You are on page 1of 4

Facility Planning for a Gas Manufacturing Plant

CHUI WING CHEONG


Hong Kong Oxygen

CHU LAP KEUNG


Dept. of Industrial and Manufacturing Systems Engineering
Hong Kong University

Abstract comparisons can be made between these cases and


in the one
question, baed on a number of viewpoints and criteria.
Unfortunately. such a COrpus of knowledge established by the
local research .and industrial communities is not sufficient.

It is not the aim of this paper to establish a benchmark as


such: this is a major undertaking itself. This paper is about the
facility planning of a gases production plant in Hong Kong,
highlighting
< the typical issues in plant relocation. and some
general approaches that can be applied (the systematic plant
layout methodology and computer-aided layout planning). This
case is interesting because the company in question is Hong
Kong Oxygen ( HKO ), a large company by Hong Kong's standard.
The steps taken in its approach are therefore carefully planned
and worked out. Another reason for the cornpany to he meticulous
is because of the need to deal with its products which are very
Introduction dangerous by. nature such a case study, in facility planning will
Facility planning is a branch of industrial engineering that
be useful in due course to fur-ther the knowledge in this area writh
cletermines the best plant location and designs the facilities for a view on establishing a benchmark.
the production of products and/or services. The choice of the
plant location depends on a number of factors such as the rapid Reasons of Relocation
growth of the company. the availability of cheap land and HKO has been operating in its exihting site in Tseung Kwan
labour. placement with respect to customers and suppliers. and
O since early. 1960's The area is about 10.000 square metres. By
the legal manoeuvrability that is available in that place (especially that time. Tseung Kwan o WaS a very rural area and transportation
in the. developing countries). On the othrr hand, the facility was via sea route only. Initially, there were only two production
aspects includes designing the building (the building itself. and plants: the Hydrogen gas and Dissolved acetylene gas plants.
other utilities like gas. water. power. heat and sewage), the More plants were later built and it now has Nitrous oxide plant,
layout of the plant and the material handling system which Carbon dioxide plant. Air separation unit, medical and industrial
provides
the links between various activities in the olant. gas filling facilities
Facility planning is typically multi-faceted, eclectic and Under the town plannin, g scheme adcanced by the Hong
complex. It draws upon. the expertise and experience from Kong Government. Tseung Kwam O is going to be developed
various departments within the organisation. There are two into a residential area. Land reclamation has started in late 1980's
major problems associated with facility planning. The first and those affected factories. mainly ship building and ship
concerns the project management aspect: coordinating such an repairing. har.e then closed. In early 1991, the South East New
activity and motivating the people with various backgrounds Territories Development Office of the government approached
Mill not be entirely Straightforward. Another is that facility HKO to discuss its proposal to gazette reclamation work in front
planning only occurs infrequently. People will generally be of HKO. This proposal could. in theory, cut off HKO's marine
lacking in experience in tackling the problems in finding the access and therefore cause both explicit and implicit impacts to
new site. designing the plant, move-in and fine tuning. Also, the company.
facility planning is domain Specific. Some mathematical models
have been proposed in tackling the plant location and layout
(i) HKO required sea water access for barges, tugs and vessels.
problems [FMA 92]. Such an operations research approach falls
These were for cylinder transportation, liquid product
short of providing a complete Solution, which requires a
combination of quantitative. qualitative and management transportation. and huge plant equipment transportation. An
adequately safe manoeuvring space had to be allowed for
techniques.
such.
On the more Specific issue of designing the plant layout and (ii) HKO used mainly sea water cooling system. There would be
material handling system, more concrete methodologies have a high chance that the cooling water intake consisting to a
been established. Generally, it depends on experience encoded material extent of water just discharged at the outlet. This
as checklists and cook-book procedures. In any case, the facility would increase the temperature and endanger the process.
designer must develop a thorough understanding in the products, Provision against short circuiting due to reduced Water
the processes, the required production volume and seasonal movements in the area had to be provided.
fluctuations, and the relationships between the various activities
(iii)Acceptable arrangements would have to be made to prevent
in the factory,
the waterway ceasing to be navigable due to silting Up or
improper uSe for mooting or anchorage, and also to prevent
In the authors’ opinion, benchmarking will be appropriate the water becoming Unusable as cooling water due to floating
and effective in tackling the facility planning problems. That detritus or other pollution that was more likely to occur in a
means, by having a number of successful cases, useful waterway with little flow.

24 1994-95 Annual Issue of IIE (HK)


Facility Planning for a Gas Manufacturing Plant
I
(iv)HKO did not wish to see that after the town development was the viability of each candidate site, the total delivery costs from
completed, public complaints about the existence of HKO each site to the five areas are calculated and compared. Based
factory would force HKO to move out of the present site. on the the data. it is found that (new) Tseung Kwan O gives
If HKO were to remain in this site. the company had to face the lowest total delivery cost for gas cylinders.
the above impacts. It was very difficult to measure the importance
or the extent of the above impacts. Also. it was not all dear For the delivery of bulk liquids. the relative unit costs from
at that time whether the volume of business would increase or Tai PO to the three candidate sites are calculated. Also, reliable
decrease in the future. There is also a number of problems data is obtained from the Distribution Department. Again, the
associated with relocating the plant, e.g. the uncertainties due to cost from Tai PO to (new) Tseung Kwan O is the lowest.
the change in technologies and the impact on labour relations
if the new site location was significantly away from Tseung Other Limitations
Kwan O. Finally. the management decided to go ahead due to Cylinder transport across barbour. Compressed gas cylinders
the following reasons: are classified as Dangerous Goods (DG). There are restrictions
in transporting cylinders across the harbour. Trucks are not
(i) better safety could be achieved in the new plant: allowed to enter crass harbour tunnels. Ferry service for DG
(ii) considerable profit could be derived by n-developing the trucks is restricted to one trip per day and moreover, advance
hooking is required. Therefore, HKO requires essentially a site
existing piece of land into a residental and commercial area.
with sea front access so that cylinder delivery to Hong Kong side
Choice of Plant Location and outlying islands can he made through barges.

HKO entered into deep discussion with the Territory Retail customers. There are some retail customers who come
Development Department of the government to see the viable directly to the factory for cylinders. This has to be considered
location for the new plant. HKO understood that the government during the selection of new plant site. Too remote an area will
preferred to have this kind of chemical processing plant to be create difficulties for these customers.
located inside an industrial estate, or in some rural areas like
Castle Peak. It then approached the Hong Kong Industrial Estate
Supply. of labours There will bound to be labour turnover
Corporation (HKIEC) to see the possibility of relocating the plant
to one of their in dustrial estates. From HKEIC, HKO recognised whenever there is plant relocation. but the extent will heavily be
the following facts: dependent on n-here the new site is. This is particularly a
problem for HKO. HKO handles a lot of dangerous goods and
the labour force requires longer periods of training than for other
(i) All the sites in the Tai Po industrial estate were occupied. industries If the company loses a large number of labour after
(ii) Suitable sites were available in the Yuen Long industrial relocation. production will be seriously affected. Such a situation
estate. is the last thing the company would like to encounter. To the
same extent. the new location cannot be at a too remote area
(iii)There was going to be a third industrial estate. the Tseung where recruitment of new work force is difficult.
Kwan O industrial estate. which was under reclamation. The
land would be available in 1995.
Major Issues in Managing the Plant
(iv)To select a site in Castle Peak, HKO would need to enter
substantial negotiation with the government.
Relocation Project
Great care has to be taken over the planning of the relocation
HKO already had a second factory in the Tai PO industrial process. Inadequate preparation of the movement process and
estate in 1991, which consisted of a Carbon dioxide plant and an of the running-in of the new plant can unnecessarily delay
Air separation plant. The remaining area. however, was not exploitation of the full potential of the investment. Cash flows
large enough for accommodating all the facilities currently in and profitability n-ill suffer. Managing projects of this scale, the
Tseung Kwan O. HKO therefore needed to decide between number of detailed studies and tasks involved has to be legion.
Yuen Long, (new) Tseung Kwan O and Castle Peak as its future The most important ones, among many others, include project
new site. There were several factors to consider but the scheduling, budget consideration, land acquisition, the future
transportation costs stood out as the most important. use of the existing site, the set-up of the project team, new office
location: and the codes of practice established for fire protection
Transportation Costs and safe handling of gases. The followings are just a few that
For the three candidate sites, the costs of production (material deserves more discussion.
and labour) are essentially the same. The only major diference is
due to the cost of delivery of the products, which include gas Process plants. The plants consist of hydrogen, dissolved
cylinders and bulk liquids. The gas cylinders are delivered from acetylene. nitrous oxide, compressed air, carbon dioxide, air
the new site to the five areas including Kowloon, Hong Kong, New separation. and cylinder filling. For each plant, detailed study is
Territories (West), Outlying Islands and to the Tai PO plant. For conducted to investigate its present state, the effect of relocation
bulk liquid delivery, the cryogenic liquids (oxygen ant. nitrogen) on it and the actions that will be taken. Take the hydrogen plant
will be delivered from the Tai PO plant to the new plant. as an example. Its production unit has been used for over thirty
years and it is the right time to upgrade its technology to expand
Since the transportation cost is a significant consideration for its capacity to cope with the expanding market. However,
choosing the new site, reliable data is required to allow its relocation of the existing production unit requires at least ten
calculation. For the delivery of gas cylinders, the cost of delivering working days The company cannot afford such a long shutdown
N cylinders from site A to site B equals to C x N, where C’ is the period because the market demand is high but the buffer stock
cost for delivering one cylinder. The values of C and N are is relatively low.
obtained from the Distribution Department of HKO. To compare

1994-95 Annual Issue of IIE (HK) 25


Facility Planning for a Gas Manufacturing Plant

Safety One of the HKO's overriding task is to ensure safe Altough both the flow and non-flow relationships are
operation of its plants. Its dealing with numerous dangerous identified independently, there are situations where they can be
goods and processes cannot fail to make this point more succinct. used together. These two types of relationships maybe combined
For the existing plaints. HKO has already followed a number of to form a final activity relationship diagram. The purpose of such
standards and codes of practice from the Industrial Cases a diagram is to depict spatially the relationships of the activities.
Committee of Australia. thte National Fire Protection Association It has nodes a the activities and links connecting those nodes
of USA and the British Compressed Gases Association. Now. to as the closeness ratings. However the combination of these
adopt new techniques and deal with newly developed situations. quantitative and qualitative values is a difficult problem from a
a number of safety studies are also made which include the decision theory viewpoint. Common sense must be resorted to
Hazard operability (HAZOP) studies. the environmental impact resolve impractical configurations. The activity relationship
assessment (EIA), and the quantitatively risk assessment (QRM). diagram is further enriched by the space requirements of the
activities to form the space relationship diagram
Facility Design and Systematic Layout Block plan Based on the space relationship diagram, a
Planning block plan describi ng themacro layout of the plant can be
The next stage in facility planning comes the design of the formed. This is essentially a search process which can be done
facility which consists of designing the structural design of the manuatlly or by means of some computer programs. When
factory, layout design and design of the material handling system several block plan have been generated. they are compared
This paper mainly deals with the plant layout aspect which seeks against a sefe of criteria(e.g. economy of cylinder transport and
to obtain an optimum arrangement of the gas plant including safety) and the "best'' one is selected.
production, office and other non-productive activities Also, in
the gas plant which concerns with continuous production flow Computer Aided Layout Planning
and steady demand. the materials handling issues will not be
The search phase of SLP should try to generate as many
discussed in great detail here.
candidate lay outs as possible for evaluation. By generating more
alternatives, the chance of getting a good one will be better.
A major step in designing the gas plant is to determine its However, typical layouts usually consist of numerous activities
physical layout. A very popular approach called the systematic and it will be time consuming to generate the layout without any
layout planning. or SLP, has been developed by Muther [MUT aids As such. computer programs assisting this process have
73]. SLP is an effective and general plant layout design been devised. Essentially. there are two types of such programs:
methodology. As such, it has a broad application areas including construction and improvement. The construction type generates
manufacturing and office activities. SLP consists mainly of three a layout straight from the activity relationship chart, space
phases, namely analysis, search and evaluation. Before the SLP requirement and shape. Examples of the construction type of
proper. the essential data have to be collected. which include layout program are ALDEP and CORELAP, among others. The
P(roduct). Q(uantity). R(outing). S(ervice) and T(ime). improvement type. on the other hand. starts with a layout and
tries to improve it by interchanging the locations of the activities.
The first phase of SLPstudies the various relationships between The criteria for such improvement is usually the transportation
the activities (or departments). Essentially, there are two major costs. An example of the improvement program is CRAFT.
types of relationship of concern. These include the flow
relationship and the activity relationship. The stucy of flow
relationship is particularly important for systems with significant Layout Design of the Gas Plant
material flow between activities, e.g. storage. processes and The design of the gas plant layout illustrates the application
warehouse. Design effort should be made to minimise and of SLP and computer aided plant layout techniques. For a
simplify the flow so that the transportation costs will be reduced complete description of this example, please refer to Chui [CHUI
and production control will be facilitated. There are several 94].
techniques for analysing and representing the flow of these
systems. The appropriate method chosen depends on a study Data Input. For the new facility, forty one major activities
of the production variety and quantity (P-Q analysis). Flow are classified. The data for each activities are collected which
relationship can be measured directly and is therefore includes the area requirement, production capacity. the
quantitatively in nature. equipment contained within the area, the utilities required and
the constraints imposed. The information on these constraints
The activity relationship, on the other hand, has a qualitative is crucial to the determination of the activity relationships.
nature and represents the various interactions amongst the
activities. Examples of such interactions include organisation, Activity Relationships. In this example which does not
control, and potential hazards if two activities are close to one involve substantial quantifiable material flow, only the activity
another. The study of activity relationships is crucial ''or facilities relationships are studied. Every pair of the activities are examined
having little flow but significant communication and organisational and a closeness rating is assigned to it. When evaluating activity
interrelations” [TOM 84] The tool for measuring the activity relationships for N activities, there are N(N-1)/2 such evaluations.
relationships ISthe activity chart. Each entry in the chart consists In order to reduce the amount of work, particularly during the
of a closeness rating and the reason of assigning that value. The initial design stage. some activities having very close relationships
alphabets A, E, I, O, U and X are used for the closeness rating. are grouped together. For example, the Hydrogen production
An A rating suggests that it is absolutely desirable for two plant (01) and Hydrogen filling & storage (07) are grouped
activities to be located next to one another. On the other hand, together under "Plant - Hydrogen”. As a result, the following
a U rating least significance, E, I, and O are intermediate values. new groups are formed:
In addition, an X rating denotes absolutely undesirable for
closeness.

26 1994-95 Annual Issue of IIE (HK)


Facility Planning for a Gas Manufacturing Plant
I
Computer-Aided Layout Planning. In generating alternative
lay-outs. the computer- program CORELAP (Computerised
Relationship Layout Planning)is also used. Unlike other layour
planning programs CORELAP works in a deterministic manner.
That means. with the same set of data input, it always comes uP
with the same answer In order to have alternative layouts, one
may r-r-arrange the input data (e.g. interchanging the positions
of two activities in the activity relationship chart) or to modify
the shapes of the departments slightly.

Etaluation. By using SLP and CORELAP, a number of layout


alternatives are generated The selection of he optimum layout
means the selection of the design that results in the most
favourable compromise among competing criteria These criteria
are listed below. together with the relative importance ratings.

Criteria Raring

Economy of cylinder handling 10


Safety 8
Ease of supervision 6
Room for expansion 5
Flow of raw material 3
Overall layout 2
Convenience 1

Each of the layout alternatives is rated against these criteria.


Points of 3 (high). 2 (medium) and 1 (low) are given. The layout
alternative shown in Fig 2 is the optimum one whereas the
layout generated by CORELAP scores very highly. Although the
macro-level of layout design has been worked out, the derailed
or micro-level design is still underway. Finally, approval must
be obtained from management.

Figure 1: Activity Relationship Chart


Conclusion
Generation of Various Layouts for
Facility planning is a major undertaking that requires
Evaluation substantial resources and careful planning. HKO, having the
Having analysed the activity relationships and then obtained necessary human and financial resources, sets an example of
the space relationship diagram, alternative layollts can be tackling such a problem in a thorough manner. The choice of
generated, either manually or using computer-aided layout the location of the new plant depends on a number of factors
planning programs. At thisstage, a number of practical limitations including transportation costs, environment, labour,
must also be considered. For example, shape and size of the administrative and other management decisions. It does not
site, location of the main entrance and the sea front access, seem that a single mathematical model can provide the complete
among others. Using the space relationship dia. gram as a solution. On the issue facility design, the well known SLP is
guideline, the space templates are modified and adjusted, and employed to carry out the macro level design and the computer-
the relative locations of the activities are shifted as necessary to aided layout planning program CORELAP is also used. At this
accommodate the practical limitations. Three alternative layouts stage, the final details have yet to be finalised.
are developed and one of them is shown in Fig 2.
References
[CHUI 94] W.C. Chui, ''Facilities Planning: Relocation of a Gas
4lanufacturing Plant'' MSc Thesis, Hong Kong University
1994
[FRA 92] R.L. Francis, L.F. McGinnis Jr, J.A. White, FACILITY
LAYOUT .AND LOCATION: AN ANALYTICAL APPROACH,
2nd ed., Prentice Hall International 1992.
[MUT 73] R. Muther, SYSTEMATIC LAYOUT PLANNING,
Cahners Books 1973.
[TOM 84] J..4. Tompkins & J.A. White, FACILITIES PLANNING,
John Wiley & Sons 1984.
Figure 2: Layout Alternative in the form of a block plan

1994-95 Annual Issue of IIE (HK) 27

You might also like