Professional Documents
Culture Documents
blow first or both the fuse and the recloser could operate at the is valid even when DG is disconnected. However, the schemes
same time. discussed in [12] and [13] may not be very effective when it
Various measures proposed in the literature for maintaining comes to maintaining coordination in the worst fault conditions
protection coordination in power systems, particularly for main- as will be discussed later in this paper.
taining RFC in DNs with DG, may be broadly divided into two To avoid simultaneous operation of the recloser’s fast curve
categories: preventive and remedial. Preventive approaches are and fuse in the case of high fault currents, a partial fuse-saving
those which aim at limiting the contribution of DG to such an scheme is described in [14]. The fuse characteristic curve is
extent that the original RFC of the network is not disturbed as truncated at the maximum coordination current (MCC), which is
proposed in [4]–[9]. Remedial solutions are those which recom- defined as the current where fuse saving can no longer be guar-
mend changes in settings of protective devices to maintain RFC anteed by the recloser. But with this scheme, it will be difficult
in the presence of DG as discussed in [2], [10]–[22]. to define the MCC when DG is connected to the network (i.e.,
it will vary depending upon the size and location of the DG).
A. Preventive Solutions Proposed in the Literature 2) Adaptive Relaying: References [15]–[17] discuss strate-
In [4], the authors recommend that protection selectivity gies relying on an adaptive of OC relays to detect faults
should be checked whenever a new DG unit is connected to a (normal or high impedance) in DNs that otherwise remain un-
DN and settings of overcurrent (OC) devices should be recalcu- detected due to fixed settings of OC relays or due to the intro-
lated to maintain it. In [5]–[7], a method based on mathematical duction of DG into the network. Most of these strategies rely on
equations of the characteristics of protective devices is used modifying relay settings in real time as operating conditions of
to determine the maximum size of DG that can be integrated the system change (i.e., is updated according to currently
into the system without causing RF miscoordination. In [8], available short-circuit current and actual loading conditions).
it is suggested that, generally, the only way to maintain RFC The adaptive protection schemes described in [18] and [19],
without modifying the protection scheme, in the presence of propose dividing the DN into various zones with a reasonable
DG, is an instant disconnection of all DG units connected balance of load and DG in each zone. The schemes aim at main-
to the system, in the case of a fault. Once DG is offline, the taining protection coordination while keeping most of the DG
original protection coordination (i.e., the one prior to DG con- online during a fault by allowing islanded operation of DG.
nection), will be restored. However, this scheme cannot work However, due to the location of DG units with respect to the
in conditions where the fault level is such that the coordination loads, the fluctuating nature of power from these DG units, and
margin between operating times of the recloser and fuse is uncertainty of utility loads, it might not be possible to establish
almost negligible. By the time the DG is disconnected, the fuse zones that fulfill the required criteria. Moreover, islanded op-
would already have blown. The use of a fault current limiter eration of DG may not be desirable. According to the current
(FCL) for maintaining protection coordination when DG is utility practice, islanding is not allowed.
connected to a DN is discussed in [9]. However, the FCL is a A scheme is proposed in [20] to keep protection coordination
relatively new device and needs more practical testing and field intact during a fault without creating any island or DG discon-
experience before becoming a reliable solution for fault current nection while ensuring that the conventional overcurrent pro-
limiting in electrical networks. In a DN with a high level of DG tection devices (i.e., OC relays, reclosers, or fuses) do not lose
penetration, the optimal location of an FCL and selection of its their proper coordination. But this scheme is intended only for
best impedance may be challenging. meshed networks.
3) Expert Systems and Agent-Based Schemes: Expert sys-
B. Remedial Solutions Proposed in the Literature tems and multiagent approaches have been discussed in [21]
1) Miscellaneous: By showing the impact of different DG and [22] to solve protection coordination problems in distribu-
types and sizes on the fuse melting time, the authors of [2] pro- tion systems. However, these systems are expensive as well as
pose changing fuse size, or the selection of faster recloser set- difficult to realize and maintain due to their complexity.
tings with fuse replacement as the most likely option for en-
suring recloser-fuse coordination. A change of the type or size C. Contributions of this Paper
of a fuse is also proposed in [10] when it is not possible to save it This paper describes an alternative protection strategy that
over the entire fault current range. In circumstances, where it is benefits from the characteristics of both time and instantaneous
not possible to save a fuse due to a high fault contribution from OC (i.e., 51 and 50) elements for maintaining RFC in a typ-
DG, the use of a sectionalizer is discussed in [11] as a solution. ical DN with DG. Moreover, a novel algorithm is proposed to
Reference [12] proposes modifying the TCC of the recloser’s adaptively change the setting of the 50 element to ensure fuse
fast curve for maximum possible fault current on the basis of saving under the worst fault conditions. Section II introduces a
the fuse to recloser currents ratio (i.e., ratio of the fuse current case study of a typical DN with DG. In Section III, the potential
to the recloser current and then coordinate it with impacts of DG on RFC are investigated through simulations of
the fuse curve). To this end, the use of an adaptive micropro- different fault scenarios with different DG configurations, and
cessor-based recloser is recommended. In [13], modifying the the results are analyzed for developing a solution strategy. In
TCC of the recloser’s fast curve based on the minimum value Section IV, a scheme is proposed to restore proper RFC for
of is proposed to ensure RFC even in the presence of DG. fuse saving even in the presence of DG. A reclosing strategy
To accomplish this, the use of a microprocessor-based recloser for the feeder with DG is described in Section V. In Section VI,
is recommended. It is shown that the revised characteristic curve some observations are made with respect to the application and
HUSSAIN et al.: ADAPTIVE RELAYING SCHEME FOR FUSE SAVING IN DISTRIBUTION NETWORKS 671
Fig. 5. of the recloser and MMTs of the fuse for an LLL fault at different
lengths of the feeder LF1-1 without DG connection.
Fig. 3. Proper coordination between the recloser R3 and the fuse F2 for an LLL
(or 3LG with zero ground resistance) close-in fault at LF1-1 without DG. “1f”
and “1” stand for the recloser fast and slow characteristics curves, respectively,
while “2” represents the fuse characteristics curve.
Fig. 6. of the recloser and MMTs of the fuse for faults shown in Fig. 4
when 3 and 10.
location of DG make it difficult for a recloser to operate before determined with DG contribution, as discussed in the following
a fuse with a safe time margin. subsections.
Modifications of TCC of the recloser are therefore necessary 1) of the 50 Element Based on Fault Currents without
to save the fuse in the event of temporary faults when DG is DG Connection: If the setting of the 50 element is performed
connected to the network. One way to do it is to follow the without considering the contribution from DG, then it will un-
procedure described in [12] and [13] (i.e., modify the fast curve derreach (i.e., the area protected by the relay will reduce) if, sub-
of the recloser on the basis of ratio of and ), as mentioned sequently, DG is connected downstream from the recloser. For
earlier. But here, this method does not give the desired results. example, in the case under study, of 1290 A for the 50
The minimum CTI for the test system is 40 ms in the case of an element will ensure that the recloser will operate for the refer-
LLL close-in fault at the feeder LF1-1 when 3 and ence faults without DG connection as can be noticed from Fig. 5.
10. By modifying the recloser (i.e., R3) fast curve as described With this setting, when the DG is connected downstream of the
in [12] and [13], the new minimum CTI for the same fault will recloser, then the latter, depending upon the number of DG units
be 73 ms whereas for a fault at 10% of the feeder LF1-1, it connected, may not operate for all of the reference faults (i.e.,
will be 96 ms. In both cases, it is less than the required margin it will operate only for faults occurring below the RP). For ex-
of 100 ms. Moreover, with the application of this method, the ample, when 0 and 2, the fault current seen by the
entire recloser’s fast curve is modified which is not desirable recloser for an LLL fault at the RP is only 1262 A whereas the
in the test system in Fig. 2 as RF miscoordination is witnessed total fault current is 1486 A. In this case, the recloser will un-
only over a quarter of the feeder LF1-1 (i.e., up to the RP). derreach.
In addition to this, the recloser also sees faults on LF1 where 2) of the 50 Element Based on Fault Currents with
fuse saving is not a matter of concern. In these cases, upgrading DG Connection: If the setting of the 50 element is done with
the recloser R2 with an instantaneous directional OC element the DG contribution taken into account, then it will overreach if,
(i.e., 67) having a suitable trip threshold greater than the full subsequently, DG units, which are connected downstream from
load current, that has a total response time (relay operating time the recloser, are disconnected from the circuit. For example,
plus CB opening time) of 2.5 to 5 cycles may not work. Since in the case under study, of 1095A for the 50 element
time margin in the scenarios discussed before is very small, the will ensure that the relay will operate for reference faults with
fuse might get damaged before the recloser R2 completes its DG connection. With this setting when downstream, connected
operation to separate DG2 from the network. DG units are disconnected, the 50 element, depending upon the
Alternatively, we propose equipping the recloser with an in- number of DG units disconnected, may operate for faults oc-
stantaneous OC phase element (i.e., 50), in addition to the 51 curring beyond the RP and, thus, encroach onto the area of the
element that is used. This will increase the CTI for the afore- 51-element operation. For example, when all of the DG units
mentioned faults. In the test system in Fig. 2, 50 element in R3, are disconnected, the 50 element with of 1095A will op-
with an operating time of 15 ms when a fault current exceeds its erate for faults up to 55% of the feeder LF1-1 as can be noticed
, will clear all phase faults occurring up to the RP with a from Fig. 5 (i.e., it will overreach).
reasonable time margin. If the operating time of the 50 element Thus, a fixed of the 50 element based either on the
is compared with fuse blowing times shown in Figs. 5 and 6, it fault current without DG connection or based on the fault
can be found that most of the faults will be cleared with a CTI of current with DG connection, has its limitations. To overcome
more than 100 ms. Even in cases where it is not possible to have this problem, an adaptive setting of the 50 element needs to be
a CTI of 100 ms (i.e., for an LLL close-in fault at LF1-1 when adopted. The strategy is to set the reference (i.e., initial)
3 and 10), a recloser with a 50 element will ensure a of the element either on the basis of fault current without a DG
CTI of 85 ms, and for a fault at 10% of the feeder LF1-1 length connection or on the basis of fault current with DG connection,
for the same case, it will ensure a CTI of 115 ms. This shows an and later on adaptively changing the setting when a DG unit is
improvement in CTI in comparison to results obtained by fol- connected or disconnected from the network.
lowing the technique described in [12] and [13]. In this paper, the initial of the 50 element is based on
the fault current calculated at the RP in case of an LLL fault
A. Options and Considerations for the Selection of without DG connection. This setting is adaptive (i.e., it will
of the 50 Element change whenever a DG unit is added or removed from the net-
of the 50 element should be such that it operates only work), ensuring that the recloser with the 50 element operates
against high magnitude faults that are unlikely to be cleared by for all reference faults with a CTI of 100 ms or more. Keeping
a 51 element safely. It is undesirable to set the 50 element to in mind the proposed adaptive change in settings, a multifunc-
operate against the low magnitude faults (i.e., faults occurring tional microprocessor-based recloser is necessary so that it can
beyond the RP). If set too low, it may maltrip when the current be programmed as required. Therefore, replacement of the ex-
momentarily rises in some conditions without a fault (e.g., due isting recloser with a microprocessor-based recloser, with com-
to transformer inrush current or cold load start conditions). Its munication capabilities, that incorporates the instantaneous and
setting should be such that it operates only for faults up to the time OC elements is recommended. A microprocessor-based re-
RP irrespective of the number of DG units connected. closer, that is capable of communicating with DG, can adap-
of the 50 element can be based either on faults currents calcu- tively change its settings online in accordance with different DG
lated without considering DG contribution or on faults currents configurations.
674 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 28, NO. 2, APRIL 2013
Fig. 7. Adaptive algorithm for modifying of the instantaneous element when a DG unit is connected or disconnected from the network.
B. Adaptive Algorithm fuse are noted. The same step is repeated with all DG units
connected, and the fault location farthest from the fuse
To enable the 50 element to adaptively modify its ,a end of the feeder, where it is not possible to have a CTI of
novel algorithm is developed that can be programmed into the 100 ms with a 51 element, is selected as an RP. In the test
recloser control logic along with some essential data that can be system in Fig. 2, RP is 25% of the feeder LF1-1 length
stored into a database. The algorithm is shown in Fig. 7 in the and acts as a basis for selecting of the 50 element.
form of a flowchart. In the flowchart, and stand for the b) Similarly, fault currents at the reference point are calcu-
number of DG units connected at DG1 and DG2, respectively. lated for different values of and . For each value of
stands for the reference of the 50 element. is , will be based on the fault current at the reference
calculated on the basis of the fault currents that result from an point when 0. In the test system, for example,
LLL fault at 25% of the feeder LF1-1 length (RP) for different 1290 A when 0, and 1365 A when 1 as
combinations of and . It can have four different values de- shown in Fig. 7. The 50-element pickup current is set to
pending upon values of while 0. is a change in the be equal to when 0.
fault current flowing through the recloser R3 in case of faults c) As increases, the fault current level changes (reduces
at the feeder LF1-1 when a single DG unit is connected or dis- on the feeder LF1-1 as seen by the recloser R3 in the test
connected at DG2; its value is different for different combina- system in Fig. 2) and accordingly the pickup current of
tions of and . stands for of the 50 element when the 50 element needs to be adjusted. When the value of
and , subscripts , , , and are defined on the changes, of the 50 element is reset adaptively by
basis of for various combinations of and . finding the corresponding reduction or increase in utility
The data that are required to be stored into a database in- fault current contribution flowing through the re-
clude different possible values of and . To implement closer R3 in case of an LLL fault occurring at the RP and
this algorithm, a communication link is necessary between the then by deducting or adding it from the reference setting,
recloser and various DG units so that the former can update (i.e., ). Thus, when a DG unit is connected or discon-
its setting when the latter are connected or disconnected from nected at DG2, of the 50 element also decreases
the network. This would require modern reclosers with suitable or increases accordingly. Fig. 7 suggests suitable values
remote communication capabilities.. With these arrangements, of for the test system that were determined based on
DG units can be treated as plug-and-play devices. fault analysis results.
1) Description of the Algorithm: Fig. 8 shows the new TCC for the 50 and 51 elements of the
a) Through fault analysis of the test system, fault currents recloser R3 of the test system obtained in accordance with the
due to an LLL fault at different lengths of the feeder LF1-1 proposed algorithm for the cases when 0 and 0 or
with no DG connection (i.e., 0 and 0) are found 10, and when 3 and 0 or 5. As can be noticed from
and corresponding operating times of the 51 element and these figures, of the 50 element will be different for each
HUSSAIN et al.: ADAPTIVE RELAYING SCHEME FOR FUSE SAVING IN DISTRIBUTION NETWORKS 675
Fig. 9. Operating time of the recloser R3 with the modified settings and MMT
of the fuse F2 for an LLL fault at 10% of the feeder LF1-1 length when 3
and 10. “1f” and “1” stand for the recloser’s fast and slow characteristics
curves, respectively, while “2” represents the fuse characteristics curve.
Fig. 8. Proposed TCC for the recloser instantaneous and time OC elements
when 0 and 0 or 10, and when 3 and 0 or 5. “1f”
and “1s” stand for the fast and slow characteristic curves of the recloser 51 OC
element while “5,” represents the fuse characteristic curve.
[14] C. McCarthy, R. O’Leary, and D. Staszesky, “A new fuse-saving phi- S. M. Sharkh received the B.Eng. and Ph.D. degrees
losophy,” in Proc. DistribuTECH, Tampa, FL, Jan. 2008, pp. 1–7. in electrical engineering from the University of
[15] M. Baran and I. El-Markabi, “Adaptive over current protection for dis- Southampton, Southampton, U.K., in 1990 and
tribution feeders with distributed generators,” in Proc. IEEE/Power 1994, respectively.
Eng. Soc. Power Syst. Conf. Expo., 2004, vol. 2, pp. 715–719. Currently, he is a Senior Lecturer and the Head
[16] A. Conde and E. Vazquez, “Operation logic proposed for time overcur- of the Electro-Mechanical Research Group at the
rent relays,” IEEE Trans. Power Del., vol. 22, no. 4, pp. 2034–2039, University of Southampton. He is also the Managing
Oct. 2007. Director of HiT Systems Ltd., Southampton. He
[17] N. Schaefer, T. Degner, A. Shustov, T. Keil, and J. Jaeger, “Adaptive has published many papers in academic journals
protection system for distribution networks with distributed energy re- and conferences. His main research interests are in
sources,” in Proc. 10th Inst. Eng. Technol. Int. Conf. Develop. Power the areas of control, electrical machines, and power
Syst. Protect., Managing the Change, Manchester, U.K., 2010, pp. 1–5. electronics with applications to electric vehicles and distributed generation.
[18] S. M. Brahma and A. A. Girgis, “Development of adaptive protection Dr. Sharkh is a member of the Institute of Engineering and Technology and a
scheme for distribution systems with high penetration of distributed Chartered Engineer. He was the 2008 winner of The Engineer Energy Innova-
generation,” IEEE Trans. Power Del., vol. 19, no. 1, pp. 56–63, Jan. tion Award for his work on rim-driven thrusters and marine turbine generators.
2004.
[19] S. A. M. Javadian, M. R. Haghifam, and P. Barazandeh, “An adaptive
over-current protection scheme for MV distribution networks including
DG,” in Proc. IEEE Int. Symp. Ind. Electron., Cambridge, U.K., 2008, S. Hussain received the B.Sc. and M.Sc. degrees in
pp. 2520–2525. electrical engineering from the UET, Lahore, Pak-
[20] F. A. Viawan, D. Karlsson, and A. Sannino et al., “Protection scheme istan, in 1992 and 2000, respectively.
for meshed distribution systems with high penetration of distributed He was a Senior Electrical Engineer at NTDC
generation,” in Proc. Power Syst. Conf.: Adv. Metering, Protect., Con- (WAPDA), Lahore, Pakistan, until he joined the
trol, Commun., Distrib. Resources, 2006, pp. 99–104. Hatch, Mississauga, ON, Canada as a Senior Su-
[21] K. Tuitemwong and S. Premrudeepreechacharn, “Expert system for pervising Engineer. He has more than 19 years
protection coordination of distribution system with distributed gener- of experience in the electric power industry. His
ators,” Int. J. Elect. Power Energy Syst., vol. 33, no. 3, pp. 466–471, research focus is on power system protection and
2011. control.
[22] H. Wan, K. K. Li, and K. P. Wong, “An adaptive multiagent approach to
protection relay coordination with distributed generators in industrial
power distribution system,” IEEE Trans. Ind. Appl., vol. 46, no. 5, pp.
2118–2124, Sep./Oct. 2010.
[23] E. P. Dick and A. Narang, Canadian Urban Benchmark Distribution M. A. Abusara received the B.Eng. degree in elec-
Systems NR, Canada, 2005-121, 2005. trical engineering from Birzeit University, Palestine,
[24] IEEE Standard Electrical Power System Device Function Numbers, in 2000 and the Ph.D. degree in electrical engineering
IEEE Standard C37.2-1987, 1987, pp. 0–1. from the University of Southampton, Southampton,
[25] IEEE Standard for Interconnecting Distributed Resources with Electric U.K., in 2004.
Power Systems, IEEE Standard 1547-2003, Jul. 2003. Currently, he is a Lecturer in Renewable Energy at
the University of Exeter, Penryn Cornwall, U.K. He
B. Hussain received the B.Sc. degree in electrical has more than ten years of industrial experience with
engineering from the University of Engineering and Bowman Power Group, Southampton, in the field of
Technology, Taxila, Pakistan, in 1995 and the Ph.D. research and development of digital control of power
degree in electrical engineering from the University electronics. During his years in the industry, he de-
of Southampton, Southampton, U.K., in 2011. signed and prototyped a number of commercial products that include grid- and
He has more than ten years of experience in the parallel-connected inverters, microgrid, dc/dc converters for hybrid vehicles,
electric power sector. His major research interests and sensorless drives for high-speed permanent-magnet machines.
include protection of distribution networks with
distributed generation, power quality, and control of
grid-connected inverters.