Professional Documents
Culture Documents
Index
Page 2 of 42
GN101-03-SP-06-R2
General Specification
1.0 Codes & standards
Materials, equipment and methods used in the Laying of 11/33/66KV Cable shall conform to the
latest edition of following –
2.0 Design guidelines and Parameter for cable laying‐
Page 3 of 42
GN101-03-SP-06-R2
• The excavated earth shall be so stored at site, that it shall
not cause trouble to running traffic
• All excavated earth shall be stored within the barricaded
area.
•
c) Full height fence, barriers, barricades etc. shall be erected
around the site in order to prevent the working area from the
risk of accidents due to speedy vehicular movement. Same the
way barricades protect the road users from the danger due to
construction equipment and temporary structures.
d) The structure dimensions of the barricades , material and
composition, its colour scheme, BSES logo and details shall be in
accordance with specification and drawing laid down in the
tender documents.
e) All the barricades shall be erected as per the design
requirements of employer, numbered painted and maintained in
good condition and also barricade in charge maintain a barricade
register at site.
f) All barricades shall be conspicuously seen in the dark/night time
by the road users so that no vehicle hits the barricades.
Conspicuity shall be ensured by affixing retro reflective strips of
required size and shape at appropriate angle at bottom and
middle portion of the barricades at a minimum gap of 1000 mm.
In addition minimum one red light /red blinker and red beacon
light should be placed at the top of each barricade.
g) PPP to be provided by vendor to all workers and engineers.
h) Also refer Annexure‐ 7: Barricading and Safety
2.3 Clearance The desired minimum clearances are as follows –
‐ Power cable to power cable – A minimum clearance equal to diameter
shall be maintained. Trench drawings shall be referred to for guidance.
‐ Power Cable to control cables – 0.2 M
‐ Power cable to communication cable – 0.3M
‐ Power cable to gas/water main – 0.3 M
2.4 Depth of Cable The desired minimum depth of laying from ground surface to the top of
Laying cable shall be:
650 / 1100V grade XLPE Cables – 75 cm
6.35 / 11KV grade XLPE Cables – 90 cm
Low voltage and Control cable ‐ 75 cm
19 / 33KV grade XLPE Cables ‐ 1.2 M
38 / 66KV grade XLPE Cables ‐ 1.5 M
Cables at Road crossing ‐ 1.0 M (min.)
Cables at railways level crossings (measured from bottom of sleepers to
the top of Pipe) ‐ 1.0 M (min.)
Whenever there is any obstacle at the laying depth, the cable should be
lowered/ raised to cross the obstacle. However variation in the depth is
to be approved by BSES. The Contractor shall provide the same in
deviation report.
2.5 Width of Cable The width and depth of Cable Trenches shall depend upon number of
Page 4 of 42
GN101-03-SP-06-R2
trenches circuits and Voltage Grade. Annexure # 3 and drawings of this
specification shall be followed.
2.6 Bending Radius While pulling of the Cable from the drum or during laying
of Cables following minimum bending radius shall be maintained so that
the cable, in particular the insulation does not get damaged –
A) Single Core Cables ( PVC & XLPE)
Upto 1.1KV grade – 15 X D
Above 11KV grade ‐ 20 X D
B) Multi Core Cables ( PVC & XLPE)
Upto 1.1KV grade ‐ 12 X D
Above 1.1KV grade – 15 X D
Where ‘D’ is overall diameter of the cable.
2.7 Maximum For cables pulled with Stocking
permissible PVC and XLPE SWA Armoured cables P = 30 X D
Tensile PVC and XLPE AWA Armoured cables P = 20 X D
Strength for Where P= pulling force in Kgrm, D= Diameter of Cable in mm
Cables
For Cables pulled by Cable eyes
Aluminium conductor – 30 N/mm2 = 3 Kg/sq. mm
Copper conductors ‐ 50N/mm2 = 5 Kg/sq. mm
Permissible force is calculated by multiplying the above values by cross
sectional area (CSA) of conductor of each core and then number of cores.
2.8 Methods of a) Cables shall be laid in direct in ground, in trenches excavated
Laying therein and shall be protected with covers as given in the
drawing. Cables shall also be drawn into pipes of ducts or laid in
the formed trenches or troughs or on racks or supported in trays
or cleats as required by the site exigencies. Where the cables are
laid in the formed trenches, the installation shall include removal
and replacement of the trench covers and the provision of
temporary protective covers on the trenches where they cross
the access ways.
b) HDPE ( 200 mm) or RCC ducts shall be used where cable cross
roads and railways tracks. Spare ducts for future extensions
should be provided. Spare duct should be sealed off. Buried
ducts or ducting blocks shall project into footpath or upto the
edge of road, where there is no footpath, to permit smooth entry
of cable without undue bending. The diameter of the cable
conduit or pipe or duct should be at least 1.5 times the outer
diameter of the cable. Angular alignment of the duct across road
crossings shall be predetermined to maintain safe bending radius
when direction of cable trench changes before or after the road.
c) The contractor shall lay cable by Horizontal direct drilling (HDD)
in main roads and highway with heavy traffic, passage to public
property where excavation is not possible. Contractor shall take
approval for laying of cable by means of HDD wherever required
from the supervising engineer. The cable laid by HDD shall be
Page 5 of 42
GN101-03-SP-06-R2
minimized so that it doesn’t exceed by 12% of total route length.
This is to avoid De‐rating of Cables.
d) Unless approved by BSES, the contractor shall lay the cables,
direct in ground, in single layer. The cables shall be laid with the
pre‐determined and approved cable route.
e) Spacing shall be maintained uniformly between the cables all
along the length including the bends, as approved by BSES. To
maintain the spacing, suitable non‐metallic formers shall be
placed uniformly with spacing not exceeding 5 meters. Every
bend shall have at least one spacer.
f) 75 mm of the sand bed shall be placed at the bottom of cable
trench.
g) After the cables have been laid the trench shall be filled with the
sand and shall be well rammed to a level not less than 75 mm
above the top of the cables all throughout the route.
h) To protect the cables against external mechanical damage, which
may be caused by other agencies, the cable shall be protected by
suitable cover. (for drawing of RCC cable cover refer annexure
VI).
i) The type of the covers shall be as under
‐ 1.1KV Cables – Single layer of brick thickness not less than
75 mm ( 3 inch)
‐ 11KV Cables – sand stone of thickness not less than 75mm (
3 inch).
‐ 33KV Cables shall be protected by reinforced concrete cover of
width 300 mm as per attached drawing with thickness not less
than 50mm.
‐ 66KV Cables shall be protected by reinforced concrete cover as
per attached drawing with thickness not less than 50mm.
The RCC cable cover shall be embossed as “BSES EHV
CABLE”.
j) Back fill to be filled up to 75mm and the warning tape shall be
installed continuously. The tape shall be yellow in colour with
Black / Red lettering of minimum 20mm height. The approved
warning message shall be written in English and Hindi/ local
language. The minimum thickness and width of the tape should
be 300 microns and 150 mm respectively.
k) The trench shall be filled‐up by loose soft soil (300mm) and
Excavated soil as indicated in drawings.
2.9 Cable over On Bridges the cables are generally supported on wooden cleats and
Page 6 of 42
GN101-03-SP-06-R2
Bridges clamped on steel supports at regular intervals. The cables laid on bridges
shall be provided with Sun shield.
Approval from appropriate authorities (PWD/railways) as applicable shall
be taken by contractor.
2.10 Laying of Single a) The single core cables shall be laid in trefoil formation. Single
Core Cables core cables can be laid individually in 200mm HDPE pipe in case
of HDD only.
b) For single core cables laid in trefoil formation, plastic cable ties
shall be used at interval of 1.0 (one) meter throughout the cable
length to maintain the trefoil arrangement.
c) To balance the inductance, the phase sequence in trefoil format
shall be maintained by vendor ( for double circuit)
d) To prevent magnetic losses (eddy current and hysteresis losses),
the base plate of the panels or the terminal box of the
equipments, shall have aluminium plate. In case the entry into
the building is through GI pipe, a “slit” in the GI pipe shall be
necessary. Alternatively GI pipes may altogether be avoided and
non‐metallic pipes such as PVC or HDPE pipe shall be used.
Concrete pipes having steel reinforcement (RCC pipe) are not to
be used.
2.11 Earthing of a) Single point bonded earthing shall be employed to prevent flow
Single Core of induced circulating current in the armour and screen and
Cables consequential de‐rating of cables for feeder less than 2.0 KM.
b) For feeder length more than 2 KM, mid point earthing shall be
provided.
2.12 Violation of On violation of barricading guideline and safety norms, a fine of Rs.5000
barricading /day shall be imposed.
guideline and BRPL inspector/engineer in‐charge shall be empowered to impose the
safety norms above penalty.
3.0 General guidelines for Laying Cables
Page 7 of 42
GN101-03-SP-06-R2
showing the entire route, road crossings, location of joints and
also the arrangement of cables to be laid. In case due to site
exigencies, cables have to cross over within the trench, the same
shall be shown in the drawing. For each and every job, these
drawings shall be approved by BSES, prior to commencement of
work.
d) BSES shall arrange for all the material and manpower required
for jointing and end termination. The Contractor shall provide
pit, carry out excavation for creation of working space required
for jointing by the jointer. All civil works, structural work,
clamping and earthing shall be carried out by the contractor, so
that the cables and accessories perform satisfactorily during the
entire life time.
e) The entry and exit of the cables into the building shall be through
RCC or GI pipe except for single core cables, which shall be
properly sealed and shall be duly supported as per the method
and technique approved by BSES, so that the outer sheath of the
cable does not get damaged at the entry and exit points. The
sealing should be of adequate length so that it minimizes the risk
of spreading of fire or ingress of water.
3.2 Handling and a) The cable drums shall be transported upright, so that the weight
Storage of is distributed on both the flanges. Under no circumstances the
Cable drums (All cable drum may be laid on its side. During transportation the
empty drums are drums must be properly secured. The cable drums should never
returnable) be dropped from Lorry or a trailer, so as to prevent damage to
the cable drum and also to the cable. Ramp may be used for
unloading. The drums may be rolled over short distance,
provided the correct direction of rolling as provided on the drum
is observed. Alternatively, a mobile crane should be used for
lifting and lowering the drum. A chain‐pulley arrangement may
also be used to lift the drums and deposit the same on ground if
required.
b) In case the drums are to be stored prior to cable laying, they
should be arranged in such a way to leave some space between
them for air circulation. It is desirable that the drums stand on
battens placed directly under the flanges. Overhead covering is
not essential except in heavy rainfall areas or during monsoon.
Cable should however be protected from direct rays of sun by
leaving the battens on or by providing some form of sunshade. In
no case the drums shall be stored in a flat position with flanges
horizontal.
c) For transportation of the cable drums from storage site to work
site, the drum should be mounted on a trailer or an open lorry
and unloaded by mobile cranes.
d) After cable laying, empty cable drums shall be taken return back
by vendor from site at their own risk and cost. Cost of empty
drums shall be deducted from vendor account during final
settlement.
3.3 Cable Laying a) The ground over which the drum is positioned at site should be
Page 8 of 42
GN101-03-SP-06-R2
properly consolidated and jacks placed on both sizes of the drum
to make the pay‐off arrangement stable. Suitable arrangement
be made to stop the drum rotation, during cable laying
preferably by square wooden poles kept temporarily pivoted
over cable roller under the flanges which when required can be
applied on the flange as a brake by personnel manning the drum.
b) The cable should always be paved off from the top of the drum.
The drum must be positioned in such a way that the arrow on
the drum points opposite to the direction of rotation marked on
the drum.
c) It must be ensured that the cable is not dragged over sharp
object or on the road surface, so as to avoid damage to the outer
sheath of the cable.
d) The pulling method to be used shall be approved by BSES. Cable
supplier’s recommended maximum pulling tension shall not be
exceeded.
e) Rollers shall be placed at intervals and the cable shall be pulled
over the rollers. The rollers shall be kept lubricated so that they
rotate freely, minimize friction to the cable in motion. Rollers
shall be positioned at the bends to minimize side wall friction.
The contractor shall ensure that PVC/HDPE sheath of cable is
free from damage due to abrasion.
f) The cable should not be pulled out from the drum by lifting of
the coil while the drum is lying flat on the flange. This leads to
twisting of the armour and cores resulting in permanent damage
to the cable.
g) To avoid ingress of moisture, it must be observed that the end
capping of the cables is not damaged. Cut pieces of the cables
must be capped immediately, before laying of the same is taken‐
up.
3.4 Excavation of a) The excavation of the trenches shall be commenced, with proper
the Trenches co‐ordination with BSES, so that all the necessary clearances for
the route are already obtained from the competent authorities,
well in time.
b) Before opening of the section of the trench, the contractor shall
satisfy himself that the line of the trench is clear of underground
obstructions, by taking out trial pits on the line of the trench.
c) The exact location of each trench shall be approved on site by
BSES. The trenches shall be kept as straight as possible and each
trench shall be excavated to approved formation and
dimensions. If necessary, the trenches shall be adequate shored
by wooden planks and bracing to avoid trench cave‐ins which
would cause injury to the persons and also damage the cables
laid.
d) The bottom of each trench shall be firm and of smooth contour.
The contractor shall take reasonable precautions to prevent
damage to the highway or ground surface from a slip or breaking
away of the sides of the trench.
e) The trench excavation and filling in shall be so executed that all
Page 9 of 42
GN101-03-SP-06-R2
walls, roads, sewers, drains, pipes, cables, structures, places and
things shall be reasonably secured against risk of subsidence or
injury and shall be carried out to the satisfaction of the
authorities concerned. Should, however, a damage to an existing
or other services be made, the Contractor will arrange and pay
for any necessary repair, to make good the damages.
f) Where trenches pass from a footway to a roadway or at other
positions where a change of level is necessary, the bottom of the
trench shall rise or fall gradually. The rate of rise or fall shall be
approved by BSES.
g) Contractor shall ensure that during excavation and until
restoration has been completed, for reasonable access of
persons and vehicles to property or places adjacent to the route.
h) When the excavation of the trenches has been accurately
executed, the contractor shall inform BSES for approval. Laying
of cables or building of structure shall not be started until the
contractor has been advised by BSES to proceed with the work.
3.5 Excavated a) The materials excavated from each trench shall be placed so as
material to prevent nuisance or damage to adjacent ditches, drains
fences, gateways and other property or things. Excavated
material shall be stacked so as to avoid undue interference with
traffic.
b) Where, owing to traffic or for reasons of safety or other
considerations, this is not permissible, the excavated material
shall be removed from the site and returned for refilling the
trench on completion of laying; surplus material shall be
disposed off by the contractor at his own cost.
3.6 Pipes and a) Care shall be taken to make the bend of the pipes or duct lines as
Ducts easy as practicable and in no case of radius less than 3 meters.
Where approved, split pipes may be used on bends, the pipes
being fitted round the cable after laying.
b) All road crossings shall be ducted. This applies to present and
future roads as indicated on the route plans. The pipes and the
ducts shall be laid in an approved manner and shall be
surrounded by 150 mm of PCC (1:2:4)
c) Ducts under the road shall be provided by the contractor, by
non‐disruptive method, if road cutting is not permitted by the
concerned authorities Cable laying shall be done by Horizontal
Direct drilling method (HDD).
d) The cables shall be suitably protected at entry and exit from the
pipes, so that the outer sheath does not come in contact with
the edges of the pipes / ducts. The pipes and ducts shall have
slope so that the seepage water can drain through the small
opening provided on the lower side of the pipe sealing.
e) The pipes and ducts shall be secured to the base at both ends
and at regular interval, throughout the length, so that at no point
the ducts or pipes get suspended over the threaded cable, and
damage the same, thus defeating the very purpose of providing
the pipe / duct.
Page 10 of 42
GN101-03-SP-06-R2
f) At all road crossings at least one spare duct / pipe shall be
provided for future use. The pipe shall be thoroughly cleaned of
obstructions. A draw wire or rope shall be left in each pipe to
facilitate the drawing in of the cables. The duct end shall be
sealed temporarily to prevent the entry of foreign matter. End
caps and permanent markers shall be placed flush with footpath
/ roadways at both the ends. The pipes and ducts shall be
cleaned again immediately before the cables are drawn in.
g) The internal diameter of the pipe / duct should be such that the
cables occupy only 40% of the area of the pipe / duct to avoid
de‐rating.
3.7 Joint Bays The contractor shall provide all help so as to enable jointers to carry out
their work efficiently and expeditiously. The method of securing and
supporting cable joints and cables also the bonding and earthing thereof,
shall be detailed on the drawing. The details shall be approved by BSES
prior to commencement or work. The joint position should be staggered.
3.8 Back filling of a) Filling in of trenches shall not be commenced until BSES has
trenches inspected and approved the cables and accessories at site. The
inspection should be got done on daily basis so that the trenches
do not remain open unnecessarily, to avoid inconvenience to
public.
b) The trench shall be backfilled after putting all protections for
cables.
c) Soft soil shall be backfilled for 300 mm above the cable
protection cover.
d) Caution Tape shall be laid all along the cable route above the soft
soil filling.
e) Complete backfilling shall be done above the caution tape.
3.9 temporary a) Where cables routes are in public highways, footpaths, gardens
Reinstatement etc., the method of reinstatement will be subject to approval by
MCD. All costs incurred will be at the contractor’s expenses.
b) The contractor shall be responsible for proper permanent
reinstatement of the upper levels, which shall be carried out to
the satisfaction of BSES and the MCD authorities concerned.
c) Before finally leaving site, permanent reinstatement shall be
executed by the contractor to the approval of MCD and the
property owners and all costs incurred shall be to the
contractor’s account.
3.10 Permanent a) In public roads and footways the surfaces and foundations shall
Reinstatement be temporarily reinstated by the contractor. After settlement,
of Public Road, temporary reinstatement material shall be removed as necessary
and the permanent reinstatement shall be carried out to the
approval of the appropriate highway authority / MCD. Stone and
pre‐cast concrete paving kerbs and channels shall also be finally
reinstated by the contractor.
b) Temporary reinstatement shall be maintained by the contractor
until commencement of final reinstatement to ensure that the
surface is always safe for the passage of pedestrians and
vehicular traffic.
Page 11 of 42
GN101-03-SP-06-R2
Page 12 of 42
GN101-03-SP-06-R2
Page 13 of 42
GN101-03-SP-06-R2
and asphalted road)
The drawing are shown in annexure IV
The guidelines for road restoration for various type of roads
and surfaces are indicated in annexure V as :‐
‐ Bituminous road Type I (category I & II)
‐ Bituminous road Type II (category III)
‐ Cement concrete road
‐ Kota/Rajasthan stone Road
‐ Brick Road
‐ Interlocking paving tiles.
‐ Agra stone road
‐ Chequered tiles road
‐ Asphalted road
4.0 Testing
Page 14 of 42
GN101-03-SP-06-R2
clearance Road cutting permission shall be taken from competent authority by
vendor. How ever official fees shall be paid by BRPL.
b) Electrical inspector clearance
Electrical Inspector clearance shall be in vendor scope. How ever
official fees shall be paid by BRPL.
5.0 Progress Reporting:
Page 15 of 42
GN101-03-SP-06-R2
7.0.0 Deviations
Deviations from this Specification shall be stated in writing by the contractor. Written approval shall
be obtained from BSES by the contractor. In absence of such a statement, it will be assumed by BSES
that the Contractor complies fully with this specification during execution of the job.
Deviation mentioned in any other submitted tender docs like in GTP, QAP, Old PO, old WO, BRPL
Standard, vendor standards etc. shall not be considered as a deviation at any stage of contract.
The format for approval of deviation attached in annexure # 1
Annexure # 1 – DEVIATION REPORT FORMAT
S. Clause No. of Details about Reason for Approved by (Sign &
NO. Specification deviation deviation Name)
Annexure # 2 – DC HIGH VOLTAGE TEST
Rated Voltage Test Voltage Between Duration in Min.
of cable in KV
Any conductor and Conductor to
metallic sheath / conductor (for
Screen / armour unscreened Cables)
0.65 / 1.1 3 3 15 Min
6.35 / 11 18 30
19 / 33 60 ‐‐‐‐
38 / 66 90 ‐‐‐‐
Reference value for DC High voltage Test.
Page 16 of 42
GN101-03-SP-06-R2
Annexure # 3 – CABLE TRENCH DETAILS
S. No. Cable Size Trench Cable Trench drawing
reference
Width (mm) Depth (mm)
1 1.1 kV LT Cables
a 3.5Cx150 mm2 ‐ Single 400 875 A – 1 (Drg. # 9)
Circuit
b 3.5Cx150 mm2 ‐ Double 400 875 A – 1 (Drg. # 9)
Circuit
c 3.5Cx150 mm2 ‐ Triple 400 875 A – 1 (Drg. # 9)
Circuit
d 3.5Cx300 mm2 ‐ Single 400 875 A – 1 (Drg. # 8)
Circuit
e 3.5Cx300 mm2 ‐ Double 400 875 A – 1 (Drg. # 8)
Circuit
f 3.5Cx300 mm2 ‐ Triple 400 875 A – 1 (Drg. # 8)
Circuit
2 11 KV Cables
a 3Cx150 / 300 mm2 ‐ Single 400 1055 A – 2 (Drg. # 6)
Circuit
b 3Cx150 / 300 mm2 ‐Double 650 1055 B – 1 (Drg. # 7)
Circuit
3 33 kV Cables
a 3Cx400 mm2 ‐ Single Circuit 400 1235 A – 3 (Drg. # 3)
b 3Cx400 mm2 ‐ Double 650 1235 B – 2 (Drg. # 4)
Circuit
c 3Cx400 mm2 ‐ Quadruple 650 1235 B – 2 (Drg. # 5A)
Circuit
d 3Cx400 mm2 ‐ Quadruple 650 1545 B – 3 (Drg. # 5B)
Circuit
e 3Cx400 mm2 ‐ Quadruple 1200 1235 C – 1 (Drg. # 5C)
Circuit
4 66 kV Cables
a 1Cx630/1000 mm2 ‐ Single 650 1445 B – 4 ( Drg. # 1)
Circuit
b 1Cx630/1000 mm2 ‐ Double 1200 1445 C – 2 (Drg. # 2)
circuit
c 3Cx300 mm2 ‐ Double circuit 1200 1445 C – 2 (Drg. # 2A)
Page 17 of 42
GN101-03-SP-06-R2
Annexure # 4 – Standard Road Profile
Page 18 of 42
GN101-03-SP-06-R2
Page 19 of 42
GN101-03-SP-06-R2
Annexure # 5 – Road Restoration Sectional Drawing
Page 20 of 42
GN101-03-SP-06-R2
Page 21 of 42
GN101-03-SP-06-R2
Page 22 of 42
GN101-03-SP-06-R2
Page 23 of 42
Page 24 of 42
Page 25 of 42
Page 26 of 42
Page 27 of 42
Page 28 of 42
Page 29 of 42
Page 30 of 42
Page 31 of 42
Page 32 of 42
Page 33 of 42
Page 34 of 42
Page 35 of 42
Page 36 of 42
Page 37 of 42
GN101-03-SP-06-02
• Helmets
Page 38 of 42
GN101-03-SP-06-02
• Mask
• Jacket
• Shoes
• First Aid Box etc.
Shall be available at site 24x7. Zero tolerance on absence of PPEs to the
working personnel. No excuse shall be acceptable in this regards.
19. EPR/Scanning shall be done by vendor of whole the route and same shall be
submitted to BRPL. This work shall be done by vendor before execution of
job.
20. Jointing TAT- Jointing to start within 48 hrs. and shall be completed by 96
hrs.+1 day.
21. Lifting of cable drums with hydraulic machine, pulling of cable from top end
of drum with pulling machine (hydraulic winch) is mandatory.
22. Violation on barricading guideline and safety norms, a fine of Rs.5000 /day
shall be imposed. BRPL inspector/engineer in-charge shall be empowered to
impose the above penalty.
Page 39 of 42
GN101-03-SP-06-02
Page 40 of 42
Page 41 of 42
Page 42 of 42
BSES Bhawan, Nehru Place, New Delhi- 19
TECHNICAL SPECIFICATION OF 66KV CONTROL & RELAY PANEL
FOR NEW GRIDS
Specification no – SP-CRP-01-R1
1.0
Revision Record
Item/Clause
S.No. Rev.No. Nature of change Approved By
No.:
1 R1 4 Width of cubicle shall be 1250mm KA
2 R1 5.7 Spare terminal in each type of terminal. KA
3 R1 6 Test terminal block for numerical relays KA
and meter.
4 R1 8 Mimic diagram alignment with KA
discrepancy type control switch.
5 R1 11.4 Multifunction meter with digital output KA
with modbus communication.
6 R1 11.4.3 Communication protocol IEC 61850 KA
metering equipment.
7 R1 12.1.5 Communication protocol IEC 61850 in KA
Numerical Relays.
8 R1 12.1.9 All necessary converters shall be consider KA
for communication of numerical relays in
case of optical fiber.
9 R1 12.1.16 Digital input and output of Numerical KA
relays
10 R1 12.2.1.2 Line current differential with distance KA
relays in Line control and relays panel.
11 R1 12.2 Optical fiber communication in line KA
current differential relays with distance
relays in Line control and relays panel.
12 R1 12.4 Auxiliary relays shall NO/NC contact shall KA
be as per BSES requirement.
13 R1 13.0 Minimum no. of annunciation window KA
shall be 24Nos.
14 R2 18.4.1 Addition of Alstom Make Relays VP
BSES Bhawan, Nehru Place, New Delhi- 19
National Standard
Standard Code Standard Description
IS‐1248, Part 1‐ 1993 Direct acting indicating analogue electrical measuring
instruments and their accessories.
IS‐3231, Part 1‐ 1986 Part 2 &3 Electrical relays for power system protection
‐1987
IS‐9000 Part 1 ‐1988 Basic environmental testing procedures for electronics &
electrical items
IS‐13703 1993 Low voltage fuses for Voltages not exceeding 1000V AC or
1500 V DC
IS‐13947 Part 1 ‐ 1993 Low voltage switchgear & control gear
IEC‐60255 ‐ 1989 Specification for electrical relays
IEC 60688 1997 Electrical measuring transducers
be more than or equal to 1250mm, double leaf doors shall
be provided. Doors shall have handles with either built‐in
locking facility or be provided with padlock.
At least two separate gland plates of removable type shall
4.5 Gland Plate be provided for each panel. They shall be of sheet steel of
thickness not less than 3.0 mm.
4.6 Cable Entry Shall be from the bottom
All doors, removable covers and panels shall be gasketed all
4.7 Gaskets
around with neoprene gaskets.
Ventilating louvers, if provided shall have screens and filters.
4.8 Ventilating louvers
The screens shall be made of either brass or GI wires mesh.
The panels shall be fixed on the embedded foundation
channels with intervening layers anti vibration strips made
4.9 Foundation
of shock absorbing materials. Base frames shall be supplied
along with panels.
Equipment on front of panel shall be flush mounted. Cutouts
if any, provided for future mounting of equipment shall be
4. 10 Mounting
properly blanked off with blanking plate no equipment shall
be mounted on the doors.
The center lines of switches, push buttons and indicating
lamps shall not be less than 750mm and that for relays,
4.11 Mounting level
meters and recorders shall be not less than 450 mm from
the bottom of the panel.
The center lines of switches, push buttons and indicating
lamps shall be matched to give a neat and uniform
4.12 Appearance
appearance. Like wise the top lines of all meters, relays and
recorders etc, shall be matched.
5.0 WIRING
1100V grade, single core, stranded copper conductor wires
5.1 Internal wiring
with PVC insulation.
5.2 Size 4 sqmm for CT circuits, 2.5 sqmm for PT and control circuits.
R ph ‐ Red, Yph ‐ Yellow, B ph ‐ Blue, Neutral ‐ Black for CT
5.3 Colour Code
and PT circuits. DC ‐ Grey, AC ‐ Black and Earth ‐ Green
Ferrules marked to correspond with panel wiring diagram
shall be fitted at both ends of each wire. Ferrules shall fit
5.4 Ferrules tightly on the wire. Wires directly connected to trip circuit
shall be distinguished by the addition of red colored
unlettered ferrule.
Fork type, pin type and ring type (as applicable) tinned
5.5 Termination copper lugs to be used. Insulated sleeves shall be provided
at all the wire terminations.
Plastic channels to be used as enclosures. PVC sleeves to be
5.6 Wiring Enclosure
used for inter panel wiring.
BSES Bhawan, Nehru Place, New Delhi- 19
Spare contacts of relays and contactors etc. should be wired
5.7 Spare Contacts
upto the terminal block
When panels are arranged adjacent to each other inter
panel wiring of common bus wires between the panels shall
5.8 Inter panel wiring
be furnished. These adjacent inter panel wiring shall be
clearly indicated in the wiring tables.
Auxiliary bus wiring for AC and DC supplies, voltage
transformer circuits, annunciation circuits and other
5.9 Auxiliary supply
common services shall be provided on the same set of
terminals in all the panels with proper segregation.
7.0 PAINT
Powder coated. Pure Polyester base Grade‐A, structure
7.1 Paint Type
finish.
7.2 Paint Shade RAL7032 ‘Siemens Grey’
7.3 Paint Thickness Minimum 50 microns
Neutral close, ON‐OFF, R‐Y‐B OFF etc.
10.0 EARTHING
All panels shall be equipped with an earth bus securely
10.1 Panel Earthing
fixed.
The material and the sizes of the bus bar shall be 25 x
10.2
Material 6 mm copper flat unless specified otherwise.
All bolted joints in the bus will be affected by
10.3
Earth Bus joints connection of two bolts.
10.4 Hinged Doors Earthed through flexible copper braid.
Instrument and All metallic cases of relays, instruments and other
Relay Earthing panel mounted equipment including gland plate, shall
10.5 be connected to the earth bus by copper wires of size
not less than 2.5 mm2. The color code of earthing
wires shall be green
CT and PT circuit VT and CT secondary neutral shall be earthed at one
10.6
Earthing place only at the terminal blocks through links.
11.0 INSTRUMENTS
11.1 Mounting Flush Mounting
Instruments dial shall be with white
circular scale and black pointer, black
11.2 Scale
numerals and lettering with red marks at
values corresponding to rated values.
11.3 Ammeters and Voltmeters Taut Band, Moving iron type
11.3.1 Size 96x96mm
11.3.2 Provision All panels
11.3.3 Selector switch to be provided
11.3.4 Accuracy Class 0.5 or better.
Multifunction meter Three phase 4 Wire ‐ digital type with
11.4
Modbus Output.
11.4.1 Provision All panels except bus‐coupler
11.4.2 Accuracy Class 0.5 or better.
Provision as per IEC 61850 Protocol with
11.4.3 Communication Capability
serial port communication to be made.
Scrolling facility with LCD display for
11.4.4 Additional facility parameters like power factor, kW, kWh,
kVA, kVAR, current, voltage etc.
BSES Bhawan, Nehru Place, New Delhi- 19
12.0 RELAYS
12.1 Protective Relays ‐ General features
Microprocessor based with provision for
multifunction protection and control,
Technology and
12.1.1 metering, monitoring, User machine interface,
Functionality
communication interface, self‐diagnosis
functionalities.
12.1.2 Mounting Flush Mounting, IP5X
Hardware and software architecture shall be
modular and disconnect able to adapt the
12.1.3 Architecture
protection and control unit to the required
level of complexity as per the application.
Relay shall utilize a user friendly setting and
Programming and operating multilingual software in windows
12.1.4
configuration environment with menus and icons for fast
access to the data required.
Serial communication interface for data
transfer and configuration PC and SCADA
using appropriate protocols as per IEC 61850.
12.1.5 Relay Communication
And in case of communication through optical
fiber then necessary converter needs to be
considered.
UMI with an alphanumeric key pad and graphical
LCD display with backlight indicating measurement
12.1.6 User Machine Interface
values and operating messages. Capability to
access and change all settings and parameters.
Relay shall integrate all necessary protections for
different applications in accordance with IS and
12.1.7 Relay Characteristics IEC. Relay shall provide wide setting ranges and
choice of all IEC, IEEE and other tripping curves
through a minimum of two setting groups.
Facility for recording various parameters of faults
12.1.8 Fault recording with option to set the duration of fault record with
maximum no. of data storage facility
Measurement of Event Recording , Disturbance
General Features of Recording, Harmonic Distortion , RMS Current
Numerical Relays values & Frequency, Peak and Rolling Current
Values, Max. and Average current Values, Phase
12.1.9
and or Neutral Angles , Max. and average voltage,
Power and Energy, Apparent Power and Apparent
Power and Apparent Energy with Time
Synchronization.
BSES Bhawan, Nehru Place, New Delhi- 19
Relay shall be able to detect internal failures. A
12.1.10 Self diagnosis watchdog relay with changeover contact shall
provide information about the failure.
12.1.11 Reset Contacts Self reset contacts except for lockout relays
12.1.12 Operation Indicators LEDs with pushbutton for resetting.
12.1.13 Auxiliary supply As per requirement
Bidder shall provide the reference list of the type
12.1.13 Operational Data
of relays offered
12.1.14 Spare Contacts Minimum 20% Spare contacts
12.1.15 Test Facility Inbuilt with necessary test plugs.
No. of Digital input / Digital output of any type of
relay which shall be used in control and relay
panel shall be as per BSES requirement and signal
12.1.16 DI / DO of Numerical relay list only. Refer the attached tentative signal list of
all feeders (Incoming/Out going, Trasformer &
Transformer Monitoring Unit, Buscoupler & Bus
PT).
Contacts for Transformer Contacts of NIFPS shall be provided in Transformer
12.1.17
NIFPS panel
12.2 Protective Relays ‐ Requirement
12.2.1 For 66kV
12.2.1.1 Bus Bar Protection Numerical type, mounted on a separate panel
with fault recording. CT wise supervision to be
provided.
12.2.1.2 Line Panel Relay‐1 Line current Differential function suitable
through optical fiber communication, Distance
Protection with multiple characteristics i.e Mho ,
Quadrilateral etc.
Relay‐2 Directional and non‐ Directional 3‐phase
over current and earth fault Protection
Combining the functions of Relays‐1 & Relays‐2 in
single relay is not acceptable
Synchronizing Check Relay
Broken Conductor Protection
12.2.1.3 Bus Coupler 3 Phase Over current protection ,
Earth fault protection
12.2.1.4 Capacitor feeder Three phase over current protection
Earth fault protection
Neutral unbalance (separate relay)
Under voltage relay
Over Voltage relay
Timer for ON time delay.
Under Current protection
BSES Bhawan, Nehru Place, New Delhi- 19
13.0 ANNUNCIATION
Static type along with alarm. Annunciations shall
13.1 Type be repetitive type and shall be capable of
registering the fleeting signal. Facia test facility
BSES Bhawan, Nehru Place, New Delhi- 19
14.0 INDICATIONS
Flush mounted Clustered LED type with rear
14.1 Indicating Lamps terminal connections. Lamp Cover to be screwed
type an moulded from heat resistant material
14.1.1 Breaker On Red
14.1.2 Breaker Off Green
14.1.3 Spring Charged Blue
14.1.4 DC control supply fail Amber
14.1.5 Auto trip Amber
14.1.6 Heater Circuit healthy Yellow
14.1.7 Trip Circuit Healthy White
14.1.8 PT supply R, Y, B
14.1.9 Hooter with isolation switch For AC and DC supply failure
Semaphore type indicators shall be provided for
14.2 Position Indicators
mimic diagrams
16.0 ACCESSORIES
16.1 Space heaters Thermostat controlled with switch for isolation
240V, 5A socket to be provided in each panel
16.2 Socket and switch
with on-off switch
Provision for receiving, distribution, isolation
and fusing of DC and AC supplies to various
16.3 MCBs and Fuses
control circuits should be made using MCBs
and Fuses of appropriate ratings.
240V AC illumination lamp controlled by panel
16.4 Panel illumination
door switch to be provided in each panel
19.0 INSPECTION
Cost of Inspection including flight tickets and lodging (Hotel minimum 3 Star) shall be in
scope of Vendor
b) Training of buyers officials (6 officials) on operation and maintenance including relay
setting/operations at site (after installation) shall be included in the proposal/bid
21.0 DEVIATIONS
Deviation from this specification, if any, shall be clearly brought out in the offer. Unless owner
explicitly accepts such deviations, it shall be considered that the offer fully complies with the
specification.
BSES Bhawan, Nehru Place, New Delhi- 19
TECHNICAL SPECIFICATION
FOR
STRUCTURAL WORK
Prepared by Rev: 0
Reviewed by Date:
Approved by
BSES Bhawan, Nehru Place, New Delhi- 19
1.0 GENERAL
1.1 The scope of specification covers design fabrication, proto assembly, supply and erection of
galvanized steel structures for towers, girders, and equipment support structures, towers
which shall be lattice type structures fabricated from structural steel conforming to IS:
2062(latest) The scope shall include supply and erection of all types of structures including
bolts, nuts, washers, hangers, shackles, clamps, anti climbing devices, bird guards, step
bolts, inserts in concrete, gusset plates equipment mounting bolts, structure earthing bolts,
foundation bolts, spring and flat washers, fixing plates and any other items as required to
complete the job.
1.2 The connection of all structures to their foundations shall be by base plates and embedded
anchor/foundation bolts. All steel structures and anchor anchor/foundation bolts shall be
galvanized. The weight of the zinc coating shall be at least 0.610 Kg/m2 for anchor
bolts/foundation bolts and for structural members. One additional nut shall be provided below
the base plate which may be used for the purpose of leveling.
2.1 For design of steel structures loads such as dead loads, live loads, wind loads etc. shall be
based on IS: 802 Part 1 Sec 1
2.2 For material and permissible stresses IS: 802, Part-1, Section-2 shall be followed in general.
However additional requirements given in following paragraphs shall be also considered.
Other members 4
Redundant members 4
2.4 Maximum slenderness ratios for leg members, other stressed members and redundant
members for compression force shall be as per IS-802
2.5 Minimum distance from hole center to edge to adjacent hole shall be minimum 1.5 X bolt
diameter. Minimum distance between center to center of holes shall be 2.5 x bolt diameter.
In order to facilitate inspection and maintenance, the structures shall be provided with
climbing devices. Each tower shall be provided with step bolts not less than 16mm diameter
and 175mm long spaced not more than 450mm apart, staggered on faces on one leg
extending from about 0.5M above ground level to the top of the tower. The step bolt shall
conform to IS: 10238
a) All structures be designed for the worst combination of dead loads, live loads, wind loads
as per code IS 802 seismic forces as per code IS : 1893, importance factor of 1.5, loads
due to deviation of conductor, load due to unbalanced tension in conductor, torsion load
due to unbalanced vertical and horizontal forces, erection loads, short circuit forces shall
be calculated considering a fault level of 31.5KA for 3 secs. IEC-865 may be followed for
evaluation of short circuit forces.
b) Switchyard girders structure shall be designed for the two conditions i.e. normal condition
and short circuit condition. In both conditions the design of all structures shall be based
on the assumption that stringing is done only on one side i.e. all the three (phase)
conductors broken on the other side. Factor of safety of 2.0 under normal conditions and
1.5 under short circuit condition shall be considered on all external loads for the design of
switchyard structures, which are of lattice type.
c) Vertical load of half the span of conductors/string and the earth wires on either side of the
beam shall be taken into account for the purpose of design. Weight of man with tools
shall be considered as 150KGs for the design of structures.
d) Terminal / line take off girders shall be designed for a minimum conductor tension of
1000Kg per sub conductor per phase for 66KV. The distance between terminal girders
and the dead end tower shall be taken as per standard. The design of these terminal
girders shall also be checked considering +/- 30 deg deviation of conductor in both
vertical and horizontal planes. For other girders the structural layout requirements shall
be adopted in design.
f) All support structures used for supporting equipments shall be designed for the worst
combination of dead loads, erection load. Wind load/seismic forces, short circuit forces.
Short circuit forces shall be calculated considering a fault level of 31.5KA for 3 seconds.
g) Foundation bolts shall be designed for the loads for which the structures are designed
BSES Bhawan, Nehru Place, New Delhi- 19
3.1 The contractor shall furnish design, drawing and BOMs to the Owner after award of the
contract. However contractor shall have to prepare and submit any other drawings, bill of
material additionally required during design and construction stage which the Owner feels
necessary. In case Owner feels that any design drawing, BOM are to be modified even after
its approval, contractor shall modify the design & drawings and resubmit the design drawing,
BOM as required in the specification.
3.2 The fabrication drawings are to be provided and furnished by the contractor shall be based
on design approved by Owner. These fabrication drawings shall be based on the design
approved by the Owner. These fabrication drawings shall indicate complete details of
fabrication and erection including all erection splicing details, lacing details, weld sizes and
lengths. BOM in the Performa approved by the Owner shall be submitted. Bolt details and all
customary details in accordance with standard structural engineering practice whether or not
given by the Owner.
3.3 The fabrication work shall start only after the final approval to the design and drawings is
accorded by the Owner. The design drawing should indicate not only profile, but section,
numbers and sizes of bolts and details of typical joints.
3.4 Such approval shall however not relieve the contractor his responsibility for the safety of the
structure and good connections and any loss or damage occurring due to defective
fabrication design or workmanship shall be borne by the contractor.
4.1 The fabrication and erection works shall be carried out generally in accordance with IS 802. A
reference however may be made to IS 800 in case of non-stipulation of some particular
provision in IS 802. All materials shall be completely shop fabricated and finished with proper
connection material and erection marks for ready assembly in the field.
5.1 The component parts shall be assembled in such a manner that are neither twisted not
otherwise damaged and shall be so prepared that the specific camber, if any, is provided. In
order to minimize distortion in member the component parts shall be positioned by using the
clamps, Clips, lugs, jigs and other suitable means and fasteners (bolts and weld) shall be
placed in a balanced pattern. If the individual components are to be bolted, paralleled and
tapered drifts shall be used to align the part so that the bolts can be accurately positioned.
5.2 Sample towers, beams and lightning masts and equipment structures shall be trial assembled
in the fabrication shop and shall be inspected and cleared by contractor based on the design
approval accorded by the Owner before mass fabrication.
BSES Bhawan, Nehru Place, New Delhi- 19
5.3 Pursuant to above the BOM’s along with proto-corrected fabrication drawing shall be
prepared and submitted by the main vendor to Owner as document for information. Such
BOM, which shall be the basis for the Owner to carry out inspection.
6.0 BOLTING
6.1 Every bolt shall be provided with two flat and one spring washer under the nut so that no part
of the threaded portion of the bolt is within the thickness of the parts bolted together. Locking
nut shall be provided with each grouting bolt.
6.2 All steel items, bolts, nuts and washers shall be hot dip galvanized.
6.3 2.0% extra nuts and bolts shall be supplied for erection.
7.0 WELDING
7.1 The work shall be done as per approved fabrication drawings, which clearly indicate various
details of joints to be welded, type of weld, length and size of weld, whether shop or site weld
etc. Symbols for welding on erection and shop drawings shall be according to IS 813. Efforts
shall be made to reduce site welding so as to avoid improper joints due to constructional
difficulties.
8.1 Foundation bolts for the towers and equipment supporting structures and elsewhere shall be
embedded in first stage concrete while the foundation is cast. The contractor shall ensure the
proper alignment of these bolts to match the holes in the base plate.
8.2 The contractor shall be responsible for the correct alignment and leveling of all steel work on
site to ensure that the towers/structures are plumb.
8.3 All foundation bolts for lattice structures are to be supplied by the contractor.
8.4 All foundation bolts shall be fully galvanized so as to achieve 0.610 kg. Per Sq.m. of Zinc
coating as per specifications.
8.5 All foundation bolts shall conform to IS 5624 but the material shall be MS conforming to IS
2062.
The method of grouting the column bases shall be subject to approval of Owner and shall be such
as to ensure complete uniformity of contact over the whole area of the steel base. The contractor
will be fully responsible for the grouting operations.
BSES Bhawan, Nehru Place, New Delhi- 19
10.0 GROUTING
The method of grouting the column bases shall be subject to approval of Owner and shall be such
as to ensure complete uniformity of contact over the whole area of the steel base. The contractor
will be fully responsible for the grouting operations.
11.0 GALVANISING
11.1 All structural steel works and support shall be galvanized after fabrication.
11.2 Zinc required for galvanizing shall have to be arranged by the manufacturer. Purity of zinc to
be used shall be 99.95% as per IS 209.
11.3 The contractor shall be required to make arrangement for frequent inspection by the Owner
as well as continuous inspection by a resident representative of the Owner, if so desired for
fabrication work.
The touch up primers and paint shall consist of Zinc phosphate / Zinc chromate conforming to the
requirements of IS 2074 with a pigment to be specified by the Owner.
13.1 Each part of the fabricated steel work shall be inspected as per approved quality plans and
certified by the Owner or his authorized representative as satisfactory before it is dispatched
to the erection site.
13.2 Such certification shall not relieve the contractor of his responsibility regarding adequacy and
completeness of fabrication.
Copies of all test certificates relating to material by the contractor for the works shall be forwarded
to the Owner.
15.0 ERECTION
The contractor should arrange on his own all plant and equipment, welding set, tools and tackles,
scaffolding, trestles equipments and all other accessories and ancillaries required for carrying out
erection without causing any stresses in the members which may cause deformation and
permanent damage.
BSES Bhawan, Nehru Place, New Delhi- 19
The contractor shall strictly follow at all fabrication, transportation and erection of steel structures,
raw m, materials and other tools and tackles, the stipulations contained in Indian standard code for
safety during erection of structural steel work.
17.0 DEVIATIONS
Deviation from this specification, if any, shall be clearly brought out in the offer. Unless owner
explicitly accepts such deviations, it shall be considered that the offer fully complies with the
specification.
BSES Bhawan, Nehru Place, New Delhi- 19
TECHNICAL SPECIFICATION
FOR
Prepared by Rev: 1
Reviewed by Date:
Approved by
BSES Bhawan, Nehru Place, New Delhi- 19
1.1 This specification is intended to cover the design, manufacture, assembly, testing at
manufacturer’s works, supply & delivery, properly packed for transport F.O.R site of 66KV
Outdoor Switchyard Material and Hardware complete with all accessories for efficient and
trouble free operation.
1.2 In the event of any discrepancy between listed documents, the stipulation of this specification
shall govern.
1.3 The specification shall be read and constructed in conjunction with other sections of bidding
document.
Type, rating, connections etc. of the materials shall be as detailed in the drawings and
annexure. The materials shall be furnished in strict compliance with the same.
Any material or accessory, which may not have been specifically mentioned but which is
usual and / or necessary shall be supplied free of cost to the Owner.
ii) Equipment and material conforming to any other standard, which ensures equal or
better quality, may be accepted. In such cases, copies of the English version of the
standard adopted shall be submitted along with the bid.
BSES Bhawan, Nehru Place, New Delhi- 19
iii) The electrical installation shall meet the requirements of Indian Electricity Rules as
amended upto date and relevant IS Codes of Practice. In addition other rules or
regulations applicable to the work followed. In case of any discrepancy, the more
restrictive rule shall be binding.
4.1 All the ACSR conductors, disc and string insulators, clamps & connectors, hardware’s etc.
will be used in extra high voltage system having characteristics as listed in the annexure.
4.2 All equipments, conductors, hardware’s, insulators & clamps etc. will be installed outdoor in a
hot, humid & tropical atmosphere.
4.3 The maximum temperature in any part of the clamps, connectors, conductors etc at specified
rating shall not exceed the permissible limit as stipulated in the relevant standards.
4.4 All equipments, conductors, clamps, connectors, insulators etc shall be capable of
withstanding the dynamic & thermal stresses of maximum short circuit current without any
damages or deterioration.
4.5 In order to avoid concentration of stresses, all sharp edges of clamps, connectors etc. shall
be rounded off.
4.6 Bi-metallic connectors shall be used for any connection between dissimilar materials.
i) Equipment & material shall comply with description, rating etc. as detailed in this
specification and annexure.
ii) All accessories, fittings, supports, bolts etc. which form part of the equipment or
which are necessary for safe and satisfactory installation and operation of the
equipment shall be furnished.
iii) All parts shall be made accurately to standard gauges so as to facilitate replacement
and repair. All corresponding parts of similar equipment shall be interchangeable.
iv) After the treatment of steel surfaces damaged during transit sufficient quantity of anti-
corrosive paint shall be applied and subsequently finished with two coats of final
paint of approved shade.
BSES Bhawan, Nehru Place, New Delhi- 19
i) The Aluminum Standard conductor and steel reinforced shall have the technical
parameters matching with the requirements given in Annexure. ACSR conductors
shall conform to the latest revision of IS-398.
ii) The material for ACSR conductor shall conform to the following:
Aluminum
The Aluminum strands shall be hard drawn from electrolytic Aluminium rods having
purity not less than 99.5% and a copper content not exceeding 0.04%.
Steel
The steel wire strands shall be drawn from high carbon steel wire rods and shall
conform to the following chemical composition:
Element -% Composition
Carbon - 0.50 to 0.85 Manganese - 0.50 to 1.10 Phosphorous -not more than 0.035
Sulphur -not more than 0.045 Silicon - 0.10 to 0.35
Zinc
The zinc used for galvanizing shall be electrolytic High Grade Zinc of 99.95% purity.
It shall conform to and satisfy all the requirements of IS: 209-1979.
i) All clamps, connectors and hardware’s shall be designed manufactured and tested
as per relevant standards.
ii) All clamps & connectors for connection with ACSR conductors shall have high tensile
Aluminum alloy grade A6 body. U- Bolt and nut for the clamp shall be made of non-
magnetic material e.g. chromium steel.
iii) Bolt, nut, washer, shackle etc. required for other purpose shall be of forged steel with
adequate strength and the surface shall be so protected as to offer maximum
resistance to corrosion. Malleable iron wherever used for any part shall be of best
quality and shall correspond to latest amendments of relevant IS.
iv) Various fittings & accessories of the clamps & connectors shall be so designed as to
eliminate sharp edges & maintain bright smooth surface. All bolts, nuts, rivets etc.
shall have round profiles.
ii) Suspension and tension insulators shall be wet process porcelain with ball and
socket connection. Glazing of the porcelain shall be uniform brown colour, free from
blisters, burrs and other similar defects. Insulators shall be interchangeable and shall
be suitable for forming either suspension or strain strings. Each insulator shall have
rated strength markings on porcelain printed and applied before firing.
iii) When operating at normal rated voltage there shall be no electric discharge between
conductor and insulator which would cause corrosion or injury to conductors or
insulators by the formation of substances due to chemical action. No radio
interference shall be caused when operating at normal rated voltage.
iv) Insulating shall be co-ordinated with basis impulse level of the system. The creepage
distance shall correspond to very heavily polluted atmosphere (31mm/KV)
vi) The design of the insulator shall be such that stresses due to expansion and
contraction in any part of the insulator shall not lead to deterioration. All ferrous parts
shall be hot dip galvanized in accordance with the latest edition of IS: 209. The zinc
coating shall be uniform, adherent, smooth, reasonably bright, continuous and free
from imperfection such as flux, ash, rust stains bulky white deposits and blisters.
vii) Bidder shall make available data on the essential features of design including the
method of assembly of discs and metal parts, number of discs per insulators, the
manner in which mechanical stresses are transmitted through discs to adjacent parts,
provision for meeting expansion stresses, results of corona and thermal shock tests,
recommended working strength and any special design or arrangement employed to
increase life under service conditions.
viii) Insulator hardware shall be of forged steel. Malleable cast iron shall not be accepted
except for insulator disc cap. The surface of hardware must be clean, smooth,
without cuts, abrasion or projections. No part shall be subjected to excessive
localized pressure. The metal parts shall not produce any noise generating corona
under operating conditions.
ix) The insulator hardware assembly and clamps shall be designed for 120KN Tensile
load. The clamps shall be designed for 700 Kg tensile load. Earth wire tension clamp
shall be designed for 1000 Kg tensile load with a factor of safety of two (2).
x) The tension string assemblies shall be supplied along with suitable turn buckle.
BSES Bhawan, Nehru Place, New Delhi- 19
6.0 TESTS
ii) The suspension and tension strings, insulator discs and hardware shall be subjected
to the following, acceptance tests and routine tests:
a) Visual examination
b) Verification of Dimensions as per Cl no. 10.5 of IS: 731
c) Temperature cycle test as per Cl no. 10.6 of IS: 731
d) Puncture test as per Cl no. 10.10 of IS: 731
e) Galvanizing test as per Cl no. 10.12 of IS: 731
f) Mechanical performance test as per IEC-575 Cl. 4
g) Test on locking device for ball & socket coupling as per IEC-372 (2)
h) Porosity test as per Cl no. 10.11 of IS: 731
Acceptance Tests
Samples taken from the zinc ingot shall be chemically analyzed as per IS: 209. The
purity of zinc shall not be less than 99.95%.
The chemical analysis, hardness tests and magnetic particle inspection for malleable
casting will be as per the internationally recognized procedure for these tests. The
sampling will be based on heat number and heat treatment batch
Samples taken from the zinc ingot shall be chemically analyzed as per IS: 209. The
purity of zinc shall not be less than 99.95%.
The chemical analysis, hardness tests and magnetic particle inspection for malleable
casting will be as per the internationally recognized procedure for these tests. The
sampling will be based on heat number and heat treatment batch
The chemical analysis, hardness tests and magnetic particle inspection for fabricated
hardware will be as per the internationally recognized procedure for these tests. The
sampling will be based on heat number and heat treatment batch.
iii) The following, acceptance & routine tests and tests during manufacturing shall be
carried out on the conductor.
Acceptance Tests
NOTE: All the above tests except test mentioned at (i) shall be carried out on
Aluminum and steel strands after stranding only
Routine Tests
iv) The following type, routine & acceptance tests and tests during manufacturing shall
be carried out on the earth wire.
Acceptance Tests
a) Visual check for joints, scratches etc. and length of Earth wire
b) Dimensional check
c) Galvanizing test
d) Lay length check
e) Torsion test
f) Elongation test
g) Wrap test
h) DC resistance test : IS: 398 (Part lll) 1976
i) Breaking load test
j) Chemical Analysis of steel
Routine Tests
Test certificates for type tests shall be from CPRI/ERDA/NABL approved lab, as stipulated in
Indian Standards carried out on similar equipment shall be furnished. If test certificate for any
of the type test is not available, the same shall be carried out free of cost from
CPRI/ERDA/NABL.
i) Certified copies of all tests carried out at works shall be furnished in requisite no. of
copies as stated in the condition of contract for approval of the Owner. The
certificates shall furnish complete identification, date including serial number of each
material and accessory.
ii) Equipment shall be dispatched from works only after receipt of Owner’s written
approval of shop test reports.
iii) Type test certificate on any equipment, if so desired by the Owner, shall be furnished.
Otherwise, the equipment shall have to be type tested, free of charge, to prove the
design.
7.0 SPARES
The Bidder shall submit a list of recommended spare parts for three (3) years of satisfactory
and trouble free operation, indicating itemized price of each item of the spares.
BSES Bhawan, Nehru Place, New Delhi- 19
vi) Any other relevant drawing, documents, calculations and data necessary for
satisfactory installation, operation and maintenance.
9.0 DEVIATIONS
Deviation from this specification, if any, shall be clearly brought out in the offer. Unless owner
explicitly accepts such deviations, it shall be considered that the offer fully complies with the
specification.
BSES Bhawan, Nehru Place, New Delhi- 19
1.0 CONDUCTORS
1.1 ACSR Conductor
1.1.1 Reference standard : IS 398
1.1.2 Code Name : ZEBRA
1.1.3 Type : ACSR
1.1.4 Overall diameter 28.62mm
1.1.5 Stranding no. of wire and diameter :
54/3.18 (Al) 7/3.18 (St)
Number of strands Core 1
1st Layer 6
2nd Layer 12
3rd Layer 18
4th Layer 24
1.1.6 Sectional area of Aluminum : 428.9 sq.mm
1.1.7 Total Sectional area : 484.5 sq.mm
1.1.9 Ultimate Strength (min) : 130.32 KN
1.1.10 Calculated DC resistance at 20 Deg C : 0.06868 ohm/Km
NOTE – The 66KV Main Bus Shall be with TWIN ZEBRA. The equipment bay shall be Single
Zebra.
deg C
4.0 INSULATORS
4.1 Reference standard
4.1.1 String Insulators/Insulator fittings IS 731/ IS 2486
4.1.2 Post Insulators IS 2544
4.2 Type Post Insulator-
Cylindrical solid
Core type,
Suspension &
Tension Insulator
4.3 Service Outdoor
4.4 System details
4.4.1 Voltage 66/72.5KV (Nom/Max)
4.4.2 Nos. of phases 3
4.4.3 Frequency 50Hz
4.4.4 System neutral earthing Effectively earthed
4.5 Insulation Level
4.5.1 Dry power frequency withstand 140KV r.m.s
4.5.2 Wet power frequency withstands 140KV r.m.s
4.6 Impulse withstand 325KV
4.7 Creepage 31mm/KV
Bus Post Insulators shall have minimum cantilever strength of 800Kg and minimum torsion moment
of 500 Kg.
Each insulator shall be furnished complete with the fittings and accessories as listed below
according to requirement
Other standard accessories which are not specifically mentioned but usually provided with insulator
of such type and rating for efficient and trouble free operation.
BSES Bhawan, Nehru Place, New Delhi- 19
TECHNICAL SPECIFICATION
FOR
Earthing Installation shall be carried out as per IS 3043/IEEE 80-2000/IEC-517. The Station
Earth mat shall be designed to meet required minimum area of cross section, current Density,
Resistance, Touch & Step voltage criteria’s mathematically before installation and shall be
tested after installation to ensure the resistance of earth mats to be less than 0.5Ohms. Bare
Earthmat conductors (Strips/ Rods) to be installed below the ground as per safe designed to
spacing in a grid pattern. Each junction of the grid shall be bonded by an electric arc welding
process. Each bond has to be painted by Anti corrosive Paint (Bitumen).All ground wires
installed in conduits shall be insulated. Bare ground conductors shall penetrate concrete
through a PVC Sleeve. Equipment shall be generally being furnished with two separate
ground pads with tapped holes, bolts, nuts & spring washers etc. Metallic frame of all
electrical equipment shall be earthed by two separate and distinct connections to earthing
system, each 100% capacity. Steel Columns, metallic stairs, hand rails etc. of the building
housing electrical equipment shall be connected to the nearby earthing grid conductor by one
Earthing. Metallic Sheaths, Screens and armour of all multi core cables shall be earthed at
both ends. Sheaths and armour of single core cables shall be earthed at switch gear end only
All ground wires installed in conduit shall be insulated. Bare ground wires shall penetrate
concrete through a PVC sleeve.
Earthing of equipment shall generally be furnished with two separate ground pads with
tapped holes, bolts, nuts and spring washers etc. Equipment ground connections, after being
checked and tested shall be coated with anti-corrosive paint.
Metallic frame of all electrical equipment shall be earthed by two separate and distinct
connections to earthing system, each of 100% capacity. Steel columns, metallic stairs, hand
rails etc. of the building housing electrical equipment shall be connected to the nearby
earthing grid conductor by one earthing. Metallic sheaths, screens, and armour of all multi
core cables shall be earthed at both ends. Sheaths and armour of single core cables shall be
earthed at switchgear end only unless otherwise instructed by Owner. Every alternate post of
the metallic fence shall be connected to earthing grid by one GS flat and gates by flexible
lead to the earthed post. Rail for transformers within the plant area shall be bonded across
fish plate and connected to earthing grid at several locations.
For prefabricated cable trays, a separate ground conductor shall run along the entire length
of cable tray and shall be suitably clamped on each cable tray at periodic intervals. Each
continuous laid out lengths of cable tray shall be earthed at minimum two places by GS
flats to Owner's earthing system, the distance between earthing points shall not exceed 30
metre. Wherever earthmat is not available Contractor shall do the necessary connections by
driving an earth electrode in the ground.
Neutral points of transformer shall be solidly earthed by means of 2 Nos 75X10mm GI flat.
Neutral Earth Electrode dimension shall be calculated by Long duration overloading of the
BSES Bhawan, Nehru Place, New Delhi- 19
Soil (i.e.) 40 A/sq.mtr as per IS 3043-1987 Clause 10.3.a Each earthing lead from the neutral
of the Transformers shall be directly connected to two electrodes in treated earth pits which in
turn shall be connected to station earthing grid.
Neutral connections and metallic conduits/pipes shall not be used for the equipment earthing.
Lightning protection system down conductors shall not be connected to other earthing
conductors above the ground level.
Connections between earth leads and equipment shall normally be of bolted type. Contact
surfaces shall be thoroughly cleaned before connections.
All ground conductor connections shall be made by electric arc welding and all equipment
earth connections shall be made by bolting with the earthing pads through flexible insulated
cable leads. Ground connections shall be made from nearest available station ground grid
risers. Suitable earth risers approved by Engineer shall be provided above finished
floor/ground level, if the equipment is not available at the time of laying of main earth
conductor
Resistance of the joint shall not be more than the resistance of the equivalent length of
conductor. For rust protection the welds should be treated with red lead compound and
afterwards thickly coated with bitumen compound.
Earthing conductors buried in ground shall be laid minimum 600 mm below grade level
unless otherwise indicated in the drawing. Earthing conductor’s crossings the road shall be
installed at 1000 mm depth and where adequate earth coverage is not provided it shall be
installed in Hume pipes. Earthing conductors embedded in the concrete floor of the building
shall have approximately 50mm concrete cover.
Minimum earth coverage of 300mm shall be provided between earth conductor and the
bottom of trench/foundation/underground pipes at crossings. Wherever earthing conductor
crosses on runs at less than 300mm distance along metallic structures such as gas, water,
steam pipe lines, steel reinforcement in concrete, it shall be bonded to the same.
Earthing conductors along their run on columns, walls, etc. shall be supported by suitable
welding/cleating at interval of 750mm.
Electrodes shall be embedded below permanent moisture level. Minimum spacing electrodes
shall be decided by calculation referred in IEEE-80 based on soil resistivity value .If soil
resistivity is poor and desired reduction in ground resistance is not achieved by adding more
Grid Conductor Earth pits shall be treated with Permanent maintenance free artificial
treatment compounds as per IEEE 80-2000 Clause14.5d.
On completion of installation, continuity of earth conductors and efficiency of all bonds and
joints shall be checked. Earth resistance at each termination shall be measured as per
BSES Bhawan, Nehru Place, New Delhi- 19
1.3 Ground Electrode shall be 3M long MS rod of required size. These are to be fabricated and
driven into the ground by the side of mat conductors. All connection to the conductors shall
be done by arc welding process.
1.4 Risers are required for connecting the equipment and structures with the ground mat. These
will be MS rod, laid from ground mat to above ground level properly clamped or supported
along the outer edge of the concrete foundation. Connection to the ground mat shall be done
by arc welding and the other end is to be kept free, at least 300 mm above ground level.
1.5 All steel Structures are required to be grounded at two points from ground mat. Laying
supporting and connection at both end are within the scope of this specification.
All Earth Pits provided at the grid substation shall be interconnected with each other by MS
Rod/Flat of adequate size as per symmetrical fault current.. The GI flat shall be buried in the
earth at a minimum depth of 300 mm. Minimum ground coverage of 300mm shall be
maintained between main earth grid and bottom of trench, tunnels, underground pipes other
services / foundations. The earth grid conductor shall be run along the building column wall
etc. with adequate and suitable supports at 750mm interval, if site conditions warrant so. The
riser for equipment earthing shall be 75X10 mm GI flat. The orientation of these risers shall
be such that minimum earthing strip is consumed for equipment earthing.
1.6 To ensure good welding, it should be carried out only after scratching off the galvanization,
dirt, grease etc by thorough cleaning of contact surface. After welding it will be made with
anticorrosive zinc rich paint.
The equipment connection with GI Flat shall be bolted connection. Each bolted connection
shall be taken through two numbers bolts at each joint to ensure tightness and avoid
loosening with passage of time.
In case the GI flat is to cross any obstruction, it shall be laid below the obstruction. At the
crossing of building walls, floors etc the earth conductor shall pass through PVC conduit.
Both ends of conduits shall be sealed after laying of conductor to prevent ingress of water.
Contractor shall use GI strip of following specification: - The GI flat will have minimum 610
gm/mm2 Zinc coating and minimum 86 microns thickness. The galvanization provided shall
be as per IS 2629. The galvanized surface shall consist of a continuous and uniform thick
coating of zinc, firmly adhering to the surfaces of steel. The finished surface shall be clean
and smooth and shall be free from defects like discolored patches, bare spots, and
unevenness of coating, spiky deposits, and blistered surfaces, flaking or peeling off.
All hardware like bolts, nuts, spring and flat washers shall be galvanized; Stainless Steel or
Zinc passivated shall be arranged by contractor.
BSES Bhawan, Nehru Place, New Delhi- 19
S. No Fault current Level (KA) Minimum Required Area of Cross Section (Sq.mm)
2.1.1 5 54
2.1.2 10 108
2.1.3 15 163
2.1.4 20 217
2.1.5 25 271
2.1.6 30 325
2.1.7 35 379
2.1.8 40 433
2.2 However the table below provides general guidelines for selection of Earth Conductor for
each Equipment
The most stringent size of conductor among the two tables above shall be selected
2.3 For switchgear rooms, a local earth conductor of size 50x 6 mm GI flat may be run around
the room below floor to facilitate earthing of equipments in switchgear room. This grid shall be
connected to the main earth grid at minimum two points. Size of the conductor shall be
selected considering the provisions in clause 2.1 and 2.2 above.
BSES Bhawan, Nehru Place, New Delhi- 19
2.4 It is to be ensured that all the switchgears and transformers earth points/ connections are
connected to earth grid and all the main and auxiliary earth grids are interconnected at
minimum two points. With the above arrangement, the return path to the respective
transformer neutral will have a predominantly metallic path. (i.e. Cable armour >>switchgear
earth bus>>external earth flat>>earth grid>>transformer neutral.).
2.5 Where a 66 kV overhead line terminates at the substation, a metallic continuity between the
end tower and the substation earth grid should be established with two independent
connections.
2.6 The GI Flat shall be laid minimum 300 mm below the ground level but for the indoor location,
it shall be embedded in the concrete floor; 50mm below the FFL.
.
2.7 The GI flat shall be welded after scratching off the galvanization locally and thorough cleaning
of contact surface. After welding or bolting arrangement the joint shall be provided with
anticorrosive Bitumen compound or zinc Phosphate paint. Wherever bolted connection is
taken, it shall be taken through two bolts at each joint to ensure tightness and avoid
loosening with passage of time.
2.8 Details of welding, bolting arrangement for various types of joints shall be as per Indian
Standard.
2.9 Two separate and distinct earth connections shall be used for safety earthing of non-current
carrying metallic enclosure of all equipments.
2.10 Two separate and distinct earth connections shall be used for earthing of Lightning / surge
absorber.
2.11 Neutral bushing of oil/dry type Station transformer shall be connected to two independent
earth pits by two no’s separate GI strips.
2.12 Transformer yard fence, structures shall also be connected with the earth mat by 50X6 GI
Flat with the help of flexible copper braid.
2.13 All damages to the galvanized finishes shall be made perfect with zinc rich or bitumen paint.
2.14 RTU, marshalling box of SCADA or any other equipment installed in substation for SCADA
shall not be connected to the earth grid, it shall be connected to separate two earth pits
connected at two separate points of the panel.
BSES Bhawan, Nehru Place, New Delhi- 19
3.1 Direct stroke lightning protection (DSLP) shall be provided in the EHV switchyard by shield
wires. The final arrangement shall be decided after approval of the DSLP calculations. The
Contractor is required to carry out the DSLP calculations and submit the same to the Owner
for approval of the same at detailed engineering stage after award of contract.
3.2 The lightning protection system shall not be in direct contact with underground metallic
service ducts and cables.
3.3 A 40 mm dia. 3000mm long MS earth electrode with test links, CI frame & Cover shall be
provided to connect down conductor of towers with peak. The test joint shall be directly
connected to the earthing system.
3.4 Conductors of the lightning protection system shall not be connected with the conductors of
the safety earthing system above ground level.
3.5 Down conductors used for lightning protection shall be cleated on the structures at 2000mm
interval.
3.6 Connection between each down conductor and rod electrodes shall be made via test joint
(pad type compression clamp) located approximately 150 mm aboveground level.
3.7 Lightning conductors shall not pass through or run inside G.I. conduits.
3.8 All metallic structures within a vicinity of 2000 mm in air and 5000mm below ground shall be
bound to the conductors of lightning protection system.
3.9 In addition to Earth wires above the EHV switchyard, ESE Lightning conductor shall provides
zone of Protection. Snapping of Earth wire does not make accidental situations during
Lightning.
3.10 This ESE Lightning Protection system requires an Air terminal, down conductor, Lightning
Counter & an Earthing System. If the structure is more than 30m height then 2 no’s of down
conductor shall be used for side flashing. The Earthing system should not exceed more than
10Ω.
3.11 A 40mm dia M.S Earth Electrodes with Test Links, HDPE Cover shall be provided to connect
down conductor. The test Link shall be directly connected to earthing system
3.12 Conductors of Lightning Protection system shall not be connected with conductors of Safety
earthing system above ground level. Lightning Earth Pits shall be connected other earthing
conductor below ground level by using Equipotential bonds which will not allow Surge current
to flow from Lightning pits to other Earth pits
BSES Bhawan, Nehru Place, New Delhi- 19
3.13 Connection between each down conductor & Test link shall be located approximately
2000mm above ground Level.
3.14 The Down conductor should be high conductivity bare copper tape with minimum size of 75
Sq.mm
3.16 Tests
3.16.1 The Contractor shall perform all tests and inspection to ensure that material and
workmanship are according to the relevant standards. Contractor shall have to demonstrate
all tests as per specification and equipment shall comply with all requirements of the
specification.
a) The galvanized steel shall be subjected to four one-minute dips in copper sulphate
solution as per IS: 2633.
b) Zinc Coating thickness : As per IS: 4759
c) Uniformity of zinc coating : As per IS: 2633
d) Adhesion Test : As per IS: 2629
e) Mass of zinc coating : As per IS: 6745
f) Chemical Analysis: As per IS: 513 & IS: 1079
3.16.2 The accessories for GSS Groundwire such as Tension Clamps, Copper braided wire etc.
shall conform to & meet the test requirements of IS: 2121.
4.0. DEVIATIONS
Deviation from this specification, if any, shall be clearly brought out in the offer. Unless owner
explicitly accepts such deviations, it shall be considered that the offer fully complies with the
specification.
BSES Bhawan, Nehru Place, New Delhi- 19
NEW GRID
TECHNICAL SPECIFICATION
FOR
K A SENTIL
Prepared by Rev: 4
KUMARAN
This specification is intended to cover the supply and execute work related to interface of all
electrical equipments with RTU panel complete with all materials and accessories for efficient
and trouble free operation. In the event of any discrepancy with the listed documents, the
stipulation of this specification shall govern.
• Supply of SCADA materials - Bay Control Units, Remote Terminal Units with Basic + PLC
Licenses (Basic License - IEC 870‐5‐101,103,104, Modbus, IEC 61850‐8‐1,IEC ‐104
• Laying and Termination of armored Communication cables (Ethernet, Fiber Optic Patch
Cards/Cable,RS 485 cables) between grid devices (Numerical Relays/BCPU,
Transformer Monitoring Modules, Smoke detector, NIFPS panel, MFM, Battery Charger)
to RTU/DCU/Gateway.
• Laying and termination of control cables between grid equipments (control and relay
panel, NIFPS, Battery Units) to RTU for hardwired signals.
• Installation of cable trays with accessories or trench as required for the cabling work.
• Separate earthing bus bars to be provided for RTU panel and it will be directly connected
to grid earthing.
BSES Bhawan, Nehru Place, New Delhi- 19
• All internal wiring between BCU and C&R Panel terminals, All Numerical relays,MFM
(Multifunctional meters) and other grid equipment integration should be under SCADA
vendor’s scope.
• Hardware & software integration of RTU, Bay Control Units along with other equipments
viz. Battery Chargers, Multi Function Meters, Fire Fighting System Signals, Transformer
relays (for OTI, WTI, TPI, AVR, etc.),Smoke Detector Panels, Numerical Relays,
11&33&66KV Control and Relay panel signals etc. shall be in Vendor’s scope.
• FAT and Training arrangements for BSES SCADA team – Travel ,Boarding,
accommodation and local conveyance etc..shall be under SCADA Vendor’s Scope.
2.1 Cables
The following types of cables / wirings will be required for extending signals and commands.
• 2.5 mm2, multi-stranded flexible copper wire, FRLS 1.1KV HRPVC for AC & DC Supply &
1.5 mm2 multi strand cables for other internal wiring for RTU.
• Red(P)and Black(N) color cable core to be used for AC and DC wiring.
• Fiber Optic Cables (GLASS&PLASTIC Types) & Ethernet cables (CAT6) with conduit
pipe for internal connections and Armored Cables for external connections.
• 2 C X 2.5 MM2 cables for external AC / DC Power Supply
• 16 C x 1.5 mm2 for DI (Digital input)
• 3P X 1.5 mm2 for DO (Digital output)
• 2P X 0.5 mm2 Screened Armored PVC cable for external (RTU to BCUs
/MFM/BATT.CHG/Transformer Monitoring Devices) RS 485 connections.
The supplied cable shall be as a latest IS, also refer control cable specification.
Cable Gland
Single Compression cable glands (PVC for RS 485 cables & Brass for Control Cables) of
different sizes for cable entry into the DAU & DCU Panels
Perforated / ladder type (galvanized Iron) with cover for laying the cables.
BSES Bhawan, Nehru Place, New Delhi- 19
To extend the current / voltage / active and reactive power, power factor, etc. to RTU, MFMs,
installed in the C & R panel, should be integrated. (Make: RISHABH or Equivalent with
MODBUS). The outputs of these meters (in groups of 5) connections should be made using
twisted pair screened cable (Typically 22gauge Belden 8761 or equivalent) & two wires (A
and B) connections are daisy chained together and integrated with RTUs. All hardware’s or
protocol converters for having Modbus Protocol output should be in Vendor’s scope.
These should be installed in C & R Panel individually for each feeder/ breakers. All CT & PT
wirings to MFMs and its Configuration should be in Vendor‘s scope.
For the protection of MFMs and RTU cards against Surges and electrical leakages, it is
necessary to install Surge Protection Devices in RTU or C&R Panel and placed in between
RTU & MFM serial loops. The typical diagram for this connection is mentioned in the System
Architecture diagram. (5 MFMs per loop with SPD)
The following parameters of MFM must be available for communication with RTU.
2.3 Numerical Relays with BCU or Bay Control Protection Units for all feeders (11,33,66KV)
Numerical Relays & Bay Control Units should be integrated with Remote Terminal Units. All
hardware’s and protocol converters if required for compatibility with SCADA shall be in
Vendor’s scope.
BSES Bhawan, Nehru Place, New Delhi- 19
The respective BCU must have dual redundancy communication ports (Fiber or Ethernet
port-RJ45) for SCADA connections.
Hot Standby/Dual Power Supply Unit & Redundancy in power source for BCU/BCPU -
Possibility to increase the BCU availability by having a second power supply card in case the
first one fails , if any one Power supply card fails the other one should keep the bay
control unit continuous live.
The following signals are to be taken from Numerical Relays to the BCUs through internal
hard wiring. This list is indicative and signals should not be limited to this. Additional signals
can be taken based on this. – Refer Para 2.8 for detail signals list with data types.
OTI, WTI, TPI, AVR and Transformer auxiliary protection signals should be integrated with an
RTU through serial communication (RS 485 cables) via TMD (REGDA, A-EBERLE relays)
having IEC 61850 Protocol output.
BSES Bhawan, Nehru Place, New Delhi- 19
All field installations of these sensors and its wiring/cabling and configuration along with
hardware’s or protocol converters, if any, should be in Contractor‘s scope. - Refer Para 2.8
for detail Transformer & Transformer Monitoring Device signal’s list with data types.
All signals of Battery Chargers should have MODBUS Protocol output and integrated with an
RTU through serial communication (RS 485) cables.
Laying communication cables through conduit pipe and battery charger signals (Soft & Hard
Signals) integration with an RTU shall be in Vendor’s Scope. - Refer Para 2.8 for detail
Battery Charger signal's list with data types.
2.6 Data Concentrator, Bay Control Units & Remote Terminal Units
For extending the signals from the grid to the Master Control Centre & Backup Control
Centre, BCUs and RTUs are to be installed. BCUs needs to be initially physically integrated
with Numerical relays of respective breakers to enable soft signals and commands for
breakers to be configured there and respectice BCU or BCPU integrated with Remote
Terminal Units through IEC – 61850 protocol. However the options for IEC-60870-103
protocol along with the MODBUS protocol option is required BCUs can be of ABB, Siemens,
Areva,Schneider Electric, etc ., make depending on the type/ make of switch gears. Remote
Terminal Units need to be installed for interface between the BCUs and Control
Centers (Main and Backup) through IEC – 60870 – 104 Protocol. The size of RTU will
depend on the size of the substation, no. of the feeders/ number of signals and command
outputs along with sufficient spares (20%) for future requirement.
All associated equipments and Supply of accessories including software &Operating tool /
multiple user licenses for RTU & BCU, MCBs for DC and AC Supply, DC to DC Converter (in
case station battery voltage level is 220 volts DC), etc. should be in Vendor’s scope.
Hardware & software integration of RTUs, BCU along with other equipments viz. Battery
Chargers, Multi Function Meters, Fire Fighting Systems, Signals, Transformer relays (for OTI,
WTI, TPI, AVR, etc.), Numerical Relays, etc. should be in Vendor’s scope.
In case of more than one BCPU,RTU,DATA Concentrator than these units must be able to
communicate with other units on internal local IPs (Ex – 192.168.0.1) other than LAN IP(Ex-
10.125.107.1) series.
BSES Bhawan, Nehru Place, New Delhi- 19
Approved RTU makes – ABB ,Synergy Systems Solution,Siemens and Schneider Electric
India Limited.
20% Spare for RTU,DCU - Provision for 20 % (Basic IO Count +20% Spare) of the total DI /
DO signals (hard/soft) as a spare should be made available for future requirement.
Spare Ports – 20% Spare ports (Minimum – 3 to 4 No’s Serial ports are essential) for IEC
103/Mod Bus Protocol Connections
20% Spare for BCU,BCPU - Each Control and Relay panel BCU must have 20% (Basic +
20% Spare) of the particular bay DI/DO signals as a spare should be available.
Panel Size & Hardware Capacity - The RTU panel sizing should be capable of
accommodating additional 50% of the basic I/O counts by way of addition of hardware such
as modules, racks, panels, Terminal Blocks of basic I/O counts.
Software Capacity - The RTU software and database generation should be sized to
accommodate for additional 50% of the basic I/O count without requiring software or
database regeneration or License.
2.6.2 Remote database, downloading of RTU from master station/SCADA control center.
2.6.3 RTU shall have the capability of automatic start-up and initialization following restoration of
power after an outage without the need for manual intervention. All restarts shall be reported
to the connected master stations.
2.6.5 Security
As the SCADA system will use public domain, such LAN/VSAT/GPRS/CDMA etc. therefore it
is mandatory to guard the data/ equipment from intrusion/damage/breach of security & shall
have SSL/VPN based security.
2.6.6 Internal battery backup to hold data in SOE buffer memory & also maintaining the time &
date.
2.6.7 RTU must have the capability of time synchronization with a GPS receiver and the GPS at
the control room will be used for this synchronization purpose. In case of failure of the GPS
receiver, the RTUs time synchronization should be through the Master’s SCADA clock.
BSES Bhawan, Nehru Place, New Delhi- 19
2.6.8 GPS for Time Synchronization - The RTU must have inbuilt (or) external GPS with antenna
& internal real time clock to synchronize the IEDs connected to it over their respective
protocol.
2.6.9 Main Processor(CPU in RTU) HOT Retundancy for MCC & BCC communication
Main processor (DCU) /RTU should have adequate capacity for data handling / processing
and main processor/CPU must have required number of communication ports for
simultaneous communication with Master Stations (MCC & BCC), /MFTs and RTU
configuration & maintenance tool.RTU main processor must have HOT redundancy cards
and features for control center communications.
2.6.10 Hot Standby/Dual Power Supply Unit & Redundancy in power source for RTU and
BCU/BCPU - Possibility to increase the RTU,BCU main rack availability by having a second
power supply card in case the first one fails , if any one Power supply card fails the other
one should keep the system continuous live.
RTU/DAU must have multiple location (minimum 5 Locations) data transmission facility VAZ
Master Control Centre, Backup Control Centre, etc.
2.6.12 Protection Devices for RTU,BCPU – All modules (all Digital, Analog Input modules) and
ports (Serial and Ethernet ports) must have in-built or external surge protection devices
and optical isolation
2.6.13 Diagnostic Software & Multi user tool/License for RTU/(Numerical Relay) BCU -
Diagnostic Software tool with licensed version shall be provided to continuously monitor the
operation of the RTU and report RTU hardware errors to the connected master stations. The
software shall check for memory, processor, and input/output ports errors and failures of
other functional areas defined in the specification of the RTU. If any system tries to connect
to RTU for download/ Upload files,itshould be stored as a log in RTU.
At least 50% of the space inside each enclosure shall be unused (spare) space that shall be
reserved for future use. The Contractor shall provide required panels conforming to IEC 529
for housing the RTU modules/racks, relays etc. and other required hardware. The panels
shall meet the following requirements:
BSES Bhawan, Nehru Place, New Delhi- 19
Shall be free standing, floor mounted and height shall not exceed 2200 mm.
All doors and removable panels shall be fitted with long life rubber beading.
All non load bearing panels/doors ,top and bottom portion, rear cover shall be fabricated
from minimum 2.0 mm thickness steel sheet and all load bearing panels, frames, top &
bottom panels shall be fabricated from minimum 3.0 mm thickness steel sheet.
Shall have maintenance access to the hardware and wiring through lockable full height
doors.
Shall have the provisions for bottom cable entry.
All panels shall be supplied with 230V AC, 50 Hz, single-phase switch and 15/5A duplex
socket arrangement for the maintenance.
All panels shall be provided with an internal maintenance lamp, space heaters and gaskets.
All panels shall be indoor, dust-proof with rodent protection, and meet IP54 class of Ingress
protection.
FAN with Filters for RTU panel cooling.
There shall be no sharp corners or edges. All edges shall be rounded to prevent injury.
Document Holder shall be provided inside the cabinet to keep test report, drawing,
maintenance register etc.
All materials used in the enclosures including cable insulation or sheathing, wire troughs,
terminal blocks, and enclosure trims shall be made of flame retardant material and shall not
produce toxic gases under fire conditions.
The safety ground shall be isolated from the signal ground and shall be connected to the
ground network. Safety ground shall be a copper bus bar. The contractor shall connect the
panel’s safety ground to the grid grounding network. Separate grounding is created for
communication equipments and Signal ground shall be connected to the communication
equipment signal ground.
The Ethernet/Fiber optic switches Should be a managed switch and are intended to be
installed in the control room and shall be complaint to IEC-61850 electrical substation
networks and IEEE 1613 standards. Provisions for additional feeders on the Ring
Configuration should be provided on the same switch.
BSES Bhawan, Nehru Place, New Delhi- 19
Laying of Ethernet/Fiber cables for relay/BCU port to the RTU via switch through conduit pipe
and integration with an RTU shall be in Vendor’s Scope.
Switch design should withstand for power substation automation applications that operate in
extremely harsh environments (High and medium voltage S/Stn environments) and it also
withstands vibration, electrical surges, fast transients, electrostatic discharge, and
extreme temperatures and humidity.
Switch features and configuration should be easy to user interface and it must directly
integrate with any other IEC-61850 devices.
The FO switch shall support Multimode fiber and single mode fiber in 10/100Mbps and 1000
Mbps ports on an SFP (simple form factor pluggable), for ease of functionality and
maintenance.
Hot Standby/Dual PSU & Redundancy in power source - Possibility to increase the switch
availability by having a second power source in case the first one fails & should be available
with 48VDC.Each PSU should be connected with a different power source, if any one power
source or Power supply card fails the other one should keep the switch continuous
operation.
20% Spare ports - Each switch must have 20% spare ports for future/back up
requirements.
Link Failure contact alarm - Failure contact alarm shall be achieved by hardware contact
that is activated when a link problem occurs.
Logs and alarms with Time Stamp - Statistics about link status alarms are to be stored with
the accurate timestamp duly tracing all events.
Advanced security features - The FO switches shall support different user levels with
different passwords, including the facility to work with different VLANs, following the
802.1Q standard, port security based on MAC addresses, possibility to disable unused ports,
authentication protocols shall be provided.
BSES Bhawan, Nehru Place, New Delhi- 19
High Speed Implementation of RSTP protocol - The FO switches shall support STP and
RSTP protocols, and shall facilitate for recovery and the fault recovery times shall be within 5
-10msec per switch, always fulfilling the RST protocol.
Tools with License - Diagnostics tool, other necessary tools with a multi user license to be
provided along with the switch.
Mounting Options - Switch should be DIN Rail Mountable & also need to quote for Optional
Wall/Rack Mountable kit.
Network based distributed security by having a firewall on each port of the switch for all the
standard Industrial protocols like MODBUS, IEC-101, IEC-104, DNP3, IEC-103, IEC-61850
should be available.
The FO switch shall have the facility of Port mirroring and the user shall configure one port to
replicate traffic flows of different ports, so the system administrator can monitor the incoming,
outgoing, or all kinds of traffic that is going through the ports under study.
ITU-T G.8032 support for Ethernet Ring redundancy, ensuring fast failure detection is
preferred.
They FO switches shall sustain the stringent levels in temperature range and
electromagnetic immunity defined in the 61850-3, but also the advanced functional
requirements defined for operation with other IEC-61850 devices. The Switch should be
certified on IEC-61850, functional & Environmental specifications by KEMA.
List of Abbreviations
AI ‐ Analog Input/Analog Values
MV ‐ Measured Value
MFM ‐ Multi Function Meter
DCO ‐ Double Command Output
DPI ‐ Double Point Indication
SCO ‐ Single Command Output
SPI ‐ Single Point Indication
RTU ‐ Remote Terminal Units
BCU ‐ Bay Control Units
Protocol
N.Relay
Input/AI soft soft through Hard Wire to signals Type
through N.Relay/BCU RTU Hard wire to
N.Relay/BCU RTU for backup
Breaker ON √
√
Breaker OFF √ DPI
Trip Ckt Healthy √ SPI
Spring Charge √ SPI
Breaker in service √ SPI
Breaker in Test SPI
Auto Trip(86) Operated √ √ SPI
Panel DC Fail √ SPI
L/R Switch in Local SPI
√
L/R Switch in SCADA √ SPI
Relay Int Fault. √ SPI
Over Current Operated √ SPI
Earth Fault Operated √ SPI
BKR Close COMMAND
√ √
IEC‐61850
BKR Open COMMAND DCO
AutoTrip(86) relay reset from Remote √ SCO
3Phase R,Y,B ‐ Current &
Voltage,Active
√
Power,Reactive Power,Power
Factor,Max.Demand,Neu.Current
AI/MV
Fault current and phase indication of
faulty phase viz. R,Y,B, Earth,
Unbalance(O/C & E/F
√
Relay).Disturbance Records,
Fault Graphs for Remote diagnosis
purpose
AI
11 DI + Analog ,
Total Signals ‐ BCPU & RTU Measurand 3 DO 2DI 5DI + 2 DO
Values
Essential inbuilt Spare in BCPU,BCU 3 DI 2 DO
BSES Bhawan, Nehru Place, New Delhi- 19
Protocol
Input/AI soft soft through Input/Output signals Type
N.Relay
through N.Relay/BCU Hard Wire to Hard wire to
N.Relay/BCU RTU RTU for backup
Breaker ON √
√ DPI
Breaker OFF √
Trip Ckt Healthy √ SPI
Spring Charge √ SPI
Breaker in service SPI
√
Breaker in Test SPI
Auto Trip(86) Operated √ √ SPI
VT fuse Blown ‐ Metering. √ SPI
VT fuse Blown ‐ Protection √ SPI
Panel DC Fail √ SPI
L/R Switch in Local SPI
√
L/R Switch in SCADA √ SPI
Relay Int Fault. √ SPI
Over Current Operated(All stages) √ SPI
Earth Fault Operated (All stages) √ SPI
Under Voltage Prot.Operated √ SPI
Over Voltage Prot.Operated √ SPI
REF Operated √ SPI
IEC‐61850
BKR Close COMMAND √
√
BKR Open COMMAND √ DCO
AutoTrip(86) relay reset from Remote √ SCO
3Phase R,Y,B ‐ Current &
Voltage,Active
√
Power,Reactive Power,Power
Factor,Max.Demand,Neu.Current
AI/MV
Fault current and phase indication of
faulty phase viz. R,Y,B, Earth,
Unbalance(O/C & E/F Relay).Fault
voltage and phase indication of faulty
√ AI
phase viz. R,Y,B (Voltage Protection
Relay). Disturbance Records,
Fault Graphs for Remote diagnosis
purpose
16 DI + Analog ,
Total Signals ‐ BCPU & RTU Measurand 3 DO 2DI 5DI + 2 DO
Values
Essential inbuilt Spare in BCPU,BCU 3 DI 2 DO
BSES Bhawan, Nehru Place, New Delhi- 19
Protocol
N.Relay
Input/AI soft Digital Out Put Input/Output signals
Signals ‐ 11KV Bus Coupler
through soft through Hard Wire to Hard wire to Signal
N.Relay/BCU N.Relay/BCU RTU RTU for backup Type
Breaker ON √
√
Breaker OFF √ DPI
Trip Ckt Healthy √ SPI
Spring Charge √ SPI
Breaker in service SPI
√
Breaker in Test SPI
Auto Trip(86) Operated √ √ SPI
Panel DC Fail √ SPI
L/R Switch in Local SPI
√
L/R Switch in SCADA √ SPI
Relay Int Fault. √ SPI
PT MCB ‐ Metering operated √ SPI
PT MCB ‐ Protection operated √ SPI
IEC‐61850
Over Current Operated √ SPI
Earth Fault Operated √ SPI
BKR Close COMMAND
√ √
BKR Open COMMAND DCO
Fault current and phase indication of
faulty phase viz. R,Y,B, Earth,
Unbalance(O/C & E/F
√
Relay).Disturbance Records,
Fault Graphs for Remote diagnosis
purpose
AI
13DI + Analog ,
Total Signals ‐ BCPU & RTU Measurand 3 DO 2DI 5DI + 2 DO
Values
Essential inbuilt Spare in BCPU,BCU 3 DI 2 DO
Additional Protocol
Digital Digital
N.Relay
signals
Signals ‐ 11KV Capacitors Input/AI soft Digital Out Put Input/Output Hard wire to
through soft through Hard Wire to RTU for backup Signal
N.Relay/BCU N.Relay/BCU RTU Type
Breaker ON √
√
Breaker OFF √ DPI
Bank ISO ON
√
Bank ISO OFF DPI
Trip Ckt Healthy √ SPI
Spring Charge √ SPI
IEC‐61850
Breaker in service SPI
√
Breaker in Test SPI
Master Trip(86) Operated √ √ SPI
Bus PT fuse Blown ‐ Metering. √ SPI
Bus PT fuse Blown ‐ Protection √ SPI
Panel DC Fail √ SPI
L/R Switch in Local √ SPI
L/R Switch in SCADA √ √ SPI
Over Current Operated √ SPI
BSES Bhawan, Nehru Place, New Delhi- 19
Earth Fault Operated √ SPI
Under Voltage Prot.Operated √ SPI
Over Voltage Prot.Operated √ SPI
Neg.Phase.sequence Operated √ SPI
Timer Relay operated/Normal √ DPI
Relay Int Fault. √ SPI
BKR Close COMMAND
√ √
BKR Open COMMAND DCO
BANK ISO OPN
√
BANK ISO CLS DCO
Master trip (86)reset from remote √ SCO
3Phase R,Y,B ‐
Current&Voltage,Reactive √
Power,Neu.Current AI/MV
Fault current and phase indication of
faulty phase viz. R,Y,B, Earth,
Unbalance(O/C & E/F Relay).Fault
voltage and phase indication of faulty
√
phase viz. R,Y,B (Voltage Protection
Relay). Disturbance Records,
Fault Graphs for Remote diagnosis
purpose
AI
18 DI + Analog ,
Total Signals ‐ BCPU & RTU Measurand 5 DO 2DI 5DI + 2 DO
Values
Essential inbuilt Spare in BCPU,BCU 3 DI 2 DO
Additional
Protocol
Digital Digital Spare signals
Signal
Signals ‐ 33 & 66KV Incomers/Out Going Input/AI soft Digital Out Put Input/Output (Hard wire to
Type
through soft through Hard Wire to RTU for
N.Relay/BCU N.Relay/BCU RTU backup)
Breaker ON √
√ DPI
Breaker OFF √
Front Bus (89A) ISO ON(In‐Case of O/D)
√ DPI
Front Bus (89A) ISO OFF (In‐Case of O/D)
Rear Bus (89B) ISO ON (In‐Case of O/D)
√ DPI
Rear Bus (89B) ISO OFF (In‐Case of O/D)
LINE ISO (89L) ON (In‐Case of O/D)
√ DPI
LINE ISO (89L) OFF (In‐Case of O/D)
Earth Switch (89LE) ‐1 ON (In‐Case of O/D)
IEC‐61850
√ DPI
Earth Switch (89LE) ‐1 OFF (In‐Case of O/D)
Earth Switch (89LE) ‐ 2 ON (In‐Case of O/D)
√ DPI
Earth Switch (89LE) ‐ 2 OFF (In‐Case of O/D)
Breaker in service (In‐case of I/D BKR) √ SPI
Breaker in Test (In‐case of I/D BKR) √ SPI
Trip coil Ckt Healthy ‐ 1 & 2 √ SPI
Spring Charge √ SPI
Master trip(86) Operated √ √ SPI
SF6 Pressure Low & SF6 Lock Out √ SPI
VT fuse Fail √ SPI
Panel DC Fail √ SPI
BSES Bhawan, Nehru Place, New Delhi- 19
L/R Switch in Local √
DPI
L/R Switch in Remote √ √
LBB Operated √ SPI
Relay Int Fault. √ SPI
Over Current Operated (All stages) √ SPI
Earth Fault Operated (All stages) √ SPI
DIFF.Prot Operated √ SPI
DIST.Ptot Operated √ SPI
BKR CLS COMMAND √
√ DCO
BKR OPN COMMAND √
Front Bus (89A) ISO OPNCOMMAND
(In‐Case of O/D)
√ DCO
Front Bus (89A) ISO CLS COMMAND
(In‐Case of O/D)
Rear Bus (89B) ISO CLS COMMAND
(In‐Case of O/D)
√ DCO
Rear Bus (89B) ISO OPN COMMAND
(In‐Case of O/D)
LINE ISO (89L) OPN COMMAND
(In‐Case of O/D)
√ DCO
LINE ISO (89L) CLS COMMAND
(In‐Case of O/D)
Master Trip(86) relay reset from Remote √ SCO
3Phase R,Y,B ‐Current&Voltage,Active&Reactive
√ AI/MV
Power,PowerFactor,Max.Demand,Neu.Current etc
Fault current and phase indication of faulty phase
viz. R,Y,B, Earth, Unbalance(O/C & E/F
Relay).Fault voltage and phase indication of faulty
phase viz. R,Y,B (Voltage Protection Relay). Fault
√ AI
Differential and Bias current in Line and
Transformer Differential Relay ,Fault distance (in
Distance Relay) ,Disturbance Records,
Fault Graphs for Remote diagnosis purpose
29 DI + Analog ,
Total Signals ‐ BCPU & RTU Measurand 9 DO 2DI 5DI + 2 DO
Values
Essential inbuilt Spare in BCPU,BCU 6 DI 3 DO
Additional
Protocol
Front Bus (89A) ISO ON(In‐Case of O/D)
√ DPI
Front Bus (89A) ISO OFF (In‐Case of O/D)
Rear Bus (89B) ISO ON (In‐Case of O/D)
√ DPI
Rear Bus (89B) ISO OFF (In‐Case of O/D)
TRF ISO (89T) ON (In‐Case of O/D) √ DPI
BSES Bhawan, Nehru Place, New Delhi- 19
TRF ISO (89T) OFF (In‐Case of O/D)
Earth Switch (89LE) ‐1 ON (In‐Case of O/D)
√ DPI
Earth Switch (89LE) ‐1 OFF (In‐Case of O/D)
Earth Switch (89LE) ‐ 2 ON (In‐Case of O/D)
√ DPI
Earth Switch (89LE) ‐ 2 OFF (In‐Case of O/D)
Breaker in service (In‐case of I/D BKR)
√ DPI
Breaker in Test (In‐case of I/D BKR)
Trip coil Ckt Healthy ‐ 1 & 2 √ SPI
Spring Charge √ SPI
Auto Trip(86) Operated √ √ SPI
Differential Operated √ SPI
LBB Operated √ SPI
REF/SEF Prot Operated √ SPI
SF6 Pressure Low & SF6 Lock Out √ SPI
Panel DC Fail √ SPI
L/R Switch in Local √
DPI
L/R Switch in Remote √ √
Relay Int Fault. √ SPI
Over Current Operated √ SPI
Earth Fault Operated √ SPI
BKR CLS COMMAND √
√ DCO
BKR OPN COMMAND √
Front Bus (89A) ISO OPNCOMMAND
(In‐Case of O/D)
√ DCO
Front Bus (89A) ISO CLS COMMAND
(In‐Case of O/D)
Rear Bus (89B) ISO CLS COMMAND
(In‐Case of O/D)
√ DCO
Rear Bus (89B) ISO OPN COMMAND
(In‐Case of O/D)
Trf ISO (89T) OPN COMMAND
(In‐Case of O/D)
√ DCO
Trf ISO (89T) CLS COMMAND
(In‐Case of O/D)
Mastertrip (86) relay reset from Remote √ SCO
3Phase R,Y,B ‐Current&Voltage,Active&Reactive
√ AI/MV
Power,PowerFactor,Max.Demand,Neu.Current
Fault current and phase indication of faulty phase
viz. R,Y,B, Earth, Unbalance(O/C & E/F
Relay).Fault voltage and phase indication of faulty
phase viz. R,Y,B (Voltage Protection Relay). Fault
√ AI
Differential and Bias current in Line and
Transformer Differential Relay ,Fault distance (in
Distance Relay) ,Disturbance Records,
Fault Graphs for Remote diagnosis purpose
28 DI + Analog ,
Total Signals ‐ BCPU & RTU Measurand 9 DO 2DI 5DI + 2 DO
Values
Essential inbuilt Spare in BCPU,BCU 6 DI 3 DO
BSES Bhawan, Nehru Place, New Delhi- 19
Protocol
Digital
Digital Digital Out Put Input/Output Analog Input Signal
Transformer ‐ RTCC/A‐Eberle Signals
Input/AI soft soft through Hard Wire to soft through Type
through TMM TMM RTU TMM
A‐Eberle Unit Faulty/DC Fail √ SPI
Oil Temp Alarm √ SPI
Oil Temp trip √ SPI
Winding Temp Alarm √ SPI
Winding Temp Trip √ SPI
Buchholz Alarm √ SPI
Buchholz Trip √ SPI
PRV TRIP √ SPI
OLTC OSR √ SPI
MOG/LOW Oil level Alarm √ SPI
SPR Trip √ SPI
OSR Main Tank √ SPI
L/R Switch in Local √
DPI
IEC‐61850
L/R Switch in Remote √
Auto Mode √
DPI
Manual Mode √
Fan Fail √ SPI
Tap Changer Fail √ SPI
OLTC Out of Step/Stuck Up/Motor trip √ SPI
Tap Rise/Tap Low Command √
DCO/RCO
Tap Rise/Tap Low Command √
Oil Temp √ AI
Winding Temp √ AI
Tap Position √ AI
3 Analog ,
Total Signals ‐ BCPU & RTU 19 DI 2 Command 1 DI Measurand
Values
Additional
Protocol
Digital Digital signals
Input/AI soft Digital Out Put Input/Output Signal
Signals ‐ 33 & 66KV BusCoupler Hard wire to
through soft through Hard Wire to Type
RTU for backup
N.Relay/BCU N.Relay/BCU RTU
Breaker ON √
√ DPI
Breaker OFF √
Front Bus (89A) ISO ON(In‐Case of O/D)
√ DPI
Front Bus (89A) ISO OFF (In‐Case of O/D)
Rear Bus (89B) ISO ON (In‐Case of O/D)
√ DPI
Rear Bus (89B) ISO OFF (In‐Case of O/D)
IEC‐61850
Earth Switch (89AE‐1) ‐ ON (In‐Case of O/D) √
DPI
Earth Switch (89AE‐1) ‐ OFF (In‐Case of O/D)
Earth Switch (89AE‐2) ‐ ON (In‐Case of O/D)
DPI
Earth Switch (89AE‐2) ‐ OFF (In‐Case of O/D)
Earth Switch(89BE‐3) ‐ ON (In‐Case of O/D) √
DPI
Earth Switch(89BE‐3) ‐ OFF (In‐Case of O/D)
Earth Switch(89BE‐4) ‐ ON (In‐Case of O/D)
DPI
Earth Switch(89BE‐4) ‐ OFF (In‐Case of O/D)
BSES Bhawan, Nehru Place, New Delhi- 19
Breaker in service (In‐case of I/D BKR)
√ DPI
Breaker in Test (In‐case of I/D BKR)
Trip coil Ckt Healthy ‐ 1 & 2 √ SPI
Spring Charge √ SPI
Auto Trip(86) Operated √ √ SPI
SF6 Pressure Low √ SPI
SF6 Lock Out √ SPI
VT fuse‐1 Blown √ SPI
VT fuse‐2 Blown √ SPI
Panel DC Fail √ SPI
L/R Switch in Local √
DPI
L/R Switch in Remote √ √
LBB Operated √ SPI
Relay Int Fault. √ SPI
Over Current Operated (All stages) √ SPI
Earth Fault Operated(All stages) √ SPI
BKR CLS COMMAND √
√ DCO
BKR OPN COMMAND √
Front Bus (89A) ISO OPNCOMMAND
(In‐Case of O/D)
√ DCO
Front Bus (89A) ISO CLS COMMAND
(In‐Case of O/D)
Rear Bus (89B) ISO CLS COMMAND
(In‐Case of O/D)
√ DCO
Rear Bus (89B) ISO OPN COMMAND
(In‐Case of O/D)
AutoTrip(86) relay reset from Remote √ SCO
3Phase R,Y,B ‐ Current ,BUS PT‐01 & BUS PT02
√ AI/MV
3Phase votages.
Fault current and phase indication of faulty phase
viz. R,Y,B, Earth, Unbalance(O/C & E/F
Relay).Fault voltage and phase indication of faulty
phase viz. R,Y,B (Voltage Protection Relay). Fault
√ AI
Differential and Bias current in Line and
Transformer Differential Relay ,Fault distance (in
Distance Relay) ,Disturbance Records,
Fault Graphs for Remote diagnosis purpose
31 DI + Analog ,
Total Signals ‐ BCPU & RTU Measurand 9 DO 2DI 5DI + 2 DO
Values
Essential inbuilt Spare in BCPU,BCU 6 DI 3 DO
BSES Bhawan, Nehru Place, New Delhi- 19
Additional
Protocol
Digital Digital
signals Signal
Signals ‐ 33 & 66KV CAP Bank Input/AI soft Digital Out Put Input/Output
Hard wire to Type
through soft through Hard Wire to
RTU for backup
N.Relay/BCU N.Relay/BCU RTU
Breaker ON √
√ DPI
Breaker OFF √
Front Bus (89A) ISO ON(In‐Case of O/D)
√ DPI
Front Bus (89A) ISO OFF (In‐Case of O/D)
Rear Bus (89B) ISO ON (In‐Case of O/D)
√ DPI
Rear Bus (89B) ISO OFF (In‐Case of O/D)
CAP Bank ISO ON (In‐Case of O/D)
√ DPI
CAP Bank ISO OFF (In‐Case of O/D)
Earth Switch ON (In‐Case of O/D)
√ DPI
Earth Switch OFF (In‐Case of O/D)
Trip coil Ckt Healthy ‐ 1 & 2 √ SPI
Spring Charge √ SPI
Auto Trip(86) Operated √ √ SPI
SF6 Pressure Low & SF6 Lock Out √ SPI
VT fuse Blown √ SPI
Cap Discharge Time √ SPI
Netural Displacement √ SPI
Panel DC Fail √ SPI
L/R Switch in Local/Remote √ √ DPI
LBB Operated √ SPI
IEC‐61850
Relay Int Fault. √ SPI
Over Current Operated √ SPI
Earth Fault Operated √ SPI
Under Voltage Prot.Operated √ SPI
Over Voltage Prot.Operated √ SPI
BKR CLS COMMAND √
√ DCO
BKR OPN COMMAND √
Front Bus (89A) ISO OPNCOMMAND
(In‐Case of O/D)
√ DCO
Front Bus (89A) ISO CLS COMMAND
(In‐Case of O/D)
Rear Bus (89B) ISO CLS COMMAND
(In‐Case of O/D)
√ DCO
Rear Bus (89B) ISO OPN COMMAND
(In‐Case of O/D)
CAP Bank ISO OPN COMMAND
( In‐case of O/D)
√ DCO
CAP Bank ISO CLS COMMAND
( In‐case of O/D)
3Phase R,Y,B ‐ Current&Voltage,Reactive
√ AI/MV
Power,Neu.Current
BSES Bhawan, Nehru Place, New Delhi- 19
Fault current and phase indication of faulty phase
viz. R,Y,B, Earth, Unbalance(O/C & E/F
Relay).Fault voltage and phase indication of faulty
phase viz. R,Y,B (Voltage Protection Relay). Fault
√ AI
Differential and Bias current in Line and
Transformer Differential Relay ,Fault distance (in
Distance Relay) ,Disturbance Records,
Fault Graphs for Remote diagnosis purpose
26 DI + Analog ,
Total Signals ‐ BCPU & RTU Measurand 9 DO 2DI 5DI + 2 DO
Values
Essential inbuilt Spare in BCPU,BCU 6 DI 3 DO
Additional
Protocol
Digital Digital signals
Input/AI soft Digital Out Put Input/Output Signal
Signals ‐ BUS PT‐1&2 Hard wire to
through soft through Hard Wire to Type
RTU for backup
N.Relay/BCU N.Relay/BCU RTU
BUS A (89A) ON
√ DPI
BUS A (89A) OFF
BUS B (89B) ON
√ DPI
BUS B (89B) OFF
Earth Switch (89LE) ‐ 1 ON
√ DPI
Earth Switch (89LE) ‐ 1 OFF
Earth Switch (89LE) ‐ 2 ON
IEC‐61850
√ DPI
Earth Switch (89LE) ‐ 2 OFF
BUS‐A ISO OPN COMMAND
√ DCO
BUS‐A ISO CLS COMMAND
BUS‐B ISO OPN COMMAND
√ DCO
BUS‐B ISO CLS COMMAND
All Sensors Alarm operated Signals √
( 10 to 20 Sensors) SPI
All Manual Call Points ‐ MCP‐
√
1,MCP‐2.etc… SPI MODBUS TCP/IP Protocol.
BSES Bhawan, Nehru Place, New Delhi- 19
Neutral Current MV/MFI
R‐Y Phase Voltage MV/MFI
Y‐B Phase Voltage MV/MFI
B‐R Phase Voltage MV/MFI
R‐Phase Current MV/MFI
Y‐Phase Current MV/MFI
B‐Phase Current MV/MFI
Neutral Current MV/MFI
R‐Y Phase Voltage MV/MFI
Y‐B Phase Voltage MV/MFI
B‐R Phase Voltage MV/MFI
Active Power MV/MFI
Active Energy MV/MFI Modbus
Reactive Power MV/MFI
Power Factor MV/MFI
Maximum Demand MV/MFI
Phase angle 1 MV/MFI
Phase angle 2 MV/MFI
Phase angle 3 MV/MFI
THD Mean Current MV/MFI
THD Mean Voltage MV/MFI
2.8.1.Comments -
Analog signals (Fault Current levels,Disturbance records, Fault graphs for remote diagnosis, etc,)
from Numerical relays needs to be confirmed by vendor before finalize the tender documents.
All the above mentioned signals are compulsory and additional signal (10%) will be considered
during detailed engineering.
Following indications data format should be configured as a DPS (Double point Status) in
Relay(BCPU).
• All Feeders Circuit Breaker ON & Circuit Breaker OFF
• All Feeders BUS Isolators (89A,89B,89L,89T) - ON & OFF
• All Earth Switches ON & OFF
Following command data format should be configured as a DPC (Double point control) in
Relay(BCPU).
• All Feeders Circuit Breaker - Open & Close
• All Feeders BUS Isolators (89A,89B,89L,89T) - Open & Close
BSES Bhawan, Nehru Place, New Delhi- 19
2 Space for Energy Meter – Only Space (Length - 185 mm & Height - 256 mm with CT, PT,
Auxiliary Supply terminals & wiring) without cut out is required to install energy meters.
3 Power Supply for Routers/ Gateway (IT Equipments) through an existing battery bank via DC to
DC Converters (Input: 48 VDC/220 VDC, Output: 12 Volt DC) or as per the requirements of
Routers.
4 Any other wiring / cabling if required due to non availability of serial communication
/MODBUS/IEC 61850 protocols (with justified reason) should be hardwired and that is in
Contractor’s scope.
5 Suitable transducers with an output of 4-20 mA have to be installed in the RTCC /Battery
charger if required and the outputs of these transducers should be extended to terminal for
further extension to the RTU.
6 The C & R ,RTCC,Battery Charger Panel should have additional spare contacts (potential free)
for all SCADA signals – Refer Signal List 2.8
7 Warranty (5 Years) for SCADA products - All Supplied SCADA material should cover
warranty for the duration of 5 years & Warranty period will start after successful
commissioning of the SCADA equipments at site. If any SCADA materials found faulty
during warranty period should be replaced within two weeks.
9 FAT expenses for BSES SCADA team (2 Persons) – Air & Local Travels, boarding and
Lodging to be arranged by vendor during FAT inspections.Complete expenditure (Air & Local
Travel, boarding and Lodging) comes under vendor scope.
10 Loose Spares (5%) - loose Spare Materials for following items with below mentioned quantity
to be supplied for emergency back up/maintenance purpose.
BSES Bhawan, Nehru Place, New Delhi- 19
• LIU Unit – 1 No
• Fiber Optic Patch Cards with Connectors - 10% of total installed cables.
• Surge Protection devices installation between RTU & MFM Serial loops.
• All modules (All Digital, Analog Input modules in BCPU and RTU) and ports (Serial
and Ethernet ports) must have in-built or external surge protection devices and optical
isolation.
12 All the above features are indicative only and detailed engineering and deviation will be
analyzed just before actual procurement and with discussion through a supplier/ vendor.
5.0 DEVIATIONS
Deviation from this specification, if any, shall be clearly brought out in the offer. Unless the
owner explicitly accepts such deviations, it shall be considered that the offer fully complies with
the specification.
85E:5
66 kV 3-CORE CABLE
Specification no - SP-EWH2-3C-OO
Page I of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
1.0 Scope
This specification covers technical requirements of design, manufacture, testing at
manufacturer’s works, packing, forwarding, supply and unloading at stores/site, performance of
66 kV 3Cx300 sq. mm cable complete with all accessories for trouble free and efficient
operations.
Indian Standards
IS 8130-1984 Specification for Conductor for insulated electric cables & flexible
Cords
IS : 3975 -1999 Mild steel wires, formed wires and tapes for Armouring of Cables
IS: 5216 Guide for Safety procedures and practices in electric works
IEC Standards
___________________________________________________________________________________________
Page 2 of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
3.4 Semi Semi-conducting water blocking tapes shall be applied over the
conducting conductor, suitable for continuous operating conductor
water blocking temperature of 90 deg C.
tape
3.5 Conductor The conductor screen shall consist of extruded semi conducting
Screen compound which shall be fully compatible with the conductor and
extruded insulation.
3.7 Insulation The insulation screen shall consist of extruded semi conducting
Screen Compound which shall be fully compatible with extruded
insulation. Insulation screen shall be firmly bonded to the
insulation
3.8 Make of TR-XLPE of Dow or Borealis (any deviation to above shall not be
insulation and acceptable unless and until it has been specially approved by
semi BSES prior to sourcing of compounds and manufacturing of
conducting cable).
screen
3.9 Core The ovality of the core shall not be more than 5%.
3.10 Inner Semi-conducting water swellable tapes shall be applied over the
Longitudinal extruded semi-conducting core screening.
water sealing
bedding Nominal Thickness of the Swellable Tape = 0.3 mm
The swell speed shall be greater 12mm/minute
3.11 Metallic Screen The metallic Screen shall consist of a layer of annealed copper
tape of minimum 0.1mm thickness and shall be applied over the
___________________________________________________________________________________________
Page 3 of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
3.12 Inner Semi-conducting water swellable tapes shall be applied over the
Longitudinal metallic screen again with a minimum overlap of 10 %.
water sealing
bedding (2nd Nominal Thickness of the Swellable Tape = 0.3 mm
layer) The swell speed shall be greater 12mm/minute
3.13 Core Cores shall be identified by coloured strips (Red, Yellow, Blue),
Identification applied helically / longitudinally over the copper tape.
3.14 Optical Fiber 30-Fiber optical Fiber cable, with such a construction to facilitate
Cable (as one to continuously operate at 80 deg C to be used without any
of the fillers) increase in loss beyond permissible limit.
3.16 Laying up of All the 3-Core, along with Fillers, water-blocking yarn and optical
Cores fiber cable shall be laid in the suitable right hand lay.
___________________________________________________________________________________________
Page 4 of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
3.18 Armour The armour shall be of galvanized round steel wires of minimum
4 mm dia complying the requirements of IS 3975:1999 with latest
amendments.
3.19 Binder Tape Rubberized cotton tape shall be wrapped with approx. 10%
overlap over armour
3.20 Outer Sheath The outer sheath shall consist of extruded black colored HDPE
type ST 7 as per IEC 60502-2 with anti termite protection. The
minimum thickness shall be 3 mm at any point.
Semi conductive layer either extruded or graphite coating shall
be provided over the Outer Sheath.
3.21 Cable Rating The cable size shall be suitable to carry rated load current on 66
kV continuously without exceeding the maximum conductor
temperature of 90 deg. C.
3.22 Drum Length 250m ± 5 % (short lengths not acceptable except the last length
and minimum acceptable short length shall be 100m). The
overall quantity tolerance shall be as purchase order.
3.23 Embossing The extruded outer sheath shall be embossed with meter
marking at interval of 1 metre. The ”A” end meter marking and
“Z” end meter marking and the drum lengths shall be printed on
the drum flange along with other markings. The outer sheath
shall also be embossed with (min.)
a) Voltage designation
b) Type of construction/cable code (i.e. A2XW2Y)
c) Number of core and nominal cross sectional area.
d) Type of cable “Electric Cable”.
e) Manufacturers name & trade mark
f) Name of buyer (e.g. BSES)
g) Month & year of manufacturing
h) Batch no / Lot no.
i) Sequential length marking.
j) Purchase Order Number and Date
3.24 Joints and The 3-Core Joints and Terminations to be used with the cable
Terminations shall be with proven design and fully type tested as per IS 60840.
___________________________________________________________________________________________
Page 5 of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
5.1 Routine test Each drum length of cable shall be subjected to the following
tests
Type test report of not more than five (5) years shall be
submitted for the same type, size and rating of the cable offered,
along with the bid.
5.3 Short Circuit The bidder shall furnish short circuit test report of 26.3 kA for 3
Test of Armour seconds from CPRI/ERDA for the same voltage, size and design
of cable.
This short circuit test shall be preceded and succeeded by high
voltage, Partial Discharge, Armour Resistance and Conductor
Resistance Test. Test report shall not be more than five (5) years
old.
5.3 Acceptance Shall be conducted as per IEC: 60840: 2004 / IS: 7098-III: 1993
Tests and approved QA plan for each lot of cable.
5.4 Special Tests The following tests shall be carried out as special tests
Hot set test for XLPE insulation as per Clause 10.9 of IEC-
60840/ IS 10810 Part 30
In the event of any discrepancy in the test reports i.e test reports
not acceptable or any type tests(including special / assitional
tests,if any) not carried out , same shall be carried out without
any cost implication to BSES before dispatch of cable.
5.6 Test certificates Three sets of complete test certificates shall be submitted along
with the dispatch documents.
___________________________________________________________________________________________
Page 7 of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
6.4 Drawing and Standard size paper A0, A1, A2, A3, A4
document sizes
6.5 No. of drwgs. / As per Annexure – A
Documents
required
at different
stages
7.2 Pulling eye & A cable pulling eye shall be provided at “Z” end of cable on each
sealing of drum. Suitable fillings/putty shall be used for sealing gap
Cable ends between outer sheath and pulling eye. Heat shrinkable sleeves
with the pulling eye shall also be provided. The pulling eye shall
be directly connected to the conductor and be capable to
withstand a tensile load of 30N / sq mm of conductor area. The
“A” end of the cable shall be sealed with heat shrinkable cap.
Drawing of the pulling eye shall be submitted along with the bid
for review.
7.5 Handling & Manufacturer instruction shall be followed. Detail handling &
Storage storage instruction sheet / manual needs to be furnished before
commencement of supply.
7.6 Transit damage The seller shall be responsible for any transit damage due to
improper packing.
9.0 Deviations
9.0 Deviation from Deviations from this Specification shall be stated in writing with
the the tender by reference to the Specification clause/GTP/Drawing
Specification. and a description of the alternative offer. In absence of such a
statement, it will be assumed by the Buyer that the Seller
complies fully with this specification.
___________________________________________________________________________________________
Page 9 of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
1.1 Design, manufacture, testing at manufacturer works before dispatch, packing, delivery
including unloading and stacking at site/store of 38/66kV 3Cx300 sq. mm cable as per BOQ and
submission of all documents.
___________________________________________________________________________________________
Page 10 of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
___________________________________________________________________________________________
Page 11 of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
___________________________________________________________________________________________
Page 12 of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
___________________________________________________________________________________________
Page 13 of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
___________________________________________________________________________________________
Page 14 of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
___________________________________________________________________________________________
Page 17 of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
Name of manufacturer:
Drawing No and date:
___________________________________________________________________________________________
Page 18 of 19
66 kV 3-CORE CABLES– SP-EWH2-3C-00
___________________________________________________________________________________________
Page 19 of 19
Specification for HT Cable
Index
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 2 of 19
SPECIFICATION FOR HT CABLE
Materials and methods used in the manufacture of Cables shall conform to the latest edition of
following –
Indian Standards
IEC Standards
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 3 of 19
SPECIFICATION FOR HT CABLE
2.3.0 Longitudinal water sealing Shall be achieved by water swelling powder/fibres in the
of conductor interstices of the conductor. The powder/fibre/yarn shall
turns into jelly, when in contact with water
2.4.0 Semi conducting separator Semi-conducting separator tapes shall be applied over
tape the conductor, suitable for continuous operating
conductor temperature of 90 deg C.
2.5.0 Conductor screen The conductor screen shall consist of extruded semi-
conducting XLPE which shall be fully compatible with
the conductor and extruded insulation. Outer surface of
semiconductor screen shall be supper smoothing,
cylindrical and firmly bonded to the overlaying
insulation.
2.6.0 Insulation The extruded XLPE insulation shall be of very high
degree of purity. The average thickness shall not be
less than nominal value as given in annexure C. The
minimum thickness at any point shall not be less by
more than 10% of the nominal value. Percentage
eccentricity of the insulation shall not be more than
10%.
2.7.0 Insulation Screen The insulation screen shall consist of extruded semi-
conducting XLPE which shall be fully compatible with
extruded insulation. Insulation screen shall be firmly
bonded to the insulation
2.8.0 Make of insulation and DOW – TR XLPE or equivalent of Borealis
semi conducting screen (any deviation to above shall not be acceptable unless
and until it has been specially approved by BSES prior
to sourcing of compounds and manufacturing of cable.
2.9.0 Core The ovality of the core shall not be more than 5%.
2.10.0 Inner Longitudinal water Semi-conducting water swellable tapes shall be applied
sealing bedding over the extruded semi-conducting core screening.
2.11.0 Metal screening (if The metallic screen shall consists of a layer of copper
required to meet the short wires, followed by a copper tape applied in helical form
circuit rating)
2.12.0 Outer Longitudinal water Semi-conducting water swellable tapes shall be applied
sealing bedding (when over the metallic screening.
metallic screening is
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 4 of 19
SPECIFICATION FOR HT CABLE
provided)
2.13.0 Characteristic of water a) Nominal thickness = 0.3mm
swellable bedding b) Swell height shall be >= 12mm in one minute.
2.14.0 Metallic sheath The metallic sheath shall consist of EITHER lead alloy
‘E’ seamless sheathing with minimum thickness in
accordance with Table-6 of IS 7098 Part – III (1993) OR
corrugated aluminium sheathing with minimum
thickness of 1.75mm and nominal thickness of 1.8mm,
provided with high-viscosity bitumen-based compound
coating, in conjunction with textile tape as carrier
material for corrosion protection of the outer surface of
corrugated aluminium sheathing. Further the
corrugations shall be filled with compatible filler material
to provide smooth round surface over the aluminium
corrugated sheathing, so as to prevent ingress /
traveling of water along the corrugations.
2.15.0 Outer Jacket The outer jacket shall consist of extruded black colored
HDPE type ST 7 with anti termite protection. The
minimum thickness at any point shall not fall below 85%
of the nominal thickness by more than 0.1mm. Nominal
thickness shall be 4mm.
2.16.0 Semi conductive layer over Semi conductive layer shall be either extruded or
the outer jacket graphite coating
2.17.0 Cable Rating The cable size shall be suitable to carry rated load
current on 66KV continuously without exceeding the
maximum conductor temperature of 90 deg. C.
2.18.0 Drum Length 500 Mtr +- 5 % (short lengths not acceptable except the
last length and minimum acceptable short length shall
be 250 mtrs.). The overall quantity tolerance shall be as
purchase order.
Manufacturer shall not be allowed to put two cable
pieces of different short length in same cable drum.
2.19.0 Embossing The extruded outer sheath shall be embossed with
meter marking at interval of 1 metre. The ”A” end meter
marking and “Z” end meter marking and the drum
lengths shall be printed on the drum flange along with
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 5 of 19
SPECIFICATION FOR HT CABLE
4.1.0 Routine test Each drum length of cable shall be subjected to the following tests
- Measurement of the electrical resistance of the conductor shall be
carried out as per the provisions of Clause 10.5 of I.E.C.
Publication No.60840 The measurement shall be made on the
conductors of each cable length. The D.C. resistance of the
conductor at 20 deg. C shall not exceed the maximum value
specified in I.E.C. Publication No.60228.
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 6 of 19
SPECIFICATION FOR HT CABLE
more than five (5) years shall be submitted for the type, size and
rating of the cable offered, along with the bid.
-If the manufacturer’s lab is accredited by govt./authorized body
then it shall be acceptable for type testing.
-All type tests shall be carried out in accordance with Clause 12 of
IEC-60840 and in accordance with the sequence prescribed
therein.
4.3.0 Acceptance Shall be conducted as per IEC: 60840 / IS: 7098 (P-3) and
Tests approved QA plan for each lot of cable.
4.4.0 Special Tests The following tests shall be carried out as special tests
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 7 of 19
SPECIFICATION FOR HT CABLE
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 8 of 19
SPECIFICATION FOR HT CABLE
- Name of manufacturer
- Nominal sectional area of the conductor of the cable
- Type of cable and voltage for which it is suitable
- Length of the cable on the drum, with “A” end and “Z”
end markings.
- Purchase order number with SAP item code.
- Year and month of manufacturing.
- Direction of rotation of drum (an arrow) and
- Net weight of cable in drum and gross weight of cable
with drum.
- Batch no or Lot no.
6.4.0 Shipping The seller shall give complete shipping information
concerning the gross weight, size of each packing.
6.5.0 Handling & Storage Manufacturer instruction shall be followed. Detail
handling & storage instruction sheet / manual neds to
be furnished before commencement of supply.
6.6.0 Transit damage The seller shall be responsible for any transit damage
due to improper packing.
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 9 of 19
SPECIFICATION FOR HT CABLE
8.0 Deviations
8.0.0 Deviation from the Specification. Deviations from this Specification shall be
stated in writing with the tender by
reference to the Specification
clause/GTP/Drawing and a description of
the alternative offer. In absence of such a
statement, it will be assumed by the Buyer
that the Seller complies fully with this
specification.
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 10 of 19
SPECIFICATION FOR HT CABLE
1.1 Design, manufacture, testing at manufacturer works before dispatch, packing, delivery
including unloading and stacking at site/store of 38/66kV single core cable as per BOQ
and submission of all documents.
1.2 BOQ as following -
Sr Purchaser Material/Equipment Location Unit Quantity
No Equipment Tag description
No / SAP code
1 e.g. Delhi km e.g. 10
2 e.g. Goa km e.g. 10
3
4
5
6
7
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 11 of 19
SPECIFICATION FOR HT CABLE
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 12 of 19
SPECIFICATION FOR HT CABLE
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 13 of 19
SPECIFICATION FOR HT CABLE
1 Name of manufacturer
2 Country of manufacturer
3 Type of cable
4 Standard according to which cable
is manufactured
5 Rated voltage kV 38/66
6 Highest system voltage kV 72.5
7 System frequency Hz 50
8 No of phases per circuit Nos 3
9 System earthing Solidly
grounded
10 Rated short time current of kA
conductor
11 Rated short time current of metal kA
sheath (alone)
12 Rated short time current of metal kA
screen (if provided)
13 Rated short time current of metal kA 19
sheath and screen
14 Duration of short circuit current Sec 1
15 Impulse withstand voltage 1.2/50 kVp 325
micro sec wave
16 Power frequency withstand kV(rms) 140
voltage
17 Conductor
a Nominal cross sectional area sqmm 1000 / 630
b Type class of conductor. Compacted
Stranded
Circular
c Material of conductor Aluminum
d Flexibility class of conductor Class -2
e Minimum numbers of strands Nos
f Diameter of strands before Mm / mm
compaction. (nominal / Minimum)
g Material of longitudinal water
sealing filling of conductor
18 Details of semi conducting tape
over the conductor
19 Conductor Screen
a Material and type
b Minimum thickness mm 0.8
c Make and grade of semi
conducting compound.
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 14 of 19
SPECIFICATION FOR HT CABLE
B Diameter of wire mm
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 17 of 19
SPECIFICATION FOR HT CABLE
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 18 of 19
SPECIFICATION FOR HT CABLE
Name of manufacturer:
Drawing No and date:
___________________________________________________________________________________________
Specification No – SP-EWH2-01-00 Page 19 of 19
SP-EWHP-01- R4
Index [R4]
Page
Annexures:
Annexure A: ………………………… 18
Scope, Documentation and Delivery Schedule
Annexure B: ………………………… 20
General Technical Particulars (GTP)
Annexure E: ………………………… 30
(Attachments)
Page 2 of 42
SP-EWHP-01- R4
Revision Record
Note:
Revisions made in R4 are marked by symbol [R4] at the respective text or drawing
throughout the Specification.
[R4]
Page 3 of 42
SP-EWHP-01- R4
Page 4 of 42
SP-EWHP-01- R4
General Specification
The cables shall be designed, manufactured and tested in accordance with the
following National Standards and IEC Standards.
National Standards
IS 7098 Part-2 Cross linked polyethylene (XLPE) insulated PVC sheathed cables
for working voltages from 3.3 kV up to and including 33 kV.
IS 5831 : 1984 PVC insulation & sheath of electric cables.
IS 10810 : 1984 Methods of test for cables.
IS 8130 : 1984 Conductors for insulated electric cables and flexible cords.
IS 3975 : 1999 Mild steel wires, formed wires and tapes for armouring of cables.
IS 0462 (Part 1) / 1983 Fictitious Calculation Method for determination of dimensions of
protective covering of cables
International Standards
Page 5 of 42
SP-EWHP-01- R4
Page 6 of 42
SP-EWHP-01- R4
Description of each item mentioned in the Specification (the text, BOQ, GTP or any
site specific requirement) shall be followed, along with IS: 7098 – Part 2.
Page 7 of 42
SP-EWHP-01- R4
Page 8 of 42
SP-EWHP-01- R4
2.1.6A Copper Tape Copper Tape shall be applied helically over the layer
formed after application of insulation screen, water-
swellable tape and identification strip. [R4]
2.1.9 Inner Sheath Extruded Inner Sheath of Black PVC type ST-2
(IS 5831)
Page 9 of 42
SP-EWHP-01- R4
Page 10 of 42
SP-EWHP-01- R4
4.0.0 Testing & Inspection Tests shall be carried out in accordance with IS 7098
(Part-2).
a) Type Tests 1. Cables must be of type tested quality. Type Test
Reports shall be submitted for the type, size and
Page 11 of 42
SP-EWHP-01- R4
Page 12 of 42
SP-EWHP-01- R4
Page 13 of 42
SP-EWHP-01- R4
5.0.2 Documents after award Within 15 days, the seller has to submit four sets of
of contract above-mentioned drawings, along with one soft copy
for buyer’s approval.
5.0.3 Final As-Built Drawings One soft copy of all documents, including type &
routine test certificates.
Page 14 of 42
SP-EWHP-01- R4
6.0.3 Short length of cables Manufacturer shall take prior approval from
Purchaser for any supply of short length cables.
Page 15 of 42
SP-EWHP-01- R4
ensured.
b) Drum Identification Direct marking (i.e. text painting through stencils,
Markings: etc.) shall be done on the drums, instead of attaching
labels, which may be misplaced/lost over a period of
time. [R4]
1. Drum identification number
2. Cable voltage grade
3. Cable code (e.g. A2XFY, etc.)
4. Number of cores and cross sectional area
5. Cable quantity, i.e. cable length (metre)
6. Purchase order number & date
7. SAP item code
8. Total weight of cable and drum (kg)
9. Manufacturer’s Name
10. Buyer’s name
11. Month & Year of Manufacturing
12. Direction of rotation of drum
13. Cable length final end-markings
(i.e., reading at the inner end and reading at the
outer end, just before packing, shall be marked
on the drum.)
c) Shipping information The seller shall give complete shipping information
concerning the weight, size of each package
d) Transit damage The seller shall be responsible for any transit
damage due to improper packing.
e) Type of Drum Steel / wooden drums, as per relevant IS / IEC.
(Wooden drums shall be with M.S. spindle plate with
nut-bolts)
f) Cable Drum handling The drums shall be with M.S. spindle plate (with nut-
bolts) of adequate size to suit the spindle rods,
normally required for handling the drums, according
to expected weight of the cable drums. [R4]
Page 16 of 42
SP-EWHP-01- R4
Page 17 of 42
SP-EWHP-01- R4
Annexure – A
1. Scope
a) Document Submission
Submission of drawings, calculations, catalogues, manuals, test reports shall be as
follows. (Also refer clause 5.0.0 – Drawings, Data and Manuals.)
Legend:
[R4]
Documents After award of contract Final documents
Along with offer - for Approval (after Approval)
GTP 3 copies ** 1 soft copy ** 1 soft copy + CD
** Soft copy and CD shall contain documents duly approved, signed and scanned.
Page 18 of 42
SP-EWHP-01- R4
Page 19 of 42
SP-EWHP-01- R4
Annexure - B
Note: [R4]
8.0 Conductor
Page 20 of 42
SP-EWHP-01- R4
10.0 Insulation
A Insulation Material As per Cl. 2.1.3
B Nominal thickness
a) 11 kV, 3c or 1c 3.6 mm
b) 33 kV, 3c or 1c 8.8 mm
C Minimum thickness
a) 11 kV, 3c or 1c 3.14 mm
b) 33 kV, 3c or 1c 7.82 mm
Page 21 of 42
SP-EWHP-01- R4
a. i) Thickness of freely mm
0.50
strippable Semi conducting
screen
ii) Make and grade of semi-
conducting compound
iii) Printing As per Cl. No. 2.1.4
(Yes / No)
iv) Ovality of the core %
As per IEC Standards
[R4]
b. Diameter over Insulation mm
Screen (apprx.)
i) Dimensions a) Thickness : Mm
0.1 +/- 5 %
b) Width : 50 mm
C) Overlap: 20%
[R4]
Page 22 of 42
SP-EWHP-01- R4
Page 23 of 42
SP-EWHP-01- R4
C Armour – GI strips
a) Width of strip & 4 x 0.8 mm
Thickness of strip (zero negative
tolerance for thickness)
b) Number of strips
no.
(min.)
D Approx. Equivalent Area sq. mm.
E Area covered by armour Min. 90 % %
Calculation shall be
attached.
F Dia. over armour - apprx. Mm
G Fault current carrying Calculation sheet … kA
capacity of armour shall be attached. for …
sec.
Page 24 of 42
SP-EWHP-01- R4
20.0 Weights
a) Net weight of cable kg / km
(apprx.)
b) Weight of empty drum Kg
c) Weight of Cable with drum kg
Page 25 of 42
SP-EWHP-01- R4
Page 26 of 42
SP-EWHP-01- R4
Annexure - C
List of Sub-Vendors
for critical items
[R4]
Vendor to state sub-vendors’ names for other items, wherever approved names are not
mentioned, for purchaser’s approval during pre-order / post-order stages.
R-Infra
Ser.
Description of Material Approved Sub-Vendors
No.
@
@ Lantor
Conductor Water-Blocking @ Geca
3.
tapes / yarn / powder @ Freudenberg
@ Scapa
@ Lantor
@ Geca
Water-Swellable Tapes @ Freudenberg
4.
(Pre-slitted) @ Scapa
@ Miracle
@ Tekstilna (Slovenia)
Page 27 of 42
SP-EWHP-01- R4
6. Aluminium Alloy
7. E.C. Grade Copper Rod
8. H.T.G.S. Wire
9. PVC Compound
10. PVC Resin
Galvanised Steel Wires /
11.
Strips
12. Copper Tape (for screening)
13. P. P. Fillers
Page 28 of 42
SP-EWHP-01- R4
Annexure - D
A. Mumbai
a) Average grade atmospheric Heavily polluted, salt-laden, dusty, humid
condition with possibility of condensation
b) Average grade soil condition Water-logged
c) Maximum altitude above sea 1000 M
level
d) Ambient Air temperature i) Highest : 45 deg C
ii) Average : 35 deg C
iii) Minimum : 15 deg C
e) Relative Humidity 100 % Max
f) Thermal Resistivity of Soil 150 deg. C . cm / W max.
g) Seismic Zone 3
h) Rainfall 3000 mm concentrated in four months
B. Delhi
a) Average grade atmospheric Heavily polluted, dry
condition
b) Average grade soil condition
c) Maximum altitude above sea 1000 M
level
d) Air temperature Ambient i) Highest : 50 deg C
ii) Average : 40 deg C
iii) Minimum : 0 deg C
e) Relative Humidity 100 % max
f) Thermal Resistivity of Soil 150 deg. C . cm / W max.
g) Seismic Zone 4
h) Rainfall 750 mm concentrated in four months
Page 29 of 42
SP-EWHP-01- R4
Annexure E
Page 30 of 42
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
Welding tack
APPRX.30 APPRX.90
60 15 (Typical)
15 THIS PART (SPHERE) WELDED
Ø16 Ø8 Thread 30° Welding tack
53 2Nos.Ø8hole TO PULLING EYE SHALL
OUTSIDE (Typical)
15 Standerd
SWIVEL FREE AT ANY ANGLE.
Threaded for
Hole to let air out locking M8 screw
Thread ROTATING PART
15 15.0 Ø8
THREAD THROUGH 360°
'A' 'A'
Ø48
Ø130 Ø118 Ø90 Ø102 Ø90 APPRX.
Ø110 Ø90
Ø60
Apprx.
Ø90
THREAD
3NOS-Ø18 HOLES
Ø102
ROTATING PART
3.0
To accommodate M8 screw
40 20
CONDUCTOR CAP SOCKET FIXING BLOCK 3 no threading required
PULLING EYE 1
SOCKET
(Made of apprx.Ø12mm rod)
260 CAP 2 OPTIONAL ARRANGEMENT
PULLING BLOCK HOUSING 4
15
THREAD
Ø8 INSIDE 30.0
125 10 LOCKING SCREW
'A' 50 45 30
'B' (Suitably long to fix CAP (2)
Ø31
with socket fixing block (3)
Ø25
15
Ø16
THREAD
M16 THREAD
'A' 10 'B' INSIDE
VIEW-A VIEW-B
CONDUCTOR SOCKET 5
(for crimping on conductor) SECTIONAL VIEW
Exploded View 10
Hole for
pouring P.U.Compound Hole to let air out
SUITABLE FOR M16 BOLT
10 LOCKING SCREW 2 M.S.Zinc-Plated
9 LOCK NUT 3 M.S.Zinc-Plated
8 NUT 3 M.S.Zinc-Plated
7 SPRING. WASHER 3 M.S.Zinc-Plated
6 PLAIN WASHER 3 M.S.Zinc-Plated
5
6 7 8 9 1 5 CONDUCTOR SOCKET 3 AL.
3 4 PULLING BLOCK HOUSING 1 M.S.Zinc-Plated
2
4 3 SOCKET FIXING BLOCK 1 M.S.Zinc-Plated
EXAMPLE: 2 CAP 1 M.S.Zinc-Plated
This space shall be filled with P.U.Coumpound
1) For cable size 33kV, 3/C X 400sq mm Al XLPE.
1 PULLING EYE 1 M.S.Zinc-Plated
2) Diameter over conductor : 23.8mm apprx.
Overall diameter : 108±3mm apprx.
NO. DISCRIPTION QTY. MATERIAL
Pulling force applicable on the cable : 30 N/sq mm
CONDUCTOR Pulling eye shall withstand total force of : 36000N+Safety margin
CABLE
NOTE: MISC/E/4-1133/1699
1) All Dimensions are in mm, unless otherwise stated.
CONDUCTOR
2) This drawing is typical / indicative.Separate dimensioned drawing for cable
CABLE PULLING EYE ASSEMBLY
pulling eye assembly, suitable for required size & rating of cables, shall be
submitted for approval,prior to manufacturing.
(TYPICAL)
3) After fixing cable pulling eye, P.U.(Poly-Urethane) Compound shall be
poured to occupy inner spaces to avoid ingress of Water / Moisture.
4) After P.U.Compound oozes/flows out from the cable side,the same edge
CRIMPING Final Assembly shall be sealed with suitable sleeve/Tape.
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
SP-EWHP-01- R4
Annexure- F
QAP Format
(Quality Assurance Plan)
For H. T. Cables (Typical)
(Page 1 to 10)
[R4]
Vendor shall submit the QAP, duly filled in, in accordance with IS / IEC
standards and manufacturer’s standards/procedures, for Purchaser’s approval,
during pre-order / post-order stages.
Page 33 of 42
QUALITY ASSURANCE PLAN (QAP)
FOR H. T. CABLES 09.03.2012
(Typical Format)
Legend : SV : Sub-Vendor of Cable Manufacturer, MFR : Cable Manufacturer, R-Infra : Reliance Infra-Structure Ltd., PS : Purchase Specification of Cable Vendor, R-Infra Spec. - R-Infra Specification
P - Perform , V - Verify , W - Witness
Sr. COMPONENT CHARACTERISTICS & UNIT CLASS Measuring TYPE OF QUANTUM OF REFERENCE ACCEPTANCE FORMAT OF AGENCY Remarks
Equipment / CHECK SV MFR R-
No. OPERATIONS CHECK DOCUMENT / NORMS RECORD
Technique
TEST Infra
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
A. RAW MATERIALS
4 Semi-conducting a) Packing P V V
Compound b) Volume Resistivity P P/V V
c) Tensile Strength N/sq.mm. P P/V V
d) Elongation at break % P P/V V
e) Cure Curve (Max. Torque) lb-in - P V
f) Density g/cc P P/V V
g) Firmly bonded over conductor P P/V V
h) Easly strippable over XLPE P P/V V
insulation
Page 1 of 8
QUALITY ASSURANCE PLAN (QAP)
FOR H. T. CABLES 09.03.2012
(Typical Format)
Legend : SV : Sub-Vendor of Cable Manufacturer, MFR : Cable Manufacturer, R-Infra : Reliance Infra-Structure Ltd., PS : Purchase Specification of Cable Vendor, R-Infra Spec. - R-Infra Specification
P - Perform , V - Verify , W - Witness
Sr. COMPONENT CHARACTERISTICS & UNIT CLASS Measuring TYPE OF QUANTUM OF REFERENCE ACCEPTANCE FORMAT OF AGENCY Remarks
Equipment / CHECK SV MFR R-
No. OPERATIONS CHECK DOCUMENT / NORMS RECORD
Technique
TEST Infra
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
B. IN-PROCESS INSPECTION
Page 2 of 8
QUALITY ASSURANCE PLAN (QAP)
FOR H. T. CABLES 09.03.2012
(Typical Format)
Legend : SV : Sub-Vendor of Cable Manufacturer, MFR : Cable Manufacturer, R-Infra : Reliance Infra-Structure Ltd., PS : Purchase Specification of Cable Vendor, R-Infra Spec. - R-Infra Specification
P - Perform , V - Verify , W - Witness
Sr. COMPONENT CHARACTERISTICS & UNIT CLASS Measuring TYPE OF QUANTUM OF REFERENCE ACCEPTANCE FORMAT OF AGENCY Remarks
Equipment / CHECK SV MFR R-
No. OPERATIONS CHECK DOCUMENT / NORMS RECORD
Technique
TEST Infra
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
+ c) Surface finish -- - P V
d) Printing on outer semi-conducting “DO NOT HEAT, FREELY - P V
layer STRIPPABLE”
Insulation
e) Tensile Strength IS 7098(Part IS 7098(Part - P V
(XLPE with water-
2)/85 2)/85
tree retardant
f) Elongation at break IS 7098(Part IS 7098(Part - P V
property) 2)/85 2)/85
g) Hot set test % IS 7098(Part IS 7098(Part - P V
+ 2)/85 2)/85
h) Eccentricity of insulation % - P V
Insulation Screen i) Core diameter mm - P V
and Ovality check on core
j) Void & contamination test for no. - P V/W
insulation (Silicon Oil test)
k) Condition of Triple Extrude - P V/W
l) CCV tube pressure (N2) and bars & - P V/W
temperature deg. C
m) Temperature of Extruder (65 mm, deg C - P V/W
80 mm, 150 mm)
n) Haul off / Line Speed m/min - P V/W
o) Dimensions and Condition of dies mm - P V/W
& nipple
p) Freely strippable insulation screen IS:7098/3, 93 IS:7098/3, 93 Cl. - P V/W
(Strippability Test) Cl. No. 20 No. 20
q) Water boil test for extruded semi- BIS draft BIS draft Specn - P V/W
conducting layers Specn
r) Longitudinal Water-Blocking Test IEC 60502-2 IEC 60502-2 - P V/W
Page 3 of 8
QUALITY ASSURANCE PLAN (QAP)
FOR H. T. CABLES 09.03.2012
(Typical Format)
Legend : SV : Sub-Vendor of Cable Manufacturer, MFR : Cable Manufacturer, R-Infra : Reliance Infra-Structure Ltd., PS : Purchase Specification of Cable Vendor, R-Infra Spec. - R-Infra Specification
P - Perform , V - Verify , W - Witness
Sr. COMPONENT CHARACTERISTICS & UNIT CLASS Measuring TYPE OF QUANTUM OF REFERENCE ACCEPTANCE FORMAT OF AGENCY Remarks
Equipment / CHECK SV MFR R-
No. OPERATIONS CHECK DOCUMENT / NORMS RECORD
Technique
TEST Infra
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Page 4 of 8
QUALITY ASSURANCE PLAN (QAP)
FOR H. T. CABLES 09.03.2012
(Typical Format)
Legend : SV : Sub-Vendor of Cable Manufacturer, MFR : Cable Manufacturer, R-Infra : Reliance Infra-Structure Ltd., PS : Purchase Specification of Cable Vendor, R-Infra Spec. - R-Infra Specification
P - Perform , V - Verify , W - Witness
Sr. COMPONENT CHARACTERISTICS & UNIT CLASS Measuring TYPE OF QUANTUM OF REFERENCE ACCEPTANCE FORMAT OF AGENCY Remarks
Equipment / CHECK SV MFR R-
No. OPERATIONS CHECK DOCUMENT / NORMS RECORD
Technique
TEST Infra
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
c) Test for thickness of insulation & mm One sample IS 7098(Part 2)/85 - P V/W
sheath
Page 5 of 8
QUALITY ASSURANCE PLAN (QAP)
FOR H. T. CABLES 09.03.2012
(Typical Format)
Legend : SV : Sub-Vendor of Cable Manufacturer, MFR : Cable Manufacturer, R-Infra : Reliance Infra-Structure Ltd., PS : Purchase Specification of Cable Vendor, R-Infra Spec. - R-Infra Specification
P - Perform , V - Verify , W - Witness
Sr. COMPONENT CHARACTERISTICS & UNIT CLASS Measuring TYPE OF QUANTUM OF REFERENCE ACCEPTANCE FORMAT OF AGENCY Remarks
Equipment / CHECK SV MFR R-
No. OPERATIONS CHECK DOCUMENT / NORMS RECORD
Technique
TEST Infra
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
g) Insulation Resistance test (Volume ohm-cm One sample IS 7098(Part IS 7098(Part - P V/W
Resistivity test) 2)/85 2)/85
h) Flammability Test One sample IS 7098(Part IS 7098(Part - P V/W
2)/85 2)/85
i) Water Penetration Test (WPT) One sample IEC 60502-2 IEC 60502-2 - P V/W
on core
(Longitudinal Water-Blocking test)
Page 6 of 8
QUALITY ASSURANCE PLAN (QAP)
FOR H. T. CABLES 09.03.2012
(Typical Format)
Legend : SV : Sub-Vendor of Cable Manufacturer, MFR : Cable Manufacturer, R-Infra : Reliance Infra-Structure Ltd., PS : Purchase Specification of Cable Vendor, R-Infra Spec. - R-Infra Specification
P - Perform , V - Verify , W - Witness
Sr. COMPONENT CHARACTERISTICS & UNIT CLASS Measuring TYPE OF QUANTUM OF REFERENCE ACCEPTANCE FORMAT OF AGENCY Remarks
Equipment / CHECK SV MFR R-
No. OPERATIONS CHECK DOCUMENT / NORMS RECORD
Technique
TEST Infra
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Page 7 of 8
QUALITY ASSURANCE PLAN (QAP)
FOR H. T. CABLES 09.03.2012
(Typical Format)
Legend : SV : Sub-Vendor of Cable Manufacturer, MFR : Cable Manufacturer, R-Infra : Reliance Infra-Structure Ltd., PS : Purchase Specification of Cable Vendor, R-Infra Spec. - R-Infra Specification
P - Perform , V - Verify , W - Witness
Sr. COMPONENT CHARACTERISTICS & UNIT CLASS Measuring TYPE OF QUANTUM OF REFERENCE ACCEPTANCE FORMAT OF AGENCY Remarks
Equipment / CHECK SV MFR R-
No. OPERATIONS CHECK DOCUMENT / NORMS RECORD
Technique
TEST Infra
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Note :
1. Checks specified above for Raw Material, In-Process and Final Inspection shall be as relevant to the specific cable construction.
2. Number of samples shall be selected as per Factory Standard/Agreement wherever ‘sample’ is indicated for extent of check.
3. Plant standards shall be followed in case Technical Data Sheet does not include requirements for characteristics to be checked.
4. R-Infra's may witness Raw materials and In process Inspections, in addition to Type/Routine/Acceptance tests, at any time/stage of manufacturing.
5. R-Infra’s Inspector shall randomly select a cable drum for type testing at vendor's premises / CPRI / ERDA among the lot offered for inspection.
6. For each of the offered lot for inspection, R-Infra may randomly select one cable drum for testing of end cap “Destructive testing” to verify
adhesion of sealing cap to cable outer sheath. Similarly, pulling eye shall be tested with 30N/mm2 pressure.
Page 8 of 8
SP-EWHP-01- R4
Annexure- G
All cables made with TR-XLPE Insulation should be tested and/or certified to meet the
following performance parameters as per ANSI /ICEA S-94-649 after one year AWTT.
Page 42 of 42
SP-LALU-01-R0
Index
5.0 Annexure – C2 : Guaranteed Tech. Particulars for 33KV Lightning Arrester….. 15-17
Page 2 of 18
SP-LALU-01-R0
General Specification
National Standards
International Standards
Important Note :
In the event of direct conflict between various order documents, the precedence of authority of
documents shall be as follows –
Page 3 of 18
SP-LALU-01-R0
3.0.0 Approved Make of Common for both 66KV and 33 KV Lightning Arresters
Components
Page 4 of 18
SP-LALU-01-R0
4.2.0 Type test The product must be of type tested quality. Type test
reports shall be submitted for the type, size & rating of
equipment offered along with bid. If the manufacturer’s
lab is accredited by govt./ authorised body then it shall
be acceptable for type testing.
4.3.0 Routine test As per relevant IS / IEC.
4.5.2 The Buyer reserves the right to inspect the product at the
Sellers works at any time prior to dispatch, to verify
compliance with the specifications.
4.6.0 Tests on fitting and As per Manufacturer’s Standards and relevant IS / IEC.
Accessories
Page 5 of 18
SP-LALU-01-R0
Page 6 of 18
SP-LALU-01-R0
7.0.0 Shipping,
Handling &
Storage
7.1.0 Shipping The seller shall give complete shipping information concerning
Information weight, size etc. of each package.
7.2.0 Shipping The seller shall ascertain at an early date before the
Constraints commencement of manufacture, any transport limitations such as
weights, dimensions, road culverts, overhead lines, free access
etc. from the manufacturing plant to the project site. Bidder shall
furnish the confirmation that the proposed packages can be safely
transported, as normal or oversize packages, upto the site. Any
modifications required in the infrastructure and cost thereof in this
connection shall be brought to the notice of the Purchaser.
7.3.0 Transit Damage The seller shall be responsible for any transit damage due to
improper packing.
7.4.0 Handling & Manufacturer’s instructions shall be followed. Detail handling &
Storage storage instruction sheet / manual needs to be furnished before
commencement of supply.
Page 7 of 18
SP-LALU-01-R0
9.0.0 Progress
Reporting
10.0.0 Deviations
i) Deviations from this Specification are only acceptable where the
Seller has listed in his quotation the requirements he can’t or
does not wish to comply with and the buyer has accepted in
writing the deviations before the order is placed.
Page 8 of 18
SP-LALU-01-R0
Annexure – A
1.0 Scope
1.2.0 Accessories
i) Supporting insulators for LA.
ii) Line terminal connectors.
Page 9 of 18
SP-LALU-01-R0
Page 10 of 18
SP-LALU-01-R0
Annexure – B
Ambient Conditions :
A) Mumbai
a) Average grade Heavily polluted , salt Laden, dusty, humid with possibility of
atmosphere condensation
b) Maximum altitude 1000 M
above sea level
c) Ambient Air Highest 45 deg C, Average 35 deg C
temperature
d) Minimum ambient air 20 deg C
temperature
e) Relative Humidity 100 % Max
f) Thermal Resistivity of 150 Deg. C cm/W
Soil
g) Seismic Zone 3
h) Rainfall 3000 mm concentrated in four months
B) Delhi
Page 11 of 18
SP-LALU-01-R0
Annexure – C1
6 Application Protection of
Transformers, circuit
breakers, lines and
other outdoor S/S
equipment.
7 LA connection to system Phase to earth
Page 12 of 18
SP-LALU-01-R0
Page 13 of 18
SP-LALU-01-R0
Page 14 of 18
SP-LALU-01-R0
Annexure – C2
6 Application Protection of
Transformers, circuit
breakers, lines and
other outdoor S/S
equipment.
7 LA connection to system Phase to earth
Page 15 of 18
SP-LALU-01-R0
Page 16 of 18
SP-LALU-01-R0
Page 17 of 18
SP-LALU-01-R0
Annexure – D
Page 18 of 18
SP-CBLU-01-R0
Index
Page 2 of 43
SP-CBLU-01-R0
General Specification
The circuit breakers shall be designed, manufactured and tested in accordance with the
latest applicable Indian Standard, IEC standard and CBIP manuals as listed below-
National Standards
Indian Electricity Rules
CBIP manual
IS-1554 Part-I 1988 PVC insulated cables up to & including 1100 volts.
Page 3 of 43
SP-CBLU-01-R0
International Standards
2.1.0 Contacts
2.1.1 Making & Breaking Hermetically sealed, free from atmospheric
Contacts effects , adjustable to allow for wear and shall
have a minimum number of moveable parts
and adjustments to accomplish these results.
2.1.2 Arcing Contacts First to close and last to open
2.1.3 Main Contacts First to open and last to close.
2.1.4 Material of tips of contact Silver-plated and have tungsten alloy tipping.
2.2.0 Sulphur Hexa Fluoride Gas SF6 gas shall comply with IEC 376 , suitable
(SF6 Gas) in all respect for use in the switchgear under
all the operating conditions.
2.3.0 Operating Mechanism a) Suitable for high speed re-closing, anti-
pumping and trip free (as per IEC definition)
electrically or mechanically under every
method of closing (except during closing for
maintenance).
b) The operating mechanism shall be such
that the failure of any auxiliary spring will not
prevent tripping.
2.4.0 Indicators Electrical indicator as well as mechanical
indicator shall be provided for
a) Open and close position indication of
breaker.
b) Spring Charged indication
Page 4 of 43
SP-CBLU-01-R0
Page 5 of 43
SP-CBLU-01-R0
Page 6 of 43
SP-CBLU-01-R0
Page 7 of 43
SP-CBLU-01-R0
Page 8 of 43
SP-CBLU-01-R0
Page 9 of 43
SP-CBLU-01-R0
Page 10 of 43
SP-CBLU-01-R0
Page 11 of 43
SP-CBLU-01-R0
Page 12 of 43
SP-CBLU-01-R0
Page 13 of 43
SP-CBLU-01-R0
Page 14 of 43
SP-CBLU-01-R0
5.3.0 Submittals required prior to a) Inspection and test reports, carried out
dispatch in manufacturer’s works (R)
b) Test certificates of all bought out items
c) Operation and maintenance Instruction as
well as trouble shooting charts/ manuals
5.4.0 Drawing and document sizes Standard size paper A0, A1, A2, A3, A4
5.5.0 No of drgs. / Documents required at As per Annexure- A
different stages
Page 15 of 43
SP-CBLU-01-R0
8.0.0 Deviations
8.0.0 Deviation from the Specification Deviations from this Specification shall
be stated in writing with the tender by
reference to the Specification
clause/GTP/Drawing and a description of
the alternative offer. In absence of such a
statement, it will be assumed by the
Buyer that the Seller complies fully with
this specification.
Page 16 of 43
SP-CBLU-01-R0
Page 17 of 43
SP-CBLU-01-R0
Delivery schedule
2.1 Delivery period start date - from date of purchase order
2.2 Delivery period end date - as agreed with supplier
2.3 Material dispatch clearance - after inspection by purchaser and
written dispatch clearances for
purchaser
Page 18 of 43
SP-CBLU-01-R0
Page 19 of 43
SP-CBLU-01-R0
Page 20 of 43
SP-CBLU-01-R0
Page 21 of 43
SP-CBLU-01-R0
Page 22 of 43
SP-CBLU-01-R0
Page 23 of 43
SP-CBLU-01-R0
Page 24 of 43
SP-CBLU-01-R0
40.3 Weight.
Page 25 of 43
SP-CBLU-01-R0
Page 26 of 43
SP-CBLU-01-R0
Page 27 of 43
SP-CBLU-01-R0
Page 28 of 43
SP-CBLU-01-R0
Page 29 of 43
SP-CBLU-01-R0
Page 30 of 43
SP-CBLU-01-R0
Page 31 of 43
SP-CBLU-01-R0
Page 32 of 43
SP-CBLU-01-R0
Page 33 of 43
SP-CBLU-01-R0
Page 34 of 43
SP-CBLU-01-R0
Page 35 of 43
SP-CBLU-01-R0
40.3 Weight.
Page 36 of 43
SP-CBLU-01-R0
Page 37 of 43
SP-CBLU-01-R0
Page 38 of 43
SP-CBLU-01-R0
Page 39 of 43
SP-CBLU-01-R0
Page 40 of 43
SP-CBLU-01-R0
b) Insulation 650V
c) Colour Grey for control, Black
for AC and Green for
earth
66.9 Normal power consumption
at rated voltage (Watt)
66.10 Normal power of spring
charging motor
66.11 Number of close/open
operation possible after
failure of AC supply to
motor
Page 41 of 43
SP-CBLU-01-R0
Page 42 of 43
SP-CBLU-01-R0
Page 43 of 43
, - ,~--------- ~,------
8SE
Specification for
I , , I I -~--- --~
NarnelSign
os 00 I 29 -Jan-OS
\
!,"
\ " ~-
'J
Page 1 of 23 \-
SP-CTLU-01-R1
Record of Revision
Page 2 of 23
SP-CTLU-01-R1
Index
Page 3 of 23
SP-CTLU-01-R1
National Standard
International Standard
Standard Code Standard Description
IEC: 137 Bushing for alternating current above 1000V
IEC: 185 Specification for current transformers
IEC: 439 Specification for Terminal box / Marshalling box
Page 4 of 23
SP-CTLU-01-R1
specified.
The quantity of insulating oil in each current transformer shall
be best available and the complete specification of the oil
shall be furnished with the tender. The current transformer
2.6 Insulation Oil
offered shall be hermetically sealed completely filled with
insulating oil with provision to replace the oil. Oil level
indication shall be provided.
Porcelain used in bushing manufacture shall be
homogenous, free from laminations, cavities and other flaws
or imperfections that might affect the mechanical or dielectric
2.7 Bushing quality. Glazing of the porcelain shall be uniform brown color
free blisters, burns and similar defects. The bushing shall be
designated to have ample insulation, mechanical strength
and rigidity.
2.8 Creepage distance Not less than 31mm /KV
2.9 Terminal Connectors
The current transformers offered shall be supplied with
2.9.1 Primary Aluminum- alloy terminal connector with bimetallic sleeve,
suitable for connection with single/double ACSR conductor.
All the secondary terminals shall be bought in IP55 box with
brass/ copper stud type terminals. The secondary terminals
shall be shorted by brass/copper links before dispatch.
2.9.2 Secondary Terminal box to be provided with earthing stud
Box shall be of adequate size with proper clearance between
the terminals for ease of working and maintenance.
Gasket for Box shall be Neoprene.
2.10 Terminal Marking Terminal marking shall be as per IS 2705
Page 5 of 23
SP-CTLU-01-R1
Page 6 of 23
SP-CTLU-01-R1
certification
f) Type test report shall be submitted for
the type, size & rating of product /
equipment offered along with bid. They
shall be considered valid for 5 years from
date of test performed on product /
equipment.
g) Complete product catalogue and manual
along with the bid.
h) Recommended spare parts and
consumable items for 5 years of
operation with prices and spare parts
catalogue with list for future
requirements.
7.2.0 After award of contract, seller has a) Programme for production and testing
to submit mentioned drawings for (A)
buyer’s Approval (A ) / Reference b) Guaranteed Techinal Particulars (A)
(R) c) Calculations to substantiate choice of
electrical , mechanical component size /
ratings (A)
d-1) General arrangement drawing of
the current transformer (A)
d-2) Typical connection diagram and
winding connection of current
Transformer (A).
d-5) Terminal connector drawings (A)
d-7) General arrangement drawing
secondary terminal box (A)
e) Detailed installation and commissioning
instructions ( R)
f) Quality plan
7.3.0 Submittals required prior to a) Inspection and test reports, carried out
dispatch in manufacturer’s work (R )
b) Test certificates of all bought out items
c) Operation and maintenance instruction
as well as trouble shooting charts /
manuals.
7.4.0 Drawing and document sizes Standard size paper A0, A1 , A2, A3, A4
7.5.0 No of drgs./Documents required at As per Annexure A
different stages
8.0.0 Packing
8.1.1 Packing protection Against corrosion , dampness, heavy rains, breakage and
vibration
8.1.2 Packing for accessories Robust wooden non returnable packing case with all the
and spares above protection and identification labels.
Page 8 of 23
SP-CTLU-01-R1
8.1.3 Packing identification In each packing case, following details are required :
label a) Individual serial number
b) Purchaser’s name
c) PO number (along with SAP item code , if any) &
date
d) Equipment Tag no. (if any)
e) Destination
f) Manufacturer / Supplier’s name
g) Address of manufacturer’s / supplier’s its agent
h) Description and quantity
i) Country of origin
j) Month and year of manufacturing
k) Case measurements
l) Gross and net weight in kilograms
m) All necessary slinging and stacking instructions.
8.1.4 Shipping a) The bidder shall furnish the confirmation that the
proposed packages can be delivered safely upto
the site.
b) The seller shall be responsible for all transit
damage due to improper packing.
8.1.5 Handling and Storage Manufacturer instruction shall be followed. Detail
handling & storage instruction sheet / manual need to be
furnished before commencement of supply.
Page 9 of 23
SP-CTLU-01-R1
10.0.0 DEVIATIONS
10.0.0 Deviation from the specification Deviation from the specification shall be
started in writing with the tender by reference
to the specification clause/GTP/Drawing and
a description of the alternative offer. In
absence of such a statement. It will be
assumed by the Buyer that the seller
complies fully with this specification.
Page 10 of 23
SP-CTLU-01-R1
Page 11 of 23
SP-CTLU-01-R1
Page 12 of 23
SP-CTLU-01-R1
Protection
Protection
(Bus Bar)
Metering
(Spare)
10.2 Purpose /Application
40 (RCT+8)
Page 14 of 23
SP-CTLU-01-R1
Protection
Protection
Protection
(Bus Bar)
Metering
(Spare)
10.2 Purpose /Application
(RCT+8)
≥ 40
Page 16 of 23
SP-CTLU-01-R1
Protection
Protection
(Bus Bar)
Metering
(Spare)
10.2 Purpose /Application
(RCT+8)
≥ 40
Page 17 of 23
SP-CTLU-01-R1
Page 18 of 23
SP-CTLU-01-R1
Protection
Protection
(Bus Bar)
Metering
(Spare)
10.2 Purpose /Application
(RCT+8)
≥ 40
Page 19 of 23
SP-CTLU-01-R1
Page 20 of 23
SP-CTLU-01-R1
Protection
Protection
Protection
(Bus Bar)
Metering
(Spare)
10.2 Purpose /Application
(RCT+8)
≥ 40
Page 21 of 23
SP-CTLU-01-R1
Page 22 of 23
SP-CTLU-01-R1
Page 23 of 23
SP-ISLU-01-R0
Index
4.0 Annexure – C1 : Guaranteed Tech. Particulars for 66KV Disconnecting Switch... 15-17
5.0 Annexure – C2 : Guaranteed Tech. Particulars for 33KV Disconnecting Switch… 18-20
Page 2 of 21
SP-ISLU-01-R0
General Specification
National Standards
Important Note :
In the event of direct conflict between various order documents, the precedence of authority of
documents shall be as follows –
Page 3 of 21
SP-ISLU-01-R0
2.1.0 Disconnect Switch Motor operated, central rotating double break with turn and twist
Type & Mechanism mechanism, triple pole, outdoor type for installation and operation
in horizontal plane for 66KV & in vertical plane for 33 kv with or
without earth switches, as required complete in all respects.
i) Motor assembly Suitable for 3 phase 415V, 50 Hz. Provided with a quick
electro-mechanical brake on high speed shaft for rapid braking.
2.2.0 Earth Switch Manually operated
Mechanism
2.3.0 Disconnector
Switch Controls
i) Remote electrical Required
control
ii) Local Manual Required
control
iii) Local electrical Required from integral Local Control Cabinet
control
2.4.0 Interlock with circuit Electrical interlock suitable for 220 V / 50 V DC
breakers
2.5.0 Interlock with Earth Mechanical & Electrical interlock
Switch
2.6.0 Padlock for Earth Padlock & keys for both positions i.e. when earth switch is
Switch grounded and when earth switch is un-grounded
ii) Fasteners All metal caps, jointing flanges, bolts and nuts shall be made of
high grade cast iron or malleable steel casting, machine faced
and hot-dip galvanised.
Page 4 of 21
SP-ISLU-01-R0
2.10.0 Current carrying Made of non aging, non magnetic stainless steel with life long
Springs spring action strength
2.11.0 Fault Current rating Earth switch shall be able to carry same Fault Current as
assigned to the disconnecting switch.
2.12.0 Disconnecting 90 deg from full open to full close in order to ensure a distinct
Switch contacts break ands clear visibility.
movement
2.13.0 Corona Effect Shall be free from visible corona discharge in both open &
close positions at visible discharge test voltages.
2.14.0 Control cabinet
i) Enclosure Weather-proof, water-shedding, corrosion-proof IP-55 steel
cabinet
ii) Cabinet Door Gasketed, hinged access door shall have a mechanical
indicator fitted to clearly indicate fully opened and fully closed
positions of the disconnection switch.
iii) Wiring Control wiring shall be done using 1.1KV grade 2.5 sq.mm
stranded copper conductor, PVC insulated, cables laid in GI
conduits.
iv) Locking Padlocking arrangement to be provided.
arrangement
v) Incomer A local TPN MCB to be provided in cabinet at power supply
incoming point.
vi) Outgoing Control All outgoing control wiring shall terminate on terminal blocks,
Wiring inside the cabinet so as to have maximum access to all
conductor terminals.
vii) Aux. Contacts All auxiliary contacts of the disconnection switch and earthing
switches shall be supplied duly wired up to the terminal blocks.
viii) Terminals Stud type terminals with at least twenty (20) percent spare
terminals shall be provided over and above the number actually
required.
Page 5 of 21
SP-ISLU-01-R0
2.16.0 Disconnection Switch shall have three (3) grounding blades forming integral
switches with Earth part of the isolator. These blades shall be capable of being
switch fitted on either side of the brakes. Flexible heavily tinned
copper braids of adequate cross-sectional area with connector
suitable for the specified short circuit current shall be provided
on the hinged end of the grounding blade for connection to the
station grounding grid.
2.17.0 Grounding Blades Manually operated and interlocked with disconnection switch
Operation so that the grounding blades can be closed only when the
disconnection switch is open.
2.19.0 Disconnection Each pole of the disconnection switch shall be provided with a
Switch Poles & complete galvanized steel base designed for mounting on a
base supporting structure/ gantry.
2.20.0 Grounding Pads Each pole of disconnection switch shall be provided with two
(2) grounding pads of non-corrodible material brazed to the
channel base at opposite ends. Flexible tinned copper (15-25
microns) connectors shall be provided for a) Connection of
earthing pad of each pole, b) Operating handle, c) Earthing
switches.
Page 6 of 21
SP-ISLU-01-R0
2.22.0 Name Plates Corrosion-proof nameplates giving all the relevant mandatory
as well as optional information as stipulated in IS shall be
provided on disconnection switches, earthing switches and
operating devices as per the Purchaser's/ Consulting
Engineer's approval.
3.0.0 Approved Make of Common for both 66KV and 33 KV outdoor disconnecting
Components switch
3.1.0 Motors ABB / Siemens / Crompton
3.2.0 Insulators JSI / WSI / Modern / Saravana / BHEL
3.3.0 Switch Kaycee / L&T (Salzer)
3.4.0 HRC Fuse Links Alstom / Siemens / L&T
3.5.0 AC Contactors & L&T / Siemens / Schneider
O/L Relay
3.6.0 Terminals Connectwell / Elmex
3.7.0 Push buttons / L&T / Teknic / Siemens
Actuator
3.8.0 MCB Merlin Gerin / Siemens / Schneider
Page 7 of 21
SP-ISLU-01-R0
4.2.0 Type test The product must be of type tested quality. Type test
reports shall be submitted for the type, size & rating of
equipment offered along with bid. If the manufacturer’s
lab is accredited by govt./ authorised body then it shall
be acceptable for type testing.
4.3.0 Routine test As per relevant IS / IEC.
4.5.2 The Buyer reserves the right to inspect the product at the
Sellers works at any time prior to dispatch, to verify
compliance with the specifications.
4.6.0 Tests on fitting and As per Manufacturer’s Standards and relevant IS / IEC.
Accessories
Page 8 of 21
SP-ISLU-01-R0
5.2.0 To be submitted after The seller has to submit : for buyer’s Approval (A) /
award of contract Reference (R)
i) Program for production and testing (A)
ii) Guaranteed Technical Particulars (A)
iii) Calculations to substantiate choice of electrical, structural,
mechanical component size / ratings (A)
5.4.0 Drawing and document Standard size paper A0, A1, A2, A3, A4
sizes
5.5.0 No of drgs. / Documents As per Annexure- A
required at different
stages
Page 9 of 21
SP-ISLU-01-R0
7.0.0 Shipping,
Handling &
Storage
7.1.0 Shipping The seller shall give complete shipping information concerning
Information weight, size etc. of each package.
7.2.0 Shipping The seller shall ascertain at an early date before the
Constraints commencement of manufacture, any transport limitations such as
weights, dimensions, road culverts, overhead lines, free access
etc. from the manufacturing plant to the project site. Bidder shall
furnish the confirmation that the proposed packages can be safely
transported, as normal or oversize packages, upto the site. Any
modifications required in the infrastructure and cost thereof in this
connection shall be brought to the notice of the Purchaser.
7.3.0 Transit Damage The seller shall be responsible for any transit damage due to
improper packing.
7.4.0 Handling & Manufacturer’s instructions shall be followed. Detail handling &
Storage storage instruction sheet / manual needs to be furnished before
commencement of supply.
Page 10 of 21
SP-ISLU-01-R0
9.0.0 Progress
Reporting
10.0.0 Deviations
i) Deviations from this Specification are only acceptable where the
Seller has listed in his quotation the requirements he can’t or
does not wish to comply with and the buyer has accepted in
writing the deviations before the order is placed.
Page 11 of 21
SP-ISLU-01-R0
Annexure – A
1.0 Scope
1.2.0 Accessories
i) Clamps & terminal connectors.
ii) Stainless steel hardware like nut bolts/ washers etc. for fixing of
all equipment / accessories in the scope of the bidder with
supporting structure.
iii) Any other item necessary or usual for efficient performance and
satisfactory maintenance under the various operating and
atmospheric conditions
Page 12 of 21
SP-ISLU-01-R0
Page 13 of 21
SP-ISLU-01-R0
Annexure – B
Ambient Conditions :
A) Mumbai
a) Average grade Heavily polluted , salt Laden, dusty, humid with possibility
atmosphere of condensation
b) Maximum altitude above 1000 M
sea level
c) Ambient Air temperature Highest 45 deg C, Average 35 deg C
d) Minimum ambient air 20 deg C
temperature
e) Relative Humidity 100 % Max
f) Thermal Resistivity of Soil 150 Deg. C cm/W
g) Seismic Zone 3
h) Rainfall 3000 mm concentrated in four months
B) Delhi
Page 14 of 21
SP-ISLU-01-R0
Annexure – C1
Page 15 of 21
SP-ISLU-01-R0
Page 16 of 21
SP-ISLU-01-R0
ii) Height
iii) Voltage level
iv) Cantilever Strength
v) Torsinal Strength
vi) Creepage Distance Min 31mm/KV
vii) Basic insulation level (1 min. power
frequency flashover voltage)
a) Dry 140 KV rms
b) Wet 140 KV rms
viii) Visible corona discharge voltage
ix) 1.2/50 micro second impulse 325 KVp
flashover voltage
x) Insulation class A
32 Drive Motor
i) Make
ii) KW Rating / rpm
iii) Rated current
iv) Frame size
v) Rated Voltage 415 V AC
vi) Degree of Protection IP-55
vii) Insulation Class B/F
viii) Duty
Page 17 of 21
SP-ISLU-01-R0
Annexure – C2
Page 18 of 21
SP-ISLU-01-R0
Page 19 of 21
SP-ISLU-01-R0
Page 20 of 21
SP-ISLU-01-R0
Annexure – D
Page 21 of 21
I I
I
!
I
f
I
!
, '
Specification for I
I
!
OUTDOO)~ !
POTENTIAL TRANSFO){MEI{
- - . - --_._- -<
Page 1 or 18
SP-PTLU-01-R1
Record of Revision
Page 2 of 18
SP-PTLU-01-R1
Index
General Specification...................................................................................................3
10.0.0 Deviations........................................................................................................11
Page 3 of 18
SP-PTLU-01-R1
General Specification
National Standard
Standard Code Standard Description
IS-3156
Specification for Voltage transformer.
(Part I to IV)
IS-4146 Application guide for voltage transformer.
IS-2099 High voltage porcelain bushings
IS-731 Insulator for O/H power line
IS-335 New insulating oil for transformer and switchgear.
IS-9676 Reference ambient temperature of electrical equipment
IS-5561 Specification of electric power connectors
IS-5621 Hollow insulator for use in electrical equipments
IS-3156 (Part I to IV) Specification for Voltage transformer.
IS-4146 Application guide for voltage transformer.
IS-2099 High voltage porcelain bushings
IS-731 Insulator for O/H power line
Indian Electricity Rules
Indian electricity act
CBIP manual
Page 4 of 18
SP-PTLU-01-R1
Page 5 of 18
SP-PTLU-01-R1
Page 6 of 18
SP-PTLU-01-R1
Forward path
Page 7 of 18
SP-PTLU-01-R1
Page 8 of 18
SP-PTLU-01-R1
9.0.0 Packing
9.1.1 Packing protection Against corrosion , dampness, heavy rains, breakage and
vibration
9.1.2 Packing for accessories Robust wooden non returnable packing case with all the
and spares above protection and identification labels.
9.1.3 Packing identification In each packing case, following details are required :
label i) Individual serial number
Page 9 of 18
SP-PTLU-01-R1
10.0 DEVIATIONS
Deviation from this specification shall be started in writing with the tender by reference to the
specification clause/ DTP/Drawing and a description of the alternative offer. In absence of such a
statement, it will be assured by the Buyer that the seller complies fully with this specification.
Page 10 of 18
SP-PTLU-01-R1
Page 11 of 18
SP-PTLU-01-R1
Page 12 of 18
SP-PTLU-01-R1
Page 13 of 18
SP-PTLU-01-R1
Sr.
Description Data By Purchaser Data By Supplier
No.
Project specific to be filled
1.0 Location of Equipment
up
2.0 Name of Manufacturer
3.0 Address & Contact details
Single phase, outdoor,
dead tank type, oil
4.0 Type
immersed, self-cooled
hermetically sealed type.
5.0 Manufacturer Model No
Reference design ambient
6.0 50 Deg C
temperature
7.0 Reference Standard IS: 3156 (Part1 to 4)
8.0 Nominal system voltage 66KV
9.0 Highest system voltage 72.5KV
10.0 Basic Insulation level 325KVp
11.0 Power frequency voltage 140KV
12.0 Type of cooling ONAN
13.0 Rated frequency (Hz) 50 Hz
14.0 Insulation Class A
15.0 Rated Primary voltage 66KV / √3
16.0 Rated secondary voltage 110V / √3
17.0 Number of secondary cores Two
18.0 CORE Specifications
18.1 Core - 1
18.2 Purpose Metering
18.3 Rated Output 50 VA
18.4 Class of accuracy 0.2
18.5 Ratio error As per IS
18.6 Phase angle error As per IS
19.0 Core - 2
19.1 Purpose Protection
19.2 Rated Output 50 VA
19.3 Class of accuracy 3P
19.4 Ratio error As per IS
19.5 Phase angle error As per IS
20.0 Rated over voltage factor
20.1 - Continuous 1.2 times
20.2 - 30 Seconds 1.5 times
Temperature rise above an
ambient of 50Deg C at 1.2
21.0
times voltage factor for 30
seconds rating
21.1 - For Winding 50 Deg C
21.2 - For Oil 40 Deg C
Page 14 of 18
SP-PTLU-01-R1
Page 15 of 18
SP-PTLU-01-R1
Sr.
Description Data By Purchaser Data By Supplier
No.
Project specific to be filled
1.0 Location of Equipment
up
2.0 Name of Manufacturer
3.0 Address & Contact details
Single phase, outdoor,
dead tank type, oil
4.0 Type
immersed, self-cooled
hermetically sealed type.
5.0 Manufacturer Model No
Reference design ambient
6.0 50 Deg C
temperature
7.0 Reference Standard IS: 3156 (Part1 to 4)
8.0 Nominal system voltage 33KV
9.0 Highest system voltage 36KV
10.0 Basic Insulation level 170KVp
11.0 Power frequency voltage 70KV
12.0 Type of cooling ONAN
13.0 Rated frequency (Hz) 50 Hz
14.0 Insulation Class A
15.0 Rated Primary voltage 33KV / √3
16.0 Rated secondary voltage 110V / √3
17.0 Number of secondary cores Two
18.0 CORE Specifications
18.1 Core - 1
18.2 Purpose Metering
18.3 Rated Output 50 VA
18.4 Class of accuracy 0.2
18.5 Ratio error As per IS
18.6 Phase angle error As per IS
19.0 Core - 2
19.1 Purpose Protection
19.2 Rated Output 50 VA
19.3 Class of accuracy 3P
19.4 Ratio error As per IS
19.5 Phase angle error As per IS
20.0 Rated over voltage factor
20.1 - Continuous 1.2 times
20.2 - 30 Seconds 1.5 times
Temperature rise above an
ambient of 50Deg C at 1.2
21.0
times voltage factor for 30
seconds rating
21.1 - For Winding 50 Deg C
21.2 - For Oil 40 Deg C
Page 16 of 18
SP-PTLU-01-R1
Page 17 of 18
SP-PTLU-01-R1
Page 18 of 18
TECHNICAL SPECIFICATIO
FOR
POLYMERIC INSULATORS
Specification No-SP-PI-Ol, RO
Index
1.0 Scope
11.0 Deviation
13.0 GTP
2
SP-PI-01-R0
TECHNICAL SPECIFICATIONS
3
SP-PI-01-R0
General Specifications
1.0 Scope
This specification covers the design, manufacture, testing & supply of Polymeric Insulators.
The Polymeric Insulator shall be designed, manufactured & tested in accordance with the following
National / International Standards (IS/IEC).
Sl
Indian Standard Title International Standard
No
1 IS:209-1992 Specification for zinc BS:3436
2 IS:406-1991 Method of Chemical Analysis of Slab Zinc BS:3436
Porcelain insulators for overhead Power lines with a BS:137- (I&II)
3 IS:731-1991
nominal voltage greater than 1000 V IEC:60383
IS:2071 Part (I) –
1993 (Part(II)-
4 Methods of High Voltage Testing IEC:60060-1
1991, Part(III)-
1991
IS:2486 Specification for Insulator fittings for Overhead Power
BS:3288
Part- I-1993 Lines with a nominal voltage greater than 1000V
5 IEC:60120
Part- II-1989 General Requirements and Tests Dimensional
IEC:60372
Part-III-1991 Requirements Locking Devices
Recommended Practice for Hot, Dip Galvanization for
6 IS:2629-1990 ISO-1461 (E)
iron and steel
7 IS:2633-1992 Testing of Uniformity of Coating of zinc coated articles
8 IS:3188-1988 Dimensions for Disc Insulators IEC:60305
Determination of Weight of Zinc Coating on Zinc BS:433-1969
9 IS:6745-1990
coated iron and steel articles ISO:1460-1973
IEC:60437
10 IS:8263-1990 Methods of RI Test of HV insulators NEMA Publication
No.07/ 1964/ CISPR
11 IS:8269-1990 Methods for Switching Impulse test on HV insulators IEC:60506
4
SP-PI-01-R0
The Polymeric Insulator to be supplied against this specification shall be suitable for
satisfactory continuous operation under the following service conditions:
h) Climatic Conditions : Moderately Hot and humid tropical climate conductive to rust and fungus
growth
• The insulators of the strings shall consist of composite long rod insulators for a three phase, 50
Hz, effectively earthed transmission system application in a very heavy polluted environment.
Couplings shall be ball and socket type.
5
SP-PI-01-R0
• Bidder shall quote such composite insulators which have proven use under foggy/humid
operational conditions in polluted environment combined with smoke and dust particles. The
Bidder shall furnish evidence in the form of certification from the power utilities that the
similar type of product supplied to them had been performing satisfactory. The Bidder shall
also submit certified test report (from CPRI/ERDA) for an accelerated ageing test of 5000
hours such as that described in Appendix-C of IEC-61109.
• Insulators shall have sheds of the “open aerodynamic profile without any under ribs” with good
self-cleaning properties. Insulator shed profile; spacing projection etc. shall be strictly in
accordance with the recommendation of IEC-60815.
• The size of long rod insulator, minimum creepage distance, electromechanical strength and
mechanical strength of insulator string along with hardware fittings up to 66 KV shall be as
follows-
Mechanical strength
Size of Min.
EM strength of of Insulator string
Sl. Composite Creepage
Type of String Insulator Unit along with Hardware
No Insulator Distance
(KN) fittings
(mm) (mm)
(kN)
* Note: The core dia. of composite insulators mentioned at column No.3 is minimum requirement.
The bidder shall offer composite long rod insulators of suitable core dia to meet specified E&M
strength requirements. However, the overall string length shall be within the limits specified in the
drawing
• Pin and cap shall be designed to transmit the mechanical stress & develop uniform mechanical
strength in the insulator. The cap shall be circular with the inner and outer surfaces concentric
of such design that it will not yield or distort under load conditions
• The design shall be such as to permit easy removal of replacement of either insulator units or
fittings under the live line conditions.
6
SP-PI-01-R0
The dimensions of the Ball and Socket shall be of 16 mm for 90kN & 120kN Insulators in
accordance with the standard dimensions stated in IEC: 120/ IS: 2486 (Part-II).
The tolerances on all dimensions e.g. diameter, length and creepage distance shall be allowed as
follows:
± (0.04d+1.5) mm when d≤300 mm.
± (0.025d+6) mm when d>300 mm
4.5 Materials:
• Core- It shall be a glass-fiber reinforced (FRP rod) epoxy resin rod of high strength. Glass
fibers and resin shall be optimized. The rod shall be electrical grade corrosion resistant (ECR),
boron free glass and shall exhibit both high electrical integrity and high resistance to acid
corrosion.
• Housing and Weather sheds- The FRP rod shall be covered by a seamless sheath of a silicone
rubber compound of a thickness of minimum 3mm. The housing & weather sheds should have
silicon content of minimum 30% by weight. It should protect the FRP rod against
environmental influences, external pollution and humidity. It shall be extruded or directly
molded on the core. The interface between the housing and the core must be uniform and
without voids. The strength of the bond shall be greater than the tearing strength of the
polymer. The manufacturer shall follow non-destructive technique (N.D.T.) to check the quality
of jointing of the housing interface with the core. The technique being followed with detailed
procedure and sampling shall be furnished along with the bid. The details for this shall be
finalized during detailed engineering and finalization of MQP.
• End Fittings- End fittings transmit the mechanical load to the core. They shall be made of
malleable cast iron spheroidal graphite or forged steel. They shall be connected to the rod by
means of a controlled compression technique. The manufacturer shall have in-process Acoustic
emission arrangement or some other arrangement to ensure that there is no damage to the core
during crimping. This verification shall be in-process and done on each insulator. The gap
between fitting and sheath shall be sealed by a flexible silicone rubber compound. The system
of attachment of end fitting to the rod shall provide superior sealing performance between
housing and metal connection. The sealing must be humidity proof and durable with time
7
SP-PI-01-R0
• Corona Ring/Grading Ring- Grading rings shall be used at both ends of each composite
insulator unit for reducing the voltage gradient on and within the insulator and to reduce radio
and TV noise to acceptable levels. The size and placement of the metallic grading rings shall be
designed to eliminate dry band arcing/corona cutting/ exceeding of permissible electrical stress
of material. The bidder shall furnish calculations along with the proposed placement and design
of corona ring in support of the above. Grading rings shall be capable of installation and
removal with hot line tools without disassembling any other part of the insulator assembly.
* Note:-The supply of grading rings shall be in the scope of the composite insulator supplier.
5.1 Interchangeability- The composite long rod insulators inclusive of the ball & socket connection
shall be standard design suitable for use with the hardware fittings of any make conforming to
relevant IEC standards.
5.2 All surfaces shall be clean, smooth, without cuts, abrasions or projections. No part shall be
subjected to excessive localized pressure. The insulator and metal parts shall be so designed and
manufactured that it shall avoid local corona formation and shall not generate any radio interference
beyond specified limit under the operating conditions.
5.3 The long rod insulators offered shall be suitable for employment of hot line maintenance technique
so that usual hot line operation can be carried out with ease, speed and safety.
5.4 All insulators shall be designed to facilitate cleaning and insulators shall have the minimum
practical number of sheds and grooves. All grooves shall be so proportioned that any dust deposit
can be removed without difficulty either by wiping with a cloth or by remote washing under live
line condition.
5.5 All the materials shall be of latest design and conform to the best modern practices adopted in the
extra high voltage field. Bidders shall offer only such insulators as are guaranteed by him to be
satisfactory and suitable for transmission lines specified and will give continued good service
5.6 The design, manufacturing process and material control at various stages shall be such as to give
maximum working load, highest mobility, best resistance to corrosion, good finish and elimination
of sharp edges and corners to limit corona and radio interference
5.7 The design of the insulators shall be such that stresses due to expansion and contraction in any part
of the insulator shall not lead to deterioration.
5.8 The core shall be free from cracks and voids which may adversely affect insulator.
8
SP-PI-01-R0
5.9 Weather sheds shall be uniform in quality. They shall be clean, sound, smooth and free from gross
defects and excessive flashing at parting lines.
5.10 End fittings shall be free from cracks, seams, shrinks, air holes and rough edges. End fittings
should be effectively, sealed to prevent moisture ingress, effectiveness of sealing system must be
supported by test documents. All surfaces of the metal parts shall be perfectly smooth with the
projecting points or irregularities which may cause corona.
5.11 All load bearing surfaces shall be smooth and uniform so as to distribute the loading stresses
uniformly.
5.12 All ferrous parts shall be hot dip galvanized to give a minimum average coating of zinc
equivalent to 600 gm/sqmm and shall be in accordance with the requirement of ISO:1461 (E) and
shall satisfy the tests mentioned in ISO:1460 (E). The zinc used for galvanizing shall be of purity of
99.95%. The zinc coating shall be uniform, adherent, smooth, reasonably bright continuous and free
from imperfections such as flux, ash rust stains, bulky white deposits and blisters. The galvanized
metal parts shall be guaranteed to withstand at least six successive dips each lasting for one (1)
minute duration under the standard test. The galvanizing shall be carried out only after any
machining
The insulators should be offered type tested from CPRI/ERDA. Type test reports should not be more
than 5 (Five) years old considered from the date of bid opening in respect of all the tests carried out in
CPRI/ERDA, based on ISO/IEC.
9
SP-PI-01-R0
7.1 Acceptance Test : The following tests shall constitute the Acceptance : -
IS/IEC
Test Description
Reference
IEC : 61109 Verification of dimensions
Verification of tightness of interface between end fittings and insulator housing
and of specified mechanical load
10
SP-PI-01-R0
Note: - 1) Test on interfaces and connection shall be carried out for a lot with qty. minimum 2000 nos.
2) Test for silicon shall be carried out for a lot with qty. minimum 2000 nos.
3) In the event of failure of the sample to satisfy the acceptance test(s) specified above, the
retest procedure shall be as per clause 7.6 of IEC 61109
2) Chemical analysis, mechanical, metallographic test and magnetic particle inspection for
malleable castings.
3) Chemical analysis hardness tests and magnetic particle inspection for forging.
11
SP-PI-01-R0
Inspection:
SL No. Descriptions
7.3.1 The buyer reserves the right to witness all tests specified on Polymeric Insulators
The buyer reserves the right to inspect Polymeric Insulators at the Seller’s works at any
7.3.2
time prior dispatch, to verify compliance with the specifications
7.3.3 In-process and final inspection call intimation shall be given in advance to purchaser
In the event of any discrepancy in the test report i.e. test reports not acceptable or any type
7.3.4 test (including special/additional test if any) not carried out, same shall be carried out
without any cost implication to BSES before dispatch.
Note:
1) The routine and acceptance tests should be performed on sample chosen at random out of
every lot.
2) Three sets of complete test certificates shall be submitted along with the dispatch documents.
8.3 Submission required a) Inspection and test reports carried out in manufacturer's works
prior to dispatch
b) Test Certificate of all bought out items.
Drawing and Documents
8.4 Standard size paper A0,A1,A2,A3,A4
Size
12
SP-PI-01-R0
No of drawings/
8.5 documents required at As per Annexure A
different stages
10 Progress reporting:
13
SP-PI-01-R0
11 Deviations:
Deviations from this Specification shall be stated in writing with the tender by reference to the
Specification clause/GTP/Drawing and a description of the alternative offer. In absence of such a
statement, it will be assumed by the Buyer that the Seller complies fully with this specification.
The bidder has to summit drawings along with bid for preliminary acceptance and for final approval
before manufacturing. BRPL may insist trial installation to check dimensions and may suggest
necessary changes if required. BRPL decision in this regard would be final and binding to short listed
vendor without any subsequent commercial liability on purchaser.
12 Marking:
13 GTP:
Data to be filled by
Sl. No. Descriptions Unit
Manufacturer
1 Name & address of manufacture
2 Weight of single unit Kg
3 Size and designation of ball & socket assembly mm
4 Core diameter mm
5 Tolerance on core diameter ±mm
6 Nominal length (section length) mm
7 Tolerance on Nominal length ±mm
8 Dry arcing distance mm
9 Number of sheds nos
10 Sheds profile (type)
11 Shed spacing mm
12 Sheds profile (regular alternating)
13 Shed diameter mm
14 Tolerance on shed diameter ±mm
15 Minimum creepage distance mm
16 Tolerance on creepage distance ±mm
14
SP-PI-01-R0
1.1 Design, manufacturing, testing at manufacturer works before dispatch, packing, delivery
including unloading and stacking at Buyer’s site/store of Polymeric Insulator including all kind
oh accessories for fixing e.g. fixing clump, hardwires etc as per BOQ and submission of all
documents.
15
SP-PI-01-R0
For
Approval
Final after
Along with offer after Remarks
approval
award of
contract
Detailed dimensional
cross-sectional drawing 6 copies + 1 soft
3 copies (Typical drgs) 4 copies
along with all kind of copy in CD
accessories for fixing
Type test and
2 copies (Type test and 6 copies + 1 soft
Type test certificates sample Routine
sample Routine Test) copy in CD
test reports
Guaranteed technical 6 copies + 1 soft
3 copies 4 copies
particulars copy in CD
Complete catalogue and 6 copies + 1 soft
1 copy
Manual copy in CD
6 copies + 1 soft
List of sub vendor 3 copies (typical) 4 copies
copy in CD
16