Professional Documents
Culture Documents
"PROJECT NAME"
NAME.....................................................................................………………………………. SNS DESIGNS
DATE...............................................................……………………………………………….
CABLE TRY LAYING QUALITY SYSTEM
TIME................................................................………………………………………………. RFWI Form No. 22A Rev 0
1st Re-
SUB-CONTRACTOR ______________________________________________ Inspection Inspection REQUEST No
WE HEREBY NOTIFY THAT THE FOLLOWING WILL BE READY FOR FINAL INSPECTION ON : Date ____________ Time : ____________
DRAWING Nos
2.DUCTING
the elevated ducts with angle brackets secured to previously installed hanger rods .
Install 45 Degree bend for any cable tray for turning
Coordination will be done with other services
Lift the vertical shaft tray using man power
Place the joint tray with angle support inside the shaft exact location
as per the drawing .
Fix the angle support on to slab using Mechanical Fasteners
Support the elevated tray at both the side running on the wall with
proper mechanicl fasteners
4. FINAL CHECK
SECTION 1
5. OTHERS
Distribution: ER, Site Staff, Head Office QA Dept. L&W Building Solutions Pvt. Ltd. Quality Assurance Record
NOTIFICATION RECEIVED
"PROJECT NAME"
NAME.....................................................................................………………………………. SNS DESIGNS
SECTION 2
WE HEREBY NOTIFY THAT THE FOLLOWING WILL BE READY FOR FINAL INSPECTION ON : Date ____________ Time : ____________
DRAWING Nos
2.PIPING
Existing ceiling levels has to be checked with drawing and marked with
help of instrument at the relevent areas
Install the required supports like u clamp, anchor fastener with threaded rod and
brackets as per the marking or drawing.
Cut pipes to correct length perpendicularly to the pipe axis. Prepare pipe
THROUGH SECTION 2 AND SIGNING OFF SECTION 3 AFTER FINAL INSPECTION.
4. FINAL CHECK
Marking and support as per the drawing
SECTION 1
5. OTHERS
Distribution: ER, Site Staff, Head Office QA Dept. L&W Building Solutions Pvt. Ltd. Quality Assurance Record
NOTIFICATION RECEIVED
"PROJECT NAME"
NAME.....................................................................................……………………………….
SECTION 2
WE HEREBY NOTIFY THAT THE FOLLOWING WILL BE READY FOR FINAL INSPECTION ON : Date ____________ Time : ____________
DRAWING Nos
2.DUCT laying
PERSON THROUGH SECTION 2 AND SIGNING OFF SECTION 3 AFTER FINAL INSPECTION.
Existing ceiling levels has to be checked with drawing and marked with
help of instrument at the relevent areas
Install all the hanger rod and brackey support
TDF type -joint ducts with flanges / clips
SLIP joint Type - joint ducts together with slip joint and sealent
lift the joint duct work to required elevation
Fire damper will be mounted on wall and the sleeve of fire damper will
be connected to duct using “S” slip (drawing attached).
Coordination will be done with other services
Grills will be connected to duct system using factory fabricated collars,
the collar flange and grill will be connected using riveting.
Supply air duct carrying cold air shall be externally insulated with
insulation material as per specification.
Support the elevated tray at both the side running on the wall with
proper mechanicl fasteners
4. FINAL CHECK
Marking and support as per the drawing
SECTION 1
5. OTHERS
DATE ___________________________
OR WORK INSPECTION
AC DUCTING QUALITY SYSTEM
RFWI Form No. 22A Rev 0
REQUEST No
_____ .
DRAWING Nos
COMMENTS FROM ER ER
D FOR _____________________
SIGNED FOR ______________
ER