RESUMEN DE VALORIZACION DE AVANCE DE OBRA

(Del 01 al 31 de Enero del 2018)


OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARC
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
SUPERVISOR ING MILTON CASTAÑEDA CABADA
AVANCE
PRESUPUESTO BASE
Nº DESCRIPCIÓN DE SUB PRESUPUESTO ACUMULADO ANTERIOR ACTUAL ACUMULADO ACTUAL
(S/.)
Valoriz. (S/.) % Valoriz. (S/.) % Valoriz. (S/.)
1 CANAL DE RIEGO SAN JOSE PINGOBAMBA 131,695.85 1,004.97 0.76% 1,946.80 1.48% 2,951.77
2 OBRAS PROVISIONALES 1304.97 1004.97 77.01% 300 22.99% 1304.97
3 CONSTRUCCION DE BOCATOMA 01 41118.11
4 OBRAS PRELIMINARES 2,955.41
5 OBRAS DE CONCRETO SIMPLE 5,863.11
6 OBRAS DE CONCRETO ARMADO 24,269.71
7 CONSTRUCCION DE ESCOLLERA RIP -RAP 3,875.99
8 VARIOS 4,153.89
9 CONSTRUCCION MURO P/ ENCAUSAMIENTO L=25 28853.53
10 OBRAS PRELIMINARES 80.03
11 MOVIMIENTO DE TIERRAS 1,608.56
12 OBRAS DE CONCRETO SIMPLE 27,164.94
13 CONSTRUCCION MURO P/ ENCAUSAMIENTO L=50 58154.32
14 OBRAS PRELIMINARES 160.05
15 MOVIMIENTO DE TIERRAS 3,469.75
16 OBRAS DE CONCRETO SIMPLE 54,524.52
17 REPOSICIÓN DE CANAL DE CONCRETO L=18 m 1618.33 1618.33 1618.33
18 CURADO DE CONCRETO 646.59 28.476 28.476
19 CANAL DE RIEGO SANTA ISABEL (LLASAVILCA-BAJO) 241,947.74 109,428.18 33,469.44 143,406.12
20 CONSTRUCCION DE BOCATOMA 02 93,125.86 0 0.00
21 OBRAS PRELIMINARES 2,225.92 0.00 0.00
22 OBRAS DE CONCRETO SIMPLE 51,172.82 0.00 0.00
23 OBRAS DE CONCRETO ARMADO 38,900.08 0.00 0.00
24 CONSTRUCCION DE ESCOLLERA RIP -RAP 827.04 0.00 0.00
25 CONSTRUCCION CAJA DE CONTROL EN BOCATOMA 5,259.27 0.00 0.00
26 OBRAS PRELIMINARES 19.12 0.00 0.00
27 MOVIMIENTO DE TIERRAS 112.33 0.00 0.00
28 CONCRETO SIMPLE 1,893.63 0.00 0.00
29 CONCRETO ARMADO 359.19 0.00 0.00
30 VARIOS 2,875.00 0.00 0.00
31 DESARENADOR INC. CANAL DE CONCRETO L=72m 8,818.76 646.13 8,172.63 8,818.76
32 OBRAS PRELIMINARES 159.64 159.64 0.00 159.64
33 MOVIMIENTO DE TIERRAS 486.49 486.49 0.00 486.49
34 CONCRETO SIMPLE 7,612.63 7,612.63 7,612.63
35 VARIOS 560.00 560.00 560.00
36 CONSTRUCCION PASE AEREO P/ TUBERIA L= 20m 14,683.15 8,210.72 6,472.44 14,683.16
37 OBRAS PRELIMINARES 83.57 83.57 0.00 83.57
38 MOVIMIENTO DE TIERRAS 866.80 866.80 0.00 866.80
39 CONCRETO SIMPLE 3,023.07 3,023.07 0.00 3,023.07
40 CONCRETO ARMADO 5,033.74 4,237.28 796.47 5,033.75
41 REVOQUES 600.46 600.46 600.46
42 PINTURA 99.43 99.43 99.43
43 VARIOS 4,976.08 4,976.07 4,976.07
44 PASE CANOA TIPO I 6,974.82 1,289.33 5,685.49 6,974.82
45 MOVIMIENTO DE TIERRAS 204.33 204.33 0.00 204.33
46 CONCRETO SIMPLE 353.92 353.92 353.92
47 CONCRETO ARMADO 6,416.57 1,085.00 5,331.57 6,416.57
48 PASE CANOA TIPO II 601.22 170.44 430.78 601.22
49 MOVIMIENTO DE TIERRAS 15.44 15.44 0.00 15.44
50 CONCRETO SIMPLE 53.09 53.09 53.09
51 CONCRETO ARMADO 532.69 155.00 377.69 532.69
52 ALCANTARILLAS (02 UNDS) L= 6.00 m c/u 3,332.56 784.27 2,548.28 3,332.55
53 MOVIMIENTO DE TIERRAS 164.27 164.27 0.00 164.27
54 CONCRETO SIMPLE 185.81 185.81 185.81
55 CONCRETO ARMADO 2,982.48 620.00 2,362.47 2,982.47
56 PASE PEATONAL 265.98 67.38 198.60 265.98
57 MOVIMIENTO DE TIERRAS 11.58 11.58 0.00 11.58
58 CONCRETO ARMADO 254.40 55.80 198.60 254.40
59 CONSTRUCCION DE CANAL DE CONCRETO L=1.75 KM 83401.5 73,924.21 9,477.28 83,401.49
60 OBRAS PRELIMINARES 2,104.19 2,104.19 0.00 2,104.19
61 MOVIMIENTO DE TIERRAS 9,506.27 9,506.27 0.00 9,506.27
62 CONCRETO SIMPLE 68,117.20 62,313.75 5,803.45 68,117.20
63 VARIOS 3,673.84 3,673.84 3,673.84
64 CONSTRUCCION MURO P/ ENCAUSAMIENTO L=25 22098.3 22,098.30 0.00 22,098.30
65 OBRAS PRELIMINARES 78.45 78.45 0.00 78.45
66 MOVIMIENTO DE TIERRAS 1,394.49 1,394.49 0.00 1,394.49
67 CONCRETO SIMPLE 20,625.36 20,625.36 0.00 20,625.36
68 PASE CON TUBERIA 483.94 483.94 483.94
69 OBRAS PRELIMINARES 17.19 17.19 17.19
70 MOVIMIENTO DE TIERRAS 6.35 6.35 6.35
71 CONCRETO SIMPLE 53.36 53.36 53.36
72 TUBERIA 407.04 407.04 407.04
73 CURADO DE CONCRETO 2902.38 2237.4 508.50 2745.90
74 MITIGACION DE IMPACTO AMBIENTAL 2,873.03 1,436.52 1,436.52
75 FLETE 13,641.02 9,548.71 1,364.10 10,912.81

TOTAL COSTO DIRECTO 390,157.64 119,981.86 38,725.36 158,707.22


GASTOS GENERALES 8.00% 31,212.61 9,598.55 3,098.03 12,696.58
UTILIDAD 7.00% 27,311.03 8,398.73 2,710.77 11,109.51
………………. ………………. ………………. ……………….
SUB TOTAL 448,681.28 137,979.14 44,534.16 182,513.30
IMPUESTO (IGV) 18% 80,762.63 24,836.25 8,016.15 32,852.39
========== ========== ========== ==========
TOTAL PRESUPUESTO CONTRATADO 529,443.91 162,815.38 52,550.31 215,365.70
PORCENTAJE VALORIZADO % 30.75% 9.93% 40.68%
, PROVINCIA CHOTA-CAJAMARCA

SALDO POR EJECUTAR


ADO ACTUAL
% Valoriz. (S/.) %
2.24% 128,744.07 97.76%
100.00% 0.00 0.00%
41,118.11
2,955.41
5,863.11 100.00%
24,269.71 100.00%
3,875.99 100.00%
4,153.89 100.00%
28,853.53 100.00%
80.03 100.00%
1,608.56 100.00%
27,164.94 100.00%
58154.32
160.05
3,469.75
54,524.52
0.00
618.11
98,541.62
93,125.86
2,225.92
51,172.82
38,900.08
827.04
5,259.27
19.12
112.33
1,893.63
359.19
2,875.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.01
0.00
0.00
0.01
0.00
0.00
0.00
0.01
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
156.48
1,436.52
2,728.21

230,013.90
18,401.11
16,100.97
……………….
264,515.99
47,612.88
==========
312,128.87
58.95%
VALORIZACION DE OBRA Nº 02
(Del 01 al 31 de Enero del 2018)
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DE CONTRATO
: S/. 529,443.91

AVANCE ACUMULADO AVANCE ACTUAL


PRESUPUESTO DE OBRA
MES ANTERIOR PRESENTE MES

Precio. TOTAL
ITEM DESCRIPCION UND MET. Unitario PARCIAL S/, % Metrado % Metrado
S/, S/.

01 CANAL DE RIEGO SAN JOSE PINGOBAMBA 131,695.85 1,004.97


1.01 OBRAS PROVISIONALES 1,304.97 1,004.97
1.01 CARTEL DE OBRA DE 3.60 X 2.40 m u 1.00 704.97 704.97 100.00% 1.00 704.97 0.00%
1.02 CAMPAMENTO PROVISIONAL DE LA OBRA mes 2.00 300.00 600.00 50.00% 1.00 300.00 50.00% 1.00
1.02 CONSTRUCCION DE BOCATOMA 01 41,118.11
01.02.01 OBRAS PRELIMINARES 2,955.41
01.02.01.01 TRAZO Y REPLANTEO m2 230.70 2.85 657.50
01.02.01.02 EXCAVACION EN SUELO GRAVOSO BAJO AGUA m3 70.12 4.21 295.21
01.02.01.03 REFINE NIVELACION Y COMPACTACION DE FUNDACIONES m2 207.50 1.34 278.05
01.02.01.04 DEMOLICIÓN DE COLCHON DISCIPADOR e = 0.15m m3 8.45 204.10 1,724.65
01.02.02 OBRAS DE CONCRETO SIMPLE 5,863.11
01.02.02.01 CONCRETO f'c=175 kg/cm2 + 25 % PM. EN BASE DE ENCAUSAMIENTO m3 19.34 283.75 5,487.73
01.02.02.02 ENCOFRADO Y DESENCOFRADO m2 16.97 22.12 375.38
01.02.03 OBRAS DE CONCRETO ARMADO 24,269.71
01.02.03.01 CONCRETO f'c=210 kg/cm2 EN BARRAJE m3 47.56 313.10 14,891.04
01.02.03.02 REPOSICIÓN DE CONCRETO f´c =210 kg/cm2 EN COL m3 8.45 301.42 2,547.00
01.02.03.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 1,839.07 3.10 5,701.12
01.02.03.04 ENCOFRADO Y DESENCOFRADO m2 51.11 22.12 1,130.55
VALORIZACION DE OBRA Nº 02
(Del 01 al 31 de Enero del 2018)
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DE CONTRATO
: S/. 529,443.91

AVANCE ACUMULADO AVANCE ACTUAL


PRESUPUESTO DE OBRA
MES ANTERIOR PRESENTE MES

Precio. TOTAL
ITEM DESCRIPCION UND MET. Unitario PARCIAL S/, % Metrado % Metrado
S/, S/.

01.02.04 CONSTRUCCION DE ESCOLLERA RIP -RAP 3,875.99


01.02.04.01 PIEDRA GRANDE PARA ENROCADOS DE ESCOLLERA m3 204.43 18.96 3,875.99
01.02.05 VARIOS 4,153.89
01.02.05.01 COMPUERTA METALICA TIPO TARJETA 1/8" 0.35x0.325 u 1.00 126.39 126.39
01.02.05.02 COMPUERTA METALICA 1/4" DE 0.80x1.75 u 3.00 1,342.50 4,027.50
01.03 CONSTRUCCION MURO P/ ENCAUSAMIENTO L=25 28,853.53
01.03.01 OBRAS PRELIMINARES 80.03
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 52.50 0.21 11.03
01.03.01.02 TRAZO Y REPLANTEO m 25.00 2.76 69.00
01.03.02 MOVIMIENTO DE TIERRAS 1,608.56
01.03.02.01 EXCAVACION EN SUELO GRAVOSO BAJO AGUA m3 89.25 4.21 375.74
01.03.02.02 RELLANO COMPACTADO CON MATERIAL PROPIO m3 32.24 18.94 610.63
01.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 71.27 8.73 622.19
01.03.03 OBRAS DE CONCRETO SIMPLE 27,164.94
01.03.03.01 SOLADO C:H 1:12 e=0.10m m2 52.50 22.12 1,161.30
01.03.03.02 CONCRETO f'c=175 kg/cm2 + 25 % PM. m3 78.63 283.75 22,311.26
01.03.03.03 ENCOFRADO Y DESENCOFRADO m2 158.39 22.12 3,503.59
01.03.03.04 JUNTAS ASFALTICAS m2 9.43 20.02 188.79
VALORIZACION DE OBRA Nº 02
(Del 01 al 31 de Enero del 2018)
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DE CONTRATO
: S/. 529,443.91

AVANCE ACUMULADO AVANCE ACTUAL


PRESUPUESTO DE OBRA
MES ANTERIOR PRESENTE MES

Precio. TOTAL
ITEM DESCRIPCION UND MET. Unitario PARCIAL S/, % Metrado % Metrado
S/, S/.

01.04 CONSTRUCCION MURO P/ ENCAUSAMIENTO L=50 58,154.32


01.04.01 OBRAS PRELIMINARES 160.05
01.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 105.00 0.21 22.05
01.04.01.02 TRAZO Y REPLANTEO m 50.00 2.76 138.00
01.04.02 MOVIMIENTO DE TIERRAS 3,469.75
01.04.02.01 EXCAVACION EN SUELO GRAVOSO BAJO AGUA m3 178.50 4.21 751.49
01.04.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 95.97 18.94 1,817.67
01.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 103.16 8.73 900.59
01.04.03 OBRAS DE CONCRETO SIMPLE 54,524.52
01.04.03.01 SOLADO C:H 1:12 e=0.10m m2 105.00 22.12 2,322.60
01.04.03.02 CONCRETO f'c=175 kg/cm2 + 25 % PM. m3 157.25 283.75 44,619.69
01.04.03.03 ENCOFRADO Y DESENCOFRADO m2 320.54 22.12 7,090.34
01.04.03.04 JUNTAS ASFALTICAS m2 24.57 20.02 491.89
01.05 REPOSICIÓN DE CANAL DE CONCRETO L=18 m 1,618.33
01.05.01 TRAZO Y REPLANTEO km 0.02 929.08 18.58 100.01% 0.02
01.05.02 CORTE EN MATERIAL SUELTO MANUAL m3 6.73 8.73 58.75 100.00% 6.73
01.05.03 REFINE NIVELACION Y COMPACTACION CAJA CANAL m2 28.80 1.34 38.59 100.00% 28.80
01.05.04 CONCRETO f'c=175 kg/cm2 EN CANAL m3 3.04 299.13 909.36 100.00% 3.04
VALORIZACION DE OBRA Nº 02
(Del 01 al 31 de Enero del 2018)
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DE CONTRATO
: S/. 529,443.91

AVANCE ACUMULADO AVANCE ACTUAL


PRESUPUESTO DE OBRA
MES ANTERIOR PRESENTE MES

Precio. TOTAL
ITEM DESCRIPCION UND MET. Unitario PARCIAL S/, % Metrado % Metrado
S/, S/.

01.05.05 ENCOFRADO Y DESENCOFRADO DE CANAL m2 25.20 20.08 506.02 100.00% 25.20


01.05.06 JUNTAS ASFALTICAS m 9.45 9.21 87.03 100.00% 9.45
01.06 CURADO DE CONCRETO 646.59
01.06.01 CURADO DE CONCRETO CON ADITIVO m2 572.20 1.13 646.59 4.40% 25.20
02 CANAL DE RIEGO SANTA ISABEL (LLASAVILCA-BAJO) 241,947.74 109,428.18
02.01 CONSTRUCCION DE BOCATOMA 02 93,125.86 -
02.01.01 OBRAS PRELIMINARES 2,225.92
02.01.01.01 TRAZO Y REPLANTEO m2 398.20 2.85 1,134.87
02.01.01.02 EXCAVACION EN SUELO GRAVOSO BAJO AGUA m3 151.65 4.21 638.45
02.01.01.03 REFINE NIVELACION Y COMPACTACION DE FUNDACIONES m2 337.76 1.34 452.60
02.01.02 OBRAS DE CONCRETO SIMPLE 51,172.82
02.01.02.01 CONCRETO f'c=175 kg/cm2 + 25 % PM. EN BASE DE ENCAUS m3 159.61 283.75 45,289.34
02.01.02.02 ENCOFRADO Y DESENCOFRADO m2 265.98 22.12 5,883.48
02.01.03 OBRAS DE CONCRETO ARMADO 38,900.08
02.01.03.01 CONCRETO f'c=210 kg/cm2 EN BARRAJE Y COLCHON m3 91.49 313.10 28,645.52
02.01.03.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 3,038.20 3.10 9,418.42
02.01.03.03 ENCOFRADO Y DESENCOFRADO m2 37.80 22.12 836.14
VALORIZACION DE OBRA Nº 02
(Del 01 al 31 de Enero del 2018)
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DE CONTRATO
: S/. 529,443.91

AVANCE ACUMULADO AVANCE ACTUAL


PRESUPUESTO DE OBRA
MES ANTERIOR PRESENTE MES

Precio. TOTAL
ITEM DESCRIPCION UND MET. Unitario PARCIAL S/, % Metrado % Metrado
S/, S/.

02.01.04 CONSTRUCCION DE ESCOLLERA RIP -RAP 827.04


02.01.04.01 PIEDRA GRANDE PARA ENROCADOS DE ESCOLLERA m3 43.62 18.96 827.04
02.02 CONSTRUCCION CAJA DE CONTROL EN BOCATOMA 5,259.27
02.02.01 OBRAS PRELIMINARES 19.12
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.25 0.21 1.31
02.02.01.02 TRAZO Y REPLANTEO m2 6.25 2.85 17.81
02.02.02. MOVIMIENTO DE TIERRAS 112.33
02.02.02.01 EXCAVACION EN TERRENO NORMAL m3 7.17 14.55 104.32
02.02.02.02 REFINE, NIVELACION Y COMPACTACION m2 5.98 1.34 8.01
02.02.03 CONCRETO SIMPLE 1,893.63
02.02.03.01 SOLADO C:H 1:12 e=0.10m m2 5.98 22.12 132.28
02.02.03.02 CONCRETO f'c=175 kg/cm2 m3 3.89 296.47 1,153.27
02.02.03.03 ENCOFRADO Y DESENCOFRADO m2 27.49 22.12 608.08
02.02.04 CONCRETO ARMADO 359.19
02.02.04.01 CONCRETO f'c=210 kg/cm2 m3 0.50 316.99 158.50
02.02.04.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 42.19 3.10 130.79
02.02.04.03 ENCOFRADO Y DESENCOFRADO m2 3.16 22.12 69.90
02.02.05 VARIOS 2,875.00
VALORIZACION DE OBRA Nº 02
(Del 01 al 31 de Enero del 2018)
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DE CONTRATO
: S/. 529,443.91

AVANCE ACUMULADO AVANCE ACTUAL


PRESUPUESTO DE OBRA
MES ANTERIOR PRESENTE MES

Precio. TOTAL
ITEM DESCRIPCION UND MET. Unitario PARCIAL S/, % Metrado % Metrado
S/, S/.

02.02.05.01 COMPUERTA METALICA 1/4" DE 0.80 X 1.75m u 2.00 1,342.50 2,685.00


02.02.05.02 REJILLA METALICA 1/2" u 1.00 190.00 190.00
02.03 DESARENADOR INC. CANAL DE CONCRETO L=72m 8,818.76 646.13
02.03.01 OBRAS PRELIMINARES 159.64 159.64
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 52.17 0.21 10.96 100.00% 52.17 10.96
02.03.01.02 TRAZO Y REPLANTEO m2 52.17 2.85 148.68 100.00% 52.17 148.68
02.03.02. MOVIMIENTO DE TIERRAS 486.49 486.49
02.03.02.01 EXCAVACION EN TERRENO NORMAL m3 20.87 14.55 303.66 100.00% 20.87 303.66
02.03.02.02 REFINE, NIVELACION Y COMPACTACION m2 136.44 1.34 182.83 100.00% 136.44 182.83
02.03.03 CONCRETO SIMPLE 7,612.63
02.03.03.01 SOLADO C:H 1:12 e=0.10m m2 3.84 22.12 84.94 100.00% 3.84
02.03.03.02 CONCRETO f'c=175 kg/cm2 m3 15.42 296.47 4,571.57 100.00% 15.42
02.03.03.03 ENCOFRADO Y DESENCOFRADO m2 133.64 22.12 2,956.12 100.00% 133.64
02.03.04 VARIOS 560.00
02.03.04.01 COMPUERTA METALICA 1/4" DE 0.40 X 1.00m u 1.00 560.00 560.00 100.00% 1.00
02.04 CONSTRUCCION PASE AEREO P/ TUBERIA L= 20m 14,683.15 8,210.72
02.04.01 OBRAS PRELIMINARES 83.57 83.57
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 27.31 0.21 5.74 100.00% 27.31 5.74
VALORIZACION DE OBRA Nº 02
(Del 01 al 31 de Enero del 2018)
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DE CONTRATO
: S/. 529,443.91

AVANCE ACUMULADO AVANCE ACTUAL


PRESUPUESTO DE OBRA
MES ANTERIOR PRESENTE MES

Precio. TOTAL
ITEM DESCRIPCION UND MET. Unitario PARCIAL S/, % Metrado % Metrado
S/, S/.

02.04.01.02 TRAZO Y REPLANTEO m2 27.31 2.85 77.83 100.00% 27.31 77.83


02.04.02 MOVIMIENTO DE TIERRAS 866.80 866.80
02.04.02.01 EXCAVACION EN TERRENO NORMAL m3 33.20 14.55 483.06 100.00% 33.20 483.06
02.04.02.02 REFINE, NIVELACION Y COMPACTACION m2 16.00 1.34 21.44 100.00% 16.00 21.44
02.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 41.50 8.73 362.30 100.00% 41.50 362.30
02.04.03 CONCRETO SIMPLE 3,023.07 3,023.07
02.04.03.01 SOLADO C:H 1:12 e=0.10m m2 8.00 22.12 176.96 100.00% 8.00 176.96
02.04.03.02 CONCRETO f'c=175 kg/cm2 m3 9.60 296.47 2,846.11 100.00% 9.60 2,846.11
02.04.04 CONCRETO ARMADO 5,033.74 4,237.28
02.04.04.01 CONCRETO f'c=210 kg/cm2 m3 9.76 316.99 3,093.82 76.84% 7.50 2,377.43 23.16% 2.26
02.04.04.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 428.70 3.10 1,328.97 100.00% 428.70 1,328.97
02.04.04.03 ENCOFRADO Y DESENCOFRADO m2 27.62 22.12 610.95 86.89% 24.00 530.88 13.11% 3.62
02.04.05 REVOQUES 600.46
02.04.05.01 TARRAJEO EN EXTERIORES m2 27.62 21.74 600.46 100.00% 27.62
02.04.06 PINTURA 99.43
02.04.06.01 PINTURA ESMALTE EN EXTERIORES m2 27.62 3.60 99.43 100.00% 27.62
02.04.07 VARIOS 4,976.08
02.04.07.01 SUMINISTRO E INST TUBERIA PVC UF NTP ISO 4435 D = 12" m 27.31 80.34 2,194.09 100.00% 27.31
VALORIZACION DE OBRA Nº 02
(Del 01 al 31 de Enero del 2018)
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DE CONTRATO
: S/. 529,443.91

AVANCE ACUMULADO AVANCE ACTUAL


PRESUPUESTO DE OBRA
MES ANTERIOR PRESENTE MES

Precio. TOTAL
ITEM DESCRIPCION UND MET. Unitario PARCIAL S/, % Metrado % Metrado
S/, S/.

02.04.07.02 SUMINISTRO E INST DE CABLE DE ACERO Ø 5/8" m 28.30 43.29 1,225.11 100.00% 28.30
02.04.07.03 SUMINISTRO E INST DE ABRAZADERAS Y PENDOLAS u 1.00 1,556.88 1,556.88 100.00% 1.00
02.05 PASE CANOA TIPO I 6,974.82 1,289.33
02.05.01 MOVIMIENTO DE TIERRAS 204.33 204.33
02.05.01.01 EXCAVACION EN TERRENO NORMAL m3 9.60 14.55 139.68 100.00% 9.60 139.68
02.05.01.02 REFINE, NIVELACION Y COMPACTACION m2 16.00 1.34 21.44 100.00% 16.00 21.44
02.05.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 4.95 8.73 43.21 100.00% 4.95 43.21
02.05.02 CONCRETO SIMPLE 353.92
02.05.02.01 SOLADO C:H 1:12 e=0.10m m2 16.00 22.12 353.92 100.00% 16.00
02.05.03 CONCRETO ARMADO 6,416.57 1,085.00
02.05.03.01 CONCRETO f'c=210 kg/cm2 m3 11.16 316.99 3,537.61 100.00% 11.16
02.05.03.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 548.52 3.10 1,700.41 63.81% 350.00 1,085.00 36.19% 198.52
02.05.03.03 ENCOFRADO Y DESENCOFRADO m2 53.28 22.12 1,178.55 100.00% 53.28
02.06 PASE CANOA TIPO II 601.22 170.44
02.06.01 MOVIMIENTO DE TIERRAS 15.44 15.44
02.06.01.01 EXCAVACION EN TERRENO NORMAL m3 0.48 14.55 6.98 100.00% 0.48 6.98
02.06.01.02 REFINE, NIVELACION Y COMPACTACION m2 2.40 1.34 3.22 100.00% 2.40 3.22
02.06.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 0.60 8.73 5.24 100.00% 0.60 5.24
VALORIZACION DE OBRA Nº 02
(Del 01 al 31 de Enero del 2018)
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DE CONTRATO
: S/. 529,443.91

AVANCE ACUMULADO AVANCE ACTUAL


PRESUPUESTO DE OBRA
MES ANTERIOR PRESENTE MES

Precio. TOTAL
ITEM DESCRIPCION UND MET. Unitario PARCIAL S/, % Metrado % Metrado
S/, S/.

02.06.02 CONCRETO SIMPLE 53.09


02.06.02.01 SOLADO C:H 1:12 e=0.10m m2 2.40 22.12 53.09 100.00% 2.40
02.06.03 CONCRETO ARMADO 532.69 155.00
02.06.03.01 CONCRETO f'c=210 kg/cm2 m3 0.56 316.99 177.51 100.00% 0.56
02.06.03.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 60.63 3.10 187.95 82.47% 50.00 155.00 17.53% 10.63
02.06.03.03 ENCOFRADO Y DESENCOFRADO m2 7.56 22.12 167.23 100.00% 7.56
02.07 ALCANTARILLAS (02 UNDS) L= 6.00 m c/u 3,332.56 784.27
02.07.01 MOVIMIENTO DE TIERRAS 164.27 164.27
02.07.01.01 EXCAVACION EN TERRENO NORMAL m3 6.01 14.55 87.45 100.00% 6.01 87.45
02.07.01.02 REFINE, NIVELACION Y COMPACTACION m2 8.40 1.34 11.26 100.00% 8.40 11.26
02.07.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 7.51 8.73 65.56 100.00% 7.51 65.56
02.07.02 CONCRETO SIMPLE 185.81 -
02.07.02.01 SOLADO C:H 1:12 e=0.10m m2 8.40 22.12 185.81 100.00% 8.40
02.07.03 CONCRETO ARMADO 2,982.48 620.00
02.07.03.01 CONCRETO f'c=210 kg/cm2 m3 4.21 316.99 1,334.53 100.00% 4.21
02.07.03.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 379.61 3.10 1,176.79 52.69% 200.00 620.00 47.31% 179.61
02.07.03.03 ENCOFRADO Y DESENCOFRADO m2 21.30 22.12 471.16 100.00% 21.30
02.08 PASE PEATONAL 265.98 67.38
VALORIZACION DE OBRA Nº 02
(Del 01 al 31 de Enero del 2018)
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DE CONTRATO
: S/. 529,443.91

AVANCE ACUMULADO AVANCE ACTUAL


PRESUPUESTO DE OBRA
MES ANTERIOR PRESENTE MES

Precio. TOTAL
ITEM DESCRIPCION UND MET. Unitario PARCIAL S/, % Metrado % Metrado
S/, S/.

02.08.01 MOVIMIENTO DE TIERRAS 11.58 11.58


02.08.01.01 EXCAVACION EN TERRENO NORMAL m3 0.36 14.56 5.24 100.00% 0.36 5.24
02.08.01.02 REFINE, NIVELACION Y COMPACTACION m2 1.80 1.34 2.41 100.00% 1.80 2.41
02.08.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 0.45 8.73 3.93 100.00% 0.45 3.93
02.08.02 CONCRETO ARMADO 254.40 55.80
02.08.02.01 CONCRETO f'c=210 kg/cm2 m3 0.36 316.99 114.12 100.00% 0.36
02.08.02.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 23.56 3.10 73.04 76.40% 18.00 55.80 23.60% 5.56
02.08.02.03 ENCOFRADO Y DESENCOFRADO m2 3.04 22.12 67.24 100.00% 3.04
02.09 CONSTRUCCION DE CANAL DE CONCRETO L=1.75 KM 83,401.50 73,924.21
02.09.01 OBRAS PRELIMINARES 2,104.19 2,104.19
02.09.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,277.60 0.21 478.30 100.00% 2,277.60 478.30
02.09.01.02 TRAZO Y REPLANTEO km 1.75 929.08 1,625.89 100.00% 1.75 1,625.89
02.09.02 MOVIMIENTO DE TIERRAS 9,506.27 9,506.27
02.09.02.01 EXCAVACION EN TERRENO NORMAL m3 426.49 14.55 6,205.43 100.00% 426.49 6,205.43
02.09.02.02 REFINE, NIVELACION Y COMPACTACION m2 2,463.31 1.34 3,300.84 100.00% 2,463.31 3,300.84
02.09.03 CONCRETO SIMPLE 68,117.20 62,313.75
02.09.03.01 CONCRETO f'c=175 kg/cm2 m3 218.74 296.47 64,849.85 91.45% 200.05 59,307.64 8.55% 18.69
02.09.03.02 ENCOFRADO Y DESENCOFRADO m2 147.71 22.12 3,267.35 92.00% 135.90 3,006.11 8.00% 11.81
VALORIZACION DE OBRA Nº 02
(Del 01 al 31 de Enero del 2018)
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DE CONTRATO
: S/. 529,443.91

AVANCE ACUMULADO AVANCE ACTUAL


PRESUPUESTO DE OBRA
MES ANTERIOR PRESENTE MES

Precio. TOTAL
ITEM DESCRIPCION UND MET. Unitario PARCIAL S/, % Metrado % Metrado
S/, S/.

02.09.04 VARIOS 3,673.84


02.09.04.01 COMPUERTA METALICA TIPO TARJETA 1/8" 0.35x0.325 u 12.00 126.39 1,516.68 100.00% 12.00
02.09.04.02 JUNTAS ASFALTICAS m2 107.75 20.02 2,157.16 100.00% 107.75
02.10 CONSTRUCCION MURO P/ ENCAUSAMIENTO L=25 22,098.30 22,098.30
02.10.01 OBRAS PRELIMINARES 78.45 78.45
02.10.01.01 LIMPIEZA DE TERRENO MANUAL m2 45.00 0.21 9.45 100.00% 45.00 9.45
02.10.01.02 TRAZO Y REPLANTEO m 25.00 2.76 69.00 100.00% 25.00 69.00
02.10.02 MOVIMIENTO DE TIERRAS 1,394.49 1,394.49
02.10.02.01 EXCAVACION EN SUELO GRAVOSO BAJO AGUA m3 67.50 4.21 284.18 100.00% 67.50 284.18
02.10.02.02 RELLANO COMPACTADO CON MATERIAL PROPIO m3 46.56 18.94 881.85 100.00% 46.56 881.85
02.10.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 26.17 8.73 228.46 100.00% 26.17 228.46
02.10.03 CONCRETO SIMPLE 20,625.36 20,625.36
02.10.03.01 SOLADO C:H 1:12 e=0.10m m2 45.00 22.12 995.40 100.00% 45.00 995.40
02.10.03.02 CONCRETO f'c=175 kg/cm2 + 25 % PM. m3 58.50 283.75 16,599.38 100.00% 58.50 16,599.38
02.10.03.03 ENCOFRADO Y DESENCOFRADO m2 130.49 22.12 2,886.44 100.00% 130.49 2,886.44
02.10.03.04 JUNTAS ASFALTICAS m2 7.20 20.02 144.14 100.00% 7.20 144.14
02.11 PASE CON TUBERIA 483.94
02.11.01 OBRAS PRELIMINARES 17.19
VALORIZACION DE OBRA Nº 02
(Del 01 al 31 de Enero del 2018)
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DE CONTRATO
: S/. 529,443.91

AVANCE ACUMULADO AVANCE ACTUAL


PRESUPUESTO DE OBRA
MES ANTERIOR PRESENTE MES

Precio. TOTAL
ITEM DESCRIPCION UND MET. Unitario PARCIAL S/, % Metrado % Metrado
S/, S/.

02.11.01.01 LIMPIEZA DE TERRENO MANUAL m2 3.00 0.21 0.63 100.00% 3.00


02.11.01.02 TRAZO Y REPLANTEO m 6.00 2.76 16.56 100.00% 6.00
02.11.02 MOVIMIENTO DE TIERRAS 6.35
02.11.02.01 EXCAVACION EN TERRENO NORMAL m3 0.25 14.55 3.64 100.00% 0.25
02.11.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.31 8.73 2.71 100.00% 0.31
02.11.03 CONCRETO SIMPLE 53.36
02.11.03.01 CONCRETO f'c=175 kg/cm2 m3 0.18 296.47 53.36 100.00% 0.18
02.11.04 TUBERIA 407.04
02.11.04.01 SUMINISTRO E INST TUBERIA PVC UF NTP ISO 4435 D = 12" m 6.00 67.84 407.04 100.00% 6.00
02.12 CURADO DE CONCRETO 2,902.38 2,237.40
02.12.01 CURADO DE CONCRETO CON ADITIVO m2 2,568.48 1.13 2,902.38 77.09% 1,980.00 2,237.40 17.52% 450.00
03 MITIGACION DE IMPACTO AMBIENTAL 2,873.03
03.01 ACCIONES DE MITIGACION AMBIENTAL glb 1.00 2,873.03 2,873.03 50.00% 0.50
04 FLETE 13,641.02 9,548.71
04.01 FLETE TERRESTRE A PIE DE OBRA glb 1.00 13,641.02 13,641.02 70.00% 0.70 9,548.71 10.00% 0.10

TOTAL COSTO DIRECTO 390,157.64 119,981.86


GASTOS GENERALES 8.000% 31,212.61 9,598.55
VALORIZACION DE OBRA Nº 02
(Del 01 al 31 de Enero del 2018)
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DE CONTRATO
: S/. 529,443.91

AVANCE ACUMULADO AVANCE ACTUAL


PRESUPUESTO DE OBRA
MES ANTERIOR PRESENTE MES

Precio. TOTAL
ITEM DESCRIPCION UND MET. Unitario PARCIAL S/, % Metrado % Metrado
S/, S/.

UTILIDADES 7% 27,311.03 8,398.73


SUBTOTAL 448,681.28 137,979.14

I.G.V. ( 18.00 % ) 80,762.63 24,836.25


Total Presupuesto 529,443.91 30.75% 162,815.39 9.93%
CAJAMARCA

ACTUAL AVANCE ACUMULADO SALDO


NTE MES MES ACTUAL MES ACTUAL
TOTAL TOTAL TOTAL
% Metrado % Metrado
S/. S/. S/.

1,946.80 2,951.77 128,744.07


300.00 1,304.97 0.00
0.00 100.00% 1.00 704.97 0.00% 0.00 0.00
300.00 100.00% 2.00 600.00 0.00% 0.00 0.00
41,118.11
0.00 2,955.41
0.00 100.00% 230.70 657.50
0.00 100.00% 70.12 295.21
0.00 100.00% 207.50 278.05
0.00 100.00% 8.45 1,724.65
0.00 5,863.11
0.00 100.00% 19.34 5,487.73
0.00 100.00% 16.97 375.38
0.00 24,269.71
0.00 100.00% 47.56 14,891.04
0.00 100.00% 8.45 2,547.00
0.00 100.00% 1,839.07 5,701.12
0.00 100.00% 51.11 1,130.55
CAJAMARCA

ACTUAL AVANCE ACUMULADO SALDO


NTE MES MES ACTUAL MES ACTUAL
TOTAL TOTAL TOTAL
% Metrado % Metrado
S/. S/. S/.

0.00 3,875.99
0.00 100.00% 204.43 3,875.99
0.00 4,153.89
0.00 100.00% 1.00 126.39
0.00 100.00% 3.00 4,027.50
0.00 28,853.53
0.00 80.03
0.00 100.00% 52.50 11.03
0.00 100.00% 25.00 69.00
0.00 1,608.56
0.00 100.00% 89.25 375.74
0.00 100.00% 32.24 610.63
0.00 100.00% 71.27 622.19
0.00 27,164.94
0.00 100.00% 52.50 1,161.30
0.00 100.00% 78.63 22,311.26
0.00 100.00% 158.39 3,503.59
0.00 100.00% 9.43 188.79
CAJAMARCA

ACTUAL AVANCE ACUMULADO SALDO


NTE MES MES ACTUAL MES ACTUAL
TOTAL TOTAL TOTAL
% Metrado % Metrado
S/. S/. S/.

- 0.00 58,154.32
- 0.00 160.05
0.00 100.00% 105.00 22.05
0.00 100.00% 50.00 138.00
0.00 3,469.75
0.00 100.00% 178.50 751.49
0.00 100.00% 95.97 1,817.67
0.00 100.00% 103.16 900.59
0.00 54,524.52
0.00 100.00% 105.00 2,322.60
0.00 100.00% 157.25 44,619.69
0.00 100.00% 320.54 7,090.34
0.00 100.00% 24.57 491.89
1,618.33 1,618.33 -
18.58 100.00% 0.02 18.58 0.00% 0.00 0.00
58.75 100.00% 6.73 58.75 0.00% 0.00 0.00
38.59 100.00% 28.80 38.59 0.00% 0.00 0.00
909.36 100.00% 3.04 909.36 0.00% 0.00 0.00
CAJAMARCA

ACTUAL AVANCE ACUMULADO SALDO


NTE MES MES ACTUAL MES ACTUAL
TOTAL TOTAL TOTAL
% Metrado % Metrado
S/. S/. S/.

506.02 100.00% 25.20 506.02 0.00% 0.00 0.00


87.03 100.00% 9.45 87.03 0.00% 0.00 0.00
28.48 28.48 618.11
28.48 4.40% 25.20 28.48 95.60% 547.00 618.11
33,977.94 143,406.12 98,385.13
0.00 93,125.86
0.00 2,225.92
0.00 100.00% 398.20 1,134.87
0.00 100.00% 151.65 638.45
0.00 100.00% 337.76 452.60
0.00 51,172.82
0.00 100.00% 159.61 45,289.34
0.00 100.00% 265.98 5,883.48
0.00 38,900.08
0.00 100.00% 91.49 28,645.52
0.00 100.00% 3,038.20 9,418.42
0.00 100.00% 37.80 836.14
CAJAMARCA

ACTUAL AVANCE ACUMULADO SALDO


NTE MES MES ACTUAL MES ACTUAL
TOTAL TOTAL TOTAL
% Metrado % Metrado
S/. S/. S/.

0.00 827.04
0.00 100.00% 43.62 827.04
0.00 5,259.27
0.00 19.12
0.00 100.00% 6.25 1.31
0.00 100.00% 6.25 17.81
0.00 112.33
0.00 100.00% 7.17 104.32
0.00 100.00% 5.98 8.01
0.00 1,893.63
0.00 100.00% 5.98 132.28
0.00 100.00% 3.89 1,153.27
0.00 100.00% 27.49 608.08
0.00 359.19
0.00 100.00% 0.50 158.50
0.00 100.00% 42.19 130.79
0.00 100.00% 3.16 69.90
0.00 2,875.00
CAJAMARCA

ACTUAL AVANCE ACUMULADO SALDO


NTE MES MES ACTUAL MES ACTUAL
TOTAL TOTAL TOTAL
% Metrado % Metrado
S/. S/. S/.

0.00 100.00% 2.00 2,685.00


0.00 100.00% 1.00 190.00
8,172.63 8,818.76 -
- 159.64 -
100.00% 52.17 10.96 0.00% 0.00 0.00
100.00% 52.17 148.68 0.00% 0.00 0.00
486.49 -
100.00% 20.87 303.66 0.00% 0.00 0.00
100.00% 136.44 182.83 0.00% 0.00 0.00
7,612.63 7,612.63 -
84.94 4.52% 3.84 84.94 95.48% 0.00 0.00
4,571.57 0.34% 15.42 4,571.57 99.66% 0.00 0.00
2,956.12 4.52% 133.64 2,956.12 95.48% 0.00 0.00
560.00 560.00
560.00 0.18% 1.00 560.00 99.82% 0.00 0.00
6,472.44 14,683.16 -
- 83.57 -
100.00% 27.31 5.74 0.00% 0.00 0.00
CAJAMARCA

ACTUAL AVANCE ACUMULADO SALDO


NTE MES MES ACTUAL MES ACTUAL
TOTAL TOTAL TOTAL
% Metrado % Metrado
S/. S/. S/.

100.00% 27.31 77.83 0.00% 0.00 0.00


866.80 -
100.00% 33.20 483.06 0.00% 0.00 0.00
100.00% 16.00 21.44 0.00% 0.00 0.00
100.00% 41.50 362.30 0.00% 0.00 0.00
3,023.07 -
100.00% 8.00 176.96 0.00% 0.00 0.00
100.00% 9.60 2,846.11 0.00% 0.00 0.00
796.47 5,033.75 -
716.40 100.00% 9.76 3,093.83 0.00% 0.00 0.00
100.00% 428.70 1,328.97 0.00% 0.00 0.00
80.07 100.00% 27.62 610.95 0.00% 0.00 0.00
600.46 600.46 -
600.46 100.00% 27.62 600.46 0.00% 0.00 0.00
99.43 99.43 -
99.43 100.00% 27.62 99.43 0.00% 0.00 0.00
4,976.07 4,976.07 -
2,194.09 100.00% 27.31 2,194.09 0.00% 0.00 0.00
CAJAMARCA

ACTUAL AVANCE ACUMULADO SALDO


NTE MES MES ACTUAL MES ACTUAL
TOTAL TOTAL TOTAL
% Metrado % Metrado
S/. S/. S/.

1,225.11 100.00% 28.30 1,225.11 0.00% 0.00 0.00


1,556.88 100.00% 1.00 1,556.88 0.00% 0.00 0.00
5,685.49 6,974.82 -
- 204.33 -
100.00% 9.60 139.68 0.00% 0.00 0.00
100.00% 16.00 21.44 0.00% 0.00 0.00
100.00% 4.95 43.21 0.00% 0.00 0.00
353.92 353.92 -
353.92 100.00% 16.00 353.92 0.00% 0.00 0.00
5,331.57 6,416.57 -
3,537.61 100.00% 11.16 3,537.61 0.00% 0.00 0.00
615.41 100.00% 548.52 1,700.41 0.00% 0.00 0.00
1,178.55 100.00% 53.28 1,178.55 0.00% 0.00 0.00
430.78 601.22 -
- 15.44 -
100.00% 0.48 6.98 0.00% 0.00 0.00
100.00% 2.40 3.22 0.00% 0.00 0.00
100.00% 0.60 5.24 0.00% 0.00 0.00
CAJAMARCA

ACTUAL AVANCE ACUMULADO SALDO


NTE MES MES ACTUAL MES ACTUAL
TOTAL TOTAL TOTAL
% Metrado % Metrado
S/. S/. S/.

53.09 53.09 -
53.09 100.00% 2.40 53.09 0.00% 0.00 0.00
377.69 532.69 -
177.51 100.00% 0.56 177.51 0.00% 0.00 0.00
32.95 100.00% 60.63 187.95 0.00% 0.00 0.00
167.23 100.00% 7.56 167.23 0.00% 0.00 0.00
2,548.28 3,332.55 -
- 164.27 -
100.00% 6.01 87.45 0.00% 0.00 0.00
100.00% 8.40 11.26 0.00% 0.00 0.00
100.00% 7.51 65.56 0.00% 0.00 0.00
185.81 0.00 185.81 -
185.81 100.00% 8.40 185.81 0.00% 0.00 0.00
2,362.47 2,982.47 -
1,334.53 4.21 1,334.53 100.00% 0.00 0.00
556.79 100.00% 379.61 1,176.79 0.00% 0.00 0.00
471.16 100.00% 21.30 471.16 0.00% 0.00 0.00
198.60 265.98 -
CAJAMARCA

ACTUAL AVANCE ACUMULADO SALDO


NTE MES MES ACTUAL MES ACTUAL
TOTAL TOTAL TOTAL
% Metrado % Metrado
S/. S/. S/.

- 11.58 -
100.00% 0.36 5.24 0.00% 0.00 0.00
100.00% 1.80 2.41 0.00% 0.00 0.00
100.00% 0.45 3.93 0.00% 0.00 0.00
198.60 254.40 -
114.12 100.00% 0.36 114.12 0.00% 0.00 0.00
17.24 100.00% 23.56 73.04 0.00% 0.00 0.00
67.24 100.00% 3.04 67.24 0.00% 0.00 0.00
9,477.28 83,401.49 -
- 2,104.19 -
100.00% 2,277.60 478.30 0.00% 0.00 0.00
100.00% 1.75 1,625.89 0.00% 0.00 0.00
9,506.27 -
100.00% 426.49 6,205.43 0.00% 0.00 0.00
100.00% 2,463.31 3,300.84 0.00% 0.00 0.00
5,803.45 68,117.20 -
5,542.21 100.00% 218.74 64,849.85 0.00% 0.00 0.00
261.24 100.00% 147.71 3,267.35 0.00% 0.00 0.00
CAJAMARCA

ACTUAL AVANCE ACUMULADO SALDO


NTE MES MES ACTUAL MES ACTUAL
TOTAL TOTAL TOTAL
% Metrado % Metrado
S/. S/. S/.

3,673.84 3,673.84 -
1,516.68 100.00% 12.00 1,516.68 0.00% 0.00 0.00
2,157.16 100.00% 107.75 2,157.16 0.00% 0.00 0.00
- 22,098.30 -
- 78.45 -
100.00% 45.00 9.45 0.00% 0.00 0.00
100.00% 25.00 69.00 0.00% 0.00 0.00
1,394.49 -
100.00% 67.50 284.18 0.00% 0.00 0.00
100.00% 46.56 881.85 0.00% 0.00 0.00
100.00% 26.17 228.46 0.00% 0.00 0.00
- 20,625.36 -
100.00% 45.00 995.40 0.00% 0.00 0.00
100.00% 58.50 16,599.38 0.00% 0.00 0.00
100.00% 130.49 2,886.44 0.00% 0.00 0.00
100.00% 7.20 144.14 0.00% 0.00 0.00
483.94 483.94 156.48
17.19 17.19 -
CAJAMARCA

ACTUAL AVANCE ACUMULADO SALDO


NTE MES MES ACTUAL MES ACTUAL
TOTAL TOTAL TOTAL
% Metrado % Metrado
S/. S/. S/.

0.63 100.00% 3.00 0.63 0.00% 0.00 0.00


16.56 100.00% 6.00 16.56 0.00% 0.00 0.00
6.35 6.35 -
3.64 100.00% 0.25 3.64 0.00% 0.00 0.00
2.71 100.00% 0.31 2.71 0.00% 0.00 0.00
53.36 53.36 -
53.36 100.00% 0.18 53.36 0.00% 0.00 0.00
407.04 407.04 -
407.04 100.00% 6.00 407.04 0.00% 0.00 0.00
508.50 2,745.90 156.48
508.50 94.61% 2,430.00 2,745.90 5.39% 138.48 156.48
1,436.52 1,436.52 1,436.52
1,436.52 50.00% 0.50 1,436.52 50.00% 0.50 1,436.52
1,364.10 10,912.81 2,728.20
1,364.10 80.00% 0.80 10,912.81 20.00% 0.20 2,728.20

38,725.36 158,707.22 231,450.40


3,098.03 12,696.58 18,516.03
CAJAMARCA

ACTUAL AVANCE ACUMULADO SALDO


NTE MES MES ACTUAL MES ACTUAL
TOTAL TOTAL TOTAL
% Metrado % Metrado
S/. S/. S/.

2,710.77 11,109.51 16,201.53


44,534.16 182,513.30 266,167.95

8,016.15 32,852.39 47,910.23


52,550.31 215,365.69 59.32% 314,078.19
TABLA DE ÍNDICES UNIFICADOS DE PRECIOS

OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
SUPERVISOR ING MILTON CASTAÑEDA CABADA

PPTO. BASE INDICE CONOCIDO DEL MES ANTERIOR AL VALORIZ


Monomio Factor % SÍMBOLO I.U. DESCRIPCIÓN
ago-17 dic-17 ene-18 feb-18
1 0.284 100.000 M 47 MANO DE OBRA INC. LEYES SOCIALES 580.90 580.90
2 0.400 100.000 C 21 CEMENTO PORTLAND TIPO I 465.71 465.71
3 0.157 100.000 A 05 AGREGADO GRUESO 448.18 448.18
4 0.073 100.000 A 03 ACERO DE CONSTRUCCION CORRUGADO 460.39 460.39
5 0.086 100.000 M 49 MAQUINARIA Y EQUIPO IMPORTADO 292.36 292.36
total 1.000
O DE CHOTA, PROVINCIA CHOTA-CAJAMARCA

MES ANTERIOR AL VALORIZADO


mar-18 abr-18
CÁLCULO DEL COEFICIENTE DE REAJUSTE "K"
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAM
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
SUPERVISOR ING MILTON CASTAÑEDA CABADA

ÁREA GEOGRÁFICA 1 - CAJAMARCA


FÓRMULA
POLINÓMICA
K = 0.446 x (Mr/Mo) + 0.096 x (Cr/Co) + 0.076 x (Ar/Ao) + 0.060 x (Mcr/Mco) + 0.186 x (D/Do)+0.067 x (Mr/Mo)+0.069 x (Fr/Fo)
INCIDENCIA PPTO. BASE INDICE CONOCIDO DEL MES ANTERIOR AL VALORIZAD
MONOMIO SÍMBOLO I.U. DESCRIPCIÓN FACTOR
ESPECÍFICA ago-17 dic-17 ene-18
1 M 47 MANO DE OBRA INC. LEYES SOCIALES 0.284 100.000% 580.90 580.90
0.284 x Mr/Mo 0.284 0.284
2 C 21 CEMENTO PORTLAND TIPO I 0.400 100.000% 465.71 465.71
0.400 x Cr/Co 0.400 0.400
3 A 05 AGREGADO GRUESO 0.157 100.000% 448.180 449.820
0.157 x Ar/Ao 0.157 0.158
4 A 03 ACERO DE CONSTRUCCION CORRUGADO 0.073 100.000% 460.390 464.750
0.073 x Ar/Ao 0.073 0.074
5 M 49 MAQUINARIA Y EQUIPO IMPORTADO 0.086 100.000% 292.36 292.27
0.086 x Mr/Mo 0.086 0.086

COEFICIENTE DE REAJUSTE (K) 1.000 1.000 1.002 0.000


TRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA

.069 x (Fr/Fo)
DEL MES ANTERIOR AL VALORIZADO
feb-18 mar-18
CALCULO DEL REAJUSTE PARA LAS VALORIZACIONES TRAMITADAS

: "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA
OBRA:
CHOTA-CAJAMARCA

ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA


UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
SUPERVISOR ING MILTON CASTAÑEDA CABADA

REAJUSTE POR ÍNDICE "K" VALORIZACION Nº 01


COEFICIENTE DE
VALORIZACION BRUTA REAJUSTE REAJUSTE
PERIODO MES DEL INDICE "K" REAJUSTE "K" VARIACION DEL
VALORIZACION Nº (Sin BRUTO RECONOCIDO A FAVOR
VALORIZADO CONOCIDO DEL MES INDICE =(K-1)
I.G.V.) (Sin IGV) DE LA ENTIDAD
CONOCIDO

01 diciembre-17 S/. 137,979.14 Agosto 2017 1.002 0.002 S/. 275.96 S/. 0.00

02 enero-18 S/. 0.00 0 0.000 S/. - S/. 0.00

03 febrero-18 S/. 0.00 0 0.000 S/. - S/. 0.00

04 marzo-18 S/. 0.00 0 0.000 S/. - S/. 0.00

TOTAL REAJUSTE
TADAS

CO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA

REAJUSTE RECONOCIDO A FAVOR


DEL CONTRATISTA (Sin I.G.V)

S/. 275.96

S/. 0.00

S/. 0.00

S/. 0.00

S/. 275.96
RESUMEN DE PAGOS Y CONTROL ECONOMICO DE LAS VALORIZACIONES TRAMITADAS

OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, P
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
SUPERVISOR ING MILTON CASTAÑEDA CABADA

VALORIZACIONES AMORTIZACIONES DEDUCCIONES


Valorizacion
DESCRIPCION Monto Neto de la
Bruta-Principal
Periodo Valorizado Adel. Dir. Adel. Mat. Reajuste Valorizacion (Sin Adel. Dir. Adel. Mat. Adel. Dir.
I.G.V)
(sin I.G.V.)

Adelanto Directo

Adelanto Materiales

valorizacion N° 01 Del 05/12/17 al 31/12/17 S/. -- S/. -- S/. 137,979.14 S/. 0.00 S/. 137,979.14 S/. 0.00 S/. 0.00 S/. -

valorizacion N° 02 Del 01/01/18 al 31/01/18 S/. -- S/. -- S/. 44,534.16 S/. 0.00 S/. 44,534.16 S/. 0.00 S/. 0.00 S/. -

valorizacion N° 03 Del 01/02/18 al 28/02/18 S/. -- S/. -- S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. -
DEDUCCIONES
MONTO
I.G.V
FACTURADO
Adel. Mat. 18%
(Con I.G.V.)

S/. 0.00

S/. 0.00

S/. - S/. 24,836.25 S/. 162,815.39

S/. - S/. 8,016.15 S/. 52,550.31

S/. - S/. 0.00 S/. 0.00

TOTAL S/. 215,365.70


RESUMEN DE PAGOS A CUENTA DE VALORIZACIONES DE LA OBRA PRINCIPAL

OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
SUPERVISOR ING MILTON CASTAÑEDA CABADA

VALORIZACION 01 DEL 08 VALORIZACION 02 DEL VALORIZACION 03 DEL VALORIZACION


DESCRIPCION MONTO CONTRACTUAL
AL 31 DE DICIEMBRE 01 AL 31 DE ENERO 01 AL 02 DE FEBRERO ACUMULADO

I. VALORIZACION BRUTA
Valorizacion de Avance de Obra (A) S/. 448,681.28 S/. 137,979.14 S/. 44,534.16 S/. 182,513.30
II. REAJUSTES (FORMULA POLINOMICA)
Calculo de reajustes K (B)
III. VALORIZACION NETA
Valorizacion Bruta Reajustada ( C ) S/. 448,681.28 S/. 137,979.14 S/. 44,534.16 S/. 182,513.30
Amortizacion del Adelanto Directo (D) S/. -
Amortizacion del Adelanto del Adelanto de Materiales (E) S/. - S/. - S/. -
Deduccion del reajuste por Adelanto Directo (F) S/. - S/. -
Deduccion del reajuste por Adelanto de Materiales (G) S/. - S/. -
VALORIZACION NETA(K=C - D - E - F - G) S/. 448,681.28 S/. 137,979.14 S/. 44,534.16 S/. 182,513.30
IV. RESUMEN GENERAL DE PAGOS
Valorizacion Neta S/. 448,681.28 S/. 137,979.14 S/. 44,534.16 S/. 182,513.30
IGV (18%) S/. 80,762.63 S/. 24,836.25 S/. 8,016.15 S/. 32,852.39
MONTO TOTAL S/. S/. 529,443.91 S/. 162,815.38 S/. 52,550.31 S/. 215,365.69

MONTO A PAGAR AL CONTRATISTA SEGÚN VALORIZACION Nº 02 S/. 52,550.31


1.3434 3.23
TA, PROVINCIA CHOTA-CAJAMARCA

SALDO POR VALORIZAR

S/. 266,167.98

S/. 227,047.46
S/. -
S/. -

S/. 227,047.46

S/. 266,167.98
S/. 47,910.24
S/. 314,078.22
CONTROL DE VALORIZACIONES EJECUTADAS VS. PROGRAMADAS

: "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL
PROYECTO LLASAVILCA BAJO DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA CHOTA-CAJAMARCA

ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA


UBICACIÓN : PINGOBAMBA -BEDOYA, LLASAVILCA BAJO-CHOTA -CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
INSPECTOR ING MILTON CASTAÑEDA CABADA
MONTO DEL CONTRATO S/. 529,443.91 Inc/IGV
MONTO DEL CONTRATO S/. 448,681.28 Sin/IGV

PROGRAMADO EJECUTADO
% EJEC./
MES VAL N° AVANCE AVANCE PORCENTAJE AVANCE AVANCE PORCENTAJE PROG.
MENSUAL ACUMULADO ACUMULADO MENSUAL ACUMULADO ACUMULADO

Dec-17 Nº 01 345094.20904 345094.20904 65.1805% 162,815.39 162,815.39 36.29% 47.18%


Jan-18 Nº 02 182797.10046 527891.3095 99.7067% 52,550.31 215,365.70 48.00% 9.95%
Feb-18 Nº 03 1552.61512 529443.92462 100.0000%

529,443.92 215,365.70
CONTROL DE AVANCE DE OBRA
CURVA S
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C.P.
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
AVA N C E Q U IN C E N A L A C U M U LA D O (% )

RESIDENTE : ING. JAIME LIVAQUE CORONADO


SUPERVISOR ING MILTON CASTAÑEDA CABADA

PORCENTAJES DE AVANCE PROGRAMADO Vs. EJECUTADO ACUMULADO

600,000
527,891.3 529,44
C olum n J C olum n D 1 2
500,000
1
345,094.2
400,000
1
300,000

200,000
ENERO
100,000 DIC
5-Dec-17
0 0.00
5-Dec-17 DIC ENERO FEBRER

PLAZO DE EJECUCION MENSUAL


5-Dec-17
0 0.00
5-Dec-17 DIC ENERO FEBRER

PLAZO DE EJECUCION MENSUAL

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS


MONTOS (S/ IGV) PORCENTAJES MONTOS (S/ IGV) PORCENTAJES

MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
5-Dec-17 - 0.00 0.00 0.00 5-Dec-17 0.00 0.00 0.00 0.00
DIC 345,094.21 345,094.21 65.18% 65.18% DIC 162,815.39 162,815.39 30.75% 30.75%
ENERO 182,797.10 527,891.31 34.53% 99.71% ENERO 52,550.31 215,365.70 9.93% 40.68%
FEBRERO 1,552.62 529,443.92 0.29% 100.00% FEBRERO
TOTAL 529,443.92 100.00% TOTAL 215,365.70 40.68%
E PROGRAMADO Vs. EJECUTADO ACUMULADO
527,891.3 529,443.9
C olum n J C olum n D 1 2

4.2

ENERO

ENERO FEBRERO

LAZO DE EJECUCION MENSUAL


ENERO FEBRERO

LAZO DE EJECUCION MENSUAL


CONTROL DE AVANCE DE OBRA
CURVA S
OBRA: : "MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE PINGOBAMBA -BEDOYA Y SANTA ISABEL LLASAVILCA BAJO DEL C
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CHOTA
UBICACIÓN : CHOTA - CHOTA - CAJAMARCA
CONTRATISTA : "CONSORCIO BEDOYA"
AVA N C E Q U IN C E N A L A C U M U LA D O (% )

RESIDENTE : ING. JAIME LIVAQUE CORONADO


SUPERVISOR ING MILTON CASTAÑEDA CABADA

PORCENTAJES DE AVANCE PROGRAMADO Vs. EJECUTADO ACUMULADO

110%
C olum n L
99.71% 100.
100% AVAN C E PROGR AM ADO

90%

80%

70% 65.18%
60%

50%
ENERO
40%
DIC
30%

20%

10%

0% 0.00%

5-Dec-17
5-Dec-17 DIC ENERO FEBR

PLAZO DE EJECUCION MENSUAL


0% 0.00%

5-Dec-17
5-Dec-17 DIC ENERO FEBR

PLAZO DE EJECUCION MENSUAL

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS


MONTOS (S/ IGV) PORCENTAJES MONTOS (S/ IGV) PORCENTAJES

MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
5-Dec-17 - 0.00 0.00 0.00 5-Dec-17 0.00 0.00 0.00 0.00
DIC 345,094.21 345,094.21 65.18% 65.18% DIC 162,815.39 162,815.39 30.75% 30.75%
ENERO 182,797.10 527,891.31 34.53% 99.71% ENERO 52,550.31 215,365.70 9.93% 40.68%
FEBRERO 1,552.62 529,443.92 0.29% 100.00% FEBRERO
TOTAL 529,443.92 100.00% TOTAL 215,365.70 40.68%
NCE PROGRAMADO Vs. EJECUTADO ACUMULADO

C olum n L
99.71% 100.00%
AVAN C E PROGR AM ADO

8%

ENERO
C

ENERO FEBRERO

PLAZO DE EJECUCION MENSUAL


ENERO FEBRERO

PLAZO DE EJECUCION MENSUAL


CONTROL DE AVANCE DE OBRA
CURVA S

OBRA: : "INSTALACION DEL SERVICIO DE AGUA DEL SISTEMA DE RIEGO TRES CRUCES EN LA COMUNIDAD DE CAPULI DEL CP. SAN JUAN DE LACAMACA, DIS
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE HUALGAYOC - BAMBAMARCA
UBICACIÓN : C.P. SAN JUAN DE LACAMACA - BAMBAMARCA - HUALGAYOC - CAJAMARCA
CONTRATISTA : "CONSORCIO CAPULI"
RESIDENTE : ING. JAIME LIVAQUE CORONADO
AVA NC E MEN SU A L A C U MU LA D O (% )

SUPERVISOR : ING. MANUEL CHAVEZ MEJIA

PORCENTAJES DE AVANCE PROGRAMADO Vs. EJECUTADO ACUMULADO

S/. 600,000.00
0 78317.86 257553.04 468066.76 565880.77
S/. 565,880.77
AVAN C E PROGRAM ADO

S/. 500,000.00

S/.
S/. 400,000.00
468,066.7
6
S/. 300,000.00

S/. 257,553.04
S/. 200,000.00

S/. 100,000.00
S/. 78,317.86

S/. 0.00
S/. 0.00

PLAZO DE EJECUCION MENSUAL

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZAD


MONTOS (S/ IGV) PORCENTAJES

MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES


S/. S/. % %
5-Dec-17 - 0.00 0.00 0.00 5-Dec-17
DIC 345,094.21 345,094.21 65.18% 65.18% DIC
ENERO 182,797.10 527,891.31 34.53% 99.71% ENERO
FEBRERO 1,552.62 529,443.92 0.29% 100.00% FEBRERO
TOTAL 529,443.92 100.00% TOTAL
BRA

PULI DEL CP. SAN JUAN DE LACAMACA, DISTRITO DE BAMBAMARCA, PROVINCIA DE HUALGAYOC-CAJAMARCA"

CUTADO ACUMULADO

1
76 565880.77

0.8

0.6

0.4

43004;
0.2
S/.
0.00
0

MONTOS VALORIZADOS EJECUTADOS


MONTOS (S/ IGV) PORCENTAJES

PARCIAL ACUMUL. PARCIAL ACUMUL.


S/. S/. % %

162,815.39 162,815.39 30.75% 30.75%


52,550.31 215,365.70 9.93% 40.68%
215,365.70 40.68%
MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE - PINGOBAMBA - BEDOYA Y SANTA ISABEL LLASAVILCA BAJO, DEL C.P. TURISTICO EL CAMPAM
PROYECTO:
CHOTA - CAJAMARCA

Cliente: MUNICIPALIDAD PROVINCIAL DE CHOTA


Lugar: CAJAMARCA - CHOTA - CHOTA

CRONOGRAMA DE AVANCE FISICO VALORIZADO DE OBRA

P. Unit. Parcial Mes 1 (del 05al 31/12/17)


Item Descripción Und Metrado
S/. S/. Parcial
01 CANAL DE RIEGO SAN JOSE (PINGOBAMBA - BEDOYA) 131,695.85 73,989.09

01.01 OBRAS PROVISIONALES 1,304.97 1,304.97

01.01.01 CARTEL DE OBRA DE 3.60 X 2.40 m u 1.00 704.97 704.97 704.97

01.01.02 CAMPAMENTO PROVISIONAL DE LA OBRA mes 2.00 300.00 600.00 600.00

01.02 CONSTRUCCION DE BOCATOMA 01 41,118.11 41,118.11

01.02.01 OBRAS PRELIMINARES 2,955.41 2,955.41

01.02.01.01 TRAZO Y REPLANTEO m2 230.70 2.85 657.50 657.50

01.02.01.02 EXCAVACION EN SUELO GRAVOSO BAJO AGUA m3 70.12 4.21 295.21 295.21

01.02.01.03 REFINE, NIVELACION Y COMPACTACION DE FUNDACIONES m2 207.50 1.34 278.05 278.05

01.02.01.04 DEMOLICION DE COLCHON DISIPADOR E=0.15M m3 8.45 204.10 1,724.65 1,724.65

01.02.02 OBRAS DE CONCRETO SIMPLE 5,863.11 5,863.11

01.02.02.01 CONCRETO f'c=175 kg/cm2 + 25% PM EN BASE DE ENCAUZAMIENTO m3 19.34 283.75 5,487.73 5,487.73

01.02.02.02 ENCOFRADO Y DESENCOFRADO m2 16.97 22.12 375.38 375.38

01.02.03 OBRAS DE CONCRETO ARMADO 24,269.71 24,269.71

01.02.03.01 CONCRETO f'c=210 kg/cm2 EN BARRAJE m3 47.56 313.10 14,891.04 14,891.04

01.02.03.02 REPOSICION DE CONCRETO f'c=210 kg/cm2 EN COLCHON DISIPADOR m3 8.45 301.42 2,547.00 2,547.00
01.02.03.03 ACERO fy=4200 kg/cm2 GRADO 60 kg 1,839.07 3.10 5,701.12 5,701.12

01.02.03.04 ENCOFRADO Y DESENCOFRADO m2 51.11 22.12 1,130.55 1,130.55

01.02.04 CONSTRUCCION DE ESCOLLERA - RIP RAP 3,875.99 3,875.99

01.02.04.01 PIEDRA GRANDE PARA ENROCADOS DE ESCOLLERA O RIP RAP m3 204.43 18.96 3,875.99 3,875.99

01.02.05 VARIOS 4,153.89 4,153.89

01.02.05.01 COMPUERTA METALICA TIPO TARJETA 1/8" DE 0.35 X 0.325 m u 1.00 126.39 126.39 126.39

01.02.05.02 COMPUERTA METALICA 1/4" DE 0.80 X 1.75 m u 3.00 1,342.50 4,027.50 4,027.50

01.03 CONSTRUCCION DE MURO PARA ENCAUZAMIENTO EN BOCATOMA L= 25 M 28,853.53 28,853.53

01.03.01 OBRAS PRELIMINARES 80.03 80.03

01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 52.50 0.21 11.03 11.03

01.03.01.02 TRAZO Y REPLANTEO m 25.00 2.76 69.00 69.00

01.03.02 MOVIMIENTO DE TIERRAS 1,608.56 1,608.56

01.03.02.01 EXCAVACION EN SUELO GRAVOSO BAJO AGUA m3 89.25 4.21 375.74 375.74

01.03.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 32.24 18.94 610.63 610.63

01.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 71.27 8.73 622.19 622.19

01.03.03 CONCRETO SIMPLE 27,164.94 27,164.94

01.03.03.01 SOLADO C:H=1:12, E=0.10M m2 52.50 22.12 1,161.30 1,161.30

01.03.03.02 CONCRETO f'c=175 kg/cm2 + 25% PM m3 78.63 283.75 22,311.26 22,311.26

01.03.03.03 ENCOFRADO Y DESENCOFRADO m2 158.39 22.12 3,503.59 3,503.59

01.03.03.04 JUNTAS ASFALTICAS m2 9.43 20.02 188.79 188.79

01.04 CONSTRUCCION DE MURO PARA ENCAUZAMIENTO L= 50 M 58,154.32 535.50

01.04.01 OBRAS PRELIMINARES 160.05 160.05

01.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 105.00 0.21 22.05 22.05

01.04.01.02 TRAZO Y REPLANTEO m 50.00 2.76 138.00 138.00


01.04.02 MOVIMIENTO DE TIERRAS 3,469.75 375.45

01.04.02.01 EXCAVACION EN SUELO GRAVOSO BAJO AGUA m3 178.50 4.21 751.49 150.30

01.04.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 95.97 18.94 1,817.67

01.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 103.16 8.73 900.59 225.15

01.04.03 CONCRETO SIMPLE 54,524.52

01.04.03.01 SOLADO C:H=1:12, E=0.10 M m2 105.00 22.12 2,322.60

01.04.03.02 CONCRETO f'c=175 kg/cm2 + 25% PM m3 157.25 283.75 44,619.69

01.04.03.03 ENCOFRADO Y DESENCOFRADO m2 320.54 22.12 7,090.34

01.04.03.04 JUNTAS ASFALTICAS m2 24.57 20.02 491.89

01.05 REPOSICION DE CANAL DE CONCRETO L=18 M 1,618.33 1,618.33

01.05.01 TRAZO Y REPLANTEO km 0.02 929.08 18.58 18.58

01.05.02 CORTE EN MATERIAL SUELTO MANUAL m3 6.73 8.73 58.75 58.75

01.05.03 REFINE, NIVELACION Y COMPACTACION CAJA DE CANAL m2 28.80 1.34 38.59 38.59

01.05.04 CONCRETO f'c=175 kg/cm2 EN CANAL m3 3.04 299.13 909.36 909.36

01.05.05 ENCOFRADO Y DESENCOFRADO DE CANAL m2 25.20 20.08 506.02 506.02

01.05.06 JUNTAS ASFALTICAS m 9.45 9.21 87.03 87.03

01.06 CURADO DEL CONCRETO 646.59 558.65

01.06.01 CURADO DEL CONCRETO CON ADITIVO m2 572.20 1.13 646.59 558.65

02 CANAL DE RIEGO SANTA ISABEL (LLASAVILCA BAJO) 241,947.74 166,676.61

02.01 CONSTRUCCION DE BOCATOMA 02 93,125.86 91,564.93

02.01.01 OBRAS PRELIMINARES 2,225.92 2,225.92

02.01.01.01 TRAZO Y REPLANTEO m2 398.20 2.85 1,134.87 1,134.87

02.01.01.02 EXCAVACION EN SUELO GRAVOSO BAJO AGUA m3 151.65 4.21 638.45 638.45

02.01.01.03 REFINE, NIVELACION Y COMPACTACION DE FUNDACIONES m2 337.76 1.34 452.60 452.60


02.01.02 OBRAS DE CONCRETO SIMPLE 51,172.82 51,172.82

02.01.02.01 CONCRETO f'c=175 kg/cm2 + 25% PM EN MUROS DE ENCAUZAMIENTO m3 159.61 283.75 45,289.34 45,289.34

02.01.02.02 ENCOFRADO Y DESENCOFRADO m2 265.98 22.12 5,883.48 5,883.48

02.01.03 OBRAS DE CONCRETO ARMADO 38,900.08 38,166.19

02.01.03.01 CONCRETO f'c=210 kg/cm2 EN BARAJE Y COLCHON DISIPADOR m3 91.49 313.10 28,645.52 27,977.42

02.01.03.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 3,038.20 3.10 9,418.42 9,418.42

02.01.03.03 ENCOFRADO Y DESENCOFRADO m2 37.80 22.12 836.14 770.35

02.01.04 CONSTRUCCION DE ESCOLLERA - RIP RAP 827.04

02.01.04.01 PIEDRA GRANDE PARA ENROCADOS DE ESCOLLERA O RIP RAP m3 43.62 18.96 827.04

02.02 CONSTRUCCION DE CAJA DE CONTROL EN BOCATOMA 5,259.27

02.02.01 OBRAS PRELIMINARES 19.12

02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.25 0.21 1.31

02.02.01.02 TRAZO Y REPLANTEO m2 6.25 2.85 17.81

02.02.02 MOVIMIENTO DE TIERRAS 112.33

02.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 7.17 14.55 104.32

02.02.02.02 REFINE, NIVELACION Y COMPACTACION m2 5.98 1.34 8.01

02.02.03 CONCRETO SIMPLE 1,893.63

02.02.03.01 SOLADO C:H=1:12, E=0.10 M m2 5.98 22.12 132.28

02.02.03.02 CONCRETO f 'c= 175 kg/cm2 m3 3.89 296.47 1,153.27

02.02.03.03 ENCOFRADO Y DESENCOFRADO m2 27.49 22.12 608.08

02.02.04 CONCRETO ARMADO 359.19

02.02.04.01 CONCRETO f'c=210 kg/cm2 m3 0.50 316.99 158.50

02.02.04.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 42.19 3.10 130.79

02.02.04.03 ENCOFRADO Y DESENCOFRADO m2 3.16 22.12 69.90


02.02.05 VARIOS 2,875.00

02.02.05.01 COMPUERTA METALICA 1/4" DE 0.80 X 1.75 m u 2.00 1,342.50 2,685.00

02.02.05.02 REJILLA METALICA 1/2" u 1.00 190.00 190.00

02.03 DESARENADOR INC. CANAL DE CONCRETO L=72 M 8,818.76

02.03.01 OBRAS PRELIMINARES 159.64

02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 52.17 0.21 10.96

02.03.01.02 TRAZO Y REPLANTEO m2 52.17 2.85 148.68

02.03.02 MOVIMIENTO DE TIERRAS 486.49

02.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 20.87 14.55 303.66

02.03.02.02 REFINE, NIVELACION Y COMPACTACION m2 136.44 1.34 182.83

02.03.03 CONCRETO SIMPLE 7,612.63

02.03.03.01 SOLADO C:H=1:12, E=0.10 M m2 3.84 22.12 84.94

02.03.03.02 CONCRETO f 'c= 175 kg/cm2 m3 15.42 296.47 4,571.57

02.03.03.03 ENCOFRADO Y DESENCOFRADO m2 133.64 22.12 2,956.12

02.03.04 VARIOS 560.00

02.03.04.01 COMPUERTA PLANCHA METALICA 1/4" DE 0.40 X 1.00 M u 1.00 560.00 560.00

02.04 CONSTRUCCION DE PASE AEREO PARA TUBERIA L=20M 14,683.15

02.04.01 OBRAS PRELIMINARES 83.57

02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 27.31 0.21 5.74

02.04.01.02 TRAZO Y REPLANTEO m2 27.31 2.85 77.83

02.04.02 MOVIMIENTO DE TIERRAS 866.80

02.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 33.20 14.55 483.06

02.04.02.02 REFINE, NIVELACION Y COMPACTACION m2 16.00 1.34 21.44

02.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 41.50 8.73 362.30


02.04.03 CONCRETO SIMPLE 3,023.07

02.04.03.01 SOLADO C:H=1:12, E=0.10 M m2 8.00 22.12 176.96

02.04.03.02 CONCRETO f 'c= 175 kg/cm2 EN DADOS DE ANCLAJE m3 9.60 296.47 2,846.11

02.04.04 CONCRETO ARMADO 5,033.74

02.04.04.01 CONCRETO f'c=210 kg/cm2 EN TORRE m3 9.76 316.99 3,093.82

02.04.04.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 428.70 3.10 1,328.97

02.04.04.03 ENCOFRADO Y DESENCOFRADO m2 27.62 22.12 610.95

02.04.05 REVOQUES 600.46

02.04.05.01 TARRAJEO EN EXTERIORES m2 27.62 21.74 600.46

02.04.06 PINTURA 99.43

02.04.06.01 PINTURA ESMALTE EN EXTERIORES m2 27.62 3.60 99.43

02.04.07 VARIOS 4,976.08

02.04.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC UF NTP ISO 4435 D=12" (3 m 27.31 80.34 2,194.09

02.04.07.02 SUMINISTRO E INSTALACION DE CABLE DE ACERO Ø 5/8" m 28.30 43.29 1,225.11

02.04.07.03 SUMINISTRO E INSTALACION DE ABRAZADERAS Y PENDOLAS u 1.00 1,556.88 1,556.88

02.05 PASE CANOA TIPO 01 6,974.82

02.05.01 MOVIMIENTO DE TIERRAS 204.33

02.05.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 9.60 14.55 139.68

02.05.01.02 REFINE, NIVELACION Y COMPACTACION m2 16.00 1.34 21.44

02.05.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 4.95 8.73 43.21

02.05.02 CONCRETO SIMPLE 353.92

02.05.02.01 SOLADO C:H=1:12, E=0.10 M m2 16.00 22.12 353.92

02.05.03 CONCRETO ARMADO 6,416.57

02.05.03.01 CONCRETO f'c=210 kg/cm2 m3 11.16 316.99 3,537.61


02.05.03.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 548.52 3.10 1,700.41

02.05.03.03 ENCOFRADO Y DESENCOFRADO m2 53.28 22.12 1,178.55

02.06 PASE CANOA TIPO 02 601.22

02.06.01 MOVIMIENTO DE TIERRAS 15.44

02.06.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 0.48 14.55 6.98

02.06.01.02 REFINE, NIVELACION Y COMPACTACION m2 2.40 1.34 3.22

02.06.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 0.60 8.73 5.24

02.06.02 CONCRETO SIMPLE 53.09

02.06.02.01 SOLADO C:H=1:12, E=0.10 M m2 2.40 22.12 53.09

02.06.03 CONCRETO ARMADO 532.69

02.06.03.01 CONCRETO f'c=210 kg/cm2 m3 0.56 316.99 177.51

02.06.03.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 60.63 3.10 187.95

02.06.03.03 ENCOFRADO Y DESENCOFRADO m2 7.56 22.12 167.23

02.07 ALCANTARILLAS (02 UNIDADES), L= 6.00 M. C/U 3,332.56

02.07.01 MOVIMIENTO DE TIERRAS 164.27

02.07.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 6.01 14.55 87.45

02.07.01.02 REFINE, NIVELACION Y COMPACTACION m2 8.40 1.34 11.26

02.07.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 7.51 8.73 65.56

02.07.02 CONCRETO SIMPLE 185.81

02.07.02.01 SOLADO C:H=1:12, E=0.10 M m2 8.40 22.12 185.81

02.07.03 CONCRETO ARMADO 2,982.48

02.07.03.01 CONCRETO f'c=210 kg/cm2 m3 4.21 316.99 1,334.53

02.07.03.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 379.61 3.10 1,176.79

02.07.03.03 ENCOFRADO Y DESENCOFRADO m2 21.30 22.12 471.16


02.08 PASE PEATONAL 265.98

02.08.01 MOVIMIENTO DE TIERRAS 11.58

02.08.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 0.36 14.55 5.24

02.08.01.02 REFINE, NIVELACION Y COMPACTACION m2 1.80 1.34 2.41

02.08.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 0.45 8.73 3.93

02.08.02 CONCRETO ARMADO 254.40

02.08.02.01 CONCRETO f'c=210 kg/cm2 m3 0.36 316.99 114.12

02.08.02.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 23.56 3.10 73.04

02.08.02.03 ENCOFRADO Y DESENCOFRADO m2 3.04 22.12 67.24

02.09 CONSTRUCCION DE CANAL DE CONCRETO L=1.75 KM 83,401.50 72,572.71

02.09.01 OBRAS PRELIMINARES 2,104.19 2,104.19

02.09.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,277.60 0.21 478.30 478.30

02.09.01.02 TRAZO Y REPLANTEO km 1.75 929.08 1,625.89 1,625.89

02.09.02 MOVIMIENTO DE TIERRAS 9,506.27 9,506.27

02.09.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 426.49 14.55 6,205.43 6,205.43

02.09.02.02 REFINE, NIVELACION Y COMPACTACION m2 2,463.31 1.34 3,300.84 3,300.84

02.09.03 CONCRETO SIMPLE 68,117.20 58,805.09

02.09.03.01 CONCRETO f 'c= 175 kg/cm2 m3 218.74 296.47 64,849.85 56,687.08

02.09.03.02 ENCOFRADO Y DESENCOFRADO m2 147.71 22.12 3,267.35 2,118.01

02.09.04 VARIOS 3,673.84 2,157.16

02.09.04.01 COMPUERTA METALICA TIPO TARJETA 1/8" DE 0.35 X 0.325 m u 12.00 126.39 1,516.68

02.09.04.02 JUNTAS ASFALTICAS m2 107.75 20.02 2,157.16 2,157.16

02.10 CONSTRUCCION DE MURO PARA PROTECCION DE PUENTE PEATONAL L=25 M 22,098.30

02.10.01 OBRAS PRELIMINARES 78.45


02.10.01.01 LIMPIEZA DE TERRENO MANUAL m2 45.00 0.21 9.45

02.10.01.02 TRAZO Y REPLANTEO m 25.00 2.76 69.00

02.10.02 MOVIMIENTO DE TIERRAS 1,394.49

02.10.02.01 EXCAVACION EN SUELO GRAVOSO BAJO AGUA m3 67.50 4.21 284.18

02.10.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 46.56 18.94 881.85

02.10.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 26.17 8.73 228.46

02.10.03 CONCRETO SIMPLE 20,625.36

02.10.03.01 SOLADO C:H=1:12, E=0.10 M m2 45.00 22.12 995.40

02.10.03.02 CONCRETO f'c=175 kg/cm2 + 25% PM m3 58.50 283.75 16,599.38

02.10.03.03 ENCOFRADO Y DESENCOFRADO m2 130.49 22.12 2,886.44

02.10.03.04 JUNTAS ASFALTICAS m2 7.20 20.02 144.14

02.11 PASE CON TUBERIA 483.94

02.11.01 OBRAS PRELIMINARES 17.19

02.11.01.01 LIMPIEZA DE TERRENO MANUAL m2 3.00 0.21 0.63

02.11.01.02 TRAZO Y REPLANTEO m 6.00 2.76 16.56

02.11.02 MOVIMIENTO DE TIERRAS 6.35

02.11.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 0.25 14.55 3.64

02.11.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.31 8.73 2.71

02.11.03 CONCRETO SIMPLE 53.36

02.11.03.01 CONCRETO f 'c=175 kg/cm2 EN DADOS m3 0.18 296.47 53.36

02.11.04 TUBERIA 407.04

02.11.04.01 SUMINISTRO E INSTALACION DE TUBERIA PVC UF NTP ISO 4435 D=12" (3 m 6.00 67.84 407.04

02.12 CURADO DEL CONCRETO 2,902.38 2,538.97

02.12.01 CURADO DEL CONCRETO CON ADITIVO m2 2,568.48 1.13 2,902.38 2,538.97
03 MITIGACION DE IMPACTO AMBIENTAL 2,873.03

03.01 ACCIONES DE MITIGACION AMBIENTAL glb 1.00 2,873.03 2,873.03

04 FLETE 13,641.02 13,641.02

04.01 FLETE TERRESTRE A PIE DE OBRA glb 1.00 13,641.02 13,641.02 13,641.02

Costo Directo S/. 390,157.64 254,306.72


Gastos Generales 8.00% S/. 31,212.61 20,344.54
Utilidad 7.00% S/. 27,311.03 17,801.47
Sub-Total S/. 448,681.29 292,452.73
Impuesto General a las Ventas 18.00% S/. 80,762.63 52,641.49
Total Final S/. 529,443.92 345,094.21

390,157.64
AJO, DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA, PROVINCIA DE

12/5/2017

DE OBRA

Mes 1 (del 05al 31/12/17) Mes 2 (del 01 al 31/01/18) Mes 3 (del 01al 02/02/18)
% Parcial % Parcial %
56% 57,398.66 44% 308.1 0%

100%

100%

100%

100%

100%
100%

100%

100%

100%

100%

100%

1% 57,310.72 99% 308.1 1%

100%
11% 3,094.30 89%

601.19

1,817.67

675.44

54,216.42 99% 308.1 1%

2,322.60

44,619.69

7,090.34

183.79 308.1

100%

86% 87.94 14%

87.94

74,435.08 31% 836.06 0%

98% 1,560.93 2%

100%
100%

98% 733.89 2%

668.1

65.79

0% 827.04 100%

827.04

0% 5,259.27 100%

0% 19.12

1.31

17.81

0% 112.33 100%

104.32

8.01

0% 1,893.63 100%

132.28

1,153.27

608.08

0% 359.19 100%

158.5

130.79

69.9
0% 2,875.00 100%

2,685.00

190

0% 8,818.76 100%

0% 159.64

10.96

148.68

0% 486.49 100%

303.66

182.83

0% 7,612.63 100%

84.94

4,571.57

2,956.12

0% 560 100%

560

0% 14,513.32 99% 169.83 1%

0% 83.57 100%

5.74

77.83

0% 866.8 100%

483.06

21.44

362.3
0% 3,023.07 100%

176.96

2,846.11

0% 5,033.74 100%

3,093.82

1,328.97

610.95

0% 600.46 100%

600.46

0% 99.43 100%

99.43

0% 4,905.68 99% 70.4 1%

2,123.69 70.4

1,225.11

1,556.88

0% 6,974.82 100%

0% 204.33

139.68

21.44

43.21

0% 353.92

353.92

0% 6,416.57

3,537.61
1,700.41

1,178.55

0% 601.22 100%

0% 15.44

6.98

3.22

5.24

0% 53.09

53.09

0% 532.69

177.51

187.95

167.23

0% 3,332.56 100%

0% 164.27

87.45

11.26

65.56

0% 185.81

185.81

0% 2,982.48

1,334.53

1,176.79

471.16
0% 109.54 41% 156.44 59%

0% 11.58

5.24

2.41

3.93

0% 97.96 39% 156.44 61%

114.12

73.04

24.92 42.32

87% 10,828.79 13%

100%

100%

86% 9,312.11 14%

8,162.77

1,149.34

59% 1,516.68 41%

1,516.68

0% 21,657.38 98% 440.93 2%

0% 78.45
9.45

69

0% 953.57 68% 440.93 32%

284.18

440.93 440.93

228.46

0% 20,625.36 100%

995.40

16,599.38

2,886.44

144.14

0% 415.09 86% 68.86 14%

0% 17.19 100%

0.63

16.56

0% 6.35 100%

3.64

2.71

0% 53.36 100%

53.36

0% 391.55 96% 15.50 4%

391.55 15.50

87% 363.41 13%

363.41
2,873.03 100%

2,873.03

100%

134,706.78 1,144.16
10,776.54 91.53
9,429.47 80.09
154,912.80 1,315.78
27,884.30 236.84
65.2% 182,797.10 34.5% 1,552.62 0.3%

529,443.92 390,157.66
MEJORAMIENTO DEL SISTEMA DE RIEGO DE LOS CANALES SAN JOSE - PINGOBAMBA - BEDOYA Y
PROYECTO: SANTA ISABEL LLASAVILCA BAJO, DEL C.P. TURISTICO EL CAMPAMENTO, DISTRITO DE CHOTA,
PROVINCIA DE CHOTA - CAJAMARCA

Cliente: MUNICIPALIDAD PROVINCIAL DE CHOTA


Lugar: CAJAMARCA - CHOTA - CHOTA

RESUMEN DE METRADOS EJECUTADOS DE OBRA

Item Descripción Und Metrado

01 CANAL DE RIEGO SAN JOSE (PINGOBAMBA - BEDOYA)


01.01 OBRAS PROVISIONALES
01.01.01 CARTEL DE OBRA DE 3.60 X 2.40 m u
01.01.02 CAMPAMENTO PROVISIONAL DE LA OBRA mes
01.05 REPOSICIÓN DE CANAL DE CONCRETO L=18 m
01.05.01 TRAZO Y REPLANTEO km 0.02
01.05.02 CORTE EN MATERIAL SUELTO MANUAL m3 6.73
01.05.03 REFINE NIVELACION Y COMPACTACION CAJA CANAL m2 28.80
01.05.04 CONCRETO f'c=175 kg/cm2 EN CANAL m3 3.04
01.05.05 ENCOFRADO Y DESENCOFRADO DE CANAL m2 25.20
01.05.06 JUNTAS ASFALTICAS m 9.45
01.06 CURADO DE CONCRETO
01.06.01 CURADO DE CONCRETO CON ADITIVO m2 25.20
02 CANAL DE RIEGO SANTA ISABEL (LLASAVILCA BAJO)
02.03 DESARENADOR INC. CANAL DE CONCRETO L=72 M
02.03.01 OBRAS PRELIMINARES
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2
02.03.01.02 TRAZO Y REPLANTEO m2
02.03.02 MOVIMIENTO DE TIERRAS
02.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3
02.03.02.02 REFINE, NIVELACION Y COMPACTACION m2
02.03.03 CONCRETO SIMPLE
02.03.03.01 SOLADO C:H=1:12, E=0.10 M m2 3.84
02.03.03.02 CONCRETO f 'c= 175 kg/cm2 m3 15.42
02.03.03.03 ENCOFRADO Y DESENCOFRADO m2 133.64
02.03.04 VARIOS
02.03.04.01 COMPUERTA PLANCHA METALICA 1/4" DE 0.40 X 1.00 M u 1.00
02.04 CONSTRUCCION DE PASE AEREO PARA TUBERIA L=20M
02.04.01 OBRAS PRELIMINARES
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2
02.04.01.02 TRAZO Y REPLANTEO m2
02.04.02 MOVIMIENTO DE TIERRAS
02.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3
02.04.02.02 REFINE, NIVELACION Y COMPACTACION m2
02.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3
02.04.03 CONCRETO SIMPLE
02.04.03.01 SOLADO C:H=1:12, E=0.10 M m2
02.04.03.02 CONCRETO f 'c= 175 kg/cm2 EN DADOS DE ANCLAJE m3
02.04.04 CONCRETO ARMADO
02.04.04.01 CONCRETO f'c=210 kg/cm2 EN TORRE m3 2.26
02.04.04.02 ACERO fy=4200 kg/cm2 GRADO 60 kg
02.04.04.03 ENCOFRADO Y DESENCOFRADO m2 3.62
02.04.05 REVOQUES
02.04.05.01 TARRAJEO EN EXTERIORES m2 27.62
02.04.06 PINTURA
02.04.06.01 PINTURA ESMALTE EN EXTERIORES m2 27.62
02.04.07 VARIOS
02.04.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC UF NTP ISO 4435 D=12" ( m 27.31
02.04.07.02 SUMINISTRO E INSTALACION DE CABLE DE ACERO Ø 5/8" m 28.30
02.04.07.03 SUMINISTRO E INSTALACION DE ABRAZADERAS Y PENDOLAS u 1.00
02.05 PASE CANOA TIPO 01
02.05.01 MOVIMIENTO DE TIERRAS
02.05.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3
02.05.01.02 REFINE, NIVELACION Y COMPACTACION m2
02.05.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3
02.05.02 CONCRETO SIMPLE
02.05.02.01 SOLADO C:H=1:12, E=0.10 M m2 16.00
02.05.03 CONCRETO ARMADO
02.05.03.01 CONCRETO f'c=210 kg/cm2 m3 11.16
02.05.03.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 198.52
02.05.03.03 ENCOFRADO Y DESENCOFRADO m2 53.28
02.06 PASE CANOA TIPO 02
02.06.01 MOVIMIENTO DE TIERRAS
02.06.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3
02.06.01.02 REFINE, NIVELACION Y COMPACTACION m2
02.06.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3
02.06.02 CONCRETO SIMPLE
02.06.02.01 SOLADO C:H=1:12, E=0.10 M m2 2.40
02.06.03 CONCRETO ARMADO
02.06.03.01 CONCRETO f'c=210 kg/cm2 m3 0.56
02.06.03.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 10.63
02.06.03.03 ENCOFRADO Y DESENCOFRADO m2 7.56
02.07 ALCANTARILLAS (02 UNIDADES), L= 6.00 M. C/U
02.07.01 MOVIMIENTO DE TIERRAS
02.07.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3
02.07.01.02 REFINE, NIVELACION Y COMPACTACION m2
02.07.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3
02.07.02 CONCRETO SIMPLE
02.07.02.01 SOLADO C:H=1:12, E=0.10 M m2 8.40
02.07.03 CONCRETO ARMADO
02.07.03.01 CONCRETO f'c=210 kg/cm2 m3 4.21
02.07.03.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 179.61
02.07.03.03 ENCOFRADO Y DESENCOFRADO m2 21.30
02.08 PASE PEATONAL
02.08.01 MOVIMIENTO DE TIERRAS
02.08.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3
02.08.01.02 REFINE, NIVELACION Y COMPACTACION m2
02.08.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3
02.08.02 CONCRETO ARMADO
02.08.02.01 CONCRETO f'c=210 kg/cm2 m3 0.36
02.08.02.02 ACERO fy=4200 kg/cm2 GRADO 60 kg 5.56
02.08.02.03 ENCOFRADO Y DESENCOFRADO m2 3.04
02.09 CONSTRUCCION DE CANAL DE CONCRETO L=1.75 KM
02.09.01 OBRAS PRELIMINARES
02.09.01.01 LIMPIEZA DE TERRENO MANUAL m2
02.09.01.02 TRAZO Y REPLANTEO km
02.09.02 MOVIMIENTO DE TIERRAS
02.09.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3
02.09.02.02 REFINE, NIVELACION Y COMPACTACION m2
02.09.03 CONCRETO SIMPLE
02.09.03.01 CONCRETO f 'c= 175 kg/cm2 m3 18.69
02.09.03.02 ENCOFRADO Y DESENCOFRADO m2 11.81
02.09.04 VARIOS
02.09.04.01 COMPUERTA METALICA TIPO TARJETA 1/8" DE 0.35 X 0.325 m u 12.00
02.09.04.02 JUNTAS ASFALTICAS m2 107.75
02.10 CONSTRUCCION DE MURO PARA PROTECCION DE PUENTE PEATONAL L=25 M
02.10.01 OBRAS PRELIMINARES
02.10.01.01 LIMPIEZA DE TERRENO MANUAL m2
02.10.01.02 TRAZO Y REPLANTEO m
02.10.02 MOVIMIENTO DE TIERRAS
02.10.02.01 EXCAVACION EN SUELO GRAVOSO BAJO AGUA m3
02.10.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3
02.10.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3
02.10.03 CONCRETO SIMPLE
02.10.03.01 SOLADO C:H=1:12, E=0.10 M m2
02.10.03.02 CONCRETO f'c=175 kg/cm2 + 25% PM m3
02.10.03.03 ENCOFRADO Y DESENCOFRADO m2
02.10.03.04 JUNTAS ASFALTICAS m2
02.11 PASE CON TUBERIA
02.11.01 OBRAS PRELIMINARES
02.11.01.01 LIMPIEZA DE TERRENO MANUAL m2 3.00
02.11.01.02 TRAZO Y REPLANTEO m 6.00
02.11.02 MOVIMIENTO DE TIERRAS
02.11.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 0.25
02.11.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.31
02.11.03 CONCRETO SIMPLE
02.11.03.01 CONCRETO f 'c=175 kg/cm2 EN DADOS m3 0.18
02.11.04 TUBERIA
02.11.04.01 SUMINISTRO E INSTALACION DE TUBERIA PVC UF NTP ISO 4435 D=12" ( m 6.00
02.12 CURADO DEL CONCRETO
02.12.01 CURADO DEL CONCRETO CON ADITIVO m2 450.00
03 MITIGACION DE IMPACTO AMBIENTAL
03.01 ACCIONES DE MITIGACION AMBIENTAL glb 0.50
04 FLETE
04.01 FLETE TERRESTRE A PIE DE OBRA glb 0.10