Existing Conditions
1
Project Timeline & Limits
Safety Gains
Crash Data
nyc.gov/dot 2
QUEENS BLVD PROJECT LIMITS & GOALS
QN CB 3
QN CB 7
QN CB 4
QN CB 2
PROJECT GOALS:
1. Calm the service roads
2. Keep the main line moving (preserve
existing lanes)
3. Reduce roadway shopping
QN CB 5
4. Accommodate all road users &
enhance the sense of place
5. Design based on crash history
6. Complete pedestrian network & QN CB 6
connect neighborhoods
7. Eliminate highway-like design features
QN CB 9
nyc.gov/dot 3
QUEENS BLVD SAFETY GAINS: 2015 - 2016
• No pedestrian or cyclist fatalities on Queens Blvd since implementation
• Pedestrian injuries decreased by 55% after implementation
• Total crashes decreased by 19% after implementation
Crashes and Injuries
One-Year After Analysis, Queens Blvd (Roosevelt Ave to Eliot Ave)
nyc.gov/dot 4
DESIGN UPDATES TO PREVIOUS PROJECTS
Project
Source Feedback Solution
Year
Drivers have difficulty seeing Modified design of stop-controlled
2018 Community oncoming traffic and cyclists at slip lanes to improve visibility for
slip lanes drivers
Traffic Analysis, Congestion near the Queens Installed additional curbside travel
2016 Community Place Mall lane to facilitate traffic flow
nyc.gov/dot 5
QUEENS BLVD 2018 PROJECT TIMELINE
• May 2014: Community Board 6 Resolution Requesting Complete Streets
Study and Redesign of Queens Boulevard
• May 2017: Presentations to Community Board 6 Transportation Committee
& Full Board and vote of support
• June – December 2017: Implementation of 2017 Street Improvement
Project
• September 2017 – April 2018: Street Ambassador On-Site Engagement &
Online Outreach, Merchant and Shopper Surveys, Public Workshop
• May 2018: Presentation to Community Board 6 Transportation Committee
• June 2018: Presentation to Community Board 6 Full Board
• July 2018: Proposed Implementation Start
nyc.gov/dot 6
QUEENS BLVD CRASH DATA
nyc.gov/dot 7
Community Outreach
2
Overview
Survey Responses
Location & Treatment Requests
nyc.gov/dot 8
COMMUNITY OUTREACH OVERVIEW
Project specific outreach conducted September 2017 – April 2018
• Safety workshop with +100
attendees (January 2018)
• Project website with feedback map
& survey (Fall 2017 – Spring 2018)
• DOT Street Ambassador outreach at
+10 locations along corridor (Fall 2017)
• Merchant surveys & shopper
surveys (January and April 2018)
nyc.gov/dot 9
SURVEY RESPONSES: WHO
81% walk on 64% own a car
68% live in
Queens Blvd 45% currently but only 26%
Forest Hills or
regularly, bicycle in drive on
an adjacent
compared to Forest Hills Queens Blvd
neighborhood
52% who drive daily
nyc.gov/dot 10
SURVEY RESPONSES: WHAT
“The traffic for [the left turn onto
“I love the bike lanes. I ride to
Yellowstone] blocks up through the
work almost every day from Rego
previous intersection. Could there be
Park to Bellevue Hospital.”
a longer left turn light cycle there?
nyc.gov/dot 12
Design Proposal
3
Key Design Features
Design Proposal & Updates
Curbside Proposals
Great Streets Capital Project
nyc.gov/dot 13
Continue previous design with
KEY DESIGN FEATURES pedestrian path & bicycle lane
along service road medians
South North
Sidewalk Sidewalk
South North
Sidewalk Sidewalk
South North
Sidewalk Sidewalk
nyc.gov/dot 14
KEY DESIGN FEATURES:
PROTECTED BICYCLE LANE & PEDESTRIAN PATH
• Calm service roads
• Expand pedestrian network
• Allow for safe, convenient bicycle travel
• Organizes roadway for all users and
creates predictable movements
• Creates footprint for Great Streets
Capital build out
Survey respondents are most likely to Eastbound Queens Blvd service road at 63rd Dr,
bicycle on protected bicycle lanes looking east: pedestrian path, buffered bike lane
with vertical delineators, stop-controlled slip lane
nyc.gov/dot 15
KEY DESIGN FEATURES:
MALL-TO-MALL CROSSINGS & PEDESTRIAN SPACE
• Shorten crossing distances Lack of pedestrian space at
• Create new crossings to improve busy intersections
access to pedestrian generators
• Visual tighten wide intersections to
discourage speeding and slow turns Long distances between safe
crossings for pedestrians
Requests to address driver Queens Blvd and Eliot Ave, looking south:
signalized pedestrian crossing, pedestrian space
failure to yield at intersections with granite blocks
nyc.gov/dot 16
KEY DESIGN FEATURES:
STOP-CONTROLLED SLIP LANES
• Create safer vehicle
transitions between mainline
and service road
• Allow for continuation
pedestrian path and bike lane
• Reduce highway-like feel
nyc.gov/dot 17
PROPOSED DESIGN DETAILS:
CORRIDOR WIDE
2018
Continue use of stop-controlled
slip lanes with updated design to
improve transition between main
line and service road
2017
nyc.gov/dot 18
PROPOSED DESIGN DETAILS:
CORRIDOR WIDE Continue pedestrian path
and bicycle lanes against
service road medians
70th Rd
nyc.gov/dot 21
Forest Hills South and Queens
PROPOSED DESIGN DETAILS: Borough President Melinda Katz
requested traffic calming around the
77TH AVE – 78TH AVE Grand Central Parkway Service Road,
77th Ave, and 78th Ave in February
Grand Central Pkwy Service Rd 2018
78th Ave
77th Ave
Add missing
crosswalk at 78th Ave
nyc.gov/dot and Queens Blvd 22
Create designated right
PROPOSED DESIGN DETAILS: turn lane and red
nyc.gov/dot 23
PROPOSED DESIGN DETAILS:
UNION TURNPIKE Contra-flow bike lane
177th St, Manhattan
Markings guide
cyclists across
Queens Blvd
Buffered contra-flow
lane from 80th Rd to
Union Turnpike with
bicycle signal
nyc.gov/dot 24
PROPOSED DESIGN DETAILS: LEFT TURN BAYS
Yellowstone Blvd
Current storage: 4 cars
Proposed storage: 10 cars
Extend westbound left turn bays at
Yellowstone Blvd and at Ascan Ave
to accommodate more vehicles and
improve vehicle mobility
Ascan Ave
nyc.gov/dot 25
CURBSIDE USAGE: EXISTING CONDITIONS
Approximately 4,420’ of
parkable space against
the median (220 spaces)
Approximately 4,280’ of
parkable space against
the curb (215 spaces)
Approximately 575’ of
dedicated truck access
(20 spaces)
nyc.gov/dot 26
CURB USAGE: FEEDBACK & CHALLENGES
Balancing diverse needs and users
68% of people shopping on Double parked trucks
Queens Blvd arrive by foot block traffic and
and 21% arrive by transit create congestion
Majority of businesses
do not control when
they receive deliveries
nyc.gov/dot 27
CURBSIDE USAGE: PROPOSAL
Add approximately 22 parking Remove approximately 4,420’
spaces curbside on Queens Blvd, of parkable space against the
Ascan Ave, Austin St, and 112th St median (220 spaces)
nyc.gov/dot 28
CURBSIDE USAGE: PROPOSAL
Location Existing Proposed Length Benefits
WB service road between Monday-Saturday No change 100’ Maintain dedicated time
1 71st Rd & 108th St 7am-7pm for truck loading on busy
retail block
EB service road between Monday-Saturday Monday-Saturday 140’ Additional parking
2 Ascan Ave & 73rd Rd 7am-7pm 7am-4pm available in evenings
EB service road between Monday-Saturday Monday-Friday 130’ Additional parking
3 73rd Rd & 75th Ave 7am-7pm 7am-4pm available in evenings and
on Saturday
WB service road between Monday-Saturday Monday-Friday 185’ Additional parking
4 76th Rd &112th St 7am-7pm 7am-7pm available on Saturdays
EB service road between No space for Monday-Saturday Approximately New dedicated time for
5 77th Ave &78th Ave loading 7am-7pm 110’ truck loading on busy
retail block
EB service road between No space for Monday-Saturday Approximately New dedicated time for
6 78th Ave & Union Turnpike loading 7am-4pm 110’ truck loading on busy
retail block
WB service road between No space for Monday-Friday Approximately New dedicated time for
7 78th Ave & 77th Ave loading 9am-5pm 65’ truck loading on busy
retail block
nyc.gov/dot 29
2018 PROPOSAL BENEFITS
• Expanded pedestrian refuge space, mall-to-mall crossings, and pedestrian path shorten pedestrian
crossing distances and extend the pedestrian network
• Protected bicycle lane allows for safe, convenient bicycle travel
• Stop-controlled slip lanes calm the service roads, create safer vehicle transitions between
mainline and service road, and reduce highway-like feeling on Queens Blvd
• Updated lane markings organize roadway for all road users and create predictable movements
• New curb regulations manage diverse needs and allow for expeditious truck loading
• 2018 project creates footprint for Great Streets Capital build out with expanded medians and
pedestrian amenities
nyc.gov/dot 30
QUEENS BLVD TRANSFORMATION
nyc.gov/dot 31
THANK YOU!
Questions?
nyc.gov/dot 32