Professional Documents
Culture Documents
Contents Of Panorama
Sl. No. Department Sl. No. Department
1. RSP – A Resume 41. Instrumentation
2. Ore Bedding & Blending Plant 42. Repair Shop (Electrical)
3. Coke Ovens 43. Air Conditioning
4. Coal Chemicals Department 44. Heavy Maintenance (Electrical)
5. Sintering Plant-I 45. Production, Planning & Control
6. Sintering Plant-II 46. Traffic and Raw Materials
7. Blast Furnace 47. Scrap & Salvage
8. Slag Granulation Plant 48. Civil Engineering (Services)
9. Steel Melting Shop-I 49. Structural Inspection
10. Steel Melting Shop-II 50. Contract Cell (Works)
11. Refractory Engineering (Services) 51. Water Management
12. Lime Dolomite Brick Plant 52. Energy Management
13. Calcining Plant-II 53. Safety Engineering
14. Tonnage Oxygen Plant-I 54. Environmental Engineering
15. Tonnage Oxygen Plant-II 55. Fire Services
16. Hot Strip Mill 56. Industrial Engineering
17. Plate Mill 57. Research & Control Laboratory
18. ERWPP 58. Total Quality Management
19. Spiral Welded Pipe Plant 59. AMR-Project Monitoring & Spl. Cell
20. Pipe Coating Plant 60. Projects
21. Special Plate Plant 61. Computer & Info. Technology
22. Cold Rolling Mill 62. Materials Management
23. Silicon Steel Mill 63. Finance & Accounts
24. Roll Shop 64. Personnel
25. Maintenance Function 65. Human Resource Dev. Centre
26. Maintenance System and Services 66. Central Power Training Institute
27. Shops- Plg & Coordination Services 67. Law
28. Shops-Foundries 68. Town Engineering
29. Shops-Mechanical Shop 69. Town Services
30. Shops-Repair Shop (Mechanical) 70. Sports
31. Shops-Structural & Fabrication Shop 71. Corporate Social Responsibility
32. Repair & Construction (Mech) 72. Public Relations
33. Crane Maintenance 73. Protocol & Hospitality Services
34. Field Machinery (Maintenance) 74. Vigilance
35. Transport 75. Internal Audit
36. Design 76. Medical & Health Services
37. Captive Power Plant-I 77. Central Industrial Security Force
38. Power Distribution
39. Electronics & Electrical Services
40. Communication Engineering
Department
Rourkela Steel Plant (RSP) is the first of the three integrated steel plants set up by
Government of India in 1959. The first Steel Industry set up under Hindustan Steel limited on
19th January 1954 which paved way for laying up of infrastructure for rapid industrialization of
the country. The plant was set up in collaboration with leading steel makers of Federal
Republic of Germany.
In the initial phase, 1.0 MT units were commissioned between December’ 1958 and early part of
1962. Hot Metal production in RSP started with lighting up of first Blast Furnace ‘Parvati’ on
3rd February’ 1959 by his Excellency President of India, Dr Rajendra Prasad.
To meet the additional demand of flat products in the country, the capacity of the plant was
expanded from 1.0 MT to 1.8 MT between the year 1965 and 1969. Besides, expansion of the
capacity of the existing units, new units like Electric Sheet Mill (for Dynamo and Transformer
Grade Steel) and Galvanising lines (for corrugated and plain galvanized sheets) were added.
Subsequently, a number of units were added to enhance the product quality, production,
productivity and to fulfill market needs. These units included Blast Furnaces, Spiral Welded
Pipe Plant, Silicon Steel Mill, Captive Power Plant-II, Mechanical Shop, Structural &
Fabrication Shop, Heavy Loco Repair Shop, Slag Granulation Plant and Coke Ovens Battery
No. 5.
In the year 1988, a new era was started with modernisation in RSP. This was necessary in
order to overcome technological obsolescence and to continue to remain competitive in the
market place. The modernization of the Plant was completed in two phases from 1994 to
1999. With this, the production capacity of the Steel Plant increased to 2 million tons of Hot
Metal and 1.9 Million tons of Crude Steel. Phase-I was completed in the year 1994 which
emphasised on improving the quality of raw materials consisting of a new Oxygen Plant,
upgradation schemes for Blast Furnaces, Dolomite Brick Plant, Cast House Slag Granulation
Plant at Blast Furnace # 4, Raw Material Handling System, Coal Handling Plant in Coke
Ovens and Power Generation and Distribution System. Phase-II consisted of a new Sinter
Plant, Basic Oxygen Furnace and Slab Casting shop in Steel Melting Shop-II, except for Hot
Strip Mill. Except Hot Strip Mill, which was completed in the year 1999, all other units were
completed in the year 1997.
Rourkela Steel Plant has carved a name for itself as a unique producer of special purpose steels
in the flat steel segment. Plates, Hot Rolled Coils, Cold Rolled Sheets and Coils, ERW Pipes,
Spiral Weld Pipes and Silicon Steel Sheets and Coils are the products in RSP’s repertoire. RSP
has many firsts to its credit. It was the first plant in India to incorporate LD technology
of steel making. It is also the first steel plant in SAIL and the only one presently, where 100%
of the slabs rolled are produced through the cost effective and quality centered continuous
casting route.
RSP is the only plant in SAIL to produce silicon steels for the power sector, high quality pipes
for the oil and gas sector and tin plates for the packaging industry. Another uniqueness of RSP
is that it does not produce semis. The use of its Plates in ship building & high pressure vessels,
Silicon Steel in the electrical machine manufacturing industries, corrugated galvanized sheets
for roofing including industrial roofing, pipes in the oil & gas sectors, tinplates in packaging
industry and Special Plates in the defence of the nation is well known.
e) Rourkela is the first in vacuum degassing metallurgy. This system has been adopted
primarily for production of silicon steel for the cold rolled non-oriented sheets. The
system consists of vacuum arc refining and vacuum oxygen refining units and a
degassing facility.
f) It is the first integrated Steel Plant of SAIL which adopted the cost effective and
quality centered continuous casting route to process 100% of steel produced.
g) All the major production departments and some service departments certified to ISO
9001:2008 QMS.
h) Silicon Steel Mill, Environmental Engineering Department and Sinter Plant – II,
HSM, PM, SPP, ERWPP, SWPP & Township certified to ISO 14001:2004 EMS.
Raw Materials
The fully mechanized captive mines under Raw Material Division (RMD), a unit of SAIL meet
the bulk requirements of Iron ore, Limestone, Dolomite, Manganese, Quartzite and coal as raw
materials of RSP.
Products Applications
LPG cylinders, automobile, railway wagon chassis and all
HR Coils
types of high strength needs.
Pressure vessels, ship building and engineering structures,
Plates
space programmes
Different defense applications, building of tanks, bullet
Special Plates
proof steel etc
Flooring and staircases in the industrial sectors and
Chequered Plates
railway platforms etc.
Steel furniture, white goods like refrigerators, washing
CR Sheets & Coils machines, automobile bodies, railway coach paneling,
drums, barrels, deep drawing and extra deep drawing etc.
Roofing, paneling, industrial sheeting, air condition ducting
Galvanised Sheets
and structural.
Containers for packaging of various products including
Electrolytic Tin Plates
edible oils, vegetables and confectionary items.
Small generators, starters for high efficiency rotating
Silicon Steel Sheets & Coils
equipment and relays etc
High-pressure transportation of crude oil, natural gas and
SW Pipes slurry transportation, water supply, sewage disposals, grain
silos, civil engineering pilings etc.
High pressure transportation of oil and water, sewage
ERW Pipes
disposal, tube wells etc.
Coils Pipes
Ore Bedding and Blending Plant of RSP came up during its modernisation and commissioned
in two stages. Phase-I was commissioned in 1994 with the facilities of unloading, screening of
Iron Ore Lumps (IOL) and dispatch of raw materials to different units like Sinter Plant-I, Blast
Furnaces and Lime Dolomite Brick Plant (LDBP). Phase-II
was commissioned in 1996 with the facilities to prepare and
supply Base Mix to Sinter Plant- I & II and screened Lime
Stone and Dolomite to Calcining Plant-II. Capacity of OBBP
is 5.0 MT of raw material dispatch per annum. In OBBP raw
material transportation takes by a series of belts. There are
around 140 numbers of belts and total length of belts added
together is around 45 Kms.
Other than the above raw materials coming from mines, OBBP also handles Coke breeze, LD
slag fines, SMS sludge, Mill scale, Flue dust and other spillage materials generated inside the
plant and process the same.
Unloading:
There are two Wagon Tipplers and two Track Hoppers for unloading of the raw materials which
comes from the mines. Generally side opening type of wagons(BOBS) are unloaded in Track
Hoppers. Track Hopper-1 is dedicated for IOL and Track Hopper-2 for IOF. Wagons viz. BOX,
BOXN, BOXC, NBOY etc. are unloaded in Wagon Tipplers numbered as WT-4 & WT-5.
After unloading in Wagon Tipplers materials are conveyed to designated bed through a series of
belts and with the help of Stacker.
IOL Screening:
IOL coming from mines contains undersize fraction of -10mm which can affect Blast Furnace
operation. Therefore, this undersize fraction is screened out in IOL Screening Section and then
stacked in Bed No. 8 & 9 from which screened ore is dispatched to Blast Furnaces.
These materials are stored in designated bunkers in Proportioning Bin building and stacked in
Bed as per the above setting from their respective Weigh Feeders.
Flux Crushing:
Flux Crushing is carried out in Rod Mills. Lime Stone and Dolomite lump conveyed to Rod Mill
hoppers before crushing at ratio of 40:60 or 30:70 as
per the requirement of Sinter Plant.
Customers of OBBP:
Auto Sampling
Station
Raw Materials
ΩΩ Iron Ore
Stock Yard
& Screening
Screened Ore & Building
Sized Ore
Base-Mix Beds Base Mix
PB
Building
Iron Ore Fines
Lime Dolo Coke & Flux
Screening Crushing
Building ΩΩ Building
LD Slag
-30 mm
Coke Breeze P/R Track
Track Hopper Hopper
Base Mix to SP-I &
LS & Dolo to CPII
SP-II
COKE OVENS
In any integrated steel plant, Coke Ovens Department is the first production unit. Coke is
required in Blast Furnace for reducing iron ore (Fe2O3) to molten iron, which is also termed as
Hot Metal. The major advantages of using coke in Blast Furnace are:
(a) It is strong & hard and can withstand the abrasive action inside the blast furnace and
remains in solid form till it reaches the tuyere zone.
(b) Because of its strength, it can take the load of the burden above it.
(c) It is porous which allows good contact between the carbon (present in coke) & oxygen in
air.
(d) It is uniform in size for better distribution inside the furnace.
(e) It is having a high heating value.
The Coke:
Coke is made from coal. Normally two varieties of coals are available in the earth's crust.
(a) Non-coking coal
(b) Coking coal
India has vast reserve of Non-coking coal, which is generally used for power generation by
Thermal Power Plants.
Coal Blending:
Coking coal is sub-divided into two categories depending upon its coking characteristics.
(i) Prime Coking Coal (PCC)
(ii) Medium Coking Coal (MCC)
The analysis, usually termed as the proximate analysis, for the above varieties of Indian coal is
as given under:
In India, the availability of PCC coal is scarce and hence its usage is also restricted. Further
due to inherent high ash content, the coke made from above coal also has high ash rendering it
unsuitable for use in Blast Furnace. In order to lower the ash in Indian coals, it has to be
suitably blended with low ash imported coking coals. Two varieties of coals are usually
imported primarily from Australia, USA & New Zealand. They are:
In order to produce good coke, PCC, MCC, ICC (H), ICC (S) coking coal is blended together. The
present blended coal analysis is as follows:
However proximate analysis provides only prima-facie data. Suitability of coal for coking is
ultimately based on more advanced analysis which is called petrographic test. Petrographic
characteristics of the different coal are as follows.
Coal Preparation:
Coal as it comes from the mine ranges in size from
large lumps to dust and is known as "Run of Mine".
This coal contains a lot of impurities which are to be
removed before it can be used. "Run of Mine" coal is
sent to washery for cleaning. After removal of gangue
material the coal is sent to steel plants in box wagons.
At RSP, all coal wagons are unloaded in Tipplers, a device which can unload at the rate of 12
wagons per hour. There are two such tipplers for unloading of wagons. The unloaded coals are
stacked in "Piles" in the coal yard. Hence coal piles of PCC, MCC, ICC (H) & ICC(S) are made
in the yard. The coal yard has a capacity to store more than 60,000 Tons of coals in piles. Coal
from the yard is reclaimed with the help of scrapper type reclaimer from the piles of stacked
coals. These are then sent to Central crushing station through various conveyor belts. Here the
coal is pulverized below 3.2 mm size. The pulverized coal is sent to blending bunkers.
The four varieties of coal is then blended proportionately such that desired coal blend is
achieved. The blended coal is then stored in coal towers.
Numbers of ovens are placed side by side and together it is called a Battery. At RSP there are
five batteries:
Battery # 1 70 Ovens
Battery # 2 70 Ovens
Battery # 3 70 Ovens
Battery # 4 80 Ovens
Battery # 5 80 Ovens
Total 370 Ovens
The walls of the ovens are maintained at a temperature of >1000oC by burners which are
located inside the walls. Here CO gas, BF gas or mixed gas are used as fuel for maintaining the
wall temperature.
The annular spaces between the walls are filled with coal taken from coal towers. The coal is
indirectly heated for a period 18 to 20 Hrs. All volatile
matters present in coal escape. The residue coke is pushed
out from the oven, quenched with water to prevent
combustion of coke and dumped into a wharf.
The empty oven is again refilled with coal & the process
continues. The by-products of carbonization namely
Ammonia, Benzol, Tar & Coke Oven gas generated during
the process are sent to Coal Chemicals Department for removing impurities. The gas after
cleaning is used as fuel throughout the steel plant.
The Wharf:
The wharf is an inclined platform lined with cast iron plates having gates at one end. Under the
gates, a conveyor belt conveys the material which falls over it. The quenched coke is dumped &
spread uniformly on the wharf. This helps to drive off any extra moisture which the coke may
carry along with it. Further any hot spot remaining after quenching is quenched here.
The quenched coke is discharged from the wharf to the belt below, and taken to coke sorting
station where the coke from the wharf is segregated as per its size.
Hard coke is sent to Blast Furnaces directly through conveyor belts. Other fractions are loaded
in BOX/ BOBS wagons & dispatched to the end user. Coke < 80 mm size are crushed in double
roll crusher & segregated as per above fractions.
COAL CHEMICALS
Coal is a treasure chest of an innumerable number of chemicals. The source for all these
chemicals is the volatile matter present in coal, which in our case is from 20-30% of the coal.
When coal is carbonised in the coke ovens, about 320 Nm3/T of gas is generated which comes
from the volatile matter of the coal. The gases escaping from the coke ovens contain tarry
matter, moisture, vapours of a number of chemical compounds like ammonia, hydrogen
sulphide, naphthalene, benzol etc. These are commonly known as by-products though they are
very useful and valuable materials. These are rightly called as coal chemicals, which form the
chief raw materials for the manufacture of dye stuffs, pharmaceuticals, flavours, perfumes,
rubber chemicals, plastics and a thousand of other useful products that are now almost
indispensable in our present day civilization.
Geographically the plant is divided into 3 areas, viz: Site-A, Site-B and Site-C. In Site-A the gas
from batteries 1, 2 and 3 is collected and cleaned and crude tar is removed. Site A and Site C
each has a refrigeration plant. Similar procedure is carried out in Site-C, which handles the gas
from battery IV and V. Site-C has low pressure cleaning units after which the gas goes to site-A
for distribution. The H2SO4 manufacturing unit also is in Site-C. Site-B has all the storage
facilities for the crude tar and it has got facilities for further processing and refining of these
products into marketable chemicals. The main units in Site-B are:
i) Crude tar distillation plant
ii) Naphthalene oil processing plant
The plant has a total capacity to treat 120,000 Nm3/hr of gas. Some of the special features of
this plant are:
i) Vapour Absorption System for Refrigeration
ii) Spray Saturator for removing ammonia
iii) Continuous pipe still furnace for crude tar distillation
iv) Double Conversion Double Absorption (DCDA) Sulphuric Acid Plant
v) Direct distillation of road tars
vi) Biological Oxidation and Dephenolisation unit for effluent treatment
This vast Coal Chemicals complex offers a unique opportunity for the chemical engineers as it
includes most of the unit operations and unit process of the chemical engineering field like fluid
flow, heat flow, various types of heat exchangers transportation and metering of fluids, mixing,
evaporation, centrifuges, crystallization, distillation (multi-component and vacuum) gas
absorption, extraction, drying, humidification etc.
The gas after the exhauster is sent to expansion units for removal of ammonia and making
ammonium sulphate. Ammonium Sulphate is made by passing total CO gas produced in MT
and expansion batteries through spray type saturator where dilute sulphuric acid is sprayed.
After spray type saturator total gas is cooled in final gas cooler where recycled water is cooled
by refrigerated water. Naphthalene is also removed in final gas cooler. The gas is then
branched into three streams:
Similarly the gas from the expansion side batteries (No. 4 and 5) is brought to the Coal
Chemicals plant of Site-C and is cooled indirectly in primary coolers using re-cooled as well as
chilled water to remove tar condensate. The gas is sucked by exhausters. The gas is then passed
through Electrostatic Tar Precipitators (ETPs) to remove the final traces of tar. The tar-free gas
from Site-A and Site-C are mixed and passed through a tower where the gas comes in contact
with two stages of sulphuric acid sprayer (1-2% in low acid sprayer, 4-5% in high acid sprayer).
The ammonium sulphate thus produced is crystallised in vacuum crystallizer, centrifuged and
bagged. The gas is then cooled in final cooler. The naphthalene content is also reduced in final
gas cooler. The gas sent to gas mixing station, underfiring line and gasholder is having the
following impurities:
The recovered tar is distilled to produce light oil, carbolic oil, naphthalene oil, wash oil,
anthracene oil, road tars, coal tar fuels, soft pitch, hard pitch and special pitch for pitch bonded
brick plant. Tar distillation plant (Capacity: 300 TPD of feed stock) is unique among SAIL
plants, as it employs vacuum distillation technique.
Naphthalene oil is redistilled in naphthalene plant.
Hot pressed naphthalene is manufactured by cooling
redistilled oil and hot pressing and cooled solid.
SINTER PLANT - I
Sinter Making:
Due to increased mechanisation in the mines, lot of fines are generated which can not be
charged into the Blast Furnaces directly. In order to conserve these, otherwise waste material,
they are compacted together and made into lumps by a process known as sintering. Sintering is
defined as the agglomeration of the fine mineral particles into a compact lumpy mass by
incipient fusion caused by the heat produced during the combustion of the solid fuel within the
moving bed of loosely particles.
Advantages of Sinter:
• Helps in the conservation of raw materials.
• Enhances the productivity of Blast Furnace.
• Decreases coke rate in BF.
• Decreases the flux rate in BF.
• Improves the permeability of BF.
• Helps in the smooth running of the BF.
Technical Data:
1. Capacity of the Plant - 1.5 MT / Annum.
2. Sinter Machine - 2 Nos. (125 T/hr), 125 m2 working area, Mixed
gas fuel, Dwight Lloyd down draft continuous
chain type machine
3. Sinter Breakers - 2 Nos.
4. Primary Mixing Drum - 1 No.
5. Pelletising drum - 2 Nos.
6. Hot Screen - 2 Nos.(separate +6 mm & -6 mm fractions)
7. Cold Screen - 2 Nos.(separate +25 mm,+15 mm-25 mm,-15 mm)
8. Process ESP - 2 Nos.
9. Dedusting ESP - 2 Nos.
10. Exhausters - 2 Nos.
11. Capacity of Sinter Storage - 1200 T
Bunker
Input material:
The input materials and average consumption for one ton of sinter are:
Input in the form of Base Mix (a homogeneous mixture of Iron ore fines, Flux, Coke Breeze,
Plant Returns) is supplied from OBBP.
Process:
The Sinter Plant-I has a rated capacity of 1.5
million tonnes of sinter per year based on 2-
strand 3 shift running. There are two sinter
machines of the Dwight-lloyd down draft type with
125 sq. meter working area. The raw materials as
specified above are brought, stored, crushed and sent
to proportionating bins. The different materials are
drawn from these bins in a fixed ratio on to a
common belt conveyor leading to the primary
mixing drum. Here water and return fines are
added. The raw mix is stored in two intermediate bins from where it is fed into the two
pelletising drums. Here further water is added to facilitate balling which increases the
permeability of the raw mix.
This is carried to the charging hopper over the sinter machine 1 & 2. The material is fed over
the sinter machine pallets and the height of the bed is maintained 400-450 mm depending upon
quality of raw material used and sinter to be made. The sinter machine is provided with 21
wind boxes at the bottom to suck the air through the bed. As the bed travels through the
Ignition Furnace, the top layer is ignited. This combustion zone proceeds downwards till the
pallets reaches the discharge end. The temperature in the last wind box is maintained at
around 250oC. The hot sinter coming out from the machine is broken by the sinter breaker and
then screened. The -6 mm fraction is sent to the Return fines bin. The sinter is then cooled in
the cooling strand by blowing air through it and finally it is sent to the double deck cold screen.
Here it is separated into 3 fractions. The +25 mm is either stored in the sinter storage bunker
(1200 T capacity) or is directly sent to the Blast furnaces. The -25 mm and +15 mm fraction is
used as a bedding hearth layer on the sinter machine in order to:
-15 mm fraction is again screened with 6mm screen. +6 mm fraction is sent to the Blast furnace
along with +25 mm fraction. -6 mm fraction is sent to return fines bin.
Two space dedusting fans with Electro Static Precipitators are installed for dedusting from
various transfer points. Two waste gas fans with Electro Static Precipitators are installed for
creating suction in the sinter bed from bottom.
Output:
The output is sinter whose typical composition is:
Total Fe 54.0 %
FeO 9.5±0.5 %
SiO2 5.5±0.5 %
Al2O3 3.0±0.2 %
CaO 10.5 ± 0.5 %
MgO 2.8 ± 0.2 %
Basicity 1.8 - 2.0 %
-6 mm
Sinter Sinter
Machine-I Machine-II
Hearth Layer (-25,+15 mm)
Cooler-I Cooler-II
Ω
Cold Screen
Sinter to Blast Furnace
+25 mm (+25,+6)
SINTER PLANT-II
Commissioned on the 29th September 1996, Sinter Plant-II was a part of the modernisation
programme of Rourkela Steel Plant. It along with Sinter Plant-I fulfils the Sinter requirement
in the Blast Furnace burden to 70% from a level of around 50%. Higher Sinter proportion in
Blast Furnace burden improves the Furnace productivity with substantial reduction in coke
rates.
Major Equipments:
• 12 nos. of proportionating bunkers with electronic belt weigh feeders/ vibro feeders.
• One 3.8 m diameter x 15.9 m long mixing and balling drum.
• One 8-metre long ignition furnace with section one roof mounted multi slit burners and
balance three with wall-mounted burners.
• One no sintering stand of 3 meters wide, 192 square meter sintering area.
• One 1.2 m high, 195 square meter linear Sinter cooler with five cooler blowers.
• One Hot Sinter Screen (-5 mm).
• Cold Sinter screens (+50 mm, +25 mm, +15 mm, +5 mm) 4 Nos.
• Waste gas fan with 5.72 MW synchronous motor.
• Two Electro Static Precipitators: one for waste gas and another for plant dedusting.
• Two Ingersoll-Rand centrifugal air compressors
Salient Features:
• Precise proportionating by using electronic weigh feeders & loss and weight system.
• One combined mixing and balling drum of 400 tons / hour capacity.
• Closed Circuit Cooling Water System.
• Use of high bed thickness (550 mm) with high under grate suction of 1350 mmWC.
• Elaborate pollution control measures with two electrostatic precipitators.
• 10 nos. of sinter storage bunkers having a cumulative capacity of 5230 ton.
• PLC controls for Plant operation, Distributed Control System (DCS) for process control.
• Waste heat recovery system along with dust recovery facilities.
• Pneumatic conveyors system for calcined lime transfer.
• Dispatch of Sinter to Blast Furnaces by belt conveyors.
Design Data:
Production 1.57 MTA (Gross Sinter)
Productivity 1.13 T/Sq.m/hr
Annual working days 300 days / year
Coke consumption 75 Kg/ton of skip sinters (dry)
Gaseous energy consumption 32,000 kcal/T of gross sinter
Sinter granulometry +50 mm 0% and -5 mm 3% (min)
ISO tumbler index (+6.3 mm) 72% (min)
Cooled sinter temp. < 100 oC
Dust content in stack emission (Maximum) 100 mg/NM3
Process:
Sintering is the process of agglomeration of particle
fines by incipient fusion, which bind them together into
hard, porous, lumpy mass of material. Base mix, coke
breeze and flux fines are received at Sinter Plant – II
by a series of belt conveyors from OBBP and collected
in bins. There are total twelve bins, four are for base
mix, one for miscellaneous, two each for flux fines, coke
breeze and Blast furnace return fines one for plant
return fines. After proportionating, the material comes
to mixing and balling drum for nodulising and
moistening. Then with help of a series of belt conveyors, it (raw mix) is laid onto sinter machine
pallets above a hearth layer. The top layer of material on pallet is ignited in ignition furnace
with the help of mixed gas. As the sinter machine continuously moves on and exhaust blower
(Waste Gas Fan) sucks air from the bottom of pallets, the combustion layer travels down. After
the sinter process is completed, the sinter cake is crushed, cooled, screened for different sizes
and the undersized (-5 mm) sent back for recycling. The sinter +15 mm to -25 mm size is used
as hearth layer on sinter machine.
Achievements:
Sinter plant – II has marched towards excellence consistently in many fields. The department
has been ISO 9001 QMS and ISO 14001 EMS certified since 2001. It has achieved annual
production of 1.98 MT against detailed project report (DPR) of 1.57 MT sinter, specific
productivity 1.3 against 1.135 T/Sq.m/hr. With installation of multi slit burner specific gas
consumption has been reduced to 23 MCal/Ton of Sinter against DPR of 32.
PR Fines
Comp. Air
Lime
Water
25mm
-25 mm
15mm
-15 mm
+25 mm
Blast
Furnaces
BLAST FURNACE
The raw materials required for production of hot metal are Iron ore, Sinter, coke, LD Slag,
Quartzite & Manganese ore (as per requirement of SMS). Apart from these solid raw materials,
it also requires air and oxygen for burning of coke, water for cooling various parts & equipment
of furnaces. Iron ore supplied from OBBP, Sinter from Sintering Plant (I & II), Coke from Coke
Oven and LD Slag and scrap from SSD.
The hot metal which is basic raw material for steel is supplied to steel melting shops I & II of
RSP. In case SMS is unable to accept hot metal, the same is poured in Pig Casting Machine to
solid iron called pigs.
BELT
Wagon
HIGH
IRON ORE
SINTER
(SCREENED AT
BF)
COKE TO OTHER
(SCREENED AT BF
THROUGH
GAS CLEANING
COLD
BLAST PIG CASTING
FROM
HOT
HOT
TAP HM SM
SLAG
FROM GCP
FURNACE
TO STOVES FOR HEATING
STOVE
SM
INBA CH SGP
SLAG
FLOW DIAGRAM OF
BLAST FURNACE
PROCESS SLAG
GRANUL-
ATION
INPUT OUTPUT
AIR 2.42 T
GAS 3.615 T
SINTER 1.25 T
ORE 0.45 T DUST 0.006 T
+ ORE 0.45 T BLAST
FURNACE
HOT METAL 1.0 T
LDS 0.005 T
COKE 0.570 T
The open storage yard is provided with a crane of 45 m span and 20 T capacities to load
material into wagons and also to stock material after it is unloaded from wagons.
There are total 65 bins for storage of various raw materials, 16 for each furnaces and one bin to
store sinter return fines falling off from the head end of sinter belt. Out of 16 bins in each
furnace 10 bins are having 246 m3 volume and called full bins. Four bins having 126 m3 volume
are called ½ bins and 2 bins having 186 m3 volume are called 3/4 th bins. Full bins are normally
meant for storing iron ore & sinter where as ¾ bins are meant for Qtz, LD slag or manganese
ore. Each bin is provided with vibro-feeders to draw material from bins to conveyor belts which
subsequently feed them to weigh hoppers and then to skips. But sinter after being drawn from
the bins is screened through +5 mm mesh size vibrating screen to weigh hopper and – 5 mm
size sinter is conveyed through sinter fines conveyor belts (SFC) to sinter fines bunkers and
subsequently to both the sinter plants.
There are two coke service bunkers in each furnace having 525 m3 capacity (300 T of coke) to
store coke coming from coke oven. Each coke bunker is connected to a coke screen to screen out
– 25 mm and discharge + 25 mm size coke to coke weigh hoppers. The + 25 mm size coke from
weigh hoppers is then discharged to skips to be charged into furnaces. The – 25 mm size coke
breeze is carried by fine breeze conveyor belt to fine breeze skip which unloads the breeze in
fine breeze bunker. The coke fine breeze is then dumped from the bunkers to wagons for further
transportation to sinter plants & OBBP.
To charge the raw materials into the furnace there are two skip cars each of 8.5 m3 volume in
MT furnaces and 10.5 m3 volume in BF-IV. The hauling capacity of each skip is 8.0. T at a
speed of 1.8 m/sec for 1 MT furnaces & BF-IV 10 T at a speed of 3.2 m/sec and while one of the
skip car remains in the skip pit to receive the raw material from the hoppers, the other one
discharges the material at the furnaces top.
The charging sequence, selection of charge material, switching of stock house equipment,
weighing of raw materials their subsequent discharge to skip and movement of skip cars, all
are controlled through a PLC system from charging side control room.
Furnace Proper
There are four Blast Furnaces with combined installed capacity of 1.8 MT of hot metal which
was upgraded during the nineties to 2.0 MT of hot metal per annum. The Blast Furnace shop is
currently passing through further modernization & technological up gradation to enhance
production capacity to 4.5 MT per annum by 2012. Some of the technical information about the
four furnaces are out listed below.
The blast furnace is a vertical shaft type furnace where reduction & melting of descending
charge material takes place due to the heat and ascending gases produced due to combustion of
coke by hot air blown through the tuyeres. The furnaces are fully refractory lined, the bottom
hearth to bosh with carbon blocks & there after with fire clay bricks whose % Al2O3 goes on
decreasing from bosh to shaft. Major sections of the furnace proper are:
2.1) Top Charging Equipments
2.2) Cooling system
2.3) Hot Blast Stoves
2.4) Cast house & cast house Slag Granulation Plant
• Decomposition of Carbonates
Combustion Zone
• Burning & combustion of coke & complete reduction of iron oxide.
C + CO2 = CO2 + 94450 Cal (Direct Reduction)
CO2 + C = 2CO – 41000 Cal (Solution loss reaction)
Race way
• Coke & Hydrocarbons are oxidized
• Large evolution of heat.
In case of BLT, these are no bells as the nomenclature states. The skips dump the materials to
a receiving hopper, which is separated from the BLT by upper material gate and upper gas seal
valve. After opening of upper material gate & upper seal valve, material is discharged into BLT
material bin placed over the lower material gate & lower gas seal valve. Then the UMG (Upper
Material Gate) & USV (Upper Seal Valve) are closed to seal the furnace from the atmosphere &
the receiving hopper is ready to receive material from the skips.
To dump the material into the furnace, the lower seal valve opens and then the lower material
gate is opened. The material is dumped through a rotating chute, which can dump material at
any position of the furnace and can complete the dumping in variable number of rotation so
that desired burden distribution is achieved. The whole BLT system is hydraulically operated &
PLC controlled. Besides achieving perfect burden distribution, BLT ensures very good gas
sealing at the furnace top so that furnace can be operated at a high top pressure.
Cooling System
In order to monitor, prevent damage and prolong the life of refractory lining inside the furnace,
it is essential to have an elaborate cooling system in the furnace. In BF 1, 2 & 3 from bosh to
2/3 stack the lining is cooled by plate coolers, from bosh to hearth by spray coolers. The top
stack is not provided with any cooling water. But the BF # 4 hearth bottom is provided with
under hearth coolers, hearth to 2/3 stack is provided with close loop stave coolers and the
tuyeres area with breast coolers. BF # 1 is provided with external spray system. The pure
copper tuyeres and main coolers that are projected into the furnace through the lining are
internally cooled by water. The temperature & steadiness of out let water of cooling members
are regularly monitored.
To control the top gas temperature in exigencies water spray system is provided at the furnace
top.
The hot blast stoves are provided with several attachments such as burners to burn the
premixed air and BF gas in the combustion chamber. Different valves are provided for
controlling the BF gas, combustion air, waste gas, cold blast and hot blast to or from the stoves.
The hot blast from stoves passes through insulating refractory bricks lined pipes (hot blast
main, bustle main & tuyeres stocks) and then injected through tuyeres into the furnaces. The
entire operation & control of stoves & hot blast is made from a control room adjacent to stove.
FACILITIES AT
MAIN UNITS UNIT
MTP EXPN
Stoves No. 3 3
Jacket Dia 8 8.5
Overall height Mtr. 37 38
Heating surface / stoves Mtr.2 34000 43000
Blast Temperature OC 950 1000
100,000 140,000
Blast Volume Nm3/hr
Nm /hr.
3 Nm3/hr.
Cast House
The Cast House is the most important section of Blast Furnace. The function of cast house is to
tap the liquid metal & slag from the hearth of furnace on schedule, separate the metal & slag in
troughs and flow them through runners to metal ladles and slag pots respectively. Production
of Blast Furnace is greatly influenced by effective tapings which depend on a good cast house
practice.
Hydro pneumatic drill machines are used to drill the tap hole up to 2 m into the hearth to tap
the metal & slag. Oxygen lancing through mild steel pipes is resorted to, if taping is not
possible by drilling alone. The troughs & runners are made with special grade refractory mass
to handle upto 40,000 T metal before repair. Few iron runners are also made with low cement
castables to handle more then 1 lakh ton metal before repair. Hydraulic powered mud guns are
used to close the tap hole after casting is over with anhydrous tap hole mass which get quickly
hardened inside the tap hole.
The main components of cast house is the tap hole, troughs, iron runners, slag runners, iron &
slag spouts, mud gun and drill machine. Each cast house is provided with an EOT crane (15 T
cap for BF – I, II & II and 30 T for BF – IV). BF 1, 2 & 3 have one tap hole where as BF – 4 has
two tap holes with separate trough & runners for Iron & slag. More over BF – 4 cast house has
two mud guns for 2 tap holes but one common drill machine. BF # 4 Cast house is provided with
tilting runner & pusher car in iron side. BF # 3 is also provided with tilting runner in Iron side.
As the Hot slag flows down from the Hot runner, several water jets from the blowing box, break
the slag stream into droplets & carried them into a receiving hopper as a slurry. The slurry
falls on wire nets and paddles of a rotating drum, wherein water passes through and goes to the
hot water tank whereas the granulated slag is captured by the paddles, which move along with
the drum rotation. When the paddles come over a belt running at the center of the drum, the
granulated slag falls into the conveyor and is carried away to the disposal yard. The yield of
granulated slag of CHSGP is around 90%. It has been designed by M/s Paul Wurth and can
handle slag upto 6 to 10 T/ minute. Granulated slag is a major raw material for Portland slag
cement. Therefore by granulating slag not only is the waste material used economically, it also
avoids environmental problem that is associated with liquid slag dumping.
Filter House
The effluent dirt water coming from the water seals of the precipitators is collected in concrete
channels leading to slurry pump sumps. From this sump, the slurry is pumped by a slurry
pump of capacity 225 m3/hr. (1 R+ 2 S) into overhead steel channels for the dirty water. This
slurry along with the slurry coming directly from gas washers goes to 3 nos. of Dorr Clarifier
Basins. After clarification, the water goes to the hot water pump sumps at the pump house. The
underflow water from of the clarifier basins is pumped to the Continuous Belt Press Filter
(CBPF) for de-watering. After the extraction of the water, the filter cake generated by CBPF is
removed by road transportation. The connections of the clarifier basins to the general sewage
system permit a complete cleaning out of each clarifier basin. The sludge pumping station and
the sludge filtration plant are provided to deal with 3,400 cbm per hour of dirt water.
DO
W
N
CO
M
ER
DUST E.S.P
CATCHER
BF CLEAN
WAGON SCRUBBER GAS MAIN
FURNACE
WATER SEAL
SLURRY PUMP
C.B.P.F
COOLING TOWER
CLARIFIERS
FILTER CAKE
One annular gap element (AGE) regulates the flow of gas into out let pipe inside the ventury
and creates a backward pressure in the furnace. As the annular gap decreases between the
element & ventury, the top gas flow is throttled and furnace top pressure increases. The AGE is
hydraulically operated & controlled by PLC to give preset top pressure. A mist eliminator
attached to the scrubber reduces the moisture content in the clean gas before it joins the main
clean gas line.
CaO 30 - 32 %
SiO2 32 – 34 %
Al2O3 20 – 22 %
MgO 10 – 11 %
MnO 1
FeO 1% Max
S 0.5 to 0.6
Process
The Rourkela Slag Granulated Plant follows the hydraulic chipping principle which can be
classified in to the semi-dry process. The slag pots are placed in position and the solid crust is
pierced by a conical dead weight of 2.5 tonnes with the help of EOT crane. Then the slag pots
are electrically tilted over a receiving bath and from it falls in to hydro-chutes where
simultaneously high pressure water is sprayed through a nozzle plate having 53 Nos. of holes of
different size. The slag is instantaneously cooled and crushed to less then 3 mm size. The
granules thus formed are thrown out in to the storage bay to a distance of 15 to 20 meters due
to the high pressure (9 kg/cm2) water spray. From the storage bay the material is shifted by
means of a 10 T – EOT crane with grab bucket arrangement to steel hoppers for truck loading.
In the process of shifting the material from the storage bay, the water flows down to a re-
circulation tank system of 450 m3 capacity. The water is allowed to settle here and the clean
water is re-circulated through the pump house by the horizontal centrifugal pumps. The water
loss is compensated by the make-up water which comes through the make-up water lines of 250
mm diameter.
The usual water consumption is 2.5 m3 per ton granulated slag. The Granulation Plant is
having the following sections:
i) Granulation Bay with one 3 Ton EOT crane, 6 numbers of Hydro-chutes and Control
Tower.
ii) Storage Bay with 2 numbers of 10 Ton capacity EOT cranes provided with Grab
Buckets (each 3 m3 capacity) and 2 numbers of steel hoppers.
iii) Water Circulation System including the pump house, re-circulation tank, 6 numbers
centrifugal pumps of 300 m3 per hour capacity and 93 m head, and tunnel house
system.
iv) Power Sub station with motor control circuits.
v) Ventilation System.
BLAST FURNACE
The Slag Granulation Plant of Rourkela Steel Plant is located by the side of NH-23 and at a
distance of 2 km from Tarapur Gate. It is in an area of 200 m X 400 m and has got a separate
boundary wall. The Plant was constructed by M/s Engineering Projects (India) Ltd. and was
commissioned on 31st March 1977 and has Capacity of 0.6 MT/year. The plant uses liquid Blast
Furnace Slag and converts into granulated slag which is used as input raw material in cement
plants for production of slag cement. The normally known Portland cement has almost same
strength and setting properties required for constructions but production cost of slag cement is
less than Portland cement. General lay out of the plant is shown in Fig. I.
CaO - 30-36%
SiO2 - 30-35%
Al2O3 - 18-26%
MgO - 10% Max.
MnO - 2.5% Max.
FeO - 1% Max.
S - 0.5-1.0%
CaO/ Si O2 = 0.96 Max
20 meters away from the chute in the storage bays along with the pressurized water.
Granulated slag in storage bay is dozed with the help of a dozer within the reach of the 2 nos. of
EOT grab cranes. The grabbing capacity of each bucket of the cranes is 3 m3. The liquid slag
residue, about 30% left over in the pot is removed at the de-sculling site of Scrap and Salvage
Department.
Ventilation System:
One centralized ventilation system has been installed on the floor of the sub-station building for
ventilation of pump house, sub-station, tunnel and control tower. Fifty meters away from sub-
station air intake house of size 1000 mm X 1600 mm is located and air is brought to the sub-
station through an underground air duct. Air is cleaned in filter panels installed in the air
intake chamber and cooled in the air washer and delivered by centrifugal fan at the rate of
40,000 m3/hr. The fan is driven by 15 kW motor.
The flow of air has branched out in the following manners:
a) For Pump House : 15,000 m3/hr.
b) For Sub-station : 13,000 m3/hr.
c) For Water Pipe Line Tunnel : 9,000 m3/hr.
d) For Control Tower : 3,000 m3/hr.
One booster fan of capacity 12,000 m3/hr driven by 3.7 kW motor has been installed at the
entrance of tunnel house to deliver air to tunnel house and control tower.
RE-CIRCULATION TANKS
Water, after use in granulation, flows from storage bay into 2 nos. recirculation tanks through a
filtering media provided at the outside wall of the tanks. Water flows from the filter to the
tanks through 11 nos. of pipes of diameter 200 mm. Each recirculation tank has got capacity of
110 m 3 located side by side. From the recirculation tank, water flows into 23 m long suction
channel from which water is supplied to the suction pipes of 6 nos. of granulation pumps. The
make-up water to the system is fed to the suction chamber through a 250 mm diameter pipeline
in order to compensate the loss of 40% of water during the granulation process.
PUMP HOUSE
The pump house is situated at 7 metres below the sub-station building. The pump house is
equipped with 6 nos. Centrifugal Pumps having capacity of 300 m3/hr each. Two dewatering
pumps are installed to take out leakage water inside the pump house. The capacity of each
Dewatering Pump is 10 m3/hr. The water from suction tank enters to the pump through suction
valve and strainer. From each pump, water comes to the ring main through non-return valve
and delivery valve. From the ring main water goes to nozzle box of hydro- chutes. The nozzle
box has got a plate having 53 holes of different diameter from 8 to 16 mm in order to release the
pressurised water to granulate the hot liquid slag. The pump house is connected to the
ventilation system. A manually operated 2 T capacity monorail hoist is provided in side pump
house for maintenance of equipments.
TUNNEL HOUSE
It is situated below the granulation bay. The major portion of recirculation water pipe line is
situated inside the tunnel house. Six vertical pipe tapings of 300 mm diameter each have been
taken from water ring main to nozzle box at granulatation bay for granulating liquid slag. The
tunnel house is connected with ventilation system. A Centrifugal Fan and an exhaust fan in the
tunnel house are used for of better ventilation.
SHIPPING
Material shipment is done by road only. Material from the storage bay is grabbed with the help
of EOT Cranes of 10 T capacity and filled in the steel hoppers and discharged in the trucks for
road dispatch.
PROSPECTIVE CUSTOMERS:
MAKE UP
WATER LINE
WATER RING
MAIN MECHANIC
AL
WORK
SHOP
PUMP HOUSE
SUB-STATION
CONTR
OL RECIR-
CR-816 TOWER CULATION
A B
GARRAGE
GRANULATION
DISPATCH BAY
CR-810
BAY
CR -814 A
ADM. BUILDING
FOR DISPATCH
CYCLE STAND
MAIN
NH -23
STEEL MAKING
Steel is made by LD process. Hot metal from Blast Furnaces, Oxygen (from Tonnage Oxygen
Plants) and Flux (from LDBP & CP-II) are the main input for steel making. Magnesia Carbon
bricks from the captive Brick Plant are used for carrying out converter relining. In addition,
purchased Magcarb bricks are also used for lining the converter.
Hot Metal and Scrap are charged in requisite quantity in converter. Oxygen is blown from the
top and flux is added in the converter in a continuous manner initially and subsequently as per
the requirement to facilitate steel production.
During oxidation of hot metal, impurities in the hot metal like C, Mn, P, Si get oxidised and are
separated by mixing them with flux (lime).The impurities thus generated are known as Slag
and are taken out in Slag Pots and dumped in Slag yard.
Steel produced in the converter is tapped into a preheated ladle, placed on the self-propelled car
below the converter (known as steel car). Ladle additives like Ferro Alloys and Aluminium are
added before/ during pouring steel in the ladle to produce/adhere to the composition of
required grades.
In early sixties SMS-I was commissioned with LD converters and later on a Secondary Steel
Making unit and a Continuous Casting unit were added to it. Hot Metal from different Blast
Furnaces is transferred to Hot Metal Mixers of SMS-I by locomotives. Using oxygen from TOPs
and Lime & Dolomite from LDBP, hot metal is converted to steel. For smooth production of
steel, SMS-I is provided with following facilities:
Mixers:
Two numbers of Hot Metal Mixers (1100 T Tons each) located at 7.5 mtrs from ground level
stage situated at both ends of Converter Shop to act as buffer storage. Homogenisation of hot
metal w.r.t. temperature and composition takes place in these Mixers. Temperature is
maintained by mixed gas burners.
LD converters
There are total two eccentric type LD converters in SMS – I having 66 T capacities each.
Converter is a vassal in which hot metal and scrap is charged and oxygen is blown from the top
through water-cooled 3 holes expansion lance. Fluxes are added from overhead bunkers with
the help of weighing hoppers and water-cooled chutes. Ferro alloys are added into tapping
ladles from the working platform.
DOLO
LIME 11 kg/T
91 kg/T
SCRAP
98 kg/T
Hot Metal
= 1041
Kg/T
INPUT
OUTPUT
Ferro-Alloys
(Fe-Mn, Fe-Si, Si- Slag
Mn) & Al 175 Kg/T
Special Alloys For
(Fe-Nb, Fe-V, Fe- disposal
Cr, Fe-Ti)
Blowing
Start blow with oxygen lance with height (working) as per the bath height measured. Before
lancing lance should be free from any skull at the nozzle and also water leakage. Then the
oxygen is blown. The agitation takes place which is indicated by luminous flame at converter
mouth. If agitation does not take place within 2 minutes then lift the lance jerk the converter 2
to 3 time and again blow it. Start adding lime as per silicon contain and loss of ignition of lime.
Add 50 % of total lime in three dozes within 4 to 6 minutes of blow start. Continue blowing up
to 6 to 9 minutes. Stop blow, lift the lance and deslag by tilting converter from backside pull pit.
Blowing oxygen pressure varies from 8 to 10 kg/cm2 and flow rate 9000 to 10000 Nm3/hr. any
deviation in blow pressure contact TOP-I, Instrumentation and Mech.
Add remaining 50 % lime in dozes during the second half of blow. Observe the flame, when
flame drops stop blowing. We can do straight blow without deslagging up to 6 to 9 minutes till
flame drop with some lime addition. Tilt the converter from back side pull pit for organizing
steel and slag sample and temperature. Take 1 to 3 slag sample per shift. FeO in slag should be
35 % max. If FeO is more then desired limit then following actions may be taken for next blow.
Corrective actions are taken based on above and add coke during blowing if necessary.
For low turn down temperature (<1580°C) add 200 kg to 500 kg FeMn or SiMn in the converter
by charging box. Rock the converter once and keep vertical. Blow at referred height. For each
minute of the blow the rise in temperature 12 ±2 °C approximately.
SLAG:
CaO - Al2O3 - SiO2
(50-55%) (30-40%) (5-10%)
In the continuous casting process, molten metal is poured from the ladle into the tundish and
then through a submerged entry nozzle into a copper mould cavity. The mould is water-cooled
so that enough heat is extracted to solidify a shell of sufficient thickness. The shell is
withdrawn from the bottom of the mould at a "casting speed" that matches the inflow of metal,
so that the process ideally operates at steady state. Below the mould, water is sprayed to
further extract heat from the strand surface, and the strand eventually becomes fully solid
when it reaches the ''metallurgical length''.
Solidification begins in the mould, and continues through the different zones of cooling while
the strand is continuously withdrawn at the casting speed. Finally, the solidified strand is
straightened, cut, and then discharged for intermediate storage or hot charged for finished
rolling.
To start a cast, a steel dummy bar seals the bottom of the mould. This bar prevents liquid metal
from flowing out of the mould and the solidifying shell until a fully solidified strand section is
obtained. The liquid poured into the mould is partially' solidified in the mould, producing a
strand with a solid outer shell and a liquid core. In this primary cooling area, once the steel
shell has a sufficient thickness, the partially solidified strand will be withdrawn out of the
mould along with the dummy bar at the casting speed. Liquid metal continues to pour into the
mould to replenish the withdrawn metal at an equal rate. Upon exiting the mould, the strand
enters a roller containment section and secondary cooling chamber in which the solidifying
strand is sprayed with water, or a combination of water and air (referred to as "air-mist") to
promote solidification. Once the strand is fully solidified and has passed through the
straightener, the dummy bar is disconnected, removed and stored.
BLAST FURNACE
HOT METAL
MIXER MIXER
CONVERTER CONVERTER
SSM UNITS
VAR VOR
LHF ARS
CASTER
SLABS
Steel Melting Shop (SMS) - II consists of a Basic Oxygen Furnace (BOF) Shop Complex and a
Continuous Slab Casting Shop (CCM-II) Complex. This Steel Melting Shop was added as a part
of RSP’s modernisation package in late nineties. Hot metal, Oxygen and Fluxes, the main input
materials for steel making are provided by Blast Furnaces (BFs), Tonnage Oxygen Plants
(TOP-I&II), Calcining Plant (CP-II) and Lime Dolomite Brick Plant (LDBP) respectively.
Capacity : 1300 T
Operating angle : 30o
Full emptying angle : 45o
Average hot metal temperature in mixer:
1250 to 1350oC.
Two Desulphurisation (DS) Units are provided for removing excess sulphur from the HM to the
acceptable norms before the HM is charged into the converter. This is being carried out by
injecting CaC2 /MgAl based compound as DS agent through top lance.
Two nos. of slag raking machines are provided to remove the slag from the HM ladles before it
is charged in the converter.
Converter Shop:
The shop is located at 9.5 m from ground level. Two
numbers of converters (150 T capacity each) of top
oxygen blown type were installed in this shop.
These converters receive HM and scrap with the
help of cranes and other input materials like Ferro
Alloys, Flux by mechanised (hopper with weighing
facility) as well as manual process. The converters
are concentric vessels manufactured from steel
plates and lined with basic refractories to sustain
desired temperature and corrosion during the
refining process. Oxygen supplied by Tonnage Oxygen Plants is blown into it from the top
through a water-cooled lance.
The scrap yard stores and provides the combination of light, medium & heavy scrap as per the
requirement of the shop. The crane used has magnets to do the loading and unloading.
LHF:
One LHF is used for homogenising and final adjustment of temperature and chemical analysis
of steel tapped from Converter before being sent to Casters for casting. LHF consist of:
- Ladle Car
- Electrode heating mechanism
- Water cooled roof with dust collector system
- Alloying system
- Wire feeding machine
ARS:
One ARS is used for homogenising and final adjustment of temperature and chemical analysis
of steel tapped from converters before being sent to casters for casting. ARS consists of:
- Alloying system
- Wire feeding machine
Casters:
There are 2 single strand slab casters and two turrets for
handling the ladles and providing steel on continuous
basis. They can rotate 360o and can lift two 240 T ladles
and rotate. The slab caster has a water cooled copper
mould, which gives the required dimensions of the slabs
produced. The strand produced is further cooled by water
sprayed through specially designed nozzles and simultaneously pulled out by drive rolls and
straightened. The continuous long strand is at suitable lengths to form slabs and are cut by
using transverse torch cutting machine, which moves along with the strand and cuts slabs
using oxygen and acetylene.
Slab Yards:
All the slabs produced are stored in two slab yards.
Slabs sent to Plate Mill are further cut to required
length before being dispatched. Hot slabs are also being
loaded in specially made flats to Hot Strip Mill. Two
slab marking machines have been installed for marking
slabs thereby reducing lead time.
Hot Metal
(Blast Furnaces)
Ferro
Alloys
LD Converters Ladle
(Steel Car) LHF /ARS
LD Gas
HSM & PM
Refractory Engineering (Services) department is responsible for maintaining the health of all
furnaces/kilns situated through out the plant. The major functions of the department are:
Cold & Hot Repairs of furnaces.
Capital & Mid. Campaign Repairs of all refractory lined structures.
Relining of Blast Furnaces Hot Metal Ladles, LD Converters, Steel Ladles, Tundishes,
Hot Metal Mixers, Limeshaft Kilns, Reheating Furnaces, Acid Proof Kilns in Cold
Rolling Mills & Silicon Steel Mills.
Carrying out technical modifications and improvements to increase the availability and
life of refractory lined furnaces, etc.
Preparing quantitative & qualitative requirements of various kinds of Refractories,
initiating for its procurement.
Follow up with Material Management to arrange supplies in time.
The total job of the department is carried out in four zones. They are as follows:
1. Blast Furnace Zone: Under this zone two types of jobs are taken up.
i) Routine Repair/lining jobs
ii) Capital Repair/lining jobs
There are two types of Capital Repairs under taken in Blast Furnaces.
a. Top Repairs: This involves dismantling of top stack, lining (badly eroded) and
then relining with new bricks. The total duration of this type of repair is
normally 14-15 days.
b. Complete Relining: This involves complete stripping of the furnace lining and
relining with new Refractories. The total duration of this type of lining takes
normally 70 days.
2. SMS-I&II Zones:
Under this zone two types of jobs are taken up.
a) Routine Repair/Relining jobs, of steel ladles, Mixer ladles, Tundish, Hot Metal
ladle etc.
b) Capital Repair and Major Lining Jobs.
Capital Repair Job – Hot Metal Mixers & Lime Kiln.
Major lining jobs – Lining of LD Converters
This zone is most important and vital among all the zones. To improve the availability of
LD Converter and Steel Teeming Ladles, numbers of steps have been taken from time to
time.
Lime Plant:
Lime Plant has a twin shaft kiln and a single shaft kiln to produce metallurgical lime for use in
LD converters of SMS-I as flux. Twin shaft parallel flow regenerating kiln namely Kiln No.5 is
of 150 T capacity per day and single shaft kiln namely Kiln No.8 is of 80 T capacity per day.
Lime stone is supplied by Ore Bedding and Blending Plant. Feed size of Lime stone is 40mm to
80 mm and CaO content is 53% min. Lime stone is stored in the High Line bunkers of LDBP
and charged in the Kiln by skip. Lime produced is stored in Kiln Bunkers and Classified
Bunkers and supplied to SMS through Belt Conveyors.
Mixed Gas is used as fuel for the calcination process and is supplied by the Energy
Management Department. Lime stone is heated in the kiln by burning mixed gas.
CaCO3 CaO + CO2
Heat input for Kiln # 5 is 850 Kcal per kg of lime and for Kiln # 8 is 1000 Kcal per kg of lime.
CALCINING PLANT – II
Calcining Plant-II (CP-II) was commissioned during modernisation in order to meet growing
demand of flux both in quality & quantity particularly of SMS-II & increased steel making
capacity after modernisation. Four lime Kilns of capacity 250 Tons/day installed in between
January 1997 and June 1998. 1st Kiln was commissioned on 12th January 1997. Lime Kilns
(four numbers) are of double shaft, parallel flow and regenerative type. Three kilns are
operated for Lime production and one for Calcined Dolo. Lime stone and Dolo Stone are stored
separately & screened before charging to the kilns. Calcinations are done by using mixed gas as
fuel. Though the installed capacity of each Kiln is 250 T/day, it is possible to operate the kilns
up to 270 T/day. Parameters like Production rate, Specific heat consumption & the stone per
skip are fed to the PLC. The other process variables are taken care by auto control system or
manual adjustment. Dust Extraction systems are available in this plant but Gas cleaning
facilities are to be renovated. A new dust cleaning system has been installed at screen house in
Dec-2007.
Raw Materials:
Limestone & Dolo stone are received from OBBP through belt conveyors and are stored in four
bunkers, each having a capacity of 500 T. Limestone and Dolo stone are screened & charged to
Kilns by skip car.
10 mm Screen
SMS-I & II
- 10 mm
SP-II and
Outside Sale
TOP-I was commissioned (1 MT Plant) in 1959-60 and expansion plant (1.8 MT) in 1966-67 for
production of Gaseous Oxygen at 99.5% purity at the rate of 3300 Nm3/hr & gaseous Nitrogen
containing less than 100 ppm of Oxygen at the rate of 6500 Nm3/hr. It comprises of 4 nos. of
Air separation Units (3 X 100 TPD & 1 X 200 TPD).
The basic principle involved is liquefying air by successive compression and cooling of
compressed air (the input material) and finally segregating the components Oxygen and
Nitrogen in Air Separation Units) through cryogenic distillation process. Oxygen and
Nitrogen thus produced are stored in identified storage tanks from where they are supplied to
the customers through header and pipelines.
• Oxygen, Nitrogen and Acetylene cylinder filling station for plant use.
• Medical Oxygen cylinder filling.
• High capacity High Pressure Nitrogen compressor has been added for meeting the High
Pressure demand for slag-splashing and gas recovery in BOF.
To meet the growing demand of Oxygen, Nitrogen and Argon, with the coming up of SMS-II,
TOP-II was added during modernization in 1993.
TOP-II comprises of two units of 180 TPD capacity. Each unit at TOP-II has got a capacity to
produce:
Oxygen : 180 TPD (with provision of 6.2 % in liquid form)
Nitrogen : 310 TPD (with 3.3 % in liquid form)
Argon : 5 TPD (gas or liquid)
TOP-II has liquid storage tank for liquid oxygen, Liquid Nitrogen and Liquid Argon. In mixed
mode operation, liquid products are transferred to the respective tanks. When the demand for
product gases is more than production, liquid is drawn from the storage tank, is vapourised and
supplied as gas to the product grid to meet the short-fall. Storage tanks are of following
capacity;
Liquid Oxygen Tank : 1000 M3
Liquid Nitrogen Tank : 1000 M3
Liquid Argon Tank : 20,000 Litres
- Wide flexibility of operation (80 % to 115 %) both in gas mode and mixed mode to take care
of fluctuating demand.
- Argon production facility using hydrogen injection for complete removal of oxygen from
argon
Oxygen:
- Reduction of hot metal to steel at SMS-I and SMS-II
Requirement per blow SMS-I : 3840 Nm3 at 16 Kg/cm2 (Min)
Requirement per blow SMS-II: 8500 Nm3 at 16 Kg/cm2 (Min)
- Enrichment of hot blast in Blast furnace
Requirement in BF-1 : 500 – 800 Nm3/Hr
Requirement in BF-4 : 1500 – 2000 Nm3/Hr
- Oxy-acetylene flame for slab cutting in CCM-I and CCM-II
Requirement 4 Nm3/TCS
- Oxygen lancing for scrap cutting in SMS-II
Requirement in SMS-II services : 1500 Nm3/hr
- Miscellaneous welding cutting jobs in Rolling Mills repair shops
Requirement: 1500 Nm3/hr
Nitrogen:
- Low pressure nitrogen in Cold Rolling Mill and Silicon Steel Mill for maintaining
inert atmospheric in furnaces:
Requirement is 9000 Nm3/Hr at 2500 mmWC
- Medium pressure nitrogen for desulphurisation unit in SMS-II and Instrument
Nitrogen for SMS-II
Requirement is 800 Nm3/Hr at 16 Kg/cm2
- High pressure nitrogen for various seals and purges in GCP of SMS-I and SMS-II
and gas recovery in SMS-II
Requirement in SMS-I GCP: 1500 Nm3/blow at 20 Kg/cm2 (Min)
Argon:
- LHF and ARS of CCM-I and CCM-II, Secondary Steel for making Steel
homogeneous.
- CCM-I and CCM-II for providing inert atmosphere during casting
- On line purging during tapping of Crude Steel in SMS-II
Requirement in SMS-I 72 Nm3/blow at 15 kg/cm2 (Min)
Requirement in SMS-II 90 Nm3/blow at 15 kg/cm2 (Min)
Filtration Cooling
Air
Warm Equipment
Cold Equipment
Hot Strip Mill (HSM) is a 1700 mm semi continuous mill comprising 2 Walking Beam Furnaces
of capacity 225 T/Hr., 3 Roughing Mills i.e. One 2-high Reversing Mill with powerful edgers
(Ro/Vo), One 4 high Reversing Mill (R1) and One 4 high Continuous Mill (R2), Coil Box, Six
Stand continuous 4 High Finishing Mill in tandem and 2 Hydraulic down Coilers. The Mill was
originally commissioned in February, 1961 and was subsequently revamped in 1980 for
computerization of Finishing Stands. During 1992-93 old Run Out Table (ROT) and Coilers
were replaced by the state of art ROT and Hydraulic Coilers during 1995 to 1999. Ro/Vo, Coil
Box, Quick Work Roll, Change Roll in Finishing Mill, High Pressure Descaler, Walking Beam
Furnace were installed under modernisation programme for rolling heavier and longer slabs to
coils. The HSM was originally designed and commissioned on turnkey basis by the M/s.
DEMAG AG, West Germany. The main mechanical equipment were supplied by M/s. DEMAG,
M/s. SACK, M/s. SCHLOEMANN and mill drives by M/s. SIEMENS and M/s. AEG (All firms of
the then West Germany).
It is designed to roll the slabs of thickness 150 – 220 mm to finished strip gauge of 1.8 to 12.5
mm in 725 – 1550 mm width. The annual production capacity of the mill is 1.44 Million Tons of
slab weight.
The HSM being an integrated unit of RSP supplies Hot Rolled Coils as input materials to its
downstream customers such as Cold Rolling Mills, Silicon Steel Mill, and Pipe Plants and also
to Dividing Line. It also caters to the requirements of external customers.
There are also 4 nos. of fixed skid pipes inside furnace on which the slabs rest while in
stationary state. Tracking and heating of slabs to required temperature is done by
computerized thermal model. Once the slab reaches the discharge end, it is detected in the
discharge pulpit by the Gamma ray system provided at the discharge side. After slab detection
and getting clearance from R1 cabin, slab is extracted from furnace by extractor and is placed
on the discharge roller table and sent to Ro/Vo through primary descaler for rolling.
PRIMARY DESCALER:
To remove the scale formed on the surface of slabs during its heating inside furnaces, water jet
at high pressure of 145-160 Bar is applied on top and bottom surface of slabs.
COIL BOX:
The Intermediate Transfer Bar after R2 travels through the
Delay Table to Coil Box, where it is coiled in hot condition and
subsequently uncoiled to feed tail end of transfer bar into the
Finishing Mills. In general coils with finish gauge less than 5
mm are taken through coil box where as for finish gauge more
than 5 mm are taken directly to Finishing Mills in Pass
Through Mode (PTM). The head end of the transfer bar/
Coiled transfer bar is cropped at Crop Shear and after
descaling at scale washer pinch roll, the transfer bar enters
the Finishing Mill for rolling to the required gauge.
COIL BOX - Coiling and Uncoiling Device for Intermediate Transfer Bar
MAJOR COMPONENTS:
Entry Side Guides, Top Bending Rolls (2 Nos.), Bottom Bending Roll, Cradle Rolls # 1, Forming
Roll, Adjustible Side Guides, Mandrel Peelar Main Arm, Cradle Rolls # 2, Pinch Roll
FINISHING MILL:
The bar enters 6 stands, 4 high continuous mills
where reduction is given to the bar in each stand. In
between the stands, loopers are provided to
maintain constant tension. There are two R-30
process computers of Siemens make. One is speed
computer, for regulating the speed of all mill
stands, ROT, coiler wrapper rolls and mandrel. The
other one is AGC computer for automatic gauge
control to get uniform thickness of the strip. AGC
hydraulic cylinders are provided in last four stands
F3, F4, F5, F6. After rolling in finishing stands, the strip temperature is controlled on Run Out
Table (ROT) by laminar cooling by water through cooling banks. There are 4 nos. of Cooling
banks. There are 4 nos of cooling banks, each having
COILERS:
The strip moves over ROT and gets coiled in one of the two hydraulic down coilers. There are
two Hydraulic down Coilers each having three Wrapper Rolls. Coils are taken out from coiler
and placed on Conveyor # 5. The hot coils are circumferentially strapped on the body by
Automatic Strapping Machine and marked for identification. Necessary samples are cut from
the coils for its testing. Coils are then transferred to coil yard where coils are allowed to cool to
room temperature before they are sent for further processing in different units of RSP (i.e.
CRM, SSM, ERWPP, SWPP & Dividing line of HSM) or to the external customers of HR Coils.
The capacity of the Coiler is 17.5 Tons (max.) coil weight.
MAJOR COMPONENTS:
Side Guides, Hold Down Roll, Top Pinch Roll, Bottom Pinch Roll, Entry Table, Wrapper Rolls (3
Nos.), Mandrel with Outboard Bearing, Coil Car Upender
PARTS OF COILER
1. Top & Bottom Pinch Roll
2. Three Numbers of Wrapper Rolls.
3. One Mandrel with Two Stages of Expansion.
4. Coil Car for Taking out The Coil
5. Centering Arm for Lifting Of Coils
6. Tilter for Tilting the Coil to the Conveyor
7. Mandrel Dia: 762 – 740 – 725 MM
Hold Down Roll for Preventing Tail end Shifting
(SHIPPING AREA)
DIVIDING LINE:
Hot Rolled Coils meant for converting into HR plates are uncoiled in Uncoiler, levelled in
Leveller-I and then sheared at Dividing Shear to the required lengths as per requirement of the
customer. After shearing, the plates are levelled once again in Leveler-II and piled in Pilers.
HR Plates of sizes 3.6 mtrs. to 10 mtrs. in length and thickness of 5 mm to 10 mm are cut.
There is also provision of plate inspection for both the sides each plate at Plate Turn over
Device (PTOD) before Piler.
PURPOSE:
SHEARING OF HR COIL TO PRODUCE HR PLATE
MAJOR EQUIPMENT
HR PLATE DETAILS
R1
MATERIAL FLOW INHOT STRIP
R2
Coil Box
Crop Shear
Through Scale Washer
MILL Hot Strip Mill
Coilers
HR Coils for
Shipping
PLATE MILL
Plate mill of Rourkela Steel Plant was commissioned on 13th September 1960. This is first Plate
Mill in the SAIL as well as in the country. This is 3.1 m, 4 high reversing mill. This mill is
certified with ISO 9001 & 14001 certificates. Over the years plate mill has been achieving new
heights. In financial year 07-08 mill has achieved 103% of ABP. The Techno economic factor is
one of the best tools to make judgment about the performance of any unit in an integrated steel
plant. For the sake evaluation data of some of the important parameters are given below:
In our plate mill we make plates from slabs which is mainly supplied to us from Continuous
Casting Machine I (CCM I) and Continuous Casting machine II (CCM II).
Our Input Slab and Finished Plates dimensions are as follows:
SLAB YARD
Slab Yard is the entry point of Plate Mill. It is situated in AB bay. In our plate mill input slabs
are received mainly from CCM I & CCM II. Apart from this input for special plates are also
received from Bokaro Steel Plant and Durgapur Steel Plant. It has a capacity to store 900 slabs.
For smoothly running of plate mill 600 slabs should always be present. The minimum weight of
slab is 3.1 tons and maximum weight being 6.9 tons. There are total 5 cranes for handling of
slabs. Slabs are kept in piles and 1 pile generally has 6 numbers of slabs.
Furnace Area
Furnace area can be divided into three sub groups as follows:
i) Charging Roller Table & Pusher
ii) Walking Beam Furnace
iii) Slab Extractor and Discharge Roller Table
iv) Primary Descaling
iv) Primary Descaling: In this unit the scales generated during reheating of slab inside
walking beam furnace is removed by impinging jet of water. This unit is a box type. As the
slab enters this unit an HMD (hot metal detector) senses it and water impact starts on slab
at very high pressure of @ 100kg/cm2. Water is sprayed through nozzle.
Mill
Plate mill is 3.1 m wide single stand, four-high
reversing type mill designed to roll medium and
heavy plates. The mechanical equipments are
supplied by M/s. KRUPP whereas the drives are
mostly supplied by M/s. AEG, both firms belongs to
Germany. Mill is having two working rolls of 1000
mm x 3100 mm size and two back up rolls of 1500
mm x 3000 mm size. The only work of the mill is to
give draft to the slab to convert it into desired plate.
The number passes to be given depends on slab and
final plate size. Draft to be given mainly depends on temperature of slab. In any case maximum
draft given is 15 mm or 20% of the instant thickness of plate whichever is less.
Features:
1. Dot matrix paint marking head with electro-magnetic activated spray guns and
activated punchers.
2. Trolley for the movement of marking head and punching heads.
3. Overhead structures/guides on which the above item moves.
4. Control panel with PLC for machine control and host communication.
5. Drive panel with driver electronics for the paint spray guns and punch marking heads.
6. Operation terminal –HMI- monitor and keyboard
7. Maintenance/Service panels with manual push buttons for maintenance
operation(mounted over machine)
8. Combined paint/pneumatic supply unit.
The punch head have one punch section with 4 punchers and the paint head have 8 paint
sections.
Marking Details:
• Position of Marking - Along the centre line of the plate
• Direction of Marking - Lengthwise paint
• Characters pattern - Standard 9 x 7 Dot Matrix (WxH)
• Characters - Alphanumeric
• Height of Characters - 40 mm
• Number of Lines - 8 (Eight)
• Number of Characters/Line - 20 Alphanumeric (Maximum)
Punching Details:
• Direction of Marking - Crosswise to Plate conveyance
• Characters pattern - 9 x 7 Dot Matrix (WxH)
• Characters - Alphanumeric
• Height of Characters - 10.5 mm (Approx)
• Number of Lines - 3 (Three)
• Number of Characters/Line - 16 Alphanumeric (Maximum)
Benefits:
I. Improvement in Manpower Productivity: Earlier 6 operators/shift were engaged in
manual marking and punching operation. Now only 2 operators/shift are operating the
new marking & punching machine.
II. Operator gallery no 4 for inspection bed drive has been removed and dismantled which
is now being operated by marking operators in the new cabin made for marking
machine. Thereby reduction of manpower i.e. 1 operator/shift.
III. The total reduction of manpower is 5 per shift i.e. 15 nos and same have been re-
deployed which was helped in introducing 7 days working in plate mill.
IV. Elimination of hazardous and tedious operation of manual spray paint marking and
punching and improving the safety and moral of the operation.
V. Drastic improvement in customer satisfaction as well as marketability of the product.
VI. Elimination of incidences of mix-ups in plates at the finishing/shipping stage, due to
illegible marking.
VII. Elimination of incidences of wrong shearing of plates due to illegible marking
Page: 83 HRD Centre
Rourkela Steel Plant
VIII. Faster loading and dispatching due to proper identification and
traceability of various grades and sizes of plates
IX. Constant paint circulation and intermediate cleaning of spray nozzles by mixture of air
and water will prevent clogging of pipelines and nozzles.
X. Better record keeping and retrieval of marking and punching records for references.
XI. Faster processing of plates in inspection beds thereby reducing the cooling bed delays.
NEED:
I. To cater to growing demands of UST plates.
II. To match with normalized and ultrasonic tested plate demand of 10,000 TPM Approx.
III. Defect liquidation by paint marking.
IV. Quick and easy liquidation of defects.
The proposed scheme is intended for non destructive ultrasonic inspection of plates online.
Plate Parameters:
• Length - 2,500 mm to 27,000 mm
• Width - 850 mm to 3,000 mm
• Thickness - 5 mm to 80 mm
• Scanning speed - 60 m/min
• Plates will move on Roller Table for online scanning.
• Paint marking on the top of plate to show defect locations.
• Testing Zone - Full Body Testing
Benefits:
Improvement of market share for quality plates.
Higher capacity production of UST plates without addition of manpower.
Online facilities with high speed inspection, data acquisition, analysis, retrieval &
storage facilities.
Net margin to go up.
High internal rate of return and payback of project.
5. Dividing Shear
The shear serves for dividing and cropping plates in the cold state. For dividing plates a gauge
is arranged at the back of the shear making it possible to set precisely every plate length within
the range of the gauge.
7. Normalizing Furnace
Normalizing furnace is used for gaining some specific physical metallurgical properties
required in some plates. It is not carried out for all plates. Whenever it is required by customers
we do normalizing on specific plates. There are 3 zones in the New Normalising Furnace named
as Zone I, Zone II and Zone III. Each zone is 15 m in length.
Zone I: Zone I is also known as Pre Heating Zone. The temperature in this zone is in-between
850 – 880 OC. There are all total 44 Burners in this Zone, 30 in top and 14 in bottom.
Zone II: Zone II is known as Heating Zone. The temperature in this zone is 910 – 930OC. There
are all total 48 burners, 32 in top and 16 in Bottom.
Zone III: Zone III is called Soaking Zone. The temperature in this zone lies in between 910 –
930 OC. There are all total 44 burners in this zone, 30 in top and 14 in bottom. Mixed Gas
mixed with air is used as fuel in the furnace and the maximum temperature in the furnace is
950OC.
PIPE PLANTS
Rourkela Steel Plant, a giant manufacturer of steel pipes, has two mills having combined
production capacity of 1,30,000 T of steel pipes per annum. All these steel pipes are produced in
two independent production lines viz.
1. Electric Resistance Welded Pipe Plant (ERWPP) having capacity of 75,000 T per
annum.
2. Spiral Welded Pipe Plant (SWPP) having capacity of 55,000 T per annum
Both the pipe plants are accredited with ISO 9001:2000 QMS, APIQ1 and ISO 140001:2004
EMS certified.
PRDODUCT RANGE:
DIAMETER (Outside Diameter): 8 5/8”, 10 ¾”, 12 ¾”, 14”, 16”, & 18” OD
WALL THICKNESS: 3.2 to 12.7 mm
GRADE: API 5L GR-A, GR-B and up to X-70 PSL 1 & 2 IS 3589 grade Fe 330, 410 & 450
INPUT MATERIAL:
The orders from different customers are conveyed to the ERW pipe plant through PPC
department. After the campaign size is decided PPC plan for the required steel and
subsequently gets rolled at HSM.
Specification of HR Coils:
Width – 693 to 1550 mm, Coil weight – 15 T max, Thickness - 3.2 to 12.7 mm,
Coil ID - 760 mm, Coil OD – 1100 to 1800 mm max.
All the processes are PLC controlled and all the entries,
information’s are logged and shared at the computers
through level-II automation system available at every
work stations. All the drives are powered by AC motor
with VVVF control.
ENTRY SECTION:
Coil Saddles: Four Saddles are provided near uncoiler to ensure a steady supply of hot rolled
coils to the uncoiler unit.
Coil Car: 5.5 KW AC operated Coil Car mounted on rail transfers the coils one by one from the
coil saddles to the uncoiling unit. Coil supporting cradles are provided on the coil car to support
all the coils to be handled for different sizes. The lifting and lowering of the cradle is brought
about by hydraulic mechanism.
Dual Uncoiler: The primary function of the dual uncoiler is to receive the coil from the coil car
and to feed it into the leveling unit. The uncoiler holds the coil during the opening process and
controls the uncoiling of the strip. It receives the coil from coil car and feeds the strip to leveling
unit by opening the coil front end by the peeler table and bending roll.
Pinch roll and Leveller-I : Pinch roll is provided for receiving the leading end of the strip and
feed it to the 5 roll leveler for flattening the whole length of the coil for subsequent forming in
the ERW mill.
Strip Centering Devices: There are five numbers of strip centering devices for aligning the
strip along with the centerline of the mill
LOOPER PIT:
Purpose of the looper pit is to keep a certain reserve of strip, so that during stand till of the line
for joining the strip- ends, strip can be pulled back by the main pinch roll 2 for cutting the crop
end (Tail end of the coil). The loop height is sensed by a sensor and a constant height is
maintained to prevent excess tension by regulating the speed of the pinch roll 2 & 3 located at
the both ends of the pit.
STRIP UST:
UST for the strip has been provided to detect the lamination and other similar defects of the
incoming strip. The system consists of ECHOGRAPH 1155 electronic equipped for 16 channels
Transmitter/receiver unit. SEE ultrasonic-amplifier between probes and ultrasonic electronics,
for long cable length to prevent disturbing noise by influence from other power stations. The
system provides the data administration system (DAV) which administers testing and order
parameters and is connected to the subordinate computers of the ultrasonic testing (USEL) via
interfaces. The DAV additionally shows all the states of operation as well as disturbance and
warning reports of ultrasonic testing electronics (USEL) and connected computer modules.
There are 12 nos of probes which cover the strip body and 4 nos of probes at both the edges for
testing.
FORMING SECTION:
• STICKER STAND: After the strip UST strip enters in to the forming section. First
unit of the forming section is STICKER stand. It is fitted with cylindrical rolls and
serves as a pinch roll unit for feeding the strip further. Screws down arrangements are
there for making top and bottom rolls up & down.
• PREFORMING SECTION: It transforms the flat strip into a shape which assists
the formation of the pipe in the subsequent breakdown stand. There are eight pairs of
idle supporting rolls arranged in a V-shape. The angle of the first pair of rolls remains
unchanged for different diameter pipes; however the final V- angle of the last pair of
rolls, close to the breakdown stand can be adjusted. The adjustments of the rolls are
motorized. When the strip edges are bent upwards by the supporting rolls, the center of
the strip is kept down by 4 idle top rolls provided in a frame. The height of the frame is
adjustable.
Page: 89 HRD Centre
Rourkela Steel Plant
• BREAK DOWN STAND: It is fitted with the top & bottom forming rolls and serves
for proper bending of the strip entering the edge bending unit.
• EDGE BENDING UNIT: It is a top & bottom roll arrangement with all
adjustments facility where when the strip passes through this unit, the pre forming is
being done at the edges for better forming at the weld point.
WELDING STAND:
The welding of pipes is carried out in a state of the art High Frequency Induction Welding
Machine. It is induction type welding of 1000 kW capacity and 200 Hz frequency. The open pipe
enters the welding stand where the strip edges are subjected to high frequency current of about
200 Hz by induction process. This generates required heat along the face of the strip edges for
welding. The heated edges of the strip are then firmly pressed together by means of squeeze
rolls, bottom roll and pair of pressure rolls to complete the welding process. The seam is thus
formed from the strip without filler metal. HF welder has two major functional units:
• Control and rectifier unit(CRU)
• Inverter, Matching and compensating unit (IMC)
The CRU unit is located at some distance behind the line, the IMC unit is located on a
positioning table close to the line between the seam guide and weld squeeze roll unit. The two
units are connected with a 10 meter long special DC cable. The CRU consists of input section,
control section and rectifier section. The control section contains operating equipment and
provides the interface with the external control equipment. The rectifier section has the main
isolating switch and a full bridge diode rectifier that converts the main voltage to DC voltage.
The IMC consists of the inverter module, a matching transformer and a capacitor bank
supplying the necessary power for the induction coil.
respect to the pipe. The welder can be operated in three modes like Manual, Power and
Temperature and it has an integrated control in which the following data is being monitored.
• Welding speed
• Welding temperature
• Welding power
ID BEAD TRIMMER:
Excess squeezed out internal bead is cut continuously as the welding proceeds by internal
carbide tool. This equipment has rigid cantilever support and cantilever tool holding arm
carries a tool holder at its extreme end. Tool holder has provision of internal tool fixing. The
cantilever arm is operated hydraulically. The ferrite beads required for HF welding is mounted
on its arm with all water cooling arrangement.
OD BEAD TRIMMER:
Excess squeezed out external bead is continuously cut external tool. Here movement of the
cutting tool is actuated pneumatically.
SIZING STAND:
The very function of the sizing stand is to make the pipe to accurate dimension by giving
reduction to 1% max. Sizing stand consists of pull out stand and sizing stand No.1,2,3. In
between sizing stand No. 2 and No. 3, there is a turk head which helps to make the pipe
straight. All these stands are four roll pass. The turk head can be adjusted up/down and
left/right. It is fitted with the encoders for its position recording.
FLYING CUT-OFF:
In this machine pipe is cut to desired length in running condition.
The main components of the fly cut off m/c are-
• The base frame
• The cutting carriage
• The disc cutter
Page: 91 HRD Centre
Rourkela Steel Plant
• The clamping devices
• The carriage drive system
• The cutter feeding hydraulics
Since there is a constant bottom line, the center line of the m/c is height adjustable by
motorized lifting jacks. No of cutting knives mounted are 6. The carriage drive system consists
of an AC-servo motor with built in encoder. The motor is flanged directly to planetary gears
which are attached to the base frame. The carriage drive system gets information about the
length and speed of the pipe emerging from an incremental encoder, coupled to a measuring
wheel. When the desired length has passed the measuring wheel, the PLC submits the start
signal and the carriage accelerates with the pre- set rate. The built in encoder of the driving
motor submits the information about the carriage speed and the carriage position to the PLC
the PLC compares the pipe speed, recorded by the measuring wheel encoder and the actual
carriage speed. When both the speeds are synchronized, the cutting signal is provided for
clamping and feeding of the cutter. After the cut has been performed the cutter knives are
retracted to the initial position and clamp is open, the carriage drive gets the signal for
reversing.
STRAIGHTENING MACHINE:
The function of this m/c is to straighten the pipe. There are 5 top rolls and 2 bottom rolls
arranged in such a position that it gives the required bending moment to make the pipe
straight. After the pipes are straightened, each pipe is numbered with a unique number for its
traceability.
BEVELING MACHINE:
After the pipes are numbered, it is brought to the beveling m/c for end facing. The beveling
angle is maintained 30-35 degree with the root face 0.8 to 1.2 mm to facilitate the pipe end to
end welding at the field. It consists of-
• Pipe loading
• Roller conveyor 1 & 2
• Cross transfer system
• Long travel system 1 & 2
• Machining station 1& 2
• Delivery rack
The machine station mainly consists of main spindle head stock and the clamping device,
mounted on a common base table. The clamping device is hydraulically actuated. The main
spindle head stock contains the main spindle drive and the spindle feed drive.
HYDRO-TESTING PRESS:
Here all the pipes are hydro tested after sealing both the
ends from outside to the required pressure as per the
specification. The maximum pressure it can test is 250
Kg/cm2. Hydro tester operates in sequential operation
through a set of sensors and timers by PLC for the full
testing cycle. Filling pump fills the required filling water
at a preset pressure in the accumulator tank. Oil to water
intensifier preset at the required water testing pressure
operates in sequential operation till the set pressure is
achieved and thereafter stops automatically. Thus testing is carried out in isolation system.
Recorder is provided to record the test pressure and pressure holding time against the each
pipe number.
SHIPPING:
The pipes are dispatched as per the movement plan in Trailer/Truck or wagon as per the
requirement. Pipes are rust preventive varnish coated before dispatch if the customer desires.
H R Coil
Through Coil Saddle Coil Car, Uncoiler
Leveler and Edge Milling Machine
These pipes are available in API – 5 L, IS 3589, IS 5504 and also in works tested commercial
quality (CQ) for application ranging from high pressure transportation of crude oil and natural
gas, slurry transportation, water supply and sewerage disposal to civil engineering pilings.
In the pipe-forming device the coil is formed to a pipe according to the principle of multi roller
levelling. The coil edges running together with the pipe forming device are first welded inside
and then outside by Submerged Arc Welding Process.
A travelling Oxy-acetylene torch cuts off the pipes to required length, as per customer
requirement. Pipes are tested in accordance with specifications of the standard / customer.
End Grinding:
In this work station end grinding of machine gas cut
pipes is done to make the ends smooth and free from gas
cut burrs. Inside and outside surface of weld seams of
pipes are ground, as marked, at inspection stand.
X-ray Screen:
This X-ray screen station is used to observe flow in weld
seam, which is not visible and this helps in process
control.
Final US Testing:
A continuous Ultrasonic check is provided here after end bevelling of pipes.
X-ray Unit:
The first step of final inspection is x-ray photo control of weld seam at pipe ends. This is done at
second X-ray station.
Weighing of Pipes:
Finally the pipe is passed through the electronic weighing
station and leaves the building through the skid to a storing
area from where the pipes are taken by EOT out door cranes for further storing and dispatch.
1.1 SWPP produces Spiral Weld Pipes from 16” dia to 64” dia. Hot rolled coils are formed in
to pipes in the forming cages of M 2.1 & M 2.2 m/cs. Automatic dc submerged arc
welding is done at inside of the pipe first which is followed by outside welding. Outside
welding is to be done exactly in the same inside weld joint.
Laser Seam tracking system tracks inside weld seam & adjusts the outside weld head so
that outside welding is done exactly on inside weld joint. The laser camera is mounted at
the outside weld head such that laser light is focused sharply at 90 ° to the inside
weld joint. The vision camera continuously detects the “V” joint & sends digital
signal to the controller. The controller processes the signal & adjusts the outside weld head
such that the welding torch continuously follows the inside weld joint.
2.2 Features:
The operator of external laptop computer can programme different types of joints. The
joints are then saved in the non-volatile memory of vision controller. After joints have been
programmed laptop computer is no longer used. However the computer can be used during
tracking process to display useful information such as profiles & status information.
3.0 Operation:
The day to day operation of the EZ-TRACK/IT system can only be accomplished using
teeth pendent. All necessary commands, either for controlling the tracking process or for
HRD Centre Page: 98
Panorama 2012
selecting tracking parameters are accessible to the operator through the teeth pendent.
Digital I/Os allow the PLC programme to perform exactly the same operation as the
operator can do through the teeth pendent.
3.2 Calibration:
In automatic mode, the EZ-TRACK / IT tracks the joint, maintaining the torch at the same
position relatively to the joint. The relative position between the joint & the torch might
however be adjusted before welding in order to obtain the optimum welding conditions.
This operation is called calibration.
During the automatic tracking mode, the operator can add offsets to the tool position by
pressing the offset button & using the joystick simultaneously.
Coil
Preparation
Stand
Forming
Cage
Outside
Repair X-Ray Grinding Welding
Welding Station Station (Skelp Joint)
Electronic
Final Works
Dispatch Weigh Inspection Inspection
Bridge
Rourkela Steel Plant (RSP), SAIL, has recently set up a 3LPE Pipe Coating Plant for applying
coatings on external surface of the pipes. The products of the 3LPE Pipe Coating Plant shall be
supplied to the oil and hydrocarbon sector and shall meet all the requirements as per the DIN
30670 Specification.
The plant has been setup with Tech-know how from M/s Socotherm SpA, Italy. The Plant is in
adherence with the Pollution Control Norms as per European Standards.
CORROSION PREVENTION
The principal methods for corrosion prevention on underground pipelines are coatings and
cathodic protection.
• Coatings are intended to form a continuous film of an electrical insulating material over
the metallic surface to be protected. The function of such a coating is to isolate the metal
from direct contact with the electrolyte, interposing a high electrical resistance so that
Electrochemical reactions cannot occur.
• Cathodic Protection (CP) is a technique to reduce the corrosion rate of a metal surface by
making it the cathode of an electrochemical cell. This is realized by shifting the potential of
the metal in the negative direction by use of an external power source. For CP to work,
current must be discharged from an earth connection called a ground bed. In the process of
discharging the current in a sacrificial system, the anodes in the ground bed are consumed
by corrosion
Three Layer
Three-layer polyethylene coatings were introduced about 1980 in Europe. They consist of:
• FBE primary coating
• Polyolefin-adhesive (or tie) layer
1. Layer 1: Immediately after abrasive blast cleaning the layer shall be formed by a film of
liquid epoxy or resin of powder. The minimum dry thickness shall be between 20 and 60
microns checked in accordance with method 5 of ISO 2808 depending on the primer used. The
thickness may be subject to agreement by the customer, and to conform to manufacturer’s
recommendations.
2. Layer 2: A polymer intended to provide adhesion between first and third layers and be
compatible with those layers shall form this layer. The minimum thickness shall be between
140 and 200 microns depending on the type of adhesive and the application. The thickness may
be subject to agreement by the customer, and conform to manufacturers recommendations.
3. Layer 3: Polyethylene coating shall form this layer. The thickness shall be uniform and the
minimum total thickness shall satisfy the requirements of DIN 30670 or as per the customer
requirement. This layer gives the mechanical protection to the 1st layer and is also corrosion
resistant to some extent.
Special Plate Plant (SPP) is a valued unit of Rourkela Steel plant. SPP was set up in 1969 to
cater the needs of country’s defense and research programs. It’s the only unit of its kind in the
nation. SPP is pioneer in the field of special steel plates; with a diverse product profile that
ranges from various grades of heat treated plates of high hardness and strength to dead
annealed plates of high resilience and ductility.
SPP products are used in various high end application e.g. T-90 tanks, MBT Arjun tanks, Ship-
building, anti mines vehicle, atomic research etc. SPP takes pride in meeting the stringent
Quality control norms of defense agencies (CQA (MET), OF CELL, DQAE(N)).
Products:- Spade Heat Treated Plate, Spade Dead Annealed Plates, Jakal heat treated
plates, jakal dead annealed plates, spade gas cut components, spade machined components,
navy grade plates.
Grades/Specification:
Jackal: CQA(M)47, Spade: CQA(M)51 & CDA99, Navy Grade: DMR 249A & DMR 249B,
SAILRATH, HARDOX, TARGET
Customers:
ORDINANCE FACTORY, MEDAK, HVF, AVADI, VF, JABALPUR, DMRL, HYDERABAD,
IGCAR, KALPAKKAM, MIDHANI, HYDERABAD, CVRDE, AVADI CSL, COCHIN, GARDEN
REACH SHIP BUILDERS, KOLKATA, TERMINAL BALLISTIC TEST LABORATORY,
CHANDIGARH
Alloy steels which are used for making armor plates are produced at ASP, Durgapur. Navy
grade steel is produced at BSP, Bhilai & ASP, and Durgapur. Slabs are rolled at plate mill of
RSP. Input material for SPP is plates rolled at plate mill of RSP. Following diagram illustrates
material flow for armor plates.
Plates received from plate-mill in rolled condition are strain hardened due to rolling. Grains are
elongated in rolling direction. Machining/grinding of plates in rolled condition is difficult; hence
soft annealing is done to improve grindeability. However for navy grade plates soft annealing
and grinding is not required. Soft annealing cycle comprises of slow heating up to 7100C in 24
hours, soaking for a period of 16 hours followed by furnace cooling up to 1000C. It relieves
stresses, reduces strain hardening and improves machinability. There are two furnaces used for
soft annealing; namely S/A furnace and S/R furnace (both in BC bay).
MATERIAL FLOW
ULTRASONIC TESTING
Top grinding is done to remove surface scale and minor defects from the plate, so that
ultrasonic test can be carried out on the plate. Testing is done by Research and Control Lab
staff. Ultrasonic testing is done to detect defects in metal. After testing, SPP index nos of the
plates are stamped on the defect free plates and plates are sent for flame cutting. Size cut
plates are then sent for primary inspection and bottom grinding. After bottom grinding
thickness is measured and plates are sent for heat treatment/dead annealing.
Heat Treatment
Heat treatment is the most crucial operation among all. The objective of heat treatment is to
impart desired mechanical properties (hardness, YS, UTS etc.) to metal by various meticulously
chosen heating and cooling schedules. It consists of following operations.
Hardening comprises of heating the plates to desired temperature, soaking for some duration
depending upon the thickness of plate and then rapid cooling (quenching) in oil/water. It
transforms microstructure of steel to martensite.
Tempering Steel in as hardened condition is highly brittle and requires further treatment
before it can be used in various applications. A heat treatment cycle, called tempering is
applied for improvement in ductility/toughness. Tempering comprises of heating to a fixed
temperature (which depends on thickness) and for a fixed time.
Hardening Furnace:-
Its capacity is 9 meters in length and 2 meters in width. This furnace uses mixed gas as fuel.
There are two zones in the furnace; each zone has different control valves for air and fuel.
Tempering Furnace:-
Tempering furnace comprises of four zones; 1 and 2 are heating zones, and zone 3 and 4 are
soaking zones. Total length of the furnace is 16 meters and width is 2 meters.
Cold Rolling Mill is one of the complex units of RSP, producing bulk amounts of quality finished
steel. Purpose of cold reduction is to achieve the following:
(i) A reduction in the thickness of the final product.
(ii) A designed surface finish.
(iii) Desirable mechanical properties.
(iv) Close dimensional tolerance.
(v) Producing as per customer requirements.
The input to Cold Rolling Mills is the Hot Rolled Coils (HR Coils).
HR Coils
PL-2 PL-1
CAL HAL
SP-1 SP-3
Legend: HR: Hot Rolled, PL: Pickling line, CR-1: Cold Reversing Mill-1,CAL:Continuous
Annealing line, HAL: Hood Annealing line, SP: Skin Pass Mill, CPL: Coil Preparation line,
ETL: Electrolytic Tinning Line, SSL: Sheet Shearing line, GP/GC: Galvanised plain/Galvanised
Corrugated , ETP: Electrolytic Tin Plates, CR: Cold Rolled.
The material flow in both the units is more or less same except for the above differences.
The material flow in Pickling line No.-II is:
Coils from HSM → Coil Conveyor → Coil ramp → uncoiler → Leveller → Crop shear →
Welding machine (with bead planner) → Stitcher → Pinch Roll-1 → Wet looping Pit →
Scale Pit → Deflector Roll (Delivery Set) → Side Trimmer → Oiling Machine → Lateral
Strip Guide → Up Coiler → Binding Station → Coil ramp → Coil Receiving Device →
Coil Conveyor → Weighing Machine → Coils to Tandem Mill → Coil Storage.
In the acid tanks (numbered from the entry side) the Strip and the concentrated acid
move in Counter direction. The Acid Concentration, Salt Concentration and temperature
are shown below.
The temperature is controlled by Steam heating. The spent liquor from Tank is sent to
the Regeneration plant where the Ferrous Sulphate is separated by Crystallisation
and Refrigeration Process and the acid is brought to original concentration by adding
new makeup acid.
Cold Rolling:
The next operation is the cold reduction of the pickled coil. After pickling, the main cold rolling
operation, i.e. cold reduction, is performed in cold reduction mill where pickled strip is fed
between very hard rolls. This is done
• Either in a single reversing stand, equipped with an uncoiler and a coiler, by making several
passes in reversing directions;
• Or In a continuous tandem mill where the strip is engaged in several stands simultaneously,
enabling high-tension force to be applied. In CRM, Cold rolling is done in two mills:
Annealing Process:
Cold rolled strip as such is not suitable for drawing and deep drawing operations due to
lack of ductility. The loss is caused by the work hardening effects of cold reduction. After
the cold reduction process, the internal structure of the steel is as follows:
1. The grains in the steel have been elongated in the direction of rolling.
2. Longitudinal rolling stresses have been set up in the steel and any foreign matter
present in the core zone of the rimmed steel have been rolled out into the form of
segregated bands.
3. The steel being very hard and brittle will fracture very easily in the direction of
transverse to the rolling.
4. Myriads of stress points are found to be present in each grain.
Now these CR coils are to be annealed to remove the stresses. The various purposes of
annealing are listed below:
1. To improve the mechanical properties.
2. To increase ductility, particularly to restore the normal conditions of steel after cold
working.
3. To relieve the internal stresses.
4. To remove chemical non-uniformity.
5. To change the micro-structure of steel from the distorted structure of cold worked steel
to the equi-axed structure.
Hood Annealing:
Hood annealing is still the most common and convenient method of annealing and a major
portion of cold rolled coils are annealed in Hood Annealing furnaces in spite of development of
continuous and open coil annealing. The main reason for its wide use is that wide range of
annealing cycles can be adopted to suit to Customers’ requirements.
In the annealing process, the temperature of annealing can be as high as 800oC. Different
annealing cycles are followed for different grade & thickness. After annealing, the coils are
given a further light tolling in a single or two strand mill, operated without strip lubrication.
This operation is called as skin passing or temper rolling.
Continuous Annealing:
In Continuous Annealing Process Coils are annealed and the cooled in controlled atmosphere
continuously. This is a much faster process compared to Hood annealing Process.
Skin Passing:
Skin passing is a cold reduction method and the steel surface or skin is hardened by cold
working, keeping the steel core soft & ductile. In Cold Rolling Mills of RSP, one single stand 4-
high mills and one twin stand 4-high mill have been installed.
Parameters SP I SP III
Rated Capacity 2,70,000T/yr 3,60,000 T/yr
Type of Mill 1700 mm, Single Stand, Two Stand 4 High
4 High
Strip Width 630-1550 mm 560-1040 mm
Strip thickness 0.35 to 1.3 mm 0.15 to 0.31 mm
Speed 500 m/min 1200 m/min
Work Roll Size 460 X 1700 mm 460 X 1200 1 st Stand
530 X 1200 2 nd Stand
Purpose Temper Rolling of SG Temper Rolling of TP & Light
Coil SG Coils
The skin passed coils are the packed and dispatched to stock yards or Customers as CR
coils.
Applications:
Used for making steel furniture, refrigerator bodies,
automobile bodies, railway coach paneling, drums, barrels,
deep drawing and extra deep drawing available as per
Indian Standard specifications.
The Ferrous Sulphate salts from regeneration plant are used for water treatment at
Tarkera Water works. Also some quantity of these are sold to outside parties and find
use in making paints and in pharmaceutical applications.
Coating Units:
RSP’s family of coated steel sheet products includes both hot-dipped and electrolytically-
applied coatings. The protective coatings add superior corrosion resistance to the many
HRD Centre Page: 112
Panorama 2012
other desirable properties of steel. The various types of Coated Steel
Sheet products gives the designer and manufacturer a choice of combinations to provide
the amount of corrosion resistance required, strength, formability, paintability surface
appearance and other properties and characteristics to closely match the steel sheet to
the need, whatever the environment. In CRM, RSP we have facilities for both Tin and
Zinc coatings.
The Entry section has two Coilers, a Double cut Crop Shear, a Welding Machine, Briddle -I,
Vertical Loopers & Briddle-II.
The Processing section has Electrolytic Cleaning Unit, Alkali Rinse Unit, Electrolytic
Pickling Unit with rinsing facility, Electroplating Unit, Hot air Drier, Melting Tower,
Quenching Tank, Chemical Treatment unit, Rinsing Unit, Hot air drier & Electrostatic strip
oiler.
Application:
Electrolytic Tin Plates are used in the manufacture of
printed and plain containers for packaging of various food
products including fruits, vegetables, edible oils and food.
Plates are available in 5.6 gm/m 2 coating weight and variety
of tempers.
These lines can produce Galvanised plain, Galvanised Corrugated as well as galvanized coils.
The material flow for Galvanising Lines is as follows:
Uncoiler → Pinch Roll → Double cut Hydraulic Shear → Pinch Roll → Loop Car1 → Pinch Roll
5 → Oxidizing Furnace → Reducing Furnace → Pit type Galvanising pot → Air jet knife →
Deflector Roll → Cooling boxes → Passivation Unit → Loop car 2 → Halden Shear → Sheet
piler → Galvanised Plain (GP) → Corrugation Line
There are 2 multi-roller corrugating machines which produce corrugated sheets.
Technical Details:
Continuous Galvanising Line Two nos.
Width of Sheet 610 mm – 1220 mm
Thickness of Sheet 0.31 mm – 1.60 mm
Capacity 1,60,000 T/Yr
(80,000 T for each line)
Maximum speed 90 m/min
Application:
Shipping Section:
Cold Rolled Non-Oriented (CRNO), the energy efficient steel, is an essential raw material,
recognized the world over for manufacturing electrical equipments like generators, motors,
relays, small transformers etc. Used primarily in special rotating & static electrical
equipments, the CRNO steel is characterized by low watt loss (core loss) & high permeability.
Silicon Steel Mill is ISO –9001 & ISO –14001 Unit. The CRNO stream has been awarded ISO -
9001, the International Quality Assurance System, certified by M/s RWTUV, Germany in
September 1996. And ISO –14001 Environmental Management System, certified by M/s BIS,
India in October 2000.
Various facilities have been added with a view to keep pace with the latest technology. The
notable features are external desulphurisation of hot metal, high purity steel making, vacuum
degassing, continuous casting, highly accurate hot rolling mill & Cold Rolling Mill complex
incorporating the most advanced technology for manufacturing CRNO steel strips. The unit has
a modern Magnetic Testing Laboratory, which is one of its kinds in the country.
FLOW SHEET
SLITTER –I
CUT TO LENGTH
PACKING
DISPATCH
MAIN UNITS:
Line Features:
1. Hydrochloric acid pickling (HCL) 5 tanks for pickling.
2. Acid conc. 8 To 12 %. Salt conc. 12 % max.
3. Acid bath temp. 70 +/- 3oC
4. Annealing of M-36 / M-27 & higher grades.
5. Gas fired & electric heating zones 3 each.
6. Annealing temp. 950 +/- 10oC
7. Anti rust oil coating after pickling.
8. Taylor - Winfield shifting head seam welding m/c
9. Line speed 10-35 mpm ( Entry-90 / Process 60 / Exit 90 mpm )
10. Tension - Entry - 0.35 to 1.05 Kg/mm2
Furnace - 0.35 to 1.05 Kg/mm2
Pickling - 1.05 Kg/mm2
Exit - 2.5 Kg/ mm 2
11. Pickling Tanks - 5 (L - 25. 7 m, W - 2.13 m, Depth - 1.207 m)
Capacity - 36,000 Lts each (1 to 3) 4A – 16800, 4B-19600 lts.
12. Cascade rinse unit 3 compartments.
Mill Features:
1. Work roll 280 / 305 x 1270 mm
Back up roll 1105 / 1220 x 1270 mm.
2. Coil ID - 510 mm
3. Coil OD - 1750 mm
4. Width - 600 - 1150 mm
5. Morgoil Bearing Size -
6. Hyd. Automatic gauge control
7. Isotope thickness gauges.
Source –Amrecium 241 / Ionisation gas – Crepton/ zenon
8. ABB computer MP-200 /1
9. Siemens plc 155 H
10. Quick work roll changing rig.
11. Work roll bending both crown in & crown out. 25 Kg/cm2 each plunger.
12. Motorised wedge drive for pass line adjustment.
13. AGC Cylinders – 780 mm Dia. & 1175 mm sroke.
14 Back Up - Morgoil Bearings
Work Roll - 4 row tapered roller bearings.
Electrics:
P.O.R. - 300 kW, 1200 rpm CONT.
E.T.R. - 1125 kW, 800 rpm
MILL STAND - 2 X 1687 kW, 670 rpm
D.T.R. - 1125 kW, 800 rpm
Line is used for head end cutting of Reversing Mill strip breakage coils, Removing off gauge
portion & dressing of coils.
Line Features:
1. Gauge 0.27 to 0.70 mm
2. Coil Wt. 15 Mt. (max )
Width 600 to 1100 mm
3. Line speed 15 mpm
Line Features:
1. Scrubber unit.
2. Elec. F/C, Length 153 mts., Decarburising zones 1 to 9 temp. 840 +/- 10oC
Annealing zones 10 to 12 temp. 1065 oC max.
3. Protective atmosphere of synthesis gas 75 % H2 + 25 % N2.
4. Two roll insulation coating system
C-3 Organic coating
C-6 Semi- organic.
5. Drying F/C
Open fire F/C using mix gas. Temp. 300 to 600oC.
Line speed – 8 to 40 mpm
Input –0.30 to 0.70 mm
I.D. 510 mm / O.D. 1650 mm
Line Ten Entry – 0.35 Kg/mm²
Process – 0.25 to 0.55 Kg /mm², Exit 4.5 Kg /mm²
DECARB ANNEALING:
Supplier: EPI / ELEC. FURNACE CO. Elec. BHEL, PLC: Siemens S-5 (135 U)
This line is used for decarburizing annealing & C-3 (Organic) & C-5 Semi – Organic Insulation
coating of cold reduced strip.
Width -600 - 1030 mm
Line Features :
1. Wean United Dual seam welder
2. Scrubbing unit
3. 2 Roll tensiometer
4. Elec. F/C
Length 153 mts., Decarburizing zones 1 to 8 temp. 840+/-20oC, Annealing zones 9 to 11 temp.
1020oC max, Protective atmosphere of synthesis gas. (75% H2 + 25 % N2) 1575 kW elec. heating
/ 1800 kW elec. soaking brick lined static cool & water jacket cool . Jet cool fans - 3 Nos.
Capacity 626 NM3 / Each –12
5. Coating System: Two roll coater; Drying F/C - Flotation type Elec. Heating temp. 300 to
450oC. length 27 mts.
6. Line Speed :
Entry - 15 to 75 mpm. Process - 25 to 60 mpm
Exit - 15 to 75 mpm
7. Line tension:
Entry 0.35 Kg/mm2
Loop storage 1.05 Kg/ mm2
Furnace - 0.35 to 1.05 Kg/mm2
Exit - 4.50 Kg/ mm2
Entry looper - 4.5 min. strip storage (270 Mts)
Exit looper -2.0 min. strip storage (120 Mts)
SLITTER - I
Supplier : STAMCO / BLUE-STAR
Elec. BHEL
PLC : Siemens 155 H
This line is used for side trimming / slitting of annealed coils.
All coils are inspected during processing.
Line Features:
1. Pull through line
2. Unwind / trimmer / rewind
3. Scrap baller
ROLL SHOP
Roll Shop caters to the requirement of Ready Roll Assemblies to all customer mills namely PM,
HSM, CRM & SSM as per schedule. Accordingly, for smooth feeding of Roll chock assemblies to
all these units three shops are located at three different locations known as Roll Shop-I, II &
III. Other than turning & grinding of rolls, Roll Shop performs various other functions as
detailed below:
• Procurement, issue & performance assessment of rolls.
• Procurement, inspection & maintenance of roll neck bearings (Oil film bearings, 4-row
taper roller, 4 row cylindrical roller, ball & thrust bearings).
• Inspection & maintenance of roll balancing cylinder assemblies (hydraulic testing & seal
replacement).
• Inspection & maintenance of chocks (chock bore; wear plates, keeper plates, hydraulic
fittings etc.).
• Lubrication of roll chock assemblies.
• Maintenance of roll grinding & shear blade grinding machines.
• Record keeping of rolls & bearings through computerized roll management system.
Roll Shop-I:
The shop came into operation from 1961 and at present caters to the roll requirement of HSM
& Plate Mill. It is situated in DE bay of Hot Strip Mill from column No. 37 to column No. 58. In
1996-97 the shop was extended up to column No. 64 to accommodate two new CNC roll grinding
machines for fulfilling the additional requirement of Hot Strip Mill.
The Shop consists of following machines:
a) Lathe- for Turning of R0 and back up rolls of HSM
b) WG1 & WG2- Grinding of back-up rolls of HSM & PM and also work rolls of PM.
c) WG 3, 4, 5- Grinding of Work Rolls of HSM finishing & roughing stands, CTS Blades of PM,
Rubber Rolls and Pipe plant cutter blades.
d) EM1 & EM2- Straight blade grinding of HSM & Plate Mill.
e) CNC-I & CNC-II - Grinding of finishing Mill work rolls of HSM.
MAINTENANCE FUNCTION
The maintenance system of at RSP has been designed and implemented by Mr. K.H. Kohrn, a
German expert, way back in early seventies. Though Kohrn’s system vouched for a centralized
system of maintenance for various production units of the integrated steel plant, with pressing
needs, RSP switched over to decentralized system in 1991. By this, maintenance management
is now responsibility of Head of the different production units. This switch over, and also timely
computerization of the maintenance information system, however has not jeopardized the core
Kohrn’s system design. The decentralized system also enjoys many centralized services, which
have been described in following paragraphs.
CENTRALIZED SERVICES
The centralized services can be categorized as Mechanical and Electrical, each one being
headed by separate General Managers. The mechanical services are –
Apart from the above maintenance services, utility service of Compressed Air is also under
G.M.(Mechanical).
Group Function
Planning group Material planning, Job cataloguing, Job planning, B/D
& delay analysis etc.
Inspection group Inspection of machineries by schedule and defect
recording.
Repair maintenance group B/D maintenance / Shut down maintenance jobs.
Preventive maintenance Lubrication, adjustments, cleaning etc.
group
Maintenance practices that are followed in shop floor are of both time based preventive
maintenance and condition based maintenance. These two types of maintenance practice, and
related information system is narrated in subsequent paragraphs. For systematic approach in
planning and execution of maintenance jobs, the equipment of the plant is classified in a
scientific manner. This is explained below.
Equipment classification number codes are referred in planning and scheduling of jobs. It is
particularly very essential in computerization of the planning system which will be discussed in
subsequent lines.
The total maintenance job requirement of different machines is first chalked out from PM
recommendations from the supplier or from experienced personnel. They are categories as time
based jobs and condition based jobs. Out of the time based jobs, on daily basis, inspection,
lubrication, adjustments etc. jobs (PM 7) are carried out as per schedule in each department on
regular basis. For other time based jobs like, periodic over hauls, checking and to take up defect
based repair or replacement jobs, shutdowns are planned in advanced. In fact, shutdowns
affecting production (PM 1) and not affecting production (PM 4) are separately planned on
monthly basis before the start of the month and consent of the operation head is taken. Before
the start of the actual shutdown, time based and condition based jobs are planned in a job list
(PM 3). Actual execution detail of each job is recorded in job history format (PM 10). A
compliance report is made for each department on plan fulfillment on monthly basis (PM 9).
While in mill side shutdown planning is a feature for the whole mill (usually weekly), in the
iron and steel side, separate shutdowns are taken for different equipment/systems at required
frequencies in a staggered manner.
Apart from regular inspection and shutdown jobs capital/ major repair is also carried out in all
units of the plant based on the condition and life cycle of the equipment. For better spare part
and capital item planning, a three year rolling plan ( PM 1a) is made, which is updated every
year with a detail plan (PM 1b) for the current year. Capital repair plan is prepared after
discussion and approval from Head of works. Just before execution, a PERT/ BAR chart
While, in the mill side CR is done usually for the whole mill, in the iron & steel side different
equipment / systems are taken up for CR in a staggered manner during the year. Capital repair
job compliance is also recorded in job history (PM 10) with details of maintenance jobs.
Breakdowns are encountered in emergency basis, particularly when it affects production. Each
breakdown is also recorded (W 1b) with its cause and prevention action for future analysis. It is
noted that breakdown job execution is also recorded in job history with details.
RSP also takes up statutory maintenance jobs under normal and capital shutdowns,
particularly for Boilers and pressure vessels. These maintenances are monitored by the Factory
inspector from the State Government.
2. Preventive Maintenance & Repair Planning: This module is the heart of CMMS. It
comprises of the following sub module which are self explanatory.
a. Job cataloguing
b. Inspection Schedule and feedback
c. Defect recording
d. Shutdown planning and feedback.
e. History monitoring
f. Breakdown/delay recording and analysis
g. Capital repair planning
3. Captive Engineering Shops Module: This module handles the following activities
which concerns with job planning for the machines in the captive engineering shop.
They are-
a. Work order forecasting & planning.
b. Process planning of jobs & route card generation.
c. Rolling Master plan for different shops.
d. Machines database maintenance.
e. Shop scheduling.
f. Feedback and MIS system.
About 50 terminals have been provided in planning cells of different departments to carry out
data feeding and data retrieval. The output reports are printed at users’ terminal as and when
required. The computer reports are also titled as per Kohrn’s system to avoid confusion to
users.
Vibration monitoring: Data collector and analyzers (FAST TRACK and DATAPAC 1500 from
Entek IRD) are used by CBMS to collect data from about 475 rotating machines around the
plant on regular basis. The analysis report is sent to departments with recommendation on
action to be taken up. For problem of unbalance, which causes vibration in particularly fans
and impellers, CBMS also takes up In-situ balancing job. RSP is first to start and is pioneer in
vibration analysis and In-situ balancing job in SAIL plants. This expertise can also be shared
with other plants with suitable arrangement.
Thermography: Condition monitoring of electrical cables, vessel & ladles walls, pipelines is
done by thermal imaging method by use of a thermo-vision camera. At present, Power
distribution and Energy Management department are adopting this method for condition
monitoring of high tension lines and pipelines respectively.
Oil Analysis: Samples of lubricating oils are collected by CBMS/LUHP department from
critical machines like gear boxes etc. These samples are analyzed for concentration of ferrous
particle in oil sample by DR Ferrography method. The analysis reports are made from their
finding and communicated to department. The concentration of metallic particles shows the
extent of wear in the equipment and that calls for timely action before a breakdown.
Motor Monitoring: This activity monitors the condition of rotor bars in electrical motors. RSP
initially started this project with RDCIS. At present it is being done on few important motors
using the equipment available in CBMS department. Plan for large scale motor monitoring
through out the plant is on the anvil.
MAINTENANCE
JOB CATALOGUE
PREVENTIVE CORRECTIVE
MAINT. JOBS MAINT. JOBS
PIE
INSPN. &
INSPN. CHART
PLAN HISTORY DEFECT
SCHEDULE RECORDING
FULFILMENT PM10
REPORT
PM9 ROOT CAUSE
ANALYSIS &
DEFECT BASED INDENTIFY
JOB EXECUTION JOB LISTING JOBS TO AVOID
& HISTORY REOCCURENCE
RECORDING
WEEKLY/
EXECUTION PLAN MONTHLY
PM3 SHUTDOWN
PM1 / PLAN
PM4
CAPITAL REPAIR
PM1b
PLAN
1 Yr. PM1a
EXECUTION PLAN
3 Yr.
PM1c
Maintenance Systems & Services Department (MSS) was formed in 2000 by merging following
six departments:
1. Lubrication (Organization Planning) - LU(OP)
2. Hydraulics & Pneumatics (Organization Planning) - HP(OP)
3. Computerized Maintenance Management Systems - CMMS
4. Condition Based Maintenance Systems - CBMS
5. Maintenance Planning (Organization Planning) - MP(OP)
6. Investigation & Evaluation - IE(OP)
Accordingly all the functions of the old departments are being carried out by MSS department.
The major areas with activities in each section are discussed below:
Lubrication:
• Provide assistance to the Materials Management Department in procurement of lubricants
with respect to technical specifications.
• Monitor & review the quota of lubricants of various departments w.r.t. past consumption &
Task force recommendations.
• Monitor the stock of lubricating & hydraulic oil by keeping liaison with oil godown of
Central Stores, Stock Control & Purchase to avoid stock out situations.
• Collect oil samples of various lubrication systems of departments as per sampling schedule.
Samples are sent to R&C lab for testing and reports are communicated to respective
departments for remedial action in time.
• Monitoring of wear trend in critical equipment through Ferrography by sending samples to
RDCIS, Ranchi periodically.
• Coordinate projects by different external agencies like RDCIS on lubrication systems.
Bearings:
• Providing technical guidance for substitution of bearings to different plant unit as per
requirement.
HRD Centre Page: 130
Panorama 2012
Presently, 5 numbers of CPT make compressors are being replaced by 2 Nos. of Centrifugal
Compressors of 15,000 m3/hr capacity (Atlas Copco make) under AMR scheme. It is being
installed at Modernisation zone. The compressors are expected to be operational by Dec’09.
The Customers of Central Compressor Station are SMS-II, CO, BF, CCD, MS-I, CPP-I, LDBP,
Shops, TOP-I, RS(E), SPP, PM, HSM, CRM and SSM.
Oil is re-refined on the principle that the lubricating oil never wears out. Its life is indefinitely
long and can be reused after necessary treatment. The old used oil contains mostly oxidation
product of oil, sediment and water etc. Following steps are involved in Oil Re-refining plant for
refining of used oils.
Objective of CBMS:
- To carry out predictive maintenance programme (PMP) at global level of steel plant.
- To take up in-situ balancing of rotating machines.
- To undertake technical surveillance of high speed machines with respect to vibration
monitoring as a second line of defense.
- To enhance equipment availability & reliability of critical production units through the
above activities.
- To cut down costs by prolonging the life of the equipment.
Services Rendered:
- Regular monitoring of health status of 475 critical machines throughout the steel plant
by vibration measurement-fault diagnosis recommendation for remedial measures.
- Presently CBMS is using E-monitor Odyssey window based software for Fast Fourier
Transforms (FFT) analysis for all types of rotating machines.
- To attend emergency calls when the equipment condition is deteriorating fast.
- To do in-situ balancing of rotating equipment in critical production units like SMS-I,
SMS-II, SP-II, CPP-I, HSM, PM, SSM etc. as and when required.
- Improvement in availability and reliability of all types of rotating machines.
- At present the reliability of rotating machines is about 96%
Output Control:
- Quantity: Daily PM reports, in-situation dynamic balancing reports, financial savings
accrued through CBMS activities, MIS monthly reports & Technical surveillance and
equipment health status reports (potential failure) etc.
- Quality: The fault diagnosis is nearly 99% correct and meets customer requirement and
satisfaction.
- External Services: Mines, NSPCL etc.
- Communication: Oral/ Telephonic communication, immediately after taking vibration
measurement and written communication within 24 hours.
Keeping the above in view CMMS was developed, which serves as a library for easy and quick
retrieval of data, information, reference and analysis of equipment maintenance related
activities.
Modules of CMMS:
• Equipment Classification: Equipment coded for location wise identification up to part level.
• Preventive Maintenance:
• Job Definition: Creates & maintains Job catalogue of equipment.
• Inspection (PM 7): Schedules and Records Inspection activities.
• Defect (PM 8): Records defect details and plans liquidation.
• Shutdown Planning: Plans shutdowns, plans jobs, Records feedback of jobs done (both
planned & unplanned)
• Breakdown & Delay (W1b): Records breakdown details for analysis.
• History (PM 10): Maintains history of jobs done and defects liquidated.
• Capital Repair (C/R): Prepares C/R plan and fulfillment details.
• Crane Status: Special MIS for over head cranes status
• Engg. Shops planning and scheduling ; Process Planning, Forecasting, Master planning,
Rout card preparation, Shop scheduling, Feedback, Status monitoring
• Material Requirement Planning: Prepares indents, budgets, tracks requirement.
Benefits:
• Better equipment availability due to reduction in breakdown and sustained health of
equipment.
• Cost effective maintenance.
• Reduction in lead time in procurement.
• Maintaining history of equipment and procurement and retention of expert knowledge.
• Scientific planning of jobs, decision support and reduction in routine job efforts.
Structural Inspection
Structural Inspection Department undertakes visual inspection of Industrial building
structures (both steel and RCC) from ground to roof level of all plant units of RSP regularly to
have well maintained buildings/shops. The main functions are:
Regular inspection of all industrial structures, chimneys and stacks, structures in mines
area, Mandira Dam and structures of NSPCL to assess quantum of defects arising due
to any accident, environmental condition etc.
Preparation of technical reports citing defect list, remedial measures/suggestions in a
book-let from and taking approval of competent authority for liquidation of
damages/defects.
Distribution of approved reports to owners of the shops/department for liquidation of
defects.
Stage-wise monitoring/rendering help during execution to liquidate defects, final
inspection after rectification/liquidation.
A joint certificate with owner department is issued stating the satisfactory liquidation of
the defects.
SHOPS-
PLANNING & COORDINATION (SERVICES)
Objectives:
• Identification & approval by the competent authority of High value make jobs, Automake
jobs & Castings (Ferrous & Non Ferrous) in consultation with internal Customers & Shops
in the beginning of each financial year to be executed in Engineering Shops. This exercise is
being done to maximize the utilization of Engineering Shops capacity in line with Purchase
policy of SAIL.
• Finalization of Capital Repair jobs of different units of plant to be executed in consultation
with Internal Customers & Engineering Shops.
• To receive requirements in the form of Indents / O5 for manufacturing/ repair of spare
parts, reconditioning of assemblies / Sub-assemblies, Gear Boxes, Hydraulic equipments &
Castings (Direct delivery or with machining) of different plant units; scrutinize the
possibilities of timely execution and distribute the work on the basis of work load and
capacity of different shops. Coordinate with different shops for execution of the jobs.
• Planning the details of the above mentioned types of jobs of different Plant units in shop
complex including Foundries.
• To achieve the pre-requisite for an economical and timely repair of manufactured parts and
spares.
• Co-ordinate the processing of Items for reconditioning through Reconditioning Route to be
executed by outsourcing.
• Processing of Indents [Buy through PC (S)] for procurement through local SSI units.
• Inspection of jobs executed in Engineering Shops, local SSI units against PC (S) orders
against Indents [Buy through PC (S)] & jobs at different plant units as per the
requirements of different Internal Customers.
• Preparation of different MIS Reports for review at different levels.
Production Control:
• Receive work order (05 form) from different plant units
• Scrutiny of the work order (05) and Record
• Prepare bi-monthly plan for different units of Engineering Shops
• Prepare monthly plan for Foundry.
• Raise work order for MAKE indents and plan for execution
Process Planning:
• Detail study of drawings in line with scope of work specified in Work Order (05).
• Allocation of the above Work Order to Planner.
• Process planning of jobs indicating details like place of execution, raw materials required,
weight of the job, sequence of operations indicating work center, sequence and process along
with catalogue number, drawing number etc.
• Estimation of time as per approved Norms for each operation
• Preparation of Cost Tickets as per the estimated time.
Inspection:
• Inspection of job on completion of different stages of operation
• Inspection of job on completion in shop complex / local SSI units
• Inspection of job at shop floor of different plant units as per requirement
• Preparation of quality report acceptance of inspected jobs in shops.
Off-loading Cell:
• Placement of orders on local SSI units against indented quantities cleared for "BUY
through PCS"
• Co-ordination with Engineering Shops & Indenting Customers for issue of raw material to
local SSI units against the PC (S) orders
• Follow-up with local SSI units for delivery of jobs as per schedule
• Processing of Bills for payment.
SHOPS-FOUNDRIES
The primary activity of this department is to make castings of spares used in various units of
the plant. Some of the products manufactured at foundry are as follows:
a) Ferrous castings like door frame, flash plate, wharf plate, sinter breakers, grate bars,
hammer heads etc.
b) Slag pots required by BF & SMS-II.
c) Steel, cast iron and non-ferrous castings of other spares needed by the plant.
d) Salvaging of copper coils from rejected electrical cables & fittings and converting them in to
ingots.
e) Conversion of Al ingots into nuggets for SMS.
f) Making of ternary alloys of zinc, aluminum and lead for use in galvanizing line of CRM.
2. Steel Foundry:
The Steel Foundry has one Electric Arc Furnace of 5 Ton capacity for making steel and cast
iron heats; one sand plant consisting of sand mixers and allied accessories for sand preparation;
two numbers of drying ovens for drying the green sand moulds; fettling equipments like swing
grinder and gas cutting facilities and one number of annealing furnace for heat treatment of
castings.
3. Non-Ferrous Foundry:
The Non-Ferrous Foundry is having the following equipment:
(a) Three nos. of bale-out pit furnaces each of a capacity of holding 300 kgs of brass / bronze
melts and one hydraulically operated tilting furnace with a holding capacity of 500 kgs
brass / bronze.
(b) One hand operated crane with SWL of 3 MT capacity.
(c) One EOT crane with a SWL of 25 MT.
5. Pattern Shops:
A well-equipped pattern shop with circular saw, band saw, surface planer, thickness planer and
drilling machine for preparing pattern required for making different moulds exists at Foundry.
Repair Shop (Mechanical) [RS(M)] is one of the three captive mechanical repair shops of
Rourkela Steel Plant engaged in manufacturing and repair of spares/equipment of different
units of the plant. This shop is equipped with conventional and modern machines for metal
cutting, heat treatment, testing of chains and slings and dynamic balancing. Besides these, RS
(M) also has a general Fitting & Assembly section, a Gearbox section, a Hydraulic section, a
Forging section and a Calibration Cell.
Following are some of the important machine tools and heat treatment facility available at RS
(M):
A) Machine Tools:
i) Lathes: Maxm. Job size 1350 mm dia. X 10 mtrs.
ii) Horizontal Boring Machine :
Maxm. spindle dia. = 175 mm
Maxm. Boring depth = 1500 mm
Maxm. Boring dia. = 1400 mm
iii) Slotting Machine: Maxm. stroke of Ram = 500 mm
Maximum swivel = 12 degrees.
iv) Hobbing Machine : Maximum dia. of gears cut with mandrel = 1900 mm, without
mandrel = 3200 mm
Maxm. Wt. of job = 40 Tons, Maximum Mod. of gear generation = 26 (Steel), Maximum
Mod. of gear generation = 30 (Cast Iron)
v) Vertical Boring: Maxm. Wt.of job = 12 Tons, Maxm. Turning Dia.= 4000 mm.
vi) Dynamic Balancing Machine: Maxm. dia.of job (bearing dia.)= 400 mm
Maxm. Length of job = 5030 mm, Maxm. dia of job over bed = 2500 mm
B) Heat Treatment:
i) Hardening Furnace: Size 1500 X 650 X 400 mm, Maximum working Temperature =
10000C, Maximum weight of the job = 500 kg.
ii) Tempering Furnace: Size 1500 X 650 X 550 mm, Maximum working Temperature =
6500C, Maximum weight of the job = 500kg.
iii) Spin Hardening Machine : Minimum dia. for Heat Treatment = 160 mm, Maximum dia.
for Heat Treatment = 450 mm, Maximum width of job for Heat Treatment = 250 mm,
Maximum weight of job for heat treatment = 800 Kg, Flat Burners size = 75, 100, 125,
150, 200 & 250
iv) Double Decker Furnace:
Pre-heating chamber size 500 X 500 X 450, Maximum temperature = 9000C.
Heating chamber size 500 X 400 X 350, Maximum temperature =13000C.
G) Forging Section:
i) Heavy forging shop: Pneumatic Power Hammers of capacity 1000 kgs and 500 kgs with
mixed gas fired furnace.
ii) Light forging shop : Pneumatic Power Hammers of capacity 200
kgs and 150 kgs with coke fired furnace.
H) Hydraulic section:
This section is equipped with a hydraulic test rig of REXROTH make. Varieties of cylinders and
pumps are overhauled & tested in this section.
Structural & Fabrication Shop is another captive shop in the Engineering Shop Complex
engaged in repair and fabrication of various plant equipment of Roukema Steel Plant. This
shop comprises of the following sections:
i) Welding Shop
ii) Rolling Stock
iii) Structural Shop
i) Welding Shop:
This is basically a reconditioning unit where worn out steel plant equipment/ spares are built
up by welding through conventional and modern welding machines like Metal Inert Gas
(MIG)/ Metal Active Gas (MAG) & Submerged Arc Welding(SAW). A selected typical
application jobs are also manufactured here.
The details of these machines are as follows:
2) a) SAW Machine:
Manufacturing Jobs like Hot Sinter Screen, Zn Pot, Skid Pipes for reheating furnace &
recuperators for HSM, Wobblers, Adaptors for Mills, BLT-chute-fabrication, Hood Annealing,
Inner Cover Fabrication etc. are done in Welding Shop. 90% of plant’s repair welding jobs are
also done.
required as per the need of plant. Major and massive repair of completely damaged Slag Cars
and 140 T HM Cars have been undertaken more than 5 times within one year.
2) Hydraulic Press:
(Capacity: 600 Tons)
Repair & Construction (Mechanical) [RC(M)] was established in the sixties in RSP, known by
the name Heavy Maintenance and Construction and was later on christened Repairs &
Construction (Mechanical) – RC (M). It takes part in the weekly shutdown programmes, capital
repairs and breakdown restoration besides fabrication and erection of equipment or facilities
depending on resources available throughout the plant.
The services are rendered through a number of zones set up at different locations of the plant
and each zone has developed expertise in the respective zonal jobs. All the zones have the
flexibility to take up any job of other zones in the plant. The zones are:
1. BF BF , CO & CCD
9. CRNO CRNO
RC(M) maintains flexibility among all the zones to increase productivity of workforce.
CRANE MAINTENANCE
EOT Cranes are the most vital material handling equipment in Steel Plant. Smooth and
continuous operation of all the units depends to a large extent on safe and efficient operation of
these equipments.
From raw materials to finished products the materials are required to be handled minimum 16-
17 times at every stage, be it hot metal, slabs, coils, plates or pipes the handling has to be safe
and prompt. This handling is being done by EOT Cranes. The mechanical and structural
maintenance of these equipments is being done by Crane Maintenance department. Total 212
EOT Cranes in different production units of the plant are being maintained by the department.
The department is broadly divided into 3 sections viz 1) Iron & Steel Zone 2) Rolling Mill Zone
& 3) Modernization Zone. In Iron & Steel zone , the cranes of Blast Furnaces including PCM,
SMS-I, Sintering Plant-I,CPP-I, Foundries, LDBP, Coke Ovens, CCD & SSD are being
maintained. Similarly, Rolling Mill Zone maintains the cranes of Plate Mill, HSM, CRM,
SSM, SPP, Pipe Plants, ESM & RS (E). In Modernization Zone, the cranes of SMS-II (i.e. BOF
& CCM-II) & LRS-II are being maintained by the deptt.
Central Planning:
The activities include:
1) Procurement of Spares & Assemblies, Consumables based on requirement from all zones.
2) Processing & finalization of Repair Job Contracts.
3) Monitoring of Data & Records.
Crane Workshop:
In Crane Workshop following activities are done:
1) Machining / Manufacturing of spares for cranes.
2) Dismantling, overhauling & assembling of crane parts.
All Mobile Heavy equipments like Dozers, Payloaders, Hydraulic Cranes, Crawler Cranes,
Forklifts, Debricking machines, side loaders, Excavators including Trucks, Mini trucks, and
tractors in Rourkela Steel Plant are maintained by Field Machinery (Maintenance)
Department. All These mobile equipments are utilized by various production / service deptts for
their production, operation, maintenance, housekeeping & erection /repair activities. Area of
utilization of equipments is wide spread in the whole Plant area. Due to this, FM (M) has
different zones (Eight Nos.) to cater to these areas.
Operational Activities:
1. SMS-I Zone: Operation of Payloaders and Dozers at SMS-I and Slag loading, attending
breakdowns at CO, BF, SMS-I related to Dozers and Payloaders.
2. Control Room: Operation of Hydraulic Cranes including Grove 20 T and 55 T, Crawler
Cranes, Haulpak Dumpers, Tippers, Tractors and Trailers, Diesel Distribution.
3. Truck Pool Operation: Operation of Trucks for operation, housekeeping, collections
funeral trucks.
Service Contracts:
Leyland Tippers, Swaraj Mazda Mini-Trucks, JCB Payloaders, TPS make Vacuum Loaders,
Sewage cleaning machines, Road Sweeping Machines, Garbage Compactors are cover under
Service Contracts.
FM (M) is having 10 executives along with strong dedicated workforce of 280 technicians and
Operators to cater to maintenance and operation activities of all mobile heavy equipments
including capital repairs. Deployment of Hydraulic Cranes for capital / breakdown repair as per
requirement, Unloading of hard coke from railways wagons, loading in internal wagons,
housekeeping in SMS-I pit side, WWTP, Tandish Removal in CCM-I, maintenance of debricking
machines during debricking of converters which are one of the most critical activities in Steel
making Process. FM(M) is an ISO certified department.
TRANSPORT
Transport department was formed to provide Transport services, as required for men and
materials. This department is a unit of Centralised Maintenance (Mechanical) department.
This is an essential service department which operates round the clock throughout the year.
The total transport service at present is reached to customers through two of its control rooms.
The major units of the department are as follows;
A) Central Pool
B) IGH Pool at IGH campus
C) Repair & maintenance centre at Central Pool
D) Registration Cell
E) Record keeping cell
F) Store & Fuel Dispensing Unit.
A) At present Transport department provides service with a fleet of 240 Nos. Light Motor
Vehicles. The department takes up repairs through departmental resources excepting
for reconditioning of vehicles as a whole. It issues fuel to all 650 Nos. of Vehicles &
Earth Moving Equipment of RSP, NSPCL, Raw Materials Division & Quality Assurance
Estate (Metal).
B) Central Pool: - Central Pool located inside the plant premises to provide light motor
vehicles and buses to different user departments. It provides Transport facility to senior
officials of RSP by deploying chauffeur driven cars.
1. Vehicles to the Plant control.
2. Vehicles to Flood Control during monsoon.
3. Providing vehicles to valued customers of Transport Department include
Central Govt. & State Govt. staff, different plant units, Township, Sports, Social
welfare, Periphery development department, Dignitaries of SAIL, Various
visitors & inspectors. Transport services for ceremonial and various occasions of
State and National importance. Provides Ambulance Service to JNC OHS Centre
at Plant premises round the clock throughout the year. Provides Ambulance
services at Fertilizer Hospital round the clock through out the year.
3. Tyre section
4. Body & chassis repair section
5. Painting section
6. Engine section
7. Battery section
8. Planning & procurement section
E) Registration Cell:-
Registration Cell looks after all statutory obligations of the whole plant vehicles i.e.,
Road Tax, Fitness, Insurance, Pollution control & Legal complications as arise for all
vehicles and Earth moving equipments of RSP.
The total numbers of vehicles with Transport Department pertaining to plant are as follows:
LIGHT VEHICLES :
DESIGN
Design Department is the think tank of the entire Steel Plant. Basically Design Dept. caters
to the maintenance needs of the plant by way of providing modification schemes, spare part
drawings, feasibility reports and technical specifications for small projects etc. to all the
departments.
For all types of Engineering Jobs to be taken up by Design Department, other departments
raise 'O3' Engineering Work orders. These work orders are raised on line through SUN systems
by the Planning groups of departments and are electronically cleared by HODs, General
Managers, General Manager (Mechanical) and HOD of Designs so as to reach the sections
concerned. The types of jobs include modifications, spare parts, re-tracings, replacement
specifications, technical studies, standardisation etc.
Engineering Drawings are prepared on drawing boards as well as using PCs. A CAD centre has
been set up in the department for preparing drawings through PCs using the software Auto
CAD. The CAD centre is equipped with 25 PCs, 1 Server, 2 A0 size Plotters & A3/A4 size
printers for this purpose. For engineering calculations of structural and piping & Electrical
designs special software viz. Auto Cad Mechanical, STAADPRO, ADL pipe and ETAP 6.0 are
also available in the CAD centre. About 90% of the total drawings made are through CAD
Centre. 3D modeling is done in some of the intricate design jobs for in-depth study. Presently
Design Department is having an Archive with almost 5 lakhs drawings and documents. They
are kept in centralised AC environment. The printing unit of Archive prepares prints for all
customers of the plant. Till recent past these activities were done manually with ammonia
printing method which was cumbersome and involved health hazard.
The files are scanned, after which the images in .tiff format, which is editable, is the output.
They are then modified or redrawn in some cases or blurry backgrounds are cleaned
according to requirements. In-house developed interface software ensures the online
archiving of drawings and documents in server which is having storage capacity of 1.2 TB.
The server is getting upgraded with acquisition of latest server with SAN system having
storage capacity of 8TB extendable up to 96 TB. User Departments can download the
drawings and documents in .pdf format from the design online intranet through RSP LAN
System. 3 Nos. 10 Kva UPS for stabilized power supply to Digitisation lab & CAD centre are
also provided. A library is set up where technical reference hand books, text books etc are
kept. The Archives store drawing-tracings, reference drawing prints, microfilms, manuals,
technical brochures etc. and is equipped with Fire Detection and Alarm system and Fire Safe
Almirahs.
HRD Centre Page: 154
Panorama 2012
The standardisation section is the custodian of RSNs (Rourkela Steel Norms) and takes up
assignments of preparation of new standards, revision of existing standards, periodical review
of the utility of work study standards etc. The section also coordinates with Inter Plant Steel
Standards (IPSS) Secretariat for distribution of IPSS copies in the plant units and other related
correspondences.
MAJOR FUNCTIONS
There are basically six categories of jobs being carried out in Design Dept. in a nutshell.
These are:-
a) Category 1 jobs:
These include jobs involving design, modification of prior design of equipments,
evolution of new designs for some equipment or job and design & engineering for
new/ongoing projects. The output is in form of drawings and design calculations. This is
generally the work of highest of magnitude being done in design department.
b) Category 2 jobs:
This category deals with jobs involving technical studies, feasibility analysis i.e.
whether an installation of a new equipment or expansion or modification of existing
themes is feasible or not. If a new machinery is to be introduced, its pros and cons are
weighed and behaviour predicted by analysis and detailed studies. It also involves
trouble shooting in case of equipment failure, problem solving and providing remedial
measures to ensure smooth flow of processes. The out put in this case is in form of
detailed report.
c) Category 3 jobs:
In this category, the jobs are in form of replacement drawings. Drawings are made
indicating the outer dimension details, technical specification & location in the
equipment so that a particular equipment / a part of the equipment can be de-
proprietorised or import substitutions of an imported equipment is made at lesser cost.
d) Category 4 jobs:
Category 4 jobs are popularly known as indigenisation jobs or reverse engineering. In
other words the plant is self reliant in these types of jobs. When RSP was started, not
all the drawings of equipments were supplied by OEM. So it was not possible to
undertake manufacturing for each and every spares. Design Department has so far
made almost 1 Lakh manufacturing drawings since its inception. These have played a
vital role in stabilising the procurement and maintenance activities. Drawings are made
generally by taking measurements from worn out or broken spares and subsequently
converted into detailed manufacturing drawings.
e) Category 5 jobs:
This category deals with rejuvenation of drawings. Some of the earlier drawings were in
the form of RTF’s (reproducible tracing films), polyester films, tracing cloths, prints etc.
Due to repeated use the tracings have become soiled and opaque thereby rendering
them unusable. The disadvantage with prints is that copying to produce more prints
was not possible. Therefore rejuvenation of drawings is done by either retracing on
another tracing paper. In case this is not possible it is redrawn using AutoCAD
software.
f) Category 6 jobs:
This deals with jobs involving Standardisation. Standardisation means to create a
specification of any part which is to be followed in a particular geographical area. It is
done primarily to reduce variety. Having no Standards not only means unavailability of
parts during crisis hours, it also means loss of man hours in manufacturing in house
each and every part which can be easily availed from outside otherwise. Design
Department follows three standards- RSN (Rourkela Steel Norms), IPSS (Inter Plant
Steel Standards) and BIS (Bureau of Indian Standards).
Design Department extends quick and prompt support to all the production units during
breakdowns by providing repair schemes and keeping close co-ordination with Shop complex,
RS (E), RCM and allied agencies throughout the repair period.
Equipment Details:
• There are 6 nos. of High Pressure Boilers to generate High Pressure Steam at 59 kg/cm2
(gauge) & 485 deg.C for running of the Turbo-Blowers as well as the Turbo- Alternators.
a. HP Boiler # 1 & 2 were originally gas fired boilers which were converted into
fluidized bed combustion (FBC) boilers by M/s. BHEL during 1990s. The capacity of
each of these FBC boilers is to generate superheated steam of 95 T/hr. at 59 Kg/Cm2
and 4850C. M/s. BHEL have supplied their make ESPs to these HP Boilers. These
HP Boilers use coal of size minus 6 mm as the only fuel.
b. HP Boiler # 3 & 4 are of Babcock Steinmuller make, radiant type water tube
boilers having maximum continuous rating of 150 T/hr. and economic continuous
rating of 125 T/hr. Fuel used in the boiler is Blast Furnace gas, Mixed gas or LSHS
Furnace Oil.
c. Boiler # 5 & 6 are also of Babcock Steinmuller make, Radiant type, water tube
boilers having maximum continuous rating of 150 T/hr. and economic continuous
rating of 125 T/hr. The fuel used here is 100% pulverized Coal or 100 % BF gas or a
combination of both. These boilers have been retro-fitted with M/s. Orient make
ESPs.
• There are 5 nos. of Turbo Blowers out of which 4 nos. run continuously to cater to the
requirement of the four Blast Furnaces. The function of the Turbo-Blower is to supply the
Cold Blast required by the Blast Furnaces. Turbo Blower # 5 can be connected to any of the
Blast Furnace. The combined Steam consumption in the running of 4 nos. of blowers is 105
T/hr., which is equivalent to approx. 21 MW of electrical power.
• There are 5 nos. of Turbo-Alternators (TA). TA #1 is presently not in service. The
Page: 157 HRD Centre
Rourkela Steel Plant
Turbines of TA # 2 & 3 originally of Siemens make have been replaced
along with condenser and pre-heaters during 1990 by M/s. BHEL make. Insulation of
Generators for TA # 2, 3 & 4 have been up graded from Class “B” to Class “F” and their
original conventional excitation system has been replaced with static excitation system
during the period of 2003-2010. The turbine of TA # 4 was refurbished in February 2004.
During refurbishing all the rows of rotor and stator blades of the turbine were changed. The
turbine rotor was straightened; condenser tubes and pre-heater tubes were changed.
• Both turbine and generator along with auxiliaries were completely changed for TA #6 with
a new BHEL make machine in 2004. State of the art ‘Brush less excitation system’ was
installed. This TA is in successful operation since October 31, 2004.
• Medium Pressure Boilers:
In order to supply process steam to the whole plant, two MP boilers were installed &
commissioned in 1978 each having a capacity of producing 60 T/hr of supersaturated steam
at 18 kg/cm2 & 350 deg. C. The feed water that is being used in Main Power Plant requires
to be de-mineralised water whereas MP boilers do not require that level of purity. In
November’ 2006 & 2007, BHEL make ESPs were installed in MP Boilers # 1 & 2
respectively.
Make : M/s. ISGEC John Thompson.
Type : Water Tube Boilers.
Firing System : Spreader Stoker.
Fuel : Coal of size minus 25 mm.
Maximum Continuous Rating : 60 T/hr.
Pressure of Steam : 18 Kg/Cm2.
Outlet Temperature : 350 ± 500C.
Required CV of Coal : 5000 to 5500 K Cal/Kg. (UHV)
Coal is supplied from Old Coal Handling Plant.
In 1998, third MP Boiler was installed to take care of increased process steam
requirement of the plant. It is CFBC boiler (Circulating Fluidized Bed Combustion) of
60 T/hr. capacity.
Make : M/s. ISGEC John Thompson.
Type : Water Tube Boilers.
Firing System : Over Feed, CFBC.
Fuel : Coal of minus 6 mm size.
Maximum Continuous Rating : 60 T/hr.
Outlet Temperature : 350 ± 500C.
POWER DISTRIBUTION
Introduction
Responsibility of Power Distribution department is to ensure availability of interruption free
quality power to all units of steel plant as well as Steel Township and Fertilizer Township. To
meet this responsibility Power Distribution department operates and maintains a vast
transmission and distribution network. In addition, illumination and power supply to major
buildings like Administrative Building, ED(W) building, Plant Medical building etc., street
lighting of majority of plant roads, boundary lighting are also catered by Power Distribution
department. Electrical Maintenance of some service departments, which do not have an
electrical section, is also looked after by Power Distribution.
Average daily power consumption of RSP (including Steel Township) is 180 MW, with a peak
demand of 230 MW. This power requirement is met from three sources viz. CPP-1, CPP-2 and
utility grid. Average generation of CPP-1 is approximately 45 MW. CPP-2 is owned and
operated by JV Company NTPC & SAIL known as NSPCL. It has an installed capacity of 2 x 60
MW and the average generation available from these units is approximately 110 MW. Balance
requirement of approximately 35 MW is met through import from our utility grid. i.e. WESCO.
Infrastructure
Power Distribution department operates and maintains a huge infrastructure of power
transmission and distribution equipment for reliable power supply to all consumers. There are
2 nos. 132/33 kV outdoor switchyards interconnected through 40 circuit kilometers of 132 kV
Overhead transmission lines.
MSDS-II & MSDS-III are main step down sub-stations where power is stepped down from
132kV to 33kV .MSDS-II 132kV is having double bus with transfer bus scheme. Both the main
bus as well as the transfer bus has ACSR ‘MOOSE” conductor. There are two nos. 33kV buses
with 21/2” IPS Aluminium tube as conductor. There are three nos. 63 MVA 132/33 kV
transformers with 11 kV tertiary winding. Primary of the transformers are solidly grounded
where as secondary are grounded through reactors. At MSDS-III, 132kV is having double bus
scheme having two main buses of ACSR ‘MOOSE” conductor. There are two nos. 33 kV buses
with 2” IPS Aluminium tube as conductor. There are three nos. 62.5 MVA 132/33 kV
transformers with 11 kV tertiary winding. Both Primary and secondary of the transformers are
solidly grounded. Originally MSDS-II had outdoor 1250 A, 25 kA MOCB circuit breakers. In
2004-05 all the old MOCBs of MSDS-II have been replaced with 2500 A, 40 kA SF6 circuit
breakers. Circuit breakers of MSDS-III are 2500 A, 25 kA Outdoor MOCB.
There are 7 nos. indoor 33 kV sub-stations. RM-1 & RM-2 sub-stations installed since inception
have 33 kV double bus system whereas all other 33 kV sub-stations have single bus system. All
circuit breakers of 33 kV are Vacuum breakers.
There are 61 nos. 6.6 kV sub-stations. Sub-stations installed during inception of the plant have
pneumatically operated circuit breakers with ‘Expansin’; a mixture of alcohol and distilled
water as quenching medium. Sub-stations installed during last modernizations and later have
spring-spring operating mechanism with Vacuum/ SF6 as quenching medium.
In addition there are approx. 100 nos. LT sub-stations under power distributions department
mostly having ACB.
Power distribution inside plant area is through hundreds of kilometers of 33 & 6.6 kV grade
cables. Majority of 33 kV cables, some 6.6 kV cables and control cables are laid inside 8 kM of
underground cable tunnel connecting different locations of the plant.
There are about 600 nos. of power and distribution transformers of various rating located at
different sub-stations. There are power transformers, distributions transformers, converter
transformers, furnace transformers and other special application transformers of various
rating. The main EHV grade transformers (6 nos.) are installed out door. Majority of other
transformers are installed indoors (transformer rooms). Small distribution transformer for
lighting and power at remote locations are out door type. 33/6.6 kV power transformers
supplied during inception of the plant are of water-cooled (OFW) design. There are two nos.
special transformers for LHF-1 and LHF-2 (furnace transformers), which are also of OFW
design. Other transformers are generally of ONAN design.
Organization
Power Distribution department is administratively under GM (Elect.). The major activity of the
department is divided in to two parts – Operation and maintenance. Operation group looks
after the total power system monitoring, operation and control round clock. The operational
activity is controlled from the main control room and is headed by one shift engineer in each
shift. All shift Engineers report to the head of operation. The maintenance activities are divided
among different zones viz.- Iron & Steel , Mills, Modernization, Switchyards , Cables &
Lighting; each headed by one area In-charge. Planning Section of the department looks after
procurement, stores, administration, documentation, energy accounting etc.
System operation
RSP power system remains synchronized with CPP-1 & CPP-2 and utility grid. Monitoring and
control of captive generation vis-à-vis the import of power from the grid is done on continuous
basis. Moreover monitoring of system frequency, power factor, maximum demand, voltage and
other parameters is also done from the main control room with help of SCADA system called
SLCC. Revival of power after interruption and normal switching operations for shut down etc.
are also part of the operation activity.
Islanding
Due to presence of Hot Rolling Mills and Ladle furnaces, the load pattern of RSP is highly
fluctuating in nature. Hence during normal condition, RSP power system remains synchronized
with the grid, even in the condition of zero average net exchange of power. Typical to any steel
industry, there are some critical loads in the steel plant, where power interruption can cause
costly damage to equipment as well as personnel. As the system has to remain synchronized
with the grid, any disturbance initiated in the grid is likely to affect the plant power system
including that of the critical loads. In order to safe guard the critical loads of RSP in the event
of grid disturbance, an ‘Islanding’ scheme has been put in place to isolate the Captive
Generating Units of RSP, along with their loads, from the grid.
SCADA / SLCC
The SCADA (supervisory control & data acquisition) of RSP power system consists of RTU
(Remote Telemetry Units) located at different sub-stations. These RTUs collect digital data
(status of CB, isolators, earth switches etc.) and analogue data (voltage, current, power etc.) of
all feeders of that sub-station and send to the Server installed in the main control room.
Communication between the RTU and the Server is through dedicated telephone cables. There
are two Operator Control Stations in the control room where the complete information about
the system is available to the Operator. The SCADA system also has facility for control of
identified Circuit Breakers from the control room itself. Other functions of the system are
Maximum Demand Control, Energy Calculation, Data logging, Trend Display and Report
generation etc.
Maintenance Practices
Preventive Maintenance as well as Predictive Maintenance practice is followed in Power
distribution department. For routine preventive maintenance, all major equipments are
Page: 161 HRD Centre
Rourkela Steel Plant
Advanced testing equipment and methods are used to carry out insulation diagnostic tests on
all major equipments. These tests are used to assess insulation health of equipment and to
predict likely failures. Based on the test results, remedial actions are taken to ensure no
surprise failure of equipment. Condition based maintenance tools like Thermo- vision camera
are also used to detect defects and likely failures.
Energy Billing and payment for import power, Unit wise energy accounting, co-ordination with
utility grid, dealing with authorities for fulfillment of statutory obligations etc, are other
responsibilities of Power Distribution department
Power Distribution department is an ISO certified department. All the documentations are
meticulously maintained as per laid down practices. SOP and SMP are strictly followed in day-
to-day work. Compliances are regularly reviewed internally and corrective actions taken.
RSP has undertaken a massive modernization plan which aims at enhancement of capacity of
the plant to 4.5 MTPA of crude steel. Estimated power requirement of RSP during 4.5 MT
stage, shall be 315 MW average 430 MVA peak. A comprehensive plan has been prepared for
augmentation of RSP power system to remove existing system constraints as well as addition of
capacity to meet power requirements of 4.5 MT stage. Major facilities being added under
modernization plan are
Installation of one 220 kV GIS (MSDS-IV) along with three no. of 160 MVA, 220/132 kV
Transformers.
Addition of Three 62.5 MVA transformer at MSDS-III and one 63 MVA transformer at
MSDS-II
New 132/33 kV S/s MSDS-V & MSDS-VI
A 33 kV Double Bus GIS indoor switchboard for RM-1 ( HRM loads)
New 33 kV (4 nos. ) and 6.6 kV (5nos.) sub-stations for power supply to all additional
loads
Interplant cabling at 33 kV & 6.6 kV and new cable tunnels
Provision of Emergency power to modernization area loads
Plant SCADA & EMS
This department mainly consists of two sections i.e. Electronics Section & Electrical Services
(Electro Technical Services) section.
Electronics:
The Electronics Section provides reinforcement to different Electrical Maintenance Units of the
plant for maintenance of advanced electronic equipment and electronic weighing systems.
These equipments are otherwise maintained by respective departmental electrical maintenance
units. But Electronics Section of E&ES department provide service support if some intricate
problem arises in the electric circuits, solving of which requires advanced diagnostic equipment
and skills. The department scrutinizes technical specification of various electronic/electrical
equipments and also involved in its commissioning. The activities are as follows:
• Repair of various electronic equipment, PCB, modules for different production units/ plant
units.
• Maintenance of all commercial weigh-bridges.
• Service support to production units maintaining of drives, power electronics, UPS, PLC,
process weighing systems etc.
• Operation and maintenance of in-motion weigh bridge at Reception Yard for weighment of
incoming raw materials.
• Maintenance of analytical equipment: X-ray & Optical Emission Spectrometers, Carbon &
Sulphur determinator, Magnetic Test console at CCM-I, SMS-I & II, BF and SSM.
• Maintenance of analytical equipment of R&C Lab and Environmental Lab.
• Maintenance of CCTV system at HSM, Plate Mill & Plant gates.
• Maintenance of Electronics/Analytical equipment of IGH.
• In-house development of new PCBs/modules for electronic controls, PLC & weighing
system.
• Centrally procurement of spare parts for specified PLCs of different plant units.
• Training on PLC, weighing & Analytical equipment.
Electrical Services:
Electrical Service Section (Electro Technical Services) is considered to the brain behind
protection and regulation philosophy being followed in the plant for AC and DC equipment. Its
main function is testing of protection relays of all electric drives and power distribution
networks. In addition to this they are called upon to carry out in depth study and analysis of
intricate and long standing electrical problems of the steel plant and to put forward
suggestions/improvements. They are also involved in commissioning of electrics of latest testing
/diagnostic equipment being purchased by the plant.
The ETS section maintains Fire Detection and Alarm systems of C&IT, Design, EMD building
and Oil Godowns. They also provide service support to all protection units in maintaining the
fire alarm system installed in their respective departments.
• Testing of Transformer oil BDV (Dielectric strength) and DGA (Dissolved gas Analysis)
as per requirement of Power distribution and all other production department.
• Testing of Electrical drives, motors, panels, bus bars and Electrical protection system of
NSPCL as well as all mines (RMD – Division of RSP).
• Calibration of megger and other electrical equipments as per ISO 9001– 2000/BIS
norms.
The Plant Exchange caters to the needs of the Plant premises and Sector-22 with features like
auto call back, BSNL and Reliance junction dialling, conference facility etc. It is integrated with
the township exchange and 200 line ISDN/ DID exchange in a closed numbering scheme. The
numbering scheme for the plant exchange is 7000 to 7999, 8000 to 8999 and 6000 to 6900. For
the Township exchange it is from 3000 to 3120, 4000 to 4999 and 9000 to 9999 with facilities
like wake up alarm. This Township exchange caters to the residential area as well as Offices
and Work sites, in the Township area like Town Services deptt, Ispat General Hospital, Power
Distribution’s Sub-station etc. Both the exchanges are installed with automatic line testing
facility. DID (Direct Inward Dialling) facility has been extended for Plant intercom members.
Prefix “244” before Plant intercom 4 digit extension to access that particular extension from
any service provider phone.
Railway Signaling:
CED maintains the Railway Signalling system for safe movement of wagons for T & RM Dept.
It maintains the route relay interlocking system in the Hot Metal Movement Yard (HMMY),
Raw Material Unloading Yard (RMUY) and Marshalling Yard of RSP. This includes the
maintenance of 71 nos. of point machine in Marshalling yard, HMMY and RMUY; 41 nos. of
track circuits in HMMY and RMUY for effective traffic movement and communication.
Other Systems:
In addition to the above CED also looks after the installation / maintenance of Road Safety
Blinkers at Railway Crossings inside the Plant, Airport Communication System, Data
Terminals – 500 circuits, High speed Internet with broadband 131 nos for senior executives at
offices and residences and 51 nos. of Dial up Internet circuits at various locations. Also CED
maintains centralized clock network consisting of 15 slave clocks with one master clock. This
network is used to keep track of synchronized time in all the pivotal spots in the Plant like
Main Buildings and Gates.
1) Toll free unlimited talk time within RSP SAIL CUG Cell.
2) Local/STD/National call/National Roaming for users of CUG phone.
3) International roaming, sending & receiving SMS, call conferencing and other value
added services like Blackberry, GPRS, 3G, ISD etc. on demand.
4) Toll free with unlimited talk time between RSP SAIL CUG and RSP intercom landline
telephones.
This has become the fastest and reliable communication amongst the SAIL employees of
various plant units.
INSTRUMENTATION
Function
Instrumentation Department works as a centralized department having a group of Executives
and Non-executives dedicated for different sections / groups throughout the plant.
• Maintenance of PLCs (19 Nos.) for starting, interlocking and monitoring functions of
critical equipments like Compressors, Expansion Turbines, Nitrogen and Argon
compressors of TOP-II.
• Control and Monitoring of Process Parameters through DCS in TOP-II.
• Quality parameters like Purity of different products are monitored by 19 nos. Analysers
in TOP-II.
Repair Shop (Electrical), the Central Captive Electrical Repair Shop of RSP caters to the need
of repair and periodical overhauling of around 15000 electrical equipments which are there in
the plant. It handles around 3000 work orders annually.
It is a well laid out workshop of about 6000 sq.m area divided into four bays with facility to
handle equipment weighing as high as 50 ton. It possesses all the facilities required to
Repair/Overhaul/ Rewind all types of Motors (AC, DC & Synchronous), Electromagnets,
Transformers, Welding Machines etc.
FITTING SECTIONS:
There are three separate fitting areas for handling motors of large, medium & small sizes
respectively. It carries out
• Overhauling/repair of large , medium and small motors (HT,LT, DC & RT motors)
• Repair of all types of electromagnet
• Repair/Rebuilding of Slip rings & Commutator , Stator / Rotor Cores
• Undercutting, Bevelling of commutator (at site also)
To carry out all these activities the areas are equipped with
• Four EOT cranes of 50/10 ton, 10/3 ton & 5 ton (2 nos.)capacity
• Induction Heaters for bearing heating in all Fitting bays
• Dedusting chambers for dedusting the equipments
• Numerous customised jigs & fixtures , Hydraulic jacks & pumps
WINDING SECTIONS:
We are equipped with 2 nos. of Rewinding sections for Round Wire & Strip Conductor electrical
equipment which can handle windings of:
• All stators & rotors with super-enamelled round copper wire
• 6.6 kV HT stators & rotors
• Strip wound LT stators & rotors
• Strip wound DC Armatures
• Repair / Manufacturing of DC field coils, Magnet coils, Vibrator coils, Magnet clutch coils
• Repair of all large DC & HT machines at site
It is equipped with:
• 6 KL/hour oil filtering machine.
• A pit at 3.5 meter level to handle large power transformer.
Along with transformer repair this area also takes care of repair of all types of welding
machines.
TESTING SECTION:
Following jobs are executed by this section:
• Final and in process testing of all electrical equipments repaired / overhauled in the shop.
• Testing of electrical machines at site as per work order or during repair executed by RS(E).
• Electrical Maintenance of the shop equipment
• Intermediate tests (routine & special tests) including core flux test, HV test, impedance
test, drop test, PI test, Growler Test, Current balance test, ratio test etc.
To carry out these jobs it is equipped with a fair amount of calibrated measuring instruments &
Power Source. Some of them are:
• Three auto transformers for AC motor/Transformer testing
• DC Power Source
• Direct Switch on for 6.6 kV Motor (upto 700 kW)
• High Voltage Test set
• Tan delta & Surge Inter turn test set
• 5 kV Digital & motorised Insulation testers
• Soft starters for no-load testing of LT Motors & HT Motors (6.6 kV) up to 500 kW
PLANNING PROGRESS
The section takes care of all activities regarding job planning & its progress monitoring.
Following jobs are executed by this section.
• Receiving and delivery of jobs
• Preparation of route card for each job
• Preparation of all types of MIS
• Progress data feeding, Planning and Monitoring of the work order/jobs through
Computerised Electrical Equipment Repair System (CEERS)
• Issue of ITC / FTC for outsourced jobs
Apart from the above sections it has got a small machine shop which takes care of turning &
manufacturing activities of smaller spare parts of the electrical equipments. Carpenters are
there for preparing formers, wedges and insulation materials. It has got a varnishing area with
two hot ovens (300 kW & 100 kW) to cater to drying and varnishing needs.
Annual Capability:
• Repair/rewinding of 1000 jobs and overhauling of 1100 jobs.
• Repair/overhauling of
6.6 KV large AC machines 120 nos.
Mill duty DC M/C & RT motors 420 nos.
Welding machines 150 nos.
Transformers 25 nos.
Electromagnets 25 nos.
Site repairs 40 nos.
Apart from handling all types of routine jobs (described above) required to keep the Plant
running, handling emergencies & site repair of large machines is one of the major function of
RS(E). When there is a break down in a huge machine bringing the process to a halt, on line
repair is the only option. On line repair demands exceptional skill which are being handled by
expert technicians of RS (E).
Computerisation:
RS(E) is having a computerised networked system called CEERS developed in-house
through which it manages all its activities from work order raising at the customer end,
planning and scheduling the jobs, repair history tracking, to delivery of jobs. The advantage of
the system is that all the information is accessible for its customers sitting at their end.
Main Features of the system are
• Databank of electrical equipment of the Plant
• Work order handling and progress monitoring
• Equipment repair history tracking
• Online monthly planning
• Failure reporting & analysis
• Overhauling scheduling
AIR CONDITIONING
These units are running with environment friendly refrigerants. The availability of AC units
contribute directly to major production units like Coke Oven, Blast Furnaces, Steel Melting
Shops, Hot Strip Mill, Plate Mill & Power Plants. Uninterrupted reliable operation of Central
Plants for Gopabandhu Auditorium, C&IT, Control Rooms and Conference Rooms of various
departments in Works & Non-works has been made possible due to expertise & skill of Air-
conditioning department. Major overhauling of Crane AC units through in-house expertise,
erection & commissioning of Central Plants & Package AC Units are major strengths of the
department. Air-conditioning department ensures operation of Room ACs for comfort and water
coolers as a welfare measure throughout the Plant.
This is a centralized department catering to the need of the whole plant in the areas of
maintenance of mechanical aspects of heavy electrical machines and electrical aspects of EOT
cranes and ground equipment. This department has two sections, i.e. Machine Section and
Electrical Section.
Machine Section:
Machine section is located in front of CET building. This section undertakes the following Jobs:
• Precision alignment of all critical electrical drives
• Dismantling and assembling of large size AC & DC machines including of preparing of
white metal bearings.
• Replacement of HT, LT and DC machines.
In addition to this daily service is given to Hot Strip Mill to maintain roller table drives.
Electrical Section:
Electrical section is located in front of ED (Works) building. It undertakes the following jobs:
• Manufacturing of electrical panels and panel boxes for EOT cranes and ground equipment
drives.
• Revamping/ Relocation/ Commissioning of EOT cranes.
• Trailing cable conversion from trolley busbar system of EOT cranes.
• Pendant operation of cranes based on customer department requisition.
Recently HM (E) has taken up the salvaging of master controllers, resistance boxes, and other
electromechanical switch gears.
The job of HM (E) covers
• Weekly shutdown
• Planned shutdown and capital repairs
• Other supportive/ preparatory requirements based on requisition.
The objective of HM (E) is to give continuous support to production departments to meet their
job requirements in terms of timely completion, quality, quantity, reliability with all-round
safety and without rework in order to meet their production targets.
The role of Production, Planning and Control department (PP&C) in an integrated steel plant
having varied product-mix of Flat Product like RSP is very vital. The growth in production and
hence its financial performance depends on the dynamic planning in tune with market demand.
The major function of the department is to ensure proper & timely execution of various orders
placed by various customers both in India and abroad. From receipt of order to its execution,
the entire planning, coordination, follow up etc. rest with PP&C.
Order Processing:
• Receipt of order
• Analysis of order
Production Scheduling/Planning:
• Issuance of Steel/slab/coil order
• Issuance of Schedule/Planning
• Management of Inventory both for finished / semi-finished & in-process materials.
Dispatch:
• Dispatch Planning both by Rail and Road.
PP&C department works as a interface between Sales Resident Manager (SRM), the nodal
agency of Central Marketing Organisation (CMO) and various Production/Service units of the
Plant. It receives order of various customers through SRM/CMO & International Trade
Division (ITD), SAIL and converts it into Production Schedule so as to ensure timely delivery of
required product w.r.t. quality and quantity. For achieving the objective the department
plans/coordinates from order procurement stage to its execution through Production Planning /
Scheduling and dispatch of finished steel to its customers spread all over the country and
export to other countries. For this round the clock planning is being done at various planning
offices situated at various Shops/Mills in the Plant.
Based on priority orders & requirement of Mill Scheduling, daily production of each unit is
planned. Daily discussions are held at a scheduled meeting with Shipping Incharges & Traffic
to plan & monitor rake dispatches.
Apart from above, other sections of PP&C carrying out the following functions also:
• Long Term Planning
• Statistical Section
• Plant Control
• Sales Co-ordination (Road Dispatches)
• Weigh Bridges
Statistical Section:
The Statistical Section Maintains the Production, Consumption and Technical Parameters of
various products. Various MIS inputs varying from daily to weekly, monthly, yearly are
generated and serves as a input in decision making process for effective control function.
Annual Statistical Books containing all important data for the Plant are also published by the
section.
Plant Control:
The Main Plant control, the centralised control room at RSP, which works round the clock
serves as the nerve centre at the plant which monitors operation, maintenance, delays &
breakdown etc. and provides feedback to the Senior Officers in turn helps them in decision
making at right time. Also certain emergency decision makings are done by the department in
emergent situations like power failure etc.
Sales Coordination:
This section
• Coordinates road dispatch for prime products both for home sales and export.
• Issues delivery order for road dispatches both for RSP & Customer Transport.
• Organises road transport/ handling of contracts.
Weigh Bridges:
13 No. of weigh bridges are manned by PP&C department which spreads through out the plant
for weighment of both for internal consumption and outward/inward movements for commercial
purposes.
Computerisation:
From 1st April 2005 the total function of the department starting from receiving/ processing
orders, production programming, material tracking and dispatch coordination has been
computerised under production, management system. This has helped in online tracking &
monitoring, production scheduling/ preparing, dispatches etc., networking of weigh bridges
system, electronic preparation & transfer of key-documents like Test Certificate, Delivery
orders, Invoices and other Management Information System reports.
Traffic & Raw Materials Department plays a vital role in the working of an Integrated Steel
Plant. It can be compared to circulatory system in Human body. As circulatory system carry
food to all parts of body and collect wastes generated by the different units of body, Traffic
Dept. Also function in similar way supplying raw material to different units of plant and collect
semi finished, finished and wastes/ bi products generated by those units. Its general role
consists of in
Procuring and supplying necessary raw materials to various user departments
Internal movement of in-process and other materials from one section to another section
Dispatching finished products to outside parties. At 1.8 MT stage of production a total of
about 14 to 15 MT of materials needs to be handled.
All the materials are handled in wagons, which move on rails with the help of Diesel Electric
Locomotives. Taking over of the wagons, coming from outside from Indian Railways and
handing over of wagons from inside the plant to Indian Railways is done at the Exchange Yard
at Bondamunda. All the incoming wagons brought to the Marshalling Yard are sorted out and
are sent to the various loading and unloading points. The marshalling yard has two grids of
tracks so laid out that there is minimum interference of wagon movement. The tracks, crossing
and about 100 points in the marshalling yard are controlled by the automatic electrical route
relay interlocking system. The Traffic and Raw Materials Department achieves its objectives
through the functioning of the following sections:
A) Movement (Logistics):
This section looks after the supervision and control of internal and foreign wagons movement in
the five zones of the plant. It is responsible for the receiving of different wagons from the
railways, sorting them out and sending them to the consuming points and collecting the loaded
wagons from the mills and handing over to the railways. This section also looks after the
various internal movements round the clock.
WAGON FLEET
It is responsible for inspection, day-to-day maintenance and major repair of wagons. Re-railing
of rolling stocks including HM ladle, Slag pot, Quenching Car and Foreign Wagons is the
responsibility of C&W section. Joint inspection of incoming and outgoing Railway wagons is
done twice in a year for fixing damage and deficiency rate.
C) Permanent Way:
This section is fully responsible for the maintenance of the 200 KM long railway tracks and 700
points. It takes up all civil works connected with these lines and new track line extensions etc.
This section is also responsible for house keeping of yards and maintenance of track drains
including removal of wild growth.
D) Raw Materials:
This section is fully responsible for the procurement, quality control, internal handling and
supply of all raw materials and dispatch of specified by-products such as coke fractions etc. It is
responsible for the unloading of various raw
materials at the proper places. It also keeps an
account of the receipts and dispatches of all raw
materials.
LOCO FLEET:
Sl. Fleet Type Detail Qty. in Remarks
No. no.
1 General 80 T, Double unit, 470 hp, 3 3 nos. will be phased out.
Electric Loco GE make, 400 series
90 T, Double unit, 600 hp, 11
GE make, 600 series
2 WDS 6 Loco 120 T, 1400 hp, DLW 20
make, 1400 series
WDS 6ad 124 T, 1400 hp, 1400 6 3 nos. will be added in lieu
series, DLW make of above phased out GE
locomotives
This shop is responsible for maintaining and up keeping of these locomotives. It is also
responsible for maintaining 2 numbers of Rail Cranes for its use in different department of
RSP.
F) Commercial:
This section deals with Indian Railways in indenting
of empty wagons for dispatching products to outside
customers and in calculating the demurrage charges
payable to Indian Railway wagons inside the plant
for more than the allotted time.
Production of iron in Rourkela Steel Plant (RSP) started in January 1958 was followed by the
formation of Scrap and Salvage Department (SSD) as a separate unit of the Plant in the
begging of 1961. SSD working area is located between Silicon Steel Mills and Pipe Plants,
extending to western side up to plant boundary.
The Scrap and Salvage Department of Rourkela Steel Plant plays significant role in achieving
twin objective of gainful utilization of solid waste generated in RSP and revenue maximization.
The Department deals with salvaging of scrap /metallic from solid waste for use as melting
scrap & also processing of LD slag for internal consumptions and external dispatch. Gainful
utilization of slag helps not only in reduction of cost of steel production, but also helps in
making the environment free from dust etc.
Apart from these major activities, SSD also collects thin baleable scrap & other heavy scrap
from length & breadth of the Plant, processes these to chargeable size for use as melting in LD
converters. Thus, it plays a major role in improving the house-keeping of the Plant also.
Main function of SSD is recovery of scrap & processing of LD slag, some of the other functions
are as enumerated below –
• Processing of tundish skull by lancing at lancing yard near SMS-II & partly by breaking at
skull cracker crane, for use as melting scrap in SMS-II.
• Collection & conversion of thin baleable scrap to Bale Press for use as melting in SMS-I.
• Receiving arising from Blast Furnaces, SMS-I etc. Processing these for recovery of iron
bearing scrap for charging in Blast Furnaces & SMS-II.
• Collecting scattered scrap i.e. wear/maint./structural scrap from various Units of the Plant,
processing the same for charging as melting scrap in SMS -I/II.
• Processing of Mill scales generated from SMS-I/II & Rolling Mills for base mix preparation
to OBBP.
• Transporting sludge generated from SMS-I to OBBP for base mix preparation.
• Co-ordination with Rolling Mills, PPC and T&RM etc. for supply of Mills scrap to SMS-I/II
for melting.
• Processing of LD slag in the crushing unit for recovery of metallic and conversion to various
useful fractions.
• Supply of various fractions of LD slag to different units of the Plant, 0 to 5 mm fractions are
sent to OBBP mainly for base mix preparation, 5 to 20 mm size is used for civil works and
20 to 40 mm size slag is used in Blast Furnaces as flux etc.
• Salvaging of rejected/used refractory bricks, damaged slide-gate plates etc. dumped in SSD
area and to dispatch the same to external customers.
All the solid waste generated in Steel Melting Shop–II during steel making process is handled
by SSD & after recovery of metallic, LD slag is crushed and screened to useful fractions which
not only helps in reducing production cost of steel making, but also helps in keeping
environment free from waste-disposal.
Another milestone achieved by SSD is handling of 100 % residual Blast Furnace slag after
partial pouring in Slag Granulation Plant. Earlier, since inception of the RSP, such slag was
dumped outside the Plant premises, which was creating Law and Order problems. After
modifying the dumping pits and arranging the required infra-structures from April ’2005, all
the residual slag is being dumped inside the Plant premises. SSD is not only managing the
dumping pits successfully for handling of BF slag as well as SMS-I slag, but also processing the
slag for recovery of metallic, which is reused in Blast Furnaces as BF fines.
While working under adverse and hazardous conditions, SSD has never over looked the
objective of the Rourkela Steel Plant to produce “injury frees steel”. As a step towards this, by
safety awareness programme and imparting Safety training to employees, SSD has a unique
distinction of having “zero accident” since October ’2007.
Believing on “healthy worker is a productive worker”, SSD with help of Jawaharlal Nehru
Occupational Health Services Center has ensured health check up of all the employees of SSD
since last 3 years. It is well known that the use of LD slag and recovery of metallic scrap in Iron
and Steel making not only helps in reducing the cost of Iron and Steel making, but also helps in
keeping environment clean & SSD is trying to achieve both.
The main job of the department is to provide service inside Steel Plant for maintenance of 750
Nos. of buildings, 50 Km of main roads, 50 Km underground drains, 51 Km of open drains, 30
Km of perimeter wall, 3,30,000 MT of roof structures of different units, 14,40,000 m2 of roofs,
16,96,000 m2 plinth area buildings, 7,500 Nos. of sanitary installations, 69 Nos. of public
conveyance buildings, canteens, rest sheds, waste disposal yards etc. The department is also
looking after the maintenance of Fertilizer Plant.
Except the maintenance jobs, small value AMR projects, pollution control & debottlenecking
schemes are also taken up by this department. Activities like building monuments, developing
gardens, renovation of canteens, rest rooms, sanitary installations, survey supports, face lifting
of plant premises during VIP visits are also taken up as & when required.
Assistance is taken from approximately 40 Nos. of external agencies for delivering Civil
Engineering Services for entire plant. The plant area is divided into 5 zones in Civil
Engineering Services.
Equipment Strength:
STRUCTURAL INSPECTION
Regular inspection of all industrial structures, chimneys and stacks, structures in mines
area, Mandira Dam and structures of NSPCL to assess quantum of defects arising due
to any accident, environmental condition etc.
Preparation of technical reports citing defect list, remedial measures/suggestions in a
book-let from and taking approval of competent authority for liquidation of
damages/defects.
Distribution of approved reports to owners of the shops/department for liquidation of
defects.
Stage-wise monitoring/rendering help during execution to liquidate defects, final
inspection after rectification/liquidation.
A joint certificate with owner department is issued stating the satisfactory liquidation of
the defects.
The Contract Cell (Works) was formed in the year 1998. It processes and awards all types of
contracts of the Works area.
WATER MANAGEMENT
In an integrated steel plant huge amount of water is required for the process as well as for
human consumption. Total industrial and potable water requirement of Rourkela Steel Plant is
met from river Brahmani. To make the raw river water suitable for use, the water is treated at
Tarkera Pump House. Water Management Department (WMD) has the responsibility of
supplying treated make-up water to different recirculation systems and other once through
systems in the plant, drinking water to the plant consumers. Supply of water is made to
Tarapur Filter House for sector-22, treatment units at sector-21 and sector-8 for township
drinking water system. The total water requirement of NSPCL (joint power venture of SAIIL-
RSP & NTPC) is also supplied from the plant make-up system. In addition to this, operation &
maintenance of total water recirculation systems of SMS-I, HSM, PM & CRM are also under
WMD. Sections of WMD and the main functions thereof are as under:
1. Tarkera Pump House: Provides make-up water to the entire plant. It also provides a
part of water requirement to township.
2. Drinking Water Station: Treatment and supply of drinking water to plant for various
use including for fire fighting
3. Mandira Dam: Stores and supply water for maintaining water level of river Brahmani
at Tarkera pump house.
4. Rolling Mill Pump House: Total recirculation water system of HSM & CRM
5. Plate Mill Pump House: Total recirculation water system of Plate Mill including soft
water system for Reheating Furnaces of PM & HSM.
6. SMS Pump House: Total recirculation system of SMS-I (excluding CCM-I), TOP-I &
CRGO complex.
7. Modernisation (Construction) Water Pump House: Provides make-up water & drinking
water to Modernization area like: OBBP, SMS-II, SP-II & TOP-II.
8. Distribution: Maintenance of make-up & drinking water pipe line network throughout
the plant including modernization area.
The river level on upstream of pick-up weir is maintained by regulating the sluice gates, as per
the requirement. Falling shutters give passage to river water during high floods.
Raw water from the river is pumped to the treatment units. There are two raw water pump
houses, one constructed originally at 1 MT. stage of the plant and other one under
modernization scheme. The old raw water pump house is designed for vertical, dry pit type
centrifugal pumps and the new one for vertical turbine wet pit type pumps.
The old raw water pump house comprises two intake chambers, named upstream and down-
stream chamber. Raw water flows by gravity through two nos. of 1000 mm diameter steel pipes
laid from the upstream of pick-up weir to each intake chambers. Each of these pipes has been
provided with 3 Nos. of stage gates which are operated during monsoon to prevent the
carryover of silts from river. Six dry pit type vertical centrifugal pumps, three in each chamber,
have been installed. The new raw water pump house has been constructed on the river itself on
the upstream of pick-up weir. It comprises four intake wells with sluice gates at inlet ports. 3
Nos. of wet pit type vertical turbine pumps for plant water supply and two nos. of wet type
vertical turbine pumps for township water supply have been installed. The capacity of raw
warter pumps for plant supply is 3500 cbm per hr at 26 mtr head and 1200 cbm/hr at 80 mtr
head for town ship water supply.
The treatment system comprises seven units of aeration tank and sludge blanket type
clariflocculators along with chemical storage, chemical solution preparation and dosing facility.
Raw water enters through the aeration tanks where aeration takes place by means of fall of
water and compressed air and then enters into the clariflocculators for flocculation and
clarification. Proportionate quantity of solutions of ferrous sulphate and hydrated lime are
dosed in raw water in the aeration tank. Clarified water which slowly rises upwards in the
clari-flocculators is collected through the peripheral launder and stored in the respective clear
water storage tank. Capacity of each treatment unit is 2000 cbm/hr.
As the water is directly drawn from the river, the turbidity of raw water varies widely over the
year. It varies from 5,000 ppm during rainy season to less than 10 ppm during summer. It also
rises very rapidly in case of any flash flood. Ferrous sulphate and hydrated lime are required to
be dosed during rainy season for treatment of raw water. These chemicals are dosed manually.
Besides the above chemicals, compressed air is used for aeration of water.
Make-up water is supplied to Rourkela Steel Plant from Tarkera Water Works, which is
situated at about 4 km away through 4 nos. of NB-1000 size underground rising mains. Two
rising mains were laid at 1 MT Plant stage, third one was laid during 1.8 MT stage. Fourth
rising main was laid during modernisation. All the rising mains are made of welded steel pipes
with anti-corrosive coating on external surface.
Make-up water received through the rising mains is distributed in the plant through an
underground ring main of size NB 1000/NB-960 spreading in the entire Plant. A high level
tank, staged at RL: 792.3 feet, is connected to the make-up water ring main to act as a surge-
cum-storage tank.
Local cooling water recirculation systems comprising of induced draft cooling towers, hot and
cold water pumps are installed separately for CCD, Blast Furnaces, SMS-I and SMS-II, TOP-I,
TOP-II, Rolling Mills, Plate Mill, Silicon Steel Mill, CPP-I, Central Air Compressor Stations
etc. Evaporation, drift and bleeding losses of recirculation systems are replenished with fresh
make-up water supplied through the ring main. Chemicals such as biocide, dispersant, scale
and corrosion inhibitor are dosed in the circulation systems, to maintain the water quality of
the recirculation systems, and to reduce the make-up water consumption. Separate cooling
water recirculation systems were provided for SMS-II, CCM-I, CCM-II, Calcining Plant during
modernization of RSP.
There are also a number of once-through cooling water systems in various shops viz., Sintering
Plant-I, Lime and Dolomite Brick Plant, Electrical Sub-stations, where make-up water is
directly used for system cooling purpose and discharged to drain. The water for NSPCL, IDL in
fertilizer plant area is supplied from the make-up water distribution network.
In order to supply make-up water at desired pressure to the modernization units in new areas
viz. SMS-II, CCM-II, Sintering Plant-II, Calcining Plant, TOP-II, OBBP, a separate pump
house has been commissioned. The modernization pump house consists of make-up water
pumps which pump make-up water to the modernization units. Separate make-up water pipe
lines with a high level tank comprising separate chambers for make-up water have been
provided in the modernization area to act as storage-cum- surge tank. Make-up water from the
existing pump house is pumped to new high level tank for onward distribution to various
modernization units. There are total 6 nos. of make-up water pumps having capacity of 300
cbm/hr at head of 55 mtr.
Mandira Dam:
The main source of water for Rourkela Steel Plant is river Brahmani, which is formed by the
confluence of two rivers, Sankh and Koel at Vedvyas near Rourkela. This river is able to supply
water throughout the year except during the summer months. In order to have a regulated flow
in river Brahmani throughout the year, a dam named Mandira Dam, was built on river Sankh,
at a distance of 26 KM upstream of the river from Rourkela by Rourkela Steel Plant. The Dam
was built mainly for the purpose of storage and supply for meeting the water requirement of
RSP during summer seasons, when there is a drastic reduction in water flow in river
Brahmani. The salient features of Mandira Dam are as given below:
A separate ring main of NB-400 size, welded steel pipe, has been laid underground for
distribution of drinking water. Besides for drinking purpose, drinking water is also supplied to
various other process requirements viz. gas cleaning, acid regeneration, air conditioning, fire
fighting etc. The drinking water pumping facility comprises horizontal, centrifugal, dry pit
installation type pumps, which pump the drinking water to the High level tank. There are total
11 Nos. of pumps comprising of 2 nos. of 3 MGD capacity, 6 nos. of 2 MGD capacity and 3 nos. of
1 MGD capacity.
A separate drinking water station has been constructed to supply drinking water to the
modernization units. Drinking water is prepared by filtration of make-up water in the pressure
filters and is then pumped to high level tank for distribution to various consumers in the
modernization station area. There are 3 nos. of pressure filters comprising of 2 nos. of 60
cbm/hr capacity and 1 no. of 80 cbm/hr capacity. For supplying filtered water there are 3 nos.
pumps of capacity 80 cbm/hr at 55 mtr head.
Rourkela Steel Plant, being the first industrial unit in Rourkela, in the late 50s’, continues to
meet its social obligations for supplying water to the various peripheral villages and colonies in
and around Tarkera and Rourkela Steel Plant.
b. Collection Pit with bucket type EOT crane for mill scale removal near SP-I.
Contaminated return water (contaminated with mill scale and oil) from HSM is
collected in Collection pits where mill scale is removed by a bucket EOT crane and
water is further sent to settling tanks through scale pumps situated at Scale Pit-I pump
house. There are 6 nos. of scale pumps of capacity 1440 cbm/hr at 45 mtr head.
c. 4 Nos. of Settling tanks each of capacity 1550 m3/hr, size: 55 mtr long x 8 mtr width x
3.5 mtr depth, where mill scale and oil is separated with the help of scrapers and oil
skimmers respectively. Overflow water from these tanks is passed to filter beds for
further purification to remove oil traces and finer size mill scale. The mill scale from
settling tank entry point is removed by one EOT crane for subsequent use at OBBP.
d. 6 Nos. of rapid sand gravity filter beds (capacity: 1100 m3/hr, size: 25 x 3 mtr) arrest
finer scale and the filtered water is stored in 2 Nos. of storage tanks for supply. The
supply pumps draws water from storage tanks. Make-up water is added in these storage
tanks to recoup the losses.
e. 2 nos. of wash water pumps and 2 nos. of wash water return pumps for filter
backwashing. Backwash water re-circulated through settling tanks.
f. Cooling water return collection pit in HSM to collect return water from CRM and
cooling water from HSM, which is non-contaminated but with high temperature. There
are 8 nos. of pumps installed in the CWRS of capacity 1200 cbm/hr at 30 mtr head. With
the help of pumps the return water is passed through cooling towers to lower the water
temperature and storage in the break-pit near RMPH.
HSM BOOSTERS
COLLECTION PIT
SETTLING TANKS
FILTER BEDS
SUPPLY PUMPS
scrapper & oil skimmer for removal of scale and oil, return pumps (2 nos. discharge 1025
CMH, head 30 mWC), pressure filters, cooling towers, sumps and supply pumps (2 nos.,
discharge 960 mWC, head 60 mWC). Mill scale is removed with an over-head bucket type
EOT crane and oil is removed from settling tan wit oil skimmers.
c. Soft Water System: This system provides soft water to Reheating Furnaces of Plate Mill
and Hot Strip Mill. Soft water is pumped to reheating furnaces (HSM: 4 pumps:
discharge 650 CMH, head 55 mWC, Plate Mill: 3 pumps, discharge 550 CMH, head 55
MWC): and the return water is passed through plate type heat exchangers for cooling.
For cooling of hot return soft water in the heat exchangers, industrial cooling water is
circulated. This industrial cooling water system is a recirculation system with pumps
(HSM: 3 pumps: discharge 930 CMH, head 30 mWC, Plate Mill: 2 pumps, discharge 655
CMH, head 30 mWC) and cooling towers. A Soft water treatment plant has been
provided to supply soft water to make up the losses in the soft water circuit. The soft
water treatment plant consists of aerator, iron removal filters, pressure filters, base
exchangers. An overhead emergency tank is provided for supply of soft water to
reheating furnaces in case of power failure up to 20 minutes. In case of extended power
failure beyond this provision is also there to supply make-up water to the furnaces. Two
pumps of discharge capacity 555 CMH and head 45 MWC take water from the common
sump of recirculation water are installed to supply water for cooling of compressor of
HSM.
There are 5 pumps each for supplying water to LD and Oxygen plant respectively and 8 nos.
pumps for supplying return hot water to cooling towers. There are 4 nos. of cooling towers.
A new pump house named as CRGO pump house was constructed to supply direct cooling water
and indirect cooling water to VAD/VOR unit of SMS-I. Each system is consisting of supply
pumps, return pumps, cooling towers and sumps. This pump house is a zero discharge unit.
Oxidation Lagoon
The effluent water from the various plant units inside the plant is collected in the oxidation
lagoon through 10 nos. of outfalls. The water is treated in the lagoon by natural oxidation
process to maintain the effluent water quality. The lagoon is spread over an area of 49 hectares
and is provided with 3 nos. emergency gates and a weir for discharge of water from lagoon.
ENERGY MANAGEMENT
Energy Management Department in Rourkela Steel Plant is primarily responsible for meeting
the fuel/ energy requirements of all the consuming units both qualitatively and quantitatively,
while keeping the energy cost at the minimum possible level. In order to meet the above
objective, the department performs the following functions:
Planning the fuel requirements and gas / utility balances as per the production plan and
consumption norms decided jointly with the consuming departments. Fuel includes
Coke Oven Gas, Blast Furnace Gas, Converter Gas and Mixed Gas while utilities
include steam, oxygen, nitrogen, argon and synthesis gas.
Monitoring of the optimum availability and distribution of fuel gases and utilities on
round the clock basis from Energy Centre.
Preparation of daily, monthly, annual gas / utility balances, specific Energy
consumption and cost reports. Analysis of deviation and taking up with the concerned
agencies.
Energy conservation activities in all the energy consuming units to ensure efficient
utilisation of energy. This includes maintaining of operational parameters, combustion
control, condition of fuel/ energy consuming equipment, status of instrumentation and
control system and inspection/ follow up for rectification of leakages.
For ensuring gas safe operation in the plant gas/ oxygen/ explosive mixture testing is
done for all protocol/ non-protocol jobs as per requirement. Also gas safety equipment
like masks, carbon monoxide and oxygen monitor and breathing apparatus etc. are
maintained in proper condition.
Maintenance of the yard utility grid to ensure uninterrupted supply of fuel gases/
utilities to the consumers besides day to day maintenance jobs. This involves repair/
replacement activities as per requirement.
Involvement and participation in all the projects as per RSP expansion programme and under
AMR and other schemes, to ensure adoption of energy efficient technologies and proper
integration of the individual unit gas/ utility pipe lines with the main grid.
SAFETY ENGINEERING
Iron and Steel production being a complex and hazardous activity, SAIL recognizes its moral,
economic and legal obligations to prevent hazards, provide healthy working environment and
guard against all foreseeable risks. The management of SAIL recognizes its obligation to
endeavour to progressively identify, control and eliminate all hazards and conditions which
present risk to employees and / or possible damage and loss to the plant and equipment
including products.
Safety Engineering Department of Rourkela Steel plant is a technical wing with a multi
disciplinary team discharging all the above functions. It has been the constant endeavour of the
department over the past 40 years to create a hazard free, safe environment for the employees
of Rourkela. Towards this end the department has been carrying out the following major
functions:
5. Creating awareness of employees through visuals like hoardings, posters, film -shows,
printed handouts, bulletins, safety campaigns, various competitions etc.
6. Publishing various safety bulletins, printing permit to work. (Holding protocol meeting
for major shutdown and other hazardous jobs.), Crane Log Book.
7. Encouraging joint participation in the field of safety through the Central Safety
Committee (at the apex level) and the safety committee of departments (headed by
General Managers). Monitoring implementation of the recommendations of these
committees.
8. Briefing the contractors on the hazards inherent in their area of work and the safety
requirements for their jobs before start of the job. Day-to-day monitoring of the work of
contractors and ensure penalty to defaulting contractors.
9. Conducting Safety Audits by internal as well as external teams and taking necessary
actions to liquidate the deficiencies noted.
10. Working in close liaison with Occupational Health Centre to promote a clean, healthy
and safe environment.
11. Monitoring compliance of the various provisions relating safety as numerated in the
Factories Act, 1948.
12. Maintaining constant liaison with the various statutory authorities like the Director of
Factories, Inspector of Factories & Boilers, various Labour Institutes.
14. Organising various safety promotional activities like National Safety Day, Safety
Housewives / school children, Road Safety Campaign.
RSP has won several National Safety Awards for its exemplary performance. RSP won Steel
Minister’s Safety Shields for best performance and RSP also won many awards from the State
Government and the Standing Committee on Safety in the Steel Industry.
a. The safety of its employees and the people associated with it including those
living in its neighbourhood.
b. Pursue the safety efforts in a sustained and consistent way by establishing
safety goals, demanding accountability for safety performance and providing the
resources to make safety programme work.
ENVIRONMENTAL ENGINEERING
The quality of waste water generated at different sources is regularly monitored by collecting
samples from 50+ locations throughout the plant including the final discharge of effluent from
Lagoon to River Brahmani. Any deviation from the norm is analysed for taking corrective
actions.
The stack emissions from 26+ number of active stacks are regularly monitored for Dust
emissions (SPM) into environment. The fugitive emissions from Coke Ovens viz., gas leakage
from oven doors, charging lids & accession pipes are regularly monitored for effective control.
The dust and noise levels in shop floor of different departments are regularly monitored. The
efficiency of air pollution control equipment like Electro Static Precipitators, Bag houses etc.
are also monitored regularly for suggesting corrective actions. Env. Engg. Dept. has also
installed 4 no. of online stack monitors at Coke Oven batteries.
The cumulative effect of air pollutant emission from different sources like stacks, sources etc.,
are monitored at 6 no. of ambient air quality monitoring stations, which are at OBBP
administration building, EED building, RDCIS building, PMPH building, BOD plant building
& TOP#2 administration building. This department has established two no. of automatic
ambient air quality monitoring stations; one inside the plant at ED (W) building and another at
Indo-German club of Steel Township which is first time in Indian Steel Industry. These
stations continuously monitor the levels of suspended particulate matter, respirable dust,
Sulphur Dioxide, Oxides of Nitrogen, Carbon Monoxide, Hydrocarbons & Methane. The
pollutant levels are displayed on a bill board continuously and the data is downloaded regularly
from the central station installed at Environmental Engineering Department.
Environment Information Management System (EIMS) has been developed, which is a unique
online software system developed on Oracle 10g platform using optical fiber network, first of its
kind in Indian Steel Industry, to strengthen the pollution control facilities by online monitoring
of various pollutants and giving first hand information to Management for taking corrective
actions. A road map identifying new pollution control projects and strengthening of existing
pollution control projects is prepared, to meet the future requirement in view of stringent
statutory requirements and commitments given under Corporate Responsibility for
Environment Protection (CREP).
Environmental Engg. Department has taken up a CDM Project “Enhancement of waste gas
recovery from SMS#2 and its utilization in Captive Power Generation”. This is the first CDM
project in SAIL which has got registered with UNFCCC. Env. Engg. Department is also
actively involved in projects for replacement of Ozone Depleting Substances (ODS) with non
ozone depleting substances.
The Environmental Engineering Laboratory is provided with latest instruments for analysis of
various parameters. The laboratory is equipped with
• AAS (Atomic Absorption Spectro Photometer)
• HACH 2010 spectrophotometers
• Orion Ion Analyser
• BOD(Biochemical Oxygen Demand) apparatus
• BOD incubator
• COD(Chemical Oxygen Demand) reactor
• Phenol Distillation Sets
• Auto Titrating apparatus
• High volume samplers
• Respirable dust samplers
• Stack monitoring kits
• Flue gas analysers
• Flow meter for open channel flow
• Noise meter
Environmental Engineering Department has recently developed facilities for biological testing
of water and waste water samples.
FIRE SERVICES
The Fire Services Wing of the erstwhile Hindustan Steel Security Force (HSF) was established
under the provision of security scheme, compiled by the security advisor, HSL. After the
induction of CISF, Fire Service was made a separate department of Rourkela Steel Plant.
Objective:
1. Prevention of Fire
2. Prevent Loss of Life & Property
3. Extinction of Fire.
Operation:
The most vital of all the four wings is the operation wing. The prime responsibility of reducing
the response time, minimize loss of Life & Property lies with the operation wing by responding
to an emergency at its earliest.
There are four strategically located Fire Stations inside RSP to cover the whole plant. These
are:
• Central Fire Station (covering Iron and Steel zone, Admn. Building, Captive Power
Plant-I, SP-I, Aux Mills, All shops, Air Strip and Steel Township areas etc;)
• Modernisation Fire Station (covering OB & BP, SMS-II, CCM-II, CP-II, SP-II and TOP-
II units etc.)
• Coal Chemicals Department Fire Station (covering Coal Chemicals department, Coke
Ovens deptt, Fertiliser Plant & Fert. Township.) and
• Rolling Mills Fire Station (Covering Rolling Mills, SSM & Pipe Plants).
These stations are fully manned round the clock in three shifts headed by a Fire Station In-
Charge in each shift. An Executive (over all in-charge) is also posted in each shift at Central
Fire Station to take care of any occurrence of Fire, Rescue and other emergencies in the Plant,
Steel & Civil Townships & Periphery. In addition, special services like De-watering, Cooling
and Stand-by duties in the plant and at Air-Port are also rendered.
The Central Fire station, which is the nerve center of the Fire Service department, on receipt of
any emergency call, dispatches its appliances at its earliest. On arrival at the scene of fire,
rescue, special service call, the Officer I/c studies the situation and plans his strategy of attack.
Further assistance of manpower or reinforcement of additional appliances / equipment is called
for inter alia VHF or other mode of communication with the control room. The Operation wing,
as a part of its pre-fire planning, also carries out regular Mock drills and Topography study.
The Operation wing fulfills the mission of Fire Service department.
Prevention
This wing fulfils the first objective of Fire Service to Prevent Fire. The major activity of this
wing is to inspection of all hazardous / fire prone areas, the detection and protection systems,
checking of all fire hydrants / fire extinguishers etc.
Maintenance Wing:
Of all the physical resources, the appliances and equipment used by fire service must be trouble
free at any point of time. The wing does all the in-house maintenance, preventive maintenance
of all the appliances and equipment available with Fire Service.
The list of appliances (vehicles) and equipment available with Fire Service department are as
under:
Fire Fighting Appliances & Critical Equipments: The fleet consisting of the following:
Training Wing:
Training wing has to carry out an important task in imparting in-house training to its new
recruits and refresher course for old timers. Both acquiring knowledge and skill, the training
wing is constantly trying to cope up with the needs of the plant employees in general and Fire
Service department in particular. The Fire Control Management (FCM) programme conducted
under the aegis of HRDC department is an unique venture. With faculty support from Fire
Service department added with practical demonstrations this FCM programme enhances both
knowledge and skill of the participants to greater extent. Scheduled Training at shop-Floors on
Fire Prevention & Hand-on-training on ‘Use of Fire Extinguishers’ are carried out every month.
Specialized training programmes, pertaining to only Fire Service personnel are also conducted
at regular intervals.
Planning:
Fire Fighting Consumables, Equipments, Appliances & Human Resources.
Human Resource:
Fire Service department is having 163 highly motivated & well trained / Qualified Officers &
Staff. The grade-wise break up is as follows:
1. Executives 08
2. Fire Station In-Charge 03
3. Leading Fire Operators 126
4. Fire Operators 18
5. Technicians 06
6. Office Staff 02
INDUSTRIAL ENGINEERING
Motivation Schemes:
IED is responsible for Design, Formulation and Implementation of Motivational Schemes in
RSP and Monitoring of the same on a regular basis for improving production, productivity and
techno-economic/cost parameters.
Procedure Orders:
IED formulates various Procedures for Works & Non-Works areas. The objective is to
streamline the system for efficient and smooth functioning and fixing agency-wise
responsibility/accountability. Making amendments in existing procedure orders and issue of
revised procedure orders are also a part of this.
Administrative Items:
The requirement of various items under administrative category are studied and recommended
for procurement for different departments.
Research & Control Laboratory provides metallurgical services to the whole plant units. RCL
role starts from product enquiry to till the product is delivered to the customer. It also handles
customer complaints if any.
It has more than 20 spot labs to carryout inspection, testing activities round the clock in almost
all the shops of the steel plant. Central Lab building houses 10 lab facilities to test water, oil,
coal& coke, refractory etc. The Centralised test house is for mechanical testing and product
certification.
To implement, document and maintain all the management systems in RSP, a Three Tier
Management Review is held regularly by HODs, GMs and ED (Works)/ED (P&A). TQM
Department facilitates in monitoring and controlling Quality, Environment and Occupational
Health & Safety Objectives of the certified departments.
To inculcate TQM culture among the employees of RSP, Quality Month Celebrations are held
every November. Essay, Debate & Quiz Competitions related to Quality is held every year
during the Quality month among employees to bring Quality Awareness and motivation.
Plans are ahead, for certification of Social Accountability i.e. SA 8000 in RSP and also for
integration ISO 9001:2008 QMS certificates of Iron & Steel Zone, Rolling Mills Zone and Shops
& Services Zone into one certificate as RSP (Works) during 2010-11. IMS (Integrated
Management System) Policy covering Quality, Environment, Occupational Health & Safety and
Social Accountability of RSP has been developed with approval of MD, RSP. Integration of
various management systems in RSP is there in the future plans under IMS.
Functioning of AMRM&SC:
AMR-M&SC is the Nodal Agency for Capital Investment Schemes. The Cell scrutinises all
Capital Investment Schemes, obtains sanction and monitors the progress of the sanctioned
schemes. The methodology adopted is:
For prioritised schemes estimated below Rs.10 lakhs the Cell itself scrutinises the proposal and
puts up for sanction. For schemes estimated above Rs.10 lakhs the Cell puts up the proposals to
a duly constituted “Investment Proposal Scrutiny Committee” generally known as IPSC for
further scrutiny and screening. All IPSC cleared schemes of estimated value less than Rs, 20
Crore put up to an APEX Committee for prioritization. Schemes below Rs.10 Lakhs are also put
up by AMR-PM&SC to the same APEX Committee for prioritisation. Thereafter necessary
sanction orders are issued after obtaining MD's approval. For all IPSC cleared schemes of
estimated value more than Rs, 20 crore put up to a committee known as Project Appraisal
Group (PAG) for prioritization and thereafter send to corporate office for necessary sanction. All
expansion plan projects are also scrutinized and processed by AMR-PM&SC for obtaining
corporate sanction and thereafter local sanction orders are issued.
AMR-PM&SC is the agency to constitute survey committee for write-off action and also the
convenor of Central Survey Committee which recommends the “Replacement” of written off
assets. AMR-PM&SC usually does not deal with assets of Administrative Category (such as
Furniture, Photocopiers etc.). Some of the items sanctioned through AMR-PM&SC and seen
around us are Mobile Equipment and Transport Vehicles, Hospital Equipment, High Mast
Luminaries Towers, Weigh Bridges, Lease line Internet Connectivity, Re-building of Coke Oven
battery, Oxygen Enrichment system for Blast Furnace and many more.
In 2008-09 Rs.50 crores were allocated and in 2009-10 Rs.50 crores are allocated to RSP from
Corporate Office for AMR Schemes. Awarding of consultancy to Centre for Engineering &
Technology (CET) for any feasibility study and making tender specification is also undertaken
by AMR-PM&SC.
In addition to that AMR-PM&SC co-ordinate the dumping activity like generation of new
dumping yard, issue of dumping permission for zero value items etc. and also co-ordinate
security related issues like boundary wall inspection, visit of central intelligence team, review
of security aspects of plant etc.
PROJECTS
The Projects Department of RSP is headed by Executive Director (Projects) supported by GMs
(Projects). A multi-disciplinary IPM (Integrated Project Management) team consisting of
officers from Project, Materials Management, Finance & Personnel, functions under the direct
control of ED (Projects). The Project Department is also assisted by a Safety Department Team
headed by DGM (Safety).
EXPANSION OF RSP:
.1 Expansion programme of RSP to 4.2 Mtpa crude steel capacity with a state-of-art facility
was approved in-principle by SAIL Board in its 324th meeting held on 21st May’ 2007 at an
indicative cost of Rs.7668 Crores net of CENVAT (base date: 1st Qtr. 2007).
.2 SAIL Board in its 351st & 351st (extended) meeting held on 15.06.2009 & 19.06.2009, after a
review of the expansion plans of SAIL plants (including investment in mines), approved an
expenditure of Rs. 70,169 Crores. In the case of RSP, the total revised cost is Rs.11,812
crore (net of CENVAT).
.3 The production capacity of Hot Metal, Crude Steel and Saleable Steel after expansion plan
is indicated below:
Techno-economic parameters
Item Present After Expansion
Coke/ Fuel Rate (Kg/thm) 577 392
BF Productivity (t/m3/d) 1.37 2.14
Specific energy (Gcal/tcs) 7.98 5.80
Manpower Productivity
148 262
(tcs man/year)
Consultants:
MECON has been appointed to provide engineering & consultancy services for the facilities in
the Iron & Steel Zone while M/s. M.N. Dastur & Co. shall provide the same services for the
Rolling Mill Zone. M/s. CET has been entrusted with the consultancy services for the packages
pertaining to Coke Oven Battery No.6 and M/s RITES for the Rail infrastructure and logistics.
FLOW CHART
BF COKE
SINTER
SINTER PLANT
PLANT BLAST
BLAST FURNACE
FURNACE COKE
COKE OVEN
OVEN BATTERIES
BATTERIES
2
125m2 (EXISTING
22 xx 125m (EXISTING SP1)
SP1) BF SINTER 6,760,000 BF 1250m33 (EXISTING)
BF ## 11 1250m (EXISTING) 1,855,000 55 EXISTING
EXISTING
11 xx 192m2
192m2 (EXISTING
(EXISTING SP
22
SP 2)
2) BF 1658m33(EXISTING)
BF ## 44 1658m (EXISTING) 1x67,7m,NEW
1x67,7m,NEW BATTERY#6
BATTERY#6
11 xx 360m (NEW)
360m (NEW) NEW
NEW BFBF ## 55 4060m
3
4060m3
4,500,000 GHM
NEW
NEWPP CCM
M (1
(1xx1500
1500 t/d)
t/d) 238,500 HM 4,410,000 NHM
28,900
28,900COLD
COLDPIGS
PIGSFOR
FOR SMS
SMSII &&IIII GROSS COKE- 2,443,400
201,800
201,800COLD
COLDPIGS
PIGSFOR
FORSALE
SALE 3,665,000 (2,192,000 BF Coke AND
506,500 HM
251 ,400 Under size, out of
SMS- SMS
SMS ––IIII((3/3
3/3BOF
BOF OPERATION
OPERATION))
SMS-II((1/2
1/2OPERATION
OPERATION)) which 270,000 BF coke will
22 xx65 22 xx150
150tt–– EXISTING,
EXISTING, 11xx150
150 tt–– (NEW)
(NEW))
65ttBOF
BOF be surplus)
3,772,000 LS
RSP-
RSP--REVISED
RSP
RSP- REVISED LS 508,400
4.5 SEC.
SEC. REF.
REF. (EXISTING) SEC.
SEC. REFINING
REFINING(150 (150ttEACH)
EACH)
4.5 MT
MT HOT
HOT METAL
METAL (EXISTING)
11 LF
11 LF,1
LF,1VOR,1
VOR,1 VAR
VAR LF (EXIS.),
(EXIS.), 22LF,
LF, 11RH
RH-- OB
OB (NEW)
(NEW)
4.2
4.2 MT
MT CRUDE
CRUDE STEEL
STEEL
LS 508,400 3,772,000 LS
(0.820
(0.820 MT
MT SEMIS)
SEMIS) CCP
CCP––II CCP
CCP––IIII
3.9
3.9 MT
MT SALEABLE
SALEABLE STEEL
STEEL 1X1-STRAND
1X1-STRAND(EXISTING)
(EXISTING) 22 xx1–STRAND
1–STRAND SLAB
SLABCASTER
CASTER (EXIST.),
(EXIST.),
500,000 SLABS
11 xx11––STRAND
STRANDSLAB
SLABCASTER
CASTER(NEW)
(NEW)
3,700,000 SLABS
1,850,000 SLABS 1,000,000
SLABS 530,000
SLABS INTERPLANT
INTERPLANT SLABS
SLABS EXISTING
EXISTING
TRANSFER
TRANSFER TO
TO BSL
BSL FOR
FOR SALE
SALE NEW
650,000 1700
1700 MM
MM HSM
HSM EXISTING
EXISTING NEW
650,000 170,000
170,000
1,805600 HR COILS PLATE
PLATE MILL
MILL PLATE
PLATE MILL
MILL
325,000 HR COILS (3.1
(3.1MM WIDE)
WIDE) (4.3
(4.3M
M WIDE)
WIDE)
85,000 HR COILS 86,000 59,500
EXISTING
EXISTING 490,800
HR
HRCOILS/SHEET/
COILS/SHEET/
PICKLING
PICKLING LINE
LINE EXIS.
EXIS. ERW
ERW SPIRAL
SPIRAL WELD
WELD
PLATES
PLATESFOR
FOR SALE
SALE ANN/PICK
ANN/PICKLINE
LINE PIPE
PIPEPLANT
PLANT PIPE
PIPEPLANT
PLANT 241,000
312,713 PICKL. COILS 1,245,400
1,245,400
197,959 114,754 18,000 42,000
NORM.
NORM.FACILITIES
FACILITIES
55 STD
STD EXISTING
EXISTING IN
EXIST.
EXIST. CRNO
CRNO INEXISTING
EXISTINGFEC
FEC
1420
1420 mm
mm 1700
1700 mmmm NEW
REVERS.CRM
FACILITIES
FACILITIES NEWPIPE
PIPE
TANDEM
TANDEM CRMCRM REVERS.CRM COATING
COATINGPLANT
PLANT
NORM. PLATES AS ROLLED AS
75,000 13,000 240,000 249,800 ROLLED
HOT 57,000 60,000 SPIRAL 579,500
HOT DIPDIP GALV.
GALV. PROC.
PROC. ANNEAL
ANNEALSPM
SPM&& CRNO SLIT COILS
II & ERW COATED PIPES WELDED (Controlled
& II
II (Existing)
(Existing) LINES
LINES & SHEETS
Rolled)
350,000
120,415 16,792 164,476
HDG PLAIN SHEETS ELEC. TIN PLATES CR SHEET & ANN COILS
The units under the Expansion Project are briefly detailed below:
The present modernization programme of RSP will increase production of hot metal capacity
from 2.0 Million tonnes per annum to 4.5 Million tonnes per annum. The new material
requirement of RSP will increase to about 12 Million Tonnes per year from present requirement
of 5.0 Million tonnes.
The base mix will be stacked in 2 Nos base mix bed and reclaimed. Equipments coming in
base mix Beds:
Twin Boom Stacker : 1 No.
Barrel Reclaimer : 2 Nos
Transfer Car : 1 No.
The entire work under this package will be executed on turnkey basis. This specification / scope
of work shall cover the following systems,
Transportation of coal from RCC silos of New CHP for CDI injection into B.F. # 5.
Transportation of coke from CDCP, de-dusting of coke in CDU, Coke Sorting, Coke
Screening, further transportation to Intermediate Coke Bunkers and conveying to stock
house of BF#5 and Coke Crushing Station of new OBBP.
Transportation of coke from existing Coke Oven to Stock House of BF#5.
Transportation of finish sinter from Sinter Plant # 3 to Blast Furnace # 5 and existing
Blast Furnaces.
To feed the coke to the new Blast Furnace #5 coming up under 4.5 Mt/yr hot metal production
expansion plan, one 7m tall battery of 67 ovens is being installed in the new coke oven complex
in the location of old Fertilizer Plant.
BASIC DESIGN: The battery will be top charged, compound twin flue, under jet, regenerative
heating with partial re-circulation of waste gases. Ovens will have 3 nos. of charging holes and
the battery will have double gas collection mains, one each on pusher side and coke side. There
will be two waste gas tunnels, one each on pusher side and coke side, with common tunnel
leading to chimney located on pusher side in the middle of the battery.
The Computerized Heating Control System (COHC) supplied by M/s Siemens VAI, Finland will
be installed for the battery operation for the process management system to improve reduction
in environmental emission, improve coke quality & productivity.
Battery heating system is designed for under firing with clean coke oven gas with average
heating value of 4200 kcal/Nm3 and/or mixed gas with average heating value of 1000 kcal/Nm3.
There will be a coal tower of 4000 t useful capacity for storing coal with dry equivalent bulk
density of 740 Kg/m3.
Buttress walls will be connected together at the top by longitudinal tie rods. To ensure proper
loading, adequate numbers longitudinal tie rods will be provided with helical springs.
No. of Ovens 67
Total Height of Battery 7M
Useful Height 6.7 M
Useful Volume 41.6 M3
Production of run – of – oven Coke (Dry) 0.768 MT/Y
Total length (between buck stays) 16,000 mm
Total useful length 15,160 mm
Width at pusher side 385 mm
Width at coke side 435 mm
Average width 410 mm
Useful volume of oven 41.6 m3
Axial distance between ovens 1.400 mm
No. of flues in heating wall 32
Distance between the flues 480 mm
The Pollution Control Stipulations applicable to New Coke Oven Battery as per MOEF as
follows
Leakage from Doors – 5 %
Leakage from Charging Lids – 1 %
Leakage from AP Caps – 4 %
Charging Emissions – 16 seconds / charge (with HPLA)
The scopes of supply for oven machines for COB # 6 under the subject package are as under;
Machines Nos.
Coke Pusher Car (PC) 2
Coal Charging Car (CC) 2
Coke Transfer Car (TC) 2
The Coke Transfer Car will supplied along with a land based Pushing Emission Control (PEC)
System.
The oven machines such as Charging Car (2 nos.), Pusher Car (2 nos.), Coke Transfer Car (2
nos.) along with Pushing Emission Control System (PEC) have been envisaged in this package
for providing and handling Input and out put of Coke Oven Battery with a cycle time of 11
minutes.
New Coke Dry Cooling Plant for 7 mtr. Tall Coke Oven Battery # 6
The Coke Dry Cooling Plant (CDCP), having four chambers and of coke cooling capacity of
0.768 Mt/yr of gross coke (dry) per annum, will be installed to cool the coke produced from Coke
Oven Battery No. 6. The pushed coke from battery shall be transported to CDCP unit by means
of self propelled hot coke bucket car.
The principle of coke dry quenching is based on cooling of hot coke with inert gas circulating in
close loop between the chamber of hot coke and the waste heat Boiler. The heat is recovered
from the red hot coke through the heat exchanger via direct contact between the circulating
inert gas and red hot coke with the transfer of this heat to the Waste Heat Boiler. The
quenched coke is discharged from the quenching chamber automatically by Discharging Device
in pre set condition. Data analysis of Blast Furnace operation show that specific coke
consumption decreases by 3-5 % by using dry quenched coke.
The major facilities for the CDCP are Coke cooling chamber, Waste heat boiler, Coke bucket
lifter, Main mill fan & Auxiliary mill fan, Circulating gas duct, Hoisting & Handling
equipment, Dust catching bunker, Dust cyclones, Boiler circulating pumps, Pneumatic
transport system for coke dust, Ventilation equipment, Blowing device, Coke charging device,
Boiler feed water pumps, De-aeration tank & column and Passenger cum goods lift of 1t
capacity.
New Coal Chemical Deptt for 7 mtr. Tall Coke Oven Battery # 6
The new CCD is being installed to process coke oven gas generated from the new Coke Oven
Battery # 6. The purpose of the CCD is to clean the raw coke oven gas with removal of Tar,
Ammonia, Hydrogen Sulphide and Naphthalene. The coke oven gas shall also be cooled finally
to 300 0C at the outlet of final gas cooler.
The liquid effluent generated within the CCD area shall be taken to the existing B.O.D. Plant
by means of underground network.
New Coke Chemical Deptt will have Sulphur removal system. There will be Naphthalene
Washer and Benzole Scrubber to have clean coke oven gas for use of the Plant.
The entire work has been executed through 11 different packages, identified suitably to
facilitate grouping of similar nature of work in one package.
Gas pre-cooler (Primary Gas Cooler), Decanter, Pit Tank & Associated
Accessories (1.0 MT & 1.8 MT)
The scope broadly covers dismantling, supply of decanter and associated accessories, Strainer
pot, process and utility piping, valves & fittings, electrics including electric motor, cable, push
buttons control panel, civil & structures and interconnecting process & utility piping with
existing Decanter system for separation of Tar & Liquor of CCD plant etc. for 1.0 MT and 1.8
MT side of RSP respectively. Total GPCs – 6 nos., Decanters, Pit Tanks - 2 nos.
Knock – out Pot Condensate Seal Pot, Gas Mixer and Interconnecting Coke Oven Gas
Pipelines & Valves and Receipt & Storage Facility for H2SO4 (In Equipment Column)
Elecrolytic Tar Precipitator – 2 nos. ETPs in first stream & 2 nos. ETPs in second stream
Instrumentation – During the up gradation of CCD, a number of new technological units have
been envisaged, while other technological units have been planned to be refurbished/ upgraded.
Wherever possible, the Control & Instrumentation (C&I) of these units have been included in
the scope of the turnkey contractors for these units. The balance C&I requirements of CCD ,
with a view to achieve safe, reliable, efficient and trouble free operation of the different units
and safety of the operational personnel, the scope has been kept in this package.
New Coal Handling Plant have been planned to have 15 days stock of Coking Coal for COB - 6
(@ 3500 T/day) and CDI Coal of 10 days stock @ 1500 T/day). For stocking of Coking Coal there
will be 24 nos. RCC silos each capacity 2500 Tons and for CDI Coal, there will be 6 nos. of RCC
silos, each capacity 2500 Tons.
The major scope of work and supply of New Coal Handling Plant (CHP) are given below:
Installation of 2 (two) nos. wagon tippler
Transportation of coal unloaded by wagon tipplers to RCC silos for storing of both Coking
coal and CDI coal.
Reclamation of coking coal from RCC silos by belt weigh feeders and further transportation
to crushing station by belt conveyor.
4 nos crushers in crusher building.
Transportation of crushed coking coal from crushing station to coal towers by belt conveyor.
Weigh feeders below coking coal silos shall be provided with automatic proportioning device
and digital system for accuracy. These feeders shall be VVVF (Variable Voltage & Variable
Frequency) controlled AC drives.
Reclamation of CDI coal from RCC silos by vibro feeders and further transportation to
junction house by belt conveyor.
This is a single strand Sinter Plant having an effective suction area of 360 m3 with an annual
production capacity of 3.70 MT of gross sinter. The sinter productivity will be 1.3T/m2 /hr and
the machine will operate at an under grate suction of
1650 mmWC for 330 day/Year on 24 hrs/day basis. There
are two wind mains followed by two ESPs leading to a 120
m high concrete chimney. The output stack emission will
be less than 50 mg/Nm3. The sinter plant has been
provided with Eirich type mixer and noduliser instead of
the conventional mixing & balling drum. A circular cooler
has been provided for sinter cooling. Another new feature
is pneumatic conveying of ESP dust. The ESP dust will be
charged to the sinter raw mix bed after passing through
an Eirich type Granulator. The Eirich type mixer, Noduliser & Granulator are being installed
for the first time in SAIL Plants.
The Furnace comprise of twin flat cast house with four tap holes. The Furnace is equipped with
modern features such as pulverized coal injection system., cast house fume extraction system,
cast house slag granulation system, the top gas recovery turbines of 14 MW capacity, Twin
material bin BLT system, Waste Heat Recovery System, Plate/Stave Coolers, Conveyor Belt
Charging System, decreased coke rate of 360 Kg/thm (min) and Level II Automation system.
The Blast Furnace will be operated at high intensification level and for a campaign life of 20
years. Accordingly the raw material handling system, interplant pipeline system, and other
Page: 221 HRD Centre
Rourkela Steel Plant
service facilities like water, gas facilities, power distribution, electrics,
instrumentation and automation will also be designed keeping in view the production level of
8320 T/day from this Blast Furnace plant.
The details of operating parameters selected for the Blast Furnace are given in the following
Table.
S1.
Parameter Unit Value
No.
1 No. of Blast Furnace No. 1
2 Working volume of BF m3 - 3470
3. Useful volume of BF m 3 4060
4. Hearth diameter m 13.2
7924 (avg.)
5. Production per day t/d
8320 (max)
6. Ash content of coke % 15
7. Ash of Coal (imported) % 9-10
8. Sinter in burden % - 80
9. Sized ore in burden % -20
10. Pellet in Burden (future) % -(10-20)
11. Availability of Blast Furnace day/yr. 350
Sp. cons. of input materials (Net &
kg/thm
dry basis
Iron ore lump As required
Sinter / Pellet As required
Lime stone As required
12.
Quartzite As required
Coke rate (Including -20 Kg Nut
360
Coke 8-34 mm)
150 (avg.)
Coal dust (CDI coal)
200 (Design)
13. Blast characteristics
S1.
Parameter Unit Value
No.
Volume (dry basis) Nm3/min 6125
1200 oC (avg.)
Temperature oC
1250 oC (max)
Humidity g/Nm3 40-60
03 nos of Turbo Blowers (2 working + 1 standby) along with its all auxiliaries shall be utilized
to provide cold blast to the stoves of new BF # 5. The blowers shall be axial with last stage
redial type. Air Blowers with variable speed control, single shaft, and multi stage without
intercoolers and directly coupled to the turbines without gearbox.
In this package, there are 3 nos of boiler arrangement and 2 nos of steam turbo generator and
one no. back pressure turbo generator. Boiler will generate steam at a rate of 300 TPH 485 +5/-
2o C and 62 Ata by evaporating water with the help of Blast Furnace gas, which has calorific
Page: 223 HRD Centre
Rourkela Steel Plant
volume 728 Kcal/Nm3 (GCV). This steam will go to 02 no of steam turbo
generator each having 18 MW power generation capacity and same steam will go to back
pressure turbo generator, which will develop 6.5 MW power. This steam will also be used to run
03 nos of turbo blowers, which shall be feeding cold blast to stoves of BF#5.
For transferring hot metal from the new Blast Furnace to Steel Melting Shop or at PCM by 10
nos. of Torpedo Ladles of 350 T capacity each has been envisaged under the current expansion
plan. These torpedoes are of first kind to be used in SAIL with features like higher capacity and
lesser hot metal temperature loss. A torpedo ladle repair shop is also envisaged wherein the
jobs like refractory lining, ladle inspection, ladle heating & cooling etc. will be done.
There is a twin strand 1500 TPD capacity Pig Casting Machine envisaged under the current
expansion plan. It is an auxiliary unit of new Blast Furnace # 5. it comprises of a Pig Storage
Yard, Pig Wagon Haulage System, Circulating water system, Graphite & Lime Milk
preparation and splashing system, Pig Dispatch Wagons etc. The average strand speed will be
9m/min.
Augmentation of SMS-II
Design Feature:
HRD Centre Page: 224
Panorama 2012
Design range: 210 - 300 x 1200 – 2500 mm x mm
Machine equipped to cast: 220, 250, 300 x 1200 – 2400 mm x mm
Slab length: 6000 – 10000 mm
Type of unbending : Continuous straightening
Casting time: ~ 50 min. (Tenderer to indicate)
Casting speed for different sizes and grades: (1.5 – 2.2) m/min, (tenderer to indicate)
Machine speed: 0.6 – 6.0 m/min
Preparation time: ~ 45 min. max
No. of heats per sequence with one tundish: 12 - 15
Avg. no. of heats/day : 26 - 30
Caster availability: 330 days/yr approx. Tenderer to indicate
Design Production capacity of CCM: 1,534,500 t/yr
One top blown basic oxygen furnace (3rd converter) of capacity 165 m3 has been considered for
this package. After installation of 3rd converter, all the three (3) converters will operate
simultaneously. The 3rd converter shall be designed with provision for adoption of combined
blowing/ inert gas stirring process. The salient operating parameters of new BOF converter is
given below.
The major design features of the BOF converter are indicated below.
Ladle Furnace (# 3)
Operating Parameters:
1. No. of ladle furnace No. :1
2. Annual treatment at LF t/yr : 1,440,000 average
3. Average no. of heats to be treated at LF per day – Average: 30
4. Nominal heat size : 150 T
5. Maximum Heat size : 165 T
6. Transformer capacity : 30 MVA
7. Heating rate deg C/min > 5 deg per minute at operating top notch
RH (OB)
One (1) off-line RH – degasser has been envisaged for vacuum treatment of liquid steel before
casting. Special value added products will be treated to achieve low level of absorbed gases,
inclusion control, trimming addition of ferro-alloys and micro-alloys. The RH – degasser is
located in the ladle furnace bay of CCP II.
Operating Parameters:
1. No. of unit One (1)
2. Heat size: 150 T (nominal) & 165 T (Maximum)
3. Type - A refractory lined vacuum vessel equipped with two refractory lined nozzles (snorkels)
attached to the bottom to the vessel- Lifting and lowering of vessel by hydraulic system
alternatively by winch system)
4. Inert gas purging Inert gas stirring facility from one of the snorkels
5. Vacuum system Steam ejector
6. Vessel heating by top oxygen injection-cum-gas burner heating system to maintain refractory
surface temperature at 1,400 – 1,500°C.
7. Steel recirculation rate >110 t /min
8. Hydrogen level in steel, after treatment < 1.5 ppm
9. Alloy addition system Ferro-alloys and micro-alloys to be added under vacuum
10. Other features - Design provision for usage of water cooled O2 lance elf propelled transfer
car
11. Suction capacity Nominal – 550 kg/h at 0.5 mbar
12. Free board Minimum – 500 mm with 165 t heat size
Addition of Lime sizing unit [Crushing Unit of Capacity 20 T / hr. to reduce lime size from 0-60
mm to 100% below 2 mm] for Sintering Plant -III
The scope of work is to set up the kiln complex which includes kiln with up-stream and down
stream facilities and its related material handling systems, air conditioning and ventilation
system, dedusting system, waste gas cleaning system, all electrics and instrumentation, civil
and structural works etc on turnkey basis. Raw material handling conveyor BC-10 will be
extended towards the tail end about 20 m and conveyor will be upgrade to 400 tph. The kilns
shall be constructed over the extended portion of 2 nos. of existing belt conveyors from existing
kilns to flux storage building.
The various equipments involved in the plant for storage, handling & screening of
limestone/dolomite, vertical double shaft kiln including firing system, lime & dolomite delivery
bin building including screening and storage facilities. The major equipments which are
envisaged for kiln area are indicated below:
Shaft kiln complex consisting of 1 no. of 350 tpd vertical double shaft limekiln, 1 no. 350 tpd
vertical double shaft dolomite kiln including refractories, skip charging system, discharging
system of products, blowers for supplying air, firing system of the kilns, storage bunkers
etc.
Belt conveyors for conveying the materials from one place to desired place, vibratory
feeders, bin vibrators, vibrating screen, weigh hopper, chutes with liners, sector gates,
switching devices, truck loading device, etc.
Waste gas cleaning and dedusting system of the kiln and all transferring points of
materials.
Air conditioning & ventilation facilities at control room, office room etc.
Shop electric, instrumentation & automation and illumination.
Utility piping network & fuel handling facilities.
Hoist and chain pulley block, elevator etc.
Fire fighting facilities.
Lime Sizing Unit for the new Sintering Plant –SP-III: The objective of lime sizing unit is to
reduce the lime size from 0-60 mm to 100 % below 2 mm having a capacity of 20 ton/hour
comprising of Hammer mill with rod shifter with the help of electro-vibratory feeders and
belt conveyors.
The Oxygen Plant is installed inside RSP premises on Build, Own & Operate (BOO) basis. The
plant will produce Oxygen, Nitrogen and Argon both Gas/Liquid. RSP will purchase on a first
132 kV bus. MSDS-IV shall be connected to 220 kV Tarkera Grid S/s of OPTCL through a
double circuit 220 kV line using HSL Fdr-3 towers (Existing HSL-3 132 kV line shall be
converted to 220 kV and terminated at MSDS-IV).
(iv) RM - 1 (NEW)
A 33 kV Double Bus GIS indoor switchboard for RM-1 for stable power supply to existing
HRM loads.
33 kV (4 nos.) and 6.6 kV (10 nos.) switchboards for power supply to all additional loads
including 33/6.6 kV transformers.
Interplant cabling at 33 kV & 6.6 kV and new cable tunnels.
Page: 229 HRD Centre
Rourkela Steel Plant
Provision of Emergency power to modernization area loads.
Plant SCADA & EMS.
Unique Features:
Under the expansion plan of Rourkela Steel Plant for 3.9 MTPA of salable steel, a new 4.3 mtr
wide Plate Mill is being installed. The Plate mill is proposed to be installed in two phases,
initially with capacity of 1.0 MT (0.92 MT saleable), which shall be augmented, to a capacity of
1.8 MT (1.674 MT saleable). The mill will be capable of rolling a wide range of products.
Input
Continuous Cast Slabs width = 1200 to 2400 mm
Length = 2200 to 4100 mm
Thickness = 210 to 300mm
Output
As Rolled Plate Length = 42 mtr maximum
Finished Plate Thickness = 6 to 100 mm
Width = 1500 to 4100 mm
Length = 6000 to 15000 mm
The Plate Mill shall be set-up as a green field project in an area of about Three (3) lakh square
meters with newly built covered bays to accommodate the mill and associated facilities
including storage of slabs and finished plates.
The Plate Mill shall have equipment with state of art technology to produce plates with close
tolerances to meet stringent international standards. The 4 Hi reversing mill shall be designed
for roll force up to 90 MN, with hydraulic automatic gauge control, roll bending and shifting
facilities and provision of on-line thickness, profile and width measurement.
The Plate Mill shall have advanced computerized control system for Plan View Rolling (PVR)
process to maximize yield and an accelerated cooling system to produce high strength TMCP
rolled plates including for pipe grades upto X 100 with lower cost.
High capacity levelers with hydraulic control and under load positioning system, high capacity
Trimming and Cross-cut-shears up 50mm capacity shall be provided to produce distortion free
plates. For operation with a lean manpower and to avoid loss of material identity throughout
the production process, the Plate Mill will be equipped with advanced control systems and
material tracking facilities.
Finishing stand
Accelerated Cooling
Hot Leveler
Inspection bed
Torch cutting for Heavy
Plate (>50 mm thick)
UST Machine
All the parameters affecting plate profile, shape and flatness will be evaluated by means of
finite element models and specific computer programs, taking into account:
PLANT AVAILABILITY
A- Calendar time (365 days/yr) 8760 h/yr
B- Weekly Shut down Days (50 days/yr) 1200 h/yr
C- Capital Repair (10 days/y) 240 h/yr
D- Operating Time (A-B-C) 7320 h/yr
The 4-high rolling mill (future) will be equipped with the following features:
• Work rolls individually direct motor driven
• Top back-up roll and work roll balance
• Work roll heavy bending(positive)
• HAGC cylinders in bottom of mill stand
• QWRC (Quick work roll change)
• Back up roll change rails in bottom window
• Entry and delivery guides, strippers and wipers
• Dedicated roll cooling headers
• On-board high pressure descaling headers and roll star
2 nos. separate installations of Propane storage & handling system have been envisaged. One
installation which shall meet the requirement of CCM-II and SRU, shall be located near
existing Propane installation (2x 20t storage) in the Acetylene Plant II area, while the another
installation which shall meet the requirement of CCM-I, New Plate Mill, Repair Shop & HSM
shall be meet the requirement of CCM-I, New Plate Mill, Repair Shop & HSM shall be located
opposite erstwhile soaking pits (SSD side) of existing area.
The following main units along with auxiliaries for Propane storage and distribution are
required.
2 nos. unloading point for transfer of Propane to storage vessels in each area.
2 nos. 80 t (each) mounded storage vessels at existing Acetylene Plant-II and 2 nos. 60 t
(each) mounded storage vessels at opposite erstwhile soaking pits (SSD side) of existing
area.
2 nos. (1W +1S) liquid unloading pumps (capacity 10t/h max.) for each unloading point in
each area.
2 nos. (1W +1S) vapor compressors (capacity 29.2 m3/h (max.)) for each unloading point in
each area.
3 nos. (2W+1S) SS coil immersed in electrically heated water bath vaporizers in each area;
capacity 500 kg/h at existing Acetylene Plant-II and 250 kg/h at opposite erstwhile soaking
pits (SSD side) of existing area.
Augmentation of facilities
The facilities in SMSII have been augmented to facilitate simultaneous blowing of both the
converters. For this purpose, secondary refining facility, piping network, for oxygen, nitrogen,
water & other utilities have been strengthened. Material handling facilities like ladles, slag
pots, etc have been procured.
CDI unit in BF #4 has a design capacity to achieve injection rate of 150 Kg/THM with 6%
Oxygen enrichment. Requirement of Oxygen & Nitrogen will be met from TOP III.
ERP at RSP:
RSP has joined the league of leading global steel producers by successfully implementing
Enterprise Resource Planning (ERP) software SAP. The GO LIVE was initiated on 1st April
2012 with the deployment of the following modules.
The ERP infrastructure comprises of two state of the art data centres and a 10 GBPS optical
fibre network backbone. The Primary Data Centre(PDC) is located at the ground floor of
MECON building in the Administrative Building Complex where as the Secondary Data
Centre(SDC) is located in the HRD Centre. Both the data centres run on 24*7 basis and provide
uninterrupted IT services to the plant and township. The SDC is designed to maintain
continuity of business in case of a disaster.
.
The ERP Data Centres are equipped with the latest range of servers, storages, backup devices
and switches from the leading manufacturers. The database services are provided by a set of
clustered enterprise class Sun M9000 servers where as the application services are rendered by
a bank of SUN T2 plus servers and Dell X86 servers. A central data repository has been created
with the deployment of enterprise class HITACHI SAN storage at each location. The storages
are connected through a pair of redundant CISCO SAN switches with 4 GBPS dark fibre link.
The automated data backup services of ERP is being handled by NetVault back-up
management software with the help of tape libraries located at both the data centres. The
server farm of each data centre is connected to the RSP LAN through an enterprise core switch.
Each server farm is protected from unwanted intrusion by a unified threat management device.
The entire ERP landscape is being centrally viewed and managed through an enterprise
management software.
Physical access to the Data Centres and server rooms is being controlled by proximity card and
biometric readers. Indoor and outdoor cameras have been deployed at each site for continuous
monitoring of the activities in and around the centre. The centres are also equipped with
latest fire detection and FM200 gas based fire suppression system. The server rooms are
equipped with very early smoke detection apparatus (VESDA) and water leakage detection
system. The centres are powered by two transformers having independent power sources for
zero power outage. All the subsystems like power, UPS, AC, access, fire detection etc are being
monitored through a Building Management system from a desktop.
ERP system integrates various shop floor activities like production planning, quality assurance,
maintenance planning with services covering marketing, materials procurement, financial
accounting & product costing. It has built interfaces with Central Marketing Organization,
Metaljunction, level-II/III process computer systems & Enterprise legacy applications. The
system covers all major production units starting from OBBP & Coke oven to Pipe Plants. In
addition to the core functions, ERP provides for business intelligence by aggregating data from
ERP & Non-ERP systems. Another module called Enterprise Portal has been put in service for
providing MIS to the senior management.
In Rourkela Steel Plant, computerization has been used for various activities:
• Quicker availability of information for decision making
• Cost Reduction & Cost Control
• Production, Planning & Control
• Stricter Procurement, Inventory & Budget Control.
RSP Portal:
• This is a corporate website designed to run on RSP intranet.
• This will provide a unified window to employees to access information spread across the
organization.
• The portal will provide access to departmental web sites, applications and RSP Mail
facility running on RSP intranet.
• It will also provide access to websites and applications running on SAIL intranet.
• This will serve as a gateway to various sources of information spread across the
organization.
• Information pertaining to company profile, management, achievements, milestones,
certifications, policy, procedures, products, facilities, annual business plan, production
highlights and financials is currently available on the site.
• The site also hosts useful details of various functions of the organization like Safety,
Environment Management, HRD, TQM, Information Technology, Corporate
Communication, Vigilance etc.
• A separate news corner has been provided to publish daily news pertaining to our
organization and industry. The homepage has facility to handle messages,
announcements, new launches, slogans, celebrations and competitions.
• The Gallery section consisting of selected photographs arranged across themes provides a
visual treat to the users.
• Users can visit the Learning Centre to update their knowledge on available articles.
• Users can access and download various publications of RSP and other SAIL units by
visiting the Publication and Download links of the site.
• The site has provision for functional departments to publish useful information which will
be accessed by employees across the organization.
• It features a privileged Employee Zone through which employees can view their
personal profile, salary profile and pay particulars.
MATERIALS MANAGEMENT
The main tenets of public procurement process are economy, efficiency, fairness and
transparency. Materials Management Department ensures availability of materials / services of
desired quality at desired time in desired quantity and at the optimum cost (maintaining
transparency) to the various consuming units of Rourkela Steel Plant. It caters to the needs of
the internal customers as well as interacts with the external agencies like suppliers/
contractors etc. Evolution of Materials Management Functions to Supply Chain Management
has made it imperative for the MM department to manage its supply chains efficiently. The
important areas under MM department are as follows:
represents a major portion of the organizations total invested capital, this responsibility is a
significant one. In Rourkela Steel Plant, Stores operations provide both service and control
functions. The main receiving stores at RSP are:
1) Central stores
2) Modernization stores
3) Refractory stores
4) Plant Stores II
5) CSM stores
6) IGH Stores
In brief the various steps in the activity chain of the Receiving Stores in RSP are as follows:
1) Receiving of materials
2) Day-book generation
3) Scrutiny and verification (Counting, checking, inspection) of materials & documents.
4) Generation of GARN (Goods Acceptance/ Rejection Note)
5) Stock charging of materials by posting of GARN’s.
6) Custody & Preservation of Materials
7) Issue of Material.
The Stock Control Section of Stores section is involved with the procurement, availability,
control and issue of Automatic Procurement Items. In brief it carries out the following
functions:
1. This is MM's material planning agency for processing indents for multi-user Automatic
Procurement (AP) items (consumables as well as spares) based on previous consumption
norms and procurement policy and specific projected requirements of user departments.
2. Stock Control monitors the safety stock of critical multi user items and issues materials
to user departments.
3. Activities include allotment of catalogue numbers for consumables.
4. Stock Control is the nodal agency for Indent Scrutiny Committee for AP Items.
The type of activities carried out by this department can be broadly classified as follows:
1. Co-ordination with user departments to identify Purchase needs
2. Discussions/ negotiations with representatives of various suppliers/ contractors.
3. Identification and selection of suppliers.
4. Market studies for important/ critical inputs.
5. Commercial Analysis of offers
6. Placement of order.
7. Post order activities like follow-up with parties, providing clarifications (if required) etc.
8. Post receipt activities like complaint settlement etc.
Inspection:
1. The broad function of the Department is to ensure that the material being supplied
meets the desired specification as per the quality requirement of the user.
2. Inspection is carried out at Stores Receipt and in the premises of vendors.
3. Inspection department develops the Quality Assurance Plan for items in consultation
with user departments.
4. Inspection also undertakes Capacity Assessment of vendors in the Vendor Registration
Process.
5. The inspection activities are carried out by the RSP Inspection Wing located at
Rourkela as well as by RSP Unit Offices located in Delhi, Kolkata, Mumbai and
Chennai.
Marketing:
Prime products of RSP are sold through Central Marketing Organization (CMO), all other
products are sold by Marketing Department. The product range dealt by Marketing
Department includes defectives, coil/sheet cuttings, rejected pipes, granulated slag, coke
fractions, fertilizers such as Ammonium Sulphate, various waste products like LD Slag,
Ferrous Sulphate etc. Marketing Department also looks after disposal of old/used machinery,
conveyor belts, drums, electrical spares and unused / surplus obsolete spares. In addition to the
above, all idle assets of plant are also disposed off by Marketing Department.
For disposal of products, there are 2 yards, namely Secondary Steel Stock Yard (SSSY), which
stores defectives, coils/sheet cuttings. The other stockyard is Central Disposal Yard (CDY),
which handles maintenance scraps/ wastes like old/used conveyor belts, old/used electrical
spares, used drums, old batteries, old vehicles etc.
For disposal of above items Marketing Department has introduced latest system of e-sale
through "Online Forward Auction". In this process customer bids its highest price through
Internet.
The present annual revenue generated through sale of secondary items is to the tune of Rs. 320
- 350 Crores.
Financial Accounting:
Finance department is responsible for recording of monetary transactions in the books of
accounts and preparation of final accounts as per the provisions of Companies Act & Clause 49
of Listing agreement, complying with provisions of Income Tax Act and Wealth Tax Act. The
final accounts are prepared as per the requirement of schedule VI of the Companies Act, 1956.
Quarterly accounts are subject to review by the auditors appointed by the Corporate Office,
SAIL. The annual accounts are examined by auditors appointed by Comptroller and Auditor
General (C&AG) of India under the provisions of Companies Act. The auditors so appointed are
required to report on true and fair view of the accounts amongst others. The annual accounts
are thereafter reviewed by the Resident Audit Officer of Commercial Audit branch of C&AG.
Memos raised by Commercial Audit are replied to with necessary clarifications and on
satisfaction of the Commercial audit, the memos are dropped otherwise the comments of C&AG
are reported in the Annual Accounts and placed before the Annual General Meeting of the
company.
Cost Accounting:
Cost Accounting involves costing of products and services, preparation of standard cost,
variance analysis, pricing of products and services and preparation of various MIS reports like
monthly profit forecast, techno economic report, cost control report, scrutiny of make/buy
proposal etc. Cost sheets are prepared on historical cost basis by following the principles of
Process Costing. Standard cost sheet is prepared for control purposes. Monthly cost sheets are
prepared and made available to different departments on line. Cost awareness workshops are
conducted department-wise. Finance department is also responsible for cost audit under
Companies Act. The cost data are examined by a qualified accountant appointed by Board of
Directors with the approval of Central Government. The cost audit report is submitted to
Company Law Board, Cost audit branch by the cost auditor.
Stock Verification:
It involves physical verification of inventory and assets. Entire inventory of raw materials and
Semi/Finished goods is physically verified at the end of each quarter. The inventory of Stores
and spares is physically verified over a period of three years. However the inventory of high
value items is verified every year. The fixed assets are physically verified over a period of three
RMB&A
It deals with Payment and accounting of bills of suppliers of limestone, dolomite, quartzite,
sand, clay, coke etc and of contractors for handling, screening public analyst, internal
shifting of materials etc., Accounting of receipts of materials from RMD mines and sister
plants, imported coal from BTSO, indigenous coal from CCSO, Accounting of materials
transferred/ diverted to sister plants.
Preparation of invoices:
Invoices are prepared for dispatch of materials from the plant in compliance with provisions of
related laws like Orissa VAT Act, Central Excise Act, Service Tax Act, Entry Tax Act and
Income Tax Act.
PERSONNEL
While managing human resource is an integral job of the Manager at all levels, in a business
organization, a nodal agency is required to oversee and monitor the myriad human processes
and also to carry out specific functions required to optimize the available human resources. The
Personnel Department of Rourkela Steel Plant is primarily responsible for this. The functions
of Personnel Department can be broadly categorized as follows:
Rationalization of Manpower:
To meet the present and future manpower needs, Personnel department makes strategic
personnel planning and ensures induction of competent personnel in the organization.
Personnel department analyses the requirement of manpower and existing profile on a
continuous basis leading to a systematic deployment plan, which comprises of both
redeployment from within and recruitment for ensuring right man on the right job. An annual
manpower budget is prepared taking care of various oragnaisational requirements and
objectives. Besides, thrust is also put for optimum utilization of the human resource by way of
redeployment, retraining etc.
Motivating Employees:
In order to encourage the employees to maintain consistently high levels of performance,
Personnel department facilitates the introduction & implementation of various financial & non-
financial motivational schemes & awards. The schemes are both group and individual-based.
Various schemes are in place linked to achievement of departmental targets based on
production, productivity, cost control, quality-consciousness etc. There are also some schemes
that reward individual/ group creativity and accomplishments. Apart from this good
performance is recognised through in-house newsletters, magazines, RSTV, Departmental
Notice Boards, appreciation letters etc.
Communication:
Communication is the lifeline of any organization. It can help establish a performance oriented
culture in the organization. Communication helps not only in disseminating information to the
employees, it also helps in enhancing employees morale, inculcating a sense of participation
and belongingness, fostering team-spirit and a motivation to perform better. To facilitate
involvement of employees in all spheres of their activity Personnel department facilitates
various structured communication programmes viz:
Issue Based Workshops: It is held whenever required and all agencies concerned with
the issue are encouraged to evolve improvement plans.
Besides these Unit Personnel Executives also communicate various plant related issues to the
employees at shop floor.
Away from the traditional fire-fighting management, the Personnel collective believes in pro-
active IR management through involving the employees in all spheres of work activities,
cultivating a participative culture and creating a atmosphere of creativity. Various committees
and bodies are in place at both the departmental and central level so as to involve the
employees in various issues of significance for the Plant as well as the welfare of the employees.
In line with its growing scope of the activities, the infrastructure of the HRD Centre has grown
over the years. The earlier building and workshop complex was installed in 1959. In 1984 the
ground floor of the present MDP wing was installed and in 1993 the first floor of the MDP wing
was built. The Refractory Shop came up in 1993. Keeping in view the need to increase the
competency level of employees to cope with the advent of latest technologies, the Hydraulics &
Pneumatics Laboratory was commissioned in 1993 with the equipment supplied by M/s
Amatrol INC, USA and the Electronics Laboratory was commissioned during 1994 with
equipments from M/s Feedback UK. The Computer Centre was installed in 1989.
Over the past years the HRD Centre has redefined its horizon and has become a center stage
for the transformational process of Rourkela Steel Plant and, has played a vital role in the
turnaround initiatives of Rourkela Steel Plant. Apart from carrying out activities towards the
competence development of employees, the HRD Centre has also become the venue for several
professional development activities by playing host to several national and international
workshops, seminars and conferences.
Prepare
Annual Training Plan
Does
Programme No
Exist?
Create &
maintain Yes Design New
Learning Programme
Environment
Conduct
Programme
Maintain &
Provide Training Review
Aids Evaluation
parameters
Areas of Training:
To streamline the reporting and monitoring system of
training MIS in SAIL the following broad areas of
training have been identified as per which the Annual
Training Plan (ATP) is prepared every year:
• Induction Training: Training of all new entrants
• Competence Enhancement: All technical and
managerial training
• Training in Specific Areas: All programmes on
Safety, Health, Environment, IMS, OHSAS, SA,
etc.
• Foreign & External Training: All outstation programmes conducted by agencies other
than SAIL and its units and all training abroad
• Other Areas: Various workshops / seminars, Hindi Training etc.
The Institute was accorded the highest recognition of being a Category – I Institute by Central
Electricity Authority (CEA) in 1996 empowering it to train operation and maintenance
personnel of Thermal Power Plants having unit size up to 500 MW.
Recipient of the Golden Peacock Award in 1999, CPTI was brought within the fold of HRD
Centre, Rourkela Steel Plant in July 2004. During February 2007, CPTI was also certified
under the ISO 9001 Quality Management System.
As an ISO 9001 QMS certified and Category –I Institute, recognised by Central Electricity
Authority, Govt of India; which also has the proud distinction of being a winner of the Golden
Peacock National Quality Award, the Central Power Training Institute has been conducting
power related training programmes, workshops, seminars etc and facilitating the conduct of
Special Events for SAIL and Non SAIL personnel to integrate the process of human resource
development with the overall corporate vision of the organisation.
The activities at CPTI are primarily directed towards providing training to personnel engaged
in the field of Operation and Maintenance of Thermal Power Plants, Power Instrumentation,
Power Management, Transmission and Distribution. It also identifies and assesses special
training needs so as to fulfill obligations under IE Rules regarding mandatory qualification of
power plant operators thereby enhancing the competence of personnel in power related areas in
and around Orissa.
Focus of CPTI:
• To contribute towards fulfilment of technical training needs of the personnel in the area of
captive power generation to meet organizational goals.
• To train employees of SAIL as well as non-SAIL organisations in the area of power.
• To provide a conducive environment for learning through excellent facilities, hospitality and
other support services.
• To facilitate and organize company wide workshops and seminars in the area of power.
operations, Instructor station and data acquisition system (DAS). The total plant is
functionally divided into process simulation, interlock simulation and control simulation for
boiler, turbine, generator and electrical system. As on date, it is in the process of being
upgraded functionally.
• Information Centre :
The information centre has a large collection of books, handbooks, journals and courseware
from Indian / foreign publishers on all areas of power engineering and management.
Documentation and drawings related to all SAIL power plants, video cassettes on power
plant operation and control are also available. It has a collection of more than 850 books
and 49 manuals on power plant engineering and allied subjects. It also subscribes to 5
journals / magazines, 5 newspapers and 10 house magazines.
• Syndicate Rooms :
Syndicate discussion is a regular feature in problem solving workshops and other action
plan oriented programmes, particularly for executives. CPTI has three well designed
syndicate rooms for smooth conduct of workshops.
• Personal Computers:
It has a network of 8 PCs. Every staff has access to the PCs. Correspondences, trainee
manuals, reading material, teaching notes and trainers’ manuals are prepared using these
computers. The Institute has adequate number of laser / other printers for this purpose.
Formats are standardized and computerized to ensure adherence to ISO norms.
• Model Room:
Large number models of power plant equipment, exhibits and schematic drawings are on
display in the Institute. Exclusive model room for housing working models and mimic
display boards also exist.
LAW
In an integrated steel plant like RSP, the role of Law department is manifold. It acts as an
adviser to the Top Management and gives a shape to the policies relating to Production,
Marketing, Administration, Health, Welfare, Safety, Land, Estate, Finance, Taxation etc.
Law department undertakes the responsibilities of defending/ protecting the policies of the
Company/ actions of the Management, when challenged in any Court of Law or before any
Statutory Authority. Matters relating to Personnel, Contracts, Sales Tax, Central Excise,
Customs and other Taxation Laws are handled in Law department. Vetting/Drafting of
contracts, schemes, statutory petition/applications are routine function of the Law department.
Law Department is instrumental in saving substantial amount for the company arising out of
litigation and it has successfully defended the policy of the Company.
Without depending on outside agencies, Law department gives Legal opinions and guidelines to
line managers on various issues and acts as an in-house attorney. Thus the Law department
touches upon the working of every department and is associated with all function of Rourkela
Steel Plant.
TOWN ENGINEERING
Town Engineering Department looks after the maintenance of 19 sectors in the Industrial
Township of Rourkela Steel Plant spread over an area of 45.13 Sq. KM. The department is
responsible for repair and maintenance works in 25,499 buildings including residential
quarters, public buildings like Socio/cultural centers, Educational Institutes, Sports Complex,
Medical & Health facilities, Market Complex, Company Officers, Parks and vital installations
including Air Strip.
The total maintenance is achieved through the Civil, Electrical, Water Supply, Horticulture
and Public Health Sections of the Department. The various repair and maintenance works are
executed through the 15 Civil Maintenance Booths and 09 Electrical Maintenance Booths
located in the various Sectors of the Steel Township.
The Contract Cell of the Town Engineering Department deals with the tendering process and
finalizes outsourced agencies for the several jobs executed in the townships by Town
Engineering, Town Services, Sports and Horticulture Departments and Peripheral areas by
CSR Department.
For encouraging sports, the number of sports complexes like Ispat Stadium, Biju Patnaik
Hockey Stadium, Basket Ball Court, Indoor Stadium and various other Sector playgrounds are
kept in good condition.
The Civil Wing of the Department maintains 382 KMs of roads and drains, 465 KMs of
sewerage system spread over the entire townships. As part of the drive for a clean and hygienic
Rourkela, Door-to-Door garbage collection and its systematic disposal from all the residential
quarters and market complex, project has been started, which is the first of its kind among all
the SAIL Units.
The department also provides logistic support during various socio-cultural functions held in
the Township as part of the cultural calendar for enhancing the quality of life of the residents
and creating an atmosphere of entertainment and enjoyment.
Vital installations are also maintained timely to meet the statutory provisions of the Factory
Act and State Pollution Control Board, 32 vital installations, which include 33 kV/11 kV Sub-
Stations, Booster Pump Houses, Intake Wells, Water Treatment Plants and Air Strips, are kept
clean and in good condition with proper approach. The department in close liaison with the
Corporate Social Responsibility Department also provides various basic facilities like class
rooms for Schools, Community Centres, roads, etc. in the peripheral villages. Providing
drinking water facilities through new tube wells and repair of old defunct tube wells, repair of
roads and drainage system in the 57 identified slums are some of the activities undertaken by
the department as a part of fulfilling RSP’s Corporate Social Responsibility. The department as
a part of its constant endeavour for larger cause towards the Community is also engaged in
different projects for Rain Water Harvesting in the Industrial Township.
Public Health:
The Public Health Section of Town Engineering Department provides conservancy services and
anti malaria services in the Steel Township. Apart from regular road cleaning, sanitization of
the dumping yards in the Township and adjoining areas are undertaken. Collecting water
samples for bacteriological tests and analysis, de-chlorination of the wells and spray of anti-
large on swampy areas and on stagnant water are also some of the major activities of the
department.
• 33 kV Distribution Network:
Two Receiving Sub-Stations at Sector-6 & Sector-2 consisting of 33 kV/11 kV power
transformer & auxiliaries are to be maintained round the clock. The capacity of Sector-6
Receiving Sub-Station is 29 MVA and that of Sector-2 Receiving Sub-Station is 12 MVA.
Power is fed at 33 kV level from Plant through overhead lines to these Receiving Sub-
Stations.
• 11 KV Distribution Network:
There are 18 numbers of 11 kV feeders to cater power to the entire Steel Township. Of
these 14 numbers feeders originates from Sector-6 Receiving Sub-Station and 4 numbers
from Sector-2 Receiving Sub-Station.
• Street Lighting:
An elaborate network of Street lighting is maintained for safety & security of the entire
Steel Township. Town Engineering (Electrical) has to maintain nearly 8000 Street lighting
fixtures consisting of HPSV, Semi High-Mast, High Mast, Metal Halide and MV fittings etc.
which also covers 14 numbers recently erected monuments.
One 11 KV overhead line comes from the Plant supplies emergency power to the vital areas of
Township like Ispat General Hospital( IGH), Rourkela House, Booster Pump Houses and VIP
Bungalows.
In addition to the above, all the commercial buildings, Central & State Government Offices,
Police Stations, and Socio-cultural Organizations located inside the Township are also provided
power supply by the Department. In this process Town Engineering (Electrical) handles a
maximum demand of 35 MW with an average of nearly 21 MW of power.
Water Supply (Town) meets the potable water requirement of Steel Township, Rourkela. It
supply potable water as per IS : 10500 – 1993 Quality norms to approx. 24000 residential
quarters apart from hospitals, schools, market places, State & Central government
organisations and public utilities. It also provides drinking water to some of the designated
slums/ Bastis inside the Steel Township. Apart from this, raw water also been supplied to
parks, nursery and gardens. It maintain water tankers (2 Nos.) to supply potable water to
ceremonies and functions organised inside Steel Township including functions organised by
employees on daily basis. Basic objectives of the Water Supply (Town) is,
"To supply potable water 1500 litres/day/Quarter (as per norm) conveniently, economically &
uninterruptedly, in a sustainable manner, twice a day."
Production Process:
Raw water comes from intake well pump house of Koel river and passes through the bubbling
tank in the Water Purification Plant. Here the speed of water is reduced and heavy particles
present in the raw water settle down to the bottom of the tank, which is finally disposed off.
Chemicals are added (coagulant) for vigorous mixing.
The water then passes through the flocculator tank where floc formation takes place, then to
the clarifier where sedimentation takes place and almost all the impurities settle down and
come to sludge chamber, from where it is disposed off. From the clarifier the water goes to filter
house, rapid sand filter, to further filtrate the water and brings down the turbidity to a value of
less than 10 NTU. Bleaching power is added to filtered water to maintain free residual chlorine
concentration in drinking water to 0.1 – 0.2 mg/litre. Free chlorine in bleaching powder acts as
a disinfectant.
The filtered water is collected in 4 drinking water reservoirs and supplied to the beneficiaries
through gravity feeders.
As the Township is situated in a hilly area, there are 12 no. of Booster Pump Houses located
strategically at different locations of different sectors to supply water by collecting in sumps
and then pumping the potable water to over head reservoirs where from, water been
distributed to different quarters situated at higher elevations.
Apart from drinking water, Water Supply (Town) also treat the domestic sewage generated
from the Steel Township quarters and collected at sewage pumping and treatment plant
located at Sector-14 (at the far end of the Township). The sewage water treated through 3 No's.
of stabilisation ponds (oxidation process) and the total sewage treatment capacity is 4.5 Million
Gallon per day. The treated sewage meets the statutory norms before being discharged to river
Koel through open channel storm water drain.
• Horticulture:
The commitment of Rourkela Steel Plant towards making its environment clean, green and safe
is achieved to a large extent by the Horticulture Department. At present, 2300 acres of
intensive green areas with 200 acres of gardens, 4 central Nurseries and 38 Parks and gardens
are being maintained by the department to enhance quality of life in the Townships. Over 150
varieties of roses of these gardens have won laurels at the national level.
So far over 40 lakhs trees have been planted in and around Rourkela. Over 2300 acres of land
has been covered with plantation blocks. Few such blocks are Green Park of 225 acres land
with 2,25,000 trees, Green Valley of 68 acres of land with 66,000 trees, Green Meadows of 85
acres of land with 84,000 trees, Lagoon Park of 50 acres of land with 27,000 trees.
Indira Gandhi Park developed in early fifties is the most prestigious park in Rourkela. Set in
the backdrop of a scenic hill range, the park contains a rich collection of flora, which is a major
source of attraction for nature lovers. A Toy Train encircling a small lake, Boating facility, Doll
Museum, Aquarium, Zoo and Musical fountain are some of the added attractions in the park.
The Jubilee Park developed in the eighties in Sector-8 along with Deer Park is also maintained
by the department and is a major attraction of the steel city.
More than 150 animals and birds of 19 species are being nourished in the zoo, maintained by
the department. Deer Park with 91 spotted deer running hither and thither in an area of 5
acres is another spot of attraction near Jubilee Park.
The Horticulture Department also plays a vital role in maintaining the greenery in the plant
adding beauty to the buildings and its surroundings. The department also supplies materials
and necessary horticultural skills to all the departments to enable them to develop gardens
inside the works.
Apart from this Horticulture Department is creating awareness among Rourkelaites regarding
environment and its protection. he department is regularly organizing Annual Horticulture
show, Rose and Chrysanthemum show and garden lay out competition with huge participation.
The department is also organizing essay, quiz and elocution competition among school children
on the various topics related to our environment. Regular Zoo Education programs are being
conducted at Indira Gandhi Park Zoo to create awareness among participants from various
schools for the conservation of wildlife and its importance.
TOWN SERVICES
Situated on the bank of river Koel & Brahamani, Rourkela is acclaimed as Industrial Capital of
Orissa. Adding to the glory of Rourkela, RSP Township enjoys the status of “FIRST
INDUSTRIAL TOWNSHIP” in the country w.e.f 15th April 1995 as declared by Hon’ble
Governer of Orissa. The Steel Township of RSP is not only famous for its green environment
but also for its planning and architecture. The Steel Township is well planned with all civic
amenities like motorable roads, drainage, sewerage system, parks, schools, gardens, play
grounds, clubs, recreation centres & other modern amenities etc.
Rourkela Steel Plant has been maintaining the entire township covering 24395 quarters of
different categories & about 3716 shops spreading over in 19 sectors. It maintains several
market complexes out of which, one Ispat central market situated in the heart of the city
consisting of more than 1800 shops which caters to the needs of the residents of Rourkela as
well as the outskirt villages in and around Rourkela. The township has about 350 kms pucca
road. All the main roads of the sectors are connected to the ring road spreading over 16 kms
within the Steel Township.
In its township there is a well-laid electrical distribution system which provides electricity to
residential houses, shopping complexes, public buildings, roads and different colonies. The
entire electrical system consists of two 33 kV receiving station, 125 electrical sub station and
1812 KM of transmission lines.
Rourkela Steel Plant has been maintaining a sewerage system in the township and
undertaking public health activities for disposal of wastes and garbage by door to door
collection of garbage.
RSP runs and maintains 04 vernacular (Oriya Medium) schools, 02 English Medium School and
one +2 school spreading over in different parts in the Township. RSP has also provided various
infrastructures like buildings, electricity, Land etc. to a number of schools both in English and
Vernacular Medium. It has also provided infrastructures to some of the colleges in the
Township.
SPORTS
Rourkela Steel Plant is a pioneer in the field of sports and games. Since inception the plant has
taken several initiatives to develop sports and also to provide recreational facilities to its
employees and their wards including the periphery inhabitants through Sports and games.
Rourkela Steel Plant has provided massive infrastructure facilities in the township for the
development of sports. Three main stadiums are – (i) The Ispat Stadium at Sector-6 which is a
multi purpose Stadium, (ii) Biju Patnaik Hockey Stadium at Sector 6 which is an exclusive
Hockey Stadium of international standard with Synthetic turf facility and (iii) Ispat Indoor
Stadium in Sector-20 with all facilities for Badminton and Table Tennis. In addition to this
there is an Ispat Basketball Complex, Chess and Weight Lifting Halls, Volleyball Courts, a
Boxing Hall where all the modern facilities for the training of the sports persons have been
provided for improving their standard to national and international level.
Summer Coaching Camps are organized in 12 disciplines for imparting scientific training to the
budding talents. This being started by RSP in the year 1986, is continuing till date with
increase in number of participants every year. This year 1300 boys and girls participated in the
Camp which was organized for a period of 30 days instead of 21 days earlier.
The sports persons developed under the watchful eyes of Trained Coaches and Senior players of
Rourkela Steel Plant have brought many laurels for the organization and the State as a whole.
The Rourkela Steel Plant teams became Champion in Inter Steel Plant Cricket tournament,
Inter Steel Pant Kabaddi tournament, Inter Steel Plant Hockey tournament and became
runners up in Inter Steel Plant Football, Inter Steel Plant Basketball and Inter Steel Plant
Table Tennis during the year 2008-09.
The efforts of Rourkela Steel Plant for honing the hidden potential of the budding talents have
gone a step further in the form of operating the SAIL Hockey Academy which has 32 Cadets.
The Cadets are not only given scientific training and the opportunity to practice on the
Synthetic turf but also given monthly stipend, furnished accommodation & free food, medical
treatment, education, kits and ceremonial dresses on a regular basis for a period of 5 years.
The Cadets of the Hockey Academy showed wonderful performance and have won the National
Under-18 Championship twice in the year 2006-07 & 2007-08. This was only possible due
to the dedicated effort of the Coaches and the modern facility of Synthetic turf provided by
SAIL management.
Today, Rourkela and its periphery with the encouragement of Rourkela Steel Plant is fast
emerging as a centre of excellence in the field of Sports and Games.
Rourkela Steel Plant has adopted 16 peripheral villages as Model steel Villages for holistic
development:
List of Villages:
1 Bankibahal Re-Settlement(RS) Colony 9 Dumerjore
2 Jagdishpur 10 Jabapanposh
3 Jamsera 11 Jabaghat
4 Bijadih 12 Kapatmunda
5 Laing RS colony 13 Dalposh
6 Baniguni 14 UsraRS colony
7 Pograbahal 15 Lodsera
8 Chikatmati 16 Jaidega RS colony
Rourkela Steel Plant has been doing many developmental activities at the peripheral villages
under Corporate Social Responsibility. Most of these peripheral villages have a large tribal
population, who are the ultimate beneficiaries.
Wadi:
Imparting skills by which the unemployed could use their only capital: land. So WADI (agro-
horti-forestry) concept was tried to improve yield and income. Now the programme is being
implemented in 16 villages under 3 blocks.
Poultry
Improved poultry breed (VANRAJ) was launched in the 16 villages of Bisra and Kuanrmunda
& Lathikata Blocks. Beneficiaries were sent to the Regional Poultry Farm, Sundargarh for
availing training and after that all the participants were provided with 15 days old chicks.
Goatery
A small ruminant intervention covering 15 project villages of Bisra & Kuarmunda cluster was
done by providing them (5 goats and 1 buck each per family) of Black Bengal breed.
AI Centre:
Breed improvement program of cows conducted regularly through Artificial Insemination (AI)
Irrigation
Check dam- At Kapatmunda MSV constructed to irrigate 88 acres of land benefiting 200
families
3) Education:
For motivating village students to improve their zeal for education RSP has taken up various
CSR projects as under:
•
•
• Infrastructure like Hostel Building, class rooms, halls, computer cum library buildings,
play ground have been provided for village students. Most of the peripheral village
schools have also been provided with teaching aids, laboratory apparatus, dictionaries,
• A free school (class I to V) for the underprivileged section of the society residing in and
around Rourkela Industrial Town operates in Sector-4 w.e.f. 1st July 2007 under the
name of Deepika Ispat Sikhya Sadan. In addition to imparting free education they have
also been provided with study kits, shoes, uniform. Mid-day meal has been introduced
w.e.f.1st August 2009.
• L2R( Learn to Read) a 3 years programme for improvement of learning of class I to III
in the Government Schools has been taken up in association with Govt of Orissa.
• Under Public Private Partnership (PPP) up gradation of ITI, Rourkela has been taken
up.
• Financial assistance provided to Rourkela School for Deaf for procurement of Mass
hearing Aid, computer & other items.
• Merit award scholarship to 45 peripheral village Middle school passed boy & girl
students. (Rs 3000/-, 2000/- & 1000 respectively to 1st, 2nd, 3rd rank holder of each
school).
3) Health Care:
EYE TREATMENT:
Project Baljyoti: Treatment of visual impaired children of different blocks of Sundargarh
District. Feedback was taken and this approach of RSP to reach the rural populace has been
appreciated by all. 100% satisfaction level was also noted as regards the quality of medical care.
HEALTH CAMPS:
Mega medical camps conducted in Bolangir and Kalahandi district of Orissa during in which
12752 patients were treated free of cost in 8 camps . Another mega camp was conducted at
Pisawan, Sitapur (UP) where 12073 patients were given free treatment.
5) TRAINING:
Improving Income generation potential through skill development & empowerment of rural
people through training programme conducted. Different modules of training programmes
undertaken at the Institute for Peripheral Development of Rourkela Steel Plant are given
below:
In view of the above RSP strives for excellence, through continual improvement in the quality
of life of the peripheral populace and deserves accolade for going beyond its primary function of
steel making to reach the rural populace.
6. INFRASTRUCTURAL Development:
As a part of CSR activity a number of activities to develop infrastructure for use of peripheral
population have been provided:
Roads, Culverts & Drains
Village Community Centres
Market Complex-2nos at Jalda & Jhirpani Resettlement colonies
7. Participative Approach:
Participation in activities jointly with local administration and government are:
• Electrification work completed in collaboration with WESCO, Govt. of Orissa
1. Bankibahal ( Model Steel Village)
2. Jagdishpur (Model Steel Village)
and continuing at Lachhada Resettlement Colony and Jaidega.
• New tube wells provided for drinking water in collaboration with Rural Water Supply &
Sanitation, Govt. of Orissa
• Pipeline water supply to 16 model steel villages are completed/ongoing
• In collaboration with the local administration and Govt. agencies undertake many
awareness and health check-up programmes. Some of the joint programmes conducted by
IGH during the year for the people belonging to different strata of the society like below the
poverty line persons, labourers, tribal people and orphans including educational institutions
is as given hereunder:
PUBLIC RELATIONS
Defining PR:
Public Relations is the deliberate, planned and sustained effort to create mutual understanding
between an organisation and its stakeholders.
Target Audience
INTERNAL (Employees)
EXTERNAL (Govt., financial institutions/banks, customers, community neighbours,
Policy makers, govt. agencies, suppliers, general public, other stakeholders)
Objectives
Reinforcing the image of Rourkela Steel Plant as a profitable, progressive and vibrant
plant that cares for all its stakeholders
Acting as a catalyst in employees adopting the philosophy of ‘Spreading SAMRIDHI’
Establishing RSP as a Socially Responsible Corporate Citizen
To create a sense of pride among the stakeholders
Corporate image building
Challenges
To propagate the vision and values of the organisation and help achieve business goals
in changing scenario
Facilitating the change in the mindset for adjusting to new situations
Establishing effective communication channels both internal and external to promote
company’s policies and image amongst the employees of the organisation and different
groups
Creating a climate of confidence and trust amongst the employees and stakeholders
To keep pace with the growing media requirement
Obtaining and evaluating opinions to provide feedback to the management and enlist
employees’ involvement. Analysing information on a continuous basis and using this
information to launch first strike programme.
Reaching out to employees/people as individuals and being environmentally sensitive.
Communication
Daily news for RSTV
Press Releases :
a) regular
b) paper specific
c) special features
Media Liasioning
Ispat Sahayog in three languages.
Brochures, posters, hoardings etc
Inputs for SAIL news, website & corporate publications
Messages of MD, Speeches, Appeals Etc
Scripts and story boards of documentaries & films
Creating and Facilitating Advertisement Campaigns
Content of Communication
Priorities of the Plant
Future Challenges
Production and productivity
Achievements of employees/ family members
Safety
Quality
Cost Control
Environment Management
Documentation Centre
Daily Press Clippings to MD and all EDs
Computerised data bank on clippings & different topics
Media Analysis
Record Keeping
Library
Ispat Press
All Technical stationeries for Internal Use
Office Stationery, Medical Books, coupons, Park tickets
APP Booklets
Messages, speeches, appeals etc
Risograph of different communication materials
Miscellaneous Jobs
Goodwill Advertisements
Releasing of Statutory Advertisements (Tenders, Inquiry Notices, Appointment Ads etc)
Distribution of SAIL News/ Wallsheets/Posters/Diaries
Liaison Cell:
The prime responsibility of the Liaison Cell is to assimilate, analyse and synthesize internal
and external intelligence on the plant affairs. It monitors important internal and external
developments of relevance to Rourkela Steel Plant and sensitizes the Higher Management on
the ensuing as well as forthcoming developments/issues in the fields of political, social and
trade unionism etc. Besides it coordinates with the appropriate authorities and agencies as per
requirement from time to time.
Protocol Unit:
The Protocol unit coordinates and handles visit of VIPs, dignitaries and other important
persons to Rourkela Steel Plant as well as visit of students from various educational
institutions. It also coordinates visit of customers as well as suppliers to the Administration
Building. It ensures observance of protocol requirements during visit, functions and events, in
association with the Government Authorities.
Hospitality Services:
The prime activity of this section is to extend due hospitality services to the Company's guests
and dignitaries. It is responsible for the effective management of the Guest Houses of Rourkela
Steel Plant at Rourkela, i.e. at present the
• Rourkela House containing 21 No. of air-conditioned suits,
• Guest House at Sector-20 containing 3 No. of air-conditioned rooms and
• Ispat Niwas containing 27 No. of air-conditioned as well as Non-air conditioned rooms.
Further, the maintenance and management of the Rourkela Air Strip is the responsibility of
the Hospitality Services unit.
VIGILANCE
‘Vigilance’ is a management function required to bring and sustain propriety and integrity at
all levels in an organization. This is very relevant and important in Government Departments
and Undertakings for safeguarding against the misuse of public money so that survival of the
undertakings will be possible in today’s economic scenario.
The functions of Vigilance Department in RSP can be categorized into two types:
Preventive Vigilance
Punitive Vigilance
Preventive Vigilance:
Prime focus of Vigilance is prevention of corruption rather than investigation of corruption.
Preventive vigilance activities consists of –
Surprise checks in different areas particularly in sensitive areas i.e. places prone to
corruption such as shipping, finance, purchase, sections dealing with execution of
contracts etc.
Identifying weaknesses in existing procedures/rules & regulations and suggesting
improvements to plug loopholes and bring greater transparency in exercise of power.
Initiating formulation of new procedures/guidelines
Scrutiny of AIPR (Annual Immovable Property Return) files of employees
Scrutiny of contract/purchase files to check any violation of Purchase & Contract
Procedure 2009 (PCP 09)
Rotation of employees in sensitive postings. As per Central Vigilance Commission
(CVC) guidelines, employees manning a sensitive post should be rotated after
completing 3 years.
Developing vigilance awareness through regular training programs.
Punitive Vigilance:
This deals with providing adequate punishment to the wrong doer promptly so that it serves as
a deterrent for others. An employee is given major punishment only after the charges are
established against him through a regular departmental inquiry (RDA). Conviction under
Ethics, transparency and fair play form the core of our democratic values and as such are of
paramount importance to an organization like RSP. It is possible to make profit through good
governance, which requires each and every officer and worker of our company to maintain
absolute integrity and follow ethical practices in their day to day functioning. Every manager
MUST remember that he is a vigilance officer in his own area of supervision.
INTERNAL AUDIT
Internal Audit Department of RSP is an integral part of Corporate Internal Audit (SAIL). It is a
statutory requirement as per Company’s Act. Accordingly an Audit Committee was constituted
by SAIL Board. For effective functions of the same, Internal Audit department of various
plants/units of SAIL functions as a part of the Corporate Internal Audit.
It examines, evaluates and provides professional opinion on its systems of financial, operational
and management controls. It is an effective management tool to ensure that management
controls are working effectively and operations are being carried out in consonance with the
overall organisational objectives. One of its major functions is to check the compliance with
established and statutory accounting system and procedures to ensure that the final accounts
represent a true and fair financial position of the company.
Heads of Internal Audits (HOIA) conduct monthly review meetings to review the
progress and status of various Audits and also the findings there-of. Wherever
necessary the matter is taken up with higher authorities for necessary action against
various Audit observations.
A monthly report as per standard proforma is sent by HOIA to Corporate Office
detailing the number of audits scheduled, done, number of PR & FR issued with details
and various Significant Audit Findings (SAF) status thereof.
Similarly, a monthly report is also submitted to MD, RSP by HOIA detailing the various
activities and significant observations for kind perusal of MD.
Quarterly HOIA meetings are held by ED (IA) to review the audit activities of various
units, status of SAF etc and also to discuss various other issues like new rules/
regulations or modifications there-of.
Action taken/proposed to be taken (with time frame) are to be indicated by the auditee for the
audit recommendations which are acceptable to them. Wherever the auditee does not agree
with the observation/suggestion/recommendation, the same is to be clearly mentioned with
reasons for disagreement/suitable explanation.
To provide basic health care and also to impart health education four Health Centres are there
spread across the Steel Township. There is also a hospital in Sector-22 with bed strength of 30.
To provide free medical care to the poor section of the society, three no. of Free Medical
Consultation Centres have been set up in Sector-6 (Ispat Sanjivani), Chikatmati and Jalda
areas.
RSP was the first to start a full-fledged Occupational Health Service (OHS) Centre in SAIL and
in Orissa. The OHS activities include 3 Ps of Health care, namely pre-employment, pre-
placement and periodic check ups. All the employees are covered under 'Man Maintenance
Programme'. Special health check up for ‘high risk groups’ is being done regularly.
A health center has been established by RSP in a unit taken over by SAIL at Jagdishpur, UP.
Various sophisticated diagnostic and therapeutic instruments have been installed for quick
The Paediatric unit in IGH has the distinction of being chosen as one of the centres of
excellence out of five in India. Working in collaboration with University of Maryland USA for
prevention of neonatal sepsis, it has contributed significantly towards reducing infant mortality
rate in adjacent rural areas.
Post graduation training (DNB): Eleven Departments of IGH, namely, General Medicines,
General Surgery, Pediatrics, O&G, Orthopedics, Anesthesia, Pulmonary Medicine,
Ophthalmology, Maternal & Child Health, Pathology and Family Medicine have been
accredited by National Board of Examinations for DNB training. Efforts are on to have DNB
training in other disciplines as well.
Treatment of around 15 lakh out door patients and 33,000 indoor patients annually is an
indication of the gamut of operations of the Medical department. But statistics alone are not
the identifying criteria of the commitment of IGH towards society. The commitment is visible in
the continually improving quality of life of the citizens of Rourkela.
Medicine:
The Medicine unit has combined services along with academics. It has various sub-specialities
like Nephrology & Dialysis unit for renal failure patients, Cardiology and Gastroenterology. It
has a modern 11 bed Intensive Care cum Coronary Care unit with facilities for artificial
ventilators, central monitoring and central oxygen. This unit holds the record of implanting a
permanent pacemaker in a boy of eight years age. The Gastroenterology unit performs upper
and lower GI endoscopy along with facility for band ligation, sclerotherapy and foreign body
removal. This unit is recognised at national as well as international level for the research
activities in tropical medicine which has brought laurels to SAIL. It has established
collaboration with World Health Organisation (WHO), Council of Scientific and Industrial
Research (CSIR) and Indian Council of Medical Research (ICMR).
Malaria Research
NIMR (ICMR) Govt. of India with Ranbaxy Research Lab sponsored project on study (Phase III)
of comparasion of Arterolane & Piperaquine phosphate with Coartem in patients with acute
uncomplicated PF Malaria.
IGH has always been in the forefront in research activities. IGH has been recognised by the
World Health Organisation as a training centre for doctors from SAARC countries on malaria
case management. It is also one of the 4 centres in South East Asia to conduct SEAQUAMET
trials in severe ‘Falciparum malaria’. Several landmark papers have been published on malaria
in international journals. Doctors of IGH have played key role in formulating the drug policy for
the treatment of severe malaria in India. New molecules have been developed in collaboration
with CDRI (Lucknow) and MMV (WHO), which will go a long way in the treatment of malaria.
WHO has prepared a documentary film on treatment of severe malaria at IGH for educating
doctors and community on the subject in other parts of India.
SNEHA- a project under CSR has been initiated for underprivileged leprosy patients of the
society. The project envisages of fundamental medical management and rehabilitative surgeries
of the leprosy patients.
KIRAN- a project started for the benefit of employees to break free from the clutches of
addiction and bringing them back to normalcy. Counseled by the psychiatrists of IGH and
supported by the family, colleagues and personnel officers, many employees have been
benefited, thus reducing absenteeism.
SUNAYANA- the community ophthalmology project for patients of the peripheral villages
adopted by RSP for free cataract removal operations and medicare.
BALJYOTI- a project for free treatment of visually impaired children in the age group 3-16
years of peripheral villages and industrial slums was taken up with the assistance of CSR dept.
The ENT unit is recognised as the centre of excellence for removal of foreign bodies from the
respiratory tract in the infants and children.
SUSHRUTI- a project under CSR has been initiated for children up to 15 years of peripheral
villages and slums, with hearing impairment.
The Dental unit is equipped for dental surgeries and artificial dentures.
Laboratory Services:
The laboratory services are the backbones of any good hospital. The Bio-Chemistry Lab is
recognised as one of the finest Labs in the country, as it regularly occupies top ranks in the
external quality control tests conducted by Association of Clinical Bio-Chemists of India (ACBI)
and Christian Medical College (CMC), Vellore for about 2000 hospitals and laboratories in
India. It stood first four times so far in this ranking.
To facilitate the patients in general and the employees in specific, centralized blood collection
system has been introduced for all laboratories.
Library:
IGH has an air-conditioned Library with two internet terminals and four computers, a scanner
and a photo-copier. It is equipped with latest edition of books on various subjects in addition to
more than 40 Journals from India and abroad.
In addition to the above facilities IGH is linked to the Computer & Information Technology
department of RSP through on-line SUN system, which supports a near total computerisation
of the Stores, Statistics, Registration and Finance Sections.
Conference Hall:
IGH is equipped with a fully air-conditioned conference hall where various conferences,
seminars, workshops etc. are conducted regularly.
Air-conditioning:
All the wards on the second floor have been air-conditioned.
Information Centre:
An information centre has been started in the lobby in front of main gate for the benefit of
patients and attendants.
Page: 287 HRD Centre
Rourkela Steel Plant
ORIGIN OF CISF
Govt of India created the post of Industrial Security Advisor in 1961 as a need was felt to
review existing security arrangements in various Public Sector Undertakings in the country.
Shri S N Dutt was appointed as Security Advisor in the Department of Industries and he
recommended that a uniformed Force is to be raised to look after the security of the Public
Sector Undertakings.
The need for a specialized security Force came into sharp focus after the disastrous fire in
Heavy Engineering Corporation Plant at Ranchi on 29th January 1964. A Commission headed
by Justice B Mukherjee was appointed to enquire into the cause of fire. Since in the enquiry it
was revealed that sabotage was committed, he recommended for creation of a Central Security
Force for providing better protection and security to Public Sector Undertakings (PSUs). A Bill
was brought before the Parliament for setting up of Central Industrial Security Force (CISF) in
August 1966 and after thorough security and certain amendments, it was finally passed by both
houses of Parliament and received President’s consent on 02.12.1968 by a notification in official
Gazette.
CISF came into existence in 1969 with a sanctioned strength of only three Battalions. In the
beginning CISF was inducted in only two Undertakings. Currently CISF is providing security
coverage to 272 Industrial Undertakings (including 54 airports out of which 12 are
international) spread all over the country in 77 different establishments Fire Protection is also
being provided.
CISF Act was amended in 1983 and the Force was declared the Armed Force of the Union on
June 15, 1983. The original charter of CISF was to provide protection and security to the
property of Public Sector Undertakings. It was amended in 1989 by Act No.20, which entrusted
the responsibility for providing protection to the employees of Public Sector Undertakings
within their premises to CISF. CISF Act was further amended by Act No.40 of 1999 which
enlarged the charter of -
(i) Providing Technical Consultancy Services related to security of any private Sector
industrial establishments (ii)
(ii) To protect and safeguard the organizations owned or funded by the Govt and the
employees of such organizations as may be entrusted by Central Govt and
(iii) Any other duties which may be entrusted by Central Govt from time to time.
CISF, which made a beginning with a sanctioned strength of 3192 in 1969, has grown to
strength of more than 1 lakh. CISF is the only Para Military Force to have a Fire Fighting
Wing. Now a day the functioning of CISF is not only existed within the periphery of Industrial
Undertakings because CISF is deployed for Election Duties, Internal Security Duties, VIP
duties, Govt Building Security, Metro Rail Security, Rescue Operation duties, UN Mission
duties etc.
Beside the above Pass system is also available in RSP Rourkela. Passes are issued by CISF on
the authentic recommendations of authorized signatories. Various types of passes are available
for making entry/exit in RSP Rourkela. Photo Passes are issued to all RSP Employees.
Separate passes are issued to Contractor Labourers and Supervisors only on proper
recommendations of RSP Management. Laser System Identity cards for the plant’s employees
are issued from CISF Pass Section on submission of filled up applications in a prescribed
proforma duly forwarded by the HODs. Visitors are also issued passes on submission of
applications duly recommended by CLC Department to CISF Pass Section.
As per the re-survey report, 21 gates are operating in RSP Rourkela, which is being guarded by
CISF round the clock besides 28 vital installations situated inside/ outside the plant.
The security system in the plant for countering criminal activities, are being up dated from
time to time according to the need of the day and round the clock guarding around the vital
installations, important stores, all gates, escorting of railway wagons, patrolling inside and
outside the plant premises etc. is ensured by CISF.
Keeping in view of crime prone areas, common modus operandi adopted by criminals and to
stop unauthorized entry, following remedial measures have been taken to ensure effective
security coverage in the plant: -
a) Computerized inventories in the Stores are maintained
b) Thorough verification of material movements is maintained
c) Combing operations/ambush is conducted at regular intervals
d) Strict checking of passes of employees, contractor labourers, visitors at the gates is
ensured
e) Thorough checking of vehicles are made at the gates
f) Random checking is being conducted at Contractor’s stores, loading
g) points and canteens
h) Patrolling has been intensified
i) Surprise re-weighment of loaded vehicle is being conducted
j) Dogs are being utilized during ambush/patrolling
k) Existing modern gadgetry equipment are utilized at gates
l) Scrap materials have been stored in a safer place
m) Character and antecedents of employees are verified
n) Control Room has been established at Main Gate to receive/pass over of various
informations to concerned authorities
o) Checking/surprise checking of various posts and activities are conducted frequently
p) All the movements through the gates are monitored by Control Room.
q) Flow of traffic, movement of vehicles and safety within the plant is also
regulated/controlled
r) Stores, Mandira Dam, Air Strip, TPH, SGP and Cash counters are guarded
effectively by deployed static duty round the clock.
Achievement of CISF
Beside effective and strenuous security duties, CISF deployed in RSP has also achieved good
fame in excellent performance during Independence Day, Republic Day Parades organized by
RSP Rourkela and Civil authorities. Various religious functions are also organized by CISF in
Birsa Camp Complex & CISF Auditorium. Due to effective security coverage in the plant and
township by CISF, crime cases have drastically been minimized.
For making appreciable correspondences and other implementation works in Hindi, this Unit
was awarded with the Best Official Language Trophy and 1st Running Shield by the Town
Official Language Implementation Committee, Rourkela in the year 2006.
MOTO OF CISF:
*-*-*
Page: 291 HRD Centre
Rourkela Steel Plant
Editorial Team