Earth work in excavation in all kinds of soils of foundation of structures as per drawing
and technical specification, including setting out, construction of shoring and bracing,
1
removal of stumps and other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
For Piers 1 x 18 10.50 5.40 4.00 4082.4
For Abutments 1 x 2 8.30 9.40 4.00 624.16
For Returns 1 x 4 8.30 6.20 4.00 823.36
TOTAL 5529.92
CUM
Providing and laying VCC M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,
2 graded aggregates for foundation filling including cost of all materials, machinery,
labour, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc.,For bottom plugging
Levelling Course
Providing, fabricating and placing in position reinforcement STEEL bars for RCC works
includingincluding cleaning, straightening, cutting, bending, hooking, soft annealed steel
6
wire, welding wherever required including cost of all materials, machinery,lapping, tying
with 1.25 mm dia.labour etc., complete with initial lead upto 50 and all lifts.
Name of the work: Construction of Single lane Bridge at Km2.300 across Nallamada
Drain Near Kappalavaripalem (V) of Guntur Dist
Sl.No
Quantity Discription Rate Per Amount
.
Earth work in excavation in all kinds of soils of
foundation of structures as per drawing and
technical specification, including setting out,
1 5529.92 construction of shoring and bracing, removal of 85.90 1 CUM 475020
stumps and other deleterious matter, dressing
of sides and bottom and backfilling with
approved material.
Foundation
Top Mat - Distribution
12 15 8.5 0.75 9.25 123.18
Top Mat - Main
12 35 3.5 0.75 4.25 132.06
Bottom Mat - Distribution
12 15 8.5 0.75 9.25 123.18
Bottom Mat - Main 16 51 3.5 0.75 4.25 342.10
For 18 piers 12969.32
Pier
Main Steel 20 57 10.59 1488.61
Distribution Steel 12 38 15.35 517.85
For 18 piers 36116.21
Slab
Bottom-Main 25 35 10.1 0.65 10.75 1449.79
Bottom-Distribution 12 79 4.7 0.65 5.35 375.23
Top - Main 12 52 10.1 0.65 10.75 496.28
Top-Distribution 12 25 4.7 0.65 5.35 118.74
For 19 slabs 46360.69
Kerb
Main 10 7 10.1 0.4 10.5 45.31
Rings 6 35 3.11 24.16
For 19 slabs 2639.99
Abutment
Main - Earth face 12 33 10.14 297.07
Distribution 12 46 6.3 1.2 7.5 306.29
Main - Water face 12 33 12.22 12.22 358.01
Distribution 12 53 6.3 1.2 7.5 352.90
Links-12mm 12 27 116.6 5589.90
For 2 Abutments 13808.34
Approach Slab
Bottom Mat-Main 12 30 3.5 0.3 3.8 101.21
Bottom Mat-Distri 12 25 4.25 0.3 4.55 100.99
TOp Mat-Main 12 30 3.5 0.3 3.8 101.21
TOP Mat-Distri 12 25 4.25 0.3 4.55 100.99
808.78
BedBlocks
Bed Block Over Pier
Main 16 12 6.1 0.3 6.4 121.21
2-Leggeged 12 40 4.6 4.6 163.35
For 18 piers 5122.21
Bed Block Over Abutment
2-Legged Stirrups
10 52 3.05 3.05 97.78
16 3 6.6 6.6 31.25
10 8 6.6 6.6 32.55
10 52 2.6 2.6 83.35
10 8 6.6 6.6 32.55
For 2 Abutments 554.98
Hand Rails as per M.O.S.T
Each Slab 1 219.6
19 4172.4
135880
Add 10% as wastage 149467.58
Providing and Fixing Mastic Pad 2'.0''x4'.0''(0.06m x 1.2 m ) of 1''(25.4mm ) thick including cost of all
materials, labour etc., complete with all leads and lifts.
Building SSR 2017-18 S.No.845 Item Code BMS-W-20 Page No. 99(Combined SSR)
B. MACHINERY
Rate in
Sl.No Description Unit Quantity Amount in Rs.
Rs.
1 Nill 0.00 0.00
0.00 0.00
Total hire chargs of
Machinery Rs. 0.00
C. LABOUR
Rate in
Sl.No Particulars Unit Qty Rs Amount in Rs.
1 Pipe fitter Day 0.25 0.00 0.00
2 Mazdoor Day 0.25 0.00 0.00
Total cost of Labour Rs. 0.00
labour component/unit qty 21.50
Add contractor's profit and overhead charges 13.615% 2.90
labour component/unit qty (including contractor's profit) 24.40
ABSTRACT
A. Cost of Materials Rs. 839.00
B. Hire charges of Machinery Rs. 0.00
C. Cost of Labour Rs. 0.00
Total Rs: 839.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 114.23
Total cost for 1.00 Rs: 953.23
Rate per Sqm (A+B+C+D) Rs. 953.23