You are on page 1of 61

SALWA

DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

DIVISION 05. METALS 
SECTION 05 10 00. STRUCTURAL METAL FRAMING 
 

1. PART 1 ‐ GENERAL 
Drawings and general provisions of the Contract, including General and Supplementary Conditions 
and Division 01 Specification Sections, apply to this Section. 

1.1. SECTION INCLUDES 
These  technical  specifications  cover  the  requirements  for  the  METAL  FRAMING  included    in  the 
Salwa Dahab Mountains Waterpark and Adventure Park. 

1.2. RELATED SECTION 
Section D05/05 30 00 metal decking. products 

1.3. REFERENCE STANDARDS 
The following standards and codes of practice are referenced within the Specification. All materials, 
workmanship and testing shall conform to the requirements of the latest editions of the following 
Standards and Codes of Practice except as explicitly varied by this specification: 

BRITISH STANDARDS: 

 BS 5950: Structural use of Steelwork in buildings 
 BS 8004: Foundations 
 BS 5950: Structural use of Steelwork in buildings 
 BS 8110: Structural use of concrete:  
 BS 8500‐1:2006, Annex A, Guidance for the specifier 

QATAR NATIONAL CONSTRUCTION STANDARDS 2010: 

 Section 16 Part 1: General 
 Section 16 Part 2: Materials 
 Section 16 Part 3: Drawings 
 Section 16 Part 4: Fabrication 
 Section 16 Part 6: Bolting 
 Section 16 Part 7: Accuracy of Fabrication 
 Section 16 Part 8: Erection 
 Section 16 Part 9: Accuracy of Erected Steelwork 
 Section 16 Part 10: Protective Treatment 

1.3.1 WELDING 
The following welding standards are referred in this section: 

BRITISH STANDARDS: 
    Structural Metal Framing
    05 10 00 / 1        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
 BS 3923 Methods for ultrasonic examination of welds 
 BS 4570 Fusion welding of steel castings 
 BS 4872 Approval testing of welders when welding procedure approval is not required 
 BS 5135 Process of arc welding of carbon and carbon manganese steels 
 BS 5289 Code of practice for visual inspection of fusion welded points 
 BS 6072 Method for magnetic particle flaw detection 
 BS 6443 Penetrant flaw detection 
 BS EN 287 Approval testing of welders for fusion welding 
 BS EN 288 Approval of welding procedures for metallic materials 

1.4. PERFORMANCE REQUIREMENTS 
A. Connections:  Design  and  provide  details  of  all  connections  required  by  the  Contract 
Documents  to  withstand  LRFD  loads  as  indicated  and  comply  with  other  information  and 
restrictions indicated 

1. Design the connections according QCS Section16 "Structural steelworks" 

2. Engineering  Responsibility:  Contractor's  responsibilities  include  using  a  qualified 


professional  engineer  to  check  and  verify  that  the  structural‐steel  connections  meet 
the design loads 

B. The  contractor  is  responsible  to  provide  detailed  design  (including  calculations  and 
drawings)  for  all  the  structural  steel  elements  and  connections  matching  with  the  design 
intent  and  submit  to  the  Design  Engineer  for  review  and  approval  prior  to  start  the 
fabrications 

1.5. SUBMITTALS 
A. Country  and  rolling  mill  origin  and  statement  indicating  that  the  steel  is  new  billet  steel  and 
that testing has been performed in accordance with the specified standards 

B. Product  data  or  manufacturer's  specifications  and  installation  instructions  for  following 
products.  Include  laboratory  test  reports  and  other  data  to  show  compliance  with 
specifications (including specified standards) 

1. Structural steel (each type), including certified copies of mill reports covering chemical 
and physical properties 

2. High‐strength bolts (each type), including nuts and washers 

a. Include Direct Tension Indicators if used. 

3. Structural steel primer paint 

4. Shrinkage‐resistant grout 

C. Shop drawings prepared under supervision of a Structural Engineer with 10 year experience in 
design,  including  complete  calculations,  details  and  schedules  for  fabrication,  connection 
design  and  assembly  of  structural  steel  members,  procedures,  and  diagrams,  Shop  Drawings 
show fabrication of structural‐steel components 

    Structural Metal Framing
    05 10 00 / 2        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
1. Submit  detailed  construction  drawings,  along  with  design  calculations  for  review 
and approval 

2. Include  details  of  cuts,  connections,  splices,  camber,  holes,  and  other  pertinent 
data 

3. Include embedment drawings 

4. Indicate  welds  by  standard  AWS  symbols,  distinguishing  between  shop  and  field 
welds, and show size, length, and type of each weld 

5. Indicate type, size, and length of bolts, distinguishing between shop and field bolts. 
Identify pre‐tensioned and slip‐critical high‐strength bolted connections 

6. For  structural‐steel  connections  indicated  to  comply  with  design  loads,  include 
structural  analysis  data  prepared,  signed  and  sealed  by  the  qualified  professional 
engineer with minimum ten year experience responsible for their preparation 

7. Field  assembly  and  erection  drawings  which  show  all  field  assembly  prior  to 
erection  and  after  erection.  The  drawings  shall  indicate  all  details,  schedules, 
procedures  and  diagrams  showing  field  assembly  and  sequence  of  erection.  The 
information  shall  indicate  locations  of  shoring  and  how  shoring  is  stabilized  and 
controlled.  The  drawings  shall  indicate  elevations  of  shored  points  and  splice 
locations. The procedures shall indicate step by step erection sequences including 
intermediate  surveys  and  allowances  for  temperature.  Diagrams  shall  indicate 
erection  equipment  size  and  weight  and  additional  elements  which  may  be 
required to support or stabilize elements during erection 

8. The  Contractor  shall  prepare  and  submit  to  the  Engineer  written  procedures  for 
fabrication  of  the  steel  work.  The  procedure  shall  describe  the  complete  welding 
process  including  machine,  current,  voltage,  preheat,  filler  metal,  welding  system 
(manual, semi‐automatic or automatic), positions of welding, number of passes for 
each weld size, preparation of surfaces prior to welding, etc. These procedures shall 
indicate  the  Contractor's  quality  control  measures,  monitoring  and  repair 
procedures 

D. Erection Drawings 

1. Include, but is not limited to: 

a. Detailed statement of erection procedure 

b. Drawings and calculations for setting out and requirement for trial erection at the 
place of fabrication 

c. Drawings and calculations for all temporary works to be used during erection 

d. Calculations of all erection loads and stresses and deflections 

    Structural Metal Framing
    05 10 00 / 3        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
e. All drawings and calculations shall be in sufficient detail, to ensure the Contractor's 
proposed  erection  procedures  are  clearly  defined  with  details  of  temporary 
attachments for lifting and erection 

E. Welding certificates 

F. Qualification  Data:  For  Installer  Fabricator  Professional  engineer  and  Independent  Testing 
Agency 

G. Mill Test Reports: Signed by manufacturers certifying that the following products comply with 
requirements: 

1. Structural steel including chemical and physical properties 

2. Bolts, nuts, and washers including mechanical properties and chemical analysis 

3. Direct‐tension indicators 

4. Tension‐control, high‐strength bolt‐nut‐washer assemblies 

5. Shear stud connectors 

6. Shop primers 

7. Nonshrink grout 

H. Source quality‐control test reports 

I. Test  reports  conducted  on  shop  and  field‐bolted  and  welded  connections.  Include  data  on 
type(s) of tests conducted and test results 

J. Certified  copies  of  each  survey  conducted  by  a  Land  Surveyor  with  10  years  experience  in 
similar  works,  showing  elevations  and  locations  of  base  plates  and  anchor  bolts  to  receive 
structural  steel  and  final  elevations  and  locations  for  major  members.  Indicate  discrepancies 
between actual installation and contract documents 

K. Contractor shall submit Method Statement for fabrication and erection sequences 

1.6. QUALITY ASSURANCE 
A. Structural steel work shall be executed by an approved specialist contractor with proven track 
record in the fabricator and erection of similar steel works to this project 

B. Qualifications  for  Welding  Work:  Qualify  welding  procedures  and  welding  operators  in 
accordance QCS Section 16 Part 5 Item 5.3"Welding procedures" 

1. Provide certification that welders to be employed in work have satisfactorily passed QCS 
qualification tests 

2. If recertification of welds is required, retesting will be Contractor's responsibility 

C. Contractor shall engage a specialized testing laboratory (Third Party) approved by the Engineer 
for QAQC, tension tests of structural steel members, inspection for connections, jointing and 
welding. Perform tests and prepare test reports as required 

    Structural Metal Framing
    05 10 00 / 4        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
D. Shop‐Painting Applicators: Qualified according to QCS Section 16 Part 10 

E. Pre‐installation  Conference:  The  Contractor  shall  schedule  and  conduct  conference  at  the 
project site. As a minimum, the meeting shall include the Contractor, Fabricator, Erector, the 
finish painting subcontractor, and the Engineer. Coordinate requirements for shipping, special 
handling, attachment of safety cables and temporary erection bracing, touch up painting and 
other requirements for Works 

1.7. DELIVERY, STORAGE, AND HANDLING 
A. Do not deliver material to the project site until the proposed method and sequence of erection 
has been reviewed and approved by the Engineer. Method and sequence shall be planned so 
as to avoid delay or damage to the work of other trades 

B. Deliver materials to site at such intervals to ensure uninterrupted progress of work 

C. Deliver  anchor  bolts  and  anchorage  devices,  which  are  to  be  embedded  in  cast‐in‐place 
concrete or masonry, in ample time to not to delay work 

D. Store materials to permit easy access for inspection and identification. Keep steel members off 
ground  by  using  pallets,  platforms,  or  other  supports.  Protect  steel  members  and  packaged 
materials from corrosion and deterioration. If  bolts and nuts become dry or rusty, clean  and 
relubricate before use 

1. Store fasteners in a protected place. Clean and re‐lubricate bolts and nuts that become 
dry or rusty before use 

2. Do not store materials on structure in a manner that might cause distortion or damage 
to members or supporting structures. Repair or replace damaged materials or structures 
as directed 

1.8. WELDER QUALIFICATION 
1.8.1 Testing 
1. Welders shall be tested to meet the requirements of BS EN 287 Part 1 but, in the case of 
welders engaged on fillet welding only, BS 4872 Part 1 is an acceptable alternative 
2. As an alternative, when permitted by the Employer, welders may be tested to meet the 
requirements of the American Society of Mechanical Engineers, ASME IX, or the American 
Welding Society, AWS Dl.1 

1.8.2 CERTIFICATION 
1. Welder testing shall be witnessed and certificates endorsed by an independent Inspection 
Authority 
2. The certification shall remain valid providing it complies with the conditions for re‐approval of 
certification specified in BS EN 287 Part 1 

   

    Structural Metal Framing
    05 10 00 / 5        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

2. PART 2 – PRODUCTS 
A. Products and fabricators specified hereinafter are specified for the purposes of establishing 
minimum  quality  standards  and  performance  requirements.  Products  which  are  equal  to, 
or better than those specified, and  which  conform to the  Engineer’s design requirements 
and color selections, may be acceptable subject to Engineer’s approval 
B. Structural Steel Fabricators: 

1. Eversendai Eng’g 

Qatar 
Tel: 974 4466 7626 
Fax: 974 4466 7316 

2. Butler ATC 

Qatar 
Tel: 974 4435 5994 
Fax: 974 4435 5997 

3. Zamil Steel 

Saudi Arabia 
Tel: 966 3 812 1120 
Fax: 966 3 812 1281 

4. Cleveland Bridge 

P.O. Box 16765, Dubai, UAE. 
Tel: 971 4 8835551 
Fax: 9714 8835416 

5. Al Nasr Engineering 

P.O. Box 1106, Dubai, UAE 
Tel: 971 4 8835030 
Fax: 971 4 8835553 

6. Emirates Building Systems 

Dubai 
Tel: 971 4 885 1122 
Fax: 971 4 885 1211 

7. Galadari Engineering Works 

P.O. Box 355, Dubai 
Tel: 971 4 2667318 
Fax: 971 4 2662151 

8. Emarates Steel 

    Structural Metal Framing
    05 10 00 / 6        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
UAE 
Tel: 971 2 551 1187 

9. Tiger Steel 

P.O. Box 6169, Sharjah 
Tel: 971 6 533 0775 
Fax: 971 6 533 9772 

10. Al Habtoor Murray 

UAE. 
Email: jocoshj@emirates.net.ae 

11. Amana Steel 

UAE 

12. Or Approved Equal 

C. The  jointing  system  (both  nodes  and  bars)  must  be  tried  and  tested  and  must  meet  the 
requirements described in the jointing system notes. 
D. The following systems are recommended: 

1. ORTZ Structural System.  

Company: LANIK.  
Paseo Mundai, 8 ‐ 20012 San Sebastian ‐ SPAIN 
www. lanik.com 

2. KUGEL KNOTEN (KK‐SYSTEM) : 

Company:  NOVUM  STRUCTURES.  Schleehosfstrasse  12  97209  Veitshoechheim  ‐ 


GERMANY 
www. novumstructures.com 

3. KK‐BALL NODE SYSTEM: 

Company: MERO STRUCTURES INC. 115 Kane St, Apt 1A Brooklyn, NY 11231 ‐ UNITED 
STATES OF AMERICA 
www. mero‐structures.com 
2.1. MATERIALS 
A. Metal  Surfaces,  General:  For  fabrication  of  work  that  will  be  exposed  to  view,  use  only 
materials  that  are  smooth  and  free  of  surface  blemishes  including  pitting,  rust  and  scale 
seam marks, roller marks, rolled trade names, and roughness. Remove such blemishes by 
grinding,  or  by  welding  and  grinding,  prior  to  cleaning,  treating,  and  applying  surface 
finishes 
B. Structural Steel Shapes, Plates, and Bars: BS EN 1025 
C. Cold‐Formed Hollow Structural Sections: BS10219 

    Structural Metal Framing
    05 10 00 / 7        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
D. Wide flange sections: BS 4 
E. Corrosion‐resistant Structural Steel: EN 10025‐5 
F. Anchor Bolts: BS 8539 
G. Unfinished Threaded Fasteners: BS 2996, regular low‐carbon steel bolts and nuts 

1. Provide hexagonal heads and nuts for all connections. 

H. High‐Strength  Threaded  Fasteners:  Heavy  hexagon  structural  bolts,  heavy  hexagon  nuts, 
and hardened washers, BS 4395 
I. Direct Tension Indicators: BS EN 14399, type as required 

1. Use on all A325 and A490 bolts on connections that are slip critical 

J. Clevises or Turnbuckles: BS 1320, cold‐finished carbon steel 
K. Eye Bolts and Nuts: BS 4253, cold‐finished carbon steel 
L. Sleeve Nuts: ASTM A 108, Grade 1018, cold‐finished carbon steel 
M. Electrodes for Welding: Comply with QCS Code 
N. Bearing Pads: Provide bearing pads as shown on drawings
O. Fireproofing
P. Cementitious Grout 

2.1.1 Steel roof framing and jointing system 
Spherical nodes: Carbon SteelC45E or C45R Normalized 

Tubular  bars:  Welded,  Cold‐Rolled  Steel  Tube.  Ideal  for  electro‐welded  applications  and  in 
compilance with the specifications outlined in QCS Section 16. The structural steel grade used for 
production is S275 

Conical  fittings:  Tempred,  Weldable  Steel.  Conical  fittings  of  the  same  steel  are  sometimes 
fashioned  from  machined  bars.  In  any  case,  digital  robotics  ensure  presssion  of  the  dimensional 
tolerance points during the wleding and bevelong processes 

Chemical composition (maximum %) 
C  Mn  Si  P  S 
0,2‐0,3  0,5‐0,8  0,15‐0,4  <0,035  <0,035 
 

Dual‐Threaded  Bolts:  Tempering  of  the  bolts  guarantees  increased  endurance  of  the  material 
without affecting its capacity 

    Structural Metal Framing
    05 10 00 / 8        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

Min. yield  Traction  Tensile 


Resilience 
Bolt type  Steel  Point  Resistance  Strenght 
(N/mm2)  (N/mm2)  (Tons)  At 20ºC (J) 
12/16  7,7 
16/20  1.7225  14,5 
22/27  42CrMo4  28 
30/36  Min.1000  51,5 
900  27 
37/45  Max.1250  79,9 
45/52  F1272  112,8 
54/64  40NiCrMo7  180 
64/76  263 
 

Chemical composition (%) 
Elements 1.7225(42CrMo4)  F1272 (40NiCrMo7) 
C   0,38‐0,45  0,37‐0,43 
Si  Max. 0,4  0,15‐0,4 
Mn  0,6‐0,9  0,55‐0,85 
P  Max.0,035  Max.0,035 
S  Max.0,035  Max.0,035 
Cr  0,9‐1,20  0,65‐0,95 
Mo  0,15‐0,3  0,15‐0,3 
Ni  ‐  1,6‐2 
 

2.2. FABRICATION 
A. Prior  to  commencing  fabrication  all  dimensions  to  be  checked  on  site  by  the  fabricator. 
Fabricator  to  ensure  adequate  allowance  is  made  for  site  tolerance  of  the  supporting 
elements  of  the  new  steelwork.  Packing  to  each  end  connection  should  be  limited  to  a 
maximum overall thickness of 30mm. If packing is used then allowance must be made for 
any associated reduction in bolt capacity by the fabricator in the connection design 
B. Fabrication and Assembly: Fabricate and assemble structural assemblies in shop to greatest 
extent  possible.  Fabricate  items  of  structural  steel  in  accordance  with  AISC  Specifications 
and as indicated on final shop drawings 

1. All  connections  for  shop  or  field  connections  or  splicing  shall  be  shown  on  the  shop 
fabrication drawings for review prior to fabrication 
2. No  combination  of  bolts  and  welds  shall  be  used  for  stress  transmission  in  the  same 
faying face of any connection 
3. The toughness and notch sensitivity of the steel shall be considered in the formation of 
all  welding  procedures  to  prevent  brittle  and  premature  fracture  during  fabrication 
and erection 
4. Welded  connections  shall  be  detailed  and  designed  to  minimize  the  accumulation  of 
thru‐thickness strains due to weld shrinkage 

    Structural Metal Framing
    05 10 00 / 9        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
5. Drill or punch holes at right angles to the surface of the metal, not more than 1.5 mm 
larger  than  the  connector  diameter.  Do  not  make  or  enlarge  holes  by  burning.  Holes 
shall be clean‐cut without torn or ragged edges. Remove outside burrs resulting from 
drilling operations 
6. Properly  mark  and  match‐mark  materials  for  field  assembly.  Fabricate  for  delivery 
sequence that will expedite erection and minimize field handling of materials 

C. Connections: Weld or bolt shop connections, as indicated 
D. Bolt  field  connections,  except  where  welded  connections  or  other  connections  are 
approved 

1. Provide  high‐strength  threaded  fasteners  for  all  bolted  connections,  except  where 
unfinished bolts are indicated 
2. The bolted connection shall have 3 thread rotations projection beyond the nut E. High‐
Strength  Bolted  Construction:  Install  high‐strength  threaded  fasteners  in  accordance 
with AISC "Specifications for Structural Joints using ASTM A 325 or A 490 Bolts." 

E. Welded  Construction:  Comply  with  QCS  Code  for  procedures,  appearance  and  quality  of 
welds, and methods used in correcting welding work 
F. Assemble and weld built‐up sections by methods that will produce true alignment of axes 
without warp 
G. Holes  for  Other  Work:  Provide  holes  required  for  securing  other  work  to  structural  steel 
framing and for passage of other work through steel framing members, as shown on final 
shop drawings 
H. Provide threaded nuts welded to framing and other speciality items as indicated to receive 
other work 
I. Cut, drill, or punch holes perpendicular to metal surfaces. Do not flame‐cut holes or enlarge 
holes by burning. Drill holes in bearing plates 
J. Fabrication  tolerances:  As  per  QCS  Section  16  Part  7  "Structural  steelworksAccuracy  of 
Fabrication" 

2.3. SHOP CONNECTIONS 
A. High‐Strength Bolts: Shop install high‐strength bolts according to BS 4395 for type of bolt 
and type of joint specified 

1. Joint Type: As indicated on drawings 

B. Weld Connections: Comply with QCS Section 16 Part 5 "Strcutural steelworks. Welding" for 
welding  procedure  specifications,  tolerances,  appearance,  and  quality  of  welds  and  for 
methods used in correcting welding work 

1. Remove backing bars or runoff tabs, back gouge, and grind steel smooth 
2. Assemble and weld built‐up sections by methods that will maintain true alignment of 
axes without exceeding tolerances of QCS Section 16 Part 9  

    Structural Metal Framing
    05 10 00 / 10        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
3. Verify  that  weld  sizes,  fabrication  sequence,  and  equipment  used  for  architecturally 
exposed structural steel will limit distortions to allowable tolerances 
a. Grind butt welds flush 
b. Grind or fill exposed fillet welds to smooth profile. Dress exposed welds 

2.4. SHOP PRIMING 
A. No material shall be shipped or delivered to site until the shop coat has dried. Shop paint all 
metal except the following: 

1. Surfaces  embedded  in  concrete  or  mortar.  Extend  priming  of  partially  embedded 
members to a depth of 50 mm 
2. Surfaces to be field welded 
3. Surfaces to be high‐strength bolted with slip‐critical connections 
4. Galvanized surfaces 
5. Surfaces to receive sprayed fire resistive materials 

B. Surface  Preparation:  Clean  surfaces  to  be  painted.  Remove  loose  rust,  loose  mill  scale, 
spatter,  slag  or  flux  deposits.  Prepare  surfaces  according  to  QCS  Section  16  Part  10 
specifications 
C. Shop  Painting:  Immediately  after  surface  preparation,  apply  primer  according  to 
manufacturer’s instructions and to provide a dry film thickness of not less than 75microns. 
Use  priming  methods  that  result  in  full  coverage  of  joints,  corners,  edges  and  exposed 
surfaces. Stripe paint corners, crevices, bolts, welds, and sharp edges. 

1. Structural steel shall be shop primed complying with QCS Section 16 Part 10 

2.5. SOURCE QUALITY CONTROL 
A. General:  Materials  and  fabrication  procedures  are  subject  to  inspection  and  tests  in  mill, 
shop, and field, conducted by a qualified inspection agency. Such inspections and tests will 
not relieve Contractor of responsibility for providing materials and fabrication procedures 
in compliance with specified requirements. 

1. Promptly remove and replace materials or fabricated components that do not comply 

B. Correct  deficiencies  in  Work  that  test  reports  and  inspections  indicate  does  not  comply 
with the Contract Documents 
C.  Bolted  Connections:  Shop  bolted  connections  will  be  tested  and  inspected  according  to 
QCS Setion 16 Part 6 "Structural steelworks.Bolting" 
D. Welded  Connections:  In  addition  to  visual  inspection,  shop‐welded  connections  will  be 
tested and inspected according to QCS Section 16 Part 5 "Structural steelworks. Welding" 
and the following inspection procedures, as directed by Engineer: 

1. Liquid Penetrant Inspection 
2. Magnetic Particle Inspection performed on root pass and on finished weld. Cracks or 
zones of incomplete fusion or penetration will not be accepted 
3. Ultrasonic Inspection  

    Structural Metal Framing
    05 10 00 / 11        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
4. Radiographic Inspection  

E. In addition to visual inspection, shop‐welded shear connectors will be tested and inspected 
according  to  requirements  in  QCS  Section16  Part  5  "Structural  steelworks.  Welding"  Item 
5.6 for shear stud welding and as follows: 

1. Bend tests will be performed if visual inspections reveal either a less than continuous 
360 degree flash or welding repairs to any shear connector 
2. Tests will be conducted on additional shear connectors if weld fracture occurs on shear 
connections already tested 

2.6. 05 12 00‐S275: STEEL GRADE 275 JR 
Steel  for  steel  structure  shall  be  275  JR  Grade  according  to  BS  5950  and  hot  dip  galvanized  in 
accordance with BS 729.  

Structural  steel  works  and  steel  structural  members  shall  be  conform  to  the  requirements  of  the 
QCS Section 16 Part 2. 

Dimensions  and  tolerances  of  the  steel  structural  members  shall  be  according  to  the  standards 
shown in table 2.1 , QCS Part 2 Section 16. 

   

    Structural Metal Framing
    05 10 00 / 12        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

3. PART 3 ‐ EXECUTION 
Galvanizing shall be performed in accordance with BS 729. 

3.1. TOUCH‐UP OF GALVANIZED SURFACES 
Small areas which are within 10 mm of intact galvanized coating may be touched up in accordance 
with Appendix D of BS 729. 

Preparation for touching up is to be as required by the manufacturer ot the one‐touch product. 

3.2. VENT HOLES 
If  so  required  by  the  Engineer,  vent  holes  in  hollow  members,  necessary  during  the  galvanizing 
process, shall be sealed after galvanizing with a plug of approved material. 

3.3. EXAMINATION 
A. Verify  elevations  of  concrete  and  masonry‐bearing  surfaces  and  locations  of  anchor  rods, 
bearing  plates,  and  other  embedments,  with  steel  erector  present,  for  compliance  with 
requirements 
B. Proceed with installation only after unsatisfactory conditions have been corrected 

3.4. PREPARATION 
A. Provide temporary shores, guys, braces, and other supports during erection to keep structural 
steel secure, plumb, and in alignment against temporary construction loads and loads equal in 
intensity  to  design  loads.  Remove  temporary  supports  when  permanent  structural  steel, 
connections, and bracing are in place, unless otherwise indicated 

1. Do not remove temporary shoring supporting  composite deck construction until cast‐in‐
place concrete has attained its design compressive strength 

3.5. EXECUTION GENERAL 
A. Where  inspection  reveals  defects,  the  extension  of  inspection  will  be  increased  as  much  as 
necessary to ensure that the full extent of the defects in a joint has been found and to ensure 
that  the  same  defects  are  not  present  in  welds  made  on  similar  parts  or  under  similar 
circumstances 
B. Work that is not acceptable will be designated by "Repair" or "Reject", as applicable 
C. Shop welds will be inspected in the shop before the work is primed and ready for shipment 
D. Each bolting crew and welder shall be assigned an identifying symbol or mark and all shop and 
field connections shall be identified so that the inspector can refer back to the crew or person 
making the connection 
E. The  Engineer  and  the  Testing  Laboratory  shall  inspect  structural  steel  at  the  plant  before 
shipment; however, the Engineer reserves the right to reject any material, at any time before 
final  acceptance,  which  does  not  conform  to  all  of  the  requirements  of  the  Drawings  and 
Specifications 

    Structural Metal Framing
    05 10 00 / 13        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
F. The  Contractor  shall  coordinate  and  allow  for  necessary  time  for  the  Testing  Laboratory  to 
complete all testing and inspections prior to shop painting 
G. The  Testing  Laboratory  shall  prepare  test  specimen  from  steel  samples  cut  from  delivered 
material and shall conduct tension tests in accordance with ASTM standards. 
H. The Contractor shall mill order 1.0 meter extra length for the members noted on the Drawings. 

3.6. WELDING PROCEDURES 
3.6.1 Preparation of Procedures 
Approved written welding procedures shall be available in accordance with BS 5135, and tested in 
accordance with BS EN 288 Part 3 by the Contractor. 

3.6.2 Approval of Procedures and Procedure Tests 
Procedures and tests shall be approved by an independent Inspection Authority. 

3.6.3 Availability of Welding Procedure Sheets 
Welding Procedure sheets shall be made available to the welder prior to the commencement of the 
work and shall be available to the Engineer and Inspection Authority on request. 

3.7. WELDING PROCEDURES 
3.7.1 Fit‐up 
Joints shall be fitted up to the dimensional accuracy required by the welding procedure, depending 
on the process to be used, to ensure that the quality in Table 5.2 is achieved. 

3.7.2 Jigs 
Fabrications assembled in jigs may be completely welded in the jig, or may be removed from the jig 
after tack welding. 

3.7.3 Tack Welds 
1. Tack welds shall be made using the same procedures as for the root runs of main welds. The 
length of the tack shall be the lesser of 4 times the thickness of the thicker part or 50 mm, 
unless demonstrated by a weld procedure qualification 
2. Tack welds which are not defective may be incorporated into main welds provided that the 
welder is qualified as in Clause 5.2 of QCS Section 16 Part 5. However, where joints are welded 
using an automatic or mechanised process, the suitability of the tack weld used for 
incorporation into automatic processes shall be demonstrated in the weld procedure 
qualification 
3. Where tack welds are made in circumstances other than those identified above, they must be 
removed 

    Structural Metal Framing
    05 10 00 / 14        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

3.7.4 Distortion Control 
The sequence of welding a joint or a sequence of joints shall be such that distortion is minimised 
(see Part 7 of QCS Section 16) 

3.7.5 Fabrication or Erection Attachments 
1. Welding of attachments required for fabrication or erection purposes shall be made in 
accordance with the requirements for a permanent weld 
2. When removal is necessary, they shall be flame cut or gouged at a point not less than 3 mm 
from the surface of the parent material. The residual material shall be ground flush and the 
affected area visually inspected. When thicknesses are greater than 20 mm it shall also be 
checked by magnetic particle inspection. Acceptance criteria are as set out in Table 5.2. 
Attachments shall not be removed by hammering. (See Clause 3.4.2 of of QCS Section 16 Part 
5) 

3.7.6 Extension Pieces 
Where the profile of a weld is maintained to the free end of a run by the use of extension pieces 
they  shall  be  of  material  of  a  similar  composition,  but  not  necessarily  the  same  grade,  as  the 
component. They shall be arranged so as to provide continuity of preparation and shall be removed 
after completion of the weld and the surface ground smooth. 

3.7.7 Production Test Plates 
Where production test plates are required for testing purposes, they shall be clamped in line with 
the joint. The grade of material and rolling direction shall match the parent plate, but need not be 
cut from the same plates or cast. 

3.8. NON‐DESTRUCTIVE TESTING OF WELDS 
3.7.1 Record of Testing 
The test results shall be recorded and be available for inspection by the Engineer. 

3.7.2 Visual Inspection of Welds 
1. Visual inspection shall be made in accordance with guidance given in BS 5289 over the full 
length of the weld and before NDT inspection is performed (see below). Any welds which will 
be rendered inaccessible by subsequent work shall be examined in accordance with tables 
below prior to the loss of access 
2. A suitably qualified person for visual inspection of welds may be a welding inspector or a 
welder who can provide evidence of having been trained and assessed for competence in 
visual inspection of the relevant types of welds 
 
 

    Structural Metal Framing
    05 10 00 / 15        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
 

3.7.3 Surface Flaw Detection 
1. Where a closer examination of a weld surface is required in accordance with table beow, 
magnetic particle inspection (MPI) shall be used in accordance with the recommendations 
given in BS 6072 
2. If magnetic particle inspection equipment is not available, dye penetrant inspection (DPI) may 
be used in accordance with the recommendations given in BS 6443 
3. Final surface flaw detection of a welded joint shall be carried out not less than 16 hours from 
the time of completion of the weld to be inspected, or not less than 40 hours in the case of 
welds to Design Grade 55 material. The Contractor shall note that where a welding procedure 
requires an inspection after initial weld runs before further welding is performed, such 
inspections may be carried out when the weld metal has cooled to ambient temperature 
4. A suitably qualified person for surface flaw detection of welds may be a welding inspector or a 
welder who holds a current certificate of competence in surface flaw detection of the relevant 
types of work, from a nationally recognised authority 

3.7.4 Ultrasonic Examination 
1. Where ultrasonic examination is required in accordance with tables below, it shall be made in 
accordance with BS 3923 Part 1, Level 2B. Examination shall be carried out not less than 16 
hours from the time of completion of the weld to be inspected, or not less than 40 hours in the 
case of butt welds thicker than 40 mm or any welds to Design Grade 55 material 
2. Operators carrying out final ultrasonic examination of the weld shall hold a current certificate 
of competence from a nationally recognised authority 

3.7.5 Scope of Inspection 
The  scope  of  inspection  shall  be  in  accordance  with  Table  below.  The  requirements  of  this  table 
shall not preclude the use of Non‐ Destructive Testing outside the limits shown should the results of 
visual inspection or NDT indicate that a lapse in quality may have occurred in specific joints 

PART A. VISUAL INSPECTION


Prior to Non -Destructive Testing all welds to be visually inspected by a
suitably qualified person (See Clause 5.5.2 of QCS Section 16 Part 5)
 

    Structural Metal Framing
    05 10 00 / 16        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

    Structural Metal Framing
    05 10 00 / 17        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

    Structural Metal Framing
    05 10 00 / 18        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

 
3.7.6 Acceptance Criteria and Corrective Action 
1. Acceptance criteria, corrective action and re‐testing shall be in accordance with table  below 
for components subject to static loading 

    Structural Metal Framing
    05 10 00 / 19        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
2. The acceptance criteria shown in table below are not intended to apply to bridges, offshore 
structures, or other dynamically loaded structures 

    Structural Metal Framing
    05 10 00 / 20        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

    Structural Metal Framing
    05 10 00 / 21        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

    Structural Metal Framing
    05 10 00 / 22        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

3.9. SHEAR STUD WELDING 
3.9.1 Method 
Shear studs shall be welded in accordance with the manufacturer's recommendations for materials, 
procedures and equipment. 

3.9.2 Trial Welding 
1. When specified by the Engineer and before production welding of studs commences, 
procedure trials shall be carried out. The trials shall be made on samples of material and studs 

    Structural Metal Framing
    05 10 00 / 23        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
representative of those to be used in the work. The samples of materials and studs shall be 
agreed with the Engineer 
2. Where primers are to be applied to the work prior to the welding of studs they shall be applied 
to the sample material before the procedure trials are made 

3.9.3 Tests and Inspection 
1. All studs are to be visually inspected. They shall show a full 360º collar 
2. At locations agreed with the Engineer a minimum of 5% of studs which have satisfied the visual 
inspection shall have a bend test. The bend test shall be made by striking the head of the stud 
with a 6kg hammer until it is displaced laterally a distance of about one quarter of the height 
of the stud. The stud weld shall not show any signs of cracking or lack of fusion 
3. Studs subjected to the bend test shall not be straightened 

3.9.4 Defective Studs 
 Studs with defective welding shall be removed in the manner described in Clause 5.4.5 of QCS Part 
16 Section 5, and replaced and re‐tested as in Clause 5.6.3 of QCS Part 16 Section 5. 

3.10. ERECTION 
A. Erection of structural steel shall be carried out by the personnel under the employment of the 
steel Contractor 
B. Surveys: Employ an experienced Land Surveyor, 10 years minimum experience, to carry out an 
accurate  survey,  prior  to  the  erection  of  structural  steel  work.  Check  elevations  of  concrete 
and  masonry  bearing  surfaces,  and  locations  of  anchor  bolts  and  similar  devices,  before 
erection work proceeds, and report discrepancies to Engineer. Do not proceed with erection 
until corrections have been made or until compensating adjustments to structural steel work 
have been agreed upon with Engineer 
C. Contractor  shall  submit  method  statement  for  erection  sequence  and  erection  design 
calculation and splicing for reviews 
D. Temporary  Planking:  Provide  temporary  planking  and  working  platforms  as  necessary  to 
effectively complete work 
E. Set  structural  steel  accurately  in  locations  and  to  elevations  indicated  and  according  to  AISC 
"Code  of  Standard  Practice  for  Steel  Buildings  and  Bridges"  and  "Specification  for  Structural 
Steel  Buildings‐‐Allowable  Stress  Design  and  Plastic  Design  or  Load  and  Resistance  Factor 
Design Specification for Structural Steel Buildings." whichever is project applicable 
F. Setting Bases and Bearing Plates: Clean concrete bearing surfaces of bond‐reducing materials 
and roughen to improve bond to surfaces. Clean bottom surface of base and bearing plates 
1. Set loose and attached base plates and bearing plates for structural members on wedges 
or other adjusting devices 

    Structural Metal Framing
    05 10 00 / 24        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
2. Tighten  anchor  bolts  after  supported  members  have  been  positioned  and  plumbed.  Do 
not remove wedges or shims, but if protruding, cut off flush with edge of base or bearing 
plate prior to packing with grout 
3. Pack grout solidly between bearing surfaces and bases or plates to ensure that no voids 
remain. Finish exposed surfaces, protect installed materials, and allow to cure 
4. For proprietary grout materials, comply with manufacturer's instructions 
G. Field  Assembly:  Set  structural  frames  accurately  to  lines  and  elevations  indicated.  Align  and 
adjust  various  members  forming  part  of  complete  frame  or  structure  before  permanently 
fastening. Clean bearing surfaces and other surfaces that will be in permanent contact before 
assembly.  Perform  necessary  adjustments  to  compensate  for  discrepancies  in  elevations  and 
alignment 
H. Level and plumb individual members of structure within specified QCS tolerances 
I. Establish  required  leveling  and  plumbing  measurements  on  mean  operating  temperature  of 
structure. Make allowances for difference between temperature at time of erection and mean 
temperature at which structure will be when completed and in service 
J. Splice members only where indicated and accepted on shop drawings 
K. Erection  Bolts:  On  exposed  welded  construction,  remove  erection  bolts,  fill  holes  with  plug 
welds, and grind smooth at exposed surfaces 
1. Comply  with  AISC  Specifications  for  bearing,  adequacy  of  temporary  connections, 
alignment, and removal of paint on surfaces adjacent to field welds 
2. Do  not  enlarge  unfair  holes  in  members  by  burning  or  by  using  drift  pins,  except  in 
secondary bracing members. Ream holes that must be enlarged to admit bolts 
L. Gas Cutting: Do not use gas‐cutting torches in field for correcting fabrication errors in primary 
structural framing. Cutting will be permitted only on secondary  members that are not under 
stress, as acceptable to Engineer. Finish gas‐cut sections equal to a sheared appearance when 
permitted 
M. Touch‐up  Primer:  Immediately  after  erection,  clean  field  welds,  bolted  connections,  and 
abraded areas of shop primer. Apply primer to exposed areas using same material as used for 
shop primer 

3.11. ERECTION TOLERANCES 
3. Permitted maximum deviations in erected steelwork shall be as specified in this clause taking 
account of the following:  
4. All measurements be taken in calm weather, and due note is to be taken of temperature 
effects on the structure. (See Clause 8.4.2 of QCS Section 19 Part 8) 
5. The deviations shown for I sections apply also to box and tubular sections 
6. Where deviations are shown relative to nominal centrelines of the section, the permitted 
deviation on cross‐section and straightness, given in Part 7 of Section, may be added 

    Structural Metal Framing
    05 10 00 / 25        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

3.7.8 Information for sub contractors. 
The  Contractor  shall  advise  sub  contractors  engaged  in  operations  following  steel  erection  of  the 
deviations  acceptable  in  this  document  in  fabrication  and  erection,  so  that  they  can  provide  the 
necessary clearances and adjustments 

3.7.9 Deviations 
The permitted deviations for foundations, walls and foundation bolts are given in the table below: 

 
The permitted deviations of erected components is given in the table below: 

    Structural Metal Framing
    05 10 00 / 26        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

    Structural Metal Framing
    05 10 00 / 27        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

    Structural Metal Framing
    05 10 00 / 28        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

 
3.12. CONNECTIONS 
A. No welding or bolting shall be done until as much of the structure as will be stiffened by the 
welding or bolting has been properly aligned 
B. Drift  pins  shall  not  be  used  to  enlarge  unfair  holes  in  main  material.  Holes  that  must  be 
enlarged to admit bolts shall be reamed. Burning and drifting may be used to align unfair 
holes in secondary bracing members only, when acceptable to the Engineer 
C. When  high  strength  bolts  or  high  strength  bearing  bolts  are  used,  the  AISC  specifications 
shall  apply  including  values  as  noted  therein,  and  installation  by  either  "turn  of  nut 
tightening"  or  with  torque  wrenches.  In  using  manual  torque  wrenches,  the  required 
torque can be read from the wrench dial. Care should be taken that the wrench is properly 
calibrated. Nuts shall be in motion when torque is measured. In using power wrenches, the 
recommendations  of  the  wrench  manufacturer  shall  be  followed.  Use  hardened  washer 
under  bolt  head  or  nut  whichever  is  turned  in  tightening,  unless  the  specified  standards 
require hardened washer under both head and nut 
D. All  bolts  shall  be  kept  in  dry  storage  until  needed  for  installation.  A325  bolts  28mm  and 
32mm  diameter  and  A490  bolts  25mm  diameter  and  over  shall  first  have  approved  wax 

    Structural Metal Framing
    05 10 00 / 29        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
applied to their threads before being assembled in the work. If bolts have been left out and 
have become rusty before use, they shall be rejected and shall not be used until they have 
been cleaned and waxed with an approved material 
 

3.13.QUALITY CONTROL 
A. The Subcontractor shall engage, at his own expense, an independent certified Testing and 
Inspection Agency to inspect high‐strength bolted connections, welded , and tension tests 
of structural steel members; and prepare test reports 
B. Testing  agency  shall  conduct  and  interpret  tests,  state  in  each  report  whether  test 
specimens comply with requirements, and specifically state any deviations there from 
C. Provide access for testing agency to places where structural steel work is being fabricated 
or produced so that required inspection and testing can be accomplished 
D. The Contractor shall provide the Testing Agency with the following: 
1. A complete set of shop fabrication and erection drawings 
2. Cutting lists, order sheets, material bills, shipping bills and mill test reports 
3. Information as to time and place of rolling and shipment of materials to shops 
4. Representative sample pieces requested for testing 
5. Full and ample means and assistance for testing all material 
6. Proper  facilities,  including  scaffolding,  temporary  work  platforms,  hoisting,  facilities, 
etc. for inspection of the work in the mills, shop and field 
E. Correct  deficiencies  in  structural  steel  work  that  inspections  and  laboratory  test  reports 
have  indicated  to  be  not  in  compliance  with  requirements.  Perform  additional  tests,  at 
Contractor's expense, as necessary to reconfirm any non‐compliance of original work and 
to show compliance of corrected work 
F. Shop‐Bolted Connections: Inspect or test in accordance with QSC specifications 
G. Shop Welding: Inspect and test during fabrication of structural steel assemblies, as follows: 
1. Certify  welders  and  conduct  inspections  and  tests  as  required.  Record  types  and 
locations  of  defects  found  in  work.  Record  work  required  and  performed  to  correct 
deficiencies 
2. Perform visual inspection of all welds 
3. Perform tests of welds as follows: 
a. Liquid Penetrant Inspection 
b. Magnetic Particle Inspection performed on root pass and on finished weld. Cracks 
or zones of incomplete fusion or penetration not acceptable 
c. Radiographic Inspection 
d. Ultrasonic Inspection 

    Structural Metal Framing
    05 10 00 / 30        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
e. Tension Tests 
H. Field‐Bolted Connections: Inspect in accordance with QSC specifications 
I. Field Welding: Inspect and test during erection of structural steel as follows: 
1. Certify  welders  and  conduct  inspections  and  tests  as  required.  Record  types  and 
locations  of  defects  found  in  work.  Record  work  required  and  performed  to  correct 
deficiencies 
2. Perform visual inspection of all welds. 
3. Perform tests of welds as follows as directed by Engineer: 
a. Liquid Penetrant Inspection 
b. Magnetic Particle Inspection performed on root pass and on finished weld. Cracks 
or zones of incomplete fusion or penetration not acceptable 
c. Radiographic Inspection 
d. Ultrasonic Inspection 
e. Tension Tests 
 

3.14.SURVEY UPON COMPLETION OF ERECTION 
A. Make  an  accurate  survey  of  actual  locations  of  steel  members  immediately  upon  the 
completion of erection of steel but before removal of shoring and promptly submit same to 
the  Engineer.  Should  locations  vary  beyond  the  allowable  tolerances,  take  necessary 
corrective measures and modify details and/or procedure as required. 
B. Survey  the  final  erected  structural  steel  after  release  of  shoring  but  prior  to  removal  of 
shoring  elements  and  prior  to  the  application  of  any  other  work,  reporting  any 
discrepancies from Contract requirements to the Engineer 
 
3.15. REPAIRS AND PROTECTION 
A. Touchup  Painting:  Immediately  after  erection,  clean  field  welds,  bolted  connections  and 
abraded areas. Paint uncoated and abraded areas with the same material as used for shop 
primer. 
 

END OF SECTION 

    Structural Metal Framing
    05 10 00 / 31        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

SECTION 05 30 00. METAL DECKING 
 

1. PART 1 ‐ GENERAL 
Drawings and general provisions of the Contract, including General and Supplementary Conditions 
and Division 01 Specification Sections, apply to this Section. 

1.1. SECTION INCLUDES 
These  technical  specifications  cover  the  requirements  for  the  METAL  DECKING  included    in  the 
Salwa Dahab Mountains Waterpark and Adventure Park: 

A. Furnish  all  labor,  materials,  tools  and  equipment  and  perform  all  services  and  operations 
necessary  for  the  complete  supply  and  installation  of  structural  steel  work  shown  in  the 
drawings 
1. Structural steel is that work defined BS Standards and as otherwise shown on drawings 

B. Contractor shall be responsible for all temporary works 
C. Contractor  shall  be  responsible  for  maintaining  stability  of  partially  and  fully  erected 
steelworks at all times including the formwork where required 
D. The drawings indicate the design intent for steel framing connections. The contractor shall 
be responsible for: 
1. Design, detailing and fabrication of all steel framing connections 

2. Connection design shall meet the requirements of BS code and Building code and shall 
be done in accordance with LRFD 

3. Connections shall be capable of resisting loads and forces listed on the Drawings. 

1.2. RELATED SECTION 
 Section 05 10 00 Structural Metal Framing. 

1.3. REFERENCE STANDARDS 
The following standards and codes of practice are referenced within the Specification. All materials, 
workmanship and testing shall conform to the requirements of the latest editions of the following 
Standards and Codes of Practice except as explicitly varied by this specification: 

BRITISH STANDARDS: 

 BS 5950: Structural use of Steelwork in buildings 
 BS 8004: Foundations 
 BS 5950: Structural use of Steelwork in buildings 
 BS 8110: Structural use of concrete:  
 BS 8500‐1:2006, Annex A, Guidance for the specifier 

    Metal Decking
    05 30 00 / 1        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
QATAR NATIONAL CONSTRUCTION STANDARDS 2010: 

 Section 16 Part 1: General 
 Section 16 Part 2: Materials 
 Section 16 Part 3: Drawings 
 Section 16 Part 4: Fabrication 
 Section 16 Part 5: Welding 
 Section 16 Part 6: Bolting 
 Section 16 Part 7: Accuracy of Fabrication 
 Section 16 Part 8: Erection 
 Section 16 Part 9: Accuracy of Erected Steelwork 
 Section 16 Part 10: Protective Treatment 
 

1.4. SUBMITTALS 
A. Country and rolling mill origin and statement indicating that the steel is new billet steel and 
that testing has been performed in accordance with the specified standards 
B. Product  data  or  manufacturer's  specifications  and  installation  instructions  for  following 
products.  Include  laboratory  test  reports  and  other  data  to  show  compliance  with 
specifications (including specified standards) 
1. Structural steel (each type), including certified copies of mill reports covering chemical 
and physical properties 

2. High‐strength bolts (each type), including nuts and washers 

a. Include Direct Tension Indicators if used 

3. Structural steel primer paint 

4. Shrinkage‐resistant grout 

C. Shop drawings prepared under supervision of a Structural Engineer with 10 year experience 
in design, including complete calculations, details and schedules for fabrication, connection 
design  and  assembly  of  structural  steel  members,  procedures,  and  diagrams,  Shop 
Drawings show fabrication of structural‐steel components 
1. Submit  detailed  construction  drawings,  along  with  design  calculations  for  review  and 
approval 

2. Include details of cuts, connections, splices, camber, holes, and other pertinent data 

3. Include embedment drawings 

4. Indicate welds distinguishing between shop and field welds, and show size, length, and 
type of each weld 

5. Indicate  type,  size,  and  length  of  bolts,  distinguishing  between  shop  and  field  bolts. 
Identify pre‐tensioned and slip‐critical high‐strength bolted connections 

    Metal Decking
    05 30 00 / 2        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
6. For  structural‐steel  connections  indicated  to  comply  with  design  loads,  include 
structural  analysis  data  prepared,  signed  and  sealed  by  the  qualified  professional 
engineer with minimum ten year experience responsible for their preparation 

7. Field assembly and erection drawings which show all field assembly prior to erection 
and  after  erection.  The  drawings  shall  indicate  all  details,  schedules,  procedures  and 
diagrams  showing  field  assembly  and  sequence  of  erection.  The  information  shall 
indicate locations of shoring and how shoring is stabilized and controlled. The drawings 
shall  indicate  elevations  of  shored  points  and  splice  locations.  The  procedures  shall 
indicate  step  by  step  erection  sequences  including  intermediate  surveys  and 
allowances  for  temperature.  Diagrams  shall  indicate  erection  equipment  size  and 
weight  and  additional  elements  which  may  be  required  to  support  or  stabilize 
elements during erection 

8. The  Contractor  shall  prepare  and  submit  to  the  Engineer  written  procedures  for 
fabrication  of  the  steel  work.  The  procedure  shall  describe  the  complete  welding 
process  including  machine,  current,  voltage,  preheat,  filler  metal,  welding  system 
(manual,  semi‐automatic  or  automatic),  positions  of  welding,  number  of  passes  for 
each  weld  size,  preparation  of  surfaces  prior  to  welding,  etc.  These  procedures  shall 
indicate the Contractor's quality control measures, monitoring and repair procedures 

D. Erection Drawings 
1. Include, but is not limited to: 

a. Detailed statement of erection procedure 

b. Drawings and calculations for setting out and requirement for trial erection at the 
place of fabrication 

c. Drawings and calculations for all temporary works to be used during erection 

d. Calculations of all erection loads and stresses and deflections 

e. All drawings and calculations shall be in sufficient detail, to ensure the Contractor's 
proposed  erection  procedures  are  clearly  defined  with  details  of  temporary 
attachments for lifting and erection 

E. Welding certificates 
F. Qualification  Data: For Installer Fabricator Professional engineer  and Independent Testing 
Agency 
G. Mill  Test  Reports:  Signed  by  manufacturers  certifying  that  the  following  products  comply 
with requirements: 
2. Structural steel including chemical and physical properties 

3. Bolts, nuts, and washers including mechanical properties and chemical analysis 

4. Direct‐tension indicators 

5. Tension‐control, high‐strength bolt‐nut‐washer assemblies 
    Metal Decking
    05 30 00 / 3        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
6. Shear stud connectors 

7. Shop primers 

8. Nonshrink grout 

H. Source quality‐control test reports 
I. Test reports conducted on shop and field‐bolted and welded connections. Include data on 
type(s) of tests conducted and test results 
J. Certified copies of each survey conducted by a Land Surveyor with 10 years experience in 
similar works, showing elevations and locations of base plates and anchor bolts to receive 
structural  steel  and  final  elevations  and  locations  for  major  members.  Indicate 
discrepancies between actual installation and contract documents 
K. Contractor shall submit Method Statement for fabrication and erection sequences 

1.5. QUALITY ASSURANCE 
A. Structural  steel  work  shall  be  executed  by  an  approved  specialist  contractor  with  proven 
track record in the fabricator and erection of similar steel works to this project 
B. Qualifications  for  Welding  Work:  Qualify  welding  procedures  and  welding  operators  in 
accordance with AWS "Qualification" requirements 
1. Provide  certification  that  welders  to  be  employed  in  work  have  satisfactorily  passed 
qualification tests 
2. If recertification of welds is required, retesting will be Contractor's responsibility 

C. Contractor  shall  engage  a  specialized  testing  laboratory  (Third  Party)  approved  by  the 
Engineer  for  QAQC,  tension  tests  of  structural  steel  members,  inspection  for  connections, 
jointing and welding. Perform tests and prepare test reports as required 
D. Pre‐installation  Conference:  The  Contractor  shall  schedule  and  conduct  conference  at  the 
project site. As a minimum, the meeting shall include the Contractor, Fabricator, Erector, the 
finish  painting  subcontractor,  and  the  Engineer.  Coordinate  requirements  for  shipping, 
special  handling,  attachment  of  safety  cables  and  temporary  erection  bracing,  touch  up 
painting and other requirements for Works 

1.6. DELIVERY, STORAGE, AND HANDLING 
A. Do  not  deliver  material  to  the  project  site  until  the  proposed  method  and  sequence  of 
erection has been reviewed and approved by the Engineer. Method and sequence shall be 
planned so as to avoid delay or damage to the work of other trades 
B. Deliver materials to site at such intervals to ensure uninterrupted progress of work 
C. Deliver  anchor  bolts  and  anchorage  devices,  which  are  to  be  embedded  in  cast‐in‐place 
concrete or masonry, in ample time to not to delay work 
D. Store materials to permit easy access for inspection and identification. Keep steel members 
off  ground  by  using  pallets,  platforms,  or  other  supports.  Protect  steel  members  and 

    Metal Decking
    05 30 00 / 4        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
packaged materials from corrosion and deterioration. If bolts and nuts become dry or rusty, 
clean and relubricate before use 
1. Store fasteners in a protected place. Clean and re‐lubricate bolts and nuts that become 
dry or rusty before use 
2. Do not store materials on structure in a manner that might cause distortion or damage 
to members or supporting structures. Repair or replace damaged materials or structures 
as directed 

   

    Metal Decking
    05 30 00 / 5        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

2. PART 2 – PRODUCTS 
2.01 AVAILABLE MANUFACTURERS 

E. Products  and  manufacturers  specified  hereinafter  are  specified  for  the  purposes  of 
establishing minimum quality standards and performance requirements. Products which are 
equal  to,  or  better  than  those  specified,  and  which  conform  to  the  Engineer’s  design 
requirements and color selections, may be acceptable subject to Engineer’s approval 
F. Butler ATC 
Qatar 
Tel: 974 4435 5994 
Fax: 974 4435 5997 
G. Zamil Steel 
Saudi Arabia 
Tel: 966 3812 1120 
Fax: 966 3812 1281 
H. Emirates Building Systems 
Dubai 
Tel: 971 4 885 1122 
Fax: 971 4 885 1211 
I. Kirby Building Systems 
Kuwait. 
Tel: 965 326 2800 
Fax: 965 326 1798 
J. TATA Steel 
UK 
K. Canam Steel 
Canada 
L. Richard Lees Steel 
UK 
www.richardleessteeldecking.com 
M. Or approved equal 

2.1. 05 31 00‐20: COLABORATING STEEL SHEET SLAB 200 MM  
The slab is composed of a collaborating galzanized steel sheet, minimun height 58 mm and 1 mm 
thick,  and  concrete  cast‐in‐situ.  The  slab  thickness  is  200  millimeters  (see  in  corresponding 
drawings). 

The  collaborating  steel  sheet  slab  should  achieve  2  hours  fire  protection  for  floor  and  1  hour  for 
floors or tower stairs platforms. 

    Metal Decking
    05 30 00 / 6        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

2.2. 05 31 00‐15: COLABORATING STEEL SHEET SLAB 150 MM  
The  slab  is  composed  of  a  collaborating  galzanized  steel  sheet,  minimun  height  58  mm  and  0.88 
mm  thick,  and  concrete  cast‐in‐situ.  The  slab  thickness  is  150  millimeters  (see  in  corresponding 
drawings). 

The  collaborating  steel  sheet  slab  should  achieve  2  hours  fire  protection  for  floor  and  1  hour  for 
floors or tower stairs platforms. 

2.3. 05 31 00‐12: COLABORATING STEEL SHEET SLAB 120 MM  
The  slab  is  composed  of  a  collaborating  galzanized  steel  sheet,  minimun  height  58  mm  and  0.88 
mm  thick,  and  concrete  cast‐in‐situ.  The  slab  thickness  is  120  millimeters  (see  in  corresponding 
drawings). 

The  collaborating  steel  sheet  slab  should  achieve  2  hours  fire  protection  for  floor  and  1  hour  for 
floors or tower stairs platforms. 

2.4. 05 31 00‐10: COLABORATING STEEL SHEET SLAB 1000 MM  
The  slab  is  composed  of  a  collaborating  galzanized  steel  sheet,  minimun  height  58  mm  and  0.88 
mm  thick,  and  concrete  cast‐in‐situ.  The  slab  thickness  is  100  millimeters  (see  in  corresponding 
drawings). 

The  collaborating  steel  sheet  slab  should  achieve  2  hours  fire  protection  for  floor  and  1  hour  for 
floors or tower stairs platforms 

   

    Metal Decking
    05 30 00 / 7        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

3. PART 3 ‐ EXECUTION 
3.1. EXAMINATION
A.  Verify elevations of concrete and masonry‐bearing surfaces and locations of anchor rods, 
bearing  plates,  and  other  embedments,  with  steel  erector  present,  for  compliance  with 
requirements 
B. Proceed with installation only after unsatisfactory conditions have been corrected 

3.2. PREPARATION 
A. Provide  temporary  shores,  guys,  braces,  and  other  supports  during  erection  to  keep
structural steel secure, plumb, and in alignment against temporary construction loads and 
loads  equal  in  intensity  to  design  loads.  Remove  temporary  supports  when permanent 
structural steel, connections, and bracing are in place, unless otherwise indicated 
1. Do  not  remove  temporary  shoring  supporting  composite  deck  construction  until 
cast‐in‐place concrete has attained its design compressive strength 

3.3. EXECUTION, GENERAL 
A. Where inspection reveals defects, the extension of inspection will be increased as much as 
necessary  to  ensure  that  the  full  extent  of  the  defects  in  a  joint  has  been  found  and  to 
ensure  that  the  same  defects  are  not  present  in  welds  made  on  similar  parts  or  under 
similar circumstances. 
B. Work that is not acceptable will be designated by "Repair" or "Reject", as applicable 
C. Shop welds will be inspected in the shop before the work is primed and ready for shipment 
D. Each bolting crew and welder shall be assigned an identifying symbol or mark and all shop 
and field connections shall be identified so that the inspector can refer back to the crew or 
person making the connection 
E. The  Engineer  and  the  Testing  Laboratory  shall  inspect  structural  steel  at  the  plant  before 
shipment;  however,  the  Engineer  reserves  the  right  to  reject  any  material,  at  any  time 
before final acceptance, which does not conform to all of the requirements of the Drawings 
and Specifications 
F. The Contractor shall coordinate and allow for necessary time for the Testing Laboratory to 
complete all testing and inspections prior to shop painting 
G. The Testing Laboratory shall prepare test specimen from steel samples cut from delivered 
material and shall conduct tension tests 
H. The  Contractor  shall  mill  order  1.0  meter  extra  length  for  the  members  noted  on  the 
Drawings. 
I. Install  deck  panels  and  accessories  according  to  manufacturer's  recommendations,  and 
requirements of this Section 
J. Install  temporary  shoring  before  placing  deck  panels  when  required  to  meet  deflection 
limitations 

    Metal Decking
    05 30 00 / 8        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
K. Place deck panels on supporting framing and adjust to final position with ends accurately 
aligned  and  bearing  on  supporting  framing  before  being  permanently  fastened.  Do  not 
stretch or contract side lap interlocks 
L. Place  deck  panels  flat  and  square  and  fasten  to  supporting  framing  without  warp  or 
deflection 
M. Cut and neatly fit deck panels and accessories around openings and other work projecting 
through or adjacent to the decking 
N. Provide additional reinforcement and closure pieces at openings as required for strength, 
continuity of decking, and support of other work 

3.4. ERECTION 
A. Erection of structural steel shall be carried out by the personnel under the employment of 
the steel Contractor 
B. Surveys:  Employ  an  experienced  Land  Surveyor,  10  years  minimum  experience,  to  carry 
out an accurate survey, prior to the erection of structural steel work. Check elevations of 
concrete and masonry bearing surfaces, and locations of anchor bolts and similar devices, 
before  erection  work  proceeds,  and  report  discrepancies  to  Engineer.  Do  not  proceed 
with  erection  until  corrections  have  been  made  or  until  compensating  adjustments  to 
structural steel work have been agreed upon with Engineer 
C. Contractor  shall  submit  method  statement  for  erection  sequence  and  erection  design 
calculation and splicing for reviews 
D. Temporary Planking: Provide temporary planking and working platforms as necessary to 
effectively complete work 
E. Setting  Bases  and  Bearing  Plates:  Clean  concrete  bearing  surfaces  of  bond‐reducing 
materials  and  roughen  to  improve  bond  to  surfaces.  Clean  bottom  surface  of  base  and 
bearing plates 
1. Set  loose  and  attached  base  plates  and  bearing  plates  for  structural  members  on 
wedges or other adjusting devices 
2. Tighten anchor bolts after supported members have been positioned and plumbed. 
Do not remove wedges or shims, but if protruding, cut off flush with edge of base or 
bearing plate prior to packing with grout 
3. Pack  grout  solidly  between  bearing  surfaces  and  bases  or  plates  to  ensure  that  no 
voids remain. Finish exposed surfaces, protect installed materials, and allow to cure 
4. For proprietary grout materials, comply with manufacturer's instructions 

F. Field  Assembly:  Set  structural  frames  accurately  to  lines  and  elevations  indicated.  Align  and 
adjust  various  members  forming  part  of  complete  frame  or  structure  before  permanently 
fastening. Clean bearing surfaces and other surfaces that will be in permanent contact before 
assembly.  Perform  necessary  adjustments  to  compensate  for  discrepancies  in  elevations  and 
alignment 

    Metal Decking
    05 30 00 / 9        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
G. Establish  required  leveling  and  plumbing  measurements  on  mean  operating  temperature  of 
structure. Make allowances for difference between temperature at time of erection and mean 
temperature at which structure will be when completed and in service 
H. Splice members only where indicated and accepted on shop drawings 
I. Erection  Bolts:  On  exposed  welded  construction,  remove  erection  bolts,  fill  holes  with  plug 
welds, and grind smooth at exposed surfaces 
1. Comply  with  BS  Specifications  for  bearing,  adequacy  of  temporary  connections, 
alignment, and removal of paint on surfaces adjacent to field welds 
2. Do  not  enlarge  unfair  holes  in  members  by  burning  or  by  using  drift  pins,  except  in 
secondary bracing members. Ream holes that must be enlarged to admit bolts 

J. Gas Cutting: Do not use gas‐cutting torches in field for correcting fabrication errors in primary 
structural framing. Cutting will be permitted only on secondary  members that are not under 
stress, as acceptable to Engineer. Finish gas‐cut sections equal to a sheared appearance when 
permitted. 
K. Touch‐up  Primer:  Immediately  after  erection,  clean  field  welds,  bolted  connections,  and 
abraded areas of shop primer. Apply primer to exposed areas using same material as used for 
shop primer 

3.5. CONNECTIONS 
A. No welding or bolting shall be done until as much of the structure as will be stiffened by the 
welding or bolting has been properly aligned 

B. Drift  pins  shall  not  be  used  to  enlarge  unfair  holes  in  main  material.  Holes  that  must  be 
enlarged to admit bolts shall be reamed. Burning and drifting may be used to align unfair holes 
in secondary bracing members only, when acceptable to the Engineer 

C. When high strength bolts or high strength bearing bolts are used, the AISC specifications shall 
apply including values as noted therein, and installation by either "turn of nut tightening" or 
with  torque  wrenches.  In  using  manual  torque  wrenches,  the  required  torque  can  be  read 
from the wrench dial. Care should be taken that the wrench is properly calibrated. Nuts shall 
be in motion when torque is measured. In using power wrenches, the recommendations of the 
wrench  manufacturer  shall  be  followed.  Use  hardened  washer  under  bolt  head  or  nut 
whichever  is  turned  in  tightening,  unless  the  specified  standards  require  hardened  washer 
under both head and nut 

3.6. DECK INSTALLATION 
1. The steel sheet should be attached to each internal and end beams, use direct fastening RIB 
S‐HSNZ4 HILTI or similar approved every 300 mm.  
2. The steel sheet  should be continuous at least 2 spans 

3.7. QUALITY CONTROL 
A. The Subcontractor shall engage, at his own expense, an independent certified Testing and 
Inspection Agency to inspect high‐strength bolted connections, welded , and tension tests 
of structural steel members; and prepare test reports 
    Metal Decking
    05 30 00 / 10        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
B. Testing  agency  shall  conduct  and  interpret  tests,  state  in  each  report  whether  test
specimens comply with requirements, and specifically state any deviations there from 
C. Provide access for testing agency to places where structural steel work is being fabricated 
or produced so that required inspection and testing can be accomplished 
D. The Contractor shall provide the Testing Agency with the following: 
1. A complete set of shop fabrication and erection drawings 

2. Cutting lists, order sheets, material bills, shipping bills and mill test reports 

3. Information as to time and place of rolling and shipment of materials to shops 

4. Representative sample pieces requested for testing 

5. Full and ample means and assistance for testing all material 

6. Proper  facilities,  including  scaffolding,  temporary  work  platforms,  hoisting  facilities, 


etc. for inspection of the work in the mills, shop and field 

E. Correct  deficiencies  in  structural  steel  work  that  inspections  and  laboratory  test  reports 
have  indicated  to  be  not  in  compliance  with  requirements.  Perform  additional  tests,  at 
Contractor's expense, as necessary to reconfirm any non‐compliance of original work and 
to show compliance of corrected work 
F. Shop‐Bolted Connections: Inspect or test in accordance with QCS specifications 
G. Shop Welding: Inspect and test during fabrication of structural steel assemblies, as follows: 
1. Certify  welders  and  conduct  inspections  and  tests  as  required.  Record  types  and 
locations of defects found in work. Record work required and performed to correct 
deficiencies. 

2. Perform visual inspection of all welds. 

3. Perform tests of welds as follows: 

a. Liquid Penetrant Inspection 
b. Magnetic Particle Inspection performed on root pass and on finished weld. Cracks 
or zones of incomplete fusion or penetration not acceptable. 
c. Radiographic Inspection 
d. Ultrasonic Inspection 
e. Tension Tests 

H. Field‐Bolted Connections: Inspect in accordance with QCS specifications 
I. Field Welding: Inspect and test during erection of structural steel as follows: 
1. Certify  welders  and  conduct  inspections  and  tests  as  required.  Record  types  and 
locations of defects found in work. Record work required and performed to correct 
deficiencies 

2. Perform visual inspection of all welds. 

    Metal Decking
    05 30 00 / 11        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
3. Perform tests of welds as follows as directed by Engineer: 

a. Liquid Penetrant Inspection 

b. Magnetic Particle Inspection performed on root pass and on finished weld. Cracks 
or zones of incomplete fusion or penetration not acceptable 

c. Radiographic Inspection 

d. Ultrasonic Inspection 

e. Tension Tests 

3.8. REPAIRS AND PROTECTION 
A. Galvanizing Repairs: Prepare and repair damaged galvanized coatings on both surfaces with 
galvanized repair paint according to the manufacturer's instructions 
B. Touchup Painting: Wire brush, clean, and paint scarred areas, welds, and rust spots on both 
surfaces of installed deck panels 
1. Touch up painted surfaces with same type of shop paint used on adjacent surfaces 

2. Where shop‐painted surfaces are exposed in‐service, apply touch up  paint to blend 
into adjacent surfaces 

END OF SECTION

    Metal Decking
    05 30 00 / 12        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

 
SECTION 05 52 00. METAL RAILINGS 
 

1. PART 1 ‐ GENERAL 
Drawings and general provisions of the Contract, including General and Supplementary Conditions 
and Division 01 Specification Sections, apply to this Section.  

1.1. SECTIONS INCLUDES 
These technical specifications have been produced to provide a technical brief for the design and 
installation  of  the  METAL  RAILINGS  included    in  the  Salwa  Dahab  Mountains  Waterpark  and 
Adventure Park. 

Section includes: 

A. Furnish  all  labor,  materials,  plant,  tools  and  equipment,  and  perform  all  operations  and 
services necessary for the supply and installation of the following: 

1. Steel pipe and tube handrails and railings. 

B. This  Section  includes  all  required  hardware,  fixtures,  anchors,  adhesives  and  related 
accessories. Contractor shall provide all miscellaneous metal, which is shown on or implied 
by the drawings and required for the work. 

1.2. RELATED SECTIONS 
Related work to be coordinated and used in conjunction with this specification includes but is not 
restricted to: 

 Section 03 30 00 – Cast‐In‐Place Concrete. 
 Section 05 50 00 ‐ Metal Fabrications. 
 Section 09 70 00 – Wall and Ceilings Finishes. 
 Section 09 90 00 – Painting and Coating. 

1.3. REFERENCE STANDARDS 
The following standards and codes of practice are referenced within the Specification. All materials, 
workmanship and testing shall conform to the requirements of the latest editions of the following 
Standards and Codes of Practice except as explicitly varied by this specification: 

BRITISH STANDARDS: 

‐ BS EN ISO 6946. 

‐ BS 8000: Workmanship on building sites. 

QATAR NATIONAL CONSTRUCTION STANDARDS: 

    Metal Railing
    05 52 00 / 1        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
‐  Section 17: Metalwork. Part 3: Metal Doors and Windows. 

AMERICANS WITH DISABILITIES ACT ACCESSIBILITY GUIDELINES (ADAAG). 

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA): 

‐ 101: Life Safety Code. 

 ASTM INTERNATIONAL: 
‐  ASTM  A  53:  Specification  for  Pipe,  Steel,  Black  and  Hot‐Dipped,  Zinc‐  Coated,  Welded  and 
Seamless 

‐  ASTM  A  743:  Specification  for  Castings,  Iron‐Chromium,  Iron‐Chromium‐  Nickel,  Corrosion‐


Resistant, for General Application 

‐ ASTM C 1107: Specification for Packaged Dry, Hydraulic‐Cement Grout (Nonshrink) 

‐  ASTM  D  1187:  Specification  for  Asphalt‐Base  Emulsions  for  Use  as  Protective  Coatings  for 
Metal 

‐ ASTM E 894: Test Method for Anchorage of Permanent 

‐ ASTM E 894 ‐ Standard Test Method for Anchorage of Permanent Metal Railing Systems and 
Rails for Buildings 

‐ ASTM E 935 ‐ Standard Test Methods for Performance of Permanent Metal Railing Systems and 
Rails for Buildings 

‐  ASTM  E  985  ‐  Standard  Specification  for  Permanent  Metal  Railing  Systems  and  Rails  for 
Buildings. 

1.4. DEFINITIONS 
Railings: Guards, handrails, and similar devices used for protection of occupants at open‐sided floor 
areas, pedestrian guidance and support, visual separation, or wall protection. 

1.5. PERFORMANCE REQUIREMENTS FOR RAILINGS 
a) General:  In  engineering  railings  to  withstand  structural  loads  indicated,  determine  allowable 
design working stresses of railing materials based on the following: 

1. Steel: 72 percent of minimum yield strength. 
b) Structural Performance of Handrails and Railings: Provide handrails and railings complying with 
requirements  of  ASTM  E  985  for  structural  performance,  based  on  testing  performed 
according to ASTM E 894 and ASTM E 935 
c) Provide railings capable of withstanding the effects of gravity loads and the following loads and 
stresses within limits and under conditions indicated: 
1. Handrails & Top Rails and Guards: 
i. Uniform load of 0.75 kN/m applied in any direction 
ii. Concentrated load of 1.00 kN applied in any direction 
iii. Uniform and concentrated loads need not be assumed to act concurrently 
2. Infill of Guards: 
    Metal Railing
    05 52 00 / 2        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
i. Concentrated load of 0.25 kN applied horizontally on an area of 0.10 sq.m. 
ii. Uniform load of 1.2 kN/sq. m applied horizontally 
iii. Infill load and other loads need not be assumed to act concurrently 
d) Thermal  Movements:  Provide  handrails  and  railings  that  allow  for  thermal  movements 
resulting  from  the  maximum  change  (range)  in  ambient  and  surface  temperatures  by 
preventing  buckling,  opening  of  joints,  overstressing  of  components,  failure  of  connections, 
and other detrimental effects. 

1. Temperature Change (Range) 67oCelsius ambient, 100oCelsius material surfaces. 

e) Control of Corrosion: Prevent galvanic action and other forms of corrosion by insulating metals 
and other materials from direct contact with incompatible materials. 

1.6. SUBMITTALS 
Drawings and documents below shall be submitted to the Engineer for approval. 

1.6.1. Programme of Works 
The Contractor shall submit his Programme of works for the Engineer's approval five (5) days of the 
start of the Contract. 

1.6.2. Staff Organization Chart 
The Contractor shall submit a Staff Organization Chart for the Engineer's approval ten (10) days of 
the start of the Contract 

1.6.3. Health and Safety Plan 
The Contractor shall submit his Health and Safety Plan for the Engineer's approval thirty (30) days 
of the start of the Contract 

1.6.4. Quality Assurance Plan 
The Contractor shall submit his Quality Assurance Plan for the Engineer's approval thirty (30) days 
of the start of the Contract 

1.6.5. Product Data  
For the following: 

a) Manufacturer's Literature for handrails and railings. 
b) Grout, anchoring cement and paint products. 
 

    Metal Railing
    05 52 00 / 3        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

1.6.6. Samples 
a) For each type of exposed finish required, prepared on components indicated below and of 
same  thickness  and  metal  indicated  for  the  Work.  If  finishes  involve  normal  color  and 
texture variations, include sample sets showing the full range of variations expected. 
1. 150‐mm‐  long  sections  of  each  distinctly  different  linear  railing  member,  including 
handrails, top rails, posts, and balusters. 
2. Fittings and brackets. 
3. Connections. 
4. Assembled sample of railings, made from full‐size components including top rail, post, 
handrail, and infill. Show method of finishing and connecting members at intersections. 

1.6.7. Test Reports 
Based  on  evaluation  of  comprehensive  tests  performed  by  a  qualified  testing  agency,  according 
ASTM E 894 and ASTM E 935. 

1.6.8. Certificates 
a) Fabrication 

1.7. QUALITY ASSURANCE 
a) Fabricator: A firm with minimum five year experience in successfully producing work similar 
to  that  indicated  for  this  Project,  with  a  record  of  successful  in‐service  performance,  and 
with sufficient production capacity to produce required units without causing delay in the 
Work. 
b) Installer:  An  installer  with  minimum  five  year  experience  in  the  use  of  the  materials  and 
equipment to be employed in the Work. Install by same firm which fabricates the Work. 
c) Welding:  Qualify  welding  processes  and  welding  operators  in  accordance  with  AWS 
requirements. 
  1. AWS D1.1 “Structural Welding Code – Steel”. 
  2. AWS D1.2 “Structural Welding Code – Aluminum. 
d) Source  Limitations:  Obtain  each  type  of  railing  through  one  source  from  a  single 
manufacturer. 
e) Mock‐ups:  Before  installing,  build  mockups  to  verify  selections  made  under  sample 
submittals  and  to  demonstrate  aesthetic  effects  and  qualities  of  materials  and  execution. 
Build  mockups  in  location  as  directed  to  comply  with  the  following  requirements,  using 
materials indicated for the completed work. 
1. Build  mockups  for  each  form  and  finish  of  railing  consisting  of  railing,  infill  area,  and 
anchorage system components that are full height and are not less than 1.5 m in length 
installation to the satisfaction of the Engineer. If the required standard is not achieved, 
the   Contractor  shall  replace  (at  the  contractor’s  cost)  until  the  required  standard  is 
achieved as  judged by the Engineer 
2. Obtain written approval of mock‐up from the Engineer before starting fabrication. 
3. Approved mockups may become part of the completed Work if undisturbed at time of 
Substantial Completion. 
    Metal Railing
    05 52 00 / 4        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

1.8. CORROSION PROTECTION
a) The climate  at the project site is particularly corrosive due to the saline atmosphere, and 
the  high  average  temperatures.  The  intense  solar  radiation  is  also  a  cause  of  accelerated 
aging of materials, as is the significant accumulation of fine sand and dust due to the nature 
of  local  soils.  The  Contractor  will  make  all  provisions  necessary  to  propose,  for  the  prior 
approval of the Engineer, and then to install, non‐corroding products and materials where 
appropriate  including  aluminum,  stainless  steel,  other  non‐corroding  metals,  and  plastics. 
In the case where no alternative to steel or other oxidizing metal is possible (or where the 
specifications  specifically  indicate  the  use  of  steel),  the  steel  or  other  material  must  be 
effectively  protected  against  corrosion  (by  galvanization  and/or  protective  paint  coatings, 
for example) with an anti‐corrosion guarantee of 10 years. In all other cases, the Contractor 
will  be  asked  to  modify  if  necessary  the  proposed  product  (even  if  a  catalogue  or 
manufactured  item)  and  to  replace  the  corroding‐type  materials  by  non‐corroding 
materials. 

1.9. WORK REASONABLE INFERRED 
a) Contractor  shall  execute  the  Work  in  accordance  with  the  intent  and  meaning  of  the 
Drawings and Specification and shall supply all accessories and other items essential for the 
proper Performance and Completion of the Work and shall execute all Work, including the 
supply of necessary materials, which can be reasonably inferred, whether or not specifically 
shown or described in the Drawings and Specification. 

1.10. DELIVERY, STORAGE, AND HANDLING 
a) Store handrails and railings in a dry, well‐ventilated, weathertight place. 

1.11. PROJECT CONDITIONS 
a) Field Measurements: Verify handrail and railing dimensions by field measurements before 
fabrication and indicate measurements on Shop Drawings. Coordinate fabrication schedule 
with construction progress to avoid delaying the Work. 

1.12. COORDINATION AND SCHEDULING 
a) Coordinate  installation  of  anchorages  for  handrails  and  railings.  Furnish  setting  drawings, 
templates,  and  directions  for  installing  anchorages,  including  sleeves,  concrete  inserts, 
anchor  bolts,  and  items  with  integral  anchors,  that  are  to  be  embedded  in  concrete  or 
masonry. Deliver such items to Project site in time for installation. 
b) Schedule installation so handrails and railings are mounted only on completed walls. Do not 
support  temporarily  by  any  means  that  does  not  satisfy  structural  performance 
requirements. 
   

    Metal Railing
    05 52 00 / 5        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

2. PART 2 – PRODUCTS 

2.1. AVAILABLE FABRICATORS
A. Products and fabricators specified hereinafter are specified for the purposes ofestablishing 
minimum quality standards and performance requirements. Products which are equal to, or 
better than those specified, and which conform to the Engineer’s design requirements and 
color selections, may be acceptable subject to Engineer’s approval. 

B. Metallica Metal Workshop 
  Qatar 
  Tel: 974 4458 0668 
  Fax: 974 4458 0662 
C. Premier Engineering & Trading 
  Qatar 
  Tel: 974 4437 4329 
  Fax: 974 4437 4303 
D. Emirates Building Systems 
  Dubai 
  Tel: 971 4 885 1122 
  Fax: 971 4 885 1211 
E. Leader Metal LLC ‐ Dubai ‐ UAE 
F. Alico Industries Co. Ltd. 
  Sharjah UAE 
  Tel: +971 6 538 8810 
  Fax: +971 6 538 8042 
G. Al Hamy for Technical Works 
  P. O. Box 11297 Dubai, UAE. 
  Tel: 971 271 1888 
H. Or Approved Equal 

2.2. METALS, GENERAL 
a) Metal  Surfaces  General:  Provide  materials  with  smooth  surfaces,  free  from  pitting,  seam 
marks, roller marks, stains, discolorations, and other imperfections where exposed to view 
on finished units. 
b) Brackets, Flanges and Anchors: Cast or formed metal of same type of material and finish as 
supported rails unless otherwise indicated. 

2.3. STEEL HANDRAILS 
The project includes four different types of steel  handrails: 

  RL‐06. Double handrail anchored to the wall. 

  RL‐07. Double handrail with  vertical bars and posts. 

  RL‐10. Maintenance stair railing. 
    Metal Railing
    05 52 00 / 6        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
  RL‐12. Handrail for pools. 

They are detailed in the drawings SDM‐1195 and SDM‐1196.   

2.3.1. 05 52 RL06. Double Handrail Anchored To The Wall. 
This handrail includes the following components: 

‐ Galvanized steel 40 mm handrail. 1100 mm high from its top surface 
‐ Galvanized steel 40 mm handrail. 865 mm high from its top surface.  
‐ Galvanized steel brackets (anchored to the wall or parapet). 

2.3.2. 05 52 RL07. Double Handrail With Vertical Bars And Posts. 
This handrail includes the following components: 

‐ Galvanized steel 40 mm handrail. 1100 mm high from its top surface 
‐ Galvanized steel 40 mm handrail. 865 mm high from its top surface.  
‐ Galvanized steel 10 mm bars (vertical, spaced 74 mm.) 
‐ Galvanized steel 50 mm posts (anchored to the floor). 
 

2.3.3. 05 52 RL10. Maintenance Stair Railing. 
This handrail includes the following components: 

‐ Galvanized steel railing 40x 40 mm. 1100 mm high from its top surface. 
‐ Galvanized steel stands 40x 40 mm (anchored to the stair stringpiece). 
‐ Galvanized steel bars 40x 40 mm. 
 

2.3.4. 05 52 RL12. Stainless steel handrail for pools. 
This handrail includes the following components: 

‐ Stainless steel 43 mm handrail. 890 mm high from its top surface. 
‐ Stainless steel 43 mm handrail. 600 mm high from its top surface. 
‐ Stainless steel 43 mm stands. (anchored to the stair's treads). 
 

2.3.5. Materials 
‐ Handrails, Railings, And Balusters:  Galvanized steel pipe meeting requirements of ASTM A 53 or 
galvanized steel tubing meeting requirements of ASTM A 501.  

‐ Sleeves:  

a) 150 to 225 mm long with cross‐section shape and dimension to allow  13 mm minimum of 
grout around perimeter of pipe or tube.  
b) Provide with fully welded steel plate forming bottom closure.  
    Metal Railing
    05 52 00 / 7        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
‐ Brackets, Flanges, Fittings, And Anchors:  

a) Provide standard wall brackets, flanges, miscellaneous fittings, and anchors for 
connection of handrails and railings to other construction.  
b) Provide inserts and other anchorage devices for connecting handrails and railing systems 
to concrete or masonry work.  

2.3.6. Fabrication  
‐  Preassemble  railing  systems  in  shop  to  greatest  extent  possible  to  minimize  field  splicing  and 
assembly.  

‐ Disassemble units only as necessary for shipping and handling limitations.  Clearly mark units for 
reassembly and coordinated installation.  Use connections that maintain structural value of joined 
pieces.  

‐ Grind smooth welded joints and buff welds to same appearance as remainder of railing.  Repair 
galvanizing and cut pipe ends as specified in Section 05 0503.  

‐ Form curves by bending pipe in jigs to produce uniform curvature for each configuration required.  
Maintain  cylindrical  cross‐section  of  pipe  throughout  entire  bend  without  buckling,  twisting, 
cracking, or otherwise deforming exposed surfaces of pipe.  

‐ Welded Connections:  

a) Fabricate railing system and handrail connections by welding.  
b)  Weld corners and seams continuously to comply with following:  

‐ Use materials and methods that minimize distortion and develop strength and corrosion 
resistance of base metals.  

‐ At tee and cross intersections, notch ends of intersecting members to fit contour of pipe 
to which end is joined and weld all around.  

‐ At exposed connections, finish exposed welds and surfaces smooth and blended so no 
roughness  shows  after  finishing  and  so  contours  of  welded  surfaces  match  adjacent 
surfaces.  

‐ Return pipe ends of wall mounted handrails into wall.  

‐ Cap pipe ends of floor / ground mounted handrails and exterior handrails.  

‐ After fabrication, shop prime metal to be painted.  

2.3.7. Finishes 
‐  Factory‐applied  powder‐coated  finish.    Color  as  selected  by  Architect  from  Manufacturer's 
standard colors.  

    Metal Railing
    05 52 00 / 8        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

2.4. ROPE RAILING 
The project includes one rope handrail: 

  RL‐05. Rope Handrail 

It is detailed in the drawing SDM‐1195.  

2.4.1. 05 52 RL05. Rope Handrail 
This railing system includes the following components: 

‐ Manila landscaping rope, 43 mm. 965 mm high from the finish floor. 
‐ Wrought iron ring bracket (anchored to rockwork wall or parapet) 
‐  

2.5. STEEL CABLE RAILING 
The project includes four different types of steel  handrails: 

  RL‐13. Cable railing. 

  RL‐14. Cable stair railing. 

They are detailed in the drawing SDM‐1196.   

2.5.1.  05 52 RL13. Cable Railing 
This railing includes the following components: 

‐ Stainless steel handrail  10x 80 mm. 915 mm high from its top surface to the finished floor. 
‐ Stainless steel cable railing (horizontal, spaced 100 mm) 
‐ Stainless steel stand 20x80 mm. (spaced 1296 mm) 
‐ Stainless steel plate and anchor bolts. 

2.5.2. 05 52 RL14. Cable Stair Railing 
This railing includes the following components: 

‐ Stainless steel handrail  10x 80 mm. 915 mm high from its top surface to the finished floor. 
‐ Stainless steel cable railing (horizontal, spaced 100 mm) 
‐ Stainless steel stand 20x80 mm. (spaced 916,67 mm, anchored to rockwork parapet). 
‐ Stainless steel plate and anchor bolts. (spaced 100 mm) 

2.5.3. Materials and finishes 
‐ Stainless Steel: Type 316 

a) Bar: ASTM A 167 
b) Pipe and Tubing: ASTM A 312 
c) Cable: MIL‐W‐87161, Type II, Composition B 
d) Cable Hardware: ASTM A 276 and A 479, SAE/AMS QQ‐S‐766, Type 316 
    Metal Railing
    05 52 00 / 9        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
‐ Steel: 

a) Pipe: ASTM A 53 
b) [Round]  Tubing: meeting ASTM [A 500] 
c) Bars and Shapes: meeting ASTM A 36. 
d) Castings: Ductile Iron meeting ASTM A 48  
e) Finish  NAAMM Metal Finishes Manual: 
Surface Preparation: Remove loose scale, rust, grease, oil, moisture or other foreign 
materials to properly prepare the surface for subsequent coating application. 

‐ Remove mill scale, rust and dirt following SSPC SP2 for hand cleaning and SSPC SP3 for 
power tool cleaning. 

Galvanizing: 

‐ Products fabricated from shapes, plates, bars and strips shall be galvanized in 
accordance with ASTM A 123. 

‐ Sheet products shall be galvanized in accordance with ASTM A 525 and ASTM A 526. 

‐ Minimum coating weight 3oz/sq. ft. 

Paint: 

‐ Minimum one coat of rust‐inhibitive primer, FS‐TT‐P‐645 Alkyd Type, Zinc Chromate, 
Paint Primer. 

Touch up for Galvanized Surfaces: Use paint primer meeting FS‐TT‐P‐645. 

2.5.4. Railing System 
‐ Material shall conform to 2.02 and be finished in accordance with 2.02. 

‐ Horizontal Stainless Steel Cable Railing System:        
  Specify railing frame components in either carbon steel or stainless steel.  

Framing: 
a. Style: Round pipe. 
b. Material: Stainless steel, ASTM A 312 
b. Wood Railing Frame Components: As specified in Section 06 43 00 
‐ Post Mounting: Floor plate. 6" extension into concrete. 

‐ Intermediate Rail Braces:  

Material: 0.625" diameter x 0.120" thickness Type 4130 chrome/moly tubing.  
Spacing: Maximum 26" on center between end and intermediate posts. 
‐ Intermediate Cable Braces: 

Type: Single piece. Size: 1/4" x 1". Spacing: Maximum 42" on center. 
Material: Stainless steel. 

    Metal Railing
    05 52 00 / 10        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
‐ Cable Grommets: 

Material: Ultraviolet‐resistant Delrin or equivalent. 
Prevent abrasion of intermediate posts, end posts, and cable braces bored for cables. 
Color: Black. 
‐ Cables: 

Material: 1 x 19, Type 316 stainless steel strand, left‐hand lay, per dimensional properties 
contained in MIL‐DTL‐87161. 
 

2.5.5. Fasteners 
‐  Handrail  Anchors:  Select  fasteners  of  type,  grade  and  class  required  to  produce  connections 
suitable for anchoring handrails and railings to other types of construction indicated and capable of 
withstanding design loads. 

‐  All  mechanical  fasteners  used  in  the  assembly  of  stainless  steel  or  aluminium  railings  shall  be 
manufactured from stainless steel. 

‐ Cement: Hydraulic, ASTM C 595, factory prepared with accelerator. 

2.5.6. Handrail brackets 
‐ Stainless steel. 

2.5.7. Fabrication 
‐ Form rail‐to‐end post connections and all changes in rail direction by miter elbows. 

‐ Cut material square and remove burrs from all exposed edges, with no chamfer. 

‐ Make exposed joints butt tight and flush. 

‐ Close exposed ends of pipe by use of appropriate end cap. 

‐ For posts set in concrete, furnish matching sleeves or inserts not less than 5 inches long. 

‐ Verify dimensions on site prior to shop fabrication. 

    Metal Railing
    05 52 00 / 11        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

3. PART 3 ‐ EXECUTION 
3.1.   EXAMINATION 
Examine areas and conditions under which the work is to be installed, and notify the Contractor in 
writing, with  a copy to the Owner and the Architect, of any conditions detrimental  to the proper 
and timely completion of the work. Do not proceed with the work until unsatisfactory conditions 
have been corrected.  

a) Examine  substrates  to  receive  anchors  verifying  that  locations  of  concealed 
reinforcements  have  been  clearly  marked  for  the  Installer.  Locate  reinforcements  and 
mark locations if not already done.  
b) Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory 
by the Installer.  

3.2. PREPARATION 
GALVANIZED STEEL PIPE AND TUBE RAILINGS  

‐  Coordinate  setting  drawings,  diagrams,  templates,  instructions,  and  directions  for  installing 
anchors,  such  as  sleeves,  concrete  inserts,  anchor  bolts,  and  miscellaneous  items  having  integral 
anchors that are to be embedded in concrete or masonry construction. Coordinate delivery of such 
items to the Project site. 

STEEL CABLE RAILING 

‐ Supply items to be cast in concrete. 

‐ Examine areas to receive cable railing system. Notify Architect if areas are not acceptable. Do not 
begin installation until unacceptable conditions have been corrected. 

3.3. INSTALLATION 
‐ Install components in accordance with manufacturer's instructions 

GALVANIZED STEEL PIPE AND TUBE RAILINGS  

‐ Coring of concrete for installation of balusters is acceptable.  

‐ Touch up field welds to match pre‐finished material.  

STEEL CABLE RAILING 

‐  Install  in  accordance  with  project  drawings  [and  manufacturer’s  instructions]  at  locations 
indicated on the drawings. 

‐  Erect  work  square  and  level  and  free  from  distortion  or  defects  detrimental  to  appearance  or 
performance. 

‐ Anchor cable railing system to mounting surface as indicated on the drawings. 

‐ Use manufacturer’s supplied cable hardware. 

    Metal Railing
    05 52 00 / 12        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
‐ Terminate and tension cables in accordance with manufacturer’s instructions. 

‐ Tension cables to a minimum of 400 pounds each in sequence in accordance with manufacturer’s 
instructions. 

‐ Ensure cables are clean, parallel to each other and without kinks or sags.  

 ‐ Adjust cables and cable hardware as required to provide properly installed cable railing system as   
directed by Architect. 

‐ Expansion joints shall be provided as needed to allow for thermal expansion or contraction. 

3.4. MAINTENANCE 
STEEL CABLE RAILING 

‐ Protect cable railing system and finish from damage during construction. 

‐ As installation is completed, wash thoroughly using clean water and soap; rinse with clean water. 

‐ Do not use acid solution, steel wool or other harsh abrasives. 

‐ Remove stained or otherwise defective work and replace with  material that meets specification 
requirements. 

‐ Repair damaged finish as directed by Architect 

‐ Replace defective or damaged components as directed by Architect. 
 
 
 
END OF SECTION

    Metal Railing
    05 52 00 / 13        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

   SECTION 05 59 10. HANDLES AND IRONMONGERY 
 

1. PART 1 ‐ GENERAL 
Drawings and general provisions of the Contract, including General and Supplementary Conditions 
and Division 01 Specification Sections, apply to this Section.  

1.1. SECTIONS INCLUDES 
Section includes: 

A. Furnish  all  labor,  materials,  plants,  tools  and  equipment  and  perform  all  operations  and 
services necessary for the supply and installation of door handles and ironmongery. 

1.2. RELATED SECTIONS 
Related work to be coordinated and used in conjunction with this specification includes but is not 
restricted to: 

 Section 08 11 00 ‐ Metal Doors and Frames 
 Section 08 14 00 ‐ Wood Doors 
 Division 26 ‐ Section for electrical service and connections for doors with card reader units 
and doors connected to fire alarm panel. 

1.3. REFERENCE STANDARDS 
The following standards and codes of practice are referenced within the Specification. All materials, 
workmanship and testing shall conform to the requirements of the latest editions of the following 
Standards and Codes of Practice except as explicitly varied by this specification: 

BRITISH STANDARDS: 

‐ BS EN ISO 6946. 

‐ BS 8000: Workmanship on building sites. 

QATAR NATIONAL CONSTRUCTION STANDARDS: 

‐ Section 15: Thermal Insulation of Buildings 

‐ Section 18: Carpentry, Joinery and Ironmongery. 

‐ Section 25: Glass and Glazing 

QUALITY STANDARDS WINDOW AND DOOR MANUFACTURES ASSOCIATION STILE AND RAIL DOORS 

    Handles and Ironmongery
    05 59 10 / 1        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 
‐ WDMA I.S.6A‐01.  

INTERNATIONAL BUILDING CODE: 

‐ IBC 2003, 714.2.1 

1.4. SUBMITTALS 
Drawings and documents below shall be submitted to the Engineer for approval. 

1.4.1. Programme of Works 
The Contractor shall submit his Programme of works for the Engineer's approval five (5) days of the 
start of the Contract. 

1.4.2. Staff Organization Chart 
The Contractor shall submit a Staff Organization Chart for the Engineer's approval ten (10) days of 
the start of the Contract 

1.4.3. Health and Safety Plan 
The Contractor shall submit his Health and Safety Plan for the Engineer's approval thirty (30) days 
of the start of the Contract 

1.4.4. Quality Assurance Plan 
The Contractor shall submit his Quality Assurance Plan for the Engineer's approval thirty (30) days 
of the start of the Contract 

1.4.5. Product Data  
Manufacturer's product construction data, hardware attachment performance data, specifications 
and installation instructions for each type of handle and oronmongery. 

a) Storage and handling requirements and recommendations. 
b) Cleaning methods. 

1.4.6. Samples  
a) Color Samples: Two samples of each products and finishes specified. 

1.4.7. Test Reports 
The  Contractor  shall  submit  copies  of  test  reports  showing  that  the  products,  materials  and 
installation  have  been  successfully  tested  and  certified,  with  the  properties  specified  and  will  be 
suitable for the job conditions. 

    Handles and Ironmongery
    05 59 10 / 2        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

1.4.8. Certificates 
Certify products meet or exceed specified requirements. 

1.5. QUALITY ASSURANCE 
a) Manufacturer's  Qualifications:  Company  specializing  in  manufacturing  products  specified 
herein with a minimum of five years documented experience. 
 

1.6. DELIVERY, STORAGE, AND HANDLING 
a) Deliver, store and handle materials and products in strict compliance with manufacturer's 
instructions and recommendations and industry standards. 
b) Store  materials  in  manufacturer's  original  sealed,  labeled  packaging  until  ready  for 
installation and in accordance with manufacturer's instructions. Protect from damage. 

 
1.7. PROJECT CONDITIONS 
a) Maintain  environmental  conditions  (temperature,  humidity  and  ventilation)  within  limits 
recommended  by  manufacturer  for  optimum  results.  Do  not  install  products  under 
environmental conditions outside manufacturer's absolute limits. 

1.8. WARRANTY 
a) Manufacturer's  Standard  Warranty:  In  interior  applications,  life  of  original  installation, 
against  defects  in  materials  or  workmanship.  Warranty  shall  provide  for  repair  or 
replacement of defective handles and ironmongery as originally furnished at Manufacturer 
option.  
 
   

    Handles and Ironmongery
    05 59 10 / 3        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

2. PART 2 – PRODUCTS 
a) Stainless steel handles and ironmongery for wooden doors and metal doors. 
b) Forged iron handles and ironmongery for themed wooden doors.  

As it is defined in the drawings SDM‐1145 and SDM‐1146. 

They are supplied with the appropriate fixing bolts.  

    Handles and Ironmongery
    05 59 10 / 4        
 
SALWA DAHAB MOUNTAINS                                            IFC‐ TECHNICAL SPECIFICATIONS II‐REV 04 
              Division 02 to Division 08 

3. PART 3 – EXECUTION 

3.1. EXAMINATION AND PREPARATION 
a) Do  not  proceed  with  installation  until  doors  have  been  prepared  using  the  methods 
recommended  by  manufacturer  and  deviations  from  manufacturer's  recommended 
tolerances  are  corrected.  Commencement  of  installation  constitutes  acceptance  of 
conditions. 
b) If  preparation  is  the  responsibility  of  another  installer,  notify  Architect  in  writing  of 
deviations from manufacturer's recommended installation tolerances and conditions. 
 

3.2.   INSTALLATION 
a) Install  handles  and  ironmongery  in  accordance  with  approved  shop  drawings  and 
manufacturer's recommendations. 

3.3. ADJUSTING AND PROTECTION 
a) Protect installed products until completion of project. 
b) Touch‐up, repair or replace damaged products before Substantial Completion. 
 
 
END OF SECTION 

    Handles and Ironmongery
    05 59 10 / 5        
 

You might also like