You are on page 1of 6

DEWATERING REPORT

BUILDING CONSTRUCTION

 SHEET 1 - INTRODUCTION
 SHEET 2 - SUMP PUMPING
 SHEET 3 - HORIZONTAL WELLPOINT AND DEEP WELL
 SHEET 4 - WELLPOINT SYSTEM
 SHEET 5 - EDUCTOR WELL AND RELIEF WELL

MANAS ARORA
3RD YEAR – B
ROLL NO. 3
VASTU KALA ACADEMY
WHICHEVER METHOD IS USED, THE EFFECT IS BROADLY THE
WHERE DOES WATER ACCUMULATE?
SAME, CREATING A CONE OF DEPRESSION IN THE WATER
• THE TOP TWO REASONS FOR WATER ACCUMULATION ARE TABLE, CENTRED ON THE EXCAVATION
1. RAIN
2. HIGH WATER TABLE
• IN CONSTRUCTION SITES, WATER CAN ACCUMULATE IN
EXCAVATIONS AND TRENCHES, IN SLOPED AREAS, OR IF THE SITE
IS NOT LOCATED WITHIN AN AREA WITH A LOW WATER TABLE
• ACCUMULATED WATER CAN BE A THREAT TO THE SAFETY OF
WORKERS WHO MAY SLIP AND INJURE THEMSELVES
WHAT IS DEWATERING?
PRECAUTIONS DURING DEWATERING
• THE PROCESS OF DEWATERING CAN BE DEFINED AS – PUMPING
FROM WELLS OR SUMPS TO TEMPORARILY LOWER GROUNDWATER • THE QUICKEST WAY TO REMOVE ACCUMULATED WATER FROM A
LEVELS, TO ALLOW EXCAVATIONS TO BE MADE IN DRY AND STABLE CONSTRUCTION SITE IS THROUGH THE USE OF PUMPS
CONDITIONS BELOW NATURAL GROUNDWATER LEVEL • HOWEVER, DEWATERING IS NOT SIMPLY SUBMERGING THE
• TO DEWATER MEANS TO REMOVE WATER FROM AN AREA. PUMP IN THE AFFECTED AREA AND LETTING THE WATER OUT
• IT IS USUALLY DONE AT A CONSTRUCTION SITE TO REMOVE SURFACE SOMEWHERE ELSE
WATER OR GROUNDWATER FROM IT. • THERE ARE PRECAUTIONS THAT MUST BE FOLLOWED TO ENSURE
• ON CONSTRUCTION SITES IT MAY BE KNOWN AS ‘CONSTRUCTION THAT SOIL EROSION AND OTHER PROBLEMS ARE AVOIDED
DEWATERING’. THE METHOD IS ALSO USED ON MINE SITES – • ONE OF THE CONSIDERATIONS THAT BUILDERS HAVE TO KEEP IN
‘MINE DEWATERING’ MIND IS THAT THE LOCATION FOR THE DISCHARGED WATER
MUST BE CAREFULLY SELECTED.
PURPOSE OF DEWATERING IN MOST NATURAL SYSTEMS, WHERE GROUNDWATER CAN
OTHER APPLICATIONS FLOW MORE EASILY IN SOME DIRECTIONS THAN OTHERS, THE
• DURING CONSTRUCTION STAGE:- CONE OF DEPRESSION WILL NOT BE A SYMMETRICAL FEATURE
1. DRY EXCAVATION. • DEWATERING IS ALSO DONE IN MINING EXCAVATIONS, THAT IS CIRCULAR IN PLAN. RATHER, IT WILL BE IRREGULAR,
2. PROCEED EFFICIENTLY. PARTICULARLY IN ROCK MINES AND BORROW PITS EXTENDING MUCH FURTHER IN SOME DIRECTIONS THAN
• IT IS ALSO CONDUCTED IN LAKE EXCAVATIONS FOR MAKING OTHERS. IN SUCH CIRCUMSTANCES IT CAN MORE USEFULLY BE
3. REDUCE LATERAL LOADS.
STORMWATER MANAGEMENT SYSTEMS REGARDED AS A ZONE OF INFLUENCE OF DEWATERING,
4. IMPROVE CHARACTERISTICS OF FOUNDATION MATERIALS. • INSTALLATION OF UTILITY LINES SUCH AS SEWERS, WATER,
5. INCREASE STABILITY OF SLOPES AND SIDE-HILL FILLS. RATHER THAN A SIMPLE CONE OF DEPRESSION.
TELEPHONE, AND ELECTRICITY ALSO REQUIRES DEWATERING
6. PREVENT PIPING AND FROST HEAVING IN PAVEMENTS.
WATER CONTAMINATION
SPECIFICATIONS:
• POST CONSTRUCTION STAGE :-
1. REDUCE UPLIFT PRESSURES ON BOTTOM SLABS. • DEWATERING AT A CONSTRUCTION SITE INVOLVES THE
• DEWATERING EXCAVATED AREAS MUST BE IN TWO DISTINCT RISK OF WATER BEING CONTAMINATED WITH GREASE AND
2. REDUCE LATERAL PRESSURES ON RETAINING STRUCTURES. PHASES; OIL
3. CONTROL EMBANKMENT SEEPAGE IN ALL DAMS. (1) THE REMOVAL OF THE COLLECTED WATER WITHIN THE • WATER CONTAMINATED WITH INDUSTRIAL GREASE MUST
EXCAVATION. NEVER BE DISCHARGED INTO THE ENVIRONMENT
TYPES OF (2) THE TREATMENT OF THE COLLECTED WATER. BECAUSE IT MAY DAMAGE THE SOIL AND THE
DEWATERING SURROUNDING AREAS THAT HAVE VEGETATION.
• IF THE ACCUMULATED WATER IS CONTAMINATED, AN OIL
AND WATER SEPARATOR MUST FIRST BE USED
• ONCE SEPARATED, THE WATER CAN BE DISCHARGED AND
SUMP HORIZONTAL WELLPOINT THE OIL CAN BE DISPOSED OF PROPERLY FOLLOWING THE
DEEP WELL EDUCTOR WELL RELIEF WELL
PUMPING WELLPOINT SYSTEM REGULATIONS

SHEET NO. SIGNATURE :


MANAS ARORA
DEWATERING BUILDING
CONSTRUCTION
1
3RD YEAR - B
VASTU KALA ACADEMY
SUMP PUMPING
• THE SIMPLEST FORM OF DEWATERING IS SUMP PUMPING, WHERE GROUNDWATER IS ALLOWED TO
ENTER THE EXCAVATION WHERE IT IS THEN COLLECTED IN A SUMP AND PUMPED AWAY BY ROBUST
SOLIDS HANDLING PUMPS.
• WATER IS COLLECTED IN DEEPER PARTS OF THE EXCAVATION (CALLED SUMPS) AND PUMPED AWAY.
• SIMPLE AND CHEAP METHOD OF DEWATERING IN FAVOURABLE GROUND CONDITIONS.
• LIMITED TO USE IN RELATIVELY COARSE SOILS OR FISSURED ROCK – IF USED IN FINE GRAINED SOILS CAN
LEAD TO EROSION AND LOSS OF FINES WITH THE RISK OF RESULTING INSTABILITY.
• THE SUMP TAKES UP SPACE WITHIN AN EXCAVATION .
• CAN LEAD TO WATER POLLUTION PROBLEMS DUE TO SILT-LADEN WATER.
TWO SIMPLE SUMPING DETAILS ARE SHOWN IN ABOVE FIGURES

GREATEST DEPTH TO WHICH THE WATER TABLE CAN BE LOWERED BY THIS


METHOD IS ABOUT 8 M BELOW THE PUMP.

• ADVANTAGES: • DISADVANTAGES:
• A SUMP IS MERELY A HOLE IN THE GROUND FROM WHICH WATER IS BEING PUMPED FOR THE PURPOSE OF
1. WIDELY USED METHOD. 1. DUE TO MORE FLOW OF GW TOWARDS
REMOVING WATER FROM THE ADJOINING AREA.
2. MOST ECONOMICAL METHOD FOR EXCAVATION RISK OF COLLAPSE OF SIDES
• THEY ARE USED WITH DITCHES LEADING TO THEM IN LARGE EXCAVATIONS.
INSTALLATION AND MAINTENANCE. OCCURS.
• UP TO MAXIMUM OF 8M BELOW PUMP INSTALLATION LEVEL; FOR GREATER DEPTHS A SUBMERSIBLE PUMP
3. CAN BE APPLIED FOR MOST SOIL AND ROCK 2. IN OPEN OR TIMBERED EXCAVATIONS THERE
IS REQUIRED.
CONDITIONS. IS RISK OF INSTABILITY OF THE BASE DUE TO
• SHALLOW SLOPES MAY BE REQUIRED FOR UNSUPPORTED EXCAVATIONS IN SILTS AND FINE SANDS. GRAVELS
4. MOST APPROPRIATE WHERE BOULDERS OR SEEPAGE TOWARDS PUMPING SUMP.
AND COARSE SANDS ARE MORE SUITABLE.
MASSIVE OBSTRUCTIONS ARE MET WITH IN
• FOR PROLONGED PUMPING THE SUMP SHOULD BE PREPARED BY FIRST DRIVING SHEETING AROUND THE
THE GROUND.
SUMP AREA FOR THE FULL DEPTH OF THE SUMP AND INSTALLING A CAGE INSIDE THE SUMP MADE OF WIRE
MESH WITH INTERNAL STRUTTING OR A PERFORATING PIPE FILLING THE FILTER MATERIAL IN THE SPACE
OUTSIDE THE CAGE AND AT THE BOTTOM OF THE CAGE AND WITHDRAWING THE SHEETING.

SHEET NO. SIGNATURE :


MANAS ARORA
DEWATERING BUILDING
CONSTRUCTION
2
3RD YEAR - B
VASTU KALA ACADEMY
HORIZONTAL WELLPOINT
• HORIZONTAL WELLS FOR DEWATERING ARE OF TWO PRINCIPAL TYPES:
1. HORIZONTAL DRAINS INSTALLED BY SPECIALIST TRENCHING MACHINES.
2. HORIZONTALLY DIRECTIONALLY DRILLED (HDD) WELLS.
• HORIZONTAL DRAINS INSTALLED BY SPECIALIST TRENCHING MACHINES
1. THIS TECHNIQUE USES A HORIZONTAL FLEXIBLE PERFORATED PIPE, PUMPED BY A WELLPOINT PUMP, TO LOWER
GROUNDWATER LEVELS.
2. THE PERFORATED PIPE IS INSTALLED BY A SPECIAL TRENCHING MACHINE.
3. ONE END OF THE PIPE IS UNPERFORATED AND IS BROUGHT TO THE SURFACE AND CONNECTED TO A WELLPOINT
SUCTION PUMP.
4. THE METHOD CAN BE VERY EFFECTIVE FOR DEWATERING LONG PIPELINE EXCAVATIONS.
• HORIZONTALLY DIRECTIONALLY DRILLED (HDD) WELLS.
1. HDD WELLS ARE USED WHERE GROUNDWATER MUST BE ABSTRACTED FROM BENEATH INACCESSIBLE AREAS OR FROM
AREAS WHERE THE DISRUPTION ASSOCIATED WITH SURFACE DRILLING IS UNDESIRABLE.
• THIS METHOD IS MORE CONVENIENT FOR THE CASE OF FISSURED ROCKS. THE WATER COLLECTED BY THE HORIZONTAL WALLS IS
PUMPED OUT OF THE SHAFT TO THE GROUND LEVEL WITH A RATE THAT GUARANTEES A WATER SURFACE BELOW THE DESIRED
LEVEL.
• DRAWDOWN IS LIMITED TO 5 OR 6 M BELOW LEVEL OF PUMP DUE TO SUCTION LIFT LIMITS.
DEWATERING BY HORIZONTAL WELLS

DEEP WELL
• WELLS ARE DRILLED AT WIDE SPACING (10 TO 60 M BETWEEN
WELLS) TO FORM A RING AROUND THE OUTSIDE OF THE EXCAVATION
• AN ELECTRIC SUBMERSIBLE PUMP IS INSTALLED IN EACH WELL.
DRAWDOWN LIMITED ONLY BY WELL DEPTH AND SOIL
STRATIFICATION
• SEVERAL WELLS ACTING IN COMBINATION CAN LOWER
GROUNDWATER LEVEL OVER A WIDE AREA BENEATH AN EXCAVATION.
• BECAUSE THE TECHNIQUE DOES NOT OPERATE ON A SUCTION
PRINCIPLE, LARGE DRAWDOWNS CAN BE ACHIEVED, LIMITED ONLY BY
THE DEPTH OF THE WELLS, AND THE HYDROGEOLOGICAL DEWATERING BY DEEP WELLS
CONDITIONS.
• THE WELLS ARE GENERALLY SITED JUST OUTSIDE THE AREA OF
PROPOSED EXCAVATION, AND ARE PUMPED BY ELECTRIC
SUBMERSIBLE PUMPS NEAR THE BASE OF EACH WELL. WATER
COLLECTION PIPES, POWER SUPPLY GENERATORS, ELECTRICAL
CONTROLS AND MONITORING SYSTEMS ARE LOCATED AT THE
SURFACE.
• EFFECTIVE IN A WIDE RANGE OF GROUND CONDITIONS, SANDS,
GRAVELS, FISSURED ROCKS
CONSTRUCTION OF DEEP WELLS

SHEET NO. SIGNATURE :


MANAS ARORA
DEWATERING BUILDING
CONSTRUCTION
3
3RD YEAR - B
VASTU KALA ACADEMY
WELLPOINT SYSTEM
• A LINE OR RING OF SMALL DIAMETER SHALLOW WELLS (CALLED
WELLPOINTS) INSTALLED AT CLOSE SPACING (1 TO 3 M CENTRES)
AROUND THE EXCAVATION.
• COMMONLY USED FOR DEWATERING OF PIPELINE TRENCHES
• CAN BE A VERY FLEXIBLE AND EFFECTIVE METHOD OF DEWATERING IN
SANDS OR SANDS AND GRAVELS
• DRAWDOWN LIMITED TO 5 OR 6 M BELOW LEVEL OF PUMP DUE TO
SUCTION LIFT LIMITS
• INDIVIDUAL WELLPOINTS MAY NEED TO BE CAREFULLY ADJUSTED
(“TRIMMING”)

DETAIL OF WELL POINT

• THE SYSTEM CONSISTS OF


VERTICAL WELL POINTS CONNECTED
THROUGH VERTICAL PIPES (RISERS).
• THE RISERS DISCHARGE THEIR WATER IN
HORIZONTAL PIPES CALLED HEADERS. THE
RISER IS SURROUNDED BY A COARSE
SAND FILTER IN ORDER TO FACILITATE THE • ADVANTAGES • DISADVANTAGES
FLOW OF WATER TOWARDS THE WELL 1. INSTALLATION IS VERY RAPID 1. A LOWERING OF ABOUT 6 M IS
POINTS. 2. REQUIRES REASONABLY SIMPLE AND LESS POSSIBLE, BEYOND WHICH EXCESSIVE
DEWATERING OF DEEP EXCAVATION
• THE HEADERS ARE CONNECTED TO THE COSTLY EQUIPMENT AIR REQUIRED, RESULTING IN THE LOSS
PUMP. 3. WATER IS FILTERED HENCE NOT CARRIES SOIL OF PUMPING EFFICIENCY.
• WHEN THE PUMP IS STRATED, THE WATER • WHEN DEWATERING DEPTH GOES BEYOND PARTICLES. 2. IF LARGE GRAVEL, STIFF CLAY OR SOIL
RISES FROM THE WELL POINTS THROUGH 6M, IT IS RECOMMENDED TO CARRY OUT 4. THERE IS LESS DANGER OF SUBSIDENCE OF THE CONTAINING BOULDERS IS AVAILABLE
THE RISERS AND FROM IT TO THE THE WELL POINT METHOD IN PHASES. SURROUNDING GROUND THAN WITH OPEN- THEN IT IS NOT POSSIBLE TO INSTALL
HEADERS AND FINALLY IS DISCHARGED • THE DEEP WELL METHOD CAN ALSO SUMP PUMPING WELL POINTS.
OUTSIDE THE SYSTEM TO COLLECTING SUPPLEMENT THE WELL POINT METHOD
TANKS OR VEHICLES. UNDER SUCH CONDITION.

SHEET NO. SIGNATURE :


MANAS ARORA
DEWATERING TYPES BUILDING
CONSTRUCTION
4
3RD YEAR - B
VASTU KALA ACADEMY
EDUCTOR WELL
• THE SYSTEM WORKS BY CIRCULATING HIGH PRESSURE WATER (FROM A TANK AND SUPPLY
PUMPS AT GROUND LEVEL) DOWN THE WELL TO A SMALL-DIAMETER NOZZLE AND VENTURI
LOCATED IN THE EDUCTOR IN EACH WELL.
• THIS GENERATES A VACUUM OF UP TO 9.5 M OF WATER AT THE LEVEL OF THE EDUCTOR. THE
VACUUM DRAWS GROUNDWATER INTO THE WELL FROM WHERE IT IS PIPED BACK TO GROUND
LEVEL VIA A RETURN RISER PIPE AND THENCE THROUGH THE RESERVOIR TANK BACK TO THE
SUPPLY PUMP FOR RECIRCULATION.
• EDUCTORS ARE TYPICALLY USED TO HELP STABILISE THE SIDE SLOPES AND BASE OF
EXCAVATIONS IN SOILS THAT WOULD BE DIFFICULT TO DEWATER WITH WELLPOINTS OR DEEP
WELLS.
• WELLS ARE DRILLED AROUND OR ALONGSIDE THE EXCAVATION.
• SUITABLE WHEN WELL YIELDS ARE LOW. FLOW CAPACITY 30 TO 50 LITRES/MIN PER WELL.
• DRAWDOWN GENERALLY LIMITED TO 25 TO 30 M BELOW PUMP LEVEL.

• ADVANTAGES • DISADVANTAGES
1. THEY ARE FLEXIBLE IN LEVEL AND LAYOUT 1. DRAWDOWN GENERALLY LIMITED TO 25
2. STABLE IN OPERATION TO 30 M BELOW PUMP LEVEL.
3. ABLE TO RUN DRY WITHOUT DAMAGE 2. SOME GROUTS ARE ONLY ABLE TO
4. NOT LIMITED BY DEPTH. ALSO EFFECTIVE REDUCE THE PERMEABILITY OF THE SOIL
TO GREATER DEPTHS BUT WILL NOT INCREASE THE SOIL’S
5. BEST IN LOW-YIELDING WELLS STABILITY.
6. ENERGY INTENSIVE
7. VENTURI IN BASE OF WELL CREATES
VACUUM

RELIEF WELL
• RELIEF WELLS (ALSO KNOWN AS PRESSURE RELIEF WELLS
OR BLEED WELLS) ARE USED TO REDUCING PORE WATER
PRESSURES IN CONFINED AQUIFERS OR IN STRATIFIED
GROUND CONDITIONS.
• THE RELIEF WELLS ARE TYPICALLY DRILLED BEFORE THE
EXCAVATION HAS EXTENDED BELOW THE PIEZOMETRIC
LEVEL IN THE AQUIFER.
• AS EXCAVATION CONTINUES, THE WELLS WILL BEGIN TO
OVERFLOW, RELIEVING PORE WATER PRESSURES IN THE
AQUIFER AND ENSURING STABILITY.
• THE WATER FLOWING FROM THE RELIEF WELLS IS
TYPICALLY DISPOSED OF BY SUMP PUMPING.
• A GRANULAR DRAINAGE BLANKET AND NETWORK OF
DRAINS CAN BE USED TO DIRECT WATER TO THE SUMPS RIGHT: A DEWATERING SYSTEM REDUCES THE GROUNDWATER UPLIFT
AND PREVENT PONDING IN THE EXCAVATION. PRESSURE TO LESS THAN THE WEIGHT OF THE OVERLYING SOIL, SO
PREVENTING GROUND HEAVE.

SHEET NO. SIGNATURE :


MANAS ARORA
DEWATERING TYPES BUILDING
CONSTRUCTION
5
3RD YEAR - B
VASTU KALA ACADEMY

You might also like