Marine Survey Practice: Surveyor Guide Notes for Anchors and Chains ... http://marinesurveypractice.blogspot.co.id/2013/01/anchors-and-chains-s...
Condition of anchor head holes for fitting of the anchor pin. If anchor head holes are worn, increased Surveyor Guide Notes for Outs
diameter anchor pin may be fitted. Inspection of the...
Surveyor Guide Notes for Anch
Condition of shackle and hole in shank (for shackle pin). Chains Survey...
Surveyor Guide Notes for Bilge
Excessive wear in anchor shank hole or to shackle pin can be repaired by welding according to AWS and/or Survey
Class requirements. Surveyor Guide Notes for Doo
Surveyor Guide Notes for Rud
Anchor pins or shackles should be renewed if mean diameter D1 is less than 0.88 times the original Rudder Stock and ...
diameter.
Surveyor Guide Notes for Prop
See table below for chain cables. Surveys
Intermediate and Periodical Su
Repairs by welding to the anchor may be permitted in accordance with repair requirements in Class
requirements procedure for steel forgings or castings, to the satisfaction of the Surveyor. Bent anchors can Renewal Survey
sometimes be straightened; the acceptance will be on a case by case basis. Following repairs, NDE should Surveyor Guide Notes for Add
be carried out and anchor re- tested for major repairs as per procedures (proof loading test). Surveys
Surveyor Guide Notes for Rep
Surveyor Guide Notes for Gen
Chain cable links Ships Surve...
Surveyor Guide Notes for Hatc
of Dry Cargo...
Surveyor Guide Notes for Bulk
Survey
Surveyor Guide Notes for Oil T
Survey
Surveyor Guide Notes for Con
Survey
Surveyor Guide Notes for Saili
Survey.
Surveyor Guide Notes for Boa
Survey
Usual method of checking wear limits is to select by visual inspection 3 worst links and calibrate them at Surveyor Guide Notes for Woo
Vessels Survey
position of most wear (area of maximum wear):
Surveyor Guide Notes for Draf
Vernier Caliper.
Surveyor Guide Notes for Tow
Arrangement Survey...
Surveyor Guide Notes for MOD
Arrangements....
Surveyor Guide Notes for Bolla
Tests.
Surveyor Guide Notes for Ship
Inclining...
Surveyor Guide Notes for P&I
Surveys
Surveyor Guide Notes on Tails
Survey
Surveyor Guide Notes on
Tailshaft/Propeller Assemb.
Surveyor Guide Notes for Boile
Surveyor Guide Notes for Mari
Chain cable link renewal criteria Engine Surv...
Link is to be renewed if D1 = 0.88D Surveyor Guide Notes for Prep
(D being Rule diameter mentioned in the Register) Condition Sur...
Surveyor Guide Notes on Safe
Construction Certif...
Surveyor Guide Notes on Safe
Equipment Certifica...
Surveyor Guide Notes on Load
Certificate Defic...
Surveyor Guide Notes on Marp
Certificate Deficie...
2 of 5 5/11/2018, 11:24 AM
Marine Survey Practice: Surveyor Guide Notes for Anchors and Chains ... http://marinesurveypractice.blogspot.co.id/2013/01/anchors-and-chains-s...
My Blog List
Digital clock
Links
ABS
American Club Mutual P&I Assoc
AWS online
Binco
Britannian Steam Ship
Securing by welding of loose chain link studs
Bureau Veritas Veristar
Proposal for repair is to be submitted to the Surveyor including a qualified welding procedure. Class NK
Acceptance of the proposal is based on the condition of the link lo be repaired and of remaining links. DNV
Welding is to be performed by qualified welders. Equasis
Estudios de Náutica
European Maritime Safety Agenc
Gard P&I
General Cargo
GL Group
IACS
INEA Venezuela
Institute of Chartered Shipbrokers
Intercargo
International Group of P&I Clubs
Intertanko
Japan Coast Guard
Japan Ship Owners' Mutual Prote
Indemnity Association
Lloyd Register of Shipping
London Pandi
Marine Society
NDE/NDT Resource Center
Following table outlines the conditions for weld procedure specification and qualification test: Paris MOU
Ship Strcture Committe
Process Rating Condition Shipyards Directory
Skuld
For grade Q1 and Q2,
consumables should have Steamship Mutual P&I Club
low hydrogen grading H15 The ImarEST
Welding or better. The Nautical Institute
Welding
procedure Grade 3 or 3Y
consumables The Standard Club
specification
For Q3, a very low The Swedish Club
hydrogen grading of H5 or UK P&I Club
better.
US Coast Guard
West of England P&I
3 of 5 5/11/2018, 11:24 AM
Marine Survey Practice: Surveyor Guide Notes for Anchors and Chains ... http://marinesurveypractice.blogspot.co.id/2013/01/anchors-and-chains-s...
Q1 and Q2:
100° C (min.) Applied to limit hardness
Preheating and to prevent risk of cold
cracks.
Q3: 175º C (min.)
Should be representative
Test procedure of the actual welding
conditions.
Repair procedure
The abutting surfaces of the link and stud to be welded are to be ground to produce a good fit with an
acceptable root gap to prevent cracking. The surfaces are to be free from moisture, grease, rust etc., just
prior to welding.
NDE to check that the link is free from cracks is to be performed before welding at Surveyor satisfaction.
Welding consumables are to be dried adequately prior to welding in accordance with manufacturer’s
recommendation.
In general the stud should be welded at the end opposite to the flash butt weld of the link and it should be
welded completely around the circumference.
All weld stop-starts shall be grounded to remove any defects and to blend smoothly with the base material.
All welds are subjected to visual examination and NDE. For Q3 chain cables, inspection is recommended to
be delayed for at least 48 hours after the weld has cooled to ambient temperature.
Studs should be located in the links centrally and at right angles to the sides of the link.