Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI

SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH

PROJECT QUALITY PLAN


PETRODEC Sdn Bhd WORK INSTRUCTION

EARTHWORK
Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH

PROJECT QUALITY PLAN


PETRODEC Sdn Bhd WORK INSTRUCTION

Flow Chart For Earthwork - EXCAVATION WORKS

Start

Mobilization

PREPATORY WORKS:
1. Check boundary and limit of work.
2. Locate existing drain and services.
3. Locate existing cables and services.
4. Site clearing.
5. Disposal of rubbish and spoils.
6. Protection to environment, services, drains and adjoining properties
7. Arrange suitable machines for works.

Survey setting out works


to determine the location and depth of excavation

Strip topsoil
haul and dump to designated area

Unsuitable Suitable
material Check suitability of material
soil excavated
(whether soil is
unsuitable material,
peat, soft soil etc)
Excavate to required Excavate to required depth.
sequence of depth Dispose off excess material

Disposal to designated dumping Disposal to designated


area (Record trips) dumping area (Record Trips)
Need
material
for Fill
Need
material
Survey / Check Level No for Fill

Continue excavation
to level Yes
Level
achieved Stop excavation
No
Tidy up site A

End

Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH

PROJECT QUALITY PLAN


PETRODEC Sdn Bhd WORK INSTRUCTION
Flow Chart For Earthwork - FILLING WORKS

Survey setting out works


level of fill required

Haul fill material


From borrow or excavation area

Record Trip

Spread and level


in layers not exceeding 300mm thick

Scarify and sun dry


material
Break up material
Check moisture
content Dry
Whether material is wet and
Wet cannot compact

Compact to required density


Compaction in layers by compactor

Compact using sheep


foot roller to required Test Soil
density Density (FDT)
Required density
No achieved
"If natural moisture content is high"

Record Results
Check
Level of fill Proceed to next layar
Required level Compaction in layers by compactor
No achieved

Yes
End - Filling
Works

Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH

PROJECT QUALITY PLAN


PETRODEC Sdn Bhd METHOD STATEMENT OF WORK

WORK INSTRUCTION FOR EARTHWORKS

OBJECTIVE

To outline the work instruction by which Earthworks are carried out.

SCOPE

The work instruction shall apply for all building and civil engineering projects.

RESPONSIBILITIES

Site Agent, Site Supervisor & Land Surveyor.

MATERIALS

Nil

HANDLING AND STORAGE OF MATERIALS

Nil

PLANT, MACHINERY & EQUIPMENT

Hydraulic excavator, Bulldozer, Low Ground Pressure (LGP) bulldozer, Dumping Truck,
Motor grader, Compactor, Motor scraper, Back-pusher, Water pumps, etc. where applicable.

DEFINITION

CBR Test - Abbreviation for California Bearing Ratio. Use to determine trial compaction of
soil.

PREPARATORY WORKS

(1) Liaison
Liaise and cooperate with appropriate authorities, clients and his representatives
regarding adjoining property and check whether approval to commence work has
been obtained. Do not trespass on adjoining property.

Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH

PROJECT QUALITY PLAN


PETRODEC Sdn Bhd METHOD STATEMENT OF WORK

(2) Locating existing drains and services.


Locate the positions and levels of the existing drains and services indicated on
drawings. Seek instructions on the method for dealing with those, which are likely
to be affected.

(3) Locating cables, pipes and services.


Mark location of all underground cables and pipes with signboards, indicating
their type eg. Water, gas, electricity, telephone, TV cable and etc. Check on their
depth with the relevant parties. Where any overhear cables exist, install restricts
headroom indicators.

(4) Site Clearance.


The clearance at site shall include surface vegetation clearance, stripping,
stockpiling of topsoil and disposal of rubbish and spoil.

(5) Surface vegetation clearance.


Cut and clear away long grass, weed branches and etc. Grub up stumps and major
root runs with unduly disturbing topsoil.

(6) Stripping and stockpiling of topsoil.


Strip topsoil to a depth of not exceeding 150mm as directed. Keep stockpiles
separate from other materials.

(7) Disposal of rubbish and spoil.


Tip rubbish and spoil only on tips controlled and recognized by the Local
authority and that comply strictly with any regulation governing the controlled
tipping of refuse.

(8) Lacating site burning areas.


Where permitted, burning unwanted timber and combustible materials on site. Locate
fore where it is safe, and shall not cause damage or spread to trees or shrubs.

(9) Protection and prevention.


Before excavation commences, check that the following items have been securely
protected.

(10) Trees and plants to be retained.


Identify the mark trees to be retained. Do not cut unless directed otherwise.

Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH

PROJECT QUALITY PLAN


PETRODEC Sdn Bhd METHOD STATEMENT OF WORK

(11) Drains.
Protect from damage. Keep drain clear of debris at all times to prevent clog.

(12) Benchmarks.
Report any benchmarks and other established survey found on areas to be cleared.
Do not remove or destroy unless instructed otherwise.

(13) Temporary water discharge.


Provide temporary gradients, water courses, ditches, drains, water pumps or other
means for the rapid disposal of water flowing on the area of work during
excavation and filling.

(14) Arrange suitable plant, machinery and equipment to be used for the work.

WORKS METHODOLOGY
(1) Excavation.

Step 1
Excavate to required profile and levels using suitable machine as required by the
contractual Specifications and Drawings. Load soft soil, loose rocks and other
unsuitable materials onto dumping truck.

Step 2
Strip and heap up topsoil to required depth.

Step 3
Make good of all formation surfaces damage by weather conditions or construction
traffic.

Step 4
Obtain approval of level and condition of formation by conducting joint inspection
where required.

Step 5
Maintain dry working conditions. Where water stagnant occurs, use water pump to
de-water areas.

Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH

PROJECT QUALITY PLAN


PETRODEC Sdn Bhd METHOD STATEMENT OF WORK

DISPOSAL OF CLEARING MATERIAL, PEAT AND UNSUITABLE MATERIAL

Step 1
Haul unsuitable materials to designated disposal area as directed.

Step 2
Remove existing stockpile earthfill to designated dump site area.

Note 1
Keep the edges of excavation clear to prevent undue pressure on the excavation sides.
Place soil raised from the excavation away from the edges to avoid overloading the
sides of the excavation and to prevent loose materials falling back in. Provide barriers
to prevent vehicles and their loads endangering the edges of excavation.

FILING AND COMPACTING

Step 1
Deposit filling material in layers to begin with install Geotextile PET 100/50.
Extend and spread layer in full width by using equialent machine for this operation.
Compact layer by compactor.

Step 2
Fills earthfill stockpile afterwards. Extend and spread layer in full width by using
bulldozer/back pusher or equivalent machine. Compact layer by compactor.

Step 3
Supply and install of Geogard EPDM liner.

Step 4
Install non-woven geotextile TS 40 at interface of excavated slope and EPDM liner.

Step 5
Fills earthfill material, extend and spread layer in full width by using equivalent
machine and compact layer by compactor.

Step 6
Supply, lay and compact road-base of approved imported crushed aggregate thickness
of 300mm

Step 7
Lay, compact stockpile road-base of approved crushed aggregate thickness of 300mm

Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH

PROJECT QUALITY PLAN


PETRODEC Sdn Bhd METHOD STATEMENT OF WORK

Step 8
Supply, lay and compacted asphaltic concrete binder course (ACB 28) to the compacted
thickness of 75mm

Step 9
Supply and install overhead mild steel round hollow section road gantry complete with
all necessary accessories.

Note 2
when moisture content is high, treatment of material is required to bring down the
natural moisture content.

TREATMENT OF MATERIAL

Step 1
Break up materials, loosen and expose material for drying. Leave material to dry up in
the sun.

Step 2
In event of rain, keep motor grader and compactor on alert to regrade, compact and
seal off the exposed surfaces.

Step 3
In area where suitable fill material has higher natural moisture content, sheep-foot
rollers are used to initially compact the material. This will result better exposure and
proper earation of soil.

RECORDS

Records in Earthwork process when required in the relevant form.


MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:

RK
MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:

required depth.
excess material

Need
material
for Fill
Need
material
for Fill

Yes

MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:

pact to required density


ction in layers by compactor
Yes

MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:

r, Dumping Truck,
s, etc. where applicable.

ne trial compaction of

his representatives
ommence work has

MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:

ces indicated on
ose, which are likely

oards, indicating
etc. Check on their
xist, install restricts

e, stripping,

p stumps and major


Keep stockpiles

ng the controlled

materials on site. Locate


trees or shrubs.

have been securely

ted otherwise.

MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:

o prevent clog.

n areas to be cleared.

water pumps or other

or the work.
as required by the
ocks and other

itions or construction

cting joint inspection

s, use water pump to

MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:

e excavation sides.
overloading the
n. Provide barriers

e PET 100/50.
ne for this operation.

ull width by using


by compactor.

ope and EPDM liner.

using equivalent

hed aggregate thickness

ate thickness of 300mm

MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:

ACB 28) to the compacted


oad gantry complete with

bring down the

ave material to dry up in

regrade, compact and

e content, sheep-foot
lt better exposure and