2. After filling all 160 pcs of sacks 4 labors will be left on 8th floor to transfer the sacks to the
crane basket.
3. After the crane has transported the basket to the Ground Floor 2 labors will unload the sacks 2
labors will transfer the sacks and load the 2 buggies 2 labors to push the 2 buggies and 3
labors will unload the sacks from the buggy and discharge each sacks on the creek side.
5. This process was completed 3 times meaning we have cleared 480 sacks of debris within 8
hours span.