EARTHWORK
Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH
Start
Mobilization
PREPATORY WORKS:
1. Check boundary and limit of work.
2. Locate existing drain and services.
3. Locate existing cables and services.
4. Site clearing.
5. Disposal of rubbish and spoils.
6. Protection to environment, services, drains and adjoining properties
7. Arrange suitable machines for works.
Strip topsoil
haul and dump to designated area
Unsuitable Suitable
material Check suitability of material
soil excavated
(whether soil is
unsuitable material,
peat, soft soil etc)
Excavate to required Excavate to required depth.
sequence of depth Dispose off excess material
Continue excavation
to level Yes
Level
achieved Stop excavation
No
Tidy up site A
End
Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH
Record Trip
Record Results
Check
Level of fill Proceed to next layar
Required level Compaction in layers by compactor
No achieved
Yes
End - Filling
Works
Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH
OBJECTIVE
SCOPE
The work instruction shall apply for all building and civil engineering projects.
RESPONSIBILITIES
MATERIALS
Nil
Nil
Hydraulic excavator, Bulldozer, Low Ground Pressure (LGP) bulldozer, Dumping Truck,
Motor grader, Compactor, Motor scraper, Back-pusher, Water pumps, etc. where applicable.
DEFINITION
CBR Test - Abbreviation for California Bearing Ratio. Use to determine trial compaction of
soil.
PREPARATORY WORKS
(1) Liaison
Liaise and cooperate with appropriate authorities, clients and his representatives
regarding adjoining property and check whether approval to commence work has
been obtained. Do not trespass on adjoining property.
Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH
Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH
(11) Drains.
Protect from damage. Keep drain clear of debris at all times to prevent clog.
(12) Benchmarks.
Report any benchmarks and other established survey found on areas to be cleared.
Do not remove or destroy unless instructed otherwise.
(14) Arrange suitable plant, machinery and equipment to be used for the work.
WORKS METHODOLOGY
(1) Excavation.
Step 1
Excavate to required profile and levels using suitable machine as required by the
contractual Specifications and Drawings. Load soft soil, loose rocks and other
unsuitable materials onto dumping truck.
Step 2
Strip and heap up topsoil to required depth.
Step 3
Make good of all formation surfaces damage by weather conditions or construction
traffic.
Step 4
Obtain approval of level and condition of formation by conducting joint inspection
where required.
Step 5
Maintain dry working conditions. Where water stagnant occurs, use water pump to
de-water areas.
Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH
Step 1
Haul unsuitable materials to designated disposal area as directed.
Step 2
Remove existing stockpile earthfill to designated dump site area.
Note 1
Keep the edges of excavation clear to prevent undue pressure on the excavation sides.
Place soil raised from the excavation away from the edges to avoid overloading the
sides of the excavation and to prevent loose materials falling back in. Provide barriers
to prevent vehicles and their loads endangering the edges of excavation.
Step 1
Deposit filling material in layers to begin with install Geotextile PET 100/50.
Extend and spread layer in full width by using equialent machine for this operation.
Compact layer by compactor.
Step 2
Fills earthfill stockpile afterwards. Extend and spread layer in full width by using
bulldozer/back pusher or equivalent machine. Compact layer by compactor.
Step 3
Supply and install of Geogard EPDM liner.
Step 4
Install non-woven geotextile TS 40 at interface of excavated slope and EPDM liner.
Step 5
Fills earthfill material, extend and spread layer in full width by using equivalent
machine and compact layer by compactor.
Step 6
Supply, lay and compact road-base of approved imported crushed aggregate thickness
of 300mm
Step 7
Lay, compact stockpile road-base of approved crushed aggregate thickness of 300mm
Main Contractor PROJEK MENAIKTARAF BAN PANTAI DAN PINTU KAWALAN PASANG SURUT SERTA KERJA BERKAITAN DI
SKIM PENGAIRAN TERKAWAL BAN MERBOK, DAERAH KUALA MUDA KEDAH
Step 8
Supply, lay and compacted asphaltic concrete binder course (ACB 28) to the compacted
thickness of 75mm
Step 9
Supply and install overhead mild steel round hollow section road gantry complete with
all necessary accessories.
Note 2
when moisture content is high, treatment of material is required to bring down the
natural moisture content.
TREATMENT OF MATERIAL
Step 1
Break up materials, loosen and expose material for drying. Leave material to dry up in
the sun.
Step 2
In event of rain, keep motor grader and compactor on alert to regrade, compact and
seal off the exposed surfaces.
Step 3
In area where suitable fill material has higher natural moisture content, sheep-foot
rollers are used to initially compact the material. This will result better exposure and
proper earation of soil.
RECORDS
RK
MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:
required depth.
excess material
Need
material
for Fill
Need
material
for Fill
Yes
MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:
MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:
r, Dumping Truck,
s, etc. where applicable.
ne trial compaction of
his representatives
ommence work has
MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:
ces indicated on
ose, which are likely
oards, indicating
etc. Check on their
xist, install restricts
e, stripping,
ng the controlled
ted otherwise.
MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:
o prevent clog.
n areas to be cleared.
or the work.
as required by the
ocks and other
itions or construction
MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:
e excavation sides.
overloading the
n. Provide barriers
e PET 100/50.
ne for this operation.
using equivalent
MOA/PSB/MERBOK
EARTHWORK/2015/
Contract No.:
e content, sheep-foot
lt better exposure and