Blk 5 – Fwd leg Well (CFE)

Look Ahead:
Description Start Finish

Fabrication 15-Oct-14 15-Jan-15

Assembly 01-Dec-14 14-Apr-15

Blast/Paint 15-Apr-15 15-May-15

Erection 16-May-15 08-Jun-15

Fabricate Assembly / Install

Disciplines Denominator Total Actual Actual Quantity Actual Quantity


Plan % Plan % Actual %
%
IP C IP C

Panels 56 0% 0% 0 0 0% 0% 0 0

Structural Steel Outfit


Number by 0% 0% 0 0 0% 0% 0 0
Drawing

Piping Pipe Spools 0% 0% 0 0 0% 0% 0 0

E&I Supports / MCT 0% 0% 0 0 0% 0% 0 0

Painting - - Plan: 0 % Actual: 0 % 12