You are on page 1of 5

Impacts of Substation Transformer Backfeed at High

PV Penetrations
Robert Mack, MD Sakib, Samir Succar
ICF
Fairfax, VA, USA – 22031
Bob.Mack@icf.com, Md.Sakib@icf.com, Samir.Succar@icf.com

Abstract—Increasing amounts of photovoltaic penetration substation power transformer. This phenomenon is knows as
(PV) on the electric distribution system have given rise to a substation transformer backfeed.
number of challenges for electric utility companies. One of the
more frequent issues utilities will have to address is the potential The distribution system’s configuration will greatly affect
for a large amount of substation transformer backfeed stemming how much of a concern substation backfeed is for each location.
from reverse power flow on distribution circuits. Excess PV Distribution systems in a network configuration typically have
output on the distribution system during periods of minimum the necessary protection schemes already in place for allowing
daytime loading causes a number of issues for utility planning and backfeed because they are designed with two way power flow in
operation, such as temporary overvoltage conditions, the need for mind [2]. Radially fed distribution systems that are tapped from
protection schemes modifications, and equipment failure from an a single source on the transmission network are more susceptible
increase in voltage regulation operations. The aim of this paper is to the substation equipment issues related to excess distributed
to summarize the considerations related to substation transformer generation because they are typically designed for power flow
backfeed, how it affects common distribution system from the transmission system only. The existence of reverse
configurations, and to also touch on opportunities for mitigating power flow on radially fed substations has exposed a number
the impact of these issues. design challenges to substation equipment. All these design
Keywords—Backfeed, substation transformer, minimum changes will also affect future planning and operation of the
daytime loading, photovoltaic. electric grid. This need to retrofit substations that have been
designed for unidirectional power flow to be upgraded to allow
I. INTRODUCTION for two-way power flow have also raised a number of economic
The increasing penetration levels of distributed generation issues related to the cost of these upgrades [3].
(DG) with variable output such as solar PV, and coincidence of Backfeeding through substation transformers can also result
these systems’ max output with minimum daytime loading, have in significant system losses because of the winding ratio bias of
already produced observed cases of substation transformer the transformer [4]. The later sections will try to describe the
backfeed on utility systems [1]. Substation transformer backfeed different system issues due to substation transformer backfeed
has a number of planning and operational implications for and will also present a few possible measures to eliminate
electric utilities such as the increased risk of sustained over- substation transformer backfeeding.
voltage conditions during a line to ground fault that could be
potentially damaging to substation equipment i.e. exceeding III. WHEN SUBSTATION TRANSFORMER BACKFEED IS LIKELY
substation equipment’s thermal rating. Maintaining substation TO OCCUR
voltage regulation equipment has also become an increasing
PV systems will only contribute to backfeed if the total
concern, as a result of the increased frequency of load tap
changer (LTC) operations due to PV variability with attendant installed capacity of PV on a feeder exceeds its minimum
impacts on equipment life and utility costs. daytime load. Otherwise power will continue to flow from the
high voltage transmission/sub-transmission system to the
II. SUBSTATION TRANSFORMER BACKFEED distribution system. Utilities typically review the minimum load
Substation transformer backfeed is most likely to occur of a substation transformer during normal system conditions and
during periods of minimum daytime loading because of the also during an N-1 contingency scenario (i.e. adjacent feeder on
coincidence between the peak output timing of PV modules and the same bus locked out) to determine when additional
daytime light load conditions. Under these conditions, localized protection may be needed. If the aggregate generation is equal
load is insufficient to consume all of the output from the local to or greater than this minimum value identified, additional
PV capacity. It is also important to note that although PV transformer protection may be required.
generation is largely the cause of substation transformer
backfeed, other forms of DG with variable output can contribute For stations where loading information is not readily
to the range of issues described here. As a result of this available, utilities would use an extrapolated percentage of the
condition, power flows in the reverse direction towards the transformer’s peak load to derive the minimum daytime loading
substation, as opposed to from the substation to the distribution data. Since maximum output for solar PV systems occurs during
feeders. Excess power then travels backward into the daylight hours, the daytime minimum loading is the most
transmission system from the distribution system via the appropriate metric for assessing the potential for backfeed

978-1-5386-2212-4/17/$31.00 ©2017 IEEE


(without seasonal daylight adjustments) and is defined between backfeeding through substation equipment, the LDC portion of
8AM and 4PM [5]. the line-tap changer will turn off. If the LTC cannot sense
reverse power-flow, the LTC will continue to incorrectly
IV. SYSTEM ISSUES DUE TO SUBSTATION TRANSFORMER regulate the voltage on the distribution system, causing voltage
BACKFEED
violations on the distribution system resulting from incorrect
The extent to which substation transformer backfeed affects measured current [10]. As current flows in reverse through the
distribution system planners and operators will vary greatly transformers, the bi-directional aspect or abilities of the LDC
depending on the existing system configuration. For example, must be disabled. The existing LTC will not be able to sense
a substation with Wye-Wye connected transformers will not be reverse power flow and could cause adverse voltage conditions
susceptible to temporary overvoltage conditions to the same on distribution feeders as well as upstream on the sub-
degree as a Delta-Wye connected transformer, even if both are transmission level as a result of incorrect voltage regulation.
radially fed from the transmission system. Existing voltage
regulators, protection, and control equipment on both the Figure 1 depicts the impact of substation transformer
distribution circuits and the substation itself will also determine backfeed on voltage regulation [3]. The figure shows how the
the necessary upgrades to allow for some, or no, amount of real power (kW) is reversed when the phenomenon of backfeed
backfeed. occurs and how it affects the voltage regulator. Because of the
reverse flow, the voltage regulator regulates voltage in the
A. Temporary Overvoltage Conditions
reverse direction. This might result in very low voltage
Even in instances where excess PV is not an issue, the conditions at the tail end of the circuit. In order to mitigate
existence of PV on a circuit can cause temporary overvoltage equipment lifespan reduction and incorrect voltage regulation
issues for substations that are radially tapped off the and advanced LTC transformer can be used to allow for greater
transmission system. For substations without the necessary
control over the voltage regulation operations. Advanced
protection schemes to accommodate two way power flow, a
single line to ground fault for a substation with PV runs the risk regulating controls would allow the utility to set the LTC
of damaging sustained overvoltage conditions [6] [7]. For settings to either block operations, or begin regulating in reverse
example the sustained overvoltage condition might cause upon detecting reverse power flow [11].
substation equipment such as buses and CTs to fail [8]. For
temporary overvoltage conditions as a result additional zero-
sequence current feeding into a ground fault, surge arrestors are
particularly vulnerable. They can typically handle transient
over-voltage conditions, but sustained over-voltage conditions
can result in equipment failure [9]. Installing an additional
grounding transformer would be one of the most common
solutions for limiting the additional zero-sequence current
contributing to the ground fault, however its effectiveness has
been debated and other solutions such as hardware and control
modifications have been also suggested [2], [6].
B. Load Tap Changer
Most distribution transformers use analog tap changers with
Line Drop Compensation (LDC) to regulate the voltage along
the distribution feeder. LDC regulates the voltage at a point on
a distribution system’s line or feeder downstream from the
transformer or regulator bus. LDC is used to make sure that the
Fig 1. Voltage regulation profiles based on regulation direction
end of the feeder does not encounter unacceptable steady-state
voltage under peak loading conditions. The control internally
calculates the line voltage drop between the controlled bus and C. Equipment Life
the load center using the input current (including the phase Large amounts of reverse power flow can also reduce the life
angle) and the R and X values. The control then automatically span of distribution system equipment by increasing the
adjusts the band-center of the load tap changer (LTC) to frequency of operation, even if the amount of reverse power
compensate the local voltage by the calculated voltage drop (If flow is not great enough to cause backfeed through the
the band-center setting is 119 V and the LDC voltage drop substation transformer. Variability in the amount of substation
calculation is 2 V, the new band-center will be 121 V. This transformer backfeed can increase cycling on the tap changer by
causes 121V to appear at the load center) [10]. requiring changes in the transformer tap position in response to
impacts of changing PV output and circuit loading. Increases in
LDC can magnify voltage impacts when combined with tap changer cycling increases will have significant impacts on
other regulation equipment at high penetration of PV. Most the expected equipment life of impacted LTCs. The number and
analog tap changer control systems cannot sense reverse power frequency of physical operations directly impacts the lifespan
flow on a substation transformer. In the event of power expectation of this equipment [12]. For LTCs that on average

978-1-5386-2212-4/17/$31.00 ©2017 IEEE


experience five daily operations, increasing LTC operations by does not exceed 100% of the service load and cause backfeed
just two operations a day could reduce expected equipment [15].
lifespan by approximately 40-50% [1], [12].

The same concept of a reduced life span due to the


intermittency of PV generation applies for voltage controlled
capacitor banks as well. The capacitor banks might be taken
offline and online within very small time-periods, similarly
increasing frequency of cap-bank operations and reducing the
life-span of the equipment.
D. Protection and Relaying
As PV penetration increases on the distribution system, basic
protection elements and design philosophies, may no longer
ensure the security and proper clearance of faults on distribution Fig 2. Minimum Import Relay diagram
networks. The prominence of radially configured systems has
led to many standardized and industry accepted protection Reverse power flow relays (RPR) (32) disconnect a PV
schemes. Higher penetrations of PV introduce the possibility system if power begins flowing from the distribution system to
that bi-directional power flow might exceed standard design transmission system. Typical RPR settings produce lock out
criteria thresholds set by utilities and can also lead to sustained when they detect power ceasing to flow or begins to flow in the
fault currents resulting in a loss of relay co-ordination and reverse direction [13]. To estimate the power level, the relay
potentially damaging overvoltage conditions. measures current and power factor. As soon as the reverse
High PV penetration might also affect the transmission power level increases above the threshold, the relay triggers a
system’s distance protection and will need to be reviewed. The trip after a predefined time delay to prevent nuisance tripping.
transmission side of a utility substation transformer is normally Current RPR can also reduce nuisance tripping by measuring if
connected in a delta configuration. A 59N relay may be used to a signal is noisy or unstable. RPR will automatically re-set once
detect the L-G faults on the transmission system and a the power level falls below the set point minus the differential.
directional over current relay can be used to identify ungrounded MIR, CR, and RPR eliminates backfeed based on real- time
faults on the transmission system. monitoring. However, since RPR require a time-delay in
tripping the PV, it cannot be set for instantaneous operation.
Communication is one of the major challenges utilities face
with higher PV deployment. Existing communication and B. Install a dynamically controlled inverter
network infrastructures were not designed to support bi- A dynamically controlled inverter (DCI) will monitor the
directional power flow, non-radial feeds etc. A reliable and amount of power flowing into the customer’s location using
secure means of communication needs to be maintained between current transformers (CTs) and reduce the amount of PV on the
all devices. Care should be taken when updating, configuring,
feeder if the load decreases below a predetermined threshold.
managing and maintaining communication infrastructure both
The power flow is monitored at the main PCC (point of
for the PV and utility owned assets.
common coupling) and a control signal is sent to the PV
V. PREVENTING SUBSTATION TRANSFORMER inverter to initiate a reduction of output power if required [13],
BACKFEEDING [14]. This approach will allow for the interconnection of larger
PV systems since it enables curtailment and ramp down to
A. Relaying on secondary networks ensure reliable operation. The ability to curtail generation also
When backfeed is a concern on secondary distribution allows for the PV to generate within the system limits, without
networks, a minimum import relay (MIR), comparative relay having to reduce output to zero like in the relaying solutions.
(CR) or reverse power flow relay (RPR) can be used to mitigate
concerns. Minimum import relays disconnect the PV from the The DCI system leverages the information obtained from
distribution network if the power flow from the utility drops current transformers (CTs) to sense power flow and verify that
below a certain threshold value [13], [14]. This is one way to a minimum threshold of power is maintained from the grid,
mitigate backfeed conditions. An example utility practice of through the distribution transformers. The inverters will track
this solution would be that the, “MIR relay shall trip or curtail the load on each of the three phases and curtail power from the
PV generation below set limits when retail customer’s service PV system, when the generating PV system current reaches
load drops to less than 200% of PV system AC rating” [15]. 95% of the current on any phase [16]. DCI systems can also be
Figure 2 illustrates aspects of the design philosophy of MIR utilized for new smart grid-enabled distribution systems where
[15]. MIR relays are also especially suited for spot networks PV power contribution during certain periods will need to be
experiencing high PV penetration [14]. For instances where PV curtailed or ramped down.
generation can be accommodated up to the service load, a
comparative relay can be installed to ensure that PV generation

978-1-5386-2212-4/17/$31.00 ©2017 IEEE


C. Relays for Fault Backfeed Detection VI. INCREASING MINIMUM DAYTIME LOADING
Increased PV on the distribution system can significantly In the case where some degree of substation transformer
impact existing protection schemes, since current protection
backfeed is allowed, it is almost always largely dependent on
relays installed at the substation may not have directional the ratio of PV generation output to the daytime minimum
capabilities. If the existing station relays do not have bi- loading. Although increasing the minimum daytime loading
directional protection, existing protection units may need to be
will not address concerns with PV contributing to fault currents,
replaced/upgraded to include bi-directional relaying (67) [17]. increasing the daytime minimum loading would allow the grid
To identify the direction of a fault, a relay requires a reference to accommodate more PV as the would-be excess generation is
to compare its line current to. This is known as the polarizing
consumed by the increased load [19], [20]. There are a number
quantity. The polarizing quantity is a reference point that the of current and future technologies that could be leveraged to
relay compares the system condition against and will not increase minimum loading in a way that is beneficial to the grid
change direction regardless of the fault location. Most in a number of ways. These technologies would include;
directional overcurrent relays have two components, a energy storage systems, and dispatch-able loads (commercial
directional component, along with an overcurrent component.
load management, smart electric vehicle charging) [19-21]. If
To activate the “Trip” setting of the relay, the magnitude of the the mentioned technologies could be used to increase minimum
overcurrent should exceed the threshold limit specified for a daytime loading it could potentially address concerns with
certain time duration, and the direction of the fault must be
substation transformer backfeed, peak load reduction, and also
within the pre-set ‘trip’ region. The 67/51P (Directional Relay increase the hosting capacity for areas where the lack of reverse
with Phase Overcurrent protection) or 67/50P (Directional power flow enabling technologies are the greatest constraint.
Relay with phase instantaneous overcurrent protection) relays
can be used to detect backfeed from the transformer’s low side It should be clear that energy storage systems and other
to the high side. These relays operate by measuring current responsive loads by no means replace the functionality of the
flow on the transformer [18]. If the 67/50P element is used, a needed protection schemes to compensate for two way power
slight time delay should be introduced to the 50P element to flow. Energy storage and demand response practices could
account for any chance of transient backfeed during load only reduce the need for costly upgrades by alleviating reverse
swings or when paralleling with other transformers [18]. power flow to an acceptable amount. The separation of
functionality between the necessary protection scheme
Additional voltage transformers and potential transformers upgrades and adopting the aforementioned technologies is
(PTs) may need to be installed since, zero sequence voltage critical because the cost of investing in either of these system
(3V0) is obtained through the broken-delta secondary of upgrades can vary by a large amount.
grounded-wye transformer configuration [17]. Modern
advanced micro-processor based relays are capable of Summary of Substation Transformer Backfeed Mitigation Methods
calculating 3V0 without any additional PTs or VTs.
Minimum Import Relay (MIR) Disconnects PV if the power flow from the utility
drops below a preset threshold value. Applicable
To summarize, in order to prevent PV from backfeeding into to networked distribution systems and spot
a fault in the distribution system, certain relays can be used: networks.
Reverse Power Flow Relay Disconnects PV if the power flow from the utility
(RPR) drops to zero or reverses direction. Applicable to
• Directional/Reverse power (32P) for irregular power flow. networked distribution systems and spot
32P should not be set for instantaneous operation and there networks. RPR can trip PV generation below set
limits when retails customer’s service load drops
should be a time delay setting to avoid nuisance tripping to less than 200% of PV system AC rating
(mentioned above)
Dynamically Controlled This inverter controls the output of the PV system
• Directional Elements (67/51P, 67/50P, 67/51N, 67/50N, Inverter (DCI) inverter(s) and is applicable to spot networks.
59N for zero sequence voltage) for fault detection and DCI can be used as a secondary measure to insure
that a minimum level of power flows back onto
backfeed protection the spot network and can also curtail PV output at
certain times or conditions.
Relays for Fault Backfeed Typically 67 or 51V relay can be used to detect
Detection supply fault and initiate PV separation. The
choice of a device for removing ground fault
backfeed should be a function of the type of
primary winding on the interconnection
transformer. For a grounded primary transformer
winding, a 51N neutral overcurrent relay or, in
some cases, a 67N ground direction relay should
be selected. For ungrounded interconnection
transformers, neutral overvoltage relays (59N,
27N relays) provide detection of supply ground
faults.

978-1-5386-2212-4/17/$31.00 ©2017 IEEE


VII. CONCLUSION [9] R. Walling, "Grounding and Overvoltage Requirements
Substation transformer backfeed will be an increasingly for Distributed Generation (Wind and Solar)," IEEE-
frequent issue utilities will need to address. The distribution PES.
systems will require upgrades to either prevent PV from [10] J. H. Harlow, "Load Tap Changing Control," Beckwith
backfeeding into the substation altogether, or to allow backfeed Electric Company, North Largo.
at a substation level while maintaining system safety and [11] Jauch, Tom; Beckwith Electric Company, Inc.,
reliability. Utilities will need to strike a balance on the amount "Maximizing Automatic Reverse Power Operations With
of allowable backfeed to accommodate more PV on the grid, LTC Transformers & Regulators," IEEE, 2005.
and the cost of investing in reverse power flow enabling
[12] D. Savenije, "SDG&E: If you're not prepared for the
technologies. The electric grid will now have to be designed
for bi-direction powerflow on the distribution system and if change, it's too late," Utility Dive, 24 February 2015.
[Online]. Available:
backfeed is allowed, it should be under safe and reliable utility
http://www.utilitydive.com/news/sdge-if-youre-not-
practices to avoid the potential of creating an uneconomical,
prepared-for-the-change-its-too-late/366979/. [Accessed
oppositely located centralized generation system on the
26 October 2016].
distribution side, that frequently feeds upstream out of the
substation. [13] M. Coddington, B. Kroposki, T. Basso, K. Lynn, D.
Sammon, M. Vaziri and T. Yohn, "Photovoltaic Systems
Interconnected onto Secondary Network Distribution
VIII. REFERENCES Systems - Success Stories," NREL, 2009.
[14] K. Anderson, M. Coddington, K. Burman, S. Hayter, B.
[1] E. Stewart, J. MacPherson, S. Vasilic, D. Nakafuji and T. Kroposki and A. Watson, "Interconnecting PV on New
Aukai, "Analysis of High-Penetration Levels of York City's Secondary Network Distribution System,"
Photovoltaics into the Distribution Grid on Oahu, National Renewable Energy Laboratory, Golden
Hawaii," NREL, 2013. Colorado, 2009.
[2] R. Salcedo, X. Ran, F. de Leon, D. Czarkowski and V. [15] Xcel Energy, "NSPM Network Connected PV
Spitsa, "Long Diration Overvoltages due to Current Recommended Practice," Xcel Energy, 2014.
Backfeeding in Secondary Networks," IEEE [16] M. H. Coddington, D. B. Kroposki, T. Basso, D. Berger,
Transactions on Power Devlivery, Vol. 28. No. 4, 2003. K. Crowell, J. Hayes, NREL and Peak Power Engieering,
[3] J. D. McDonald, B. Wojszczyk, B. Flynn and I. Voloh, Inc, "Performance Of A Dynamically Controlled Inverter
"Distribution Systems, Substations, and Inegration of In A Photovoltaic System Interconnected With A
Distributed Generation," in Electrical Transmission Secondary Network Distribution System," IEEE, 2011.
Systems and Smart Grids, Springer, 2013, pp. 8-68. [17] G. Antonova, M. Nardi, A. Scott and M. Pesin,
[4] Siemens Energy Sector, "Power Engineering Guide, "Distributed Generation and Its Impact on Power Grids
Edition 7.0 Chapter 5," Siemens Aktiengesellschaft and Microgrids Protection," IEEE, 2012.
Energy Sector, Erlangen Germany, 2012. [18] J. G. Andrichak and S. C. Patel, "Polarizing Sources For
[5] O. Comstock, "Solar photovoltaic output depends on Directional Ground Relays".
orientation, tilit, and tracting," Today In Energy, 19 [19] B. Palmintier, R. Broderick, B. Mather, M. Coddington,
November 2014. [Online]. Available: K. Baker, F. Ding, M. Reno, M. Lave and A.
http://www.eia.gov/todayinenergy/detail.php?id=18871. Bharatkumar, "On the Path to SunShot: Emerging Issues
[Accessed 26 10 2016]. and Challenges in Integrating Solar with the Distribution
[6] H. Ghoddami and A. Yazdani, "A Mitigation Strategy for System," NREL, Golden, CO, 2016.
Temporary Overvoltages Caused by Grid-Connected [20] M. E. Alam, K. M. Muttaqi and D. Sutanto, "Distributed
Photovoltaic Systems," IEEE, 2015. energy storage for mitigation of voltage-rise impact
[7] V. Madani, R. Das, F. Aminifar, J. McDonald, S. S. caused by rooftop solar PV," IEEE, 2012.
Venkata, D. Novosel, A. Bose and M. Shahidehpour, [21] Idaho National Laboratory, "What is the Controllable
"Distribution Automation Strategies Challenges and Electrical Demand from Residential EVSE in the San
Oppurtunities in a Changing Landscape," IEEE, 2015. Diego Region," The EV Project, Idaho Falls, 2015.
[8] R. F. Arritt and R. C. Dugan, "Distributed Generation
Interconnection Transformer and Grounding Selection,"
IEEE, 2008.

978-1-5386-2212-4/17/$31.00 ©2017 IEEE

You might also like