Professional Documents
Culture Documents
1E\&5&3UHVV//&
of construction. I would also like to pass along a funda- the detail conveys this message. Note the detail shown in
mental premise to bear in mind on any field check, and that is: Figure D-3. Sprinkler feed main piping in this case needs to
be run through an existing area that is congested with some
WHEN YOU’RE ON A JOB, TAKE YOUR TIME round ductwork and an electrical cable tray. It would be next
AND OBSERVE! to impossible for the installer to understand precisely what he
is supposed to do with his pile of pipe and grooved fittings,
I might add this note as well: always ask an installer to without the benefit of this detail. Again, specific dimensions
critique your engineering skills. This he will gladly do, and must be provided.
you would be wise to listen closely to what he has to say. Figure D-9 shows a section detail of a “double riser-
For one thing, it is in their best interest for engineered plan nipple,” which is often used for efficient installation in a case
quality to increase. If you seize the opportunity to ask the where branch-lines running on either side of a cross-main
sprinkler fitters how you can improve your work, you will must initially be run at separate elevations. Again, the de-
become much better at your job, believe me. tail (which need not be very fancy) gives the installer a clear
The field check is your one occasion to check to see if picture of intended pipe routing.3 Time is of the essence when
field conditions are exactly as they were presupposed to be. drawing. The detail shown in Figure D-10 is very nicely done,
For example, was the water brought in to the correct loca- but probably too fancy for our purposes. However, since the
tion, or even the right room? Was the steel set at the correct detail is a supplement to the delineations shown on the plan,
elevations?2 Is the ductwork being installed where it is sup- all information that needs clarification must be detailed. In-
posed to be? Are there any visible obstructions where our cidentally, all details thus far referred to in this chapter have
cross-main is to be installed? Should any holes be cored in been “double-line” drawings. You should always draw what-
any concrete walls or floors? What is the elevation of the bot- ever is most comfortable to you. But there is absolutely noth-
tom of the ductwork? Will there be any problem hanging the ing wrong with the use of “single-line” drawings, such as
pipe from building structural members? You get the idea. that displayed in Figure D-11, or in previous examples noted
The field check is a troubleshooting phase of the engi- in Figures E-1 and E-2. The only idea or method not to be
neering, a time to look for problems before they occur. This compromised is that of getting your message across.
phase is important because “engineering revisions by crisis” A detail may be so cluttered that it becomes necessary
is simply too costly, and can hold up the overall construction to include your own reference marks. This is usually done in
process. You may dislike the chore of revising work that you instances where a lot of valving and other system components
have already plan-engineered, but it is much cheaper than are to be installed. Referring to Figure E-9, we can see that the
revising the work at a later date. pipe dimensions shown are made clearer by this method, and
the entire picture is cleaner.4 The exactness of the engineering
*** is less apt to be compromised through the use of these circle
I would also encourage you to show a detail or two on any references.
fire sprinkler plan.
***
A PICTURE IS WORTH A THOUSAND WORDS! Very often, the two-dimensional plan itself is not scaled
large enough in certain areas, to include all noted informa-
This axiom applies directly to the job of sprinkler design. tion. When this occurs, an “enlarged plan view” is the only
For one detail example, refer to Figure E-5. The fitter will means by which to show all the engineered pipe offsets and
not really be sure that the 1 1/2 vertical piece is to be in- routing changes. In both examples noted as Figures E-10
stalled inside the wall shown, unless this is detailed on the el- and E-11, the plan’s scale is 1/8 = 1 0 . By enlarging the
evation. Remember, looking at a two-dimensional blueprint plan view to a scale of 1/4 = 1 0 , we are simply adding
in the field is not the easiest task, especially for someone space for our dimensions and notes. This method will be
not schooled in blueprint reading. The section shown in utilized most often in cases where the building is already
Figure E-8 is another good example of a plan depiction that existing (and the possibilities of long straight piping runs
will save the fitter time in the field. The dimensions delin- are limited), or (as in Figure E-11) there is a stairwell or
eated by you give the fitter exact coordinates with which to some other location involved that requires valving, drains,
carry out his work. and/or alarm zoning. The numerous detailed notes are an
Details shown in Figures D-5 through D-8 are examples obvious necessity and simply cannot fit on the plan at the
of plan depictions that are about as detailed as you will want smaller scale. Speaking of stairwells, and referring specif-
to get. In certain decorative or “fussy” building areas, the ically to the example shown in Figure E-12, the stairways
detail is utilized to get across as much specific informa- in a high-rise building are usually areas that will require
tion as you need to deliver. In these examples, obviously, an elevation to be drawn. The dashed line in Figure E-12
the sidewall sprinkler positioning is critical to the job, and refers to existing fire protection piping.5 Again, a picture is
1E\&5&3UHVV//&
worth a thousand words, and the numerous dimensions in r required hydrostatic testing
Figure E-12 will assist you in your plan engineering as much r occupancy of building
as it will help the sprinkler fitter in installing system piping. r flow test results
They establish the “starting point” benchmarks for the system r hydraulic design data
design. r the inclusion/exclusion of tamper switches7
The many examples and details used for reference in r NFPA #13, or other, code compliance
this chapter are definitely not typical of the usual sprinkler r items of fire protection work that are not within the
engineering project but are simply included to convey the scope of the contract
idea that details are a necessary plan component. A detail r the sprinkler-head count
such as the one depicted in Figure D-5, while simplistic, may r typical suspended ceiling height
be just as necessary as any other. r which side of joist or beam to hang the cross-main
An additional plan component that may be required is
an engineer’s (or architect’s) stamp. There is, as of this You may also wish to refer to Section 8-1.1.1 on page 137
date, no actual fire protection engineer’s stamp that is either of NFPA #13 for a complete list of standard required elements
recognized or approved on a national level. If a stamp is a of working plans. That list, however, is not relative to every
requirement, and cannot be overlooked, it will be necessary job that you will engineer. For example, on a small job that
to consult with the Authority Having Jurisdiction (AHJ) to consists only of the relocation of existing sprinklers, it would
determine exactly what his requirement is. take longer to engineer the project than it would to install it,
Two details that are most often used are shown in if Section 8-1.1.1 was strictly adhered to.
Figures D-12 and D-13, and both are used in cases where pen- One final note to be made is especially relevant for be-
dent sprinkler location is to be “intentional,” with the usual ginning engineers. Office personnel, and field labor manage-
required placement to be within one inch of the geometric ment, will be glad to look over your completed work for you.
center of the ceiling grid panel.6 Both configurations allow Ask for suggestions relative to the plan’s thoroughness and
for 360◦ flexibility for the 1 arm that supplies the 1 drop completion. This will give you a frame of reference for know-
to the sprinkler-head. Figure D-12 is typical of the situation ing when the plan is actually finished. It’s always better to
where drops from an existing system must be relocated for be safe than sorry, and two heads are better than one. Also,
construction remodeling. In new construction, Figure D-13 is three heads are better than two, and I promise these will be
most widely used. This “mutual” or “return-bend” arrange- the last worn-out cliches used in this book.
ment, also noted in Figure 5-13.19 NFPA #13, is paramount
for the avoidance of sediment accumulation in the 1 drop.
An often overlooked requirement of NFPA #13 when using ENDNOTES
either method can be found in Section 6-2.3.4 of the 1999
edition. This stipulates the rules governing the length of the 1
NFPA #24 requires that hydrants be located at least 40 away from
armover that can be installed with or without an additional any structure. That rule in origin is for firefighter protection from
hanger. By code, an unsupported armover may not exceed wall collapse. Also, a hydrant located very close to a building may
become so hot during a fire that it is actually unapproachable and
24 inches in length. unusable by the time of fire company arrival.
2
The survey equipment you will want to bring along on a field check
***
will include a telescopic measuring pole, two 8 folding carpenter’s
Finally, the last addition to the sprinkler plan will be a list- rulers, a 50 measuring tape, a flashlight, and a hard hat. And don’t
ing of explanatory notes. This text includes some examples forget the blueprints.
3
(Figures E-13 through E-15) of general notes. These can in- In this example, “GR.EL.” refers to a grooved elbow, “T.B.E.”
refers to pipe threaded on both ends, and “G-T” refers to pipe with
clude a legend of symbols as well. The notes are necessary for
one grooved end and one threaded end.
thorough completion of work, and should most importantly, 4
The “FL-FL” reference in this example refers to a piece of piping
convey the scope of work, design criteria used, type of mate- with companion flanges made on each end. “C.O.J.” refers to a piece
rial used, building construction, and the nature of the hazard of piping that is to be “cut on job.” Since the exact elevation of the
being protected. Do not forget to include the following, if incoming water service is uncertain or not known, the actual length
applicable, amongst your plan notes: of the riser piece cannot be prefabricated.
5
In this example, “E-E” references the pipe dimension as “end-
r type of sprinkler-heads
to-end.” “F-F” refers to “finished floor.” The cL notation refers to a
r type of pipe and fittings
“centerline” of pipe elevation.
6
r type of hangers
The sprinklers depicted are those of the recessed pendent type
(Figure D-12) and the “phantom” or concealer type (Figure D-13).
r whether or not pendent sprinklers are to be “centered” The “BCI” reference stands for “black cast-iron.”
7
in ceiling tile panels Valve electrical supervisory switches.
1E\&5&3UHVV//&