You are on page 1of 9

IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 28, NO.

2, APRIL 2013 669

An Adaptive Relaying Scheme for Fuse Saving in


Distribution Networks With Distributed Generation
B. Hussain, S. M. Sharkh, S. Hussain, and M. A. Abusara

Abstract—In some situations, utilities may try to “save” the fuse


of a circuit following temporary faults by de-energizing the line
with the fast operation of an upstream recloser before the fuse
is damaged. This fuse-saving practice is accomplished through
proper time coordination between a recloser and a fuse. However,
the installation of distributed generation (DG) into distribution
networks may affect this coordination due to additional fault
current contributions from the distributed resources. This phe-
nomenon of recloser-fuse miscoordination is investigated in this
paper with the help of a typical network that employs fuse saving.
The limitations of a recloser equipped with time and instantaneous
overcurrent elements with respect to fuse savings, in the presence
of DG, are discussed. An adaptive relaying strategy is proposed
to ensure fuse savings in the new scenario even in the worst
fault conditions. The simulation results obtained by adaptively
changing relay settings in response to changing DG configurations Fig. 1. Typical time-current coordination (TCC) curve for protective devices.
confirm that the settings selected theoretically in accordance with
the proposed strategy hold well in operation.
discontinuity of service due to temporary faults), utilities nor-
Index Terms—Adaptive relaying, distributed generation (DG), mally employ a fuse-saving strategy. Through this strategy, util-
distribution network, protection. ities try to “save” the fuse on the circuit following temporary
faults by de-energizing the line with the fast operation of up-
stream interrupting device (i.e., a recloser) before the fuse has
I. INTRODUCTION a chance to blow. The interrupting device then recloses and re-
stores power beyond the fuse. This is a useful practice since
it saves expensive fuse replacement and unnecessary extended
service interruption which otherwise could be quite burdensome

T HE BASIC objective of protection coordination in power


systems is to achieve selectivity (i.e., to switch off only
the faulted component and leave the rest of the power system in
as temporary faults constitute almost 70% to 80% of faults oc-
curring in DNs. In case of a permanent fault, upon completion
of the recloser’s fast mode shots, the fuse blows to clear the fault
service in order to minimize discontinuity of supply and to en- while the recloser is waiting to operate on its slow curve. The
sure stability). Proper coordination ensures that there is neither a feeder-head-end CB provides overall backup protection since
maloperation of protective devices nor a duplication of their op- its time–current characteristics (TCC) curve is above all of the
eration. The traditional coordination between a circuit breaker other curves.
(CB), a recloser, and a lateral fuse in a typical distribution net- As shown in Fig. 1, the coordination between a recloser and
work (DN) is illustrated in Fig. 1 [1]. To achieve selectivity in a fuse will be valid only if the fault current is between the min-
the isolation of a fault, protective devices in series are time co- imum fault current of the feeder and maximum fault
ordinated so that the upstream device electrically closest to the current of the feeder , and provided that there is some
short circuit or overload opens first to isolate the faulty section. margin between operating times of these two devices. This is
However, to ensure reliability of supply (i.e., to avoid prolonged because between and , the recloser’s fast char-
acteristic curve lies below the minimum melt (MM) character-
Manuscript received November 18, 2011; revised March 16, 2012; accepted istic of the fuse and the recloser slow characteristic curve lies
September 29, 2012. Date of publication February 05, 2013; date of current above the total clearing (TC) characteristic of the fuse. How-
version March 21, 2013. Paper no. TPWRD-00991-2011.
ever, the integration of distributed generation (DG) into DNs,
B. Hussain and S. M. Sharkh are with the Electro-Mechanical Re-
search Group, Faulty of Engineering and the Environment, University of depending upon the size, type, and location of DG units, may
Southampton, Southampton SO17 1BJ, U.K. (e-mail: bh1k06@soton.ac.uk; affect the recloser and fuse coordination (RFC) [1]–[3]. Re-
suleiman@soton.ac.uk).
closer-fuse (RF) miscoordination can occur when the fault cur-
S. Hussain is with the Hatch, Mississauga, ON L5K 2R7 Canada (e-mail:
engrsajidhussain@hotmail.com). rent becomes greater than due to the additional fault cur-
M. A. Abusara is with the Renewable Energy Research Group, University of rent contribution from DG. It can also happen when, due to the
Exeter, Penryn Cornwall TR10 9EZ, U.K. (e-mail: m.abusara@exeter.ac.uk).
location of DG, the fault current seen by a recloser is less than
Color versions of one or more of the figures in this paper are available online
at http://ieeexplore.ieee.org. the current that passes through a fuse, even when the fault cur-
Digital Object Identifier 10.1109/TPWRD.2012.2224675 rent is between and . As a result, the fuse could

0885-8977/$31.00 © 2013 IEEE


670 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 28, NO. 2, APRIL 2013

blow first or both the fuse and the recloser could operate at the is valid even when DG is disconnected. However, the schemes
same time. discussed in [12] and [13] may not be very effective when it
Various measures proposed in the literature for maintaining comes to maintaining coordination in the worst fault conditions
protection coordination in power systems, particularly for main- as will be discussed later in this paper.
taining RFC in DNs with DG, may be broadly divided into two To avoid simultaneous operation of the recloser’s fast curve
categories: preventive and remedial. Preventive approaches are and fuse in the case of high fault currents, a partial fuse-saving
those which aim at limiting the contribution of DG to such an scheme is described in [14]. The fuse characteristic curve is
extent that the original RFC of the network is not disturbed as truncated at the maximum coordination current (MCC), which is
proposed in [4]–[9]. Remedial solutions are those which recom- defined as the current where fuse saving can no longer be guar-
mend changes in settings of protective devices to maintain RFC anteed by the recloser. But with this scheme, it will be difficult
in the presence of DG as discussed in [2], [10]–[22]. to define the MCC when DG is connected to the network (i.e.,
it will vary depending upon the size and location of the DG).
A. Preventive Solutions Proposed in the Literature 2) Adaptive Relaying: References [15]–[17] discuss strate-
In [4], the authors recommend that protection selectivity gies relying on an adaptive of OC relays to detect faults
should be checked whenever a new DG unit is connected to a (normal or high impedance) in DNs that otherwise remain un-
DN and settings of overcurrent (OC) devices should be recalcu- detected due to fixed settings of OC relays or due to the intro-
lated to maintain it. In [5]–[7], a method based on mathematical duction of DG into the network. Most of these strategies rely on
equations of the characteristics of protective devices is used modifying relay settings in real time as operating conditions of
to determine the maximum size of DG that can be integrated the system change (i.e., is updated according to currently
into the system without causing RF miscoordination. In [8], available short-circuit current and actual loading conditions).
it is suggested that, generally, the only way to maintain RFC The adaptive protection schemes described in [18] and [19],
without modifying the protection scheme, in the presence of propose dividing the DN into various zones with a reasonable
DG, is an instant disconnection of all DG units connected balance of load and DG in each zone. The schemes aim at main-
to the system, in the case of a fault. Once DG is offline, the taining protection coordination while keeping most of the DG
original protection coordination (i.e., the one prior to DG con- online during a fault by allowing islanded operation of DG.
nection), will be restored. However, this scheme cannot work However, due to the location of DG units with respect to the
in conditions where the fault level is such that the coordination loads, the fluctuating nature of power from these DG units, and
margin between operating times of the recloser and fuse is uncertainty of utility loads, it might not be possible to establish
almost negligible. By the time the DG is disconnected, the fuse zones that fulfill the required criteria. Moreover, islanded op-
would already have blown. The use of a fault current limiter eration of DG may not be desirable. According to the current
(FCL) for maintaining protection coordination when DG is utility practice, islanding is not allowed.
connected to a DN is discussed in [9]. However, the FCL is a A scheme is proposed in [20] to keep protection coordination
relatively new device and needs more practical testing and field intact during a fault without creating any island or DG discon-
experience before becoming a reliable solution for fault current nection while ensuring that the conventional overcurrent pro-
limiting in electrical networks. In a DN with a high level of DG tection devices (i.e., OC relays, reclosers, or fuses) do not lose
penetration, the optimal location of an FCL and selection of its their proper coordination. But this scheme is intended only for
best impedance may be challenging. meshed networks.
3) Expert Systems and Agent-Based Schemes: Expert sys-
B. Remedial Solutions Proposed in the Literature tems and multiagent approaches have been discussed in [21]
1) Miscellaneous: By showing the impact of different DG and [22] to solve protection coordination problems in distribu-
types and sizes on the fuse melting time, the authors of [2] pro- tion systems. However, these systems are expensive as well as
pose changing fuse size, or the selection of faster recloser set- difficult to realize and maintain due to their complexity.
tings with fuse replacement as the most likely option for en-
suring recloser-fuse coordination. A change of the type or size C. Contributions of this Paper
of a fuse is also proposed in [10] when it is not possible to save it This paper describes an alternative protection strategy that
over the entire fault current range. In circumstances, where it is benefits from the characteristics of both time and instantaneous
not possible to save a fuse due to a high fault contribution from OC (i.e., 51 and 50) elements for maintaining RFC in a typ-
DG, the use of a sectionalizer is discussed in [11] as a solution. ical DN with DG. Moreover, a novel algorithm is proposed to
Reference [12] proposes modifying the TCC of the recloser’s adaptively change the setting of the 50 element to ensure fuse
fast curve for maximum possible fault current on the basis of saving under the worst fault conditions. Section II introduces a
the fuse to recloser currents ratio (i.e., ratio of the fuse current case study of a typical DN with DG. In Section III, the potential
to the recloser current and then coordinate it with impacts of DG on RFC are investigated through simulations of
the fuse curve). To this end, the use of an adaptive micropro- different fault scenarios with different DG configurations, and
cessor-based recloser is recommended. In [13], modifying the the results are analyzed for developing a solution strategy. In
TCC of the recloser’s fast curve based on the minimum value Section IV, a scheme is proposed to restore proper RFC for
of is proposed to ensure RFC even in the presence of DG. fuse saving even in the presence of DG. A reclosing strategy
To accomplish this, the use of a microprocessor-based recloser for the feeder with DG is described in Section V. In Section VI,
is recommended. It is shown that the revised characteristic curve some observations are made with respect to the application and
HUSSAIN et al.: ADAPTIVE RELAYING SCHEME FOR FUSE SAVING IN DISTRIBUTION NETWORKS 671

each induction generator at full generation and 1-p.u. voltage


is about 740 kVAR.
Although the total rated capacity of the wind turbines is
greater than that of the substation, it does not, in practice,
cause any issues. Due to the variability of wind speed, the
wind turbines rarely ever operate at their full rated capacity
of 21.45 MW. It is also worth noting that most of the power
generated by the wind turbines will be consumed locally, and
the remaining small excess power (less than 15 MVA), that
is not consumed by the local loads, could be exported via the
substation to the grid. This, of course, may require changes to
Fig. 2. Single-line diagram of a section of a typical distribution network (DN)
with distributed generation (DG) where Sub-TL stands for the subtransmission
the upstream protection system setting.
line, CF and LF represent collector feeder, and load feeder, respectively. IEEE/ IEEE/ANSI-designated protective device numbers [24] are
ANSI-designated protective device numbers [24] are used. used in Fig. 2. Load and collector feeders are equipped with
reclosers R1, R2, R3, and R4 that contain time OC phase and
ground fault (i.e., 51/51N) elements for protection against
implementation of the proposed strategy. Finally, Section VII phase and ground faults. The autoreclose feature is disabled
concludes this paper. for the reclosers R1 and R2. A commercial software package
(ASPEN OneLiner) is used to determine short-circuit levels in
the presence of DG and to investigate their impact on RFC. The
II. CASE STUDY impedance values of the subtransmission lines (Sub-TLs) and
Fig. 2 shows a single-line diagram of a typical distribution the feeders, and pickup current settings of the various
network section described in [23], which is henceforth referred protective devices (Table I) are given in the Appendix.
to as the test system. This test system is simulated to demon-
strate and investigate the impact of DG on the fuse-saving III. SIMULATION RESULTS AND DISCUSSION
scheme and to show the viability of the proposed protection To illustrate the impact of DG on the fuse-saving scheme,
strategy for fuse saving. A typical DN is configured down- the time coordination between the recloser R3 and the fuse F2
stream of a 69/25-kV substation named as the main substation. (150 K) of the test system shown in Fig. 2 has been investigated.
The grid network upstream of the substation is represented by The coordination is represented by the TCC of the recloser and
a Thevenin equivalent circuit of a voltage source and a series MM and TC characteristics of the fuse in Fig. 3 (mathematical
impedance with a short-circuit level of 637 MVA and an X/R description of the TCC is given in [6]). Two reclosing attempts
ratio of 8.38 at the 69-kV input bus. The network is equipped (i.e., one in fast mode and one in slow mode) are planned. The
with a 69-kV/25 kV, 15-MVA substation load tap-changing coordination holds well for different faults with no DG connec-
transformer, with a delta-wye-grounded configuration. The tion. For example, in case of a three-phase (LLL) close-in fault
transformer has a series equivalent impedance of 7.8% and of 1551 A at the feeder LF1-1, the recloser’s fast curve oper-
connects the 69-kV subtransmission system to the DN. The DN ates in 70 ms whereas minimum melt time of the fuse is 290 ms
is modelled as two load feeders—LF1 and LF2—emanating as shown in Fig. 3. The relay current and operating times are
from the 25-kV bus and a tapped line from LF1, which is shown both as points on the curves and as text within the de-
named LF1-1. The system loads are considered as constant scription boxes.
impedances that make no contribution to the fault current. However, when DG is connected to the test system, then, de-
Thirteen wind turbines with a total rated capacity of pending upon the DG size, type, and location, and the nature and
21.45 MW are connected to the 25-kV bus through two 25-kV location of fault, there is a real chance of RF miscoordination
collector feeders named CF1 and CF2. The DG unit is an actual (i.e., fuse may blow, even in the case of temporary faults). It can
wind powerplant. The wind turbines use induction generators be noticed from Fig. 3 that the chances of RF miscoordination
with the rated capacity of 1.65 MW each (with a power factor are high when the fault current is high. Generally, maximum
of 0.95 lagging) which are connected to the network through fault current is expected in case of a bolted LLL fault (hence-
0.6/25-kV, 1.8-MVA stepup transformers. Based on their geo- forth referred to as an LLL fault). The same is true in case of
graphical proximity, ten wind turbines are grouped together and the test system. So to investigate RFC limitations (i.e., the con-
are modelled as an equivalent single machine, designated as ditions where it is not possible to save the fuse), an LLL fault
DG1 in Fig. 2, with a total capacity of 16.5 MW. The location has been simulated at different lengths of LF1-1 with different
of all generators of DG1 is such that their contributions to DG configurations. The total fault currents and the fault currents
different faults are almost the same. Similarly, the remaining seen by the recloser and the fuse obtained by simulating an LLL
three wind turbines are grouped together and are modelled as fault at different lengths of the feeder LF1-1 are shown in Fig. 4.
an equivalent single machine, designated as DG2 in Fig. 2, with The results are for different values of and , where and
a total capacity of 4.95 MW. The contributions of DG2 units to are numbers of DG units at DG1 and DG2, respectively. It is
different faults are also assumed to be the same. Each generator clear from the figure that the fault currents seen by the recloser
is provided with capacitor banks at its terminal for reactive R3 and the fuse are different. This is because the recloser is not
power compensation. The total reactive power required by seeing the fault current contribution from DG2 since the latter is
672 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 28, NO. 2, APRIL 2013

Fig. 5. of the recloser and MMTs of the fuse for an LLL fault at different
lengths of the feeder LF1-1 without DG connection.

Fig. 3. Proper coordination between the recloser R3 and the fuse F2 for an LLL
(or 3LG with zero ground resistance) close-in fault at LF1-1 without DG. “1f”
and “1” stand for the recloser fast and slow characteristics curves, respectively,
while “2” represents the fuse characteristics curve.

Fig. 6. of the recloser and MMTs of the fuse for faults shown in Fig. 4
when 3 and 10.

ensured by the recloser against all phase faults (i.e., phase-to-


phase (LL) and LLL faults) over the entire length of the feeder
LF1-1 when no DG is connected to the network. When DG is
connected to the network, it may not be possible to ensure a CTI
Fig. 4. Fault current magnitudes for an LLL fault at different lengths of the of 100 ms between operation of the recloser’s fast curve and
feeder LF1-1 for different values of and . the fuse in case of an LLL fault up to 25% of the feeder LF1-1
length when 3 and 10. Fuse saving cannot be ensured
in that case. From now onwards, LLL faults up to the 25% of the
connected downstream from the former whereas this is not true feeder LF1-1 length will be mentioned as reference faults, and
for the fuse (i.e., the fuse sees the entire fault current). the location corresponding to 25% of the feeder LF1-1 length
The operating times of the recloser R3 time OC phase will be denoted as a reference point (RP).
element 51, and minimum melt times of the fuse for an LLL
fault at different lengths of the feeder LF1-1, without and with IV. FUSE-SAVING STRATEGY
DG connection, are shown in Figs. 5 and 6. A coordination time
interval (CTI) of 100 ms is assumed to account for CB opening As discussed in the previous section that is based on Figs. 5
time, errors, and tolerances in current transformers (CTs) and and 6, a recloser equipped with a 51 element, can ensure fuse
relays. The results for cases when 1 or 2 and 10, saving only against low-fault currents when DG is present
are not included as in these cases, the conclusions are the same. (i.e., against LL and high-impedance LLL faults over the entire
Moreover, results for the single-phase-to-ground (1LG) or two- length of feeder LF1-1 and against bolted LLL faults only
phase-to-ground faults (2LG) are also not considered here as beyond the RP). This is due to the fact that in case of low-fault
they are cleared by the recloser R3 ground OC time element currents, enough time margin is available for a recloser to
51N, without causing RF miscoordination. operate before the fuse has any chance to blow. But this is not
A comparison of of the recloser R3 with MMT of the fuse true in case of high fault currents (e.g., bolted faults up to the
as shown in Figs. 5 and 6 makes it clear that fuse saving will be RP). The increased fault currents along with the downstream
HUSSAIN et al.: ADAPTIVE RELAYING SCHEME FOR FUSE SAVING IN DISTRIBUTION NETWORKS 673

location of DG make it difficult for a recloser to operate before determined with DG contribution, as discussed in the following
a fuse with a safe time margin. subsections.
Modifications of TCC of the recloser are therefore necessary 1) of the 50 Element Based on Fault Currents without
to save the fuse in the event of temporary faults when DG is DG Connection: If the setting of the 50 element is performed
connected to the network. One way to do it is to follow the without considering the contribution from DG, then it will un-
procedure described in [12] and [13] (i.e., modify the fast curve derreach (i.e., the area protected by the relay will reduce) if, sub-
of the recloser on the basis of ratio of and ), as mentioned sequently, DG is connected downstream from the recloser. For
earlier. But here, this method does not give the desired results. example, in the case under study, of 1290 A for the 50
The minimum CTI for the test system is 40 ms in the case of an element will ensure that the recloser will operate for the refer-
LLL close-in fault at the feeder LF1-1 when 3 and ence faults without DG connection as can be noticed from Fig. 5.
10. By modifying the recloser (i.e., R3) fast curve as described With this setting, when the DG is connected downstream of the
in [12] and [13], the new minimum CTI for the same fault will recloser, then the latter, depending upon the number of DG units
be 73 ms whereas for a fault at 10% of the feeder LF1-1, it connected, may not operate for all of the reference faults (i.e.,
will be 96 ms. In both cases, it is less than the required margin it will operate only for faults occurring below the RP). For ex-
of 100 ms. Moreover, with the application of this method, the ample, when 0 and 2, the fault current seen by the
entire recloser’s fast curve is modified which is not desirable recloser for an LLL fault at the RP is only 1262 A whereas the
in the test system in Fig. 2 as RF miscoordination is witnessed total fault current is 1486 A. In this case, the recloser will un-
only over a quarter of the feeder LF1-1 (i.e., up to the RP). derreach.
In addition to this, the recloser also sees faults on LF1 where 2) of the 50 Element Based on Fault Currents with
fuse saving is not a matter of concern. In these cases, upgrading DG Connection: If the setting of the 50 element is done with
the recloser R2 with an instantaneous directional OC element the DG contribution taken into account, then it will overreach if,
(i.e., 67) having a suitable trip threshold greater than the full subsequently, DG units, which are connected downstream from
load current, that has a total response time (relay operating time the recloser, are disconnected from the circuit. For example,
plus CB opening time) of 2.5 to 5 cycles may not work. Since in the case under study, of 1095A for the 50 element
time margin in the scenarios discussed before is very small, the will ensure that the relay will operate for reference faults with
fuse might get damaged before the recloser R2 completes its DG connection. With this setting when downstream, connected
operation to separate DG2 from the network. DG units are disconnected, the 50 element, depending upon the
Alternatively, we propose equipping the recloser with an in- number of DG units disconnected, may operate for faults oc-
stantaneous OC phase element (i.e., 50), in addition to the 51 curring beyond the RP and, thus, encroach onto the area of the
element that is used. This will increase the CTI for the afore- 51-element operation. For example, when all of the DG units
mentioned faults. In the test system in Fig. 2, 50 element in R3, are disconnected, the 50 element with of 1095A will op-
with an operating time of 15 ms when a fault current exceeds its erate for faults up to 55% of the feeder LF1-1 as can be noticed
, will clear all phase faults occurring up to the RP with a from Fig. 5 (i.e., it will overreach).
reasonable time margin. If the operating time of the 50 element Thus, a fixed of the 50 element based either on the
is compared with fuse blowing times shown in Figs. 5 and 6, it fault current without DG connection or based on the fault
can be found that most of the faults will be cleared with a CTI of current with DG connection, has its limitations. To overcome
more than 100 ms. Even in cases where it is not possible to have this problem, an adaptive setting of the 50 element needs to be
a CTI of 100 ms (i.e., for an LLL close-in fault at LF1-1 when adopted. The strategy is to set the reference (i.e., initial)
3 and 10), a recloser with a 50 element will ensure a of the element either on the basis of fault current without a DG
CTI of 85 ms, and for a fault at 10% of the feeder LF1-1 length connection or on the basis of fault current with DG connection,
for the same case, it will ensure a CTI of 115 ms. This shows an and later on adaptively changing the setting when a DG unit is
improvement in CTI in comparison to results obtained by fol- connected or disconnected from the network.
lowing the technique described in [12] and [13]. In this paper, the initial of the 50 element is based on
the fault current calculated at the RP in case of an LLL fault
A. Options and Considerations for the Selection of without DG connection. This setting is adaptive (i.e., it will
of the 50 Element change whenever a DG unit is added or removed from the net-
of the 50 element should be such that it operates only work), ensuring that the recloser with the 50 element operates
against high magnitude faults that are unlikely to be cleared by for all reference faults with a CTI of 100 ms or more. Keeping
a 51 element safely. It is undesirable to set the 50 element to in mind the proposed adaptive change in settings, a multifunc-
operate against the low magnitude faults (i.e., faults occurring tional microprocessor-based recloser is necessary so that it can
beyond the RP). If set too low, it may maltrip when the current be programmed as required. Therefore, replacement of the ex-
momentarily rises in some conditions without a fault (e.g., due isting recloser with a microprocessor-based recloser, with com-
to transformer inrush current or cold load start conditions). Its munication capabilities, that incorporates the instantaneous and
setting should be such that it operates only for faults up to the time OC elements is recommended. A microprocessor-based re-
RP irrespective of the number of DG units connected. closer, that is capable of communicating with DG, can adap-
of the 50 element can be based either on faults currents calcu- tively change its settings online in accordance with different DG
lated without considering DG contribution or on faults currents configurations.
674 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 28, NO. 2, APRIL 2013

Fig. 7. Adaptive algorithm for modifying of the instantaneous element when a DG unit is connected or disconnected from the network.

B. Adaptive Algorithm fuse are noted. The same step is repeated with all DG units
connected, and the fault location farthest from the fuse
To enable the 50 element to adaptively modify its ,a end of the feeder, where it is not possible to have a CTI of
novel algorithm is developed that can be programmed into the 100 ms with a 51 element, is selected as an RP. In the test
recloser control logic along with some essential data that can be system in Fig. 2, RP is 25% of the feeder LF1-1 length
stored into a database. The algorithm is shown in Fig. 7 in the and acts as a basis for selecting of the 50 element.
form of a flowchart. In the flowchart, and stand for the b) Similarly, fault currents at the reference point are calcu-
number of DG units connected at DG1 and DG2, respectively. lated for different values of and . For each value of
stands for the reference of the 50 element. is , will be based on the fault current at the reference
calculated on the basis of the fault currents that result from an point when 0. In the test system, for example,
LLL fault at 25% of the feeder LF1-1 length (RP) for different 1290 A when 0, and 1365 A when 1 as
combinations of and . It can have four different values de- shown in Fig. 7. The 50-element pickup current is set to
pending upon values of while 0. is a change in the be equal to when 0.
fault current flowing through the recloser R3 in case of faults c) As increases, the fault current level changes (reduces
at the feeder LF1-1 when a single DG unit is connected or dis- on the feeder LF1-1 as seen by the recloser R3 in the test
connected at DG2; its value is different for different combina- system in Fig. 2) and accordingly the pickup current of
tions of and . stands for of the 50 element when the 50 element needs to be adjusted. When the value of
and , subscripts , , , and are defined on the changes, of the 50 element is reset adaptively by
basis of for various combinations of and . finding the corresponding reduction or increase in utility
The data that are required to be stored into a database in- fault current contribution flowing through the re-
clude different possible values of and . To implement closer R3 in case of an LLL fault occurring at the RP and
this algorithm, a communication link is necessary between the then by deducting or adding it from the reference setting,
recloser and various DG units so that the former can update (i.e., ). Thus, when a DG unit is connected or discon-
its setting when the latter are connected or disconnected from nected at DG2, of the 50 element also decreases
the network. This would require modern reclosers with suitable or increases accordingly. Fig. 7 suggests suitable values
remote communication capabilities.. With these arrangements, of for the test system that were determined based on
DG units can be treated as plug-and-play devices. fault analysis results.
1) Description of the Algorithm: Fig. 8 shows the new TCC for the 50 and 51 elements of the
a) Through fault analysis of the test system, fault currents recloser R3 of the test system obtained in accordance with the
due to an LLL fault at different lengths of the feeder LF1-1 proposed algorithm for the cases when 0 and 0 or
with no DG connection (i.e., 0 and 0) are found 10, and when 3 and 0 or 5. As can be noticed from
and corresponding operating times of the 51 element and these figures, of the 50 element will be different for each
HUSSAIN et al.: ADAPTIVE RELAYING SCHEME FOR FUSE SAVING IN DISTRIBUTION NETWORKS 675

Fig. 9. Operating time of the recloser R3 with the modified settings and MMT
of the fuse F2 for an LLL fault at 10% of the feeder LF1-1 length when 3
and 10. “1f” and “1” stand for the recloser’s fast and slow characteristics
curves, respectively, while “2” represents the fuse characteristics curve.

Fig. 8. Proposed TCC for the recloser instantaneous and time OC elements
when 0 and 0 or 10, and when 3 and 0 or 5. “1f”
and “1s” stand for the fast and slow characteristic curves of the recloser 51 OC
element while “5,” represents the fuse characteristic curve.

of these cases (i.e., it changes according to the values of and


). It will be 1290A when 0 and 0 while it will be
1095A when 0 and 10. Similarly, it will be 1500A
when 3 and 0 while it will be 1370A when 3
and 5.
To evaluate the effectiveness of the proposed scheme, an LLL
close-in fault and an LLL fault at 10% of the feeder LF1-1 Fig. 10. of the 50 and 51 elements of the recloser and MMTs of the fuse
for an LLL fault at the reference point when 3 while varies from 0 to
length, were modelled with the recloser R3 settings modified in
10.
accordance with the proposed algorithm when 3 and
10. Both of the faults were cleared by the recloser 50 element
with a CTI of 85 ms and 115 ms, respectively. The simulation be disconnected under abnormal system conditions so that its
results for the 10% case are shown in Fig. 9. fault contribution cannot disturb existing protection coordina-
Fig. 10 shows the fault currents and corresponding of tion [25]. When DG2 is separated from the network, a reclosing
the 50 and 51 elements, and MMT of the fuse in case of an LLL attempt will be made by the fast curve of recloser R3 to re-
fault at the RP when 3 and 10. For the results shown store the supply. To ensure that the reclosing is successful, in-
in the figure, the settings of the 50 element were obtained by im- stead of an instantaneous reclosing attempt, delayed reclosing
plementing the proposed algorithm in Matlab while the required is recommended (i.e., an increase of the reclose interval from
input data for the algorithm were found by simulating an LLL the usual 300 ms to 1 s should be considered). If this attempt is
fault at the RP with 3 and 10. Thus, from the results successful, DG2 will be reconnected to the system with proper
presented in Figs. 9 and 10, it is clear that the proposed algo- synchronization. If the attempt is unsuccessful, then if the fault
rithm is valid and the recloser with that is modified in is at the feeder LF1-1, it will be cleared by the fuse. If it is at
accordance with the proposed algorithm can ensure fuse saving the feeder LF1, then it will be cleared by the recloser R3 slow
with an acceptable time margin in the presence of DG even in curve. When the recloser R3 closes for the first time and the fault
the worst fault conditions. is cleared, its settings will be updated according to the value of
at DG1, with 0. When, subsequently, DG2 units are
V. HOW RECLOSING WILL BE APPLIED reconnected, the pickup current of the 50 element will be read-
justed according to the proposed algorithm.
Ideally, whenever the recloser R3 operates due to a trigger
from either the 51 or the 50 elements, a trip signal should be
sent simultaneously to the recloser R2 to disconnect DG2 from VI. OBSERVATIONS
the network to avert formation of an undesirable island. This is Although the protection strategy is described for a particular
in accordance with IEEE standard 1547 that requires the DG to network, it may be successfully applied to restore RFC in other
676 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 28, NO. 2, APRIL 2013

networks. The algorithm for adaptively changing of a re- TABLE I


closer in response to the varying network configuration can be CURRENT SETTINGS OF THE PROTECTION DEVICES INSTALLED
IN THE TEST SYSTEM SHOWN IN FIG. 2
derived by following the method introduced in Section IV. The
authors are working on some other sample networks to gener-
alize the application of the proposed scheme, and the results will
be published in future publications.
The proposed algorithm is based on the magnitude of the fault
current and is independent of the fault type. The fault current
magnitude, irrespective of the nature of the fault, which is most
to varying network configurations (due to connection and dis-
likely to cause the RF miscoordination, is used as the basis for
connection of DG units), to ensure fuse saving in the presence
setting of the 50 element. In the system under study,
of DG.
the maximum fault current that causes RF miscoordination, is
due to an LLL fault, so it is used as a reference in the proposed
APPENDIX
scheme. Since an instantaneous relay can be set to operate in less
than a cycle (15 ms in our study), the proposed scheme should Impedances of feeders and Sub-TLs of the test system are
be equally effective for synchronous and induction generators- shown in Fig. 2.
based DG.
The working of the proposed strategy is examined when
the contribution from DG is high compared to the grid source,
which will be very rare, as discussed earlier. This is because
protection design needs to be performed for the worst case
scenario. Moreover, in the future, as DG becomes more wide-
spread, there may be situations where DG outstrips the supply
from the utility substation. RF miscoordination also occurs where B stands for line charging.
in the test system even when the DG capacity is less than or
equal to the utility supply substation and can be restored by the REFERENCES
proposed scheme.
[1] P. M. Anderson, Power System Protection. New York: IEEE, 1998.
Protection schemes requiring communication links between [2] R. C. Dugan and D. T. Rizy, “Electric distribution protection prob-
various protection devices are unpopular due to their high cost. lems associated with the interconnection of small, dispersed genera-
tion devices,” IEEE Trans. Power App. Syst., vol. PAS-103, no. 6, pp.
However, by making use of low-cost wireless communication
1121–1127, Jun. 1984.
channels, which are now commercially available, such schemes [3] A. A. Girgis and S. M. Brahma, “Effect of distributed generation on
may be implemented in a cost-effective manner. Moreover, mul- protective device coordination in distribution system,” in Proc. Large
Eng.Syst. Conf. Power Eng., Halifax, NS, Canada, 2001, pp. 115–119.
tifunctional microprocessor-based reclosers are already in use
[4] N. Hadjsaid, J. F. Canard, and F. Dumas, “Disperse generation impact
for power system protection. So this scheme could be prac- on distribution network,” IEEE Compu. Appl. Power, vol. 12, no. 2,
tical and may be successfully implemented in the actual power pp. 22–28, Apr. 1999.
[5] Y. Lu, L. Hua, J. Wu, G. Wu, and G. Xu, “A study on effect of dispersed
networks.
generator capacity on power system protection,” in Proc. IEEE Power
Eng. Soc. Gen. Meeting, 2007, pp. 1–6.
[6] S. Chaitusaney and A. Yokoyama, “Prevention of reliability degrada-
VII. CONCLUSION tion from recloser-fuse miscoordination due to distributed generation,”
IEEE Trans. Power Del., vol. 23, no. 4, pp. 2545–2554, Oct. 2008.
Recloser-fuse coordination designed for fuse saving in a dis- [7] A. Farzanehrafat, S. A. M. Javadian, S. M. T. Bathaee, and M.-R.
tribution network may be lost when DG is connected to that net- Haghifam, “Maintaining the recloser-fuse coordination in distribution
systems in presence of dg by determining dg’s size,” in Proc. 9th IET
work, as observed in the case study. To restore this coordination Int. Conf. Develop. Power Syst. Protect., 2008, pp. 124–129.
in the case of a typical DN with DG connection, use of a re- [8] S. M. Brahma and A. A. Girgis, “Impact of distributed generation
closer having a 50 element along with a 51 element is shown on fuse and relay coordination: Analysis and remedies,” in Proc.
IAESTED Int. Conf. Power Energy Syst., 2001, pp. 384–389.
to be a valid solution as either of them used alone has its lim- [9] H. H. Zeineldin and E. F. El-Saadany, “Fault current limiters to
itations. To this end, replacement of the existing recloser with mitigate recloser fuse miscoordination with distributed generation,” in
a multifunction microprocessor-based recloser having commu- Proc. 10th Inst. Eng. Technol. Int. Conf. Develop. Power Syst. Protect.
Managing the Change, Manchester, U.K., 2010, pp. 1–4.
nication capabilities is recommended. Moreover, it may not be [10] J. F. Witte, S. R. Mendis, M. T. Bishop, and J. A. Kischefsky, “Com-
possible to ensure fuse saving with different DG sizes and con- puter-aided recloser applications for distribution systems,” IEEE
figurations if the 50 element has a fixed . To compensate Comput. Appl. Power, vol. 5, no. 3, pp. 27–32, Jul. 1992.
[11] Working Group D3, “Impact of distributed resources on distribution
for this, a novel algorithm is proposed for an online adaptive relay protection, A (special) report to the Line Protection Subcom-
change of of the 50 element in response to different DG mittee of the Power System Relay Committee of the IEEE Power Eng.
configurations. The simulation results, obtained by adaptively Soc.” Aug. 2004.
[12] S. M. Brahma and A. A. Girgis, “Microprocessor-based reclosing to
changing relay settings in response to changing DG configura- coordinate fuse and recloser in a system with high penetration of dis-
tions, confirm that the settings selected theoretically hold well tributed generation,” in Proc. IEEE Power Eng. Soc. Winter Meeting,
in operation. The proposed scheme combines the characteristics 2002, vol. 1, pp. 453–458.
[13] A. Zamani, T. Sidhu, and A. Yazdani, “A strategy for protection coor-
of both the 51 and 50 elements, along with a novel algorithm, for dination in radial distribution networks with distributed generators,” in
adaptively changing the setting of the 50 element, in response Proc. IEEE Power Energy Soc. Gen. Meeting, 2010, pp. 1–8.
HUSSAIN et al.: ADAPTIVE RELAYING SCHEME FOR FUSE SAVING IN DISTRIBUTION NETWORKS 677

[14] C. McCarthy, R. O’Leary, and D. Staszesky, “A new fuse-saving phi- S. M. Sharkh received the B.Eng. and Ph.D. degrees
losophy,” in Proc. DistribuTECH, Tampa, FL, Jan. 2008, pp. 1–7. in electrical engineering from the University of
[15] M. Baran and I. El-Markabi, “Adaptive over current protection for dis- Southampton, Southampton, U.K., in 1990 and
tribution feeders with distributed generators,” in Proc. IEEE/Power 1994, respectively.
Eng. Soc. Power Syst. Conf. Expo., 2004, vol. 2, pp. 715–719. Currently, he is a Senior Lecturer and the Head
[16] A. Conde and E. Vazquez, “Operation logic proposed for time overcur- of the Electro-Mechanical Research Group at the
rent relays,” IEEE Trans. Power Del., vol. 22, no. 4, pp. 2034–2039, University of Southampton. He is also the Managing
Oct. 2007. Director of HiT Systems Ltd., Southampton. He
[17] N. Schaefer, T. Degner, A. Shustov, T. Keil, and J. Jaeger, “Adaptive has published many papers in academic journals
protection system for distribution networks with distributed energy re- and conferences. His main research interests are in
sources,” in Proc. 10th Inst. Eng. Technol. Int. Conf. Develop. Power the areas of control, electrical machines, and power
Syst. Protect., Managing the Change, Manchester, U.K., 2010, pp. 1–5. electronics with applications to electric vehicles and distributed generation.
[18] S. M. Brahma and A. A. Girgis, “Development of adaptive protection Dr. Sharkh is a member of the Institute of Engineering and Technology and a
scheme for distribution systems with high penetration of distributed Chartered Engineer. He was the 2008 winner of The Engineer Energy Innova-
generation,” IEEE Trans. Power Del., vol. 19, no. 1, pp. 56–63, Jan. tion Award for his work on rim-driven thrusters and marine turbine generators.
2004.
[19] S. A. M. Javadian, M. R. Haghifam, and P. Barazandeh, “An adaptive
over-current protection scheme for MV distribution networks including
DG,” in Proc. IEEE Int. Symp. Ind. Electron., Cambridge, U.K., 2008, S. Hussain received the B.Sc. and M.Sc. degrees in
pp. 2520–2525. electrical engineering from the UET, Lahore, Pak-
[20] F. A. Viawan, D. Karlsson, and A. Sannino et al., “Protection scheme istan, in 1992 and 2000, respectively.
for meshed distribution systems with high penetration of distributed He was a Senior Electrical Engineer at NTDC
generation,” in Proc. Power Syst. Conf.: Adv. Metering, Protect., Con- (WAPDA), Lahore, Pakistan, until he joined the
trol, Commun., Distrib. Resources, 2006, pp. 99–104. Hatch, Mississauga, ON, Canada as a Senior Su-
[21] K. Tuitemwong and S. Premrudeepreechacharn, “Expert system for pervising Engineer. He has more than 19 years
protection coordination of distribution system with distributed gener- of experience in the electric power industry. His
ators,” Int. J. Elect. Power Energy Syst., vol. 33, no. 3, pp. 466–471, research focus is on power system protection and
2011. control.
[22] H. Wan, K. K. Li, and K. P. Wong, “An adaptive multiagent approach to
protection relay coordination with distributed generators in industrial
power distribution system,” IEEE Trans. Ind. Appl., vol. 46, no. 5, pp.
2118–2124, Sep./Oct. 2010.
[23] E. P. Dick and A. Narang, Canadian Urban Benchmark Distribution M. A. Abusara received the B.Eng. degree in elec-
Systems NR, Canada, 2005-121, 2005. trical engineering from Birzeit University, Palestine,
[24] IEEE Standard Electrical Power System Device Function Numbers, in 2000 and the Ph.D. degree in electrical engineering
IEEE Standard C37.2-1987, 1987, pp. 0–1. from the University of Southampton, Southampton,
[25] IEEE Standard for Interconnecting Distributed Resources with Electric U.K., in 2004.
Power Systems, IEEE Standard 1547-2003, Jul. 2003. Currently, he is a Lecturer in Renewable Energy at
the University of Exeter, Penryn Cornwall, U.K. He
B. Hussain received the B.Sc. degree in electrical has more than ten years of industrial experience with
engineering from the University of Engineering and Bowman Power Group, Southampton, in the field of
Technology, Taxila, Pakistan, in 1995 and the Ph.D. research and development of digital control of power
degree in electrical engineering from the University electronics. During his years in the industry, he de-
of Southampton, Southampton, U.K., in 2011. signed and prototyped a number of commercial products that include grid- and
He has more than ten years of experience in the parallel-connected inverters, microgrid, dc/dc converters for hybrid vehicles,
electric power sector. His major research interests and sensorless drives for high-speed permanent-magnet machines.
include protection of distribution networks with
distributed generation, power quality, and control of
grid-connected inverters.

You might also like