Professional Documents
Culture Documents
(Week 2)
by Dr Mohammad Fardipour
Subject: Topographic Engineering CVE20001
Reading/Lecture slides reference: Surveying’ (1998-7th edition) by Arthur Bannister, Stanley Raymond & Raymond Baker
2
Levelling (definition)
Levelling is the operation required to compare the
height of points on the surface of earth
Height of a point can only be determined relative to
another point or surface.
3
Height Datum
A level surface is a surface of constant elevation that
is perpendicular to a plumb line at every point. It is best
presented by the shape that a large body of still
water would take if it were unaffected by tides
In practice the mean sea level is taken as the
reference level surface or datum
Datum makes national and international comparisons of
heights possible
4
Some terms used in levelling
A Vertical Line is a line parallel to the direction of gravity at any
given point . Elevation of points on ground (e.g. A or B) are
measured along relevant vertical lines relative to datum.
Level line is a curve which is at a constant elevation relative to
mean sea level (or datum).
Horizontal line is tangential to the level line at any particular
point. It is perpendicular to the direction of gravity at that point.
B Elevation of point B
5
Australian Height Datum (AHD) (Reference: Wikipedia)
The Australian Height Datum is a geodetic datum for altitude measurement in Australia.
According to Geoscience Australia, "In 1971 the mean sea level for 1966-1968 was assigned the
value of 0.000m on the Australian Height Datum at thirty tide gauges around the coast of the
Australian continent. The resulting datum surface, with minor modifications in two metropolitan
areas, has been termed the Australian Height Datum (AHD) and was adopted by the National
Mapping Council as the datum to which all vertical control for mapping (and other surveying
functions) is to be referred."[1][2]
References:
Australian Height Datum Geoscience Australia
6
Basic equipment required for levelling
∆ℎ
24
Measuring height difference
e e
26
Collimation error
• If the backsight and foresight distances are not equal, the measured height difference
between two points of A & B is affected by the collimation error.
• The greater is the distance to the staff the larger is the effect of collimation error
FS BS
e
A
27
Procedure to conduct two peg test
The Two Peg Test is to be done before the start of any survey job to make sure the time, energy
and cost spent on the project is not wasted due to using an out of calibration level equipment.
28
Two peg test- Standard booking
Intermediate
Backsight (BS) sight (IS) Foresight (FS) Remarks
∑BS ∑FS
∑BS-∑FS=error
29
Practical recommendations
If 0< error <5mm
With this level of generally accepted error, it is adequate to visually have the same backsight and foresight
distances to achieve a higher level of accuracy
BS IS FS Comment
3.649 3.652
3.649-3.652=-0.003
If the reduced level at one point is given (e.g.𝑅𝐿𝐴 = 128.480𝑚), reduced level at the other point
can be calculated using the ‘Rise and Fall’ method :
𝑅𝐿𝐵 =𝑅𝐿𝐴 + a Rise
Example: 𝑅𝐿𝐵 = 128.480 + 1.808 = 130.288𝑚
If level at a point is given (e.g. RL at Point A=128.480) , level at all other points can also be
calculated using the ‘Height of Collimation’ method:
The first staff reading after each level set up is a backsight . So considering the
set up at the first level position above, 2.554m is recorded as a backsight.
note: The very first reading in a level run is usually to a point of known RL.
The last reading before moving the level is recorded as a foresight which is
3.589 corresponding to Level position 1
Alternatively the level run has to start from a point of known RL and end to
another point of known RL
41
Height of Collimation method of reduction
• The height of collimation is updated following each set up by adding the backsight reading on the staff to corresponding RL value (e.g.
50+2.554=52.554m)
• Height of collimation taken away the staff reading gives the RL value at any other points, for instance: RL D= 52.554-3.589=48.965m
• Every time we change the position of the level, a new collimation line is to be calculated (i.e. 48.965+ 1.305= 50.27m)
42
Height of Collimation method of reduction
𝑖𝑓 𝑅𝐿𝐴 = 54.965𝑚
B
𝐻𝑜𝑓 𝐶 = 54.965 + 1.555 = 56.52𝑚
𝑅𝐿𝐵 = 56.52 − −2.535 = 59.055𝑚
Headroom of Bridge:
A
1.555 + 2.535 = 4.09𝑚
45
Application of Levelling:
Apart from the general application as discussed so far
levelling can be made for the purpose of :
Longitudinal sections
Cross Sections
Contouring
Setting out levels
Some of these will be covered in later lecture/field work
practices
46
Levelling for Longitudinal sections
47
Depth of cuts and fills at centre line
The following readings were taken along the centre line of a length of pipeline:
Reduce levels with the rise and fall method and perform all the checks on computations
If the finished pipeline level (Form RL) is to have the elevation of 102m at chainage point 500m with a constant
gradient of 1:200 increasing in the direction of chainage then calculate the depth of cuts and fills at centre line
as required to achieve this.
BS IS FS RISE FALL RL Form RL CUT FILL DIST
3.00 100 0
2.80 1.50 100
1.80 1.70 200
1.40 300
1.20 400
1.10 102 500
1.60 600
2.50 2.00 700
1.20 1.80 800
0.80 2.20 900
0.90 1000
48
Depth of cuts and fills at centre line
105
104
Elevation (RL) in m
103
102
101
100
99
0 100 200 300 400 500 600 700 800 900 1000 1100
Chainage (m)
Existing ground surface Finished pipeline level
49
Depth of cuts and fills at centre line
Reduce levels with the rise and fall method and perform
all the checks on computations
BS IS FS RISE FALL RL Form RL CUT FILL DIST
3.00 100 0
2.80 1.50 1.5 101.5 100
1.80 1.70 1.1 102.6 200
1.40 0.4 103 300
1.20 0.2 103.2 400
1.10 0.1 103.3 102 500
1.60 0.5 102.8 600
2.50 2.00 0.4 102.4 700
1.20 1.80 0.7 103.1 800
0.80 2.20 1 102.1 900
0.90 0.1 102 1000
Thank You