Empire East Corporate Head Office

Alliance Global Tower, Uptown Bonifacio, Taguig City As of March 21, 2018

PUNCHLIST
10TH FLOOR
ITEM NO. AREA PARTY RESPONSIBLE COMMENTS/REMARKS STATUS
-Installation of Graphicote
1 Training Room Pacific Glass/ Triframe Waiting for installation
-Backing (c/o Triframe)
General Storage
2 Razor -Sensor - for checking DONE
Room
3 Pantry Triframe Inc. -Paint on trim DONE
11TH FLOOR
-Rectification of walls near glass door and
4 CNC Area Excell DONE
thermostats

5 Client's Room Excell -Rectification of walls DONE

-Paint on trim
6 Pantry Triframe Inc. -Faucet DONE
-Baseboard
12TH FLOOR
-Alignment of Cabinets - Committed date:
7 OP Excell
Installation of Mohair March 22, 2018
Committed date:
8 Den Excell -Installation of cabinet laminate
March 22, 2018
Committed date:
9 Toilet (ACY) Excell -Change Tiles (wood planks) @ Door
March 22, 2018
-Alignment of Cabinets (installation of hook
and eye) - Committed date:
10 Receiving Area Excell
Installation of tile (near the door) - March 22, 2018
Wire Manager (c/o Triframe Inc.)

11 Lounge Microgen -Door access ID not recognized On-going


Was requested last March
12 Board Room Triframe Inc. -Installation of HDMI Port
29, 2018

EGC Office and


-HR requested for
13 Disbursement Megaworld -Rectification of leak
inspection
Area
Comitted date: March
14 Legal Area Jogging Path -for re-installation
23, 2018
10TH AND 12TH FLOOR
15 Built-in Cabinets Triframe Inc. -Installation of edge bands
ALL FLOORS
For approval of change
16 Razor -Installation of additional CCTV
order
-Supply and Installation of additional
17 Group Perspective Inc. On-process of PR
partition