You are on page 1of 163

Estimating Concession Period for Public Private

Partnership (PPP)-based Infrastructure


Development: Application of LCCA for Highway
Projects

Thesis of

Master of Science

By

Engr. Fahim Ullah

(NUST201362138MSCEE15413F)

Department of Construction Engineering and Management


National Institute of Transportation (NIT)
School of Civil and Environmental Engineering (SCEE)
National University of Sciences and Technology (NUST),
Islamabad, Pakistan.
August, 2015
This is to certify that the
thesis titled

Estimating Concession Period for Public Private Partnership


(PPP)-based Infrastructure Development: Application of LCCA
for Highway Projects

Submitted by

Engr. Fahim Ullah

(NUST201362138MSCEE15413F)

has been accepted towards the partial fulfillment


of the requirements for the degree of
Masters of Science in Construction Engineering and Management

_____________________________

Dr. M. Jamaluddin Thaheem


Supervisor,
Department of Construction Engineering and Management,
NICE, National University of Sciences and Technology (NUST), Islamabad

ii
This thesis is dedicated to my parents, siblings, grand-parents,

colleagues and my respected teachers!

iii
ACKNOWLEDGEMENTS

First and foremost I would like to thank Allah Almighty Who always

helped me throughout my life and to get through this research degree and thesis.

I would like to pay debt of gratitude to my supervisor Dr. M. Jamaluddin

Thaheem (HoD, CE&M), for his profound guidance and encouragement, to

complete this research work. I sincerely appreciate the valuable time, motivation

and personal support accorded by him. I am also extremely grateful to the

committee members, Dr. M. Bilal Khurshid, Dr. Hamza Farooq Gabriel, Dr.

Arshad Hussain and Engr. Kashif Ahmed Khan for their sincere guidance to

complete this research work. I owe my special thanks to my batch mates of CEM-

05 for their support and motivation throughout the course work and in the initial

research work. I am very grateful to all the respondents for their valuable

contribution to this research. And in the end I would like to pay my earnest and

honest gratitude to my family especially my parents for their unconditional support,

encouragement, prayers and patience.

iv
ABSTRACT

Public-Private-Partnership (PPP) is a widely adopted delivery method for

public infrastructure throughout the world. The factors affecting PPP and its

concession period have always presented complexities to decision makers. The

optimum concession period for any PPP based infrastructure project is very

important and sometimes conflicting; private parties attempt at not only ensuring

payback of capital amount but also getting attractive ROI (profit) thus seeking a

lengthy concession period, but the public entity ensures timely transfer of the

constructed facility/infrastructure all the while assuring customer satisfaction and

high quality of service. To make matters worse, the concession agreements rarely

take into consideration the life cycle cost of constructing, operating and

maintaining the infrastructure. In order to reconcile this critical conflict of interest,

the proposed research aims at improving the concession period estimation by

incorporating the probabilistic LCCA as well as System Dynamics.

This will help parties involved in PPP initiatives better understand the

financial implications of their undertaking: the private parties may ensure

substantial profit on top of capital expenditure along with the confidence of closure

within planned and mutually agreed upon time. The donor agencies, which

otherwise have trepidation regarding the extension of concession, causing either

loss of cash flow or negatively affecting the financial viability of the constructed

facility, may make critical decisions based on better estimates – following their

long-term investment policies and exposing optimum levels of portfolio. The

v
public entity, on the other hand, may figure out the optimum amount of toll/tariff to

be charged from the users, as well as timely transfer of rights from concessionaire.

The decision-making implications of this research deal with donor

confidence at the planning phase as well as monitoring the concession period as the

increased certainty of such period will encourage other funding agencies to invest

in the infrastructure development. This will also impact the economic and social

sector development indices of the country. This study attempts to provide a win-

win-win decision making process for considering the significant factors by

formulating a decision making equation. It further classifies and arranges these

factors on the basis of literature review. As a result the existing research from 2005

to 2015 was classified into 6 groups and 3 areas of influence containing a total of

59 factors with the factor involved risk’s severity [in PPP projects] having

maximum frequency. The practical implications of this matrix facilitate the

decision makers in critical scenarios. The discussion and conclusions are expected

to trigger an interesting debate over the criticality of decision making factors for

estimating the concession period as reported in the literature.

vi
Table of Contents

ACKNOWLEDGEMENTS ......................................................................... iv

ABSTRACT...................................................................................................v

List of Abbreviations .....................................................................................x

List of Figures .............................................................................................. xi

List of tables ............................................................................................... xiii

Chapter 1 .......................................................................................................1

INTRODUCTION .........................................................................................1

1.1 Inputs....................................................................................................1
1.1.1 Introduction ...................................................................................1
1.1.2 Private Finance Initiative ..............................................................3
1.1.3 PPP (Public Private Partnership) ..................................................4
1.1.4 PPP in Pakistan .............................................................................5
1.2 Tools and Techniques ..........................................................................9
1.2.1 Life Cycle Cost Analysis (LCCA) ................................................9
1.2.2 Inputs to LCCA ...........................................................................11
1.2.3 The Need for Concession Period Estimation and Use of LCCA 14
1.2.4 Systems Dynamics ......................................................................20
1.3 Outputs ...............................................................................................23
1.3.1 Objectives of the Research..........................................................23
1.3.2 Relevance to National Needs ......................................................23
1.3.3 Advantages ..................................................................................23
1.3.4 Areas of Application ...................................................................24
Chapter 2 .....................................................................................................25

LITERATURE REVIEW ............................................................................25


vii
2.1 Inputs..................................................................................................25
2.1.1 Introduction to PPP .....................................................................25
2.2 Tools & Techniques ...........................................................................27
2.2.1 Identification of factors affecting concession period ..................27
2.2.2 Grouping of the factors ...............................................................32
2.2.3 Areas affected by the factors.......................................................36
2.2.4 Yearly distribution of the factors ................................................62
2.3 OUTPUTS..........................................................................................70
2.3.1 Frequency analysis ......................................................................70
2.3.2 Decision making matrix ..............................................................73
Chapter 3 .....................................................................................................62

RESEARCH METHODOLOGY.................................................................75

3.1 Inputs..................................................................................................75
3.2 Tools and Techniques ........................................................................75
3.2.1 Pilot Survey.................................................................................75
3.2.2 Initial Questionnaire....................................................................77
3.2.3 MODAL Analysis .......................................................................81
3.3 Outputs ...............................................................................................84
3.3.1 Top 10 factors Identification.......................................................84
3.3.2 Developing an LCCA model for top 10 factors ..........................88
Chapter 4 ...................................................................................................100

RESULTS AND SYNTHESIS ..................................................................100

4.1 Tools and Techniques ......................................................................100


4.1.1 The gap between the academia and Industry ............................100
4.1.2 The gap between Academia and Pakistani Industry .................103
4.2 Outputs .............................................................................................106
4.2.1 The Overall gap between Industry and Academia ...................106
4.2.2 Developing the equation for Concession period Improvement
............................................................................................................106
4.2.3 Synthesis ...................................................................................112
viii
4.2.4 Case Projects .............................................................................115
4.2.5 Discussion .................................................................................123
Chapter 5 ...................................................................................................124

CONCLUSIONS AND RECOMMENDATIONS ....................................124

5.1 Inputs................................................................................................124
5.1.1 Literature review .......................................................................124
5.1.2 Methodology .............................................................................125
5.1.3 Results .......................................................................................125
5.2 Tools & Techniques .........................................................................125
5.2.1 Achieving the objectives ...........................................................125
5.2.2 Concluding the Objectives ........................................................126
5.3 Outputs .............................................................................................128
5.3.1 Summarizing the conclusions ...................................................128
5.3.2 Recommendations .....................................................................128
5.3.3 Recommendations for further research .....................................129
REFERENCES ..........................................................................................131

ix
LIST OF ABBREVIATIONS

PPP = Public Private Partnership

EPA = Environmental Protection Agency

EU = European Union

GOP = Government of Pakistan

NHA = National Highways Authority

GDP = Gross Domestic Product

HSE = Health, Safety and Environment

FWO = Frontier Works Organization

ISO = International Organization for Standardization

HDI = Human Development Index

NPV = Net Present Value

SD = Systems Dynamics

CP = Concession Period

IPO = Input Process Output

PMBOK = Project Management Body of Knowledge

BOT = Build Operate Transfer

VGF = Viability Gap Fund

x
LIST OF FIGURES

Figure 1: Sketch of NPV approach ..............................................................11

Figure 2: System diagram for areas affected ...............................................43

Figure 3: Factors appearance frequency chart .............................................61

Figure 4: Factors identification chart (2005-2012) ......................................69

Figure 5: Factors repetition chart (2012-2015) ............................................70

Figure 6: Factors frequency v/s areas affected ............................................74

Figure 7: Pilot Survey options .....................................................................77

Figure 8: 3D cube showing allocation of factors .........................................88

Figure 9: Systems Diagram for model .........................................................90

Figure 10: SD model for calculating concession period ..............................91

Figure 11: Revenue stream ..........................................................................92

Figure 12: Involved risk severity .................................................................93

Figure 13: NPV ............................................................................................94

Figure 14: Return on investment..................................................................95

Figure 15: Construction cost ........................................................................95

Figure 16: Operational revenue in year .......................................................96

Figure 17: Income in year ............................................................................97

Figure 18: Market situation..........................................................................98

Figure 19: Traffic count ...............................................................................98

Figure 20: Size of investment ......................................................................99

Figure 21: Comparison of Academia and Industry ....................................102

Figure 22: Pakistani industry vs Academia ...............................................105

xi
Figure 23: Normal behavior for Concession period ..................................113

Figure 24: If only risks are increased .........................................................113

Figure 25: Worst ever possibilities for 20 year CP0 ..................................114

Figure 26: Best possible conditions ...........................................................114

Figure 27: Data from responses .................................................................115

xii
LIST OF TABLES

Table 1: Different forms of PFI 17


Table 2: PPP Projects in Pakistan 19
Table 3: Identified Factors with their references 42
Table 4: Functional and characteristic groups 47
Table 5: Groups with their factors 47
Table 6: Areas affected by the factors 50
Table 7: Appearance of factors and their criticality 64
Table 8: Yearly appearance of the factors 76
Table 9: Initially identified factors in year 2005 79
Table 10: Frequency Analysis 85
Table 11: Names and Countries of experts 92
Table 12: Questions from questionnaire and average response score 93
Table 13: Modal analysis of responses 96
Table 14: Top 10 factors from Industry 98
Table 15: Top 10 factors from literature 98
Table 16: Total score of factors 100
Table 17: Deviation table for both scores 114
Table 18: Deviation of Pakistani industry and Academia 117
Table 19: Industrial score and year of identification by Academia 120
Table 20: Table for % effect 124
Table 21: Modified % effect table 124
Table 22: Data from Lahore-Sheikhopora-Faisalabad Dual Carriageway 130
Table 23: Data Obtained from Lahore Islamabad Motorway (M-2)
Overlay and Rehabilitation Project 133
Table 24: Data of Lahore Sialkot Motorway Project 134

xiii
Table 25: Data of M-9 Project 136
Table 26: Achieving the objectives 139

xiv
Chapter 1

INTRODUCTION

The input–process–output (IPO) model, or input-process-output pattern, is a


widely used approach in systems analysis for describing the structure of an information
processing program or other process. Many introductory programming and systems
analysis texts introduce this as the most basic structure for describing a process. (Goel,
2010). A program or process using the input-process-output model receives inputs from
a user or other source, does some computations on the inputs, and returns the results of
the computations.

This method is widely used in construction engineering and management related


documentation and is also adopted by the Project Management Body Of Knowledge
(PMBOK).This thesis follows the same format.

1.1 INPUTS

1.1.1 Introduction

The private sector’s participation in infrastructure funding and management is


growing around the world and this increase is taking especial relevance in the case of
road projects (toll roads) and other PPP projects (Albalate et al., 2013). Recently noted

1
that as the size of the private sector increases in the road projects in Europe, the more
detailed and specific its regulation becomes. Privatization of construction projects is an
emerging market in the US too. Indeed, there have been significant Greenfield projects
in the US since the early 90s, such as the Dulles Greenway (MWAA, 2012) opened in
1995. More recently several Brownfield privatizations have occurred: the Chicago
Skyway in 2005, the Indiana Toll Road in 2006, and the Pennsylvania Turnpike in
2008, within a more general trend that includes prospects for privatization of roads in
New Jersey, as well as build-operate-and-transfer (BOT) concessions in Texas.
Therefore, the described wave of privatization is accompanied by a renewed interest on
the way the public sector regulates, and this interest can be explained by the
redistributive effects that can arise by the fact of giving the right to exploit a network
asset as a motorway (Albalate and Bel, 2009).

In recent years there has been a proliferation of schemes promoting cooperation


between the public and private sectors to provide infrastructure development over a
wide range of economic activities. Governments in many different parts of the world
have embraced these Public-Private Partnership (PPP) arrangements. One stated reason
for these developments is a concern over public expenditure. These arrangements are
often presented as a core part of “modernizing public services, so there is a claim that
such initiatives are part of improving the quality and efficiency of public services”
(Fairbrother, 2003; Albalate and Bel, 2009).

However, while this is a positive view of PPPs, many take a more skeptical view
of their value, pointing to their complexity, the short-term and long-term costs and the
consequences for labor and those reliant on public services (Demirag et al., 2011).
Decision making for concession period of PPP projects has always been tricky for the
parties associated and various factors have been identified over the years that help
propose such duration of concession period which allows for overall advantage. From
year 2005 till 2012 significant work has been performed on finding and identifying the
factors which affect this length. And from 2012 onwards, the research has been applied
in nature and the already identified factors are repeated with no new factors being
recognized. During this time, the severity of risk associated with PPP projects have

2
received significant attention from researchers around the world and due considerations
have been given to these projects.

This thesis attempts to collect and synthesize the performance and decision
factors which may be formulated/formalized as policy guidelines regarding PPP
projects. Further, it attempts to provide a decision making criteria for determining major
components of a concession period by using the analysis of the factors identified from
the literature and their effects on the three parties to the PPP arrangement i.e. the user,
the concessionaire and the public body.

1.1.2 Private Finance Initiative

Private Finance Initiative (PFI) projects are usually long-term contracts for
services that include the provision of associated facilities or properties. Under the
contract, the private sector entity will have responsibility for designing and constructing
the building or facility and maintaining and servicing it throughout the contract term
(Fairbrother, 2003)

In the PFI model, the private sector assumes responsibility for the design,
construction and operation of an infrastructure facility. In this model, the public sector
purchases infrastructure services from the private sector through a long-term agreement.
PFI projects, therefore, bear direct financial obligations to the government in any event
(Zawawi et al., 2014). In addition, explicit and implicit contingent liabilities may also
arise due to loan guarantees provided to the lenders and default of a public or private
entity on non-guaranteed loans. In the PFI model, asset ownership at the end of the
contract period is generally transferred to the public sector. Setting up of a Special
Purpose Vehicle (SPV) may not be always necessary. A PFI contract may be awarded to
an existing company. For the purpose of financing, the lenders may, however, require
the establishment of an SPV (Takim, 2009). The PFI model also has many variants. In a
PFI project, as the same entity builds and operates the services, and is paid for the
successful supply of services at a pre-defined standard, the SPV-private company has no
incentive to reduce the quality or quantity of services. This form of contractual
agreement reduces the risks of cost overruns during the design and construction phases
or of choosing an inefficient technology, since the operator’s future earnings depend on

3
controlling the costs (Ke et al., 2010). The public sector’s main advantages lies in the
relief from bearing the costs of design and construction, the transfer of certain risks to
the private sector, and the promise of better project design, construction and operation
(Rossi and Civitillo, 2014).

As per Davenport (2002), there are a variety of slightly different forms of PFI,
the most important of which are listed as shown in Table 1.

Table 1: Different forms of PFI

BOT build-operate-transfer DBO design-build-operate


BOO build-own-operate DBOM design-build-operate-
maintain
BLT build-lease-transfer DBFOM Design-Build-Finance-
Operate-Maintain
BOOM build-own-operate-maintain DOT design-operate-transfer
BOOT build-own-operate-transfer ROO rehabilitate-own-operate
BOOTT build-own-operate-train- ROT rehabilitate-operate-transfer
transfer
BTO build-transfer-operate DOT develop-operate-transfer
DBFO design-build-finance-operate PPP public private partnership

1.1.3 PPP (Public Private Partnership)

The Public Private Partnership (PPP) form of procurement is recognized as an


effective way of delivering value-for-money public infrastructure or services. It seeks to
combine the advantages of competitive tendering and flexible negotiation, and to
allocate risk on an agreed basis between the public sector and the private sector
(Carbonara et al., 2014). It is important that risk allocation is clearly communicated and
understood between the parties. It is thus essential for public clients and private bidders
to evaluate all of the potential risks throughout the project life. Public and private sector

4
bodies must place particular attention on the procurement process while negotiating
contracts for PPP to ensure a fair risk allocation between them (Carbonara et al., 2014).
In recent years there has been an increasing market of PPP for the development and
operation of infrastructure projects (Demirag et al., 2011). With the fast pace of market-
oriented transformation, a delicate balance has to be sought among private sector
capacity, government regulatory function and public satisfaction.

PPPs are contentious. The European Commission (2013) identifies four


principal roles for the private sector in PPP schemes:

• To provide additional capital;


• To provide alternative management and implementation skills;
• To provide value added to the consumer and the public at large;
• To provide better identification of needs and optimal use of resources.

PPP projects are usually long-term contracts for services that include the
provision of associated facilities or properties. Under the contract, the private sector
entity will have the responsibility for designing and constructing the building or facility,
and maintaining and servicing it throughout the contract term (Fairbrother, 2003;
Albalate and Bel, 2009). In practice, concessions do not always fit neatly into a single
category. However, the technical distinction between concessions and operating
concessions may be of great significance in respect of rules on public finances and
tendering.

1.1.4 PPP in Pakistan

In order to facilitate private investment, the Ministry of Finance, Government of


Pakistan, established the Infrastructure Project Development Facility (IPDF) and
Infrastructure Project Financing Facility (IPFF) in May 2006 to facilitate the preparation
and closure of PPP transactions between public sponsors and private investors and to
determine the funding gap for public funding for making transactions viable while
minimizing the cost for the public through competitive bidding (IPDF 2006).

According to National Highways Authority (NHA) a grand total of PKR


425,678 Million has been utilized so far in PPP projects as shown in the Table 2 (NHA

5
2013).

Table 2: PPP Projects in Pakistan

A) Projects at Implementation Stage

Length Approximate
Sr.
Cost
# Project Status
(Km) (Rs in Mil)

1 10 Service areas at M-2 - 1,125 Operational (13th Year)

N-25 Lakpass Tunnel


2 0.18 679 Operational (5th Year)
M-1 service areas at Indus
3 river - 689 Construction stage
Concession Agreement signed
M-1 Haro service areas in March 2013. Financial
4 - 260 Close stage.
Subtotal : 2,753

B) Procurement Stage

Length Approx.Cost
Sr.
# Project Status
(Km) (Rs in Mil)
1 Karachi-Hyderabad 136 21,000 Prequalification Completed, Bids
Motorway (M-9) to be received on 16-01-2014
Connecting Road Concession Negotiation Stage
Network for New 21 7,149

2 Benazir Bhutto

6
International Airport,
Islamabad
Multan - Muzaffargarh - Evaluaton is pending for want of
3 D.G Khan (N-70) 80 6,979 VGF Rs 1.5 Billion

4 Habibabad Bridge (N-5) - 831 Concession Approval Stage.

Overlay and Financial Evaluation is in hand


Modernization of and Letter of Support to be

5 Lahore-Islamabad 357 46,000 issued


Motorway (M2)
Improvement / widening of
6 N-5 from M-2/N-5 junction 20 6,162 Concession Negotiation Stage
to Wah underpass(Taxila)
Karachi Northern Bypass Financial Evaluation is in hand.
(M- 10) & Karachi - Hub Pending for want of Rs 3.7~6.5

7 Bypass (N-25) 63 12,130 Billion as VGF.

Subtotal : 100,251

C) Development Stage

Length Approx.Cost
Sr.
# Project Status
(Km) (Rs in Mil)

Pindi Bhattian to Faisalabad Shall be available for


1 Motorway (M-3) 53 4,770 investment in June 2014
after completion of
Commercial Feasibility.

2 Khanewal to Lodhran (E-5A) 100 24,000 Shall be available for


investment in June 2014
Shall be available for

7
Lodhran to Sukkur investment in Jun 2014
3 Throughway (E5B) 385 40,000 after completion of
Commercial Feasibility.

Sukkur to Hyderabad Shall be available for


4 Highway (N-5) 350 21,000 investment in June 2014
after completion of
Commercial Feasibility.
Shall be available for
Havelian to Mansehra investment in Jun 2014
5 Expressway (E-35) 72 20,000 after completion of
Commercial Feasibility.
Shall be available for
Khushal Garh Additional investment in Dec. 2013
6 Bridge (N-80) -- 1,500 after completion of
Commercial Feasibility.
Shall be available for
Two Service Areas at River investment in Dec. 2013
7 Kabul on (M-1) -- 800 after completion of
Commercial Feasibility.

234 70,000 Shall be available for


8 Multan – Rajanpur investment in Dec. 2013
Motorway after completion of
(M-5) Commercial Feasibility

Shall be available for


9 Rajanpur – Shikarpur 226 56,000 investment in Dec. 2013
Motorway (M-6) after completion of
Commercial Feasibility
Shall be available for
investment in July 2014
10 Tarnol - Fateh Jang (N-80) 32 3,604 after completion of
Commercial Feasibility

8
Shall be available for
Karachi – Hub – Dureji investment in Dec. 2013
11 – Dadu Motorway (M-7) 350 81,000 after completion of
Commercial Feasibility

Shall be available for


12 Nowshera–Peshawar (N-5) 43 - investment in June 2014
after completion of
Commercial Feasibility.
Shall be available for
investment in June 2014
13 Lahore - Multan (N-5) 335 - after completion of
- Commercial Feasibility.
SUB-TOTAL : 322,674
GRAND TOTAL (A+B+C): 425,678

1.2 TOOLS AND TECHNIQUES

1.2.1 Life Cycle Cost Analysis (LCCA)

LCCA is an engineering economic analysis technique that builds on the well-

founded principles of economic analysis to evaluate the over-all long-term economic

efficiency between competing alternative investment options. It does not address equity

issues. It incorporates initial and discounted future agency, user, and other relevant costs

over the life of alternative investments. It attempts to identify the best value (the lowest

long-term cost that satisfies the performance objective being sought) for investment

expenditures (USDOT, 2002).

LCCA can be used to study new construction projects and to examine

preservation strategies for existing transportation assets. LCCA considers all agency

9
expenditures and user costs throughout the life of an alternative, not only initial

investments. More than a simple cost comparison, LCCA offers sophisticated methods

to determine and demonstrate the economic merits of the selected alternative in an

analytical and fact-based manner. LCCA helps transportation agencies answer questions

like these:

• Which design alternative results in the lowest total cost to the agency over the

life of the project?

• To what level of detail have the alternatives been investigated?

• What are the user-cost impacts of alternative preservation strategies?

LCCA’s structured methodology provides the information and documentation

necessary for successful public dialogue. Because of this, LCCA is a valuable tool to

demonstrate a transportation agency’s commitment to infrastructure preservation.

Many agencies are turning to life cycle cost analysis as a means of evaluating

the long-term economic viability of pavement designs. As such, it is important for each

agency to conduct a realistic assessment of pavement economics in order to provide

objective input in the life cycle cost analysis.

The determination of life cycle costs of alternative pavement types is an

important part of a rational means for decision making. An appropriate and non-biased

method of LCCA is articulated by the Federal Highway Administration (FHWA) in

1998. It uses the net present value (NPV) approach of determining the costs of several

alternatives.(FHWA, 2009)

10
1.2.2 Inputs to LCCA

1.2.2.1 Net Present Value Method

A simplified sketch of how the NPV method of LCCA works is shown in Figure

1. The initial cost, the rehabilitation costs, and the salvage value are all considered

according to what their values would be in terms of the present value of money. Then a

discount rate factor is applied to account for the time value of money, and the future

rehabilitation costs and salvage value are discounted back to the present.

This simply means that dollars in the present are presumed to be worth more

than dollars in the future. The life cycle cost is then the sum of the initial costs and

discounted future costs and salvage value.

In determining the life cycle cost of a pavement, it is important to include only

those costs which pertain to the pavement. In other words, common costs such as

striping, sod, guardrails, etc. should not be included unless the difference in pavement

type causes a cost differential in these items.

Rehabilitation
Initial Cost
Maintenance Maintenance

Year 0
n

Salvage

Figure 1: Sketch of NPV approach

11
1.2.2.2 Initial Cost

The basis for cost of the initial construction should be unit prices from bid

records of projects constructed over the last two or three years, and only representative

prices should be included. For example, very small projects or projects where paving is

only a minor component of the total cost may cause unit prices to be skewed. It is

realistic to consider the initial cost both by itself and as part of the life-cycle cost

analysis.

This recognizes that the agency is constrained by an annual budget, and needs to

examine the short-term ramifications of expenditures as well as the long-term impact of

pavement type decisions.

1.2.2.3 Predicted Performance Life

It is important that the agency refer to its past experiences with different

pavement types. It is important to document the performance from the time of original

construction or reconstruction until the next reconstruction. In other words, a simple

overlay or mill and fill are rehabilitation activities and do not constitute the end of the

pavement life. The analysis period should be long enough to capture major

rehabilitation or reconstruction activities for all pavement options. The Asphalt

Pavement Alliance recommends that the analysis period be around 40 years and that it

include at least one rehabilitation activity for each pavement option (Alliance 2012).

This complies with the FHWA-recommended minimum of 35 years.

12
1.2.2.4 Maintenance Costs

Maintenance costs are frequently difficult to define because of either a lack of

record keeping or accounting that does not appropriately discriminate between different

types of maintenance activities. Maintenance costs in a life-cycle cost analysis usually

have minimal impact when compared to the initial and first rehabilitation costs. If

maintenance costs are used within an LCCA procedure, then historical documentation

of actual pavement activities and expenditures should be used.

As with rehabilitation, unrealistically frequent or inappropriate maintenance

activities can artificially increase life-cycle cost.

1.2.2.5 Salvage Value

Because some or all of the pavement structure continues to serve its purposes

beyond the analysis period, it is important to account for its condition at the end of the

analysis period.

Salvage value is typically the term used in life-cycle cost analysis, but FHWA

chooses to use the term “remaining service life” (RSL) value to distinguish the idea that

the pavement will continue to serve beyond the end of the analysis period. Another

method used is to consider the salvage value as some percentage of the initial pavement

construction cost.

1.2.2.6 Discount Rate

The selection of a discount rate in life-cycle costing can be contentious because

there is a great deal of uncertainty associated with future interest rates and inflation. An

unreasonably low or negative discount rate essentially means that it would not matter

financially if a project were to be constructed today or 10 years from now. This would

13
overemphasize the influence of uncertain future costs. Too high a discount rate would

overemphasize the importance of the initial cost.

1.2.3 The Need for Concession Period Estimation and Use of LCCA

The massive financial investment in infrastructure and highway projects deters

the public procurement in the face of declining monetary reserves. This offers

investment venture to the private entities which may invest in constructing the facility

and earn from the users by charging nominal amount of toll/tariff. The concession

period for such megaprojects is usually 25-30 years; from an estimation point of view –

keeping into consideration the uncertainty, the length of concession period makes

estimates very difficult. On top of that, the lifecycle cost of operating and maintaining

the facility also needs to be incorporated. In case no such provision is offered, the

concessionaire is not left with more options (The China Post, 2013). The existing

concession models in Pakistan do not necessarily take into account the probabilistic

analysis of project lifecycle cost which either results in an extension of concession

period or an escalation of tool/tariff beyond nominal/economically viable levels.

This research focuses on incorporating the probabilistic LCCA in the planning

phase to facilitate the project financing entities by better estimating the concession

period. It involves estimating various uncertain variables: economic variables

(consumer price index, purchasing power parity, interest rate, inflation rate, exchange

rate, etc.); project variables (material cost, traffic forecast, growth rate, environmental

cost, operations and maintenance cost, debt servicing cost, discount rate, etc.);

alternative variables (projected alternative routes, potential diversion of traffic flow on

alternative routes, investment in other means of transport, etc.). These variables will be

14
modeled to estimate improved concession period which reconciles the heightening

contractual and use-based relationship between public and private entities, and the

service users.

This research attempts to add into the confidence of funding agencies by

working out better concession agreement which ensures timely recovery of capital as

well as interest. The public agencies will also benefit from this research as they can

better estimate the total cost of project during the pre-feasibility phase where the

financial evaluation is performed. With this knowledge, the public agencies may better

perform the concession negotiation and set the toll/tariff rules keeping in view not only

the present economic conditions but also estimate the escalations from a lifecycle point

of view. The user will benefit from this research in the shape of nominal tariff charges

and improved quality of service as the probabilistic analysis, in the light of performance

curves, will dictate the maintenance and rehabilitation decisions which will ascertain

top-quality condition of highways resulting in reduced travel time and comfortable

journey.

Public Private Partnership (PPP) is an emerging procurement pattern which aims

at efficiently as well as affectively achieving the value for money (VFM) in the

infrastructure projects, which otherwise might suffer delayed, or worse declined,

procurement (Nisar, 2007; Andersen, 2000).

Before making a PPP procurement decision – and figuring out if the allocation

of risk between public and private sectors is optimum and acceptable, developed

countries calculate a so-called Public Sector Comparator (PSC). It aims at addressing

the allocation of risk which is a central issue in contracting (Quiggin, 2004). Further, the

15
justifiable and economically viable VFM is assessed prior to committing to the PPP

(Coulson, 2008) as the lack of such critical findings may result in avoiding PPP and

opting for public procurement. Since there is some criticism on the utilization of PPP,

raising concerns that some projects should not have been developed under this model

(Cruz & Marques, 2013), it is only relevant to perform a thorough risk management in

the prefeasibility or conception phases.

Of other risks involved in these partnerships, the estimation risk for the

concession period is of serious concern. The closure risk – the inability of the funding

agency to reach financial closure – poses great concern for the public entity partnering

on behalf of the government (Bracey & Moldovan, 2006). However, at the feasibility

and planning level, a poor estimate of period for which the concessionaire will be

allowed to operate and maintain the facility, and raise revenues poses even greater

challenge to both public and private entities. For the public agency, an administrative

and decision making scenario raises which commands and influences the bid process;

with ample knowledge of total project cost (estimated or calculated), the public agency

may decide for the minimum possible offer to accept. It also has implications in

establishing the toll/tariff rate as the public agency is responsible for not only ensuring

the financial recovery on part of donor agencies but also providing market compatible

toll/tariff rates in the light of economic capacity of the users. For the private sector, this

risk is tantamount to make-or-break situation; the corporate sector needs to guarantee a

profitable ROI within a stipulated time. Any extension in this time may pose serious

financial pressures demoralizing the private investors from further doing business with

those public agencies. In case no extensions are given, the financier has no other option

but to escalate the revenue generation by unjustifiably and excessively raising the usage
16
charges, transferring the financial burden to the common public. Thus, considerable

research has gone into identifying the length of concession period in a transportation

projects under BOT arrangement (Yu & Lam, 2013).

The general trend suggests that risk allocation between the public and private

sectors involved in public-purpose transport investments is an onerous and tricky matter

to resolve owing to opportunistic behavior by the stakeholders committed to the PPP

contract in transport concessions (Medda, 2007). Although the allocation of risk

between public and private stakeholders in the PPP construction projects vary from

country to country, a major consensus is found over the assumption of entire financial

risk by the private sector (Ke et al., 2010; Li et al., 2005), undertaking long-term

maintenance and operation responsibilities. Thus, the common contractual forms are

BOT (Build-Operate-Transfer) and DBFOM (Design-Build-Finance-Operate-Maintain).

An exception to this risk sharing is such projects where promotion and/or development

of some underdeveloped and deprived parts of the country. For this purpose, public

planning authorities make use of Human Development Index 1 (HDI) and offer Viability

Gap Fund 2 (VGF) to initiate such PPP ventures. As a concluding thought, it must be

noted that because of being megaprojects, highway infrastructure projects are threatened

1
HDI is a complex figure used to rank cities/areas in a country by the generic level of "human

development". By the virtue of its function, HDI helps differentiating between developed, developing and

underdeveloped areas. The statistic is calculated on the basis of life expectancy, education and per-capita GNI (Gross

National Income) data collected over a period of time at the national level.
2
VGF is the type of fund offered by the governments to finance such projects where, though the economic

gains are high, enough financial attraction is missing due to contextual limitations, putting off the private investors.

Governments provide VGF for improving the general conditions of the people living in those areas, and uplifting

their economic and living standards.

17
by emerging risks and their cost needs to be worked out in concession awards

(Wirahadikusumah et al., 2014).

The effect of risk is further exasperated due to the time factor; these concessions

are usually very lengthy (25 – 30 years), giving raise to the stochasticity of various

estimates. This warrants for improved estimation of concession period, which is usually

identified by three major elements:

(1) structure,
(2) length and
(3) Incentive scheme (Ye & Tiong, 2003).

The length of concession is a critical issue in the infrastructure development

ventures as it shares and allocates the rights and responsibilities between the public and

privates sectors in the lifecycle of the projects (Zhang & AbouRizk, 2006). The typical

estimation of concession time is as follows;

CT = Tc + To (1.1)

Where CT is Concession Time; Tc is Construction Time and To is Operations

Time. As a general rule;

Tc ≤ Tcmax

To ≤ Toe

NPV1 (1+Rmin) ≤ NPV|T 0 =t≤ NPV1 (1+Rmax) (1.2)

Where Tcmax is latest allowed time for completion, Toe is designed economic

operation life of the infrastructure before justifying for the salvage-type valuation,

NPV1 is the net present value of total cost of the project, Rmin is the minimum rate of

18
return private sector can acquire by investing in the project, Rmax is the maximum rate of

return public sector may allow during project development, NPV|T0 = t is the net present

value of revenues generated from an operation period t. Working out Tcmax can be fairly

easy however the estimation of Toe is the real challenge as it is not only derived from

the inflationary and speculative future value but also involves stochastic behavior and

usage pattern by the commuters. This also has implications on the estimation and fixing

of toll rates which also need to remain in check as an excessive raise will render the

highway cost-unfriendly and thus avoidable (Thomas et al., 2007).

It is evident that in the simplified version, concession period estimation is

terribly easy but in actual projects, the uncertainty amplified by the inherent

stochasticity makes such estimates very erroneous and unreliable. The research impetus

offered here is of prime interest and the same should be banked upon in order to offer

better models and tools for the public and private agencies alike aspiring to venture into

the PPPs for procurement of highways and public-purpose infrastructure projects. In

this regard, the usage of Lifecycle Cost Analysis (LCCA) is proposed in order to

improve the existing concession models.

In this regard, possibly the only work is done by the Minnesota Department of

Transportation in the USA very recently (2013) where the research is gearing up

towards better understanding and planning for forecasting the operations and

maintenance (O&M) costs over the long term (TRS, 2013). Owing to this major

literature and research gap, as well as significant financial implications, this research

aims at not only bridging the said gulf but also helping the public agencies in Pakistan

by offering practical model which can be used to better estimate the concession time.

19
This will involve performing fuzzy-based as well as system dynamics modeling in order

to model the uncertain variables for estimating the lifecycle cost of the construction,

financing, operation and maintenance of the highways for the sake of contractual

decision making.

1.2.4 Systems Dynamics

System Dynamics is a method extending beyond conventional systems approach

to incorporate large-scale complex engineering problems. Dealing with interaction of

various elements of a system in time the Systems Dynamics incorporates the dynamic

concepts such as flows, feedbacks, stock and delays, and hence provide an intuition into

the dynamic behavior of system over time (Tang et al., 2001).

SD can be thought of as an extension of the well-known concepts of systems

engineering (SE) and systems analysis (SA). It gives due consideration to the dynamic

behavior resulting due to delays and feedbacks in systems. Jay W. Forrester,

Management professor at the MIT/Sloan School is considered to be the father of this

new approach to understand and solve the problems in the business and social science

domains. (Anderson et al., 1990)

1.2.4.1 History and Origin

Jay W. Forrester, introduced the concept of Systems Dynamics in 1956. His key

contributions are the design and development of servomechanisms for control of gun

mounts, radar antennas and other military equipment. He applied the mathematical

theory of controls and concepts of feedback and stability leading to the design and

development of the Whirlwind I, the first digital computer designed at the MIT Digital

Computer Laboratory. He also developed the SAGE (Semi-Automatic Ground


20
Environment) air defense system for North America. Development of SAGE was the

key step towards “systems thinking” (Forrester, 1991). Extending use of system

dynamics in the field of business management, he articulated the SD methodology in his

book Industrial Dynamics, published in 1961.

1.2.4.2 Causal loop diagrams

SD uses the logic of causal loop diagrams by representing a system or problem (e.g.,

ecosystem, political system or mechanical system) in form of causal loop diagram. A

causal loop diagram is a simple map of a system with all its constituent components and

their interactions. It captures the interactions and feedback loops to reveal the structure

of a system. Understanding the structure of a system ascertains a system’s behavior over

a time.

SD contains two feedback loops. The positive reinforcement (represented by an arrow

with “+” sign) and negative (or "balancing") reinforcement (represented by an arrow

with “-” sign). Both feedback loops act simultaneously and may have different strengths

at different times.

1.2.4.3 Stock and flow diagrams

A stock is the used for any entity accumulating or depleting over time. A flow is the rate

of change or accumulation of the stock.

Causal loop diagrams helps in qualitatively analyzing the system by providing a

visualization of system’s structure and behavior, and analyzing the system qualitatively.

For performing an in-depth quantitative analysis, a causal loop diagram is transformed

21
to a stock and flow diagram. This model aids in studying and analyzing the system in a

quantitative way; models are usually built and simulated using computer software.

1.2.4.4 Applications

System dynamics is widely used in different areas

like population, ecological and economic systems, interacting strongly with each other.

System dynamics have various "back of the envelope" management applications. SD is

a good tool for:

• Analyzing and comparing the assumptions and mental models

• Gaining qualitative insight into the workings of a system or the consequences of

a decision

Computer software like Vensim®, AnyLogic®, Dynamo® are used to simulate a

system dynamics model of the situation being studied and validate its results. Running

"what if" simulations to test certain policies on such a model can greatly aid in

understanding how the system changes over time. SD being similar to systems thinking,

constructs the same causal loop diagrams of systems with feedback. However, system

dynamics typically goes a step further and uses simulation to study the behavior of

systems and the impact of varying alternative policies.

System dynamics has been used to investigate resource dependencies, and resulting

problems, in product development.

22
1.3 OUTPUTS

1.3.1 Objectives of the Research

• To figure out the factors affecting the length of concession period of PPP

Projects

• To highlight the key factors affecting the length of concession period and hence

helping in more realistic concession period.

• To synthesize the decision making model for concession period using LCCA

• To Bridge the gap between the literature and industry regarding the concession

period of PPP Projects

1.3.2 Relevance to National Needs

This research will be useful for the PPP units of provincial ministries of finance

(MoF) in Punjab and Sindh. It will also benefit the IPDF and IPFF working under the

federal MoF. Lastly, and possibly the most importantly, this research will help NHA in

better planning the financial closure of highway infrastructure projects, ensuring

affective elimination of potential conflict between the prime stakeholders

The decision-making implications of this research deal with donor confidence at

the planning phase as the increased certainty of concession period will encourage other

funding agencies to invest in the infrastructure development of Pakistan. This will also

impact the economic and social sector development indices of the country.

1.3.3 Advantages

• To add into the confidence of funding agencies by working out better concession

agreement which ensures timely recovery of capital as well as interest.

23
• Better estimation the total cost of project during the pre-feasibility phase where

the financial evaluation is performed.

• With this knowledge, the public agencies may better perform the concession

negotiation and set the toll/tariff rules keeping in view not only the present

economic conditions but also estimate the escalations from a lifecycle point of

view.

• The user will benefit from this research in the shape of nominal tariff charges

and improved quality of service as the probabilistic analysis, in the light of

performance curves, will dictate the maintenance and rehabilitation decisions

which will ascertain top-quality condition of highways resulting in reduced

travel time and comfortable journey.

1.3.4 Areas of Application

This research is aimed at studying and investigating the currently prevailed

concession period estimation methods for the highway projects under the PPP

arrangement in the context of Pakistan. So the government as well as the private

contractual arrangements under the PPP delivery method is the major focus area.

24
Chapter 2

LITERATURE REVIEW

2.1 INPUTS

2.1.1 Introduction to PPP

PPP projects raise a variety of concerns as they move from concept through

project delivery. These concerns range from the initial decision to use a PPP

procurement/delivery mechanism through specifics of who has the control over toll

setting (where there are tolls involved), how risks and revenue are shared, and how the

complexities of agreements can be communicated to the public and decision makers

(NCHRP, 2009).

The general trend suggests that risk allocation between the public and private

sectors involved in public-purpose transport investments is an onerous and tricky matter

to resolve owing to opportunistic behavior by the stakeholders committed to the PPP


25
contract in transport concessions (Medda, 2007). Although the allocation of risk

between public and private stakeholders in the PPP construction projects vary from

country to country, a major consensus is found over the assumption of entire financial

risk by the private sector (Ke et al., 2010; Li et al., 2005) undertaking long-term

maintenance and operation responsibilities. Thus, the common contractual forms are

BOT (Build-Operate-Transfer) and DBFOM (Design-Build-Finance-Operate-Maintain).

An exception to this risk sharing is such projects which aim at promoting and/or

developing some underdeveloped and deprived parts of the country. For this purpose,

public planning authorities make use of Human Development Index 3 (HDI) and offer

Viability Gap Fund 4 (VGF) to initiate such PPP ventures. As a concluding thought, it

must be noted that because of being megaprojects, highway infrastructure projects are

threatened by emerging risks and their cost needs to be worked out in concession

awards (Wirahadikusumah et al., 2014).

The effect of risk is further exasperated due to the time factor; these concessions

are usually very lengthy (25 – 30 years), giving raise to the stochasticity of various

estimates. This warrants for improved estimation of concession period which is usually

identified by three major elements: (1) structure, (2) length and (3) incentive scheme

3
HDI is a complex figure used to rank cities/areas in a country by the generic level of "human

development". By the virtue of its function, HDI helps differentiating between developed, developing and

underdeveloped nation. The statistic is calculated on the basis of life expectancy, education and per-capita GNI

(Gross National Income) data collected over a period of time at the national level.
4
VGF is the type of fund offered by the governments to finance such projects where, though the economic

gains are high, enough financial attraction is missing due to contextual limitations, putting off the private investors.

Governments provide VGF for improving the general conditions of the people living in those areas, and uplifting

their economic and living standards.

26
(Ye and Tiong, 2003). The length of concession is a critical issue in the infrastructure

development ventures as it shares and allocates the rights and responsibilities between

the public and privates sectors in the lifecycle of the projects (Zhang and AbouRizk,

2006).

The optimum concession period for any PPP based infrastructure project is very

important and sometimes conflicting; private parties attempt at not only ensuring

payback of capital amount but also getting attractive ROI (profit) thus seeking a lengthy

concession period. However the public entity ensures timely transfer of the constructed

facility/infrastructure all the while assuring customer satisfaction and high quality of

service. To make matters worse, the concession agreements rarely take into

consideration the lifecycle cost of constructing, operating and maintaining the

infrastructure (Chen and Flintsch, 2007).

2.2 TOOLS & TECHNIQUES

2.2.1 Identification of factors affecting concession period

After extensive literature review a total of 59 factors were identified that affect

the concession period of PPP based projects. For searching the related papers and

literature “Science Direct” database and “ASCE” library were used .The searching

process used consisted of both the keywords based and semantic techniques. As a result,

a total of 121 research publications were studied which were published between the

years 2005 – 2015. The lower limit to the study period was set to deliberate only the

recent trends in this area of research. After careful analysis of the published research

papers, articles and journals, a total of 59 concession period affecting factors were

identified. These are shown in Table 3.


27
Table 3: Identified Factors with their references

S/n Factors S/n Factors S/n Factors


1 Social welfare 21 Organizational 41 Constructability
(Maffii and Parolin structure of project (Ferrari et al.,
,2010; Niu and (De Marco et al., 2013;
Zhang, 2013; Hu and 2012;Taylor, Liu and
Zhu, 2015) 2010;Auriol and Wilkinson, 2014;
Picard, 2013) Zhang and Chen,
2013)

2 Service price 22 Site limitation 42 Right project


(Guasch et al., 2008; (Yang et al., 2010; identification
Fairbrother, 2003; Karim, 2011; (Yu and Lam,
Takim, 2009) Ke et al., 2010) 2013;
Karsenty et al.,
2008;
IPDF, 2006)
3 Toll price 23 Political 43 Strength of the
(Rangel et al., 2013; (Yu and Lam, 2013; consortium
de Brux, 2010; Nombela and de Rus, (Cruz and
Ameyaw and Chan, 2004; Marques, 2013;
2015) Chen and Subprasom, Caicedo and
2007) Diaz, 2013;
Ekambaram
Palaneeswaran,
2001)

4 Travel time 24 Promotion 44 Differentiation


(de Brux, 2010; (Sanz, 2014; in guarantees
Niu and Zhang, 2013; Jain, 2014; (Cantos-Sánchez
Rolim et al., 2014) NHA, 2009) et al., 2011;

28
Buffie, 1995;
Ferreira et al.,
2011)

5 Traffic congestion 25 Government 45 Net Present


(Ubbels and Verhoef, effectiveness value
2008; (Hanaoka and Palapus, (Nieto-Morote
Rodriguez-Oreggia 2012; and Ruz-
and Rodriguez-Pose, Albalate et al., 2013; Vila,2012;
2004; Rangel et al., 2013) Verhoef, 2007;
Daniel Albalate, de Lemos et al.,
2015) 2004)

6 Population in area 26 Adequacy of funding 46 Operation


(Caicedo and Diaz, (Willoughby, 2013; revenue in year
2013; Maltby, 2013; (Liu and
Cruz and Marques, Viegas, 2010) Wilkinson, 2014;
2013; Karsenty et al.,
Bao et al., 2014) 2008;
Zhang and Chen,
2013)
7 Construction period 27 Entrepreneurship 47 Income in year
(Zhang and and leadership (Khanzadi et al.,
AbouRizk, 2006; (McCay et al., 2014; 2012;
Santos et al., 2010; Yu and Lam, 2013; Wang and Palli,
Maffii and Parolin, Jolly and Raven, 2014;
2010) 2015) Ambituuni et al.,
2014)
8 Operation period 28 Poorly defined sector 48 Return on
(Hanaoka and policies investment
Palapus, 2012; (Rocha et al., 2006; (Ubbels and

29
Jain, 2014; Takim, 2009; Rangel Verhoef, 2008;
Geraldi et al., 2011) et al., 2013) Takim, 2009;
IPDF, 2006)
9 Project development 29 Lack of clear 49 Traffic count
cost government (Athias and
(Bao et al., 2014; objectives and Nuñez, 2008;
NHA, 2012; commitment Daniel Albalate,
Ferreira et al., 2011) (Anderson et al., 2015; 2015;
Post, 2013; Rangel et al.,
Synthesis, 2013) 2013)
10 Sale price 30 Poor risk 50 Corruption
(Bourguignon, 2013; management (Santos et al.,
Siguaw et al., 2003; (Bray and Mulley, 2010;
Wang, 2015) 2013; Guasch et al.,
Verhoef, 2007 ;Zhang, 2008;
2011) Zawawi et al.,
2014)
11 Discount rate 31 Credibility of 51 Profitability
(Wang and Pallis, government policies (Xu et al.,
2014; (Taylor, 2010; 2012;Carbonara
Baird, 2013; Boeing Singh and et al., 2014;
de Lemos et al., Kalidindi, 2006; Hwang et al.,
2004) Ng et al., 2007) 2013)
12 Market demand 32 Poor transparency 52 Size of
(Albalate and Bel, (Ezzine de Blas and investment
2009; Ruiz Pérez, 2008; (Niu and Zhang,
Bao et al., 2014; Zhang and Chen, 2013;
Geenen, 2014) 2013; Ezzine de Blas
Santos et al., 2010) and Ruiz Pérez,
2008;
Felton et al.,

30
2010)
13 O & M costs 33 Size of project 53 Procurement
(Monios and (Nombela and de Rus, (Boeing Singh
Bergqvist, 2015; 2004; and Kalidindi,
Farnad Nasirzadeh, Bourguignon, 2013; 2006;
2014; G. Maughaqa T. J. Bray and Mulley,
Ross, 2004) Price, 1997) 2013; Zhang and
Chen, 2013)
14 Lack of competition 34 Complexity 54 Strength of SPV
(Rolim et al., 2014; (Cruz and Marques, (Demirag et al.,
Demirag et al., 2011; 2013; 2011; Burke and
Subramanian and Nieto-Morote and Demirag, 2015;
Ramanathan, 2012) Ruz-Vila, 2012; Rossi and
Ameyaw and Chan, Civitillo, 2014)
2015)
15 Economic viability 35 Operational life 55 Investment
(Hanaoka and (Zhang and AbouRizk, attraction
Palapus, 2012; 2006; (Maffii and
Rolim et al., 2014; Ferrari et al., 2013; Parolin, 2010;
Sanz, 2014) Monios and Bergqvist, Wang et al.,
2015) 2014;
Ambituuni et al.,
2014)
16 Construction cost 36 Capital structure of 56 Innovative
(Zhang, 2011; company design
Jain, 2014; (Willoughby, 2013; (De Marco et al.,
Geraldi et al., 2011) De Marco et al., 2012; 2012;
NHA, 2012) Takim, 2009;
Theodor J
Stewarta, 2013)
17 Operation cost 37 Market situation 57 Construction

31
(Ng et al., 2007; Ke (Wang et al., 2014; logistics
et al., 2010; Karim, McCay et al., 2014; (Patel and
2011) Hu and Zhu, 2015) Bhattacharya,
2010; Junge and
Levinson, 2013;
Lopes and
Teixeira Caetano,
2015)
18 Government’s 38 Severity of risks 58 No of partners
interests involved (Ng et al., 2007;
(Baird, 2013; (Carbonara et al., Yang et al., 2010;
Willoughby, 2013; 2014; Ameyaw and
Yu and Lam, 2013) de Lemos et al., 2004; Chan, 2015)
Boeing Singh and
Kalidindi, 2006)
19 Type of project 39 Inflation rate 59 Equity allocation
(Tang et al., 2010; (G. Maughaqa T. J. (Scandizzo and
Kang et al., 2011; Xu Price, 1997; Nombela Ventura, 2010;
et al., 2012) and de Rus, 2004; Yang et al., 2010;
Hwang et al., 2013) Baird, 2013)
20 Revenue stream 40 Construction period
(Siguaw et al., 2003; (NHA, 2009; Viegas,
Maffii and Parolin, 2010; Iseki and
2010; Zhang and Houtman, 2012)
Chen, 2013)

2.2.2 Grouping of the factors

After careful observations, discussion with experts and using the extracted

knowledge of the related literature, these 59 factors were divided into 6 groups .The

classification was done on the basis of both functional and characteristic based criteria:

32
3 groups formulated on the basis of functional attributes while the remaining three

followed the characteristic based classification principle. These groups are shown in

Table 4.

Table 4: Functional and characteristic groups

S/no Functional Groups S/no Characteristic Groups

1 Financial Indicators 4 National Attributes

2 Project’s Executability 5 Consortium’s Attributes

3 Revenue 6 Purchase Power (User)

After Table 4 was developed, the next step was assigning the factors identified

in Table 3 to the functional and characteristics groups. Table 5 shows this classification.

Table 5: Groups with their factors

S/no Group Factors

Discount rate

O & M costs

Inflation rate

1 Financial Indicators Profitability

Net present value

Income in year

Economic viability

Construction cost

33
Operation cost

Project development cost

Construction period

Operation period

Type of project

Size of project

Complexity

2 Project’s Executability Constructability

Size of investment

Procurement

Innovative design

Construction logistics

Site limitation

Severity of risks involved

Service price

Toll price

Sale price

Market demand

3 Revenue Operational life

Equity allocation

Operation revenue in year

Return on investment

34
Market situation

Revenue stream

Traffic count

Project promotion

Government effectiveness

Investment attraction

Poorly defined sector policies

4 National Attributes Lack of clear government objectives


and commitment

Credibility of government policies

Poor transparency

Government’s interests

Political Stability

Corruption

Organizational structure of project

5 Consortium’s Attributes Adequacy of funding

Entrepreneurship and leadership

No of partners

Strength of SPV

Capital structure of company

Right project identification

Risk management maturity

Differentiation in guarantees

Lack of competition

35
Social welfare
6
Purchase Power Travel time

Traffic congestion

Population in area

2.2.3 Areas affected by the factors

In the next step these factor are analyzed against the three main parties i.e. the
concessionaire, the public body and the user, to a PPP based project in order to work out
a concession period based on win-win-win principle for all the three parties. In
analyzing the factors, their effects were studied and noted accordingly based upon the
principle whether they affect the three parties directly or indirectly. The shaded region
shows that the analyzed variable has no effect on the area against which it is analyzed.
The analysis is shown in Table 6 .

Table 6: Areas affected by the factors

Factors Sub factors Area/Domain Affected

User Consortium Public entity


Directly

Indirectly

Directly

Indirectly

Directly

Indirectly

Discount rate ✓ ✓ ✓

O & M costs ✓ ✓ ✓

Inflation rate ✓ ✓ ✓

36
Financial Profitability ✓ ✓

Indicators
Net present value ✓ ✓

Income in year ✓ ✓

Economic viability ✓ ✓ ✓

Construction cost ✓ ✓ ✓

Operation cost ✓ ✓ ✓

Project ✓ ✓ ✓

development cost

Construction ✓ ✓ ✓

period

Operation period ✓ ✓ ✓

Project’s Type of project ✓ ✓

Executability
Size of project ✓ ✓

Complexity ✓ ✓

Constructability ✓ ✓

Size of investment ✓ ✓

37
Procurement ✓ ✓

Innovative design ✓ ✓

Construction ✓ ✓

logistics

Site limitation ✓ ✓

Severity of risks ✓ ✓ ✓

involved

Service price ✓ ✓ ✓

Toll price ✓ ✓ ✓

Sale price ✓ ✓ ✓

Revenue
Market demand ✓ ✓ ✓

Operational life ✓ ✓ ✓

Equity allocation ✓

Operation revenue ✓ ✓

in year

Return on ✓ ✓

investment

38
Market situation ✓ ✓

Revenue stream ✓ ✓

Traffic count ✓ ✓ ✓

Project promotion ✓ ✓ ✓

Government ✓ ✓ ✓

National effectiveness

Attributes Investment ✓ ✓

attraction

Poorly fined
de ✓ ✓ ✓

sector policies

Lack of clear ✓ ✓ ✓

government

objectives and

commitment

Credibility of ✓ ✓ ✓

government

policies

Poor transparency ✓ ✓

39
Government’s ✓ ✓ ✓

interests

Political Stability ✓ ✓ ✓

Corruption ✓ ✓ ✓

Organizational ✓ ✓

structure of project

Adequacy of ✓ ✓
Consortium’s
funding
Attributes

Entrepreneurship ✓ ✓ ✓

and leadership

No of partners ✓ ✓

Strength of SPV ✓ ✓

Capital structure of ✓ ✓

company

Right project ✓

identification

Risk management ✓ ✓ ✓

maturity

40
Differentiation in ✓ ✓

guarantees

Lack of ✓ ✓ ✓

competition

Social welfare ✓ ✓

Purchase Travel time ✓ ✓ ✓


Power (User)
Traffic congestion ✓ ✓ ✓

Population in area ✓ ✓ ✓

Some factors like service price, sale price, toll price and government’s

effectiveness directly affect all the three parties while some factors affect only two or

one of the concerned parties (Hu and Zhu, 2015) .The system diagram, as shown in

Figure 2, explains this phenomenon.

For developing the system diagram, those factors as mentioned in Table 5 which

directly affect an area or areas among the three mentioned areas were used and an effort

was made to show this effect graphically. A factor affecting a particular area will have

an arrow leading from the factor to that area. A factor affecting more than one area will

have multiple arrows corresponding to number of affected areas leading from it and

ending at the areas being affected.

41
Factors like service price, toll price, sale price and government’s effectiveness directly

affect all the three areas and hence three arrows can be seen leaving these factors

towards the areas being affected. On the other hand, factors like credibility of

government’s policies and social welfare affect 2 areas resulting in 2 arrows leaving

them whereas some factors are exclusive to a specific area i.e. traffic congestion affects

the user only and hence only one arrow leaves it. As an example, it can be understood

that increased toll price affects all the three concerned parties: user will have to pay

more and the usage of the project might not be within his purchase power for persistent

use, concessionaire will have a quick recovery of his investment whereas the public

body can have a shorter concession duration and can acquire the project back swiftly

(Rouhani et al., 2013). However, this is not necessarily a win-win-win situation.

42
Social welfare
Credability of govt`s policies
Sale price
Governments` effectiveness
Service price Poor sector policies
Competetion Risk management maturity
Enterpreneurship
Inflation rate
Type of project
Net present value.
Profitability
No of partners Income per year
Complexity Construction period

Figure 2: Systems diagram for areas affected


SPV strength Transperancy
Corruption
Discount rate
Political stability
O & M costs
Area Population ++ -+- + - ++---- -+ + Project Promotion
+
-- -+ +
Travel time - User Concessionaire + Public Body
+- + - Government`s interest
+-

43
- Market demand
Traffic congestion +-- + + +
Construction cost
Traffic count economic viability
Operation cost
Investment size
Development cost
Revenue stream Operation period
Return on investment Size of project
Operational life
Equity allocation
Operation revenue
Constructability Market situation
Procurement Investment attraction
Innovative design
Capital structure of company
Construction logistics
Site limitation
Organizational structure
Right project identification
Funding adequacy
Difference in guarantees
Toll price
Risk severity
Govt`s commitment & objectives
After a link is established between the factors and the areas affected, the next

step was carrying out a frequency analysis for the identified factors. For the sake of

understanding and simplicity the factors are placed in the same 6 groups as previously

S/No Groups Factors Appea Criticalit

rance y (%)

identified and their total appearances are calculated in the 121 research papers. This not

only helps in having an idea about the research trends and focus for the last 10 years but

also helps in finding the number of appearances and calculating the relative importance

or criticality of the involved factors.

For inclusion in the analysis a minimum of 11 appearances out of 121 papers

(10%) is set as lowest limit. The analysis shows the lowest appearance of 11 papers

(10%) out of 121 papers whereas the maximum appearance recorded is 98 (81%).

Different zones can be formulated on the basis of the frequency analysis: high

appearance zone (fourth quartile) or most critical zone contains the factors having an

appearance count of 76 and above, upper normal range (third quartile) and the factors

placed in this range have an appearance count between 54 and 75, lower normal value

(2nd quartile) and the factors placed in this range have an appearance count between 33

and 53 whereas the lowest appearance zone (first quartile) has the factors having

minimum appearance with the lowest count of 11 while maximum limit set is 32.

Table 7: Appearance of factors and their criticality


44
1 Discount rate 35 28.92

2 O & M costs 62 51.23

3 Inflation rate 21 17.35

4 Profitability 21 17.35

5 Net Present 79 65.28

value
Financial Indicators

6 Income in year 76 62.80

7 Economic 14 11.57

viability

8 Construction 64 52.89

cost

9 Operation cost 48 39.66

10 Project 12 9.91

development cost

11 Construction 45 37.19

period
Executability

12 Operation 42 34.71
Project’s

period

13 Type of 12 9.91

45
project

14 Size of project 16 13.22

15 Complexity 54 44.62

16 Constructabilit 16 13.22

17 Size of 68 56.19

investment

18 Procurement 75 61.98

19 Innovative 11 9.09

design

20 Construction 34 28.09

logistics

21 Site limitation 42 34.71

22 Severity of 98 80.99

risks involved

23 Service price 16 13.22

24 Toll price 28 23.14


Revenue

25 Sale price 11 9.09

46
26 Market 15 12.39

demand

27 Operational 43 35.53

life

28 Equity 71 58.67

allocation

29 Operation 78 64.46

revenue in year

30 Return on 77 63.63

investment

31 Market 66 54.54

situation

32 Revenue 90 74.38

stream

33 Traffic count 74 61.15

34 Project 30 24.79
Promotion

35 Government 26 21.48
Attributes

effectiveness
National

36 Investment 72 59.50
attraction

37 Poorly defined 12 9.91


sector policies

47
38 Lack of clear 18 14.87
government objectives
and commitment

39 Credibility of 15 12.39
government policies

40 Poor 39 32.23
transparency

41 Government’s 28 23.14
interests

42 Political 73 60.33
Stability

43 Corruption 36 29.75

44 Organizational 11 9.09
structure of project

45 Adequacy of 72 59.50
funding

46 Entrepreneurs 13 10.74
hip and leadership

47 No of partners 49 40.49
Consortium’s Attributes

48 SPV strength 38 31.40

49 Strength of the 48 39.66


consortium

50 Capital 68 56.19
structure of company

51 Right project 19 15.70


identification

52 Construction 69 57.02
period

53 Differentiation 62 51.23
in guarantees

48
54 Risk 58 47.93
management maturity

55 Lack of 23 19.00
competition

56 Social welfare 18 14.87

57 Travel time 29 23.96


Purchase Power

58 Traffic 11 9.09
congestion

59 Population in 41 33.88
area

Legends

S/No Criteria Range (Appearance)

1 Least Critical 11 - 32

2 Lower Normal 33 - 53

3 Upper Normal 54 - 75

4 Most Critical 76 and above

shows this frequency analysis.

49
Table 7: Appearance of factors and their criticality

50
S/No Groups Factors Appea Criticalit

rance y (%)

1 Discount rate 35 28.92

2 O & M costs 62 51.23

3 Inflation rate 21 17.35

4 Profitability 21 17.35

5 Net Present 79 65.28

value
Financial Indicators

6 Income in year 76 62.80

7 Economic 14 11.57

viability

8 Construction 64 52.89

cost

9 Operation cost 48 39.66

10 Project 12 9.91

development cost

11 Construction 45 37.19
Executability

51
period
Project’s

12 Operation 42 34.71
period

13 Type of 12 9.91

project

14 Size of project 16 13.22

15 Complexity 54 44.62

16 Constructabilit 16 13.22

17 Size of 68 56.19

investment

18 Procurement 75 61.98

19 Innovative 11 9.09

design

20 Construction 34 28.09

logistics

21 Site limitation 42 34.71

22 Severity of 98 80.99

risks involved

23 Service price 16 13.22


enue

24 Toll price 28 23.14


Rev

52
25 Sale price 11 9.09

26 Market 15 12.39

demand

27 Operational 43 35.53

life

28 Equity 71 58.67

allocation

29 Operation 78 64.46

revenue in year

30 Return on 77 63.63

investment

31 Market 66 54.54

situation

32 Revenue 90 74.38

stream

33 Traffic count 74 61.15

34 Project 30 24.79
Promotion
Attributes

35 Government 26 21.48
National

effectiveness

36 Investment 72 59.50
attraction

53
37 Poorly defined 12 9.91
sector policies

38 Lack of clear 18 14.87


government objectives
and commitment

39 Credibility of 15 12.39
government policies

40 Poor 39 32.23
transparency

41 Government’s 28 23.14
interests

42 Political 73 60.33
Stability

43 Corruption 36 29.75

44 Organizational 11 9.09
structure of project

45 Adequacy of 72 59.50
funding

46 Entrepreneurs 13 10.74
hip and leadership
Consortium’s Attributes

47 No of partners 49 40.49

48 SPV strength 38 31.40

49 Strength of the 48 39.66


consortium

50 Capital 68 56.19
structure of company

51 Right project 19 15.70


identification

52 Construction 69 57.02
period

54
53 Differentiation 62 51.23
in guarantees

54 Risk 58 47.93
management maturity

55 Lack of 23 19.00
competition

56 Social welfare 18 14.87

57 Travel time 29 23.96


Purchase Power

58 Traffic 11 9.09
congestion

59 Population in 41 33.88
area

Legends

S/No Criteria Range (Appearance)

1 Least Critical 11 - 32

2 Lower Normal 33 - 53

3 Upper Normal 54 - 75

4 Most Critical 76 and above

From

55
Table 7: Appearance of factors and their criticality

S/No Groups Factors Appea Criticalit

rance y (%)

1 Discount rate 35 28.92

2 O & M costs 62 51.23

3 Inflation rate 21 17.35

4 Profitability 21 17.35

5 Net Present 79 65.28

value
Financial Indicators

6 Income in year 76 62.80

7 Economic 14 11.57

viability

8 Construction 64 52.89

cost

9 Operation cost 48 39.66

10 Project 12 9.91

development cost

56
11 Construction 45 37.19

period

12 Operation 42 34.71

period

13 Type of 12 9.91

project

14 Size of project 16 13.22

15 Complexity 54 44.62
Project’s Executability

16 Constructabilit 16 13.22

17 Size of 68 56.19

investment

18 Procurement 75 61.98

19 Innovative 11 9.09

design

20 Construction 34 28.09

logistics

21 Site limitation 42 34.71

22 Severity of 98 80.99

57
risks involved

23 Service price 16 13.22

24 Toll price 28 23.14

25 Sale price 11 9.09

26 Market 15 12.39

demand

27 Operational 43 35.53

life

28 Equity 71 58.67

allocation
Revenue

29 Operation 78 64.46

revenue in year

30 Return on 77 63.63

investment

31 Market 66 54.54

situation

32 Revenue 90 74.38

stream

33 Traffic count 74 61.15

58
34 Project 30 24.79
Promotion

35 Government 26 21.48
effectiveness

36 Investment 72 59.50
attraction

37 Poorly defined 12 9.91


sector policies

38 Lack of clear 18 14.87


National Attributes

government objectives
and commitment

39 Credibility of 15 12.39
government policies

40 Poor 39 32.23
transparency

41 Government’s 28 23.14
interests

42 Political 73 60.33
Stability

43 Corruption 36 29.75

44 Organizational 11 9.09
structure of project

45 Adequacy of 72 59.50
funding
Consortium’s Attributes

46 Entrepreneurs 13 10.74
hip and leadership

47 No of partners 49 40.49

48 SPV strength 38 31.40

49 Strength of the 48 39.66


consortium

59
50 Capital 68 56.19
structure of company

51 Right project 19 15.70


identification

52 Construction 69 57.02
period

53 Differentiation 62 51.23
in guarantees

54 Risk 58 47.93
management maturity

55 Lack of 23 19.00
competition

56 Social welfare 18 14.87

57 Travel time 29 23.96


Purchase Power

58 Traffic 11 9.09
congestion

59 Population in 41 33.88
area

Legends

S/No Criteria Range (Appearance)

1 Least Critical 11 - 32

2 Lower Normal 33 - 53

3 Upper Normal 54 - 75

4 Most Critical 76 and above

60
, a bar chart is developed showing the frequency of the factors as shown in

Figure 3.

Figure 3: Factors appearance frequency chart

61
2.2.4 Yearly distribution of the factors

After the total appearance of the factors was known, year wise study was

performed in order to organize the factors and get a yearly distribution table for the

factors during the study life. This helped in developing the yearly distribution and

addition chart in Figure 3 and Figure 4. Table 8 shows the factors and their year of

identification.

Table 8: Yearly appearance of the factors

Year of appearance

S/No Groups Factors


2005
2006

2007
2008

2009

2010

2011
2012
2013
2014
2015
1. Discount rate ✓ ✓ ✓ ✓
Financial Indicators

2. O & M costs ✓ ✓ ✓ ✓ ✓

3. Inflation rate ✓ ✓ ✓ ✓ ✓ ✓

4. Profitability ✓ ✓ ✓ ✓

5. Net present value ✓ ✓ ✓ ✓ ✓

6. Income in year ✓ ✓ ✓ ✓

7. Economic viability ✓ ✓ ✓ ✓ ✓

8. Construction cost ✓ ✓ ✓ ✓

9. Operation cost ✓ ✓ ✓

10. Project development cost ✓ ✓ ✓ ✓ ✓

11. Construction period ✓ ✓ ✓ ✓


ty
Executabili
Project’s

12. Operation period ✓ ✓ ✓ ✓ ✓

13. Type of project ✓ ✓ ✓ ✓ ✓

62
14. Size of project ✓ ✓ ✓ ✓ ✓

15. Complexity ✓ ✓ ✓ ✓ ✓

16. Constructability ✓ ✓ ✓ ✓

17. Size of investment ✓ ✓ ✓ ✓

18. Procurement ✓ ✓ ✓ ✓ ✓

19. Innovative design ✓ ✓ ✓ ✓ ✓

20. Construction logistics ✓ ✓ ✓ ✓ ✓

21. Site limitation ✓ ✓ ✓ ✓ ✓ ✓

22. Severity of risks involved ✓ ✓ ✓ ✓

23. Service price ✓ ✓ ✓ ✓ ✓


Revenue

24. Toll price ✓ ✓ ✓ ✓

25. Sale price ✓ ✓ ✓ ✓

26. Market demand ✓ ✓ ✓ ✓ ✓

27. Operational life ✓ ✓ ✓ ✓ ✓

28. Equity allocation ✓ ✓ ✓

29. Operation revenue in ✓ ✓ ✓ ✓ ✓


year

30. Return on investment ✓ ✓ ✓ ✓ ✓

31. Market situation ✓ ✓ ✓ ✓

32. Revenue stream ✓ ✓ ✓ ✓ ✓ ✓

33. Traffic count ✓ ✓ ✓ ✓

34. Project promotion ✓ ✓ ✓ ✓


Attributes
National

35. Government ✓ ✓ ✓ ✓
effectiveness

36. Investment attraction ✓ ✓ ✓ ✓

63
37. Poorly defined sector ✓ ✓ ✓ ✓ ✓
policies

38. Government objectives ✓ ✓ ✓


and commitment

39. Credibility of ✓ ✓ ✓ ✓
government policies

40. Poor transparency ✓ ✓ ✓ ✓

41. Government’s interests ✓ ✓ ✓ ✓

42. Political Stability ✓ ✓ ✓ ✓ ✓

43. Corruption ✓ ✓ ✓ ✓

44. Organizational structure ✓ ✓ ✓ ✓ ✓


Consortium’s Attributes

of project

45. Adequacy of funding ✓ ✓ ✓ ✓

46. Entrepreneurship and ✓ ✓ ✓ ✓


leadership

47. No of partners ✓ ✓ ✓ ✓ ✓

48. Strength of SPV ✓ ✓ ✓ ✓ ✓

49. Strength of consortium ✓ ✓ ✓ ✓

50. Capital structure of ✓ ✓ ✓


company

51. Right project ✓ ✓ ✓ ✓ ✓


identification

52. Risk management ✓ ✓ ✓ ✓ ✓ ✓


maturity

53. Differentiation in ✓ ✓ ✓ ✓ ✓
guarantees

54. Poor risk management ✓ ✓ ✓ ✓ ✓ ✓

55. Lack of competition ✓ ✓ ✓

64
56. Social welfare ✓ ✓ ✓ ✓ ✓

Purchase Power
57. Travel time ✓ ✓ ✓ ✓ ✓

58. Traffic congestion ✓ ✓ ✓ ✓

59. Population in area ✓ ✓ ✓ ✓ ✓

Initially 5 groups of factors were identified and grouped in literature review: 1)

financial indicators, 2) project’s executability, 3) revenue, 4) national attributes and 5)

consortium’s attributes. Table 9 shows the factors identified in year 2005 and the

assigned groups.

Table 9: Initially identified factors in year 2005

Group S/No Factors

3 Inflation rate

Financial Indicators 5 Net present value

7 Economic viability

16 Constructability
Project’s Executability
21 Site limitation

30 Return on investment
Revenue
32 Revenue stream

36 Investment attraction

37 Poorly defined sector policies

38 Lack of clear government objectives and


National Attributes commitment
39
Credibility of government policies
40
Poor transparency
41

65
Government’s interests

45 Adequacy of funding

46 Entrepreneurship and leadership

47 No of partners

49 Strength of consortium

51 Right project identification


Consortium’s Attributes
52 Risk management maturity

53 Differentiation in guarantees

54 Poor risk management

55 Lack of competition

These factors are used since a long time for critical decision making in PPP

projects such as estimating the length of concession period.

Considerable attention was given to the users being affected by the PPP projects

and the interaction of traffic and construction machinery in the literature following 2005

which led to the introduction of a new factor i.e. factor 59 population in area. Due to

this addition and some factors that followed, a new group of classification is introduced,

named as “Purchase Power” by the end of 2006.

Similarly other factors like factors 1, 2 and 10 were identified and added to

“Financial Indicators”; factors 12, 13, 14, 15, 18, 19 and 22 were identified and added

to “Project’s Executability”; factors 25, 26, 27, 29 and 31 were added to “Revenue”;

and factor 50 was added to “Consortium’s Attributes”. There were no new factors

identified in “National Attributes”.

66
Due to the larger considerations given to “Financial indicators”, three new

factors were identified an added in the next year i.e. 6, 8 and 9 to this group. Similarly

factor 11 was added to “Project’s Executability” whereas factor 34 was added to

“National Attributes” by the end of 2007. The remaining groups proceeded as they were

with no additions. The trend of financial indicators continued for the next year as well

as substantial considerations were given by researchers to the social welfare aspects and

hence certain critical additions were made to “Purchase Power”. Some additions were

made to groups “Project’s Executability”, “Revenue” and “National Attributes”: factor

17 to “Project’s Executability”; 23 and 24 to “Revenue” and 35 to “National

Attributes”. “Consortium’s Attributes” continued as the previous year with no additions.

After these inclusions research trend started focusing the “National Attributes”

like corruption and political stability in 2009, leading to the addition of factors 42 and

43 to “National Attributes”. The previous trend of “Purchase Power” also continued

with the addition of a new factor i.e. 58 social welfare. The remaining groups stayed

dormant with no additions of further factors for another year. The research trend started

shifting towards the “Project Executability” and “Consortium’s Attributes” in the next

year and one factor was added to the mentioned groups i.e. factor 48 strength of SPV to

“Consortium’s Attributes” and factor 20 construction logistics to “Project

Executability”.

The “Consortium’s Attributes” continued its trend with the addition of a new

factor i.e. 44 organizational structure of the project with no changes to the remaining

groups in 2011. The focal point of the research shifted towards the equity allocation and

its effects on revenue and the list is completed with the addition of a factor i.e. factor 28

67
equity allocation to “Revenue” by the end of 2012. This trend can be observed in Figure

4.

After 2012 till 2015 the groups as shown in Figure 5 had no new additions and

emphasis was laid on the already identified factors and researchers analyzed the effects

and interactions of these factors from different angles. Hence no new factors were

identified but the already identified factors appeared repeatedly. The encircled factors

are the ones added to the groups with time. A trend can be observed in the chart given

below after year 2012 to 2015 in which the encircled factors are the ones periodically

repeating each year.

68
Figure 4: Factors identification chart (2005-2012)

69
Figure 5: Factors repetition chart (2012-2015)

2.3 OUTPUTS

2.3.1 Frequency analysis

This thesis attempts to help in decision making regarding various critical aspects

of PPP projects based on the trends of identified factors and assigned groups for last 10

years i.e. 2005 to 2015. As a result a decision making matrix is formulated based on the

analysis of number of appearances of factors versus the number of areas affected by

them. The area of a factor’s influence relate to user, concessionaire or public body, or a

combination of these.The ranges followed were the same as described in the frequency

70
analysis. The analysis, as shown in Table 10, concludes that a total of 6 factors out of 59

(10.17%) eventually ended up in the red zone, 15 factors (25.42%) ended up in the

upper normal (pink) zone, 13 factors (22.03%) ended up in lower normal (yellow) zone

whereas the remaining 25 factors (42.4%) eventually ended up in the green (non-

critical) zone. It points to a very pertinent conclusion that a large portion of PPP

projects falls into the non-critical or safe zone, an argument that may easily be used in

the favor of these projects. Further, like most traditional works, only a minor

quantitative portion of decision making attributes of PPP projects fall into very critical

zone. These factors may have qualitatively substantial impact on these projects

therefore factors such as severity of risk of PPP projects get the highest attention from

both researchers and practitioners.

Table 10: Frequency Analysis

Red Zone (4th Quartile) Green Zone (1st Quartile)


Appearance

Appearance
Affected

Affected
Areas

Areas
S/No S/No

5 79 2 26 15 2

6 76 2 3 21 2

22 98 3 4 21 1

29 78 2 7 14 2

30 77 1 10 12 2

32 90 1 13 12 1

Pink Zone (3rd Quartile) 14 16 2

71
16 16 1

Areas Affected
Appearance
S/No 19 11 1

23 16 3

24 28 3

2 62 2 25 11 3

8 64 2 34 30 1

15 54 1 35 26 3

17 68 2 37 12 2

18 75 1 38 18 2

28 71 1 39 15 2

31 66 2 41 28 1

33 74 2 44 11 1

36 72 2 46 13 1

42 73 2 51 19 1

45 72 1 55 23 1

50 68 2 56 18 2

52 69 2 57 29 1

53 62 1 58 11 1

54 58 2

S/No 59 47 48 49 43 40 27 20 21 11 12 9 1
Yellow
Zone Appearance 41 49 38 48 36 39 43 34 42 45 42 48 32

(2nd Area 1 1 1 1 2 2 2 1 1 2 2 2 2
Quartile) Affected

72
2.3.2 Decision making matrix

After this analysis, finally the matrix shown in Figure 6 was obtained. The

matrix places the identified factors in various zones based upon the appearances of the

factors in the literature and analyzes them against the number of areas affected by them.

The maximum appearance recorded was 98 out of 121 (81%) while the minimum

appearance and consideration limit was 11 out of 121 (10%).The most appearing factor

i.e. severity of the risks involved ended up at the upper right most corner of the matrix

confirming that it is the most appearing and critical factor on the basis of research trend

followed during the last 10 years. Almost 81% (98 out of 121) papers have given due

consideration to this factor. Similarly all of the factors identified in the Table 9 are

placed in the matrix on basis of their appearance vs the areas affected by them.

The factors ending in fourth quartile (75% and above) are the most critical

factors and require proper considerations during the decision making of the concession

period’s length. The factors in 3rd quartile (50% - 75%) should also be given proper

considerations as these factors can anytime make it into the 4th quartile because of being

the nearest to the most critical zone. The factors in 2nd quartile (25%-50%) should be

watched and observed with proper management techniques being used to keep a check

on them whereas the factors placed in 1st quartile (0-25%) need only observation and no

intensive management effort is required for them. Once the analysis is performed and

the factors are placed in the matrix, different management techniques are required to be

used on these factors. Special considerations are required for the factors ending up in

the 4th quartile; they must either be exploited or extreme care must be taken to mitigate

their negative effects, if any.

73
Figure 6: Factors frequency v/s areas affected

74
Chapter 3

RESEARCH METHODOLOGY

3.1 INPUTS

• Literature Review

• Decision making matrix

• Frequency analysis

3.2 TOOLS AND TECHNIQUES

3.2.1 Pilot Survey

After the literature review a comprehensive list of factors was developed that

affect the length of concession period of PPP projects.

75
The method of factor identification was mainly focused on literature review. In

the next step a pilot survey was conducted to identify the top 10 factors that affect the

length of the concession period of PPP projects. For the said survey three different paths

were identified and one of them (Shown in red below) was selected.

The main question of the survey was whether or not to carry out a level “0”

screening to reduce the number of factors to the most significant ones only. This led to

two options. In case of “NO”, questionnaire was to be developed for all the 59 factors

and a comprehensive survey would have been carried out. In case of “YES”, we had to

face another critical decision which was the screening panel selection. Two options

were available for that i.e. Pakistani experts only or international experts including

those from Pakistan.

These options led to different questionnaire development.

Selecting only Pakistani experts led to 2 options i.e. taking responses for the top

factors of literature review from Pakistani experts whereas the next option had two

steps:

1) Questionnaire from Pakistani experts to shortlist the top factors

2) Asking detailed questions from international experts on those shortlisted factors.

The other option for panel selection was to seek help of international experts for

shortlisting the top factors affecting the length of concession period of PPP Projects and

carry out a global survey including responses from Pakistani experts. This procedure

was followed as shown in red color in the Figure 7. The screening panel consisted of

authors and field experts having vast experience in PPP projects.

76
Figure 7: Pilot Survey options

3.2.2 Initial Questionnaire

A questionnaire was developed in accordance to the pilot survey which focused

on the simple question of whether a particular factor affect the concession period of PPP

projects or not? Say “Does "Toll price" affect the length of concession period of PPP

projects?”

The respondents included experts from different countries throughout the world.

The distribution of experts is shown in

Table 11.

77
Table 11: Names and Countries of experts

S/No Name Country of Residence


1 Prof. Dr. Roehrich U.K
2 Mr. Tan China
3 Dr. HanaOKA shinya Japan
4 Mr. Taylor Colorado (US)
5 Mr. Tere Lamos Poland
6 Nikola Constantino Mexico (US)
7 Brig. Dr. Nadeem Ehsan Pakistan
8 Dr. Giulio Mangano Italy
9 Prof. Dr. Rickard Bergqvist Sweden
10 Ms. Ana Lopez Portugal
11 Dr. Tei Italy
12 Ms. Kitti Subprasom Thailand
13 Mr. Urjit Patel India
14 Dr. Zhang Hongkong
15 Prof. Dr. Athias France
16 Mr. E. Hoef Netherland
17 Prof. Dr. Amilawa Malaysia
18 Dr. Knittel (MIT) Cambridge (U.S)
19 Mr. Minnery Australia
20 Ms. Ameida Brazil
21 Engr. Kang Taiwan
22 Dr. Khanzadi Turkey
23 Engr. M. Alipour Ireland
24 Mr. Trujillo Spain
25 Mr. Ubbels New Zealand
26 Dr. Yevstafyev Costa Rica (U.S)

The respondents were asked to respond in Yes or No. If their answer was a yes,

they were further requested to assign the factors a quantitative score on the scale of 1 to

10 depending upon the impact of the said factor on the length of concession period.

78
As a result the Table 12 was obtained. The average score in the table refers to

the average of the scores assigned by the respondents to the said factor.

Table 12: Questions from questionnaire and average response score

S/No Questions/Factors Average- Percentage


Score
1 Does "Toll price" affect the length of concession period of PPP 9 90
projects?
2 Does "Operation period" affect the length of concession period 8.884615385 88.84615
of PPP projects?
3 Does "Project development cost" affect the length of concession 8.615384615 86.15385
period of PPP projects?
4 Does "Construction cost" affect the length of concession period 8.461538462 84.61538
of PPP projects?
5 Does "Revenue stream" affect the length of concession period 8.461538462 84.61538
of PPP projects?
6 Does "Market demand" affect the length of concession period of 7.923076923 79.23077
PPP projects?
7 Does "Net Present value of project" affect the length of 7.881656805 78.81657
concession period of PPP projects?
8 Does "Return on investment" affect the length of concession 7.881656805 78.81657
period of PPP projects?
9 Does "Discount rate" affect the length of concession period of 7.769230769 77.69231
PPP projects?
10 Do "Severity of risks involved" affect the length of concession 7.769230769 77.69231
period of PPP projects?
11 Does "Economic viability" affect the length of concession 6.99408284 69.94083
period of PPP projects?
12 Does "Operation cost" affect the length of concession period of 6.99408284 69.94083
PPP projects?
13 Does "Operational life of project" affect the length of 6.816568047 68.16568
concession period of PPP projects?
14 Does "Sale price" affect the length of concession period of PPP 6.674556213 66.74556
projects?
15 Does "Market situation" affect the length of concession period 6.390532544 63.90533
of PPP projects?
16 Does "Service price" affect the length of concession period of 6.319526627 63.19527
PPP projects?
17 Does "Profitability" affect the length of concession period of 6.313609467 63.13609
PPP projects?
18 Do "O & M costs" affect the length of concession period of PPP 6.142011834 61.42012
79
projects?
19 Does "Operation revenue in year" affect the length of 5.923076923 59.23077
concession period of PPP projects?
20 Does "Construction period" affect the length of concession 5.822485207 58.22485
period of PPP projects?
21 Does "Size of investment" affect the length of concession period 5.792899408 57.92899
of PPP projects?
22 Does "Income in year" affect the length of concession period of 5.727810651 57.27811
PPP projects?
23 Does "Size of project" affect the length of concession period of 5.597633136 55.97633
PPP projects?
24 Does "Construction period" affect the length of concession 5.597633136 55.97633
period of PPP projects?
25 Do "No of vehicles" affect the length of concession period of 5.597633136 55.97633
PPP projects?
26 Does "Complexity of project" affect the length of concession 5.532544379 55.32544
period of PPP projects?
27 Does "Risk management maturity of concessionaire" affect the 5.337278107 53.37278
length of concession period of PPP projects?
28 Does "Government’s interest" affect the length of concession 5.304733728 53.04734
period of PPP projects?
29 Does "Inflation rate" affect the length of concession period of 5.304733728 53.04734
PPP projects?
30 Does "Political influence" affect the length of concession period 4.914201183 49.14201
of PPP projects?
31 Does "Adequacy of funding" affect the length of concession 4.674556213 46.74556
period of PPP projects?
32 Does "Population in area" affect the length of concession period 4.142011834 41.42012
of PPP projects?
33 Does "Corruption" affect the length of concession period of PPP 4.082840237 40.8284
projects?
34 Does "Type of project" affect the length of concession period of 3.940828402 39.40828
PPP projects?
35 Do "Lack of clear government objectives and commitments" 3.807692308 38.07692
affect the length of concession period of PPP projects?
36 Does "Strength of the consortium" affect the length of 3.609467456 36.09467
concession period of PPP projects?
37 Does "Equity allocation" affect the length of concession period 3.550295858 35.50296
of PPP projects?
38 Do "Poorly finedde sector policies" affect the length of 3.489230769 34.89231
concession period of PPP projects?
39 Does "Traffic congestion" affect the length of concession period 3.381656805 33.81657
of PPP projects?
40 Does "Constructability of project" affect the length of 3.142011834 31.42012
concession period of PPP projects?
41 Does "Lack of competition" affect the length of concession 3.129230769 31.29231
period of PPP projects?
80
42 Does "Capital structure of company" affect the length of 2.849112426 28.49112
concession period of PPP projects?
43 Do "Difference in guarantees" affect the length of concession 2.692307692 26.92308
period of PPP projects?
44 Does "Credibility of government policies" affect the length of 2.512820513 25.12821
concession period of PPP projects?
45 Does "Procurement" affect the length of concession period of 2.177514793 21.77515
PPP projects?
46 Does "Strength of SPV" affect the length of concession period 2.082840237 20.8284
of PPP projects?
47 Does "Effectiveness of Government" affect the length of 2.071005917 20.71006
concession period of PPP projects?
48 Does "Investment attraction" affect the length of concession 2.071005917 20.71006
period of PPP projects?
49 Does "Entrepreneurship and leadership" affect the length of 2.019230769 20.19231
concession period of PPP projects?
50 Do "Construction logistics" affect the length of concession 1.809230769 18.09231
period of PPP projects?
51 Does "Social welfare" affect the length of concession period of 1.698224852 16.98225
PPP projects?
52 Does "Right project identification" affect the length of 1.513846154 15.13846
concession period of PPP projects?
53 Does "Site limitation" affect the length of concession period of 1.349112426 13.49112
PPP projects?
54 Does "Innovative design" affect the length of concession period 1.313609467 13.13609
of PPP projects?
55 Do "Number of partners" affect the length of concession period 0.887573964 8.87574
of PPP projects?
56 Does "Poor transparency" affect the length of concession period 0.591715976 5.91716
of PPP projects?
57 Does "Travel time" affect the length of concession period of 0.579881657 5.798817
PPP projects?
58 Does "Project’s promotion" affect the length of concession 0.328402367 3.284024
period of PPP projects?
59 Does "Organization structure of project" affect the length of 0.301775148 3.017751
concession period of PPP projects?

3.2.3 MODAL Analysis

In the next step MODAL analysis were performed and the agreeing experts’

percentage was calculated. This helped in identification of the top factors that affect the

length of concession period as shown in Table 13.

81
The collected survey responses were 26 in number; hence a factor having a

mode count of 26 means 100% of the experts agree that this factor has a significant

effect on the length of concession period.

Table 13: Modal analysis of responses

S/No Factors Mode Avg Score Standard Deviations Agreeing


Percentage
1 Toll price 26 9 0.848528137 100
2 Operation period 26 8.884615385 1.4512594 100
3 Project development cost 26 8.615384615 1.098250357 100
4 Discount rate 26 7.769230769 2.084374099 100
5 Market demand 26 7.923076923 1.741793947 100
6 Construction cost 26 8.461538462 2.231246633 100
7 Revenue stream 26 8.461538462 1.794007118 100
8 Severity of risks involved 26 7.769230769 1.945408796 100
9 Service price 24 6.846153846 2.633511841 92.30769231
10 Construction period 24 6.307692308 2.97683363 92.30769231
11 Sale price 24 7.230769231 2.470751988 92.30769231
12 O & M costs 24 6.653846154 2.755972535 92.30769231
13 Economic viability 24 7.576923077 2.610334491 92.30769231
14 Operation cost 24 7.576923077 2.548302602 92.30769231
15 Operational life of 24 7.384615385 2.757925642 92.30769231
project
16 Market situation 24 6.923076923 2.726508051 92.30769231
17 Net Present value of 24 8.538461538 2.656776532 92.30769231
project
18 Return on investment 24 8.538461538 2.641677789 92.30769231
19 Government’s interest 22 6.269230769 3.424122571 84.61538462
20 Political influence 22 5.807692308 3.059663129 84.61538462
21 Risk management 22 6.307692308 3.171992822 84.61538462
maturity of
concessionaire
22 Size of project 22 6.615384615 3.175870565 84.61538462
23 Complexity of project 22 6.538461538 3.190370126 84.61538462
24 Inflation rate 22 6.269230769 3.256472844 84.61538462
25 Construction period 22 6.615384615 3.225857072 84.61538462
26 Operation revenue in 22 7 3.322649545 84.61538462
year
27 Income in year 22 6.769230769 3.290078325 84.61538462
28 No of vehicles 22 6.615384615 3.371372695 84.61538462
29 Profitability 22 7.461538462 3.501208583 84.61538462
30 Size of investment 22 6.846153846 3.233478717 84.61538462
82
31 Population in area 20 5.384615385 3.699480213 76.92307692
32 Adequacy of funding 20 6.076923077 3.621304482 76.92307692
33 Strength of the 20 4.692307692 2.83928485 76.92307692
consortium
34 Corruption 20 5.307692308 3.246773546 76.92307692
35 Equity allocation 20 4.615384615 2.980965254 76.92307692
36 Traffic congestion 18 4.884615385 3.73445496 69.23076923
37 Lack of competition 18 4.52 3.417113792 69.23076923
38 Type of project 18 5.692307692 4.212070567 69.23076923
39 Poorly de fined sector 18 5.04 3.645545227 69.23076923
policies
40 Lack of clear government 18 5.5 3.92173431 69.23076923
objectives and
commitments
41 Capital structure of 18 4.115384615 3.011005454 69.23076923
company
42 Constructability of 18 4.538461538 3.51261463 69.23076923
project
43 Credibility of 16 4.083333333 3.843873348 61.53846154
government policies
44 Procurement 16 3.538461538 3.373197524 61.53846154
45 Strength of SPV 16 3.384615385 3.073459589 61.53846154
46 Social welfare 14 3.153846154 3.390484422 53.84615385
47 Effectiveness of 14 3.846153846 3.996921893 53.84615385
Government
48 Entrepreneurship and 14 3.75 3.529379795 53.84615385
leadership
49 Difference in guarantees 14 5 4.373835249 53.84615385
50 Investment attraction 14 3.846153846 3.812529949 53.84615385
51 Construction logistics 14 3.36 3.545889639 53.84615385
52 Site limitation 12 2.923076923 3.762159773 46.15384615
53 Right project 12 3.28 3.769615365 46.15384615
identification
54 Innovative design 12 2.846153846 3.563058323 46.15384615
55 Number of partners 10 2.307692308 3.030105355 38.46153846
56 Travel time 8 1.884615385 3.011005454 30.76923077
57 Poor transparency 8 1.923076923 3.097393445 30.76923077
58 Organization structure of 6 1.307692308 2.478212756 23.07692308
project
59 Project’s promotion 6 1.423076923 2.700712157 23.07692308

83
3.3 OUTPUTS

3.3.1 Top 10 factors Identification

The modal analysis helped us in identification of the top factors from industry

that the field experts gave maximum considerations to throughout the world. Hence we

obtained two tables, one consisting of the factors obtained from literature through year

2005 till 2015 and other from the professionals focusing on the current trends .These are

shown in the Table 14 andTable 15.

Table 14: Top 10 factors from Industry

From Industry
S/No Factors Score Rank
1 Toll price 9 1
2 Operation period 8.884615 2
3 Project development cost 8.615385 3
4 Construction cost 8.461538 4
5 Revenue stream 8.461538 5
6 Market demand 7.923077 6
7 Net Present value of project 7.881657 7
8 Return on investment 7.881657 8
9 Discount rate 7.769231 9
10 Severity of risks involved 7.769231 10

Table 15: Top 10 factors from literature

From Literature
S/No Factors Score Rank
1 Severity of risks involved 8.099 1
2 Revenue stream 7.438 2

84
3 Net Present value 6.528 3
4 Operation revenue in year 6.446 4
5 Return on investment 6.363 5
6 Income in year 6.28 6
7 Procurement 6.198 7
8 Traffic count 6.115 8
9 Political Influence 6.033 9
10 Investment attraction 5.95 10

The results from both the tables show similarities and differences at different

points which are debatable due to the dynamic nature of the construction industry. To

cut it short we obtained 4 common factors among the top 10 factors identified by both

methods: severity of risks involved, revenue stream, NPV and return on investment.

To get a clear picture of the top factors, a cumulative scoring was applied as

shown in Equation 3.1.

Total Factor Score (T.F.S) = L.S x I.S (3.1)

Where:

T.F.S = Total factor score,

L.S = Score from Literature (Frequency on scale 1 to 10)

I.S = Score from Industry.

As a result of the combined score the top 10 factors affecting the length of

concession period, as shown in Table 16, are identified.

85
Table 16: Total score of factors

S/No Factor Literature Score Industry Score Total Score


1 Revenue stream 7.438 8.461538462 62.93692308
2 Severity of risks involved 8.099 7.769230769 62.923
3 Net Present value 6.528 7.881656805 51.45145562
4 Return on investment 6.363 7.881656805 50.15098225
5 Construction cost 5.289 8.461538462 44.75307692
6 Operation revenue in year 6.446 5.923076923 38.18015385
7 Income in year 6.28 5.727810651 35.97065089
8 Market situation 5.454 6.390532544 34.8539645
9 Traffic count 6.115 5.597633136 34.22952663
10 Size of investment 5.619 5.792899408 32.55030178
11 O & M costs 5.123 6.142011834 31.46552663
12 Operation period 3.471 8.884615385 30.8385
13 Political Influence 6.033 4.914201183 29.64737574
14 Adequacy of funding 5.95 4.674556213 27.81360947
15 Operation cost 3.966 6.99408284 27.73853254
16 Risk management maturity 4.793 5.337278107 25.58157396
17 Complexity 4.462 5.532544379 24.68621302
18 Operational life 3.553 6.816568047 24.21926627
19 Discount rate 2.892 7.769230769 22.46861538
20 Poor risk management 3.967 5.337278107 21.17298225
21 Equity allocation 5.867 3.550295858 20.8295858
22 Toll price 2.314 9 20.826
23 Construction period 3.719 5.597633136 20.81759763
24 Capital structure of company 5.619 2.849112426 16.00916272
25 Strength of the consortium 3.966 3.609467456 14.31514793
26 Population in area 3.388 4.142011834 14.03313609
27 Differentiation in guarantees 5.123 2.692307692 13.79269231
28 Procurement 6.198 2.177514793 13.49623669
29 Investment attraction 5.95 2.071005917 12.32248521
30 Government’s interests 2.314 5.304733728 12.27515385
31 Corruption 2.975 4.082840237 12.1464497
32 Profitability 1.735 6.313609467 10.95411243
33 Market demand 1.239 7.923076923 9.816692308
34 Inflation rate 1.735 5.304733728 9.203713018
35 Project development cost 0.991 8.615384615 8.537846154
36 Service price 1.322 6.319526627 8.354414201
37 Economic viability 1.157 6.99408284 8.092153846
38 Size of project 1.322 5.597633136 7.400071006
39 SPV strength 3.14 2.082840237 6.540118343
40 Sale price 0.909 6.674556213 6.067171598
41 Lack of competition 1.9 3.129230769 5.945538462
42 Government objectives & 1.487 3.807692308 5.662038462

86
commitment
43 Construction logistics 2.809 1.809230769 5.082129231
44 Site limitation 3.471 1.349112426 4.682769231
45 Government effectiveness 2.148 2.071005917 4.44852071
46 Constructability 1.322 3.142011834 4.153739645
47 Type of project 0.991 3.940828402 3.905360947
48 No of partners 4.049 0.887573964 3.593786982
49 Poorly defined sector policies 0.991 3.489230769 3.457827692
50 Credibility of government 1.239 2.512820513 3.113384615
policies
51 Traffic congestion 0.909 3.381656805 3.073926036
52 Social welfare 1.487 1.698224852 2.525260355
53 Right project identification 1.57 1.513846154 2.376738462
54 Entrepreneurship and leadership 1.074 2.019230769 2.168653846
55 Poor transparency 3.223 0.591715976 1.907100592
56 Travel time 2.396 0.579881657 1.38939645
57 Innovative design 0.909 1.313609467 1.194071006
58 Project Promotion 2.479 0.328402367 0.814109467
59 Organizational structure of 0.909 0.301775148 0.274313609
project

This trend can also be observed on the 3D cube chart as shown in Figure 8. All

the identified 10 factors end up at the upper right corner referring to the fact that they

are the top most influential factors for PPP Projects. For the sake of understanding one

of the lowest scoring factors i.e. “organizational structure of the project” is also plotted

on the cube and it ends up at the lowest left corner showing that the level of influence it

has.

The x-axis of the cube refers to the response score, the y-axis to frequency from

literature while the z-axis to the mode value. All the scores are normalized and plotted

accordingly.

87
Figure 8: 3D cube showing allocation of factors

3.3.2 Developing an LCCA model for top 10 factors

After identification of the top 10 factors affecting the length of concession

period of PPP projects, LCCA model was developed for the mentioned factors.

The technique followed for the LCCA model is that of NPV analysis. According

to Walls and Smith (1998) as mentioned in USDOT (2010) NPV analysis consists of the

initial construction cost and the corresponding rehabilitation and maintenance costs

discounted through year n as shown in equation 3.2.

88
(3.2)

The Systems Dynamic (SD) models as shown in Figure 9 and Figure 10 use the

NPV analysis concept and incorporates the top 10 identified factors that affect the

length of concession period.

The “+” and “-” signs on the arrow heads show the reinforcing and balancing

natures of the factors respectively. Hence the factors return on investment, salvage

value, the traffic count and revenue stream positively affect and hence support the NPV

analysis whereas the factors construction costs, maintenance costs and rehabilitation

costs balances the analysis (University 2005).

89
Figure 9: Systems Diagram for model

90
Figure 10: SD model for calculating concession period

91
It must be noted that the factors as presented in the model are further comprised

of various sub-factors that asses and ensure proper estimation. Figure 11 shows the

systems diagram for the factor “Revenue stream”. It depends upon the toll price,

service price, traffic count, discount rate, equity, bank loan and costs in such a way that

the first 5 factors enforce it whereas the last two are the balancing factors for revenue

stream.

Figure 11: Revenue stream

Figure 12 shows the systems diagram for the “severity of risks involved”. It can

be observed that this factor is enforced by opportunities whereas the negative nature of

92
risk perception assigns sub-factors like those of planning, implementation, execution,

monitoring and control, and closure related as balancing factors and risks to it.

Figure 12: Involved risk severity

In case of the “NPV” as explained earlier all the benefits and costs related

factors must be considered. Generally factors like toll price, expected usage, revenue,

traffic count, salvage value and other benefits are the enforcing factors for NPV

whereas rehabilitation, routine maintenance, discount rate, construction costs, taxes

and other costs are the factors that balance it out. Figure 13 shows the systems diagram

for NPV.

93
Figure 13: NPV

In case of “return on investment” as shown in Figure 14, the reinforcing factors

are the shares, equity and revenues whereas the costs, taxes and interest rate are the

balancing factors.

The next factor among the top 10 factors affecting the length of concession

period of PPP projects is the “construction cost”. The systems diagram as shown in

Figure 15 demonstrates that the revenues are the balancing sub-factors for it whereas the

costs incurred in form of initial construction costs, maintenance, rehabilitation, service

areas’ construction and additional services construction are the reinforcing sub-factors

for this factor.

94
Figure 14: Return on investment

Figure 15: Construction cost


95
Figure 16 shows that the only balancing sub-factor for “operational revenue in

year” is that of costs; whereas the revenues obtained from toll price, service price, asset

selling and other sources are the reinforcing sub-factors.

Figure 16: Operational revenue in year

In case of “Income in year” as shown in Figure 17, the enforcing factors are

equity, operational areas and services areas revenues whereas the balancing factors are

expenditures, taxes and salaries. Furthermore taxes may be imposed upon the salaries

and other expenditures and the salaries may contain salaries of toll collection staff,

patrolling staff and other employed staff.

96
Service areas revenue
Operational revenues

Salaries

+ +
+
Taxes
Income in year - +
Equity revenues +
- - Expenses

+
Salaries of staff
+
+ Toll collection staff
Expenditures

Patrolling staff
Others

Figure 17: Income in year

The systems diagram for “market situation” as shown in Figure 18 identifies

latest trends, demand and supply, and need for project as the reinforcing sub-factors

whereas the law and order, political factors and other associated risks are the balancing

factors.

In case of the factor “Traffic count” as shown in Figure 19, the balancing sub-

factors are those associated with project location and truck loads whereas the estimated

usage, toll, number of vehicles, service price, and population density are identified as

the reinforcing sub-factors.

97
Figure 18: Market situation

Figure 19: Traffic count

98
The last factor of the top 10 factors i.e. “size of investment” as shown in Figure

20 constitutes of investments, shares, equity and other finances as the reinforcing sub-

factors while the taxes and debts/loans are the balancing sub-factors.

Figure 20: Size of investment

99
Chapter 4

RESULTS AND SYNTHESIS

4.1 TOOLS AND TECHNIQUES

4.1.1 The gap between the academia and Industry

One of the interesting findings of this research work is the gap between

academia and industry. The score already obtained from Table 16 and questionnaire as

described in the methodology section was used and the deviations were calculated for

both taking absolute values only. Table 17 shows these deviations and the comparison

chart is shown in Figure 21.

Table 17: Deviation table for both scores

S/No Factors Literature Score Industry Score Deviation


1 Right project identification 1.57 1.513846154 0.056153846
2 Government effectiveness 2.148 2.071005917 0.076994083
3 Size of investment 5.619 5.792899408 0.173899408
4 Social welfare 1.487 1.698224852 0.211224852
5 Severity of risks involved 8.099 7.769230769 0.329769231
6 Strength of the consortium 3.966 3.609467456 0.356532544
7 Innovative design 0.909 1.313609467 0.404609467
8 Traffic count 6.115 5.597633136 0.517366864
9 Operation revenue in year 6.446 5.923076923 0.522923077
10 Risk management maturity 4.793 5.337278107 0.544278107
11 Income in year 6.28 5.727810651 0.552189349
12 Organizational structure of project 0.909 0.301775148 0.607224852
13 Population in area 3.388 4.142011834 0.754011834
14 Market situation 5.454 6.390532544 0.936532544
15 Entrepreneurship and leadership 1.074 2.019230769 0.945230769
16 Construction logistics 2.809 1.809230769 0.999769231
17 O & M costs 5.123 6.142011834 1.019011834
18 Revenue stream 7.438 8.461538462 1.023538462
19 SPV strength 3.14 2.082840237 1.057159763
20 Complexity 4.462 5.532544379 1.070544379

100
21 Corruption 2.975 4.082840237 1.107840237
22 Political Influence 6.033 4.914201183 1.118798817
23 Lack of competition 1.9 3.129230769 1.229230769
24 Credibility of government policies 1.239 2.512820513 1.273820513
25 Adequacy of funding 5.95 4.674556213 1.275443787
26 Net Present value 6.528 7.881656805 1.353656805
27 Poor risk management 3.967 5.337278107 1.370278107
28 Return on investment 6.363 7.881656805 1.518656805
29 Travel time 2.396 0.579881657 1.816118343
30 Constructability 1.322 3.142011834 1.820011834
31 Construction period 3.719 5.597633136 1.878633136
32 Site limitation 3.471 1.349112426 2.121887574
33 Project Promotion 2.479 0.328402367 2.150597633
34 Equity allocation 5.867 3.550295858 2.316704142
35 Government objectives & 1.487 3.807692308 2.320692308
commitment
36 Differentiation in guarantees 5.123 2.692307692 2.430692308
37 Traffic congestion 0.909 3.381656805 2.472656805
38 Poorly defined sector policies 0.991 3.489230769 2.498230769
39 Poor transparency 3.223 0.591715976 2.631284024
40 Capital structure of company 5.619 2.849112426 2.769887574
41 Type of project 0.991 3.940828402 2.949828402
42 Government’s interests 2.314 5.304733728 2.990733728
43 Operation cost 3.966 6.99408284 3.02808284
44 No of partners 4.049 0.887573964 3.161426036
45 Construction cost 5.289 8.461538462 3.172538462
46 Operational life 3.553 6.816568047 3.263568047
47 Inflation rate 1.735 5.304733728 3.569733728
48 Investment attraction 5.95 2.071005917 3.878994083
49 Procurement 6.198 2.177514793 4.020485207
50 Size of project 1.322 5.597633136 4.275633136
51 Profitability 1.735 6.313609467 4.578609467
52 Discount rate 2.892 7.769230769 4.877230769
53 Service price 1.322 6.319526627 4.997526627
54 Operation period 3.471 8.884615385 5.413615385
55 Sale price 0.909 6.674556213 5.765556213
56 Economic viability 1.157 6.99408284 5.83708284
57 Market demand 1.239 7.923076923 6.684076923
58 Toll price 2.314 9 6.686
59 Project development cost 0.991 8.615384615 7.624384615

Irrespective of the impact on the concession period there are certain factors like

those from serial 1 to 16 in Table 17 to whom both the industry and academia give

equal importance and considerations. These factors show overall deviation of less than 1

in 10 or 10%.
101
Figure 21: Comparison of Academia and Industry

102
In case of factors 17 to 48 in Table 17, there is a variation of 11 to 40 % in the

opinions of academia and industry.

Whereas factors like those from serial 49 to 59 in Table 17 show a variation of

more than 40% in both the streams. The most significant deviation is in case of Project

development cost to which the academia is giving minimum whereas the industry is

assigning maximum scores.

4.1.2 4.2.2 The gap between Academia and Pakistani Industry

In case of Pakistani industry though the overall deviation is a little lesser

comparatively but the deviation has considerably increased for the factors like

Government’s interests, Corruption, Market situation, Market demand, Discount rate,

Government effectiveness, Service price and Sale price. Table 18 shows the deviation of

Pakistani industry and academia.

Table 18: Deviation of Pakistani industry and Academia

Factor Avg score Academia score Standard deviation


Differentiation in guarantees 2.7 2.692307692 0.007692308
Revenue stream 8.4 8.461538462 0.061538462
Poorly defined sector policies 3.4 3.489230769 0.089230769
Site limitation 1.5 1.349112426 0.150887574
Adequacy of funding 4.5 4.674556213 0.174556213
Government objectives & 4 3.807692308 0.192307692
commitment
Investment attraction 2.3 2.071005917 0.228994083
Type of project 3.7 3.940828402 0.240828402
Construction period 5.3 5.597633136 0.297633136
Strength of the consortium 3.3 3.609467456 0.309467456
Profitability 6 6.313609467 0.313609467
O & M costs 6.5 6.142011834 0.357988166
Risk management maturity 5.7 5.337278107 0.362721893
Poor risk management 5.7 5.337278107 0.362721893

103
Right project identification 2 1.513846154 0.486153846
Credibility of government policies 2 2.512820513 0.512820513
Equity allocation 3 3.550295858 0.550295858
No of partners 1.5 0.887573964 0.612426036
Innovative design 0.6 1.313609467 0.713609467
Operational life 6 6.816568047 0.816568047
Net Present value 7 7.881656805 0.881656805
Lack of competition 2.2 3.129230769 0.929230769
Operation revenue in year 6.9 5.923076923 0.976923077
Return on investment 6.9 7.881656805 0.981656805
Size of investment 4.8 5.792899408 0.992899408
Capital structure of company 1.8 2.849112426 1.049112426
Operation cost 5.8 6.99408284 1.19408284
Inflation rate 4.1 5.304733728 1.204733728
Poor transparency 1.8 0.591715976 1.208284024
Constructability 1.9 3.142011834 1.242011834
Operation period 7.6 8.884615385 1.284615385
Construction logistics 3.1 1.809230769 1.290769231
Organizational structure of project 1.7 0.301775148 1.398224852
Severity of risks involved 6.3 7.769230769 1.469230769
Income in year 7.2 5.727810651 1.472189349
Social welfare 0.2 1.698224852 1.498224852
Entrepreneurship and leadership 3.6 2.019230769 1.580769231
Traffic count 7.2 5.597633136 1.602366864
Complexity 3.9 5.532544379 1.632544379
Procurement 0.5 2.177514793 1.677514793
Traffic congestion 5.2 3.381656805 1.818343195
Population in area 2.3 4.142011834 1.842011834
Travel time 2.5 0.579881657 1.920118343
Political Influence 6.9 4.914201183 1.985798817
Toll price 7 9 2
SPV strength 4.1 2.082840237 2.017159763
Construction cost 6.4 8.461538462 2.061538462
Size of project 3.5 5.597633136 2.097633136
Project Promotion 2.5 0.328402367 2.171597633
Economic viability 4.6 6.99408284 2.39408284
Project development cost 5.8 8.615384615 2.815384615
Government’s interests 8.3 5.304733728 2.995266272
Corruption 1 4.082840237 3.082840237
Market situation 2.9 6.390532544 3.490532544
Market demand 4.2 7.923076923 3.723076923
Discount rate 4 7.769230769 3.769230769
Government effectiveness 6 2.071005917 3.928994083
Service price 2.3 6.319526627 4.019526627
Sale price 1.4 6.674556213 5.274556213

104
Figure 22: Pakistani industry vs Academia

In case of global industry vs academia the deviations between the factors like

political influence, market situation, government’s effectiveness and corruption etc. are
105
lesser as compared to Pakistani industry. Figure 22 shows these deviations in graphical

form.

4.24.3 OUTPUTS

4.2.1 4.3.1 The Overall gap between Industry and Academia

After comparison of the top 10 factors from industrial response with their

identification year as stated by academia the conclusion can be made that there is a

difference of around 9 years between the academia and industry. The conclusion is

made by averaging the appearance of the factors and on average most of the factors

appeared between year 2006 to 2007 giving an average value of 8.9 so we can say that

there is a difference of around 9 years between the academia and the industry. The

industry is lagging behind the academia. This deviation can be observed in Table 19.

Table 19: Industrial score and year of identification by Academia

Questions/Factors Average Score Year of identification


Toll Price 9 2008
Operation period 8.884615385 2006
Project development cost 8.615384615 2006
Construction cost 8.461538462 2007
Revenue stream 8.461538462 2006
Market demand 7.923076923 2006
NPV 7.881656805 2005
Return on investment 7.881656805 2005
Discount rate 7.769230769 2006
Severity of involved risks 7.769230769 2006

4.2.2 4.3.2 Developing the equation for Concession period Improvement

Among the top 10 factors we have the factors Income in year, Return on

investment and Operation revenue in year that can be represented by a single variable

106
“Project income”. Also the factors Construction cost and traffic count are intrinsically

included in the factor NPV, so these can be represented by single factor “NPV”.

R.S ∝ (4.1)

Revenue stream is inversely proportional to the length of concession period

(Karim 2011).The more smoother and increased revenue stream will ultimately help in

quick recovery of the invested money and hence the concession period must be reduced

proportional to the increase in the revenue stream as shown in equation 4.1.

S.I.R ∝ (4.2)

More the severity of the involved risks in projects more will be the concession

period as indicated by Albalate (2013). The severity of risks demand for added time to

the concession length in order to cope with any unexpected surprise and risks. So there

is a direct relation between the severity of involved risks and length of concession

period as shown in equation 4.2.

P.I ∝ (4.3)

Tan (2012) indicated that the income from project inversely affects the length of

concession period of PPP projects. Hence a project offering more income will

intrinsically call for a lesser concession period .The relation is shown in equation 4.3.

M.S ∝ (4.4)

107
The better the market situation the lesser must be the concession period as quick

recovery of the investment is ensured (Wang 2015).So the market situation is inversely

proportional to the concession period as expressed in equation 4.4.

I.S ∝ (4.5)

The recovery of larger sized investment calls for a longer concession period as

suggested by Erick (2006).So there is a direct proportionality between the investment

size and the concession period as the larger investment will intrinsically need larger

time for its recovery under normal circumstances. The relation is shown in equation 4.5.

NPV ∝ (4.6)

The greater the net present value, lesser should be the minimum concession

period (Zhang, 2011). Though this is highly debatable due to the dynamic nature of the

factors constituting the NPV in itself but overall from decision making point of view the

minimum concession is the point at which NPV=0 whereas the increase in this depends

upon the acceptable level of IRR to both the parties so generally we can say that there is

an inverse relation between the NPV and concession period as shown in equation 4.6.

Using the Top 10 factors an equation can be developed for the modification of

the concession period of PPP projects as shown in equation 4.7.

M.C.P = K x C.P0 (4.7)

Where:

M.C.P = Modified concession period

C.P0 = originally sought concession period based upon NPV calculation.

108
(4.8)

Just like the FIDIC’s price adjustment formula (2009), the value of K is

comprised of fixed as well as adjustable portion.0.29 out of 1 or 29% of the value is

fixed for NPV analysis. The NPV is highly subjective to the understanding of both the

parties upon the acceptable IRR value and payback period hence an acceptable

concession period is proposed by the lending authority.

The coefficients a, b, c, d, e must sum to 0.71 or 71% constituting the adjustable

portion of the formula. The value for k will be 0.01 to 1.99 with 1 as the normal value in

exactly the same as expected circumstances. Further exploratory study expressed the

relations between the factors and Concession period as follow:

The 29% effect due to NPV will always be fixed while the remaining 71 % will

vary depending upon the conditions keeping the equations 4.1 to 4.6 in mind.

The NPV will decide the CP0 and is hence given a fixed portion of 29% in the

value for K whereas the rest of the coefficients and corresponding factors are highly

subjective to the opinions of the experts deciding the concession length. Hence the said

formula is aimed at policy making and is aimed at helping the policy makers and

decision makers.

For evaluation purposes the response score was incorporated in the formula by

using total score obtained from equation 3.1 and its % effect was calculated by dividing

the score of individual factor by total cumulative score for all factors hence the values

as shown in Table 20.

109
Table 20: Table for % effect

S/No Factor Total Score % effect


1 Revenue stream 62.93692308 0.140484203
2 Severity of risks involved 62.923 0.140453125
3 Net Present value 51.45145562 0.114846999
4 Return on investment 50.15098225 0.111944157
5 Construction cost 44.75307692 0.099895261
6 Operation revenue in year 38.18015385 0.085223558
7 Income in year 35.97065089 0.080291631
8 Market situation 34.8539645 0.077799028
9 Traffic count 34.22952663 0.076405193
10 Size of investment 32.55030178 0.072656924

Project Income = 50.15098225+38.18015385+35.97065089 or effect of

0.111944157+0.085223558+0.080291631 =0.28

Also the factors Construction cost and traffic count are intrinsically included in

the factor NPV , so the NPV can also be expressed as the combined sum of 0.29

calculated as before. These calculations are shown in Table 21.

Table 21: Modified % effect table

S/No Factor Code Total Score % Effect


1 Revenue stream R.S 62.93 0.140484203
2 Severity of risks involved S.I.R 62.923 0.140453125
3 Net Present value NPV 130.42 0.29
4 Project Income P.I 124.39 0.28
5 Market situation M.S 34.85 0.077799028
6 Size of investment I.S 32.55 0.072656924

110
Furthermore the values for the factors should always be used in portion of 1 and

added or subtracted to 1 depending upon the relations shown in equations e.g. in case of

a project being 20% more risky than normal, the R.S value will be 1+ ( )x1=1.2

Similarly in case of the expected project income being 20% more the P.I value

will be 1-( ) x1=0.8

In case of a project having 25% more risks, acceptable NPV value, and almost

same income as the project to which it is compared and an increased Investment size of

about 30 percent, the calculations would be as follow:

The original concession proposed/sought is of 20 years based upon NPV

analysis.

Factor Increase Decrease Overall score


R.S 20% - 0.8
S.I.R 25% - 1.25
NPV - - 1
P.I - - 1
M.S - 25% 1.25
I.S 30% - 1.3

As

Putting the values we get,


So
K=

K=1.135
And

111
M.C.P = 1.135 x 20
M.C.P = 22.7 years
So in these conditions the concession period must be revised and increased to

22.7 years to incorporate the additional risks and worst market situation.

4.2.3 Synthesis

For synthesis of the equation and in order to validate it, Vensim PLE ® software

was used. Vensim PLE ® is software designed for modeling one or more quantities that

change over time. The software uses the concepts of systems dynamics.

The diagrams shown in Figures 9,10,11,12,13,14,15,16,17,18,19 as well as the

model in Figure 10 are drafted using Vensim PLE ® .

For the synthesis and validation of the prosed equation and the model various

iterative studies were conducted using Vensim .The conditions used are the worst,

normal and best conditions and comparative charts are formulated.

Under normal conditions we have a graph as shown in Figure 23. Now if on a

project we have 99 % more risks and the rest of the factors are kept as normal, we will

end up having the graph as shown in Figure 24.

We can clearly see the effect of increasing risks on the length of the concession

period and the concession length is considerably increased as evident from the figure.

Under the worst conditions i.e. using the worst possible values for all the factors,

we get a graph as shown in Figure 25.

It is evident from the comparative graph that the concession period will be

increased up to as long as 62 years if the initial concession period is kept to 20 years but

to get the same results as that of 20 years effect, we can use a concession of 34.1 years.
112
Figure 23: Normal behaviour for Concession period

22.7

Figure 24: If only risks are increased

Similarly for best ever conditions, as shown in Figure 26, the concession period

becomes 5.94, meaning that there is no need of reconsidering the concession period on

behalf of the concessionaire but rather the public entity or decision makers have made a

serious mistake and they should revise the concession.


113
34.1

Figure 25: Worst ever possibilities for 20 year CP0

Using the data obtained from the response and as obtained from the example

solved above, it can be evidently observed in Figure 27 that there is a need of extending

the concession period.

5.94

Figure 26: Best possible conditions

114
20.96

Figure 27: Data from responses

4.2.4 Case Projects

In order to validate the proposed methodology, a number of case studies are run.
For the sake of overarching effect, the case projects encompass completed, running and
under-procurement projects. This allows studying and understanding the pros and cons
of proposed model. In the following sections detailed analysis and discussion pertaining
to real projects are presented.
1) Completed Projects
a. Lahore-Sheikhopora-Faisalabad Dual Carriage Way

This project was constructed during 2003 to 2005 and became operational in
2005. It involved the renowned construction firms like Frontier Works Organization
(F.W.O), Sachal Group and National Highways Authority (N.H.A) Pakistan. The
carriage way was basically the extension of the already existing route and the source of
major income was that of the tolling. An SPV was developed for the project by the
name of LAFCO. The original concession period sought and agreed upon was 25 years.
The data reported in Table 22 was obtained from the project stakeholders.

115
Table 22: Data from Lahore-Sheikhopora-Faisalabad Dual Carriageway

Factor Increase Decrease Overall score


R.S 11% - 0.89
S.I.R - - 1
NPV - - 1
P.I 10% - 0.9
M.S - - 1
I.S - - 1

As

Putting the values we get,


So
K=

K=0.9566
And

M.C.P = 0.9566 x 25
M.C.P = 23.915 years
As per the calculation, it seems that the project would have been justified even if
the concession period of 24 years was committed under the existing conditions. The
reduction in the concession period is due to the following reasons:
• There was an average growth of 30% in number of vehicles or transportation
means during years 2003 – 2005.
• No route promotion was required to attract new traffic as the route was already
well established.
• High tolling was available during the years of concession.

116
• The companies involved in construction had high expertise in field of highway
construction.
So a recommendation for futuristic construction considerations can be that if the above

conditions are prevailing, the concession period can be shortened.

In the current form, the concessionaire seems to have been incentivized for committing

to the project. It must be appreciated but not at the cost of opportunities for public

revenue generation.

b. Habibabad Project
Started operating in 2009, this project is one of the most successful BOT projects in

PPPs of Pakistan. Though it was initially given a concession of 10 years (to be

transferred back to NHA by 2019), virtually the payback was achieved in half of

that time. The feasibility studies revealed an interesting pattern of recovery and

hence it was made in 5 years only. The project was transferred back to the public

party in 2014 on the initiation of concessionaire. The data obtained is as follow:

Factor Increase Decrease Overall score


R.S 50% - 0.5
S.I.R - 70% 0.3
NPV - - 1
P.I 70% - 0.3
M.S 50% - 0.5
I.S - 20% 0.8

As

117
Putting the values we get,
So
K=

K=0.5829
And

M.C.P = 0.5829 x 10
M.C.P = 5.8 years
The calculation only strengthens what is already known in this scenario. As per
the proposed equation, the project would have been feasible even if the concession had
been reduced to 6 years and the study confirms it. The officials quoted that the
concession was ended by the contractor himself as a gesture of good well after 5.5 years
and transferred it back to NHA.
The key factors leading to the success of the mentioned project were its huge
payback in form of tolling due to existing higher traffic volume. Further, owing to
positive socio-political support, the market was desirable and supportive. Furthermore
the feasibility studies of the project predicted a huge success. Also the smaller project
size, the less complicated nature, brownfield construction and easy access approach due
to non-proximity with any urban area aided to the huge success of this project.

2) Ongoing Project :
a. Lahore Islamabad Motorway (M-2) Overlay and Rehabilitation Project

M-2 Motorway joins Islamabad to Lahore and has a span of around 358 km. The

rehabilitation project started in 2014 and currently is in progress since almost a year.

The companies involved in this project are FWO, Bin Nadeem Associates (BNA) and

118
Zeeruk International. The concession sought for this project is of 20 years and the SPV

is known as Motorway Overlay and Rehabilitation Engineering Company (MORE). The

data as shown in Table 23 was obtained from the deputy project manager’s office.

Table 23: Data Obtained from Lahore Islamabad Motorway (M-2) Overlay

and Rehabilitation Project

Factor Increase Decrease Overall score


R.S - 5% 1.05
S.I.R 15% - 1.15
NPV - - 1
P.I - - 1
M.S - - 1
I.S 10% - 1.10

As

Putting the values we get,


So
K=

K=1.0353
And

M.C.P = 1.0353 x 20
M.C.P = 20.706 years

So based upon the current situation the concession length must be increased to

21 years to incorporate the additional risks and decreasing revenue stream. Keeping in

119
mind that just one year has passed since the construction has started, the situation seems

very alarming and steps are required to be taken to keep the concession in check.

The project income and market situation balance each other out because of the

soon to be constructed interchanges and hence more toll production so overall there will

be no change in expected motorway usage.

The main reason for the increase in the concession period can be linked to:

• Lack of coordination and communication between the stakeholders as quoted by

the DPM office.

• The increased risks of rework due to poor quality management and rushing

through the work.

b. Lahore Sialkot Motorway


The Lahore Sialkot motorway project is currently ongoing. Due to the risky nature

of the project, prequalification technique is used for shortlisting the potential

contractors. The project’s income is supposed to be following the tolling stream as

well as the Government of Pakistan (GOP) will be providing the required subsidy

for the project as tolls are not expected to meet the contractor’s expenses by 100%.

The following data as shown in Table 24 was obtained for this project.

Table 24: Data of Lahore Sialkot Motorway Project

Factor Increase Decrease Overall score


R.S - - 1
S.I.R 30% - 1.3
NPV - - 1
P.I - 15% 1.15
M.S - 8% 1.08
I.S 10% - 1.10
120
As

Putting the values we get,


So
K=

K=1.0975
And

M.C.P = 1.0975 x 25
M.C.P = 27.44 years
The concession length must have been around 28 years to incorporate the

additional financial risks associated with this project. Furthermore the project is a green

field construction on virgin land so the risks intrinsic to this project are of varying

severity.

3) Under-Planning Project:
a. Motorway M-9
A very ill-fated and highly convicted project, the M-9 can be considered as a bad

example of the project execution. The project faced failures in each of the last 3

attempts to be started. The main reasons for the unsuccessful startup of the project

can be linked directly to the political interests and will of the prime stakeholders.

The socio-political complexity in the form of land acquisitions and riots has been

one of the primary issues of this inauspicious project. As a result the government

has awarded the project to the armed forces of Pakistan to be executed by its
121
premium construction services organization FWO. The data as shown in Table 25

was obtained for this project.

Table 25: Data of M-9 Project

Factor Increase Decrease Overall


score
R.S - 20% 1.2
S.I.R 40% - 1.4
NPV - - 1
P.I - 10% 1.10
M.S - 30% 1.30
I.S 10% - 1.10

As

Putting the values we get,


So
K=

K=1.1424
And

M.C.P = 1.1424 x 25
M.C.P = 28.56 years
So the above conditions force the decision makers to revise the concession

length. In case these conditions prevail, the calculation demonstrates that the concession

has to be increased to 29 years for incorporating the increased risks and poor market

situation.

122
4.2.5 Discussion

From these demonstrations, it can be seen that in most of the projects the

proposed methodology has advocated revisiting the original plans and increasing the

concession period. The inability to do so may result not only in failure of specific

projects but will paint a negative picture of entire PPP procurement capability of the

concerned authorities. Such negative image will discourage the investors who may

otherwise be agents of running the engine of economy and uplifting the social standards

by providing jobs and better infrastructure. Therefore, the PPP procurement agencies

will need such a mechanism where the concession agreement of a running or under

operations project can be revisited and the improved concession lengths can be

incorporated.

It is a general rule that a concession length longer than 30 years may not be

agreed. Preserving the logic behind such limitation, it can be argued that every project

may not be cast into such rigid policy lines. As mentioned above, the revision

mechanism along with incorporating the strategy offered by this study may help

rationalize the concession lengths and the 30-year rule may be localized with respect to

each project. This may result into increased level of confidence to investors and

concessionaires along with the public agency. The elated confidence is aimed at

boosting the infrastructure procurement resulting in better and economic infrastructure

facilities to users.

123
Chapter 5

CONCLUSIONS AND RECOMMENDATIONS

5.1 INPUTS

5.1.1 Literature review

Literature review consisted of 131 research papers, online materials and various

journals and magazines. The study period was restricted to the last decade i.e. 2005-

2015 .A total of 59 factors were identified that affect the length of concession period of

PPP projects which were further divided into 6 categories. Frequency analysis was

performed on these factors to find out the most frequent factors amongst the identified

ones. As a result a list of factors along with their frequency was obtained which was

used for further analysis and shortlisting.

Furthermore an attempt was made to classify the papers on the basis of their

year of appearance in order to know the trends being followed in the research.

124
5.1.2 Methodology

In the methodology section, a global survey was conducted from industrial

experts and the scores obtained were compared to the scores from literature. After the

comparison a combined score was developed using the modal analysis and scores from

both streams. Using the principles of System Dynamics a model was developed which

was later on synthesized using Vensim® software. The synthesis helped in validating

the model and formulating an equation for concession period improvement.

5.1.3 Results

The model developed was tested for ideal, worst and best possible conditions

and some case projects were analyzed to get the results. This led to the validation of the

proposed equation.

5.2 TOOLS & TECHNIQUES

5.2.1 Achieving the objectives

Table 26 shows the different objectives and the methodology of achieving them.
A reference section has also been provided in the table in order to simplify the searching
procedure.

Table 26: Achieving the objectives

S/No Objectives Methodology Status Reference


1 To figure out the factors affecting the Literature Review Achieved Table 3
length of concession period of PPP
Projects

125
2 To highlight the key factors affecting the Literature review Achieved Table 16
length of concession period and hence vs Industrial S/No 1 to 10
helping in more realistic concession review
period. (Questionnaire
Response)
3 To Bridge the gap between the literature Literature review Achieved Table 18 ,
and industry regarding the concession vs Industrial Figures 20 &
period of PPP Projects review 21
4 To synthesize the decision making model Making a system Achieved Figures 1 to
for concession period using LCCA dynamics model 19 ,
for application of Equations 4.1
LCCA to 4.8

5.2.2 Concluding the Objectives

1) To figure out the factors affecting the length of concession period of PPP
Projects
An extensive literature review consisting of 130 published papers and various

online materials was performed to figure out the factors affecting the length of the

concession period of PPP projects. As a result a total of 59 factors were identified that

affect the concession period length. These factors along with their sources are shown in

Table 3. In order to streamline the research further, an attempt was made to classify

these factors and as a result 6 groups have been formulated based upon both functional-

and characteristic-based criteria.

2) To highlight the key factors affecting the length of concession period and hence
helping in more realistic concession period.
In order to further highlight the key factors among the already identified ones,

an international survey was carried out. The factors obtained from literature were

126
compared to the responses obtained through the survey. Numerical scoring was

performed and as a result top 10 factors were identified that affect the length of

concession period as shown in Table 16 (S/No 1 to 10).

3) To bridge the gap between the literature and industry regarding the concession
period of PPP Projects
In order to bridge the gap between academic and industry, it was imperative to

first find out the lack of alignment between the two sources. The results of literature

review and international survey were compared as shown in Table 18 and Figures 20 &

21. The scores for Pakistani industry and academia were also compared and can be

observed in the aforementioned tables and figures.

The key conclusion that can be drawn from observing the figures is that there is

a gap of around 9 years between the academia and industry on a global scale.

4) To synthesize the decision making model for concession period using LCCA
For synthesizing a decision support model and tool the principles of LCCA and

System Dynamics were used and as a result a model as shown in Figure 9 was

developed. Using Vensim®, synthesis was carried out on the proposed model. Then

using the concept and logic of the proposed model and the top 10 factors, an equation as

shown in 4.8 was developed to help the decision makers while deciding the concession

period initially as well as its revision at any point within project life cycle.

127
5.3 OUTPUTS

5.3.1 Summarizing the conclusions

• The proposed model contributes to a more transparent concession system through the
introduction of the formula for modifying the concession period that can help the

three parties to perceive and achieve their own goals.

• The model aims at providing a win-win-win scenario for all the concerned parties.

• Concession period is dependent upon various dynamic factors like project income,

toll price, severity of involved risk, market situation, other revenues etc. And hence it

must also be treated as a dynamic variable and therefore must be revised from time to

time within the life of the project.

• There is a gap of almost 9 years between the academia and industry when it comes to

concession period of PPP projects. The industry lags behind the academia and needs

to upgrade their planning and decision making capabilities in order to achieve

overall success.

• Decision makers tend to rely more on the historical data. Undoubtedly this is a useful

source of information, but it sometimes oversees the unique nature of projects. As a

result unrealistic or overambitious concession periods may be proposed.

5.3.2 Recommendations

• Concession period is of dynamic makeup as it is dependent upon factors with

varying nature. Hence it must be revised from time to time within the project life

cycle. There must be some mechanism put in place which allows for revising the

concession period after each year of work as the inflation and budget for the next

year are determined. For Pakistan the recommendation would be to revise it after
128
every 5 years where the new government tends to set its own rules and goals. The

incorporation of this formula should be somewhere in the midst of the

government`s tenure. By doing so a taste of the previously adopted policies can be

acquired and the ground will be set for successful implementation of the proposed

formula. Also doing the analysis every year may be more resource consuming and

costly.

• There is an increased need of incorporating the top factors identified in this study

in the decision making of concession period.

• Steps must be taken to enforce the considerations of the key factors that affect the

length of concession period and make the estimation process more realistic rather

than dependent upon historical data. The proposed formula can be adopted and

modified to suite the national needs and must be consulted when deciding or

revising the concession period.

• Regular meetings and seminars must be conducted inviting both the industrial and

academic experts so as to bridge the knowledge gap between the academia and

industry.

5.3.3 Recommendations for further research

• The current study is the first step in wider analysis of the arrangement of available

literature on the PPP projects and the decision making criteria. Further assessment

is required for the identified factors along with finding other important factors by

enhancing the search criteria followed in this paper. Proper management techniques

must be applied on these identified factors and their effects should be observed.

129
• A critical point in the decision making efficiency is connected with the difficulty in

collecting data referring to the internal organization of the 3 involved parties. A

chance tofill this information gap could easily be achieved incentivizing the

concessionaire of the terminal area to release all the needed information due to the

new proposed link between the identified factors on the concession period and

performance achievements.

• An interesting evolution of the presented work considers the evaluation of the

effects of the social welfare and the user expectations on the length of concession

period in order to better understand the impact of the proposed methodology in

different PPP projects.

• This study uses LCCA and NPV techniques as its basis. Other financial techniques

like IRR could be explored for evaluating the same phenomenon.

• Furthermore the proposed study uses the methodology of Systems Dynamics and

there is a need of reevaluating the proposed formula by other statistical techniques

as well as some graphical techniques like Structural Equation Modeling (SEM).

• The proposed methodology appears as afirst approach in order to set a conceptual

framework; in this context future studies and research will work on the above

mentioned considerations in order to enrich the potential application of the

proposed methodology.

130
REFERENCES

1. Albalate, D. and G. Bel (2009). "Regulating concessions of toll motorways: An


empirical study on fixed vs. variable term contracts." Transportation Research
Part A: Policy and Practice 43(2): 219-229.

2. Albalate, D., L. Fernandez, et al. (2013). "The road against fatalities:


infrastructure spending vs. regulation??" Accid Anal Prev 59: 227-239.

3. Alliance, A. P. (2012). "LIFE-CYCLE COST ANALYSIS: A POSITION


PAPER."

4. FHWA (2009). "Transportation Asset Management Case studies- The Colorado


experience."

5. IPDF (2006). "Facilitating and Promoting Viable, Sustainable and Affordable


Public PrivatePartnerships in Pakistan."

6. NHA (2013). "LIST OF PPP PROJECTS 2013."

7. USDOT (2002). "Life Cycle cost analysis Primer."

8. Ambituuni, A., J. Amezaga, et al. (2014). "Analysis of safety and environmental


regulations for downstream petroleum industry operations in Nigeria: Problems
and prospects." Environmental Development 9: 43-60.

9. Ameyaw, E. E. and A. P. C. Chan (2015). "Evaluation and ranking of risk


factors in public–private partnership water supply projects in developing
countries using fuzzy synthetic evaluation approach." Expert Systems with
Applications 42(12): 5102-5116.

10. Anderson, D., Sweeney, D., Williams, T., Camm, J., & Cochran, J. (2015). An
introduction to management science: quantitative approaches to decision
making, 14th Edition. Cengage Learning.

11. Athias, L. and A. Nuñez (2008). "Winner’s curse in toll road concessions."
Economics Letters 101(3): 172-174.

131
12. Auriol, E. and P. M. Picard (2013). "A theory of BOT concession contracts."
Journal of Economic Behavior & Organization 89: 187-209.

13. Baird, A. J. (2013). "Acquisition of UK ports by private equity funds." Research


in Transportation Business & Management 8: 158-165.

14. Bao, H., Y. Peng, et al. (2014). "An alternative incomplete information
bargaining model for identifying the reasonable concession period of a BOT
project." International Journal of Project Management.

15. Boeing Singh, L. and S. N. Kalidindi (2006). "Traffic revenue risk management
through Annuity Model of PPP road projects in India." International Journal of
Project Management 24(7): 605-613.

16. Bourguignon, C. (2013). "Leases, concessions, and authorizations. Searching for


an alternative to the privatization of federal domain in Brazil." Land Use Policy
33: 100-110.

17. Bray, D. and C. Mulley (2013). "Workshop 4: Designing contracts/concessions:


What has worked and what has not and why?" Research in Transportation
Economics 39(1): 226-231.

18. Brown, A. C. (2012). "Concessions, Markets and Public Policy in the Brazilian
Power Sector." The Electricity Journal 25(9): 67-81.

19. Buffie, E. F. (1995). "Trade liberalization,credibility and self-fulfilling failures."

20. Burke, R. and I. Demirag (2015). "Changing perceptions on PPP games:


Demand risk in Irish roads." Critical Perspectives on Accounting 27: 189-208.

21. Cabrera, M., A. Suárez-Alemán, et al. (2015). "Public-private partnerships in


Spanish Ports: Current status and future prospects." Utilities Policy 32: 1-11.

22. Cai, W. and X. Lu (2015). "Housing affordability: Beyond the income and price
terms, using China as a case study." Habitat International 47: 169-175.

23. Caicedo, F. and A. Diaz (2013). "Case analysis of simultaneous concessions of


parking meters and underground parking facilities." Transportation Research
Part A: Policy and Practice 49: 358-378.

24. Cantos-Sánchez, P., R. Moner-Colonques, et al. (2011). "Viability of new road


infrastructure with heterogeneous users." Transportation Research Part A: Policy
and Practice 45(5): 435-450.

25. Carbonara, N., N. Costantino, et al. (2014). "Concession period for PPPs: A
win–win model for a fair risk sharing." International Journal of Project
Management 32(7): 1223-1232.

132
26. Casarin, A. A., J. A. Delfino, et al. (2007). "Failures in water reform: Lessons
from the Buenos Aires's concession." Utilities Policy 15(4): 234-247.

27. Chen, A. and K. Subprasom (2007). "Analysis of regulation and policy of


private toll roads in a build-operate-transfer scheme under demand uncertainty."
Transportation Research Part A: Policy and Practice 41(6): 537-558.

28. Chissano, M. P. H. and J. Minnery (2014). "Roads, rates and development:


Urban roads and growth in Xai-Xai, Mozambique." Habitat International 42: 48-
57.

29. Chou, J.-S., H. Ping Tserng, et al. (2012). "Critical factors and risk allocation for
PPP policy: Comparison between HSR and general infrastructure projects."
Transport Policy 22: 36-48.

30. Claude Crampes a, Antonio Estache ba IDEI and Gremaq "Regulatory trade-offs
in the design of concession contracts."

31. Cruz, C. O. and R. C. Marques (2013). "Flexible contracts to cope with


uncertainty in public–private partnerships." International Journal of Project
Management 31(3): 473-483.

32. Daniel Albalate, G. B. n., Xavier Fageda (2015). "When supply travels far
beyond demand: Causes of oversupply in Spain's transport infrastructure."

33. Davenport, P. (2002). "Fundamentals of Building Contract Management 2002."

34. de Brux, J. (2010). "The Dark and Bright Sides of Renegotiation: An


Application to Transport Concession Contracts." Utilities Policy 18(2): 77-85.

35. de Lemos, T., D. Eaton, et al. (2004). "Risk management in the Lusoponte
concession—a case study of the two bridges in Lisbon, Portugal." International
Journal of Project Management 22(1): 63-73.

36. De Marco, A., G. Mangano, et al. (2012). "Factors influencing the equity share
of build‐operate‐transfer projects." Built Environment Project and Asset
Management 2(1): 70-85.

37. Demirag, I., I. Khadaroo, et al. (2011). "Risks and the financing of PPP:
Perspectives from the financiers." The British Accounting Review 43(4): 294-
310.

38. DuBay, K. H. and P. L. Geissler (2009). "Calculation of proteins' total side-


chain torsional entropy and its influence on protein-ligand interactions." J Mol
Biol 391(2): 484-497.

39. Ekambaram Palaneeswaran, M. M. K., Xue Qing Zhang (2001). "Reforging


construction supply chains:
133
40. a source selection perspective."

41. Ezzine de Blas, D. and M. Ruiz Pérez (2008). "Prospects for Reduced Impact
Logging in Central African logging concessions." Forest Ecology and
Management 256(7): 1509-1516.

42. Fairbrother, S. D. a. P. (2003). "Private Finance Initiative (PFI) and Public


Private Partnerships (PPPs): Definitions and Sources."

43. Farnad Nasirzadeh, M. K., Majid Alipour (2014). "Determination of Concession


Period in Build-Operate-
44. Transfer Projects Using Fuzzy Logic ".

45. Felton, A. M., A. Felton, et al. (2010). "The role of timber tree species in the
nutritional ecology of spider monkeys in a certified logging concession,
Bolivia." Forest Ecology and Management 259(8): 1642-1649.

46. Ferrari, C., P. P. Puliafito, et al. (2013). "Performance and quality indexes in the
evaluation of the terminal activity: A dynamic approach." Research in
Transportation Business & Management 8: 77-86.

47. Ferreira, A., L. d. Picado-Santos, et al. (2011). "Selection of pavement


performance models for use in the Portuguese PMS." International Journal of
Pavement Engineering 12(1): 87-97.

48. G. Maughaqa T. J. Price, n. S. D. P. G. R. (1997). "Transportation Policy-How


Acting Locally Can Be Beneficial: The Rhymney Valley, South Wales as an
Example."

49. Geenen, S. (2014). "Dispossession, displacement and resistance: Artisanal


miners in a gold concession in South-Kivu, Democratic Republic of Congo."
Resources Policy 40: 90-99.

50. Geraldi, J., H. Maylor, et al. (2011). "Now, let's make it really complex
(complicated)." International Journal of Operations & Production Management
31(9): 966-990.

51. Guasch, J. L., J.-J. Laffont, et al. (2008). "Renegotiation of concession contracts
in Latin America." International Journal of Industrial Organization 26(2): 421-
442.

52. Hanaoka, S. and H. P. Palapus (2012). "Reasonable concession period for build-
operate-transfer road projects in the Philippines." International Journal of Project
Management 30(8): 938-949.

53. Hu, H. and Y. Zhu (2015). "Social Welfare–Based Concession Model for
Build/Operate/Transfer Contracts." Journal of Construction Engineering and
Management 141(1): 04014064.
134
54. Hwang, B.-G., X. Zhao, et al. (2013). "Public private partnership projects in
Singapore: Factors, critical risks and preferred risk allocation from the
perspective of contractors." International Journal of Project Management 31(3):
424-433.

55. Institute, V. T. P. "Transportation Cost and Benefit Analysis II – Roadway Costs


".

56. IPDF (2006). "Facilitating and Promoting Viable, Sustainable and Affordable
Public Private Partnerships in Pakistan."

57. Iseki, H. and R. Houtman (2012). "Evaluation of progress in contractual terms:


Two case studies of recent DBFO PPP projects in North America." Research in
Transportation Economics 36(1): 73-84.

58. Jain, G. (2014). "The role of private sector for reducing disaster risk in large
scale infrastructure and real estate development: Case of Delhi." International
Journal of Disaster Risk Reduction.

59. Jin, X.-H. and G. Zhang (2011). "Modelling optimal risk allocation in PPP
projects using artificial neural networks." International Journal of Project
Management 29(5): 591-603.

60. Jolly, S. and R. P. J. M. Raven (2015). "Collective institutional entrepreneurship


and contestations in wind energy in India." Renewable and Sustainable Energy
Reviews 42: 999-1011.

61. Junge, J. and D. Levinson (2013). "Property tax on privatized roads." Research
in Transportation Business & Management 7: 35-42.

62. Kang, C.-C. and C.-M. Feng (2009). "Risk measurement and risk identification
for BOT projects: A multi-attribute utility approach." Mathematical and
Computer Modelling 49(9-10): 1802-1815.

63. Kang, C.-C., C.-M. Feng, et al. (2011). "A royalty negotiation model for BOT
(build–operate–transfer) projects: The operational revenue-based model."
Mathematical and Computer Modelling 54(9-10): 2338-2347.

64. Karim, N. A. A. (2011). "risk allocation in public-private partnership (PPP)


project: a review on risk factors".

65. Karsenty, A., I. G. Drigo, et al. (2008). "Regulating industrial forest concessions
in Central Africa and South America." Forest Ecology and Management 256(7):
1498-1508.

135
66. Ke, Y., S. Wang, et al. (2010). "Preferred risk allocation in China’s public–
private partnership (PPP) projects." International Journal of Project Management
28(5): 482-492.

67. Khanzadi, M., F. Nasirzadeh, et al. (2012). "Integrating system dynamics and
fuzzy logic modeling to determine concession period in BOT projects."
Automation in Construction 22: 368-376.

68. Kordi, M. and S. A. Brandt (2012). "Effects of increasing fuzziness on analytic


hierarchy process for spatial multicriteria decision analysis." Computers,
Environment and Urban Systems 36(1): 43-53.

69. Lemaire, X. (2011). "Off-grid electrification with solar home systems: The
experience of a fee-for-service concession in South Africa." Energy for
Sustainable Development 15(3): 277-283.

70. Liu, T. and S. Wilkinson (2014). "Large-scale public venue development and the
application of Public–Private Partnerships (PPPs)." International Journal of
Project Management 32(1): 88-100.

71. Lopes, A. I. and T. Teixeira Caetano (2015). "Firm-level conditions to engage in


public-private partnerships: What can we learn?" Journal of Economics and
Business 79: 82-99.

72. Maffii, S. and R. Parolin (2010). "Applying social marginal costs pricing to the
road sector." Research in Transportation Economics 30(1): 38-42.

73. Maltby, T. (2013). "European Union energy policy integration: A case of


European Commission policy entrepreneurship and increasing
supranationalism." Energy Policy 55(100): 435-444.

74. McCay, B. J., F. Micheli, et al. (2014). "Cooperatives, concessions, and co-
management on the Pacific coast of Mexico." Marine Policy 44: 49-59.

75. Mohammad Sadegh Asgari, A. A. (2008). "Modeling Subcontractors


Cooperation in Time; Cooperative Game Theory Approach."

76. Monios, J. and R. Bergqvist (2015). "Intermodal terminal concessions: Lessons


from the port sector." Research in Transportation Business & Management 14:
90-96.

77. MWAA (2012). "Dulles International A International Airport: 2012 Governor’s


Transportation Conference Virginia."

78. NCHRP (2009). "Public Sector Decision Making for Public–Private


Partnerships."

136
79. Ng, S. T., J. Xie, et al. (2007). "A simulation model for optimizing the
concession period of public–private partnerships schemes." International Journal
of Project Management 25(8): 791-798.

80. NHA (2009). "NHA PPP Policy and Regulatory Framework."

81. NHA (2012). "Connecting road network for new Benazir Bhutto International
Airport (NBBIA) Islamabad through public private partnership (PPP)."

82. NHA (2013). "LIST OF PPP PROJECTS 2013."

83. NHA (2013). "Treatment-Costs-2012-13."

84. Nieto-Morote, A. and F. Ruz-Vila (2012). "A fuzzy multi-criteria decision-


making model for construction contractor prequalification." Automation in
Construction 25: 8-19.

85. Niu, B. and J. Zhang (2013). "Price, capacity and concession period decisions of
Pareto-efficient BOT contracts with demand uncertainty." Transportation
Research Part E: Logistics and Transportation Review 53: 1-14.

86. Nombela, G. and G. de Rus (2004). "Flexible-term contracts for road


franchising." Transportation Research Part A: Policy and Practice 38(3): 163-
179.

87. Patel, U. R. and S. Bhattacharya (2010). "Infrastructure in India: The economics


of transition from public to private provision." Journal of Comparative
Economics 38(1): 52-70.

88. Post, T. C. (2013). "THSR calls on gov't to extend concession period."

89. Rangel, T., J. M. Vassallo, et al. (2013). "The influence of economic incentives
linked to road safety indicators on accidents: the case of toll concessions in
Spain." Accid Anal Prev 59: 529-536.

90. Rocha, K., A. R. B. Moreira, et al. (2006). "The market value of forest
concessions in the Brazilian Amazon: a Real Option approach." Forest Policy
and Economics 8(2): 149-160.

91. Rodriguez-Oreggia, E. and A. Rodriguez-Pose (2004). "The Regional Returns of


Public Investment Policies in Mexico." World Development 32(9): 1545-1562.

92. Roehrich, J. K. and N. D. Caldwell (2012). "Delivering integrated solutions in


the public sector: The unbundling paradox." Industrial Marketing Management
41(6): 995-1007.

137
93. Rolim, F., E. Santos, et al. (2014). "Competitiveness in the Invitation to Bid for
the Concession of the Urban Bus System of the Metropolitan Region of Recife."
Procedia - Social and Behavioral Sciences 160: 160-169.

94. Ross, T. J. (2004). "Fuzzy logic with engineering applications."

95. Rossi, M. and R. Civitillo (2014). "Public Private Partnerships: A General


Overview in Italy." Procedia - Social and Behavioral Sciences 109: 140-149.

96. Rouhani, O. M., D. Niemeier, et al. (2013). "Integrated modeling framework for
leasing urban roads: A case study of Fresno, California." Transportation
Research Part B: Methodological 48: 17-30.

97. Santos, G., H. Behrendt, et al. (2010). "Part I: Externalities and economic
policies in road transport." Research in Transportation Economics 28(1): 2-45.

98. Sanz, L. D. B. (2014). "Working Conditions of Microbus Drivers in Mexico


City as a Risk Factor in Road Safety." Procedia - Social and Behavioral Sciences
160: 188-194.

99. Scandizzo, P. L. and M. Ventura (2010). "Sharing risk through concession


contracts." European Journal of Operational Research 207(1): 363-370.

100. Siguaw, J. A., S. E. Kimes, et al. (2003). "B2B sales force productivity:
applications of revenue management strategies to sales management." Industrial
Marketing Management 32(7): 539-551.

101. Smith, W. a. (1998). "Life-Cycle Cost Analysis."

102. Spiridoula Marinou, M. g., Greece "Project Risk Management".

103. Subramanian, N. and R. Ramanathan (2012). "A review of applications of


Analytic Hierarchy Process in operations management." International Journal of
Production Economics 138(2): 215-241.

104. Synthesis, T. R. (2013). "The Use of Life-Cycle Cost Analysis to Evaluate


Public-Private Partnerships."

105. Takim, R. (2009). "The Malaysian Private Finance Initiative and Value for
Money."

106. Tan, Z. and H. Yang (2012). "Flexible build-operate-transfer contracts for road
franchising under demand uncertainty." Transportation Research Part B:
Methodological 46(10): 1419-1439.

107. Tang, L., Q. Shen, et al. (2010). "A review of studies on Public–Private
Partnership projects in the construction industry." International Journal of
Project Management 28(7): 683-694.
138
108. Taylor, P. L. (2010). "Conservation, community, and culture? New
organizational challenges of community forest concessions in the Maya
Biosphere Reserve of Guatemala." Journal of Rural Studies 26(2): 173-184.

109. Theodor J Stewarta, Simon Frenchb,1, Jesus Riosc (2013). "Integrating


Multicriteria Decision Analysis and Scenario Planning – Review and
Extension."

110. Ubbels, B. and E. T. Verhoef (2008). "Auctioning concessions for private


roads." Transportation Research Part A: Policy and Practice 42(1): 155-172.

111. Vassallo, J. M. (2010). "The role of the discount rate in tendering highway
concessions under the LPVR approach." Transportation Research Part A: Policy
and Practice 44(10): 806-814.

112. Verhoef, E. T. (2007). "Second-best road pricing through highway franchising."


Journal of Urban Economics 62(2): 337-361.

113. Viegas, J. M. (2010). "Questioning the need for full amortization in PPP
contracts for transport Infrastructure." Research in Transportation Economics
30(1): 139-144.

114. Wang, G. W. Y. and A. A. Pallis (2014). "Incentive approaches to overcome


moral hazard in port concession agreements." Transportation Research Part E:
Logistics and Transportation Review 67: 162-174.

115. Wang, G. W. Y., A. A. Pallis, et al. (2014). "Incentives in cruise terminal


concession contracts." Research in Transportation Business & Management 13:
36-42.

116. Wang, Y. (2015). "Evolution of public–private partnership models in American


toll road development: Learning based on public institutions' risk management."
International Journal of Project Management 33(3): 684-696.

117. WilliamF.Messier Jr. a, b., 1, Jesse C. Robertson c,2, Chad A. Simon d "The
effects of client management concessions and ingratiation attempts on auditors'
trust and proposed adjustments."

118. Willoughby, C. (2013). "How much can public private partnership really do for
urban transport in developing countries?" Research in Transportation Economics
40(1): 34-55.

119. Witold Pedrycz, P. P. E. a. R. P. "Fuzzy multicriteria decision-making models,


methods and applications."

139
120. Xu, Y., C. Sun, et al. (2012). "System Dynamics (SD) -based concession pricing
model for PPP highway projects." International Journal of Project Management
30(2): 240-251.

121. Yang, J.-B., C.-C. Yang, et al. (2010). "Evaluating schedule delay causes for
private participating public construction works under the Build-Operate-Transfer
model." International Journal of Project Management 28(6): 569-579.

122. Yu, C. Y. and K. C. Lam (2013). "A Decision Support System for the
determination of concession period length in transportation project under BOT
contract." Automation in Construction 31: 114-127.

123. Zawawi, N. A. W. A., A. A. Umar, et al. (2014). "PFI Procurement Skills: A


Cross-sector Survey of Practitioners." Procedia Engineering 77: 170-178.

124. Zhang, X. (2011). "Web-based concession period analysis system." Expert


Systems with Applications.

125. Zhang, X. and S. M. AbouRizk (2006). "Determining a reasonable concession


period for private sector provision of public works and service." Canadian
Journal of Civil Engineering 33(5): 622-631.

126. Zhang, X. and S. Chen (2013). "A systematic framework for infrastructure
development through public private partnerships." IATSS Research 36(2): 88-
97.

127. Zhao, Z.-Y., J. Zuo, et al. (2013). "Factors influencing the success of BOT
power plant projects in China: A review." Renewable and Sustainable Energy
Reviews 22: 446-453.

128. Karim, N. A. A. (2011). "RISK ALLOCATION IN PUBLIC-PRIVATE


PARTNERSHIP (PPP) PROJECT: A REVIEW ON RISK FACTORS ".

129. University, S. (2005). "GUIDELINES FOR LIFE CYCLE COST ANALYSIS."

130. Wang, Y. (2015). "Evolution of public–private partnership models in American


toll road development: Learning based on public institutions' risk management."
International Journal of Project Management 33(3): 684-696.

131. Andersen, David F. Ik J. Chung, George P. Richardson, and Thomas R. Stewart.


1990. "Issues in Designing Interactive Games Based on System Dynamics
Models." pp. 31-45. In: David F. Andersen, George P. Richardson, and John D
140
Sterman, eds. System Dynamics ‘90 -- Proceedings of the 1990 International
Conference of the System Dynamics Society. Chestnut Hill, Massachusetts. July
10-13, 1990.

132. Armstrong, J. Scott. 1985. Long-Range Forecasting. New York: John Wiley and
Sons, Inc.

133. Eberlein, Robert, James Hines, Richard Ho, James Melhuish and George P.
Richardson. 1996. "Modeling with Molecules." Available on the World Wide
Web at: http://news.std.com/vensim/MOLDOC.HTM.

134. Systems Thinker. 19XX. "Guidelines for Drawing Causal Loop Diagrams." 3(1).

135. Wagenaar, W. and H. Timmeri. 1979. "The Pond and Duckweed Problem: Three
Experiments in the Misperception of Exponential Growth." Acta
Psychologica 43: 239-251.

136. Wolstenholme, Eric. F. and D. A. Corben. 1993. "Towards a Core Set of


Archetypal Structures in System Dynamics." pp. 583-588. In: Enrique Zepeda
and José A. D. Machuca, eds. The Role of Strategic Modeling in International
Competitiveness. Proceedings of the 1993 System Dynamics Conference.
Cancún, Mexico.

141
APPENDIX 1
Factors affecting the concession period of PPP Projects
This form assesses the effects of various factors on the concession period of PPP based
Highway Projects.

Please select Yes or No

If yes please assign a score out of 10 depending upon its impact on the length of
concession period.

Where 1=lowest influence, 10= highest influence

Your Name: ______________________

Country of residence: __________________

S/No Questions/Factors Yes /No Score


1 Does "Toll price" affect the length of concession period of Y / N 1 2 3 4 5 6 7 8 9 10
PPP projects?
2 Does "Operation period" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10
period of PPP projects?

3 Does "Project development cost" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10


concession period of PPP projects?

4 Does "Construction cost" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

5 Does "Revenue stream" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

6 Does "Market demand" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

7 Does "Net Present value of project" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10


concession period of PPP projects?

8 Does "Return on investment" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

9 Does "Discount rate" affect the length of concession period Y / N 1 2 3 4 5 6 7 8 9 10


of PPP projects?

10 Do "Severity of risks involved" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10


concession period of PPP projects?

142
11 Does "Economic viability" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10
period of PPP projects?

12 Does "Operation cost" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

13 Does "Operational life of project" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10


concession period of PPP projects?

14 Does "Sale price" affect the length of concession period of Y / N 1 2 3 4 5 6 7 8 9 10


PPP projects?

15 Does "Market situation" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

16 Does "Service price" affect the length of concession period Y / N 1 2 3 4 5 6 7 8 9 10


of PPP projects?

17 Does "Profitability" affect the length of concession period Y / N 1 2 3 4 5 6 7 8 9 10


of PPP projects?

18 Do "O & M costs" affect the length of concession period of Y / N 1 2 3 4 5 6 7 8 9 10


PPP projects?

19 Does "Operation revenue in year" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10


concession period of PPP projects?

20 Does "Construction period" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

21 Does "Size of investment" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

22 Does "Income in year" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

23 Does "Size of project" affect the length of concession period Y / N 1 2 3 4 5 6 7 8 9 10


of PPP projects?

24 Does "Construction period" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

25 Do "No of vehicles" affect the length of concession period Y / N 1 2 3 4 5 6 7 8 9 10


of PPP projects?

26 Does "Complexity of project" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10


concession period of PPP projects?

27 Does "Risk management maturity of concessionaire" affect Y / N 1 2 3 4 5 6 7 8 9 10


the length of concession period of PPP projects?

143
28 Does "Government’s interest" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10
concession period of PPP projects?

29 Does "Inflation rate" affect the length of concession period Y / N 1 2 3 4 5 6 7 8 9 10


of PPP projects?

30 Does "Political influence" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

31 Does "Adequacy of funding" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

32 Does "Population in area" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

33 Does "Corruption" affect the length of concession period of Y / N 1 2 3 4 5 6 7 8 9 10


PPP projects?

34 Does "Type of project" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

35 Do "Lack of clear government objectives and Y / N 1 2 3 4 5 6 7 8 9 10


commitments" affect the length of concession period of PPP
projects?
36 Does "Strength of the consortium" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10
concession period of PPP projects?

37 Does "Equity allocation" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

38 Do "Poorly defined sector policies" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10


concession period of PPP projects?

39 Does "Traffic congestion" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

40 Does "Constructability of project" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10


concession period of PPP projects?

41 Does "Lack of competition" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

42 Does "Capital structure of company" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10


concession period of PPP projects?

43 Do "Difference in guarantees" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10


concession period of PPP projects?

44 Does "Credibility of government policies" affect the length Y / N 1 2 3 4 5 6 7 8 9 10


of concession period of PPP projects?

144
45 Does "Procurement" affect the length of concession period Y / N 1 2 3 4 5 6 7 8 9 10
of PPP projects?

46 Does "Strength of SPV" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

47 Does "Effectiveness of Government" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10


concession period of PPP projects?

48 Does "Investment attraction" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

49 Does "Entrepreneurship and leadership" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10


concession period of PPP projects?

50 Do "Construction logistics" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

51 Does "Social welfare" affect the length of concession period Y / N 1 2 3 4 5 6 7 8 9 10


of PPP projects?

52 fication" affect the length of


Does "Right project identi Y / N 1 2 3 4 5 6 7 8 9 10
concession period of PPP projects?

53 Does "Site limitation" affect the length of concession period Y / N 1 2 3 4 5 6 7 8 9 10


of PPP projects?

54 Does "Innovative design" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

55 Do "Number of partners" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

56 Does "Poor transparency" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

57 Does "Travel time" affect the length of concession period of Y / N 1 2 3 4 5 6 7 8 9 10


PPP projects?

58 Does "Project’s promotion" affect the length of concession Y / N 1 2 3 4 5 6 7 8 9 10


period of PPP projects?

59 Does "Organization structure of project" affect the length of Y / N 1 2 3 4 5 6 7 8 9 10


concession period of PPP projects?

145
APPENDIX 2

Improving the decision making for the length of Concession period of


PPP Projects
Respondent’s Name: _______________________________________
Designation: ______________________________________________
Organization: _____________________________________________
Project’s Name: ___________________________________________
Original Concession period: __________________________________
Have you used/considered the NPV technique for the concession period
estimation (Yes/ No): _______________________________________________
Please fill the following table in accordance to your project:

S/No Factors Considered Increase Decrease %


(Yes/No) Increase/Decrease
1 Revenue Stream Yes No

2 Project Income Yes No

3 Market Situation Yes No

4 Severity of Yes No
involved risks

5 Investment size Yes No

146
Modified Concession Period 23.915 20.706
K value 0.9566 1.0353
Effect 1 1.1
Investment size No change 10% Increase
Effect 1 1.15
Severity of involved risks No change 15% Increase
Effect 1 1
Market Situation No change No change
Effect 0.9 1
Responses

Project Income 10% Increase No Change

147
Effect 0.89 1.05
Revenue Stream 11% Increase 5% Decrease
Orignal Concession Period 25 20
(Years)
NPV Technique Used Yes Yes
Project’s Name Lahore-Sheikhopora-Faisalabad Dual M-2 Overlay and Rehabilitation
Carriage way
Organization PMO NUST FWO
Designation DD Construction DPM
Respondent’s Name Col .Khalid Baig Maj.Jawad
S/No 1 2
5.829 27.4365 28.56
0.5829 1.09746 1.1424
0.8 1.1 1.1
20% Decrease 10 % Increase 10% Increase
0.3 1.3 1.4
70% Decrease 30% Increase 40% Increase
0.5 1.08 1.3
50% Increase 8% decrease 30% decrease
0.3 1.15 1.1
70% Increase 15% decrease 10% decrease

148
0.5 1 1.2
50% Increase No change 20% decrease
10 25 25
Yes Yes Yes
Habibabad Project Lahore Sialkot Motorway M-9 Motorway
NHA NHA NHA
Director PPP Director PPP Director PPP
M.Azeem M.Azeem M.Azeem
3 4 5
149

You might also like