Professional Documents
Culture Documents
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General Requirements (Complete SATR-A-2007, listed as Attachment 5 & use SATR-A-2011 & SATR-A-6133)
Inspection strategies & plans shall be prepared and agreed on prior to SAES-L-350,
A2 commencing of fabrication and erection. This is in common with Pipelines.
Pipelines simply follow their reinstatement procedure. Para. 17.2
Page 1 of 5
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff -March 2013) Rev 7 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 30-Apr-13 Piping-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
B SAIC-A-2010 Checklist (Reinstatement Procedure & Checklist item required when bold.)
All joints including welded shall be left exposed for visual leak detection
during the strength test. External coating and priming of such joints are not
SAES-L-150,
B1 allowed unless approved by the Manager of Inspection Department and the
Para. 7.3
proponent Organization representative. The pipe itself can be externally
primed and coated to a final coat.
SAES-L-450,
B2 The assembly of bolted flange joints shall be in accordance with SAEP-351.
Para. 9.4
Drains: Excluding submarine and buried pipelines, drains shall be provided at SAES-L-150,
B3
all low points of the piping system. Para. 6.2
Vents and drain valves, both temporary and permanent, conforms with the SAES-L-105,
B4
piping class or rating. ( Refer SAES-L-108) Para. 5.9
Supports: For above ground installation, the piping system shall be analyzed
to foresee whether temporary supports are required during hydrostatic
testing to limit the sustained longitudinal stresses to acceptable limits by the SAES-L-150,
B5
code. If temporary supports are found to be needed and more economical Para. 6.3
than permanent supports, this should be highlighted in the hydrotesting
procedure.
Arc strikes, gouges, and other indications of careless workmanship (such as SAES-W-011,
B7 surface porosity, uneven weld profiles, and undercut) shall be removed by Para. 11.6 and
grinding and inspected by magnetic particle or liquid penetrant method. 11.9
SAES-W-011,
Temporary welded attachments to the pipe were ground off and inspected
B8 Para. 11.7 and
by magnetic particle or liquid penetrant method
11.9
All threaded joints and faying surfaces shall be seal welded by a continuous SAES-W-011,
B9
fillet weld (required weep holes shall be left unwelded). Para. 11.15.1
If requested by the proponent, all new valves designated for isolation service
SAES-L-108,
B10 (as specified by the Proponent) shall be subjected to a high pressure
Section 4.7.2
hydrostatic seat test prior to installation in the line.
Filling and pressurizing shall be done on the upstream side of check valves in
the system. The test fluid shall be injected at the lowest point in the system
SAES-A-004,
B11 to minimize entrapped air. When filling at the lowest point is not practical, the
Para. 9.1.1
Inspection Department/ Operations Inspection Engineering Unit shall be
consulted. All vents shall be open during filling.
No one shall approach the test area for a minimum of 10 minutes after the
test pressure is reached and before commencement of inspection of the
system, the isolation valve between the temporary test manifold/piping and SAES-A-004,
B12
the piping/equipment under pressure test shall be closed and the test pump Para. 9.1.2
disconnected. The isolation valve downstream of the manifold shall be
opened after the pump is disconnected.
During the application of the test pressure, all in-line valves if not used as test SAES-A-004,
B13
isolation valves shall be in a partially open position. Para. 9.1.3
SAES-A-004,
B14 Vents shall be provided at all high points in the tested system as needed.
Para 8.4.1
Page 2 of 5
Excluding scrapable, submarine and buried pipelines, drains shall be
SAES-A-004,
B15 provided at all low points in the system and immediately above check
Para 8.4.2
valves in vertical lines.
Unless the check valve has a by-pass valve, the disc of the check valve shall
SAES-A-004,
B16 be removed, and securely attached to the outside of the check valve prior to
Para 8.4.3
the pressure test.
Soft seated valves and control valves shall not be installed until after the lines SAES-A-004,
B19
have been thoroughly flushed. Para. 8.1.3
Buried pipeline are adequately bermed or covered to anchor the line during SAES-L-450
B21
pressure test. Appendix C
All gauges and recorders shall be calibrated prior to use. The calibration
interval shall not exceed one (1) month prior to the test date and calibration SAES-A-004,
B22 certificates shall be made available to Inspection personnel prior to Para. 8.1.5.1 and
commencement of the pressure test. Stickers shall be applied indicating the 8.1.5.2
latest calibration date.
All gauges shall have a range such that the test pressure is within 30 to 80% SAES-A-004,
B23
of the full range. Para. 8.1.5.3
A minimum of two pressure gauges are required for the test system. One
SAES-A-004,
B24 pressure gage shall be on the test manifold and the other(s) on the test
Para. 8.1.5.4
system. Their accuracy shall be within 5% of one another.
When large systems are tested, Inspection personnel will determine the need SAES-A-004,
B25
for additional gauges. Para. 8.1.5.5
Pressure and temperature recording gauges shall be used for all buried SAES-A-004,
B26
piping systems on plot and per SAES-L-150 for pipelines. Para. 8.1.5.6
SAES-A-004,
B27 Blind flanges, Paddle or spectacle blinds shall be used to isolate test sections.
Para. 8.3
A bleed valve readily accessible is provided in case immediate SAES-A-004,
B28
depressurization is required. Para. 5.5.2
Draining of Test Fluid- Release of pressure and draining shall be done on the
downstream side of check valves. All vents shall be opened before draining SAES-A-004,
B29
to facilitate drainage and to prevent formation of a vacuum. No test fluid shall Para. 10.1
remain in low spots.
Disposal of Test Fluid-The test fluid shall be disposed in accordance with SAES-A-004,
B30
SAEP-327 or as directed by the Owner. Para. 10.2
Test Vents and Drains-Vents and drains used only for the pressure test shall SAES-A-004,
B31
be plugged, seal welded and penetrant tested. Para. 10.3
Page 3 of 5
Removal and Reconnection of Components- All temporary items installed for
testing purposes (e.g., manifolds, valves, blinds, spacers, supports) shall be
removed. Items that were removed from testing shall be reinstalled. Items,
such as instrument air tubing, check valve discs which were disconnected SAES-A-004,
B32
before testing shall be reconnected. Isolation valves closed for the test Para. 10.4
purposes and that are required to be in the open position for process
reasons shall be opened. If the valve cavity has a drain, the cavity shall be
drained.
REMARKS:
REFERENCE DOCUMENTS:
Page 4 of 5
SAUDI ARAMCO ID/PID - 18-MAY-05- REV 0(Standards Cutoff -March 2013) Rev 7 31-Mar-13
SATR NUMBER DATEAPPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Pre-Pressure Test Checklist (Form) SATR-A-2007 30-Apr-13 MECH-
PROJECT TITLE WBS /BI /JO NUMBER CONTRACTOR /SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION TEST SYSTEMNo./Test Pack No. PLANT NO.
DRAWING NUMBER (P&ID/ISO) /REV. No. PRESSURETEST DIAGRAM NATUREOF TEST WORK PERMIT REQD?
SAUDI ARAMCO TIP (SATIP) NUMBER SATIP Activity No. SUPPORTING SAIC Number SAIC QR No.
3 Check valve upstreamclearance is not five (5) pipe diameters (40" req'd, 20" actual), in violation of
RLC
SAES-L-108. SAES-L-108, Section 5 A ABC/QC 1/1/2007 DEF-1/1/07
1/1/07
4 Check valve is orientedin the wrongdirection (flow arrow). Reverse check valve toassure correct
flow direction. Reposition valve & restore internals immediately after test, COMPANY towitness. RLC
SAES-L-108, Section 6 B ABC/QC 1/4/2007 DEF-1/4/07
1/4/07
7 Completely remove all water anddebris fromlow point/valve cavity for the (3) in-line Valves (8" - 300#)
with SS 400trim, dosoimmediately after test. Clean with dry compressedair andrelubricate sealing
SAES-A-007, RLC
surfaces with approvedlubricant in preparation for "ambient" lay-upspecifiedin test package. B ABC/QC 1/4/2007 DEF-1/4/07
Para 6.2 1/4/07
8
NOTES: a. Above Items are samples for formuse.
b. Indicate " NoPunch items. " as applicable c. QA col is reviewed/
initialed/datedprior topackage certification toverify completeness
I
Reinstatement (Post-Test) Checklist Items & Verified
T Reference & A or Origi- ETC
Concur
Q
complete by
E
Description (Option per Note 5 Above) Applicable SATIP B nator (Note 6) PID Insp A
M QC
1 Flushing& hydrotest complete anddocumentedas accepted. Reinstatement
Procedure
2 All test vents & drains pluggedandseal welded ditto
3 Lines drainedandlay-upper customer approvedspecification ditto
4 Valves (400SS Trim) testedin-line removed, cleaned, & lubricatedfor Amblay-up ditto
5 Jackingscrews, process blinds (spectacles, spades, etc) correctly installed ditto
6 SpringHangers & components (bellows, etc) adjustedper mfginstructions. ditto
7 Weepholes pluggedwith heavy grease (reinforcement padair test complete) ditto
8 Chain wheel operators installed ditto
9 All instruments, control valves & check valves reinstalledin correct flow position ditto
10 Restriction orifice/flow elements installed ditto
11 Relief Valves are Poptested/calibrated, taggedandSAP approved/installed ditto
12 All Temporary Test Components (spools, test blinds, gaskets etc) are removed ditto
13 Correct bolts/gaskets are installedandtorquedper SAEP-351requirements ditto
14 Check Valves andinternals reinstalled(Internal Cleanliness & gasket check) ditto
15 All Start-upitems installed(strainers, filters, other items restrictedfromtest) ditto
16 Chemical Cleaningcompletedanddocumented
17 Final Line Check complete & meets all special process specs. See Spec Check.
Page 5 of 5