PRESUPUESTO RESUMEN

Propietario: Constructora Perú Top


Obra: Edificio Multifamiliar Mediterraneo
Fecha: Thursday, February 23, 2017

Item Descripción Parcial Sub-Total


I ESTRUCTURAS
01.00.00 Obras y Trabajos Preliminares S/. 27,316.01
02.00.00 Movimiento de Tierras S/. 23,387.50
03.00.00 Concreto Simple S/. 17,705.38
04.00.00 Concreto Armado S/. 336,605.63
04.01.00 Cisterna de Concreto S/. 7,355.51
04.02.00 Zapatas de Concreto S/. 26,276.48
04.03.00 Vigas de Cimentación S/. 9,130.75
04.04.00 Sobrecimientos Armados S/. 10,913.98
04.05.00 Columnas y Placas 1º Nivel S/. 19,602.66
04.06.00 Losa Aliegrada, Vigas y Escalera 1º Nivel S/. 28,256.57
04.07.00 Columnas y Placas 2º Nivel S/. 16,552.30
04.08.00 Losa Aliegrada, Vigas y Escalera 2º Nivel S/. 30,342.44
04.09.00 Columnas y Placas 3º Nivel S/. 15,021.73
04.10.00 Losa Aliegrada, Vigas y Escalera 3º Nivel S/. 31,245.49
04.11.00 Columnas y Placas 4º Nivel S/. 15,722.96
04.12.00 Losa Aliegrada, Vigas y Escalera 4º Nivel S/. 31,699.85
04.13.00 Columnas y Placas 5º Nivel S/. 13,355.77
04.14.00 Losa Aliegrada, Vigas y Escalera 5º Nivel S/. 38,097.41
04.15.00 Columnas y Placas 6º Nivel S/. 12,258.75
04.16.00 Losa Aliegrada, Vigas y Escalera 6º Nivel S/. 26,607.91
04.17.00 Columnas y Placas 7º Nivel S/. 2,236.40
04.18.00 Losa Aliegrada, Vigas y Escalera 7º Nivel S/. 1,928.68
05.00.00 Ladrillo, Revoques y Enlucidos S/. 233,721.29
05.01.00 Ladrillo Bloque 09 S/. 55,309.05
05.02.00 Ladrillo Bloque 14 S/. 14,845.91
05.03.00 Ladrillo Asentado Cabeza S/. 6,961.66
05.04.00 Tarrajeo Interior S/. 61,874.81
05.05.00 Tarrajeo de Vigas S/. 3,358.59
05.06.00 Tarrajeo de Exteriores S/. 35,752.81
05.07.00 Bruñas de pared S/. 3,648.65
05.08.00 Tarraejo de Cielo Raso S/. 23,515.95
05.09.00 Contrapisos y Ladrillo Pastelero S/. 25,809.24
05.10.00 Pasos de Escaleras S/. 2,644.62
06.00.00 Prevención y seguridad S/. 9,000.00

II ARQUITECTURA
07.00.00 Vidrio en General S/. 24,164.89
08.00.00 Barandas Metálicas S/. 15,236.76
09.00.00 Acabados de Pisos y Cerámica S/. 99,285.15
10.00.00 Aparatos Sanitarios y Sanitarios S/. 20,489.00
11.00.00 Pintura en General S/. 63,624.09
12.00.00 Carpintería Madera y Cerrajería S/. 26,908.64
13.00.00 Carpintería de Melamina S/. 45,444.00
14.00.00 Carpintería Metálica S/. 30,944.07

III INSTALACIONES SANITARIAS


15.00.00 M.O. Instalaciones Sanitarias S/. 18,065.00
16.00.00 Materiales Instalaciones Sanitarias S/. 9,939.69

IV INSTALACIONES ELECTRICAS
17.00.00 M.O. Instalaciones Electricas S/. 31,271.00
18.00.00 Materiales Electricos S/. 81,521.50

Costo Directo
IGV 18%
Presupuesto

Área Techada

Costo S/. / m2

Tipo Cambio

Costo US$ / m2
MEN

Totales
S/. 647,735.80

S/. 326,096.60
S/. 326,096.60

S/. 28,004.69

S/. 112,792.50

S/. 1,114,629.59
S/. 200,633.33
S/. 1,315,262.92

1097.66 m2

S/. 1198.24 / m2

S/. 3.24 / US$

US$ 369.83 / m2
V y S - SOLO MANO DE OBRA

Item Descripción Metrado M.O. V y S


01.00.00 Obras y Trabajos Preliminares
01.01.00 Cerco Provisional metálico 75.00 20.00
01.02.00 Trazo y Replanteo de Cimentación 404.66 2.50
01.03.00 Trazo y Replanteo de Obra 1,062.01 2.50
01.04.00 Caseta de Vigilancia
01.05.00 Ofcina de Ingeniería
01.06.00 Almacén provisional de Obra
01.07.00 Limpieza de Obra en ejecución 5.00 1,200.00
01.08.00 Alquiler de Disal
01.09.00 Acometida Provisional para construcción
01.10.00 Sistema de Video Vigilancia
01.11.00 Iluminación de Obra
01.12.00 Tanque de Agua de 1100 lt
01.13.00 Fibra de polipropileno bolsa x 600 g
01.14.00 Señaletica de seguridad
01.15.00 Botiquín de obra
01.16.00 Tecnopor 1/2"
01.17.00 Tecnopor 2"
01.18.00 Uniformes Epps
01.19.00 Agua en bidones
01.20.00 Utiles para oficina ingeniería
02.00.00 Movimiento de Tierras
02.01.00 Corte de Terreno en general inc/elim. 39.45 30.00
02.02.00 Excavación de cisterna inc/elim. 41.74 30.00
02.03.00 Excavación de Sub-Zapatas inc/elim. 35.80 30.00
02.04.00 Excavación de Zapatas inc/elim. 234.42 30.00
02.05.00 Excavación de Cimientos Corridos inc/elim. 14.08 30.00
02.06.00 Excavación de Vigas de Cimentación 9.10 45.00
02.07.00 Relleno controlado de Pisos 364.19 13.00
02.08.00 Acarreo Desmonte en departamentos 110.00 22.00
02.09.00 Eliminación de desmonte
03.00.00 Concreto Simple
03.01.00 Solado de Cisterna 7.48 8.00
03.02.00 Solado de Vigas de Cimentación 5.72 8.00
03.03.00 Solado de Zapatas 90.16 8.00
03.04.00 Solado de Cimientos Corridos 9.76 8.00
03.05.00 Sub cimiento en Cisterna 11.34 90.00
03.06.00 Sub cimiento en Zapatas 49.21 90.00
03.07.00 Falso Piso Concreto Simple e=10cm 179.35 14.00
04.00.00 Concreto Armado
V y S - SOLO MANO DE OBRA

Item Descripción Metrado M.O. V y S


04.01.00 Cisterna de Concreto
04.01.01 Acero en Cisterna 967.38 0.80
04.01.02 Encofrado en Cisterna 29.64 35.00
04.01.03 Concreto de Cisterna 210 4"-6" Ms - Fondo 3.07 90.00
04.01.04 Concreto de Cisterna 210 6"-8" Ms - Muro 5.13 80.00
04.01.05 Concreto de Cisterna 210 4"-6" Ms - Tapa 1.18 80.00
04.01.06 Tarrajeo de Cisterna 27.96 18.00
04.03.00 Zapatas de Concreto
04.03.01 Acero en Zapatas y Cimientos 3,318.13 0.80
04.03.02 Concreto de Zapatas 210 4"-6" Ms (mixer) 62.00 40.00
04.03.03 Concreto de Cimientos 210 4"-6" Ms (mixer) 6.14 40.00
04.04.00 Vigas de Cimentación
04.04.01 Acero en Vigas de Cimentación 1,140.02 0.80
04.04.02 Concreto de Vigas Cim. 210 4"-6" Ms 10.09 85.00
04.04.03 Encofrado de vigas de cimentación 79.94 30.00
04.05.00 Sobrecimientos Armados
04.05.01 Acero en Sobrecimientos Armados 148.46 0.80
04.05.02 Concreto de Sobrecimientos 210 4"-6" Ms 14.05 85.00
04.05.03 Encofrado de vigas de cimentación 169.03 30.00
04.06.00 Columnas y Placas 1º Nivel
04.06.01 Acero en Columnas y Placas 1° Nivel 3,286.11 0.80
04.06.02 Concreto de Columnas 1° Nivel 13.56 110.00
04.06.03 Encofrado de Columnas 1º Nivel 152.09 32.00
04.07.00 Losa Aliegrada, Vigas y Escalera 1º Nivel
04.07.01 Acero en Losa Aligerada, Vigas y Esc. 1º Nivel 3,457.76 0.80
04.07.02 Concreto de L. Aligerada, Vigas y Esc. 1° Nivel 25.30 40.00
04.07.03 Encofrado de Losa Aligerada 1º Nivel 141.15 28.00
04.07.04 Encofrado de Vigas 1º Nivel 79.86 32.00
04.07.05 Encofrado de Escaleras 1º Nivel 1.00 850.00
04.07.06 Ladrillo de Techo 1º Nivel 1,235.00 0.60
04.08.00 Columnas y Placas 2º Nivel
04.08.01 Acero en Columnas y Placas 2° Nivel 2,624.84 0.80
04.08.02 Concreto de Columnas 2° Nivel 11.97 110.00
04.08.03 Encofrado de Columnas 2º Nivel 134.60 32.00
04.09.00 Losa Aliegrada, Vigas y Escalera 2º Nivel
04.09.01 Acero en Losa Aligerada, Vigas y Esc. 2º Nivel 3,584.13 0.80
04.09.02 Concreto de L. Aligerada, Vigas y Esc. 2° Nivel 27.98 40.00
04.09.03 Encofrado de Losa Aligerada 2º Nivel 145.67 28.00
04.09.04 Encofrado de Vigas 2º Nivel 99.95 32.00
04.09.05 Encofrado de Escaleras 2º Nivel 1.00 850.00
V y S - SOLO MANO DE OBRA

Item Descripción Metrado M.O. V y S


04.09.06 Ladrillo de Techo 2º Nivel 1,274.00 0.60
04.10.00 Columnas y Placas 3º Nivel
04.10.01 Acero en Columnas y Placas 3° Nivel 2,235.48 0.85
04.10.02 Concreto de Columnas 3° Nivel 10.42 120.00
04.10.03 Encofrado de Columnas 3º Nivel 124.30 34.00
04.11.00 Losa Aliegrada, Vigas y Escalera 3º Nivel
04.11.01 Acero en Losa Aligerada, Vigas y Esc. 3º Nivel 3,634.84 0.85
04.11.02 Concreto de L. Aligerada, Vigas y Esc. 3° Nivel 28.10 40.00
04.11.03 Encofrado de Losa Aligerada 3º Nivel 145.37 30.00
04.11.04 Encofrado de Vigas 3º Nivel 100.22 34.00
04.11.05 Encofrado de Escaleras 3º Nivel 1.00 850.00
04.11.06 Ladrillo de Techo 3º Nivel 1,272.00 0.65
04.12.00 Columnas y Placas 4º Nivel
04.12.01 Acero en Columnas y Placas 4° Nivel 2,235.48 0.95
04.12.02 Concreto de Columnas 4° Nivel 10.82 135.00
04.12.03 Encofrado de Columnas 4º Nivel 128.67 34.00
04.13.00 Losa Aliegrada, Vigas y Escalera 4º Nivel
04.13.01 Acero en Losa Aligerada, Vigas y Esc. 4º Nivel 3,889.48 0.85
04.13.02 Concreto de L. Aligerada, Vigas y Esc. 4° Nivel 28.68 40.00
04.13.03 Encofrado de Losa Aligerada 4º Nivel 132.48 30.00
04.13.04 Encofrado de Vigas 4º Nivel 108.97 34.00
04.13.05 Encofrado de Escaleras 4º Nivel 1.00 850.00
04.13.06 Ladrillo de Techo 4º Nivel 1,159.00 0.65
04.14.00 Columnas y Placas 5º Nivel
04.14.01 Acero en Columnas y Placas 5° Nivel 1,773.26 0.90
04.14.02 Concreto de Columnas 5° Nivel 9.35 130.00
04.14.03 Encofrado de Columnas 5º Nivel 114.51 36.00
04.15.00 Losa Aliegrada, Vigas y Escalera 5º Nivel
04.15.01 Acero en Losa Aligerada, Vigas y Esc. 5º Nivel 5,023.80 0.90
04.15.02 Concreto de L. Aligerada, Vigas y Esc. 5° Nivel 30.79 40.00
04.15.03 Encofrado de Losa Aligerada 5º Nivel 121.92 30.00
04.15.04 Encofrado de Vigas 5º Nivel 108.61 36.00
04.15.05 Encofrado de Escaleras 5º Nivel 4.00 850.00
04.15.06 Ladrillo de Techo 5º Nivel 1,066.00 0.65
04.16.00 Columnas y Placas 6º Nivel
04.16.01 Acero en Columnas y Placas 6° Nivel 1,666.46 0.90
04.16.02 Concreto de Columnas 6° Nivel 8.40 130.00
04.16.03 Encofrado de Columnas 6º Nivel 103.95 36.00
04.17.00 Losa Aliegrada, Vigas y Escalera 6º Nivel
04.17.01 Acero en Losa Aligerada, Vigas y Esc. 6º Nivel 3,000.80 0.90
V y S - SOLO MANO DE OBRA

Item Descripción Metrado M.O. V y S


04.17.02 Concreto de L. Aligerada, Vigas y Esc. 6° Nivel 23.99 40.00
04.17.03 Encofrado de Losa Aligerada 6º Nivel 132.46 30.00
04.17.04 Encofrado de Vigas 6º Nivel 88.98 36.00
04.17.05 Encofrado de Escaleras 6º Nivel - 850.00
04.17.06 Ladrillo de Techo 6º Nivel 1,159.00 0.70
04.18.00 Columnas y Placas 7º Nivel
04.18.01 Acero en Columnas y Placas 7° Nivel 226.83 1.00
04.18.02 Concreto de Columnas 7° Nivel 1.68 145.00
04.18.03 Encofrado de Columnas 7º Nivel 21.78 36.00
04.19.00 Losa Aliegrada, Vigas y Escalera 7º Nivel
04.19.01 Acero en Losa Aligerada, Vigas y Esc. 7º Nivel 209.06 0.90
04.19.02 Concreto de L. Aligerada, Vigas y Esc. 7° Nivel 1.82 40.00
04.19.03 Encofrado de Losa Aligerada 7º Nivel 7.39 34.00
04.19.04 Encofrado de Vigas 7º Nivel 10.35 30.00
04.19.05 Encofrado de Escaleras 7º Nivel - 850.00
04.19.06 Ladrillo de Techo 7º Nivel 64.00 0.70

05.00.00 Ladrillo, Revoques y Enlucidos


05.01.00 Ladrillo Bloque 09
05.01.01 Ladrillo bloque 09 - 1º Nivel 26.44 25.00
05.01.02 Ladrillo bloque 09 - 2º Nivel 190.63 25.00
05.01.03 Ladrillo bloque 09 - 3º Nivel 193.73 26.00
05.01.04 Ladrillo bloque 09 - 4º Nivel 193.20 26.00
05.01.05 Ladrillo bloque 09 - 5º Nivel 130.46 27.00
05.01.06 Ladrillo bloque 09 - 6º Nivel 261.24 27.00
05.01.07 Ladrillo bloque 09 - 7º Nivel 59.40 27.00
05.02.00 Ladrillo Bloque 14
05.02.01 Ladrillo bloque 14 - 1º Nivel 69.46 26.00
05.02.02 Ladrillo bloque 14 - 2º Nivel 39.06 26.00
05.02.03 Ladrillo bloque 14 - 3º Nivel 37.70 28.00
05.02.04 Ladrillo bloque 14 - 4º Nivel 37.70 28.00
05.02.05 Ladrillo bloque 14 - 5º Nivel 49.53 30.00
05.02.06 Ladrillo bloque 14 - 6º Nivel 18.76 30.00
05.03.00 Ladrillo Asentado Cabeza
05.03.01 Ladrillo bloque 25 - 1º Nivel 12.38 28.00
05.03.02 Ladrillo bloque 25 - 2º Nivel 23.35 28.00
05.03.03 Ladrillo bloque 25 - 3º Nivel 12.85 28.00
05.03.04 Ladrillo bloque 25 - 4º Nivel 14.43 28.00
05.03.05 Ladrillo bloque 25 - 5º Nivel 12.45 28.00
05.03.06 Ladrillo bloque 25 - 6º Nivel 14.70 28.00
V y S - SOLO MANO DE OBRA

Item Descripción Metrado M.O. V y S


05.04.00 Tarrajeo Interior
05.04.01 Tarrajeo Interno 1º Nivel 245.74 16.00
05.04.02 Tarrajeo Interno 2º Nivel 539.59 16.00
05.04.03 Tarrajeo Interno 3º Nivel 531.07 16.00
05.04.04 Tarrajeo Interno 4º Nivel 534.31 16.00
05.04.05 Tarrajeo Interno 5º Nivel 370.77 16.00
05.04.06 Tarrajeo Interno 6º Nivel 629.64 16.00
05.04.07 Tarrajeo Interno 7º Nivel 84.93 16.00
05.05.00 Tarrajeo de Vigas
05.05.01 Tarrajeo Vigas 1º Nivel 42.03 18.00
05.05.02 Tarrajeo Vigas 2º Nivel 14.89 18.00
05.05.03 Tarrajeo Vigas 3º Nivel 19.07 18.00
05.05.04 Tarrajeo Vigas 4º Nivel 19.07 18.00
05.05.05 Tarrajeo Vigas 5º Nivel 30.18 18.00
05.05.06 Tarrajeo Vigas 6º Nivel 15.03 18.00
05.05.07 Tarrajeo Vigas 7º Nivel 5.28 18.00
05.06.00 Tarrajeo de Exteriores
05.06.01 Tarrajeo Exteriores 1º Nivel 150.67 31.00
05.06.02 Tarrajeo Exteriores 2º Nivel 151.58 31.00
05.06.03 Tarrajeo Exteriores 3º Nivel 144.82 31.00
05.06.04 Tarrajeo Exteriores 4º Nivel 144.82 31.00
05.06.05 Tarrajeo Exteriores 5º Nivel 145.67 31.00
05.06.06 Tarrajeo Exteriores 6º Nivel 144.52 31.00
05.06.07 Tarrajeo Exteriores 7º Nivel 90.68 31.00
05.07.00 Bruñas de pared
05.07.01 Bruñas de Muros 1º Nivel 62.79 5.50
05.07.02 Bruñas de Muros 2º Nivel 83.79 5.50
05.07.03 Bruñas de Muros 3º Nivel 83.79 5.50
05.07.04 Bruñas de Muros 4º Nivel 83.79 5.50
05.07.05 Bruñas de Muros 5º Nivel 111.09 5.50
05.07.06 Bruñas de Muros 6º Nivel 83.79 5.50
05.07.07 Bruñas de Muros 7º Nivel 52.29 5.50
05.08.00 Tarraejo de Cielo Raso
05.08.01 Tarrajeo de Cielo Raso 1º Nivel 157.02 20.00
05.08.02 Tarrajeo de Cielo Raso 2º Nivel 161.21 20.00
05.08.03 Tarrajeo de Cielo Raso 3º Nivel 160.25 20.00
05.08.04 Tarrajeo de Cielo Raso 4º Nivel 159.78 20.00
05.08.05 Tarrajeo de Cielo Raso 5º Nivel 152.92 20.00
05.08.06 Tarrajeo de Cielo Raso 6º Nivel 138.67 20.00
05.08.07 Tarrajeo de Cielo Raso 7º Nivel 8.00 20.00
V y S - SOLO MANO DE OBRA

Item Descripción Metrado M.O. V y S


05.09.00 Contrapisos y Ladrillo Pastelero
05.09.01 Contra piso 1º Nivel 192.74 13.00
05.09.02 Contra piso 2º Nivel 158.94 13.00
05.09.03 Contra piso 3º Nivel 166.90 14.00
05.09.04 Contra piso 4º Nivel 167.66 14.00
05.09.05 Contra piso 5º Nivel 170.59 15.00
05.09.06 Contra piso 6º Nivel 147.76 15.00
05.09.07 Contra piso 7º Nivel 169.76 15.00
05.09.08 Piso Pastelero 12.33 19.00
05.10.00 Pasos de Escaleras
05.09.01 Pasos Escaleras 1º Nivel 17.00 21.00
05.09.02 Pasos Escaleras 2º Nivel 15.00 21.00
05.09.03 Pasos Escaleras 3º Nivel 15.00 21.00
05.09.04 Pasos Escaleras 4º Nivel 15.00 21.00
05.09.05 Pasos Escaleras 5º Nivel 45.00 21.00

06.00.00 Prevención y seguridad


06.00.01 Paz Social 1.00 3,000.00
06.00.02 Prevencionista de Obra 1.00 6,000.00

COSTO DIRECTO
IGV 18%
PRESUPUESTO
S - SOLO MANO DE OBRA

Sub Parcial

1,500.00
1,011.65
2,655.03

6,000.00

1,183.63
1,252.15
1,074.06
7,032.48
422.37
409.62
4,734.52
2,420.00

59.84
45.76
721.28
78.08
1,020.60
4,428.90
2,510.90
S - SOLO MANO DE OBRA

Sub Parcial

773.91
1,037.40
276.51
410.59
94.25
503.28

2,654.50
2,480.18
245.70

912.02
857.23
2,398.20

118.77
1,194.17
5,070.87

2,628.89
1,491.28
4,866.92

2,766.21
1,011.94
3,952.23
2,555.48
850.00
741.00

2,099.87
1,316.70
4,307.05

2,867.31
1,119.08
4,078.84
3,198.50
850.00
S - SOLO MANO DE OBRA

Sub Parcial
764.40

1,900.16
1,250.55
4,226.04

3,089.62
1,123.99
4,361.23
3,407.60
850.00
826.80

2,123.71
1,460.03
4,374.87

3,306.06
1,147.33
3,974.36
3,705.04
850.00
753.35

1,595.93
1,214.85
4,122.37

4,521.42
1,231.54
3,657.63
3,910.08
3,400.00
692.90

1,499.81
1,092.00
3,742.30

2,700.72
S - SOLO MANO DE OBRA

Sub Parcial
959.51
3,973.74
3,203.35
-
811.30

226.83
243.30
784.24

188.16
72.98
251.09
310.62
-
44.80

660.98
4,765.69
5,036.85
5,023.20
3,522.49
7,053.48
1,603.80

1,805.90
1,015.56
1,055.46
1,055.46
1,485.75
562.80

346.68
653.86
359.86
403.96
348.68
411.60
S - SOLO MANO DE OBRA

Sub Parcial

3,931.79
8,633.46
8,497.09
8,549.00
5,932.39
10,074.22
1,358.88

756.62
267.98
343.32
343.32
543.16
270.60
95.00

4,670.66
4,698.98
4,489.43
4,489.43
4,515.86
4,479.99
2,811.08

345.35
460.85
460.85
460.85
611.00
460.85
287.60

3,140.47
3,224.11
3,204.95
3,195.68
3,058.48
2,773.38
160.06
S - SOLO MANO DE OBRA

Sub Parcial

2,505.67
2,066.21
2,336.62
2,347.29
2,558.83
2,216.46
2,546.47
234.25

357.00
315.00
315.00
315.00
945.00

3,000.00
6,000.00

353,063.89
63,551.50
416,615.40
PRESUPUESTO ARQUITECTURA

Propietario: Constructora Perú Top


Obra: Edificio Multifamiliar Mediterraneo
Fecha: Thursday, February 23, 2017

Item Descripción Unidad Metrado M.O.


07.00.00 Vidrio en General
07.01.00 Vidrio de baños unid 23.00
07.02.00 Vidrio de 6 mm m2 616.35
07.03.00 Vidrio de 6 mm pavonado m2 447.83
07.04.00 Vidrio de 8 mm m2 1,375.44
07.05.00 Block de Vidrio unid 210.00 5.00
08.00.00 Barandas Metálicas
08.01.00 Baranda Metálica ml 69.26
09.00.00 Acabados de Pisos y Cerámica
09.01.00 Pisos
09.01.01 Piso Pulido m2 167.81 4.00
09.01.02 Piso Porcelanato 1º a 6º Nivel m2 648.90 14.00
09.01.03 Piso Cerámico 1º a 6º Nivel m2 173.27 14.00
09.01.04 Piso Escalera 1º a 5º Nivel m2 53.98 14.00
09.01.05 Mueble de Cocina unid 9.00 350.00
09.02.00 Contra zócalos
09.02.01 Contra zócalo Pulido ml 104.10 5.00
09.02.02 Contra zócalo porc. 1º a 6º Nivel ml 746.43 5.00
09.02.03 Contra cerá. porc. 1º a 6º Nivel ml 82.27 5.00
09.02.04 Contra escalera 1º a 6º Nivel ml 82.31 5.00
09.03.00 Zócalo
09.03.01 Zócalo de cerámico m2 445.50 15.00
09.03.02 Piedra en Ingreso m2 40.00 25.00
09.04.00 Pasos
09.04.01 Pasos unid 106.00 20.00
10.00.00 Aparatos Sanitarios y Sanitarios
10.01.00 Inodoro Sifón Jet unid 24.00
10.02.00 Lavatorio Semi Pedestal unid 24.00
10.03.00 Grifería de Lavatorio unid 24.00
10.04.00 Lavaplatos unid 9.00
10.05.00 Grifería de Lavaplatos unid 9.00
10.06.00 Lavarropa de porcelanato unid 9.00
10.07.00 Grifería de Lavarropa unid 9.00
10.08.00 Mezcladora de ducha unid 22.00
10.09.00 Registro 4" unid 24.00
10.10.00 Registro 6" unid 4.00
10.11.00 Sumidero 2" unid 65.00
10.12.00 Niquelado de reg. y sumideros unid 93.00
11.00.00 Pintura en General
11.01.00 Pintura en interiores m2 4,019.46 5.00
11.02.00 Pintura en exteriores m2 972.76 9.00
11.03.00 Enyesado de exterior m2 516.59 8.00
11.04.00 Pintura en estacionamientos glb 1.00 200.00
11.03.00 Pintura de color en fachada m2 93.00 13.00
12.00.00 Carpintería Madera y Cerrajería
12.01.00 Puertas Interiores unid 60.00
12.02.00 Puertas Exteriores unid 10.00
12.03.00 Chapas Puertas Interiores unid 60.00
12.04.00 Chapas Puertas Exteriores unid 10.00
12.05.00 Bisagras 3 1/2" unid 236.00
12.06.00 Bisagras 4" unid 40.00
12.07.00 Bisagras vaivén unid 7.00
12.08.00 Celosia de Madera unid 1.00
13.00.00 Carpintería de Melamina
13.01.00 Closets
13.01.01 Closets Tipo 01 unid 3.00
13.01.02 Closets Tipo 02 unid 4.00
13.01.03 Closets Tipo 03 unid 4.00
13.01.04 Closets Tipo 04 unid 4.00
13.01.05 Closets Tipo 05 unid 3.00
13.01.06 Closets Tipo 06 unid 3.00
13.01.07 Closets Tipo 07 unid 1.00
13.01.08 Closets Tipo 08 unid 1.00
13.01.09 Closets Tipo 09 unid 1.00
13.01.10 Closets Tipo 10 unid 1.00
13.01.11 Closets Tipo 11 unid 1.00
13.02.00 Reposteros Bajos
13.02.01 Repostero Bajo Tipo 01 unid 3.00
13.02.02 Repostero Bajo Tipo 02 unid 3.00
13.02.03 Repostero Bajo Tipo 03 unid 1.00
13.02.04 Repostero Bajo Tipo 04 unid 1.00
13.02.05 Repostero Bajo Tipo 05 unid 1.00
13.02.06 Mueble de Recepción unid 1.00
13.03.00 Reposteros Altos
13.03.01 Repostero Alto Tipo 01 unid 3.00
13.03.02 Repostero Alto Tipo 02 unid 3.00
13.03.03 Repostero Alto Tipo 03 unid 1.00
13.03.04 Repostero Alto Tipo 04 unid 1.00
13.03.05 Repostero Alto Tipo 05 unid 1.00
14.00.00 Carpintería Metálica
14.01.00 Puertas plegadizas 5.05 m unid 1.00
14.02.00 Puertas plegadizas 4.95 m unid 1.00
14.03.00 Puertas plegadizas 2.50 m unid 2.00
14.04.00 Tapa de entrada cuarto de cisterna unid 1.00
14.05.00 Rejilla para bombas unid 1.00
14.06.00 Escaleras de Acero Inoxidable en C.Maq. unid 1.00
14.07.00 Escalera para Tanque Elevado unid 1.00
QUITECTURA

P.U. MAT Precio Sub Parcial Parcial Sub-Total


24,164.89
50.00 50.00 1,150.00 24,164.89
7.50 7.50 4,622.63
8.50 8.50 3,806.51
9.00 9.00 12,378.98
5.51 10.51 2,206.78
15,236.76
220.00 220.00 15,236.76 15,236.76
99,285.15
52,012.52
5.34 9.34 1,567.15
32.92 46.92 30,448.81
46.27 60.27 10,442.98
46.27 60.27 3,253.58
350.00 700.00 6,300.00
8,461.30
1.60 6.60 687.25
3.29 8.29 6,189.68
4.63 9.63 791.99
4.63 9.63 792.38
31,296.11
46.27 61.27 27,296.11
75.00 100.00 4,000.00
7,515.22
50.90 70.90 7,515.22
20,489.00
210.00 210.00 5,040.00 20,489.00
110.00 110.00 2,640.00
110.00 110.00 2,640.00
200.00 200.00 1,800.00
80.00 80.00 720.00
150.00 150.00 1,350.00
60.00 60.00 540.00
150.00 150.00 3,300.00
20.00 20.00 480.00
30.00 30.00 120.00
10.00 10.00 650.00
13.00 13.00 1,209.00
63,624.09
63,624.09
5.00 10.00 40,194.65 63,624.09
6.00 15.00 14,591.34
4.00 12.00 6,199.10
300.00 500.00 500.00
10.00 23.00 2,139.00
26,908.64
280.00 280.00 16,800.00 26,908.64
510.00 510.00 5,100.00
30.00 30.00 1,800.00
101.69 101.69 1,016.95
3.39 3.39 800.00
2.54 2.54 101.69
70.00 70.00 490.00
800.00 800.00 800.00
45,444.00
20,520.00
760.00 760.00 2,280.00
900.00 900.00 3,600.00
480.00 480.00 1,920.00
1,060.00 1,060.00 4,240.00
820.00 820.00 2,460.00
880.00 880.00 2,640.00
540.00 540.00 540.00
860.00 860.00 860.00
660.00 660.00 660.00
520.00 520.00 520.00
800.00 800.00 800.00
13,260.00
1,140.00 1,140.00 3,420.00
915.00 915.00 2,745.00
1,395.00 1,395.00 1,395.00
1,595.00 1,595.00 1,595.00
2,105.00 2,105.00 2,105.00
2,000.00 2,000.00 2,000.00
11,664.00
1,104.00 1,104.00 3,312.00
1,364.00 1,364.00 4,092.00
1,220.00 1,220.00 1,220.00
1,200.00 1,200.00 1,200.00
1,840.00 1,840.00 1,840.00
30,944.07
9,322.03 9,322.03 9,322.03 30,944.07
9,322.03 9,322.03 9,322.03
5,500.00 5,500.00 11,000.00
300.00 300.00 300.00
300.00 300.00 300.00
350.00 350.00 350.00
350.00 350.00 350.00
COSTO DIRECTO 326,096.60
IGV 18% 58,697.39
PRESUPUESTO 384,793.98
PRESUPUESTO INSTALACIONES SANITARIAS

Propietario: Constructora Perú Top


Obra: Edificio Multifamiliar Mediterraneo
Fecha: Thursday, February 23, 2017

Item Descripción Unidad Metrado M.O.


15.00.00 M.O. Instalaciones Sanitarias
16.00.00 Materiales Instalaciones Sanitarias

PRESUPUESTO INSTALACIONES ELECTRICAS

Propietario: Constructora Perú Top


Obra: Edificio Multifamiliar Mediterraneo
Fecha: Thursday, February 23, 2017

Item Descripción Unidad Metrado M.O.


17.00.00 M.O. Instalaciones Electricas
18.00.00 Materiales Electricos
NES SANITARIAS

P.U. MAT Precio Sub Parcial Parcial Sub-Total


18,065.00
9,939.69

COSTO DIRECTO 28,004.69


IGV 18% 5,040.84
PRESUPUESTO 33,045.54

NES ELECTRICAS

P.U. MAT Precio Sub Parcial Parcial Sub-Total


31,271.00
81,521.50

COSTO DIRECTO 112,792.50


IGV 18% 20,302.65
PRESUPUESTO 133,095.15
COLUMNAS

PISO ALTURA (m) ÁREA (m2) PERÍMETRO (m) % CONCRETO % ENCOFRADO


1 2.45 5.27 60.27
2 2.50 4.56 52.27
3 2.50 3.97 48.27
4 2.50 4.12 49.97 5% 3%
5 2.50 3.56 44.47
6 2.50 3.20 40.37
7 2.35 0.68 9.00

VIGAS Y LOSAS

PISO h viga (m) ÁREA (m2) PERÍMETRO (m) % CONCRETO % ENCOFRADO


0.40 18.65 153.67
0.30 2.43 23.10
1º Nivel 5% 3%
0.20 8.55 102.80
FRISO 76.23

LOSA 137.04 0.09


1º Nivel ESC TRAMO 1 1.61 1.20 5% 3%
ESC TRAMO 2 0.42 1.20

PISO h viga (m) ÁREA (m2) PERÍMETRO (m) % CONCRETO % ENCOFRADO


0.40 26.01 211.78
0.30 2.01 17.60
2º Nivel 5% 3%
0.20 9.90 142.17
FRISO 77.02

LOSA 141.43 0.09


2º Nivel ESC TRAMO 1 0.62 1.20 5% 3%
ESC TRAMO 2 0.61 1.20

PISO h viga (m) ÁREA (m2) PERÍMETRO (m) % CONCRETO % ENCOFRADO


0.40 25.62 206.45
0.30 2.70 23.10
3º Nivel 5% 3%
0.20 10.43 145.33
3º Nivel 5% 3%

FRISO 77.02

LOSA 141.14 0.09


3º Nivel ESC TRAMO 1 0.62 1.20 5% 3%
ESC TRAMO 2 0.61 1.20

PISO h viga (m) ÁREA (m2) PERÍMETRO (m) % CONCRETO % ENCOFRADO


0.40 25.62 206.45
0.30 2.70 23.10
4º Nivel 5% 3%
0.20 19.10 158.58
FRISO 77.40

LOSA 128.62 0.09


4º Nivel ESC TRAMO 1 0.62 1.20 5% 3%
ESC TRAMO 2 0.61 1.20

PISO h viga (m) ÁREA (m2) PERÍMETRO (m) % CONCRETO % ENCOFRADO


0.40 26.26 212.25
0.30 2.70 23.10
5º Nivel 5% 3%
0.20 16.97 147.98
FRISO 77.00

LOSA 118.37 0.09


ESC TRAMO 1 0.62 1.20
ESC TRAMO 2 0.61 1.20
5º Nivel 5% 3%
ESCALERA 501 1.10 0.90
ESCALERA 502 1.23 0.90
ESCALERA 503 1.23 0.90

PISO h viga (m) ÁREA (m2) PERÍMETRO (m) % CONCRETO % ENCOFRADO


0.40 23.48 189.95
0.30 0.65 5.70
6º Nivel 5% 3%
0.20 10.58 157.38
6º Nivel 5% 3%

FRISO 67.32

6º Nivel LOSA 128.60 0.09 5% 3%

PISO h viga (m) ÁREA (m2) PERÍMETRO (m) % CONCRETO % ENCOFRADO


0.40 2.49 22.00
0.30 - -
7º Nivel 5% 3%
0.20 0.60 7.40
FRISO 12.90

7º Nivel LOSA 7.17 0.09 5% 3%

ACERO

PARTIDAS X ELEMENTOS
PESOS %
ACERO EN GENERAL 39647.05 kg
PRIMER NIVEL 11512.02 kg
ACERO Fy=4,200 kg/cm2 EN ZAPATAS 2877.96 kg
ACERO Fy=4,200 kg/cm2 EN VIGAS DE CIMENTACIÓN 1065.44 kg
ACERO Fy=4,200 kg/cm2 EN CIMIENTOS CORRIDOS ARMADOS 223.09 kg
ACERO Fy=4,200 kg/cm2 EN SOBRECIMIENTOS CORRIDOS ARMADOS 138.74 kg
ACERO Fy=4,200 kg/cm2 EN CISTERNA 904.10 kg
ACERO Fy=4,200 kg/cm2 EN PLACAS Y COLUMNAS 3071.13 kg
ACERO Fy=4,200 kg/cm2 EN VIGAS 2175.47 kg
ACERO Fy=4,200 kg/cm2 EN LOSAS ALIGERADAS 668.53 kg
ACERO Fy=4,200 kg/cm2 EN ESCALERAS 387.56 kg
SEGUNDO NIVEL 5802.78 kg
ACERO Fy=4,200 kg/cm2 EN PLACAS Y COLUMNAS 2453.12 kg
ACERO Fy=4,200 kg/cm2 EN VIGAS 2254.35 kg
ACERO Fy=4,200 kg/cm2 EN LOSAS ALIGERADAS 707.75 kg
ACERO Fy=4,200 kg/cm2 EN ESCALERAS 387.56 kg
TERCER NIVEL 5486.28 kg
ACERO Fy=4,200 kg/cm2 EN PLACAS Y COLUMNAS 2089.23 kg
ACERO Fy=4,200 kg/cm2 EN VIGAS 2297.66 kg
ACERO Fy=4,200 kg/cm2 EN LOSAS ALIGERADAS 711.83 kg 7%
ACERO Fy=4,200 kg/cm2 EN ESCALERAS 387.56 kg
CUARTO NIVEL 5724.26 kg
7%

ACERO Fy=4,200 kg/cm2 EN PLACAS Y COLUMNAS 2089.23 kg


ACERO Fy=4,200 kg/cm2 EN VIGAS 2562.16 kg
ACERO Fy=4,200 kg/cm2 EN LOSAS ALIGERADAS 685.31 kg
ACERO Fy=4,200 kg/cm2 EN ESCALERAS 387.56 kg
QUINTO NIVEL 6352.39 kg
ACERO Fy=4,200 kg/cm2 EN PLACAS Y COLUMNAS 1657.25 kg
ACERO Fy=4,200 kg/cm2 EN VIGAS 2563.04 kg
ACERO Fy=4,200 kg/cm2 EN LOSAS ALIGERADAS 581.87 kg
ACERO Fy=4,200 kg/cm2 EN ESCALERAS 1550.24 kg
SEXTO NIVEL 4361.93 kg
ACERO Fy=4,200 kg/cm2 EN PLACAS Y COLUMNAS 1557.44 kg
ACERO Fy=4,200 kg/cm2 EN VIGAS 2169.97 kg
ACERO Fy=4,200 kg/cm2 EN LOSAS ALIGERADAS 634.52 kg
SEPTIMO NIVEL 407.38 kg
ACERO Fy=4,200 kg/cm2 EN PLACAS Y COLUMNAS 211.99 kg
ACERO Fy=4,200 kg/cm2 EN VIGAS 111.24 kg
ACERO Fy=4,200 kg/cm2 EN LOSAS ALIGERADAS 84.15 kg

LADRILLO BLOCK 09

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
1º Nivel MURO 2.45 0.97 2.37 23.67
1º Nivel ALFEIZAR 0.60 0.46 0.28 2.77
26.44

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
2º Nivel MURO 2.50 7.09 17.72 177.19
2º Nivel ALFEIZAR 1.00 1.34 1.34 13.44
190.63

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
3º Nivel MURO 2.50 7.37 18.43 184.28
3º Nivel ALFEIZAR 1.00 0.95 0.95 9.45
193.73

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
4º Nivel MURO 2.50 7.35 18.38 183.75
4º Nivel ALFEIZAR 1.00 0.95 0.95 9.45
193.20

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
5º Nivel MURO 2.50 4.92 12.31 123.11
5º Nivel ALFEIZAR 1.00 0.74 0.74 7.35
130.46

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
6º Nivel MURO 2.50 10.08 25.20 252.00
6º Nivel ALFEIZAR 1.00 0.92 0.92 9.24
261.24

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
7º Nivel MURO 2.50 - - -
7º Nivel ALFEIZAR 1.00 5.94 5.94 59.40
59.40

LADRILLO BLOCK 14

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
1º Nivel MURO 2.45 4.25 10.42 69.46
1º Nivel ALFEIZAR 0.60 - - -
69.46

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
2º Nivel MURO 2.50 2.10 5.25 35.00
2º Nivel ALFEIZAR 1.00 0.61 0.61 4.06
39.06

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
3º Nivel MURO 2.50 2.13 5.33 35.53
3º Nivel ALFEIZAR 1.00 0.33 0.33 2.17
37.70

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
4º Nivel MURO 2.50 2.13 5.33 35.53
4º Nivel ALFEIZAR 1.00 0.33 0.33 2.17
37.70

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
5º Nivel MURO 2.50 2.97 7.43 49.53
5º Nivel ALFEIZAR 1.00 - - -
49.53

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
6º Nivel MURO 2.50 1.01 2.52 16.80
6º Nivel ALFEIZAR 1.00 0.29 0.29 1.96
18.76

LADRILLO BLOCK 25

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
1º Nivel MURO 2.45 1.09 2.68 10.70
1º Nivel ALFEIZAR 1.00 0.42 0.42 1.68
12.38

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
2º Nivel MURO 2.50 1.58 3.94 15.75
2º Nivel ALFEIZAR 1.00 1.90 1.90 7.60
23.35

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
3º Nivel MURO 2.50 0.84 2.10 8.40
3º Nivel ALFEIZAR 1.00 1.11 1.11 4.45
12.85

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
4º Nivel MURO 2.50 1.00 2.49 9.98
4º Nivel ALFEIZAR 1.00 1.11 1.11 4.45
14.43

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
5º Nivel MURO 2.50 0.41 1.02 4.10
5º Nivel ALFEIZAR 1.00 2.09 2.09 8.36
12.45

NIVEL ELEMENTO ALTURA (m) METRADO (m2) Volumen (m3) Área (m2)
6º Nivel MURO 2.50 1.16 2.89 11.55
6º Nivel ALFEIZAR 1.00 0.79 0.79 3.15
14.70

TARRAJEO INTERIOR

16.66 44.15
8.60 22.79
1.55 4.11
13.10 34.72
5.18 13.73
1º Nivel 6.25 2.65 16.56 3% 245.74
15.71 41.63
4.10 10.87
16.03 42.48
1.80 4.77
1.05 2.78

12.90 32.25
7.30 18.25
6.41 16.03
6.31 15.78
12.80 32.00
23.45 58.63
10.00 25.00
2º Nivel 9.17 2.5 22.93 3% 539.59
30.54 76.35
14.74 36.85
32.23 80.58
2º Nivel 2.5 3% 539.59

8.20 20.50
8.80 22.00
13.60 34.00
13.10 32.75

0.51 1.28
0.25 0.63
10.73 26.83
7.30 18.25
6.41 16.03
6.31 15.78
12.80 32.00
23.45 58.63
3º Nivel 10.00 2.5 25.00 3% 531.07
9.16 22.90
29.50 73.75
14.74 36.85
32.23 80.58
8.20 20.50
8.80 22.00
12.25 30.63
13.60 34.00

0.51 1.28
0.25 0.63
10.73 26.83
7.30 18.25
6.41 16.03
6.31 15.78
13.20 33.00
23.45 58.63
4º Nivel 10.00 2.5 25.00 3% 534.31
9.17 22.93
29.50 73.75
14.74 36.85
32.23 80.58
8.20 20.50
8.80 22.00
13.10 32.75
13.60 34.00

36.39 90.98
6.31 15.78
4.70 11.75
22.14 55.35
19.20 48.00
5º Nivel 11.40 2.5 28.50 3% 370.77
4.80 12.00
5º Nivel 2.5 3% 370.77

20.09 50.23
9.20 23.00
8.61 21.53
1.15 2.88

0.51 1.28
10.98 27.45
7.30 18.25
6.41 16.03
6.31 15.78
13.30 33.25
10.50 26.25
12.80 32.00
14.80 37.00
12.79 31.98
15.82 39.55
6º Nivel 7.58 2.5 18.95 3% 629.64
12.70 31.75
13.32 33.30
12.60 31.50
7.40 18.50
5.30 13.25
8.90 22.25
9.20 23.00
17.55 43.88
13.90 34.75
13.45 33.63
11.10 27.75

11.15 2.35 26.20


7º Nivel 3% 84.93
51.14 1.1 56.25

TARRAJEO VIGAS PERALTADAS

4.90 3.43
5.05 3.54
5.05 3.54
2.85 2.00
4.35 3.05
4.95 3.47
5.10 3.57
2.50 1.75
1º Nivel 0.95 0.7 0.67 4% 42.03
3.20 2.24
1.85 1.30
2.35 1.65
3.79 2.65
2.50 1.75
3.35 2.35
2.50 1.75
2.50 1.75

1.90 1.33
2.20 1.54
3.00 2.10
2.00 1.40
2º Nivel 1.80 0.7 1.26 4% 14.89
2.70 1.89
1.70 1.19
2.50 1.75
2.65 1.86

2.75 1.93
1.70 1.19
1.90 1.33
2.50 1.75
2.20 1.54
3º Nivel 2.65 0.7 1.86 4% 19.07
3.00 2.10
3.00 2.10
2.00 1.40
1.80 1.26
2.70 1.89

2.75 1.93
1.90 1.33
2.20 1.54
3.00 2.10
3.00 2.10
4º Nivel 2.00 0.7 1.40 4% 19.07
1.80 1.26
2.70 1.89
1.70 1.19
2.50 1.75
2.65 1.86

2.75 1.93
5.05 3.54
1.10 0.77
1.80 1.26
2.90 2.03
3.00 2.10
1.55 1.09
5º Nivel 0.7 4% 30.18
5.10 3.57
2.70 1.89
2.50 1.75
5º Nivel 0.7 4% 30.18

2.80 1.96
4.35 3.05
3.20 2.24
2.65 1.86

2.75 1.93
2.90 2.03
2.95 2.07
2.95 2.07
6º Nivel 0.7 4% 15.03
2.05 1.44
2.35 1.65
2.20 1.54
2.50 1.75

2.40 1.68
7º Nivel 2.50 0.7 1.75 4% 5.28
2.35 1.65

TARRAJEO EXTERIOR

34.48 99.99
1º Nivel 2.9 5% 150.67
15.00 43.50

34.78 100.86
2º Nivel 2.65 5% 151.58
15.00 43.50

32.56 94.42
3º Nivel 2.65 5% 144.82
15.00 43.50

32.56 94.42
4º Nivel 2.65 5% 144.82
15.00 43.50

32.84 95.24
5º Nivel 2.65 5% 145.67
15.00 43.50

32.46 94.13
6º Nivel 2.65 5% 144.52
15.00 43.50

29.78 86.36
7º Nivel 1.1 5% 90.68
- -

JUNTAS

9-14-25 verticales derrames


5% 62.79
1º Nivel 19.80 20.00 20.00

9-14-25 verticales derrames


5% 83.79
2º Nivel 19.80 20.00 40.00
9-14-25 verticales derrames
5% 83.79
3º Nivel 19.80 20.00 40.00

9-14-25 verticales derrames


5% 83.79
4º Nivel 19.80 20.00 40.00

9-14-25 verticales derrames


5% 111.09
5º Nivel 19.80 20.00 66.00

9-14-25 verticales derrames


5% 83.79
6º Nivel 19.80 20.00 40.00

9-14-25 verticales derrames


5% 52.29
7º Nivel 19.80 20.00 10.00

CIELORASOS

Nivel Metrados % Metrado Final


1º Nivel 152.45 157.02
2º Nivel 156.51 161.21
3º Nivel 155.58 160.25
4º Nivel 155.13 3% 159.78
5º Nivel 148.47 152.92
6º Nivel 134.63 138.67
7º Nivel 7.77 8.00

CONTRA PISOS

Nivel Metrados % Metrado Final


1º Nivel 187.13 192.74
2º Nivel 154.31 158.94
3º Nivel 162.04 166.90
4º Nivel 162.78 167.66
3%
5º Nivel 165.62 170.59
6º Nivel 143.46 147.76
7º Nivel 164.82 169.76
PASTELERO 11.97 12.33
CONCRETO (m3) ENCOFRADO (m2) PISO
13.56 152.09 1
11.97 134.60 2
10.42 124.30 3
10.82 128.67 4
9.35 114.51 5
8.40 103.95 6
1.68 21.78 7

CONCRETO (m3) ENCOFRADO (m2)


7.83 50.87
0.73 4.74
1.71 8.55
15.70
79.86

12.59 141.15
1.93
0.50
141.15

25.30

CONCRETO (m3) ENCOFRADO (m2)


10.92 70.42
0.60 3.77
1.98 9.90
15.87
99.95

12.99 145.67
0.74
0.73
145.67

27.98

CONCRETO (m3) ENCOFRADO (m2)


10.76 68.92
0.81 5.01
2.09 10.43
15.87
100.22

12.97 145.37
0.74
0.73
145.37

28.10

CONCRETO (m3) ENCOFRADO (m2)


10.76 68.92
0.81 5.01
3.82 19.10
15.94
108.97

11.82 132.48
0.74
0.73
132.48

28.68

CONCRETO (m3) ENCOFRADO (m2)


11.03 70.77
0.81 5.01
3.39 16.97
15.86
108.61

10.88 121.92
0.74
0.73
0.99
1.11
1.11
121.92

30.79

CONCRETO (m3) ENCOFRADO (m2)


9.86 63.31
0.20 1.22
2.12 10.58
13.87
88.98

11.82 132.46
132.46

23.99

CONCRETO (m3) ENCOFRADO (m2)


1.05 7.10
- -
0.12 0.60
2.66
10.35

0.66 7.39
7.39

1.82

PESOS
42422.35 kg
12317.86 kg
3079.42 kg
1140.02 kg
238.70 kg
148.46 kg
967.38 kg
3286.11 kg
2327.75 kg
715.32 kg
414.69 kg
6208.98 kg
2624.84 kg
2412.16 kg
757.29 kg
414.69 kg
5870.32 kg
2235.48 kg
2458.50 kg
761.66 kg
414.69 kg
6124.96 kg
2235.48 kg
2741.51 kg
733.28 kg
414.69 kg
6797.06 kg
1773.26 kg
2742.46 kg
622.60 kg
1658.75 kg
4667.26 kg
1666.46 kg
2321.87 kg
678.94 kg
435.90 kg
226.83 kg
119.02 kg
90.04 kg
VIDRIO

Descripción Metrado % Desperdicio Metrado Final


Vidrio de baños 23.00 1.00 23.00
Vidrio de 6 mm 587.00 1.05 616.35
Vidrio de 6 mm pavonado 426.50 1.05 447.83
Vidrio de 8 mm 1,309.94 1.05 1,375.44

VIDRIO DE BAÑOS

VIDRIO BAÑO 1° Nivel 1.00


VIDRIO BAÑO 2° Nivel 4.00
VIDRIO BAÑO 3° Nivel 4.00
VIDRIO BAÑO 4° Nivel 4.00 23.00
VIDRIO BAÑO 5° Nivel 4.00
VIDRIO BAÑO 6° Nivel 6.00
VIDRIO BAÑO 7° Nivel -

VIDRIO 6 MM

2º Nivel
D201 Sala 3.00 1.50 50.00
D201 Estar 0.95 1.50 15.83
D201 D1 2.75 1.50 45.83
D201 D2 1.50 1.50 25.00
D202 D2 1.20 1.50 20.00
D202 Estar 1.20 1.50 20.00

3º Nivel
D301 D2 1.50 1.50 25.00
D301 Estar 0.95 2.10 22.17
D302 D2 1.20 1.50 20.00
D302 Estar 1.20 1.50 20.00

4º Nivel
D401 D2 1.50 1.50 25.00
D401 Estar 0.95 2.10 22.17
587.00
D402 D2 1.20 1.50 20.00
D402 Estar 1.20 1.50 20.00

5º Nivel
D501 Sala 0.95 2.10 22.17
D501 Comedor 1.50 1.50 25.00
D503 Cocina 1.20 1.50 20.00
D503 Cocina 2 1.00 1.50 16.67
Exterior 2.50 1.50 41.67

6º Nivel
D501 D2 0.95 2.10 22.17
D502 D2 1.70 1.50 28.33
D502 D3 1.20 1.50 20.00
D503 D2 1.20 1.50 20.00
D503 D3 1.20 1.50 20.00

VIDRIO 6 MM pavonado

2º Nivel
D201 Cocina 1.70 1.50 28.33
D201 Tendal 2.05 1.60 36.44
D201 Estudio 1.40 1.60 24.89
D202 Estudio 1.85 1.50 30.83

3º Nivel
D301 Cocina 1.70 1.50 28.33
D301 Tendal 2.05 1.60 36.44
D301 Estudio 1.40 1.60 24.89
D302 Estudio 1.85 1.50 30.83
426.50

4º Nivel
D401 Cocina 1.70 1.50 28.33
D401 Tendal 2.05 1.60 36.44
D401 Estudio 1.40 1.60 24.89
D402 Estudio 1.85 1.50 30.83

5º Nivel
D502 Cocina 1.85 1.50 30.83
D502 Tendal 2.05 1.50 34.17

VIDRIO 8 MM

1º Nivel
Ingreso 2.40 2.50 66.67

2º Nivel
D202 Sala 2.75 2.30 70.28
D202 D1 2.65 2.30 67.72
3º Nivel
D301 Sala 3.00 2.30 76.67
D301 D1 2.75 2.30 70.28
D302 Sala 2.75 2.30 70.28
D302 D1 2.65 2.30 67.72

4º Nivel
D401 Sala 3.00 2.30 76.67
D401 D1 2.75 2.30 70.28 1,309.94
D402 Sala 2.75 2.30 70.28
D402 D1 2.65 2.30 67.72

5º Nivel
D501 Sala 2.75 2.30 70.28
D501 Escalera 2.05 2.30 52.39
D502 Sala 3.00 2.30 76.67
D503 Sala 2.70 2.30 69.00
D503 Comedor 2.70 2.30 69.00

6º Nivel
D501 Sala 2.75 2.30 70.28
D501 Escalera 2.05 2.30 52.39
D502 D1 2.95 2.30 75.39

BARANDA

Resumen 65.96 1.05 69.26

2º Nivel 2.65
3º Nivel 3.31 3.64 2.5 3.41
4º Nivel 3.31 3.64 2.5 2.78
5º Nivel 3.31 3.64 6.92
6º Nivel 3.31 3.64
Escaleras 3.00 4.80 4.80 4.80

PISOS

Piso Pulido 1º Nivel n2 162.92


Piso Porcelanato 1º Nivel n2 20.91
Piso Porcelanato 2º Nivel n2 115.08
Piso Porcelanato 3º Nivel n2 122.73
Piso Porcelanato 4º Nivel n2 123.66
Piso Porcelanato 5º Nivel n2 142.13
Piso Porcelanato 6º Nivel n2 105.49
Piso Cerámico 1º Nivel n2 1.75
Piso Cerámico 2º Nivel n2 34.50
Piso Cerámico 3º Nivel n2 34.50
Piso Cerámico 4º Nivel n2 34.50
Piso Cerámico 5º Nivel n2 21.25
Piso Cerámico 6º Nivel n2 41.72
Pisos Escaleras 1º Nivel n2 9.00
Pisos Escaleras 2º Nivel n2 9.81
Pisos Escaleras 3º Nivel n2 9.81
Pisos Escaleras 4º Nivel n2 9.81
Pisos Escaleras 5º Nivel n2 14.00

CONTRA ZÓCALOS

Contrazócalo Pulido 1º Nivel ml 101.07


Contrazócalo Porc. 1º Nivel ml 22.68
Contrazócalo Porc. 2º Nivel ml 134.34
Contrazócalo Porc. 3º Nivel ml 142.52
Contrazócalo Porc. 4º Nivel ml 149.62
Contrazócalo Porc. 5º Nivel ml 119.21
Contrazócalo Porc. 6º Nivel ml 156.32
Contrazócalo Cerá. 1º Nivel ml -
Contrazócalo Cerá. 2º Nivel ml 13.35
Contrazócalo Cerá. 3º Nivel ml 13.35
Contrazócalo Cerá. 4º Nivel ml 13.35
Contrazócalo Cerá. 5º Nivel ml 17.15
Contrazócalo Cerá. 6º Nivel ml 22.67
Pisos Escaleras 1º Nivel ml 17.51
Pisos Escaleras 2º Nivel ml 13.25
Pisos Escaleras 3º Nivel ml 13.25
Pisos Escaleras 4º Nivel ml 13.25
Pisos Escaleras 5º Nivel ml 22.65

ZÓCALOS

Zócalo Cerá. 1º Nivel m2


Zócalo Cerá. 2º Nivel m2 92.49
Zócalo Cerá. 3º Nivel m2 92.49
Zócalo Cerá. 4º Nivel m2 92.49
Zócalo Cerá. 5º Nivel m2 49.76
Zócalo Cerá. 6º Nivel m2 105.29
167.81 167.81 167.81
21.54 648.90
118.53 173.27
126.41 53.98
648.90
127.37
146.39
108.65
1.80
1.03
173.27
35.54
1.03
35.54
173.27
35.54
21.89
42.97
9.27
10.10
10.10 53.98
10.10
14.42

104.10 104.10 104.10


23.36 746.43
138.37 82.27
146.80 82.31
746.43
154.11
122.79
161.01
-
13.75
1.03
13.75
82.27
13.75
17.66
23.35
18.04
13.65
13.65 82.31
13.65
23.33

- 445.50
95.27
95.27
1.03 445.50
95.27
51.25
108.45
Acero

Descripción Unidad Metrado Precio Parcial


Acero Corrugado kg 1.00 1.88 1.88
Alambre # 16 kg 0.03 3.24 0.10
1.98

Analisis de Ladrillo

Descripción Unidad Metrado Precio Parcial


Ladrillo bloque 09 m2 12.50 1.70 21.25
Cemento MS bls 0.25 17.80 4.45
Arena Gruesa m3 0.02 25.00 0.50
26.20

Descripción Unidad Metrado Precio Parcial


Ladrillo bloque 14 m2 12.50 2.00 25.00
Cemento MS bls 0.31 17.80 5.56
Arena Gruesa m3 0.03 25.00 0.63
31.19

Descripción Unidad Metrado Precio Parcial


Ladrillo kk 18 m2 63.00 0.59 37.37
Cemento MS bls 0.63 17.80 11.21
Arena Gruesa m3 0.03 25.00 0.63
49.21

Tarrajeo Interior

Descripción Unidad Metrado Precio Parcial


Cemento MS bls 0.25 17.80 4.45
Arena Fina m3 0.02 25.00 0.38
Agua m3 0.05 5.00 0.25
5.07

Tarrajeo Exterior

Descripción Unidad Metrado Precio Parcial


Cemento MS bls 0.25 17.80 4.45
Arena Fina m3 0.02 25.00 0.38
Agua m3 0.05 5.00 0.25
Clavos tamaño promedio kg 0.05 3.40 0.17
Alambre # 08 kg 0.15 3.40 0.51
5.75

Contrapiso
Descripción Unidad Metrado Precio Parcial
Cemento MS bls 0.33 17.80 5.93
Arena Gruesa m3 0.05 25.00 1.25
Agua kg 0.05 5.00 0.25
7.43

Pastelero

Descripción Unidad Metrado Precio Parcial


Cemento MS bls 0.05 17.80 0.89
Ladrillo Pastelero unid 16.00 1.14 18.31
Tierra Chacra m3 0.06 40.00 2.40
Agua kg 0.05 5.00 0.25
21.84

Pasos de escaleras

Descripción Unidad Metrado Precio Parcial


Cemento MS bls 0.17 17.80 2.97
Arena Gruesa m3 0.03 25.00 0.63
Agua kg 0.03 5.00 0.13
3.72

Ventana de Baño

Descripción Unidad Metrado Precio Parcial


Ventana Baño glb 1.00 50.00 50.00
50.00

Vidrio 6 mm

Descripción Unidad Metrado Precio Parcial


Vidrio 6 mm pie2 1.00 7.50 7.50
7.50

Vidrio 6 mm pavonado

Descripción Unidad Metrado Precio Parcial


Vidrio 6 mm pavonado pie2 1.00 8.50 8.50
8.50

Vidrio 8 mm

Descripción Unidad Metrado Precio Parcial


Vidrio 8 mm pie2 1.00 9.00 9.00
9.00
Porcelanato

Descripción Unidad Metrado Precio Parcial


Porcelanato m2 1.00 22.25 22.25
Pegamento bls 0.40 25.42 10.17
Fragua bls 0.10 5.08 0.51
32.92

Descripción Unidad Metrado Precio Parcial


Porcelanato m2 1.00 35.59 35.59
Pegamento bls 0.40 25.42 10.17
Fragua bls 0.10 5.08 0.51
46.27