You are on page 1of 6

NOTIFICATION RECEIVED

"PROJECT NAME"
NAME.....................................................................................………………………………. SNS DESIGNS

REQUEST FOR WORK INSPECTION


SECTION 2

DATE...............................................................……………………………………………….
CABLE TRY LAYING QUALITY SYSTEM
TIME................................................................………………………………………………. RFWI Form No. 22A Rev 0

1st Re-
SUB-CONTRACTOR ______________________________________________ Inspection Inspection REQUEST No

WE HEREBY NOTIFY THAT THE FOLLOWING WILL BE READY FOR FINAL INSPECTION ON : Date ____________ Time : ____________

NOTIFIED BY (NAME) ___________________________ (L&W STAFF) ON _________________ .

LOCATION I&T PLAN OPERATION


REFERENCE

DRAWING Nos

SNS Staff COMMENTS FROM ER ER


CHECKS (refer to I&TP)
Initial Date (Where Applicable) Initial Date
1. APPROVAL OF SHOP DRAWINGS
& METHOD STATEMENT
ENSURE THESE CHECKS ARE COMPLETED FIRST BEFORE NOTIFYING THE AUTHORISED PERSON

2.DUCTING

Existing ceiling levels has to be checked with drawing &


marked with the help of instrument at the relevant areas.
Install hanger rod and bracket support.
THROUGH SECTION 2 AND SIGNING OFF SECTION 3 AFTER FINAL INSPECTION.

For TDF type - join ducts together with flange/clips. Ensure


matching flanges are secured firmly.
For Slip Joint type - join ducts together with slip joint and apply
necessary sealant along joint
Lift the joined ductwork to the required elevation
Earthing strip to be will be welded not less than 10 mtrs

3. POINTING & PROTECTION

the elevated ducts with angle brackets secured to previously installed hanger rods .
Install 45 Degree bend for any cable tray for turning
Coordination will be done with other services
Lift the vertical shaft tray using man power
Place the joint tray with angle support inside the shaft exact location
as per the drawing .
Fix the angle support on to slab using Mechanical Fasteners

Support the elevated tray at both the side running on the wall with
proper mechanicl fasteners

4. FINAL CHECK
SECTION 1

Marking and support as per the drawing


Size of the cable tray as per drawing
Tray colour /powder coating is matching with the requirement
Ensure the trays is covered by stickers to prevent from dust
sharp edges are removed properly
levels in drawing & at site before installation of cable tray , periodic level

5. OTHERS

AUTHORITY IS GIVEN TO PROCEED TO NEXT STAGE


AUTHORITY TO PROCEED TO NEXT STAGE DOES NOT RELIEVE THE CONTRACTOR FROM HIS RESPONSIBILITY & LIABILITY CONCERNING COMPLIANCE WITH CONTRACT REQUIREMENTS
SECTION 3

SIGNED FOR _____________________


SNS DESIGNS SIGNED FOR ______________
ER

PRINT NAME _______________


PRINT NAME _____________________

DATE ___________________________ DATE _____________________

Distribution: ER, Site Staff, Head Office QA Dept. L&W Building Solutions Pvt. Ltd. Quality Assurance Record
NOTIFICATION RECEIVED
"PROJECT NAME"
NAME.....................................................................................………………………………. SNS DESIGNS
SECTION 2

DATE...............................................................………………………………………………. REQUEST FOR WORK INSPECTION


TIME................................................................……………………………………………….
PIPING QUALITY SYSTEM
RFWI Form No. 22A Rev 0
1st Re-
SUB-CONTRACTOR ______________________________________________ Inspection Inspection REQUEST No

WE HEREBY NOTIFY THAT THE FOLLOWING WILL BE READY FOR FINAL INSPECTION ON : Date ____________ Time : ____________

NOTIFIED BY (NAME) ___________________________ (L&W STAFF) ON _________________ .

LOCATION I&T PLAN OPERATION


REFERENCE

DRAWING Nos

SNS Staff COMMENTS FROM ER ER


CHECKS (refer to I&TP)
Initial Date (Where Applicable) Initial Date
1. APPROVAL OF SHOP DRAWINGS
& METHOD STATEMENT
ENSURE THESE CHECKS ARE COMPLETED FIRST BEFORE NOTIFYING THE AUTHORISED PERSON

2.PIPING
Existing ceiling levels has to be checked with drawing and marked with
help of instrument at the relevent areas
Install the required supports like u clamp, anchor fastener with threaded rod and
brackets as per the marking or drawing.
Cut pipes to correct length perpendicularly to the pipe axis. Prepare pipe
THROUGH SECTION 2 AND SIGNING OFF SECTION 3 AFTER FINAL INSPECTION.

joints surface to 45-degree chamfer for welded joint.


Leave a gap of 3-5mm between pipe ends for weld penetration. And
also leave gaps for valves. Weld the pipes together. Ensure weld is
smooth and no pitting.
Insert the valves and gauges as per the drawing.

3. POINTING & PROTECTION


Join threaded pipes using sockets. PTFE tape is applied on the thread
together with strings wound around it (If required).
Test hydro-statically the pipework installation.
Coordination will be done with other services
If required, insulate pipes after test is accepted.
Supply air duct carrying cold air shall be externally insulated with
insulation material as per specification.
Confirm colour code for finish paint.
Label pipes with appropriate wordings and directional arrows.

4. FINAL CHECK
Marking and support as per the drawing
SECTION 1

Size of the duct as per drawing


Duct colour /powder coating is matching with the requirement
Check for straightness of pipe .
check for all the joints
levels in drawing & at site before installation of pipe , periodic level
checking before lifting
Final level checking after lifting

5. OTHERS

AUTHORITY IS GIVEN TO PROCEED TO NEXT STAGE


AUTHORITY TO PROCEED TO NEXT STAGE DOES NOT RELIEVE THE CONTRACTOR FROM HIS RESPONSIBILITY & LIABILITY CONCERNING COMPLIANCE WITH CONTRACT REQUIREMENTS
SECTION 3

SIGNED FOR _____________________


SNS DESIGNS SIGNED FOR ______________
ER

PRINT NAME _______________


PRINT NAME _____________________

DATE ___________________________ DATE _____________________

Distribution: ER, Site Staff, Head Office QA Dept. L&W Building Solutions Pvt. Ltd. Quality Assurance Record
NOTIFICATION RECEIVED
"PROJECT NAME"
NAME.....................................................................................……………………………….
SECTION 2

DATE...............................................................………………………………………………. REQUEST FOR WORK INSPECTION


TIME................................................................……………………………………………….
HVAC DUCTING
1st Re-
SUB-CONTRACTOR ______________________________________________ Inspection Inspection

WE HEREBY NOTIFY THAT THE FOLLOWING WILL BE READY FOR FINAL INSPECTION ON : Date ____________ Time : ____________

NOTIFIED BY (NAME) ___________________________ (L&W STAFF) ON _________________ .

LOCATION I&T PLAN OPERATION


REFERENCE

DRAWING Nos

SNS Staff COMMENTS FRO


CHECKS (refer to I&TP)
Initial Date (Where Applicable)
1. APPROVAL OF SHOP DRAWINGS
& METHOD STATEMENT
ENSURE THESE CHECKS ARE COMPLETED FIRST BEFORE NOTIFYING THE AUTHORISED

2.DUCT laying
PERSON THROUGH SECTION 2 AND SIGNING OFF SECTION 3 AFTER FINAL INSPECTION.

Existing ceiling levels has to be checked with drawing and marked with
help of instrument at the relevent areas
Install all the hanger rod and brackey support
TDF type -joint ducts with flanges / clips
SLIP joint Type - joint ducts together with slip joint and sealent
lift the joint duct work to required elevation

3. POINTING & PROTECTION


The volume control damper / Spigot / Variable air volume damper will be
connected to duct using nut bolt system the joint will be made air tight
using gasket and sealant.

Fire damper will be mounted on wall and the sleeve of fire damper will
be connected to duct using “S” slip (drawing attached).
Coordination will be done with other services
Grills will be connected to duct system using factory fabricated collars,
the collar flange and grill will be connected using riveting.
Supply air duct carrying cold air shall be externally insulated with
insulation material as per specification.
Support the elevated tray at both the side running on the wall with
proper mechanicl fasteners

4. FINAL CHECK
Marking and support as per the drawing
SECTION 1

Size of the duct as per drawing


Duct colour /powder coating is matching with the requirement
SECTION 1
Ensure the trays is covered by stickers to prevent from dust
sharp edges are removed properly
levels in drawing & at site before installation of duct , periodic level
checking before lifting
Final level checking after lifting

5. OTHERS

AUTHORITY IS GIVEN TO PROCEED TO NEXT STAGE


AUTHORITY TO PROCEED TO NEXT STAGE DOES NOT RELIEVE THE CONTRACTOR FROM HIS RESPONSIBILITY & LIABILITY CONCERNING COMPLIANCE WITH CONT
SECTION 3

SIGNED FOR _____________________


SNS DESIGNS

PRINT NAME _____________________

DATE ___________________________

Distribution: ER, Site Staff, Head Office QA Dept.


OJECT NAME"
SNS DESIGNS

OR WORK INSPECTION
AC DUCTING QUALITY SYSTEM
RFWI Form No. 22A Rev 0

REQUEST No

ate ____________ Time : ____________

_____ .

I&T PLAN OPERATION


REFERENCE

DRAWING Nos

COMMENTS FROM ER ER

(Where Applicable) Initial Date


ROCEED TO NEXT STAGE
ESPONSIBILITY & LIABILITY CONCERNING COMPLIANCE WITH CONTRACT REQUIREMENTS

D FOR _____________________
SIGNED FOR ______________
ER

PRINT NAME _______________


NAME _____________________

___________________________ DATE _____________________

L&W Building Solutions Pvt. Ltd. Quality Assurance Record

You might also like