a.6 Mercantile:Mall (excl accent lighting) 16.1 0.00 Technical specifications of
lights is different from lamp
a.7 Exterior facade 2.15 0.00 Technical specifications
Yes No fixtures indicated in LEGEND
a.8 Active entrance (pedestrian conveyance) 98.4 0.00 of light fixtures
BOX of Electrical Lighting
Inactive entrance (normally Layout
a.9 65.6 0.00
locked/inactive)
a.10 Covered Parking 3.2 0.00
a.11 Open Parking 1.6 0.00
EVALUATION SIMULATION NO. 4
PHILIPPINE GREEN BUILDING CODE COMPLIANCE CHECKLIST
10 ENERGY EFFICIENCY GB Code Developer Regulator
Philippine Green Building Code Design Compliance
Required
Item Applicability Design Value Document
Requirement value Documentation needed Design Specification Relevant
Provided?
Mechanical Systems Yes/No Yes/No Remarks
Applies to all building occupancies except building EER or COP or EER or COP or
10.5.1 Air Conditioning Equipment kW/Ton kW/Ton
and spaces without air-conditioning system
a Efficient air-conditioning equipment Air-cooled, split systems <68,585 KJ/H 12.0 EER 13
Equipment Schedule Yes Yes
Water cooled, Electrically operated, centrifugal Air-conditioning &
0.57 Kw/ton 0.55 Ventilation Layout
Yes Yes
≥600 tons
Technical Specifications
Through-the-wall, air-cooled, single packaged
12.0 SEER of the various AC Yes Yes
<31,655 KJ/H
10.9 equipment
Applies to all building occupancies except building EER or COP or EER or COP or
10.5.1 Air Conditioning Equipment kW/Ton kW/Ton
and spaces without air-conditioning system
a Efficient air-conditioning equipment Air-cooled, split systems <68,585 KJ/H 12.0 EER 13
Equipment Schedule Yes Yes
Water cooled, Electrically operated, centrifugal Air-conditioning &
0.57 Kw/ton 0.55 Ventilation Layout
Yes Yes
≥600 tons
Technical Specifications
Through-the-wall, air-cooled, single packaged
12.0 SEER of the various AC Yes Yes
<31,655 KJ/H
10.9 equipment
Overhead water storage tank on top of Water Distribution Ocular Inspection &
a Yes Yes Yes Yes
building at least 10 stories high Required Complied Layout plan Verification
Applies to all building occupancies Single Line or Schematic Product Labels and/or Capacity indicated on the
Yes Yes Yes Yes
except buildings below 10 storeys high Diagram namepate rating tank
Water Tank Details Yes Yes Brochures & Catalogues No No Tank is site fabricated
Overhead water storage tank on top of Water Distribution Ocular Inspection &
a Yes Yes Yes Yes
building at least 10 stories high Required Complied Layout plan Verification
Applies to all building occupancies Single Line or Schematic Product Labels and/or Capacity indicated on the
Yes Yes Yes Yes
except buildings below 10 storeys high Diagram namepate rating tank
Water Tank Details Yes Yes Brochures & Catalogues No No Tank is site fabricated
Other Codes
& Laws
63
GREEN BUILDINGS
FOR A SMARTER WORLD
www.edgebuildings.com
THE SOLUTION IS EDGE: A SOFTWARE, A STANDARD,
AND A GREEN BUILDING CERTIFICATION SYSTEM.
________
20%
Green Building Voluntary
Code Rating Systems
Number of buildings
66
PHILIPPINE
GREEN BUILDING CODE