Professional Documents
Culture Documents
FOR
SUPPLY OF
INDEX
1. Tender notice
2. Special Instructions
4. Schedules “A to P”
7. Technical Specifications
We confirm as under:
SIGNATURE OF TENDERER
With Seal
NOTE: - Please furnish the above required confirmations without which your offer
is liable to be passed over.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
INDEX
I – INSTRUCTION TO TENDERERS
2.1 Scope
2.2 Standards
2.3 Project Data
2.4 System Particulars
2.5 Erection Supervision
2.6 Drawings and manuals
2.7 Raw material
2.8 Testing and inspection
2.9 Spare Parts
2.10 Production Schedule & Progress Report
2.11 Packing & Dispatch of Equipment
2.12 Rejection
2.13 Mode of Dispatch
2.14 Insurance
2.15 Terms of Payment
2.16 Foreign Exchange
2.17 Delivery
2.18 Deviations from Specification
2.19 Performance Guarantee
2.20 Quantity
2.21 Training of Engineers
2.22 Penal Charges
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
SCHEDULES
[I-1]
1. INSTRUCTIONS OF TENDERERS
Tenderers are requested to go through the tender inviting notice & instructions carefully and
furnish complete information along with their tender bid offer, failing which their tender may not
be considered. Tenderers are requested to visit wave site www.upptcl.org &
etender.up.nic.in for other details & corrigendum if any, may also be noticed till date of
opening of tender. In case of ambiguity, the Tenderer may contact in the office. Tenders shall
be received upto 12:00 Hrs. on date of opening in two parts each shall be in separate sealed
cover.
[I-2]
Offered equipment should have given three years proven trouble free operational
service in tropical climate. However, in case of equipment being manufactured in India
under valid FOREIGN COLLABORATION, operating experience in tropical climate of
offered collaborator’s equipment, shall also be acceptable provided copy of valid
collaboration agreement for the equipment offered, is submitted with the tender.
Further in case of offer of imported equipment, the three years operating experience
will be considered in respect of those areas only which are similar to the tropical
conditions prevailing in India.
The tenderer must have all necessary facilities at their works for carrying out such
routine and acceptance tests as prescribed in the relevant ISS and any other routine
and acceptance test as specified in the specification. Documentary evidence of
existence of such facilities will be filled along with the tender.
1.2.4 (A) TYPE TEST FOR INDIGENOUS BIDS OR FULLY IMPORTED BIDS:
The offered equipment must have been fully type tested as per relevant ISS and / or
any other specified international standards, during the last 5 years period to be
reckoned from the date of opening of tender, Photo copy of such type test reports/
certificates must be submitted along with the tender bid. The type test certificates of
proto type manufactured and tested by foreign collaborators of the tenderers at their
works shall not be acceptable for indigenously manufactured equipment.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
[I-3]
(B) FOR BIDS UNDER 1.2.2 (A)
1.2.5 For those indigenous manufacturers who have neither manufactured 20% quantity
indigenously nor got their equipment type tested but are qualifying because of their
foreign collaborator’s manufacturing experience and type testing, the maintenance
period shall be 54 months from the date of receipt of material at site or 48 months from
the date of commissioning, which ever is earlier, instead of 18 months & 12 months
respectively as provided under clause 30 of Form B.
1.2.6 The purchaser at his discretion may consider to award a trial order for small quantity to
those bidders who have proven design & meet the requirements of Clause 1.2.1, 1.2.3
& 1.2.4 (A) Such suppliers shall continue to be eligible for trial order under this clause
till their equipment has given three years trouble free operational service except for
new transformer oil for which one year trouble free operational service against trial
order will suffice for regular orders.
The above cited experience and manufactured quantities shall be counted as on the
date of opening of the tender.
1.3.1 The tenderer shall submit his tender in two separate parts. Each part shall be kept in
double cover, inner one being sealed.
The envelopes of both the parts shall be kept in another envelope which shall also be
sealed and super-scribed on top, as under:
“Tender for supply of 36 KV, 400-200/1-1A Single Phase, 2-Core CTs, 0.2 accuracy
class against E-Tender specification No. T-17/2017-18 due for opening on date
03.05.2017 at 13.00 hrs.”
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
10
[I-4]
1.3.2.1 Tenderers required to deposit earnest money as specified Rs. 33,000.00 for full
tendererd quantity. In case, any tenderer wishes to quote for lesser quantity, the
amount of earnest money may be reduced proportionately.
In case, any tenderer deposits earnest money of a lesser amount, his offer shall be
considered for the proportionate quantity only unless specified otherwise in the special
instructions, earnest money shall be accepted in any of the following forms only.
(a) Bank Draft drawn in favour of the officer specified in tender notice.
OR
(b) Bank Guarantee from a scheduled Bank In India, executed on a non-judicial stamp
paper worth Rs. 100/- as per U.P Stamp Act, on the specified proforma appended with
form ‘B” ( only applicable when amount of earnest money exceeds Rs. 5,000/-)
Any deviation from or addition to the text of the specified proforma of bank Guarantee
shall render the bank guarantee invalid for the purpose of opening of tender bid part–II.
1.3.2.2 Offers without earnest money shall not be considered under any circumstances.
1.3.2.3 Besides the Earnest money, other relevant informations and the following documents,
duly filled in must also accompany the tender bid part-I.
TENDER COST AMOUNTING TO RS. 3435/- IN FAVOUR OF EXECUTIVE
ENGINEER, ELECTRICITY TRANSMISSION DIVISION, UPPTCL, MEERUT.
1. Schedule A: Tender Form
2. Schedule B: Document regarding Pre-qualifying details of the tenderer.
3. Schedule C: Declaration
4. Schedule D: Proforma for joint undertaking by the collaborator/
Associates with tenderer
5. Schedule E: General particulars
6. Schedule F: List of drawings and literature enclosed with the tender
7. Schedule G: Schedule of Deviations from “Technical specification”.
8. Schedule H: Schedule of Deviations from “Instructions to Tenderers”.
9. Schedule I: Schedule of deviations from “General requirements of
Specification”.
10. Schedule J: Schedule of deviations from “General Condition of
Contract Form A/B”.
11. Schedule K: List of recommended spare parts for five years.
12 Schedule L: List of recommended special tools & tackles.
13. Schedule M: List of recommended test sets & testing Instruments.
14. Schedule N: Terms & conditions of supervision of erection &
Commissioning.
15. Schedule P: Schedule of quoted guaranteed delivery.
16. Schedule Q: Schedule of offered quantity.
17. Schedule R: Guaranteed Technical Particulars
18. Complete technical details, specification and literature of the equipment
offered.
19. Income Tax Clearance.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
11
[I-5]
Only the prices and the following documents duly filled in must accompany tender bid
part-II.
1.3.4. On the date of tender opening at appointed time, part –I of the tender shall be opened
publicly in the presence of authorized representatives of the tenderers. The date and
time of opening of tender part-II shall be intimated separately, later on.
1.3.5 Any action on the part of the tenderers to revise the prices and / or change the
structure of price (s) at his own instance after the opening of the tender may result in
rejection of the tender and/or debarring the tenderer for participation in purchase by the
Corporation for one year in first instance.
1.4 VALIDITY
The tenders shall be valid for 90 days from the date of opening of the tender or any
extended date of opening. Tender with lesser validity are liable to be rejected.
1.5.1 The equipment shall be installed at different places in U.P. hence the tenderer must
quote F.O.R Destination prices of all the items (along with F.O.R. works prices) for
dispatch to any Railway Station in U.P. The unit F.O.R destination price shall comprise
of the following components.
The Tenderers must clearly specify these components individually besides the F.O.R.
destination prices.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
12
[I-6]
The prices quoted should be exclusive of all taxes, duties, octroi charges etc, which will
be paid at actuals on production of relevant original vouchers. However the tenderers
must indicate the rates of various taxes/ duties leviable, as on the date of tender
opening, on various price components as given in price schedule. Form C will be
obtained by the contractor from the concerned consignees. In no case form C will be
demanded through bank.
1.5.3.2.The component of packing and forwarding, freight and insurance charges shall remain
FIRM in all respects throughout the currency of the contract.
1.5.3.3 Tenderer shall quote FIRM prices only, for the spare parts, type tests, service charges
for erection and commissioning of the equipment.
1.5.3.4 No price variation shall be claimed against documents to be negotiated through bank.
1.5.3.5 Bank charges, if any, for documents to be negotiated through bank, shall be borne by
the tenderer.
1.5.3.6 In the event of dispatch of equipment beyond contractual delivery period, the claims
shall be raised only after allowing for the due price reduction as per provisions of the
order.
13
[I-7]
1.6.1 In comparing tenders and making awards, the purchaser may consider such factors as,
compliance with specification, relative quality and adaptability of suppliers or services,
experiences, record of integrity in dealing, ability to furnish repairs and maintenance
service, the time of delivery, capability to perform, and available facilities such as
adequate shops, equipment plant, technical organization etc.
1.6.2 In case prices of some items are given in lump-sum, where unit prices are required,
purchaser reserve the right to evaluate unit price on the basis of the quoted lump-sump
prices.
1.6.3 In case, where a tenderer does not quote F.O.R. destination price asked for, their
quoted unit prices shall be loaded by appropriate additional factors on Ex-work prices
as below.
1.6.4 Since the Tenderers have been asked to quote unit variable (Ex-work) prices only
without any ceiling limit on either side, no advantage shall be given to those tenderers
who quote either “FIRM” price or “VARIABLE PRICES WITH CEILING”.
1.6.5 No payment prior to dispatch of materials shall be made by the Corporation under any
circumstances. Tenderers are advised not to ask any such advance payment. Request
for such advance payment will not be considered even if the tenderers are willing to
pay interests charges thereon. Tenderers asking for advance payment are liable to be
rejected.
1.6.6 The ruling date of basic prices of raw materials for the price variation purposes shall be
same for all the offers (as specified in Clause No. 1.5.3.1 of these instructions). In
case, it is prior to the notified date, the quoted Ex-works prices shall be brought as per
IEEMA formula. However, no loading shall be considered for dates mentioned beyond
notified date.
1.6.7 Any rebate/discount linked with quantity, terms of payments in any conditions shall not
be considered for the purpose of evaluation and comparison of such offers vis-à-vis
others. However, the same may be availed while placing order with such successful
Tenderers.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
14
[I-8]
1.6.8 If the tenderer fails to quote pries for any of the item(s) /component(s) as asked for or
confirm its supply free of cost, the highest prices as quoted by other tenderer for the
same shall be added to arrive at F.O.R. destination computed prices of such tenderer
for comparison purpose only.
1.6.9 The prices shall be compared inclusive of excise duty & VAT.
1.6.10 Loading on any account as may be deemed necessary in the opinion of the Purchaser
to bring the various offers at par to each other for comparison purposes, may be done
at the discretion of the Purchaser.
The purchaser reserves the right to split the order among various tenderers in any
manner chooses without assigning any reason.
1.8.1 The purchaser is not bound to accept the lowest tender and may reject any or all the
tenderers, without assigning any reason.
1.8.2 The successful tenderers, if required to do so, may have to enter into a contract
agreement with the purchaser as per General conditions of form A/B and other special
conditions attached with the tender specifications.
1.8.3 For signing the contract a duly authorized representative of the successful tenderer
shall be required to sign and accept the contract at Meerut at a reasonable notice.
1.8.4 Tenderers shall ensure to put initials on each and every page of the tender. Last page
of each document forming part of the tender shall bear full signature under official seal
fully disclosing the name, designation and relationship with the firm of the signatory. In
case of a partnership concern, the tender may be signed by all the partners of the firm
or by one of them holding power of attorney (copy to be furnished along with the offer).
In case of Corporation/Companies, tender may be signed either by the President or
Secretary or any other person authorized to tender in the legal name of corporation /
company (copy of such authority to be furnished along with the offer).
15
[I-9]
1.10 DEVIATIONS :
The offer should be strictly in line with conditions, specification and other requirements
maintained in this tender specification document. No deviations are permitted except
under special circumstances should the tenderer wish to depart from the General
requirements or Technical Specification or General Conditions of Contract Form A/B. In
any way he must draw specific attention to such departure(s). All such deviations shall
specifically be filled up in the relevant deviation schedule. If deviations are not
specifically recorded in these schedules and submitted along with the tender
document it will be presumed that there are no deviations and this interpretation will be
binding upon the tenderer.
Purchaser is, however, not bound to accept all or any deviations as mentioned in such
schedules. Tenderers are also advised not to enclose their own standard or printed
conditions for sale etc. as the same shall not be considered.
1.11 CANVASSING :
No tenderer shall canvass any Corporation’s official of the Engineer, with respect to his
own or other’s tender. Contravention of this condition will result in rejection of the
tender. This clause shall not be deemed to prevent the tenderer from supplying to the
Engineer any further information/clarification asked for, by the Engineer.
All disputes arising out of and touching or relating to the subject matter of agreement,
shall subject to the jurisdiction of Local Courts of Meerut and High Court of judicature
at Allahabad only.
The following is deemed to be added at the end of the Para-1 in the Arbitration clause
31 of Form-B. “In the case of refusal/neglect by such nominee, chairman UPPTCL may
nominate another person in his place.”
SPECIAL NOTE:
It would be possible to consider offers only if both the above conditions are
acceptable.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
16
[G-1]
2.1 SCOPE:
2.1.2 Equipments shall be offered complete with all parts necessary for their efficient
operation. Such parts shall be deemed to be within Contractor’s scope whether
specifically mentioned or not. Equipments in all respects shall incorporate the high test
quality of modern engineering, design and workmanship.
2.1.3 The General Conditions of Contract Form “A/B”, copies of which are attached hereto,
form an integral part of this specification. The contractor shall supply all material and
perform all works in strict accordance therewith. In the event of conflict between
General conditions of contract form ‘A/B’ and this specification, the later shall prevail.
2.1.4 The General requirement of specifications comprise of this chapter and detailed
technical specifications. These are supplementary to each other and essential for
complete interpretation of the Purchaser’s requirement.
2.2 STANDARD:
2.2.1 Except as modified by this tender specification, all material and equipment shall
conform to the requirement of the latest editions of relevant ISS/IEC.
2.2.2 However, in the event of the tenderer offering equipment conforming to standards other
than ISS/IEC standards, the salient point of comparison between the standard adopted
and relevant ISS/IEC standards shall be indicated clearly in the proposal.
2.2.3 Should the tenderer wish to depart from the provisions of the specifications, either on
accounts of manufacturing practices or for any other reason, he shall clearly mention
the departure and submit complete justification supported by information, drawings etc
as will enable to assess the suitability of equipment(s) offered.
In the event of the tenderer’s specifications, drawings, forms and tables etc. being
found to disagree with the requirement of this specification at any stage, these
specifications shall be binding, unless the departures have been duly approved in
writing by the purchaser.
17
[G-2]
(h) Hot and humid tropical Climate conducive to rust and fungus growth.
(i) Rated system voltage 420 kV, 245 kV, 145 kV, 36 kV
(ii) System frequency 50 Hz, This may vary by + 5%
(iii) Number of phases Three
(iv) Neutral Effectively Earthed
(v) Auxiliary power supply:
Auxiliary electrical equipment shall be suitable for operation on the following supply
system.
All devices must be suitable for a continuous operation over the entire range of voltage
variations:
18
Each of the forgoing supplies will be made available by purchaser at one terminal point
for each equipment for operation of accessory and auxiliary equipment. If 110 Volts AC
supply is required, the Contractor shall provide his own auxiliary transformer.
Contractor’s scope shall include distribution beyond the points of supply, including
supply of interconnection cables and terminal blocks etc.
2.5.1 The tenderer shall quote for the services of an Erection Engineer who shall assume full
responsibility for the erection, testing and commissioning of the equipment offered.
Skilled and unskilled labour and petty tools of general use would be provided by the
purchaser.
2.52 The tenderer shall submit a list of all special tools and instruments required for the
erection, testing & commissioning and shall include the same in the tender.
2.5.3 The tenderer shall indicate perdiem, and per mensem rates for the services of the
Erection Engineer. Tenderer shall also indicate the estimated time required for the
erection, testing and commissioning of the equipment offered.
2.6.1 Along with the tender the tenderers shall submit the following drawings :
2.6.2 In the event of order being placed, the Contractor shall furnish three prints of each
drawing of the Engineer of the Contract, within 4 weeks of the date of order.
2.6.3 In addition, the Contractor shall submit to the Engineer within reasonable time but at
least 3 months before despatch of equipments, the complete bill of material with each
item identifiable in the detailed drawing with references. This will also form detailed
packing list of the equipments.
2.6.4 The Engineer shall return to the contractor one print of each drawing (a) stamped
“APPROVED’ OR (b) marked up with comments.
19
[G-4]
2.6.5 The Contractor on receipt of prints stamped “APPROVED” shall furnish the following
drawings to the Engineer of the contract:
(a) 6 sets of prints of each drawings for each consignee and 3 sets for Engineer of
the Contract.
(b) 6 Sets of detailed bill of material for each consignee and 3 sets for Engineer of
contract.
(c) One direct reading reproducible of each drawing and bill of material.
All the prints of drawings and bills of materials and the reproducible are to be
forwarded to the Engineer of the Contract, before any dispatches are made.
2.6.6 MANUALS :
The Contractors shall furnish bound copies of erection, commissioning and operation /
maintenance manuals giving detailed instructions, procedures, precautions for all the
equipments supplied by him. The manuals shall be specific to equipments supplied and
not of general nature.
The contractor shall submit two preliminary copies of such manuals to the Engineer for
review and approval.
Thereafter, six sets of final approved manuals shall be sent to each consignee and 3
sets shall be sent to Engineer of the contract, shall be sent before dispatch of the
equipment otherwise the contractor shall reduce ex-works price by an amount of 2%
from his bill. This amount will be released only on the certificate from the Engineer of
the Contract about receipt of all drawings / reproducible manuals.
2.8.1 TESTING:
Purchaser shall have the right to witness any type, routine and acceptance test on the
equipment offered.
Witnessing of test or their approval would not relieve the contractor of his responsibility
to supply the equipment as per the specification.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
20
[G-5]
The contractor shall adhere to strict quality assurance over all the manufacturing,
testing processing and other activities, whether at his works, or his sub-contractor’s
work, including the suppliers of the raw materials, etc. Detailed Quality Assurance
Programme (QAP) will be submitted with the tender, giving step by step checks and
counter check, tests, sampling procedures etc, to ensure quality of the equipment to
meet the requirements. This shall also include the test details for type, routine and
acceptance test required, Such Q.A.P. shall be approved by the purchaser before
implementation.
2.8.3 INSPECTION:
2.8.3.1 The purchaser reserves the right to inspect any machinery and material to ensure that
approved Q.A.P. is being strictly implemented by the Contractor or his Sub-Contractor
/Supplier under this contract, and to reject any item found defective in workmanship or
design, or otherwise unsuitable for the use and purpose intended or which is not in
accordance with the intent of this contract. The Contractor should, on demand by the
purchaser, rectify or replace such defective or unsuitable equipment, or the purchaser
may, at the contractor’s expense, rectify or replace such defective or unsuitable
equipment, whether before or after supply.
2.8.3.2 The contractor shall advise the purchaser at least 4 weeks in advance as to when the
equipment will be ready for stage / final inspection at the contractor’s work or at his
Sub-contractor’s works.
2.8.3.3 The Purchaser’s Inspecting Engineers at all time have access to all part of shops
where the equipment is being manufactured and also shall be provided with all
reasonable inspection facilities by the contractor and /or sub-contractor.
2.8.3.5 The tenderer is required to record the following certificates on the invoices and
challans of each and every consignment:
“Certified that material being dispatched against the above invoices and challan has
been inspected and tested by the representative of Engineer of the contract or (date)
and all the test results were satisfactory, as per approved test certificate enclosed”.
OR
Certified that inspection of material being dispatched against the above invoice and
challan has been waived off by …………………………………………………..(Engineer
of Contract vide letter No………………Dt. )”(Copy enclosed) and all the acceptance
and Routine tests as per relevant standards and those
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
21
[G-6]
provided in Contract, have been conducted and all the test results were found
satisfactory as per test certificates enclosed.”
Tenderer shall be recommended a set of spare parts required for normal maintenance
or equipment offered for a period of five years.
The Contractor shall furnish detailed production schedule for all major component to be
supplied. The schedule shall include dates of completion of:-
2.11.1 All equipment/material shall be suitably packed for transport, carriage at site and
outdoor storage during transit. The contractor shall be responsible for any damages to
the equipment during transit due to improper and inadequate packing. The cases
containing fragile material, or material easily prone to damage, shall be very carefully
packed and marked with appropriate caution symbols i.e. ‘FRAGILE’, HANDLE WITH
CARE; USE NO HOOK etc. The contents of each packing shall bear marking that can
be readily identified from the packing shall provide complete protection from moisture,
termites and mechanical shocks etc. Wherever necessary proper arrangement for
attaching slings for lifting shall be provided. All packages shall be clearly marked with
gross weight, signs showing ‘UP & DOWN’, sides for boxes, contents of each
package, order No. and date and unpacking instruction considered necessary. Any
material found short inside the packing case, shall be supplied by the contractor
without any extra cost. Tenderer shall ascertain prior to shipment, from concerned
authorities, the transport limitations, like weight and maximum allowable package size
of transportation.
All packing case and packing material shall become the property of the Purchaser.
2.11.2 The equipment/material shall be dispatched to the respective sub-station. The detailed
dispatch instruction will be intimated to the successful tenderer.
The contractor shall intimate, at least ten days in advance, to the consignee (s), as
well as to the Engineer, the probable date when the equipment are to be ready for
dispatch. A telegraphic intimation shall also be given to the consignee (s) immediately
after the dispatch of equipment mentioning the specification number and approximate
weight of each package to enable him to take the delivery and unload the material in
case the dispatch document are not received by him in time.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
22
[G-7]
2.11.3 A list in duplicate containing details of equipment for verification at site shall also be
placed inside each package and shall correspond with the advice note and approved
bill of material.
2.11.4 Bill (s), duly pre receipted, in triplicate in accordance with approved terms of payment
and together with all necessary dispatch documents, shall be sent to consignee (s)
under registered cover with intimation to Engineer of the Contract.
2.11.5 Any demurrage/wharfage or other charges payable due to non implementation of any
of the above instruction shall be to contractor’s account.
2.12. REJECTION:
2.12.1 Purchaser reserves the right to reject any equipment if during the tests at works or
site, the test value achieved do not comply with the respective standard / specifications
and exceeds that tolerable limits.
2.12.2 Contractor shall replace rejected equipment with a new equipment complying with the
guaranteed value as promptly as possible and at no extra cost to the purchaser.
Purchaser reserves the right to retain any rejected equipment and take into service
until the contractor supplies the new equipment.
2.12.3 Rejection of any equipment will not be held as a valid reason for delay in timely
completion of the work.
2.13.1 The equipments are to be dispatched from Contractor’s work to any destination in U.P.
as per the dispatch instructions given by the Engineer (Consignees).
2.13.2 All other equipments shall be dispatched by goods trains, unless otherwise advised by
the Engineer / consignee (s).
2.14 INSURANCE
2.14.1 The contractor shall arrange, secure or maintain insurance as may be necessary to
protect his own interests and the interests of the Corporation against all risks. The risks
that are to be covered under the insurance shall include, but not be limited to, the loss
or damage in transit, theft, pilferage/riot, civil commotion, weather conditions, accident,
or all kinds of fire war risks during ocean transportation only.
2.14.2 Insurance is to be taken FOR destination value of the Equipment for transit from the
manufacturer’s warehouse to the Purchaser’s warehouse plus 45 days storage
thereafter.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
23
[G-8]
2.14.3 All damages and shortages of the equipment after its delivery to destination railway
station and transportation to stores and storage thereafter shall be notified by the
consignee by registered post to contractor or his authorized representative, within 30
days for making good the damage or loss by way of replacement of the equipment
damaged or lost.
2.14.4 The contractor shall take up the matter with insurance company for finalization of
claims and Purchaser shall provide required information. All further action in
connection with making and setling of claim, if any, will be carried out by the contractor
for which no extra payment will be made.
The contractor shall be responsible to make good the damage or loss by way of repairs
and /or replacement of equipment free of cost irrespective of the fact whether claim is
accepted by the insurance Co. or not, without waiting claims settlement.
2.14.5 The scope of such insurance shall cover the entire value of the Contract from time to
time.
2.15.1 The terms of payment shall be as per Clause 21 of form B/clause 25 of form A. In case
of delay in delivery the Tenderer shall raise invoices after allowing price reduction due
to late delivery as detailed in Clause 27 of Form B/Clause 32 form A. In case drawings
and manuals are not submitted as per clause 2.6.5 and 2.6.6, a further deduction of
2% shall also be made.
2.15.2 For equipment to be dispatched by Road transport, the payment will be made after the
receipt of goods at site.
2.15.3 Tenderers may note that terms of payment through letter of credit is not acceptable.
2.17 DELIVERY:
2.17.1 Material will be delivered within 45 days from the date of approval of drawing. Firm will submit
drawing within seven days from the date of issue of order. If the firm does not submit drawing
within seven days of order the delivery period shall be count from the date of issue of supply order..
2.17.2 Date of despatch documents (R/R) shall be treated as the date of delivery. In case of
dispatch by road transport, the date of receipt of goods at site/UPPTCL store shall be
treated as date of delivery.
2.17.3 Delivery should be quoted specifically and explicitly and should be guaranteed under
price reduction clause of form A/B.
2.17.4 The delivery should be effected in serviceable lot/sets of equipment. In case of part
dispatch, the delivery shall be deemed to have been effected when last component/
part of the equipment of serviceable lot/set has been delivered.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
24
[G-9]
2.18 DEVIATION:
2.20.1 The purchaser will depute his engineers for period as mutually agreed, at the
manufacture’s work for a purpose of familiarization with equipments and techniques
covered under the specification, including training in commissioning, operation,
maintenance and trouble shooting aspects etc. The contractor shall provide the
necessary training facilities free of cost to the Purchaser and also indicate suggested
training programme etc. In case, this training course is being run regularly by the
Manufacturer or his principals, this may be indicated in the tender along with details of
training duration, scheduled date, course content etc. The traveling expenses from
U.P. to their place of training and back and maintenance expenses of the deputed
trainees shall be borne by the purchaser.
2.20.2 The contractor shall depute his senior Engineer/Specialists to the Training
Institute/Staff college of the purchaser for training /familiarization course when
requested by the purchaser.
2.21PENAL CHARGES :
The inspection call shall be given only when the equipment has actually become ready,
in all respects. A period of 4 weeks (WITHIN U.P) /6 weeks (beyond U.P) shall be
allowed to U.P.P.T.C.L for making travel arrangements of inspecting officers to reach
the works. In case the equipment is not available for inspection at the time of arrival of
inspecting officers, the tenderer shall pay to UPPTCL towards futile journey a sum
decided by Chief Engineer (Transmission West) and demanded by “Engineer of
Contract”. This amount shall be paid within 30 days from the date of demands.
Further action for inspection of material shall be taken only after the said amount is
deposited”.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
25
[S-1]
SCHEDULE ‘A’
TENDER FORM
FOR SUPPLY / SUPPLY & ERECTION OF EQUIPMENT/MATERIAL FOR SUB-
STATIONS
FROM:
To,
The Chief Engineer (Transmission West)
U.P.Power Transmission Corporation Ltd.,
‘’Pareshan Bhawan” 130-D,Victoria Park,
Meerut.
Sir,
With reference to your invitation to tender for the above I / WE hereby offer to the U.P. Power
Transmission Corporation Limited. Items in the schedule of prices and delivery annexed or such portion
thereof as you determine in strict accordance with the annexed conditions of contract Form ‘B’ /’A’,
specifications and schedules of Rates to the Satisfaction of the Purchaser or in default thereof to forfeit
and pay to the Uttar Pradesh Power Transmission Corporation Ltd., the sum of money mentioned in the
said conditions.
The rates quoted are inclusive pro-rata and in full satisfaction of all claims.
I/WE agree to abide by tender for the period of 6 months from the date fixed for receiving of the same .
I/We hereby undertake and agree to execute a contract in accordance with the conditions of the contract.
Encl: As above
Date……………………………Day of …………………………………………2017
Yours faithfully
26
[S-2]
SCHEDULE ‘B’
PRE QUALIFICATION DETAIL OF THE OFFER
1. EXPERIENCE:
Sl. Breif No. of years of Name and complete Date of Name of S/S Period of Copy of
No. Technical experience of address of Purchaser supply & or power stn. Trouble type test
details of manufacturer (copies of performance quantity where installed free report s
equipment report be enclosed) and date of operation (enclosed
Commissioning / not
enclosed)
2. TESTING FACILITIES:
Sl. Name of tests Details of testing Range upto which place testing
No equipment test can be performed
available
(i) Routine:
a)
b)
c)
(ii) Acceptance:
a)
b)
c)
(iii) Type :
a)
b)
c)
Note: IN case facility of test not available at works, place where such test would be carried out be
specified.
Full Signature……………………..
Name ……………………………..
Designation………………………..
Company Seal
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
27
[S-3]
SCHEDULE ‘C’
DECLARATION
(To be executed on a non-judicial stamp paper of Rs. 10/- with a revenue stamp of Rs.1/- affixed)
…………………………………….
In Consideration of the U.P. Power Transmission Corporation Ltd., having treated the Tenderer
to be an eligible person whose tender may be considered , the Tenderer hereby agree to the
condition that the proposal in response to the above invitation shall not be withdrawn within 6
months (or any extension thereof ) from the date of opening of the tender, also to the condition
that if thereafter the Tenderer does withdraw his proposal within the said period, the Earnest
Money deposited by him may be forfeited to the U.P. Power Transmission Corporation Limited
and at the discretion of the Purchaser, the purchaser may debar the tenderer from tendering for
minimum period of one year reckoned from the date of opening of the tender.
Witness Tenderer
Full Signature……………………..
Name ……………………………..
Designation………………………..
Company Seal
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
28
[S-4]
SCHEDULE ‘D’
PROFORMA FOR JOINT UNDERTAKING BY THE COLLABORATOR /
ASSOCIATE AND THE TENDERER
(To be stamped in accordance with U.P. State Act.)
To,
The Chief Engineer (Transmission West)
U.P.Power Transmission Corporation Ltd.,
‘’Pareshan Bhawan” 130-D,Victoria Park,
Meerut.
Dear Sir,
(In terms of ‘Instruction to Tenderer’ in the specification no………………………for the
design, manufacture, testing, delivery erection & commissioning (as specified ),of
…………………………………………………………
……………………………………………………………………………………………………………
………………………………………………(Name of the Equipment)
It is a condition that the tenderer as well as their collaborator / associate shall jointly and
severally undertake the responsibility for the successful performance of the Contract (herein after
referred to as contract) which is qualified for the award on the basis of expertise of collaborator
/associate.
We …………………………………having our registered office at
………………………….(herein after referred to as Collaborator /Associate ) which in turn shall
include our successor, admistatrator, recruiter and assign and we ……………………having our
registered office at ……………………………………….((herein after called Tenderer /Contractor ) are
held jointly and severally liable and bound up-to U.P POWER TRANSMISSION CORPORATION
LIMITED ( herein after referred to as Purchaser ) which expression shall include its successor,
administrator and assign, for the successful performance of the contract including the overall
responsibility for the design, manufacturer, testing delivery, performance etc of
…………………………………………….(Name of the equipment ) in accordance with the contract.
The Collaborator / Associate hereby agree to depute their technical experts from time to time to
Contractor’s works / project site as mutually agreed upon between the Purchaser and the Contractor’s in
order to discharge the Contractor’s obligations as stipulated in the Contract. The Tenderer and the
Collaborator / Associate hereby agree that this undertaking shall be irrevocable and it shall form and
integral part of the Contract.
In witness there of the Collaborator / Associate and the Tenderer have through their authorized
representative, set their hands seal on this ………………………………………………….day of
……………………………………2017.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
29
[S-5]
WITNESS: COLLABORATOR/ASSOCIATE
Designation………………………..
Seal
WITNESS: TENDERER
Designation………………………..
(Official address)
Seal
Seal
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
30
[S-6]
SCHEDULE ‘E’
SCHEDULE OF GENERAL PARTICULARS
31
[S-7]
32
[S-8]
36. Equipment quoted in-service since : Given the year with evidence/
Not given
37. Tax and duties : Applicable extra / not applicable
38. Excise duties : Applicable extra / not applicable
41. Erection and commissioning period Per unit : Enclosed / not enclosed
(Schedule N)
42. Commissioning charges :
Name ……………………………..
Designation………………………..
Date…………………………………
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
33
[S-9]
SCHEDULE ‘F’
LIST OF DRAWING AND LITERATURE ENCLOSED WITH THE TENDER
Seal of company
Full Signature……………………..
Name ……………………………..
Designation………………………..
Date…………………………………
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
34
[S-10]
SCHEDULE ‘G’
DEVIATIONS FROM ‘TECHNICAL SPECIFICATION’ & ITS PRICE INCIDENCE.
(All deviations from the “Technical Specification” shall be filled in clause, in this schedule; compliance
with the specification will be taken as granted if the deviation is not specifically mentioned in this
schedule. In case the tenderer is required to agree to the standard clause, then he may indicate the
amount by which the tenderered price will thereby be increased or decreased.
The Tenderer hereby certifies that the above mentioned are the only deviations from the ‘Technical Specification’.
Seal of company
Full Signature……………………..
Name ……………………………..
Designation………………………..
Date…………………………………
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
35
[S-11]
SCHEDULE ‘H’
DEVIATIONS FROM ‘INSTRUCTION TO TENDERERS’ & SPECIAL CONDITION
OF THE CONTRACT.
(All deviations from the ‘Instruction to Tenderers ’ shall be filled in clause, in this schedule,
compliance with the Specification will be taken as granted if the deviation are not specifically
mentioned in this schedule. In case the tenderer is required to agree to the standard clause, then he may
indicate the amount by which the tenderered price will thereby be increased or decreased.
The Tenderer hereby certifies that the above mentioned are the only deviations from the ‘Instructions to
Tenderers’.
Seal of company
Full Signature……………………..
Name ……………………………..
Designation………………………..
Date…………………………………
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
36
[S-12]
SCHEDULE ‘I’
DEVIATIONS FROM “GENERAL REQUIREMENTS OF SPECIFICATION” & ITS
PRICE INCIDENCE.
(All deviations from the “General requirements of specification” shall be filled in clause, in this
schedule, compliance with the Specification will be taken as granted if the deviation are not specifically
mentioned in this schedule. In case the tenderer is required to agree to the standard clause then he may
indicate the amount by which the tenderered price will thereby be increased or decreased.
The Tenderer hereby certifies that the above mentioned are the only deviations from the ‘General requirements of
specification’.
Seal of company
Full Signature……………………..
Name ……………………………..
Designation………………………..
Date…………………………………
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
37
[S-13]
SCHEDULE ‘J’
DEVIATIONS FROM “GENERAL CONDITONS OF CONTRACT FORM A/B” & ITS
PRICE INCIDENCE.
(All deviations from the “General Conditions of Contract form A/B” shall be filled in clause, in this
schedule, compliance with the specification will be taken as granted if the deviation are not specifically
mentioned in this schedule. In case the tenderer is required to agree to the standard clause then he may
indicate the amount by which the tenderered price will thereby be increased or decreased .
The Tenderer hereby certifies that the above mentioned are the only deviations from the ‘General conditions of
contract form A/B’.
Seal of company
Full Signature……………………..
Name ……………………………..
Designation………………………..
Date…………………………………
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
38
[S-14]
SCHEDULE ‘K’
LIST OF RECOMONDED SPARE PARTS & THEIR PRICES
(Tenderer shall give below a list of spare parts recommended for 5 years trouble free operations of
equipment offered by them and its prices.)
Seal of company
Full Signature……………………..
Name ……………………………..
Designation………………………..
Date…………………………………
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
39
[S-15]
SCHEDULE ‘L’
LIST OF RECOMONDED SPECIAL TOOLS AND TACKLES & ITS PRICES
(Tenderer shall give below a list of special tools and tackles required for erection, commissioning,
operations and maintenance of equipment offered by him.)
The tenderer hereby certifies that the above mentioned are the only special tools and tackles required for
erection, commissioning, operation and maintenance of equipment offered by him.
Seal of company
Full Signature……………………..
Name ……………………………..
Designation………………………..
Date…………………………………
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
40
[S-16]
SCHEDULE ‘M’
LIST OF RECOMONDED TEST SETS & TESTING INSTRUMENTS & THEIR
PRICES
(Tenderer shall give below a list of recommended test sets and testing instruments required for erection,
commissioning, operations and maintenance)
The Tenderer hereby certifies that the above are the only test sets and testing instruments required for erection,
commissioning operation and maintenance of equipment offered by him.
Seal of company
Full Signature……………………..
Name ……………………………..
Designation………………………..
Date…………………………………
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
41
[S-17]
SCHEDULE ‘N’
RATES OF SUPERVISION CHARGES OF ERECTION & COMMISSIONING
ENGINEER
Seal of company
Full Signature……………………..
Name ……………………………..
Designation………………………..
Date…………………………………
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
42
[S-18]
SCHEDULE ‘P’
SCHEDULE OF QUOTED GUARANTEED DELIVERY
(Guaranteed delivery completion period will be reckoned from the date of issue of letter of
intent or detailed order as the case may be)
(date or R/R will be deemed to be the date of delivery). In case of dispatch by road transport,
date of receipt of material at site/Corporation stores shall be taken as date of delivery.
Seal of company
Full Signature……………………..
Name ……………………………..
Designation………………………..
Date…………………………………
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
43
SCHEDULE - R
SCHEDULE OF TECHNICAL AND GUARANTEED PARTICULARS FOR CTs
(To be filled by the Tenderer)
1. Type
2. Manufacturer’s Type Designation
3. (i) Rated Voltage
(ii) Max. Operating Voltage
4. (i) Rated Primary Current
(ii) Continuous Primary Current Rating
5. (i) Rated Primary Current
(ii) Continuous Secondary Current Rating
6. Number of Primary Turns
1. Number of Cores
2.
Rated Class of Saturation Factor
Outpur Accuracy (Accuracy Limit Factor)
Core-I
Core-II
Core-III
3. Secondary Voltage
Knee Point Secondary Limiting
Voltage Voltage
Core-I Volts
Core-II Volts
Core-III Volts
44
11. One minute power frequency wet withstand test voltage KV rms
12. Weight of oil Kg.
13. Total Weight Kg.
14. Mounting details
15. Overall dimensions
16. Characteristics (To be enclosed)
(i) Ratio & Phase angle curves
(ii) Magnetisation curves
(iii) Ratio correction factor curves
23. Details of insulation materials used for
Primary & secondary windings.
45
The CTs should be of outdoor type single phase oil immersed, self cooled hermetically
sealed, suitable for operation in humid atmosphere in the tropical sun with climatic
conditions as indicated in para 2.3 of page G-2 and in areas subject to heavy lightening
storms. The CTs shall comply with requirements as indicated below:-
1. Nominal System Voltage 33KV (rms)
2. Highest System voltage 36KV (rms)
3. Frequency 50 C/s (47 to 51 C/s)
4. Insulation level (BIL) 170KV
5. Short Time Current rating (1 sec.) 25.00KA (rms)
6. Transformation Ratio 400-200/1-1A
7. No. of Cores 2 Nos.
8. Quantity required 90 Nos.
9. Creepage distance of bushing Not less than 900mm.
10. Continuous Primary Current rating 120% of rated primary current.
11. Continuous Secondary current rating 2A
3.0 DESIGN CRITERIA & STANDARD:
It shall be as under:
CT Ratio Core No. Rated Accuracy Accuracy Resistance Min. Max. Purpose
Output Class Limit of Sec. Knee mag.
Factor Wdg. Point Current
(Ohm) Voltage at 25%
not (Volts) Knee
exceeding Voltage
(mA)
46
Except as modified in the specification the CTs and accessories shall be in accordance
with the latest editions of the following standards:
1. IS 2705 (Part I to IV) Specification for CTs
& IEC 60444-1
2. IS 2099 Specification for High Voltage porcelain bushing
3. IS 3347 Specification for dimensions for porcelain T/F
4. IS 335 Specification for Insulating oil for T/F & switchgear
5. IS 3202 Code of practice : climate proofing of electrical
equipment
4.0 GENERAL :
The separately mounted CTs should be of single phase, oil immersed, hermetically
sealed type and self cooled, suitable for the service indicated, complete in all respects
confirming to the modern practice and of design and manufacture.
5.0 WINDINGS :
5.1 The instrument security factor of the CTs core to be used for metering should be low
enough not to cause any damage to measuring instruments on account of maximum
short circuit current (The instrument security factor should not exceed 5.0).
5.2 CT core to be used for protective relaying purpose should be of accuracy class
specified. Magnetization curves should be furnished with the tender for the CTs for
metering and protection cores.
5.3 Continuous current rating of the secondary winding of core-II & III should be min. 2
Amp. The secondary terminals should be brought out in a compartment on once side of
CT for easy access. The secondary terminals should be provided with short circuiting
arrangement. The secondary leads should be adequately reinforced to withstand normal
handling without damage. The secondary terminal box should also be partitioned so as
to house the metering terminals separately with the provision of sealing and locking of
the metering terminals. “METERING” & PROTECTION’ should be clearly indicated
on each compartment cover respectively by engraving or by providing the metallic
plate.
6.0 The CTs should withstand satisfactorily the di-electric test voltage corresponding to
basis impulse level of 170KV for 36KV CTs.
7.0 SPECIAL FEATURES OF CTs:
7.1 The protection cores should be of high grade non-aging electrical silicon laminated steel
of low hysteresis loss and high permeability to ensure hign accuracy at both, normal and
over current. The CTs should be hermetically sealed to eliminate breathing and prevent
air moisture from entering the tank. These should be provided with the oil level gauge
and pressure relieving device capable of releasing at normal internal pressure.
7.2 INSULATING OIL : Should confirm to the requirement of IS – 335.
7.3 CREEPAGE DISTANCE :
The bushing and insulating porcelains should be suitable for installation in heavily
polluted atmospheres having creepage distance of 900mm (min).
8.0 TYPE OF MOUNTING :
The CTs should be suitable for mounting on steel structures having 4 Nos. holes of
15mm Ø at 300mm x 300mm square spacing.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
47
Necessary galvanized flanges etc. for the base of the CTs should be supplied.
48
(i) Verification of terminal marking and polarity (as per clause 9.2 of IS – 2705).
(ii) Power frequency dry withstand tests on primary windings (as per clause 9.3 of
IS–2705).
(iii) Power frequency wet withstand tests on secondary windings (as per clause 9.4
of IS-2705).
(iv) Over voltage inter turn test (as per clause 9.5 of IS-2705)
(v) Determination of errors or other characteristics of 0.2 accuracy class.
(vi) An excitation curve with voltage in volts on ordinate and magnetization current
in mA on abscissa plotted up to the voltage level above knee point voltage when
10% increase in voltage causes 50% increase in magnetization current.
(vii) The CT shall be tested for leakage and strength by applying to complete CT and
porcelain housing filled with oil at a pressure not less than 0.7 Kg/cm2 for a
period of 24.00 hrs. or not less than 1 Kg./ cm2 above the maximum operating
pressure for a period of 6.00 hrs. If leakage occurs the CT shall be retested after
all leakages have been stopped.
11.4 TYPE TESTS:
11.4.1 The bidders must have not the following type tests carried out on their offered CTs as
per latest edition of IS-2705 to PREQUALIFY.
Following latest type test reports may be submitted with the offer, which should have
been conducted within 5 years of date of tender opening.
(a) Short time current test (as per clause 9.6 of IS-2705).
(b) Temperature rise test (as per clause 9.7 of IS-2705).
(c) Lightning impulse test for current transformer for service in electrically exposed
(as per clause 9.8 of IS-2705).
(d) High voltage power frequency withstand voltage test on outdoors current transformer
(dry & wet) as per clause 9.9 of IS-2705.
(e) Determination of errors or other characteristics of 0.2 accuracy class.
All other type tests shall be in accordance with the latest revision of IS-2009 : 1973.
11.4.2. In the event of an order the supplier shall arrange to carry out Heat run test on one CT
selected by the representative of Purchaser in his presence.
11.5. One certified copies of routine test reports for each CT shall be furnished. Each report
shall include the following information:
(a) Complete identification of the CT including UPPTCL contract No. and item No.
manufacture type and Sl. No. and CT rating brief particulars of the CT parameter and
specification.
(b) Brief description of each test as specified and carried out, results of test and where
necessary interpretations of results. Tests shall be listed in the same order to facilitate
checking the report.
Any fittings, accessories, or apparatus which might not have been mentioned in the specification but
which are usual or necessary in the equipment of similar nature, are to be provided by the contractor
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
49
without extra cost. All apparatus must be complete in all details whether mentioned in the specification or
not.
18.0. INSURANCE :
The supplier shall arrange to provide insurance cover for the equipment for transit cum 45 days storage
from manufactures warehouse to purchaser’s warehouse as detailed in clause 2.14.2 of General
Requirements of specification.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
50
FORM - B
General Conditions of Contract
For
Supply of Plant and Machinery for Works
General Conditions for the Supply of Plant and Machinery for Works Pertaining to the
U.P. Power Transmission Corporation Limited
The "Sub Contractor" shall mean the person named in the contract
for any part of the work or any person to whom any part of the
Contact has been sublet with the consent in writing of Engineer and
the heirs, legal representatives, successors and assigns of such
person.
The "Engineer" shall mean the officer placing the order for the work
with the Contractor and such other officer as may be duly
authorised and appointed in writing by the Purchaser to act as
Engineer for the purposes of the Contract and in case where no
such officer has been so appointed, the Purchaser or his duly
authorised representative.
The "Site" shall mean the site of the proposed work as detailed in
the Specification or any other place in Uttar Pradesh where work is
to be executed under the Contract.
51
(2)
Words importing the singular only shall also include the plural and
vice versa where the context requires.
After the tender has been accepted by the Purchaser all order or
instructions to the Contractor shall, except as herein otherwise
provided, be given by the Engineer on behalf of Purchaser.
Contract Drawing 4. The Contractor shall submit in duplicate, to the Engineer for
his approval, drawings of the General Arrangement of the plant to
be provided and such detailed drawings, other than shop drawings,
as may be reasonably necessary.
52
(3)
Mistake in drawings 5. The Contractor shall be responsible for and shall pay for any
alterations of the plant due to any discrepancies, errors or
omissions in the drawings and other particulars supplied by him,
whether such drawing or particulars have been approved by the
Engineer or not, provided that is such discrepancies, errors or
omissions are due to inaccurate information or particulars furnished
to the Contractor by the Engineer any alterations in the plant
necessitated by reasons of such inaccurate information or
particulars shall be paid for by the Purchaser.
Subletting of contract 6. The Contractor shall not, without consent in writing of the
Engineer or Purchaser which shall not, be unreasonably withheld,
assign or sublet this Contract, any substantial part thereof other
than for raw materials, or minor details or for any part of the plant of
which makers are named in the Contract provided that any such
consent shall not relieve the Contractor from any obligation, duty or
responsibility under the contract.
Patent rights 7. In the event of any claim or demand being made or action
being brought against the Purchaser for infringement or alleged
Infringement of Letters patent, in respect of any machine, plant or
thing used or supplied by the Contractor under this Contract or in
respect of any method of using or working by the Purchaser of such
machine, plant or thing, the Contractor will indemnify the Purchaser
against such claim or demand and all costs and expenses arising
from or incurred by reason of such claim or demand PROVIDED
THAT the Purchaser shall notify the Contractor immediately any
claim is made and that the Contractor shall be at liberty, if he so
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
53
(4)
Quality of materials 8. The plant shall be manufactured and constructed in the best
and most substantial and most workmanlike manner and with
materials of the best or of approved qualities for their respective
uses.
Delivery and import 10. The costs of delivering the whole of the material f.o.r., at the
license fee railway stations specified shall be borne by the Contractor.
The Import Lenience fee for the Import of equipment or component part of
raw materials, if required, shall be paid by the Contractor even when the
Import License may have to be taken in the name of the Purchaser.
54
(5)
Death, Bankruptcy etc. 13. If the contractor shall die or commit any act of Bankruptcy,
or being a corporation commence to be wound up except for
reconstruction purposes or carry on its business under a Receiver,
the executors, successors, or the representatives in law of the
estate to the contractor or any such receiver, liquidator, or any
person in whom the contract may become vested shall forthwith
give notice thereof in writing to the purchaser and shall for one
month, during which he shall take all reasonable steps to prevent
stoppage of the manufacture of plant have the option of carrying out
the contract subject to his or their providing such guarantee as may
be required by Purchaser, but not exceeding the value of the plant,
for the time being remaining unexecuted. In the event of stoppage
of the manufacture of the plant the period of the option under this
clause shall be fourteen days only provided that should the above
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
55
(6)
Inspection and testing 14. The Engineer and his duly authorized representatives, shall
have at all reasonable time access to the contractor's premises, and
shall have the power at all reasonable times to inspect and examine
the materials and workmanship of the plant during its manufacture
there and if part of the plant is being manufactured on other
premises the contractor shall obtain for the Engineer and for his
duly authorised representatives permission to inspect its as if the
plant manufactured on the Contractor's own premises.
Test at Contractor's In all cases where the contractor provides for tests, whether at the
Premises premises of the contractor or of any sub-contractor the contractor,
except where otherwise specified shall provide free of charge such
labour, materials, electricity, fuel, water, stores apparatus, plant in
accordance with the contract and shall give facilities to the Engineer
or to his authorized representative to accomplish such testing.
56
(7)
Test on site In all cases where the contract provides for tests on the site, the
purchaser, except otherwise specified, shall provide, free of charge,
such labour, materials, electricity, fuel, water, stores, apparatus and
instruments as may be requisite from time to time and as may
reasonably be demanded, efficiently to carry out such tests of the
plant or workmanship in accordance with the contract.
Delivery of plant 15. The plant or material shall not be forwarded until
shipping/dispatch instructions shall have been given to the
contractor.
Engineer's Supervision 16. The manufacture and supply of plant shall be carried out under the
direction and to the reasonable satisfaction of the Engineer.
Engineer's decision 17. In respect of all matters which are left to the decision of the
Engineer including the granting or with holding of certificates, the
Engineer shall if required to do so by the Contractor, give in writing
a decision thereon, and his reasons for such decision. If the
decision is not accepted by the contractor the matter shall at the
request of the contractor be referred to arbitration under the
provision for arbitration hereinafter contained, but subject to the
right of reference to arbitration such decision shall be final and
binding on the contractor.
Liability for accident and 18. The contractor shall be responsible for loss, damage or
damage depreciation to goods up to delivery at site.
Replacement of defective 19. If during the progress of manufacture of supply or plant the
plant or materials Engineer shall decide and notify in writing to the contractor that the
contractor has manufactured any plant or part of plant unsound or
imperfect, or had supplied any plant inferior in quality to that
specified, the contractor on receiving details of such defect or,
deficiency shall, at his own expense, within such time that may be
reasonably necessary for the purpose proceed to alter, reconstruct
or remove such plant or part of plant, or supply fresh materials up to
the standard specification and in case the contractor shall fail
to do so, the Purchaser may, on giving the contractor seven day's
notice in writing of his intention to do so proceed to alter,
reconstruct or remove such plant or part of plant, or supply
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
57
(8)
Deduction from 20. All costs, damages of expenses which the Purchaser may
contract price have paid for which under the contract the contractor is liable may
be deducted by the Purchaser from any money due or which may
become due by him to the contractor under this contract, or may be
recovered by suit or otherwise from the contractor.
Terms of payment 21. (1) Subject to any deduction which the Purchaser may be
authorised to make under the contract, or subject to any additions
or deductions provided for under clause 11, the Contractor shall, on
the certificate of the Engineer, be entitled to payment as follows:
Provided that each of the payments under this clause shall be due
on the last day of the month in which the invoice for the amount due
together with necessary documents is received by the Purchaser:
Provided also that the Purchaser shall not be bound to make any
payment under sub-clause (a) unless the amount of such payment
represents at least 8 percent of the total contract value of the plant.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
58
(9)
Provisional sums 22. In any case where the contract price includes a provisional
sum to be provided by the contractor for meeting the expenses of
extra work or for work to be done or material to be supplied by a
sub-contractor, such sum shall be expended or used, either wholly
or in part or be not used at the discretion of the Engineer and
entirely as he may decide and direct. If no part or only a part thereof
be used, then the whole or the part not used, as the case may be
shall be deducted from the contract price. If the sum used is more
than such provisional sum the contractor shall pay the excess. In
the case of material supplied or work done by a sub-contractor, the
total of the net sum paid to the sub Contractor on account of such
materials or works and a sum equal to 10% of such net sum
allowed as contractor's profit shall be deemed to be the sum of
used. Non of the work or articles to which such sum of money refers
shall be done or purchased without the written order of the
Engineer. The Contractor shall allow the subcontractors every
facility for the supply of materials or execution of their several works
simultaneously with his own, and shall, within fourteen days after
the Engineer has requested him in writing to do, so pay the dues of
such sub-contractors on account of such materials or works,
PROVIDED ALWAYS that the contractor shall have no
responsibility with regard to such works or articles unless he shall
have previously approved the sub-contractor and/or the material or
plant to be supplied.
Certificate of Engineer 23. (1) Every application to the Engineer for a certificate
must be accompanied by a detailed invoice (in duplicate) setting
forth in order of the Schedule of Prices, particulars of the plant
supplied and the certificates as to such plant as in the reasonable
opinion of the Engineer, in accordance with the contract shall be
issued within fourteen days of the application for the same.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
59
(10)
Certificate not to effect 24. No certificate of the Engineer on account, nor any sum paid on
right of the Purchaser or account by the Purchaser, nor any extension of time granted under
Contractor clause 26 shall affect or prejudice the rights of the Purchaser,
against the Contractor either under this Agreement or under the
law, or relieve the Contractor, of his obligations for the due
Performance of the Contract or be interpreted as approval of the
plant manufactured or supplied, and no certificate of the Engineer
shall create liability on the Purchaser to pay for any alteration,
amendments, variations or additions not ordered in writing by the
Engineer, or absolve the Contractor of his liability for the payment of
damages whether due, ascertained or certified or not, or of any
such sum against the payment of which he is bound to indemnify
the Purchaser nor shall any such certificate nor the acceptance by
him of any sum paid on account otherwise affect or prejudice the
rights of the contractor against the Purchaser either under this
Agreement or under the law.
Suspension of works 25. The Purchaser shall pay to the Contractor all reasonable
expenses incurred by the Contractor by reason of suspension of the
manufacture of plant or delay in shipment by order in writing of the
Purchaser or the Engineer unless such suspension or delay shall
be due to some default on the part of the Contractor or Sub-
Contractor.
Extension of time for 26. The time given to the Contractor for dispatch or delivery
completion shall be reckoned from the date of receipt by the Contractor of the
order, together with all necessary information and drawings, to
enable the work to be put in hand.
Price reduction 27. If the Contractor shall fail in the due performance of his
Contract with in the time fixed by the purchaser or any extension
thereof, the contractor agrees to accept a reduction of the Contract
price by half percent per week reckoned on the contract values of
such portion only of the plant as cannot in consequences of the
delay be used commercially and efficiently during each week
between the appointed or extended time, as the case may be and
actual time of acceptance under clause 29, and such reduction shall
be in full satisfaction of the Contractor's liability for delay but shall
not in any case exceed 10 percent of the contract value of such
portion of the plant.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
60
(11)
Taking over 29. Where the specification calls for performances test before
shipment and these have been successfully carried out, the plant
shall be accepted and taken over and the Engineer shall notify the
Contractor to that effect. When the specification calls for tests on
site the plant shall be taken over immediately after such tests have
been satisfactorily carried out and the Engineer shall notify the
Contractor to that effect.
61
(12)
62
(13)
Construction of 32. The contract shall in all respect be construed and operated
contract as a Contract as defined in the Indian Contract Act, 1872, and all
payments there under shall be made in rupees unless otherwise
specified.
Marginal Notes 33. The marginal notes to any clause of this Contract shall not
affect or control the construction of such clause.
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
63
(14)
FORM OF AGREEMENT
(REFERRED TO IN CLAUSE -3)
THIS AGREEMENT made on the --------------------------- day of -------------2017---------BETWEEN----
--------------------- (hereinafter referred to as the “Contractor”) of the one part AND the U.P. Power
Transmission Corporation Limited (hereinafter called “Purchaser”) of the other part
AND WHEREAS the Purchaser has accepted the tender of the Contractor for the supply and
delivery of the said plant and machinery for the sum of -------------------------------- upon the terms and
subject to the conditions hereinafter mentioned.
NOW THESE PRESENT WITNESSES and the parties hereto hereby agree and declare as
follows, that is to say, in consideration of the payment to be made to the Contractor by the purchaser as
hereinafter mentioned the Contractor shall and will fully provide the said plant and machinery for the said
works on the terms and conditions mentioned in the Contract.
AND in consideration of the due provisions of the said plant and machinery by the Contractor and
due performance of this part of the contract, the purchaser does hereby for himself, his successors or
assigns convenant with the Contractor that he (the Purchaser), his successor or assigns will pay to the
Contractor the said sum of ----------------------------- or such other sum as may become payable to the
Contractor under the provision of the Contract, such payments to be made at such time and in such
manner as is provided by this contract.
IN WITNESS WHEREOF the Parties here to have signed this Deed here under on the dates
respectively mentioned against the signature of each.
(Signed) (Signed)
(for & on behalf of the Purchaser) (Contractor)
(date) (date)
(date) (date)
(date) (date)
Location :: Meerut; Uploading Date And Time ::Saturday, April 1, 2017-14:29:14
64
(15)
1. In consideration of the U. P. Power Transmission Corporation Ltd, Meerut (hereinafter called “the
corporation”) having agreed to exempt --------------- (hereinafter called "the Contractors") from the
demand, under the terms and conditions of Agreement dated ............. made between ---------------
---------- and ---------------------------- for ------------------------ (hereinafter called “the said Agreement”)
of security deposit for the due fulfillment by the said Contractor(s) of the terms and conditions
contained in the said Agreement on production of a Bank Guarantee for Rs. -----------------
(Rupees---------------------only). We ----------------- Bank Ltd. (hereinafter referred as “The Bank”) do
hereby undertake to pay to the Corporation an Amount not exceeding Rs. ---------------------
against any loss of or damage caused to or suffered or would be caused to or suffered by the
Corporation by reasons of any breach by the said Contractor(s) of any of the terms and
conditions contained in the said Agreement.
2. We ------------------------- Bank Ltd. do hereby under take to pay the amount due and payable under
this guarantee without any demur, merely on demand from the Corporation stating that amount
claimed is due by way of loss or damage caused to or would be caused to or suffered by the
Corporation by reason of any breach by the said Contractor of any of the terms or conditions
contained in the said Agreement or by reason of the Contractor’s(s) failure to perform the said
Agreement. Any such demand made on the Bank shall be conclusive as regards the amount due
and payable by the Bank under this guarantee. However, our liability under this guarantee shall
be restricted to an amount not exceeding Rs. ----------
3. We ----------------------- Bank Ltd. further agree that the guarantee herein contained shall remain in
full force, and effect during the period that would be taken for the performance of the said
agreement and that it shall continue to be enforceable till all the dues of Corporation under or by
virtue of the said agreement have been fully paid and its claims satisfied or discharged or till the
Corporation or their only authorised officer certified that the terms and conditions of the said
agreement have been fully and properly carried out by the said Contractor(s) and accordingly
discharge the guarantee. Unless a demand or claim under this guarantee is made on us in writing
on or before ------------------------- we shall be discharged from all liability under this guarantee
there after.
4. We----------------------Bank Ltd further agree with the Corporation that the Corporation shall have
the fullest liberty without affecting in any manner or obligation hereunder to vary any of the terms
and conditions of the said agreement or to extend time of performance by the said Contractor(s)
from time to time or to postpone for any time or from time to time any of the powers exercisable
by the Corporation against the said Contractor(s) and to forbear or enforce any of the terms and
conditions relating to the said Agreement and we shall not be relieved from our liability by reason
of any such variation, or extension, or extension(s) being granted to the said Contractor(s) or for
any forbearance, act of omission on the part of the Corporation or any indulgence by the
Corporation to the said Contractor(s) or by any such matter or thing whatsoever which under the
law relating to sureties would but for this provision have effect of so relieving us.
5. We ------------------------- Bank Ltd. lastly undertake not to revoke this guarantee during its currency
except with the previous consent of the Corporation in writing.
6. Not withstanding any thing contained above the liability of the guarantor hereunder is restricted to
the said sum of Rs.------------------------- and this guarantee shall expire on the -----------------------
day------------------------- of------------------------- 200 --------. Unless a claim under the guarantee is
filled with the guarantor within six months of such date, all claim shall lapse and the guarantor
shall be discharged from the guarantee.
65
(16)
WHEREAS in accordance with the contract agreement dated the ---------------day of ------------ the
Purchaser & Messers ------------------------- a company within the meaning of the Companies Act and
having its registered office at ------------------------- (hereinafter called “the Contractor”) the Contractor
agrees to supply to the Purchaser the ------------------------- as provided in the said Contract.
AND WHEREAS the payment terms under the said Contract provide that in order to take 100%
payment of the Contract value the Contractor shall furnish to the Purchaser a Bank Guarantee in the sum
of 10% value of each consignment dispatched valid for ------------------.
AND WHEREAS instead of furnishing separate guarantee as aforesaid the Contractor wishes to
furnish one guarantee in the sum of 10% value of the Contract valid for ------------------------- and reckoned
from the date ---------------.
66
(17)
unless claim under the guarantee is filed within six months of such date, all claims shall lapse and the
Guarantor shall be discharged from the Guarantee.
IN WITNESS HEREOF
For and on behalf of the Guarantor has signed this deed on the day and year first above written.
Witness:
1. ……………………………………
…………………………………. Signed by
2. ………………………………….
67
(18)
To
Sir,
WHEREAS, Messers ------------------------- a company incorporated under the Indian Companies Act, its
registered offices at -------------------------a firm registered under the Indian Partnership Act and having its business
office at ----------------- son of -------------------- resident of -------------------------carrying on business under the firm's
name and style of Messers ------------------------- at ------------------------- / Sri------------------------- son of ---------------------
----resident of -------------------------at ---------------- / Sri -------------------------son of ------------------------- resident of --------
----------------- / Sri ------------------------- son of -------------------------resident of --------------- / Sri-------------------------son of
------------------------- resident of -----------------of--------partners carrying on business under the firm's name and style
of Messer -------------------------at-------------------------which is a registered partnership (hereinafter called “The
Tenderer”) has/have in response to your Tender Notice against specification number--------- for -------------offered to
supply and/or execute the works contained in the Tenderer's letter no------------------------.
AND WHEREAS the Tenderer is required to furnish you a bank guarantee for the sum of Rs.-------------------
------as earnest money against the tender's offer as aforesaid.
AND WHEREAS we -------------------------------------------------- (name of the Bank), have at the request of the
Tenderer agree to give you his guarantee as hereinafter contained.
NOW THEREFORE in consideration of the promises We, the undersigned, hereby convenant that the aforesaid
tender of the Tenderer shall remain open for acceptance by you during the period of validity as mentioned in the
tender or any extension there of as you and the Tenderer may subsequently agree and if the Tenderer shall, for
any reason back out, whether expressly or impliedly, from his said tender during the period of its validity or any
extension thereof as aforesaid we hereby guarantee to you the payment of the sum of Rs.-------------------------on
demand, notwithstanding the existence of any dispute between the UP Power Transmission Corporation Ltd, and
the Tenderer in this regard AND We hereby agree as follows:
a. That you may without affecting this guarantee grant time or other indulgence to or negotiate further with the
Tenderer in regard to the conditions contained in the said tender and hereby modify these conditions or
add there to any further conditions as may be mutually agreed upon between you and the Tenderer.
b. That the guarantee herein before contained shall not be affected by any change in the constitution of our
Bank or in the constitution of the Tenderer.
c. That any account settled between you and the Tenderer shall be conclusive evidence against us of the
amount due here under and shall not be questioned by us.
d. That this guarantee commences from the date hereof and shall remain in force till the Tenderer, if his
tender is accepted by you, furnished the security as required under the said specifications and executes a
formal agreement as therein provided or (till four months after the period of validity) or the extended period
of validity, as the case may be, of tender, whichever is earlier.
e. That the expressions “Tenderer” and “The Bank” and “The UP Power Transmission Corporation Ltd.”
herein used shall, unless such interpretation is repugnant to the subject or context, include their respective
successors and assigns.
Yours faithfully