ID Task Name Duration Start Finish Dec '15 Jan '16

1 WELENCHITI TOWN CRUSH PROGRAM 124 days Mon 22-01-18 Thu 12-07-18
2 Bill No 03: Pipes & fittings 108 days Tue 13-02-18 Thu 12-07-18
3 1) Supply and installation of pipes and fittings for transmission main 103 days Mon 29-01-18 Wed 20-06-18
4 1.1)Transmission main 35 days Mon 26-02-18 Fri 13-04-18
5 Supply and installation of DCI pipes and fittings. 15 days Mon 26-02-18 Fri 16-03-18
6 Supply and installation of fittings for the remaining activities 15 days Mon 26-02-18 Fri 16-03-18
7 Supply of materials and installation in valve chamber 32 days Thu 01-03-18 Fri 13-04-18
8 Construction of concrete valve chamber 32 days Thu 01-03-18 Fri 13-04-18
9 Gully crossings 32 days Thu 01-03-18 Fri 13-04-18
10 Construction of C-20 reinforced concrete support columns 32 days Thu 01-03-18 Fri 13-04-18
11 Trust and anchor blocks 32 days Thu 01-03-18 Fri 13-04-18
12 C20 concrete trust blocks 32 days Thu 01-03-18 Fri 13-04-18
13 Pressure test and desinfection 32 days Thu 01-03-18 Fri 13-04-18
14 Pressure test and desinfection of pipelines 32 days Thu 01-03-18 Fri 13-04-18
15 1.2) New rising main from New borehole site to DC 69 days Mon 29-01-18 Thu 03-05-18
16 Supply and installation of DCI pipes and fittings. 40 days Mon 19-02-18 Fri 13-04-18
17 Supply and installation of fittings. 40 days Mon 19-02-18 Fri 13-04-18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 1
ID Task Name Duration Start Finish Dec '15 Jan '16
18 Supply of materials and installation in valve chamber 32 days Mon 19-03-18 Tue 01-05-18
19 Construction of concrete valve chamber 32 days Mon 19-03-18 Tue 01-05-18
20 Gully crossings 17 days Mon 09-04-18 Tue 01-05-18
21 Construction of C-20 reinforced concrete support columns 17 days Mon 09-04-18 Tue 01-05-18
22 Trust and anchor blocks 49 days Mon 26-02-18 Thu 03-05-18
23 C20 concrete trust blocks 32 days Mon 26-02-18 Thu 03-05-18
24 Pressure test and desinfection 60 days Mon 29-01-18 Fri 20-04-18
25 Pressure test and desinfection of pipelines 60 days Mon 29-01-18 Fri 20-04-18
26 construction of valve chamber with concrete manhole cover 55 days Mon 12-02-18 Fri 27-04-18
27 Construction of C-15 reinforced concrete valve chamber 55 days Mon 12-02-18 Fri 27-04-18
28 1.3) Gravity main for direct supply to Feto satelite village 69 days Mon 29-01-18 Thu 03-05-18
29 Supply, and installation of HDPE pipes and Fittings 69 days Mon 29-01-18 Thu 03-05-18
30 Supply and installation of remaining fittings 10 days Mon 19-02-18 Fri 02-03-18
31 Supply of materials and installation in valve chamber 32 days Mon 19-03-18 Tue 01-05-18
32 Construction of concrete valve chamber 32 days Mon 19-03-18 Tue 01-05-18
33 Gully crossings 17 days Mon 09-04-18 Tue 01-05-18
34 Construction of C-20 reinforced concrete support columns 17 days Mon 09-04-18 Tue 01-05-18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 2
ID Task Name Duration Start Finish Dec '15 Jan '16
35 Trust and anchor blocks 49 days Mon 26-02-18 Thu 03-05-18
36 C20 concrete trust blocks 32 days Mon 26-02-18 Thu 03-05-18
37 Pressure test and desinfection 60 days Mon 29-01-18 Fri 20-04-18
38 Pressure test and desinfection of pipelines 60 days Mon 29-01-18 Fri 20-04-18
39 construction of valve chamber with concrete manhole cover 55 days Mon 12-02-18 Fri 27-04-18
40 Construction of C-15 reinforced concrete valve chamber 55 days Mon 12-02-18 Fri 27-04-18
41 2) Supply and installation of pipes and fittings and execution of associated 69 days Mon 29-01-18 Thu 03-05-18
civils works for distribution network
42 Supply, and installation of HDPE pipes and Fittings 69 days Mon 29-01-18 Thu 03-05-18
43 Supply and installation of remaining fittings 10 days Mon 19-02-18 Fri 02-03-18
44 Supply of materials and installation in valve chamber 32 days Mon 19-03-18 Tue 01-05-18
45 Construction of concrete valve chamber 32 days Mon 19-03-18 Tue 01-05-18
46 Gully crossings 17 days Mon 09-04-18 Tue 01-05-18
47 Construction of C-20 reinforced concrete support columns 17 days Mon 09-04-18 Tue 01-05-18
48 Trust and anchor blocks 49 days Mon 26-02-18 Thu 03-05-18
49 C20 concrete trust blocks 32 days Mon 26-02-18 Thu 03-05-18
50 Pressure test and desinfection 60 days Mon 29-01-18 Fri 20-04-18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 3
ID Task Name Duration Start Finish Dec '15 Jan '16
51 Pressure test and desinfection of pipelines 60 days Mon 29-01-18 Fri 20-04-18
52 construction of valve chamber with concrete manhole cover 55 days Mon 12-02-18 Fri 27-04-18
53 Construction of C-15 reinforced concrete valve chamber 55 days Mon 12-02-18 Fri 27-04-18
54 3) Sevice connections Water points & water Kiosks. 66 days Mon 29-01-18 Mon 30-04-18
55 Instalation of HDPE pipes for service connections 30 days Tue 20-03-18 Mon 30-04-18
56 Water Kiosks 30 days Mon 29-01-18 Fri 09-03-18
57 Miscellaneous works 30 days Mon 29-01-18 Fri 09-03-18
58 Water points 39 days Mon 29-01-18 Thu 22-03-18
59 Construction of valve chamber 10 days Mon 29-01-18 Fri 09-02-18
60 Installation of water meters 7 days Mon 12-02-18 Tue 20-02-18
61 Fence and gate 15 days Wed 21-02-18 Tue 13-03-18
62 Drainage system and water disposal 7 days Wed 14-03-18 Thu 22-03-18
63 4) Supply of pipes, fittings, tools and equipment 8 days Mon 11-06-18 Wed 20-06-18
64 Tools and equipments 8 days Mon 11-06-18 Wed 20-06-18
65 Bill 05: Power line 80 days Mon 29-01-18 Fri 18-05-18
66 Leasing with EEPCO 30 days Mon 29-01-18 Fri 09-03-18
67 Connection of Power line with BH 50 days Mon 12-03-18 Fri 18-05-18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 4
ID Task Name Duration Start Finish Dec '15 Jan '16
68 Leasing with SIGMA for connection of Switch Gear 30 days Tue 13-02-18 Mon 26-03-18
69 Bill No 06: 105 days Mon 22-01-18 Fri 15-06-18
70 Construction of Generator houses 10 days Thu 15-02-18 Wed 28-02-18
71 Loading & unloading Ramp 10 days Thu 15-02-18 Wed 28-02-18
72 Miscellaneous 10 days Thu 15-02-18 Wed 28-02-18
73 Construction of two Chlorination buildings 10 days Mon 26-02-18 Fri 09-03-18
74 Miscellaneous 10 days Mon 26-02-18 Fri 09-03-18
75 Guard houses 10 days Mon 26-02-18 Fri 09-03-18
76 Miscellaneous 10 days Mon 26-02-18 Fri 09-03-18
77 Construction of Operator's Dwelling 10 days Mon 26-02-18 Fri 09-03-18
78 Miscellaneous 10 days Mon 26-02-18 Fri 09-03-18
79 Construction of Water Supply Service Office 10 days Mon 26-02-18 Fri 09-03-18
80 Painting 10 days Mon 26-02-18 Fri 09-03-18
81 Hydraulics 10 days Mon 26-02-18 Fri 09-03-18
82 Site work 10 days Mon 26-02-18 Fri 09-03-18
83 Fences and gates operational compounds 30 days Fri 02-02-18 Thu 15-03-18
84 Fence and gates 30 days Fri 02-02-18 Thu 15-03-18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 5
ID Task Name Duration Start Finish Dec '15 Jan '16
85 Bill No 07: Reservoirs 30 days Mon 29-01-18 Fri 09-03-18
86 Construction of two 500m3 RC Reservoir 66 days Mon 29-01-18 Mon 30-04-18
87 Supply and installation of pipes, valves & fittings 30 days Mon 29-01-18 Fri 09-03-18
88 valve chambers 30 days Mon 26-02-18 Fri 06-04-18
89 Site work 36 days Mon 12-03-18 Mon 30-04-18
90 Construction of two 200 m3 RC ground reservoirs 66 days Mon 29-01-18 Mon 30-04-18
91 Supply and installation of pipes, valves & fittings 30 days Mon 29-01-18 Fri 09-03-18
92 valve chambers 30 days Mon 26-02-18 Fri 06-04-18
93 Site work 36 days Mon 12-03-18 Mon 30-04-18
94 Component 3 30 days Mon 29-01-18 Fri 09-03-18
95 Construction of Sanitation Facilities in Welenchiti 30 days Mon 29-01-18 Fri 09-03-18
96 BILL No. 1: Construction of Public Toilet and Shower 30 days Mon 29-01-18 Fri 09-03-18
97 Hydraulics and sanitary fixtures 30 days Mon 29-01-18 Fri 09-03-18
98 Site work 30 days Mon 29-01-18 Fri 09-03-18
99 Bill No.02:Construction Septic Tank and Soak away pit for public Toilet 30 days Mon 29-01-18 Fri 09-03-18

100 Miscellaneous 30 days Mon 29-01-18 Fri 09-03-18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 6
ID Task Name Duration Start Finish Dec '15 Jan '16
101 Bill No.03:Construction of flush school toilet for girls 30 days Mon 29-01-18 Fri 09-03-18
102 Hydraulics and sanitary fixtures 30 days Mon 29-01-18 Fri 09-03-18
103 Site work 30 days Mon 29-01-18 Fri 09-03-18
104 Bill No.4:Construction Septic Tank and Soak away pits for School Toilets 30 days Mon 29-01-18 Fri 09-03-18

105 Miscellaneous 30 days Mon 29-01-18 Fri 09-03-18


106 Bill No 5: BOQ for Sanitary Land fill site and Leachet Pond 89 days Tue 13-02-18 Fri 15-06-18
107 Bill No.6: Sludge Drying Bed 89 days Tue 13-02-18 Fri 15-06-18
108 Comp 1-WS to Feto Satelite Village 30 days Mon 29-01-18 Fri 09-03-18
109 Supply and installation of pipes and fittings 90 days Mon 05-02-18 Fri 08-06-18
110 Supply of Fittings for HDPE pipes 20 days Mon 05-02-18 Fri 02-03-18
111 Installation of Fittings for HDPE pipes 30 days Mon 05-03-18 Fri 13-04-18
112 Trust & anchor blocks and crossings 30 days Mon 16-04-18 Fri 25-05-18
113 Road crossings 15 days Mon 19-03-18 Fri 06-04-18
114 Valve chambers 30 days Mon 19-03-18 Fri 27-04-18
115 PRESSURE TESTING AND DISINFECTION 30 days Mon 30-04-18 Fri 08-06-18
116 Service connections 55 days Mon 19-02-18 Fri 04-05-18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 7
ID Task Name Duration Start Finish Dec '15 Jan '16
117 Service Connections 30 days Mon 26-03-18 Fri 04-05-18
118 Water points 30 days Mon 19-02-18 Fri 30-03-18
119 Power lines from EEPCO tranformers and from of the generators 70 days Mon 29-01-18 Fri 04-05-18
120 Power line from EEPCO transformer 70 days Mon 29-01-18 Fri 04-05-18
121 Bill No. 6 70 days Mon 22-01-18 Fri 27-04-18
122 Construction of Generator houses 53 days Mon 22-01-18 Wed 04-04-18
123 Doors, Windows and ventilation frames 45 days Thu 01-02-18 Wed 04-04-18
124 Electrical Installation 45 days Mon 22-01-18 Fri 23-03-18
125 Miscellaneous 45 days Mon 22-01-18 Fri 23-03-18
126 Construction of one Chlorination buildings 30 days Mon 19-03-18 Fri 27-04-18
127 Miscellaneous 30 days Mon 19-03-18 Fri 27-04-18
128 Guard houses 30 days Mon 19-03-18 Fri 27-04-18
129 Miscellaneous 30 days Mon 19-03-18 Fri 27-04-18
130 Fences and gates operational compounds 30 days Mon 19-03-18 Fri 27-04-18
131 Fence and gates 30 days Mon 19-03-18 Fri 27-04-18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 8
Jan '16 Feb '16 Mar '16 Apr '16 May '16 Jun '16 Jul '16 Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 9
Jan '16 Feb '16 Mar '16 Apr '16 May '16 Jun '16 Jul '16 Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 10
Jan '16 Feb '16 Mar '16 Apr '16 May '16 Jun '16 Jul '16 Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 11
Jan '16 Feb '16 Mar '16 Apr '16 May '16 Jun '16 Jul '16 Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 12
Jan '16 Feb '16 Mar '16 Apr '16 May '16 Jun '16 Jul '16 Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 13
Jan '16 Feb '16 Mar '16 Apr '16 May '16 Jun '16 Jul '16 Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 14
Jan '16 Feb '16 Mar '16 Apr '16 May '16 Jun '16 Jul '16 Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 15
Jan '16 Feb '16 Mar '16 Apr '16 May '16 Jun '16 Jul '16 Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 16
May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 17
May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 18
May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 19
May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 20
May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 21
May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 22
May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 23
May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Driving Predecessor Milestone Task

Inactive Task Path Predecessor Summary Task

Project: Welenchiti Crush progr Inactive Milestone Path Driving Predecessor Summary Task
Date: Tue 20-02-18 Inactive Summary Path Predecessor Normal Task

Manual Task Path Driving Predecessor Normal Task

Duration-only Path Driven Successor Milestone Task

Manual Summary Rollup Path Driven Successor Summary Task

Manual Summary Path Driven Successor Normal Task

Start-only Progress

Finish-only Manual Progress

Page 24