DAFTAR ANALISA BIAYA KONSTRUKSI (ABK) SNI

BANGUNAN GEDUNG DAN PERUMAHAN

HARGA
KODE ANALISA DAN URAIAN PASANGAN KOOFISIEN JUMLAH ( Rp.)
SATUAN ( Rp. )
ANALISA BIAYA KONSTRUKSIPekerjaAN PERSIAPAN (ABK-A) RSNI T-15-2002
ABK-A 6.4 1 M1 PENGUKURAN DAN PEMASANGAN BOWPLANK
Kayu balok 5/7 CM (Klas IV) 0,01200 M3 2.500.000,00 30.000,00
Kayu papan 3/20 CM (klas IV) 0,00700 M3 2.500.000,00 17.500,00
Paku 2" - 5" 0,02000 Kg 22.300,00 446,00
Pekerja 0,10000 Oh 86.000,00 8.600,00
Tukang 0,10000 Oh 100.000,00 10.000,00
Kepala tukang 0,01000 Oh 110.000,00 1.100,00
Mandor 0,00500 Oh 110.000,00 550,00
68.196,00
ANALISA BIAYA KONSTRUKSIPekerjaAN TANAH (ABK-B) SNI DT 91-0006-2007
ABK-B 6.4a 1 M3 GALIAN TANAH KERAS SEDALAM 2 METER
Pekerja 1,15000 Oh 86.000,00 98.900,00
Mandor 0,08700 Oh 110.000,00 9.570,00
108.470,00
ABK-B 6.9.b 1 M3 URUGAN TANAH KEMBALI TANAH GALIAN BIASA SEDALAM 2 METER
Pekerja 0,30000 Oh 86.000,00 25.800,00
Mandor 0,01500 Oh 110.000,00 1.650,00
27.450,00
ABK-B 6.10.a 1 M3 TIMBUNAN TANAH DIPADATKAN PERLAPISAN 20 CM
Tanah urug 1,20000 M3 34.000,00 40.800,00
Pekerja 0,50000 Oh 86.000,00 43.000,00
Mandor 0,05000 Oh 110.000,00 5.500,00
89.300,00
ABK-B 6.11 1 M3 URUGAN PASIR
Pasir urug 1,20000 M3 200.000,00 240.000,00
Pekerja 0,30000 Oh 86.000,00 25.800,00
Mandor 0,01000 Oh 110.000,00 1.100,00
266.900,00
ANALISA BIAYA KONSTRUKSIPekerjaAN DINDING (ABK-D) SNI DT 91-0009-2007
ABK-D 6.7.a 1 M2 PASANGAN 1/2 BATU BATA 1 PC : 2 PP
Batu bata lokal 1,00000 M2 66.400,00 66.400,00
Portland cement 18,95000 Kg 1.400,00 26.530,00
Pasir pasang 0,03800 M3 192.000,00 7.296,00
Pekerja 0,30000 Oh 86.000,00 25.800,00
Tukang 0,10000 Oh 100.000,00 10.000,00
Kepala tukang 0,01000 Oh 110.000,00 1.100,00
Mandor 0,01500 Oh 110.000,00 1.650,00
138.776,00
Untuk 1 M3 = 10 x nya 1.387.760,00
ABK-D 6.9.a 1 M2 PASANGAN 1/2 BATU BATA 1 PC : 4 PP
Batu bata lokal 1,00000 M2 48.800,00 48.800,00
Portland cement 11,50000 Kg 1.400,00 16.100,00
Pasir pasang 0,04300 M3 192.000,00 8.256,00
Pekerja 0,30000 Oh 86.000,00 25.800,00
Tukang 0,10000 Oh 100.000,00 10.000,00
Kepala tukang 0,01000 Oh 110.000,00 1.100,00
Mandor 0,01500 Oh 110.000,00 1.650,00
111.706,00
Untuk 1 M3 = 10 x nya 1.117.060,00
HARGA
KODE ANALISA DAN URAIAN PASANGAN KOOFISIEN JUMLAH ( Rp.)
SATUAN ( Rp. )
ANALISA
ANALISA BIAYA
BIAYA KONSTRUKSIPekerjaAN
KONSTRUKSIPekerjaAN PERSIAPAN
PLESTERAN (ABK-A)
(ABK-E) SNIRSNI T-15-2002
DT 91-0010-2007
ABK-E 6.4 1 M2 PLESTERAN 1 PC : 4 PP, TEBAL 15 MM
Portland cement 6,24000 Kg 1.400,00 8.736,00
Pasir pasang 0,02400 M3 192.000,00 4.608,00
Pekerja 0,30000 Oh 86.000,00 25.800,00
Tukang 0,15000 Oh 100.000,00 15.000,00
Kepala tukang 0,01500 Oh 110.000,00 1.650,00
Mandor 0,01000 Oh 110.000,00 1.100,00
56.894,00
ABK-E 6.27 1 M2 ACIAN PLESTERAN/BETON
Portland cement 3,25000 Kg 1.400,00 4.550,00
Pekerja 0,20000 Oh 86.000,00 17.200,00
Tukang 0,10000 Oh 100.000,00 10.000,00
Kepala tukang 0,01000 Oh 110.000,00 1.100,00
Mandor 0,01000 Oh 110.000,00 1.100,00
33.950,00
ABK-F 6.22.a 1 M1 PASANGAN FIBERSEMEN PLANK LEBAR 25 CM
Fiber plank 1,10000 M1 44.000,00 48.400,00
Paku skrup 0,05000 Kg 45.000,00 2.250,00
Pekerja 0,10000 Oh 86.000,00 8.600,00
Tukang 0,20000 Oh 100.000,00 20.000,00
Kepala tukang 0,02000 Oh 110.000,00 2.200,00
Mandor 0,00500 Oh 110.000,00 550,00
82.000,00
ABK-F 6.22.b 1 M1 PASANGAN FIBERSEMEN PLANK LEBAR 20 CM
Fiber plank 1,10000 M1 34.000,00 37.400,00
Paku skrup 0,05000 Kg 45.000,00 2.250,00
Pekerja 0,10000 Oh 86.000,00 8.600,00
Tukang 0,20000 Oh 100.000,00 20.000,00
Kepala tukang 0,02000 Oh 110.000,00 2.200,00
Mandor 0,00500 Oh 110.000,00 550,00
71.000,00
ABK-F 6.60.a 1 M1 PASANGAN LIST LANGIT-LANGIT PVC SUDUT
List PVC sudut 1,05000 M1 74.000,00 77.700,00
Skrup 0,01000 Kg 45.000,00 450,00
Pekerja 0,05000 Oh 86.000,00 4.300,00
Tukang 0,05000 Oh 100.000,00 5.000,00
Kepala tukang 0,00500 Oh 110.000,00 550,00
Mandor 0,00300 Oh 110.000,00 330,00
88.330,00
HARGA
KODE ANALISA DAN URAIAN PASANGAN KOOFISIEN JUMLAH ( Rp.)
SATUAN ( Rp. )
ANALISA ANALISA BIAYA KONSTRUKSIPekerjaAN
BIAYA KONSTRUKSIPekerjaAN BETON DAN PERSIAPAN (ABK-A)
BEGISTING RSNI
(ABK-G) SNIT-15-2002
DT 91-0008-2007
Catatan : Bobot isi pasir = 1400 Kg/M3, Bobot isi kerikil = 1350 Kg M3, Buckling faktor pasir = 20%
ABK-G 6.4 1 M3 BETON TUMBUK 1 PC : 3 PP : 5 KR DENGAN MUTU f'c = 7,4 Mpa (K 100)
Portland cement 230,00000 Kg 1.400,00 322.000,00
Pasir Beton 0,63786 M3 192.000,00 122.468,57
Kerikil bersih 0,73357 M3 234.000,00 171.655,71
Air 200,00000 Liter 240,00 48.000,00
Pekerja 1,20000 Oh 86.000,00 103.200,00
Tukang 0,20000 Oh 100.000,00 20.000,00
Kepala tukang 0,02000 Oh 110.000,00 2.200,00
Mandor 0,06000 Oh 110.000,00 6.600,00
796.124,29
ABK-G 6.5 1 M3 BETON TUMBUK 1 PC : 2 PP : 3 KR DENGAN MUTU f'c = 14,5 Mpa (K 175)
Portland cement 326,00000 Kg 1.400,00 456.400,00
Pasir pasang 0,54286 M3 192.000,00 104.228,57
Kerikil bersih 0,73500 M3 234.000,00 171.990,00
Air 215,00000 Liter 240,00 51.600,00
Pekerja 1,65000 Oh 86.000,00 141.900,00
Tukang 0,27500 Oh 100.000,00 27.500,00
Kepala tukang 0,02800 Oh 110.000,00 3.080,00
Mandor 0,08300 Oh 110.000,00 9.130,00
965.828,57
ABK-G 6.7 1 M3 BETON TUMBUK 1 PC : 2 PP : 3 KR DENGAN MUTU f'c = 19,3 Mpa (K 225)
Portland cement 371,00000 Kg 1.400,00 519.400,00
Pasir pasang 0,49857 M3 192.000,00 95.725,71
Spliet 2/3 cm 0,74786 M3 543.000,00 406.086,43
Air 215,00000 Liter 240,00 51.600,00
Pekerja 1,65000 Oh 86.000,00 141.900,00
Tukang 0,27500 Oh 100.000,00 27.500,00
Kepala tukang 0,02800 Oh 110.000,00 3.080,00
Mandor 0,08300 Oh 110.000,00 9.130,00
1.254.422,14
ABK-G 6.17 10 KG PEMBESIAN DENGAN BESI POLOS/ULIR
Besi beton 10,50000 Kg 12.000,00 126.000,00
Kawat beton 0,15000 Kg 25.000,00 3.750,00
Pekerja 0,07000 Oh 86.000,00 6.020,00
Tukang besi 0,07000 Oh 100.000,00 7.000,00
Kepala Tukang 0,00700 Oh 110.000,00 770,00
Mandor 0,00400 Oh 110.000,00 440,00
143.980,00
Untuk 1 Kg nya = 1/10 nya 14.398,00
ABK-G 6.20 1 M2 PASANGAN BEGISTING UNTUK PONDASI
Kayu papan kelas IV 0,04000 M3 2.500.000,00 100.000,00
Paku 2" - 5" 0,30000 Kg 22.300,00 6.690,00
Minyak begisting 0,10000 Ltr 5.400,00 540,00
Pekerja 0,52000 Oh 86.000,00 44.720,00
Tukang kayu 0,26000 Oh 100.000,00 26.000,00
Kepala tukang 0,02600 Oh 110.000,00 2.860,00
Mandor 0,02600 Oh 110.000,00 2.860,00
183.670,00
ABK-G 6.21 1 M2 PASANGAN BEGISTING UNTUK SLOOF
Kayu papan kelas IV 0,04500 M3 2.500.000,00 112.500,00
Paku 2" - 5" 0,30000 Kg 22.300,00 6.690,00
Minyak begisting 0,10000 Ltr 5.400,00 540,00
Pekerja 0,52000 Oh 86.000,00 44.720,00
Tukang kayu 0,26000 Oh 100.000,00 26.000,00
Kepala tukang 0,02600 Oh 110.000,00 2.860,00
Mandor 0,02600 Oh 110.000,00 2.860,00
196.170,00
HARGA
KODE ANALISA DAN URAIAN PASANGAN KOOFISIEN JUMLAH ( Rp.)
SATUAN ( Rp. )
ABK-G 6.22 1 M2 PASANGANANALISA BIAYA
BEGISTING KONSTRUKSIPekerjaAN
UNTUK KOLOM PERSIAPAN (ABK-A) RSNI T-15-2002
Kayu papan kelas IV 0,04000 M3 2.500.000,00 100.000,00
Paku 2" - 5" 0,40000 Kg 22.300,00 8.920,00
Minyak begisting 0,20000 Ltr 5.400,00 1.080,00
Kayu Balok kelas IV 0,01500 M3 2.500.000,00 37.500,00
Multiplek 9 mm 0,35000 Lbr 162.000,00 56.700,00
Kayu dolken Ø 8 CM x 4 m 2,00000 Btg 11.000,00 22.000,00
Pekerja 0,66000 Oh 86.000,00 56.760,00
Tukang kayu 0,33000 Oh 100.000,00 33.000,00
Kepala tukang 0,03300 Oh 110.000,00 3.630,00
Mandor 0,03300 Oh 110.000,00 3.630,00
323.220,00
ABK-G 6.23 1 M2 PASANGAN BEGISTING UNTUK BALOK
Kayu papan kelas IV 0,04000 M3 2.500.000,00 100.000,00
Paku 2" - 5" 0,40000 Kg 22.300,00 8.920,00
Minyak begisting 0,20000 Ltr 5.400,00 1.080,00
Kayu Balok 5/7 CM (kelas IV) 0,01800 M3 2.500.000,00 45.000,00
Multiplek 9 mm 0,35000 Lbr 162.000,00 56.700,00
Kayu dolken Ø 8 CM x 4 m 2,00000 Btg 11.000,00 22.000,00
Pekerja 0,66000 Oh 86.000,00 56.760,00
Tukang kayu 0,33000 Oh 100.000,00 33.000,00
Kepala tukang 0,03300 Oh 110.000,00 3.630,00
Mandor 0,03300 Oh 110.000,00 3.630,00
330.720,00
ABK-G 6.24 1 M2 PASANG BEGISTING UNTUK LANTAI
Kayu papan kelas IV 0,04000 M3 2.500.000,00 100.000,00
Paku 2" - 5" 0,40000 Kg 22.300,00 8.920,00
Minyak begisting 0,20000 Ltr 5.400,00 1.080,00
Kayu Balok 5/7 CM (kelas IV) 0,01500 M3 2.500.000,00 37.500,00
Multiplek 9 mm 0,35000 Lbr 162.000,00 56.700,00
Kayu dolken Ø 8 CM x 4 m 6,00000 Btg 11.000,00 66.000,00
Pekerja 0,66000 Oh 86.000,00 56.760,00
Tukang kayu 0,33000 Oh 100.000,00 33.000,00
Kepala tukang 0,03300 Oh 110.000,00 3.630,00
Mandor 0,03300 Oh 110.000,00 3.630,00
367.220,00
ABK-G 6.28.a I M3 MEMBUAT PONDASI BETON BERTULANG 20/120/120 CM, TYPE P1
Begisting + perancah (ABK-G 6.20) 2,13333 M2 183.670,00 391.829,33
Pembesian Bawah D 16 - 15 cm + Atas D 16 - 20 cm (ABK-G 6.17) 135,26832 Kg 14.398,00 1.947.593,27
Beton 1 : 2 : 3 (ABK-G 6.7) 1,00000 M3 1.254.422,14 1.254.422,14
3.593.844,75
ABK-G 6.28.b I M3 MEMBUAT PONDASI BETON BERTULANG 50/60/60 CM, TYPE P2
Begisting + perancah (ABK-G 6.20) 2,66667 M2 183.670,00 489.786,67
Pembesian Bawah D 16 - 15 cm + Atas D 16 - 20 cm (ABK-G 6.17) 167,17653 Kg 14.398,00 2.407.007,73
Beton 1 : 2 : 3 (ABK-G 6.7) 1,00000 M3 1.254.422,14 1.254.422,14
4.151.216,54
ABK-G 6.29.a 1 M3 MEMBUAT SLOOF BETON BERTULANG 20/30 CM, TYPE S1
Begisting + perancah (ABK-G 6.21) 10,00000 M2 196.170,00 1.961.700,00
Pembesian 8 D 16 , cincin Ø 10 - 15/10 CM (ABK-G 6.17) 286,05600 Kg 14.398,00 4.118.634,29
Beton 1 : 2 : 3 (ABK-G 6.7) 1,00000 M3 1.254.422,14 1.254.422,14
7.334.756,43
ABK-G 6.30.a 1 M3 MEMBUAT KOLOM BETON BERTULANG 40/40 CM, TYPE K1
Begisting + perancah (ABK-G 6.22) 10,00000 M2 323.220,00 3.232.200,00
Pembesian 8 D 16, cincin Ø 10 - 10/15 CM (ABK-G 6.17) 125,76600 Kg 14.398,00 1.810.778,87
Beton 1 : 2 : 3 (ABK-G 6.7) 1,00000 M3 1.254.422,14 1.254.422,14
6.297.401,01
HARGA
KODE ANALISA DAN URAIAN PASANGAN KOOFISIEN JUMLAH ( Rp.)
SATUAN ( Rp. )
ABK-G 6.30.b 1 M3 MEMBUAT KOLOM ANALISABETON
BIAYA BERTULANG
KONSTRUKSIPekerjaAN PERSIAPAN
20/20 CM, TYPE K2 (ABK-A) RSNI T-15-2002
Begisting + perancah (ABK-G 6.22) 20,00000 M2 323.220,00 6.464.400,00
Pembesian 4 Ø 10, cincin Ø 8 - 10/15 CM (ABK-G 6.17) 93,60936 Kg 14.398,00 1.347.787,57
Beton 1 : 2 : 3 (ABK-G 6.7) 1,00000 M3 1.254.422,14 1.254.422,14
9.066.609,71
ABK-G 6.30.c 1 M3 MEMBUAT KOLOM PRAKTIS BETON BERTULANG 10/10 CM, TYPE Kp
Begisting + perancah (ABK-G 6.22) 20,00000 M2 323.220,00 6.464.400,00
Pembesian 4 Ø 8, cincin Ø 6 - 15 CM (ABK-G 6.17) 205,17120 Kg 14.398,00 2.954.054,94
Beton 1 : 2 : 3 (ABK-G 6.7) 1,00000 M3 1.254.422,14 1.254.422,14
10.672.877,08
ABK-G 6.31.a 1 M3 MEMBUAT BALOK BETON BERTULANG 30/50 CM, TYPE B2
Begisting + perancah (ABK-G 6.23) 7,06667 M2 330.720,00 2.337.088,00
Pembesian 16 D 16, cincin Ø 10 - 10/15 CM (ABK-G 6.17) 218,32320 Kg 14.398,00 3.143.417,43
Beton 1 : 2 : 3 (ABK-G 6.7) 1,00000 M3 965.828,57 965.828,57
6.446.334,01
ABK-G 6.31.c 1 M3 MEMBUAT BALOK BETON BERTULANG 20/30 CM, TYPE B1
Begisting + perancah (ABK-G 6.23) 9,33333 M2 330.720,00 3.086.720,00
Pembesian 8 D 16 , cincin Ø 8 - 10/15 CM (ABK-G 6.17) 258,83136 Kg 14.398,00 3.726.653,92
Beton 1 : 2 : 3 (ABK-G 6.7) 1,00000 M3 965.828,57 965.828,57
7.779.202,49
ABK-G 6.31.d 1 M3 MEMBUAT BALOK BETON BERTULANG 15/20 CM, TYPE B3
Begisting + perancah (ABK-G 6.23) 10,33333 M2 330.720,00 3.417.440,00
Pembesian 4 D 12 , cincin Ø 8 - 10/15 CM (ABK-G 6.17) 155,06208 Kg 14.398,00 2.232.583,83
Beton 1 : 2 : 3 (ABK-G 6.7) 1,00000 M3 965.828,57 965.828,57
6.615.852,40
ABK-G 6.31.e 1 M3 MEMBUAT BALOK BETON BERTULANG 10/15 CM, TYPE B4
Begisting + perancah (ABK-G 6.23) 20,00000 M2 330.720,00
6.614.400,00
Pembesian 4 Ø 8 , cincin Ø 6 - 15 CM (ABK-G 6.17) 154,93056 Kg 14.398,00
2.230.690,20
Beton 1 : 2 : 3 (ABK-G 6.7) 1,00000 M3 965.828,57
965.828,57
9.810.918,77
ABK-G 6.33.b 1 M3 MEMBUAT PLAT BETON BERTULANG TEBAL 12 CM, PEMBESIAN WIREMESH MANUAL DUA LAPIS (PLAT LANTAI)
Begisting + perancah (ABK-G 6.24) 8,33333 M2 367.220,00 3.060.166,67
Pembesian Ø 10 - 15 cm (ABK-G 6.17) 148,50800 Kg 14.398,00 2.138.218,18
Beton 1 : 2 : 3 (ABK-G 6.7) 1,00000 M3 965.828,57 965.828,57
6.164.213,42
ABK-G 6.33.c 1 M3 MEMBUAT PLAT BETON BERTULANG TEBAL 10 CM, PEMBESIAN WIREMESH MANUAL SATU LAPIS (CANOPY & GROUND TANK)
Begisting + perancah (ABK-G 6.24) 10,00000 M2 367.220,00 3.672.200,00
Pembesian Ø 10 - 15 cm (ABK-G 6.17) 88,98150 Kg 14.398,00 1.281.155,64
Beton 1 : 2 : 3 (ABK-G 6.7) 1,00000 M3 965.828,57 965.828,57
Untuk Konstruksi Dengan Begisting = 5.919.184,21
Untuk Konstruksi Tanpa Begisting = 2.246.984,21
HARGA
KODE ANALISA DAN URAIAN PASANGAN KOOFISIEN JUMLAH ( Rp.)
SATUAN ( Rp. )
ANALISA
ANALISA BIAYABIAYA KONSTRUKSIPekerjaAN
KONSTRUKSI PERSIAPAN
PEKERJAAN PENUTUP (ABK-A)
ATAP RSNI
(ABK-H) SNI.T-15-2002
03-3436-1994
ABK-H 6.32.b 1 M2 PASANGAN ATAP GENTENG METAL WARNA BERPASIR (2 SUSUN 4 GELOMBANG)
Genteng metal 0,25 x 770 x 800 mm (2 susun 4 gelombang) 1,62000 Lbr 86.000,00 139.320,00
Paku skrup 0,20000 Kg 45.000,00 9.000,00
Pekerja 0,20000 Oh 86.000,00 17.200,00
Tukang 0,10000 Oh 100.000,00 10.000,00
Kepala tukang 0,01000 Oh 110.000,00 1.100,00
Mandor 0,00100 Oh 110.000,00 110,00
176.730,00
ABK-H 6.36.a 1 M1 PASANGAN NOK ATAS, SAMPING DAN WALLFLASHING GENTENG METAL WARNA POLOS
Nok atas, samping dan wallflashing genteng metal 1,10000 M1 34.000,00 37.400,00
Paku skrup 0,05000 Kg 45.000,00 2.250,00
Pekerja 0,25000 Oh 86.000,00 21.500,00
Tukang 0,15000 Oh 100.000,00 15.000,00
Kepala tukang 0,01500 Oh 110.000,00 1.650,00
Mandor 0,01300 Oh 110.000,00 1.430,00
79.230,00
ABK-H 6.36.b 1 M1 PASANGAN NOK ATAS, SAMPING DAN WALLFLASHING GENTENG METAL WARNA BERPASIR
Nok atas, samping dan wallflashing genteng metal 1,10000 M1 54.500,00 59.950,00
Paku skrup 0,05000 Kg 45.000,00 2.250,00
Pekerja 0,25000 Oh 86.000,00 21.500,00
Tukang 0,15000 Oh 100.000,00 15.000,00
Kepala tukang 0,01500 Oh 110.000,00 1.650,00
Mandor 0,01300 Oh 110.000,00 1.430,00
101.780,00
ANALISA BIAYA KONSTRUKSIPekerjaAN LANGIT-LANGIT (ABK-I) SNI DT 91-0013-2007
ABK-I 6.7.a 1 M2 PASANGAN LANGIT-LANGIT PLAFOND GYPSUM BOARD 9 MM
Gypsum board 120 x 240 x 9 mm 0,36400 Lbr 123.000,00 44.772,00
Paku skrup 0,11000 Kg 45.000,00 4.950,00
Pekerja 0,10000 Oh 86.000,00 8.600,00
Tukang 0,05000 Oh 100.000,00 5.000,00
Kepala tukang 0,00500 Oh 110.000,00 550,00
Mandor 0,00500 Oh 110.000,00 550,00
64.422,00
ABK-I 6.7.b 1 M2 PASANGAN LANGIT-LANGIT PVC PANEL
Panel PVC warna putih 1,25000 Lbr 148.000,00 185.000,00
Paku skrup 0,11000 Kg 45.000,00 4.950,00
Pekerja 0,10000 Oh 86.000,00 8.600,00
Tukang 0,05000 Oh 100.000,00 5.000,00
Kepala tukang 0,00500 Oh 110.000,00 550,00
Mandor 0,00500 Oh 110.000,00 550,00
204.650,00
ANALISA BIAYA KONSTRUKSIPekerjaAN SANITASI (ABK-J) RSNI. T-15-2002
ABK-J 6.16.a 1 M1 PASANGAN SALURAN AIR HUJAN 30 X 30 CM
Galian tanah 26/56 CM (ABK-B 6.1) 0,14560 M3 62.950,00 9.165,52
Pasangan 1/2 batu bata 1 : 4 (ABK-D 6.11) 0,70000 M2 111.706,00 78.194,20
Plesteran 1 : 4, tebal 15 mm (ABK-E 6.4) 1,18000 M2 56.894,00 67.134,92
Acian plesteran 1,18000 M2 33.950,00 40.061,00
Beton tumbuk 1 : 3 : 5, tebal 5 CM (ABK-G 6.1) 0,01500 M3 796.124,29 11.941,86
Pasir urug, tebal 5 CM (ABK-B 6.11) 0,03000 M3 266.900,00 8.007,00
214.504,50
HARGA
KODE ANALISA DAN URAIAN PASANGAN KOOFISIEN JUMLAH ( Rp.)
SATUAN ( Rp. )
ANALISAANALISA BIAYA KONSTRUKSIPekerjaAN
BIAYA KONSTRUKSIPekerjaAN PERSIAPAN
BESI DAN (ABK-A)
ALUMINIUM RSNI
(ABK-K) SNIT-15-2002
DT 91-0014-2007
ABK-K 6 1 M2 MEMASANG BAJA RINGAN ZINCALUME C.75.75 + R.32.45 DENGAN JARAK 120 - 150 CM
Chanal zincalume C.75.75 mm 0,62000 Btg 95.000,00 58.900,00
Reng zincalume R.32.45 mm 0,60000 Btg 74.000,00 44.400,00
Baut screw driver 28,00000 Bh 400,00 11.200,00
Dyna bold 1,60000 Bh 4.800,00 7.680,00
Pekerja 0,20000 Oh 86.000,00 17.200,00
Tukang las 0,45000 Oh 100.000,00 45.000,00
Kepala tukang 0,01000 Oh 110.000,00 1.100,00
Mandor 0,05000 Oh 110.000,00 5.500,00
190.980,00
ABK-K 21.a 1 M1 PASANGAN RANGKA HOLLOW 40.40 MM
Holow galvanis 40.40 mm 2,00000 M1 15.400,00 30.800,00
Perlengkapan (100% dari harga rangka) 1,00000 Unit 15.400,00 15.400,00
Pekerja 0,35000 Oh 86.000,00 30.100,00
Tukang 0,35000 Oh 100.000,00 35.000,00
Kepala tukang 0,03500 Oh 110.000,00 3.850,00
Mandor 0,01800 Oh 110.000,00 1.980,00
117.130,00
ANALISA BIAYA KONSTRUKSIPekerjaAN LANTAI DINDING (ABK-M) SNI DT 91-0012-2007
ABK-M 6.35.a 1M2 PASANGAN LANTAI KERAMIK WARNA ANTI SLIP 20 x 20 CM
Keramik warna anti slip 20 x 20 CM 25,00000 Bh 3.500,00 87.500,00
Portland cement 10,00000 Kg 1.400,00 14.000,00
Pasir pasang 0,04500 M3 192.000,00 8.640,00
Semen warna 1,30000 Kg 2.500,00 3.250,00
Pekerja 0,70000 Oh 86.000,00 60.200,00
Tukang 0,35000 Oh 100.000,00 35.000,00
Kepala tukang 0,03500 Oh 110.000,00 3.850,00
Mandor 0,03500 Oh 110.000,00 3.850,00
216.290,00
ABK-M 6.35.e 1M2 PASANGAN LANTAI GERANIT WARNA 60 x 60 CM
Geranit warna 60 x 60 CM 2,77778 Bh 117.000,00 325.000,00
Portland cement 10,00000 Kg 1.400,00 14.000,00
Pasir pasang 0,04500 M3 192.000,00 8.640,00
Semen warna 1,30000 Kg 2.500,00 3.250,00
Pekerja 0,70000 Oh 86.000,00 60.200,00
Tukang 0,35000 Oh 100.000,00 35.000,00
Kepala tukang 0,03500 Oh 110.000,00 3.850,00
Mandor 0,03500 Oh 110.000,00 3.850,00
453.790,00
ABK-M 6.35.g 1M2 PASANGAN LANTAI KARPET KARET ANTI SLIP
Karpet Karet Anti Slip 1,25000 M 205.000,00 256.250,00
Tukang 0,35000 Oh 100.000,00 35.000,00
Mandor 0,03500 Oh 110.000,00 3.850,00
295.100,00
HARGA
KODE ANALISA DAN URAIAN PASANGAN KOOFISIEN JUMLAH ( Rp.)
SATUAN ( Rp. )
ANALISABIAYA
ANALISA BIAYAKONSTRUKSIPekerjaAN
KONSTRUKSIPekerjaANPENGECATAN
PERSIAPAN (ABK-A)
(ABK-N)RSNI T-15-2002
PT.T.38-2000-C
ABK-N 6.7 1 M2 PENGECATAN BIDANG KAYU LAMA
Plamir dempul kayu 0,15000 Kg 25.100,00 3.765,00
Cat Dasar (1 kali ulang) 0,17000 Kg 45.000,00 7.650,00
Cat penutup (1 kali ulang) 0,17000 Kg 65.000,00 11.050,00
Pekerja 0,07000 Oh 86.000,00 6.020,00
Tukang 0,07500 Oh 100.000,00 7.500,00
Kepala tukang 0,00800 Oh 110.000,00 880,00
Mandor 0,00300 Oh 110.000,00 330,00
37.195,00
ABK-N 6.14.a 1 M2 PENGECATAN EXTERIOR TEMBOK BARU
Plamir tembok/semen putih 0,10000 Kg 2.200,00 220,00
Cat dasar wiether shield (1 kali ulang) 0,10000 Kg 54.000,00 5.400,00
Cat penutup exterior ( 2 kali ulang ) 0,26000 Kg 61.000,00 15.860,00
Pekerja 0,02000 Oh 86.000,00 1.720,00
Tukang 0,06300 Oh 100.000,00 6.300,00
Kepala tukang 0,00600 Oh 110.000,00 660,00
Mandor 0,00300 Oh 110.000,00 330,00
30.490,00
KETERANGAN SINGKATAN ISTILAH
Singkatan CM = Centi Meter (satuan)
Singkatan KG = Kilo Gram (satuan)
Singkatan M1 = Meter Panjang (satuan)
Singkatan M2 = Meter Persegi (satuan)
Singkatan M3 = Meter Kubik (satuan)
Singkatan OH = Orang Hari (satuan)
Singkatan PC = Portland Cement (semen)
Singkatan PU = Pasir Urug (agregat)
Singkatan PP = Pasir Pasang (agregat halus <5 mm)
Singkatan PB = Pasir Beton (agregat kasar -40 mm)
Singkatan KR = Kerikil/Koral (agregat pasir batu)