EQUIPMENT
1. PLC.
2. USB wire connection PLC and computer.
3. Power supply to the PLC.
4. Computer.
5. Simatic Manager ( PLC Programming Software)
6. Lamp
SCHEMATIC DIAGRAM
S1 Switch 1
S2 Switch 2
Lamp Output device
3. AND before OR operation 4. OR before AND operation
S1 Switch 1
S2 Switch 2
S3 Switch 3
S4 Switch 4
Lamp Output device
PLC PROGAMMING
Explanations:
RESULT
Switch 1 Switch 2 Output
0 0 0
1 0 0
0 1 0
1 1 1
Task 2: OR operation
LAD (Ladder Diagram)
Explanation:
Explanation:
for E124.1, S4 is switch for E124.3, and L stand for A124.4 is output
device (lamp). As we can see, when we switch on switch S1 and S2,
the lamp will turn on automatically. This is because the electricity can
flow trough the circuit that we create on PLC programming. When we
turn on S3 switch and S4 switch, the lamp also produce the same
result like the statement below.
2. When we turn switch S1 and S4, there no action happen on the output
Explanation:
3. When we turn switch S1 and S4, the lamp will switch on. This is
because there has connection between this switch on the circuit that
we program on programming. When we turn S2 and S3, same result
will happen like the above statement.
RESULT
Switch 1 Switch 2 Switch 3 Switch 4 Output
0 0 0 0 0
1 0 0 0 0
0 1 0 0 0
0 0 1 0 0
0 0 0 1 0
1 0 1 0 1
0 1 0 1 1
1 1 0 0 1
0 1 0 1 1
1 1 1 1 1
CONCLUSION