Professional Documents
Culture Documents
discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/265178984
Article
CITATIONS READS
8 228
4 authors, including:
Bernd Engel
Technische Universität Braunschweig
30 PUBLICATIONS 87 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Thomas Stetz on 25 February 2015.
ABSTRACT: In this paper the economically optimized inverter sizing is determined for PV inverters which have to
provide reactive power. A PV module model and a PV inverter model were developed in Matlab®, based on real
one-year solar irradiation profiles provided by Meteonorm® and recorded at Fraunhofer IWES test sites. The single
cost categories of a PV inverter are introduced and discussed with respect to an economically optimized sizing
considering reactive power supply. The investigated reactive power supply methods follow the suggestions in the
German technical guideline for the connection of generators to the medium voltage network and the recent draft of
the technical guideline for the connection to the low voltage network. The results show that the sizing of a PV
inverter has to be adapted to the respective reactive power supply methods in order to keep it economically
optimized.
3 COST CATEGORIES
This section describes the single cost categories which
Figure 2: Investigated cosφ(P) characteristics. have to be taken into account for the determination of an
economically optimized inverter sizing under
consideration of reactive power provision.
Cinv = S ⋅ c [€ ] (1)
Table 1: Specification of the reference scenario Costs by additional inverter losses: Providing reactive
Location Kassel, Mid-Germany power by PV inverters leads to additional active power
Module tilt angle 30°
losses ΔPL [kW] within the inverter, compared to pure
Module orientation 0° (south)
Module technology Polycrystalline silicon active power feed-in. The specific additional losses ΔpL
SMA Sunny Mini [kW/ kVA] can be calculated solving a recursive
PV Inverter
Central TL algorithm introduced in [8].
Max.inverter efficiency / Euro-eta 97.7% / 97.3%
Reimbursement PV for energy 0.3405 €/ kWh
2 2 2
Specific investment costs 320 €/ kVA ⎛ P (t ) ⎞ ⎛ Q(t ) ⎞ ⎛ ⎛ PAC (t ) ⎞ ⎛ Q(t ) ⎞ ⎞
Reactive power supply method Fixed cosφ Δp L (t ) = c self + cv ⋅ ⎜ AC ⎟ + ⎜ ⎟ + c R ⎜⎜ ⎜ ⎟+⎜ ⎟ ⎟⎟
⎝ S ⎠ ⎝ S ⎠ ⎝⎝ S ⎠ ⎝ S ⎠⎠
Inverter lifetime 10 years
Discount rate 5% ⎡ ⎛ P (t*) ⎞
2
⎛ P (t*) ⎞ ⎤⎥
2
− ⎢c self + cv ⋅ ⎜ AC ⎟ + c R ⎜ AC ⎟
⎢ ⎝ S ⎠ ⎝ S ⎠ ⎥⎦
Voltage profile for Q(U) droop function ⎣
For the simulations of the Q(U) reactive power supply (3)
method a voltage profile for the point of common
coupling (PCC) is needed as an input value for the
Here, cself stands for the standby losses [kW/ kWp], cv [-]
for the voltage dependent losses and cR [kWp/ kW] for
the current dependant losses within the inverter. For the
same generator DC power output (PDC) the active power
output of the inverter PAC is different
The annual additional operational costs ΔCoperational [€/ yr] Figure 5: PQ-Diagram for a PV inverter, explaining the
is the product of the specific annual additional energy different kinds of opportunity costs.
losses ΔEL [kWh/(kVA yr)] multiplied with the current
The PV energy which cannot be fed-in (ΔEopp) [kWh/ yr]
reimbursement for PV energy co [€/ kWh] and the size of
due to reactive power supply, assessed with the current
the inverter S [kVA].
reimbursement for PV energy co [€/ kWh], leads to the so
called additional opportunity costs ΔCopp [€/ yr].
⎛T ⎞ ⎡€⎤
ΔCoperational = ⎜⎜ ∫ Δp L (t ) ⎟⎟ ⋅ S ⋅ co = ΔE L ⋅ S ⋅ co ⎢ ⎥ (4)
⎝ t =1 ⎠ ⎣ yr ⎦ ⎛T ⎞ ⎡€⎤
ΔCopp = ⎜⎜ ∫ ΔPopp ,Q ≠ 0 (t ) ⎟⎟ ⋅ co = ΔEopp ⋅ co ⎢ ⎥ (8)
⎝ t =1 ⎠ ⎣ yr ⎦
The total operational costs of an inverter with reactive
power provision Coperational,Q≠0 [€/ yr] can be calculated as
The total opportunity costs Copp,Q≠0 comprise of the
Coperational , Q ≠ 0 = Coperational , Q = 0 + ΔCoperational (5) regular opportunity costs Copp,Q=0 and the additional
opportunity costs ΔCopp.
considering also the operational costs by active power
feed-in Coperational,Q=0 [€/ yr]. ⎡€⎤ (9)
Copp ,Q ≠0 = Copp ,Q =0 + ΔCopp ⎢ yr ⎥
⎣ ⎦
Costs by additional opportunity losses: Opportunity
losses in general occur, if the active power output of a Now, the goal is to find the specific inverter sizing s
PV inverter has to be reduced. This might happen during [kVA/ kWp] where the total annual inverter costs CQ≠0
times of high solar irradiation, when the current DC
are at its minimum.
power generation exceeds the sizing of the inverter. Now,
considering reactive power provision by PV inverters, the
CQ≠0 = f ( s) → min (10)
active power reduction Popp,Q≠ 0 [kW] does not only
with ⎡ € ⎤ (11)
depend on the DC power generation, but also on the CQ≠0 = A + Copp ,Q≠0 + Coperational ,Q≠0 ⎢ yr ⎥
reactive power output Q(t) (compare figure 5). The part ⎣ ⎦
of the total opportunity losses Popp,Q ≠ 0 which is only due
Figure 6 shows the respective characteristics of the
to the additional reactive power provision is called different cost categories for the reference scenario using
additional opportunity losses ΔPopp,Q≠0 [kW]. a fixed cosφ method with a power factor of 0.9. The costs
respectively savings, depicted on the Y-axes, are the
annual additional costs compared to the annual costs of
ΔPopp ,Q ≠0 (t ) = Popp ,Q ≠0 (t ) − Popp ,Q =0 (t ) [kW ] (6) an inverter without reactive power provision and a sizing
ratio Smax/ PDCmax of 1.
ΔPopp ,Q ≠0 (t ) = S max (1 − Δp L (t ) ) − S max − Q(t ) 2 [kW ] (7)
2
Here,
Smax = maximum apparent power of the inverter [kVA]
Q(t) = reactive power provision at time t [kvar]
ΔpL = specific additional operational losses [kW/ kVA]
PDC(t) = DC power generation at time t [kW]
increases, leading to lower annual savings compared to
pure active power feed-in. The single reactive power
supply methods can be distinguished by the color of the
respective bubbles. Index (1) depicts those methods with
a minimum power factor of 0.9 (as currently discussed
for generators installed in Germany with more than
13.8 kVA [3]) and index (2) all methods with a minimum
power factor of 0.95 (as currently discussed for
generators installed in Germany with less than 13.8 kVA
[3]). Due to the fact that a lower minimum power factor
leads to more reactive power provision during one year,
all methods with a minimum power factor of 0.9 show a
higher optimized sizing than their respective subversion
with a minimum power factor of 0.95.
Figure 6: Single cost categories for an economically
optimized inverter sizing.
Figure 11 depicts the specific additional inverter costs by Future costs and reimbursements developments
providing a fixed power factor of 0.95 (compare In this paragraph the influence of reimbursement rates for
Figure 9) compared to the reference scenario at different PV energy and investment costs of the PV inverter on the
tilt and orientation angles. It can be seen that the highest economically optimized inverter sizing are discussed.
additional costs by reactive power occur in cases where Figure 13 shows the economically optimized inverter
the PV module is aligned energetically optimized. This is sizing and the specific costs respectively savings of the
due to higher average solar irradiation on the tilted reference scenario, depending on the reimbursement for
surface and therefore influences the additional PV energy. A power factor of 0.95 is considered for the
opportunity costs during operation. fixed cosφ method.
It can be seen that the additional reactive power provision
increases the additional costs and the economically
optimized sizing compared to pure active power feed-in. economically optimized inverter sizing is the reactive
The higher the reimbursement rates for PV energy, the power supply method itself. Simulations, conducted for a
higher the economically optimized inverter sizing. This is PV system Germany showed a wide range for the
due to the fact that the costs by operational inverter additional sizing of up to +12% compared to no reactive
losses and opportunity losses gain in importance at power provision, depending on the reactive power supply
higher reimbursement rates. In future, lower method.
reimbursement rates will lead to lower economically It turned out that the influence of the orientation and tilt
optimized inverter sizings. angle as well as the location of the PV system on the
additional inverter sizing due to reactive power is
marginal. Further simulations showed that decreasing
reimbursement rates for PV energy lower the
economically optimized inverter sizing while decreasing
investment costs lead to the opposite effect.
ACKNOWLEDGEMENT
The authors thank the German Federal Ministry for
the Environment, Nature Conservation and Nuclear
Safety and the Forschungszentrum Jülich GmbH (PTJ)
for the support within the framework of the project “PV-
EMS” (FKZ 0325028). The authors are solely
responsible for the content of this publication.
Figure 13: Economically optimized inverter sizing and
related costs considering different reimbursement rates.
REFERENCES
Figure 14 shows the economically optimized inverter
sizing, depending on the specific investment costs for the [1] SMA Regelsysteme GmbH, Department Solartechnics
(2003). Die optimale Auslegung einer netzgekoppelten PV-
PV inverter. In contrast to the energy dependent costs by
Anlage – Vorabausgabe. Kassel, 2003
opportunity and additional inverter losses (which Published at:
increase with increasing reimbursement rates), the http://www.sonne-nrw.de/Dokumente/
economically optimized inverter size decreases with SMA+optimale+Auslegung-PV-Anlage.pdf (13.01.2010)
increasing specific investment costs. By the increasing
specific investment costs for the PV inverter also the [2] Woyte, A., Islam, S., Belmans, N., Nijs, J. (2003).
savings potential by an economically optimized sizing Unterdimensionieren des Wechselrichters bei der
will be increased (see right Y-axes). Possible investment Netzkopplung - Wo liegt das Optimum? 18th Symposium
cost reduction in future will hence lead to bigger inverter Photovoltaic Solar Energy, Bad Staffelstein, 2003; pp. 433-
438.
sizes. The additional provision of reactive power
increases the economically optimized inverter sizing and [3] Verband der Elektrotechnik Elektronik Informationstechnik
the additional costs compared to pure active power feed- e.V. (VDN) (2010). Erzeugungsanlagen am Nieder-
in. spannungsnetz Technische Mindestanforderungen für
Anschluss und Parallelbetrieb von Erzeugungsanlagen am
Niederspannungsnetz – Draft of 07-08-2010. Berlin
www.vde.com/de/fnn/dokumente/documents
[5] Braun, M., Stetz, T., Reimann, B., Valov, B., Arnold, G.
(2009). Optimal Reactive Power Supply in Distribution
Networks – Technological and Economic Assessment for
PV-Systems. 24th European Photovoltaic Solar Energy
Conference and Exhibition. Hamburg, 2009