T3072 Instruments Installation Progress

Remaining 3 Cell Box Drain( 10 meters drain)


Approved
Overall
Item Instrument Name Installed Outstanding Drawing Progress ( % ) Percentage
Remarks
(Quantity)
1 Inclinometer (Soil) 13 2 15 87% To be installed after sheet piling

2 Water Standpipe 11 1 12 92% To be installed after sheet piling

3 Vibrating Wire Strain Gauge 48 12 60 80% To be installed after excavation

4 Load Cell 6 1 7 86% To be installed after excavation

5 Ground Settlement Marker 179 1 180 99% (1 no omitted)


97%
6 Utility Settlement Marker 31 3 34 91% (54 nos omitted)

7 Building Settlement Marker 179 0 179 100% Completed (5 nos omitted)

8 Tilt Meter 53 0 53 100% Completed (1 no omitted)

9 Prism 120 0 120 100% Completed (2 nos omitted)

10 Tape Extensometer 48 0 48 100% Completed (20 nos omitted)

STATION
Approved
Overall
Item Instrument Name Installed Outstanding Drawing Progress ( % ) Percentage
Remarks
(Quantity)
1 Ground Settlement Marker 40 390 430 9%

2 Building Settlement Marker 244 20 264 92% (5 nos Propose to omit)

3 Tilt Meter 50 0 50 100% Completed

4 Prism 90 0 90 100% Completed

5 Tape Extensometer 84 0 84 100% Completed (32 nos Propose to omit)


54%
6 Inclinometer (Wall) 5 28 28 18%

7 IE/MX 3 3 6 50%

8 Water Standpipe 5 2 7 71%


Vibrating Wire Strain
9 21 15 36 58% 12x3=36
Gauge(3 Tips)
Vibrating Wire Strain
10 0 4 4 0%
Gauge(1 Tip)
11 Utility Settlement Marker 32 388 420 8%

Note : 40 nos installed LG's used at ERsS Drain works


TUNNEL (T307~T306)
Approved
Overall
Item Instrument Name Installed Outstanding Drawing Progress ( % ) Percentage
Remarks
(Quantity)

1 Ground Settlement Marker 0 124 124 0%

2 Building Settlement Marker 122 214 336 36%

3 Tilt Meter 40 66 106 38%

4 Prism 72 62 134 54%

5 Tape Extensometer 4 81 85 5%
29%
6 IE/MX 0 5 5 0%
Vibrating Wire Strain
7 0 4 4 0% 2x2=4
Gauge(2 Tips)
Vibrating Wire Strain
8 0 9 9 0%
Gauge(1 Tip)
9 Rod Extensometer (2 Tips) 0 6 6 0% 3x2=6

1 of 2
10 Rod Extensometer (1 Tip) 0 4 4 0%

TUNNEL (T307~T308)
Approved
Overall
Item Instrument Name Installed Outstanding Drawing Progress ( % ) Percentage
Remarks
(Quantity)
1 Ground Settlement Marker 0 327 327 0%

2 Building Settlement Marker 70 16 86 81% Outsanding (Gracious Mans)

3 Utility Settlement Marker 0 69 69 0%

4 Tilt Meter 32 4 36 89% Outsanding (Gracious Mans)

5 Prism 44 8 52 85% Outsanding (Gracious Mans)

6 IE/MX 0 19 19 0% 19%
Vibrating Wire Piezometer(3
7 0 45 45 0% 15x3=45
Tips)
Vibrating Wire Piezometer(2
8 0 42 42 0% 21x2=42
Tips)
Vibrating Wire Piezometer(1
9 0 22 22 0%
Tip)
10 Rod Extensometer (3 Tips) 0 36 36 0% 12x3=36

11 Rod Extensometer (1 Tip) 0 32 32 0%

(T307~T308 INTERFACE )
Approved
Overall
Loc Instrument Name Installed Outstanding Drawing Progress ( % ) Percentage
Remarks
(Quantity)
Changi bound Ground Settlement Marker 33 33 33 100% 7 nos omitted
100%
Woodland
Ground Settlement Marker 34 34 34 100% 6 nos omitted
bound

2 of 2