Professional Documents
Culture Documents
CN-326
Fall 2016
Introduction
• Time and cost are the two most important components
of project economy.
• If time is not important, management can utilize its
resources in the most cost-effective way, even stopping
work on one project, moving to another for a while,
and then coming back. This allows the management to
complete the project in minimum cost.
• On the other hand, if money is not important,
management can obtain the best of resources and
schedule work around the clock, hence completing the
project in minimum time.
Introduction
• The objective of the project manager would
then be to identify the budget and cash inflow
constraints and develop a project schedule
with the most efficient usage of available
resources with cost incurrence within the
identified budget and cash flow limits.
COSTS IN A CONSTRUCTION PROJECT
Variable Costs
• Variable Costs are costs that are incurred in relation to
the variation in duration of an activity, project phase or
whole project. This means that if the duration (of
project, phase or activity) changes, the associated
variable cost changes in relation.
• For e.g: cost of labor incurs daily, cost of excavator
incurs hourly, etc. Some indirect costs may also be
variable; for e.g., cost of site utilities incurs monthly,
cost of labor accommodation incurs weekly, cost of site
security incurs daily, etc.
COSTS IN A CONSTRUCTION PROJECT
Fixed Costs
• A set cost that remains constant regardless of duration
or the work performed by a resource. In other words,
any variation in duration or resource work does not
affect the fixed cost. Fixed costs can be assigned to
activities, WBS levels as well as resources.
• A resource fixed cost can refer to its mobilization, de-
mobilization, installation or calibration cost. Like
variable costs, fixed costs can be direct or indirect.
COST PLANNING AND SCHEDULING
• Cost planning and scheduling refers to the
procedure of identifying the overall project
budget and the allocation of this budget to
individual activities in accordance with the
resource requirement as well as in
consideration with the cash inflow constraints
COST PLANNING AND SCHEDULING
It involves the following four major processes:
• Resource Planning
• Cost Estimating
• Cost Budgeting
• Cash Flow Analysis
Cost Planning and Scheduling
Resource Planning
• Determining what resources and what quantities
of each should be used to perform project
activities and developing the most efficient
resource loaded schedule.
Cost Estimating
• Developing an approximation (estimate) of the
cost of the direct and indirect resources as well as
other cost incurrence needed to complete project
activities and hence complete project.
Cost Planning and Scheduling
Cost Budgeting
• Identifying project-level and activity-level
budget constraints.