Professional Documents
Culture Documents
Quickly and without the need for control during the sequence
WARNING:
• Safety Systems do not eliminate all hazards (e.g. hot spots)
• Safety Systems sequence must be safe in itself and lead to a safe and
stable final status
• Special cases (e.g. down-graded mode of operation or simultaneous
operation) cannot always be covered by safety systems
Reliability
AVAILABILITY
RELIABILITY
Safety Integrity Level (SIL) Average Probability of Failure on Demand
4 10-5 to 10-4
3 10-4 to 10-3
2 10-3 to 10-2
1 10-2 to 10-1
I/O I/O
LOGIC SOLVER
PSHH SDV
LOGIC FINAL
SENSORS
SOLVER ELEMENT
(PSHH…)
(P.L.C.) (SDV…)
Recommended figures:
• Availability of the whole loop between 99% and 99.9%
• Availability of the solver between 99.9% and 99.99%
Warning
• High availability figures are useless if safety systems are too difficult
to repair (high qualified technician or vendor’s representative)
TOOL EFFECT
Voting 1ooN increases reliability
MooN decreases spurious trips
Redundancy Increases MTBF (Mean Time Between Failure)
(availability)
Diversification Decreases common mode failures
Testing Increases testing frequency decreases probability failure
on demand
On-line repair Increases drastically MTBF (availability)
Fault coverage Decreases probability of failure upon demand
Fault tolerance Increases MTBF and reliability
Independency Increases MTBF and reduce risk of operator errors
1 Programmable Logic Controller for the PCS and PSS: for redundancy
and independency
• Segregation of the I/O cards, racks and processors
• SIL 2
1 PLC for the ESD, 1 PLC for the F&G: for independency and redundancy
• SIL 3
PSD ESD
ESD0 ESD1 F&G initiators
FIELD PKGE PB PB
initiators
(1)
1
Actions
T T Actions links
Data (3) (3)
logic
PCS 2 PSS USS ESD Data
F&G solvers
Solid State SIL 3 SIL 3
SIL 2 (5) (5)
(4) links
FIELD PKGE SDV ’s PKGE ESDV ’s ESDV ’s ESDV ’s Electrical Fire HVAC
terminal motors BDV ’s BDV ’s BDV ’s breakers fighting
elements UPS Power Grid Large Motors Final
Power Grid elements
PKGE (2)
Process Control Process Safety Ultimate Safety Emergency S/D Fire &Gas
HIPS purpose:
• To replace PSV
• A HIPS (or IPPS) is made up of dedicated components for detection
of the overpressure and isolation by SDVs/ ESDVs
• The HIPS components shall be independent from the PCS, PSD and
the ESD systems, with the exception of the SDVs and ESDVs which
can be used for both the HIPS and ESD (or PSD)
1st Barrier
(instrum) 2nd Barrier
(mechanical)
Failure scenario:
PSS
Choke fails open
Subsea
Pipeline
Liquids
1st Barrier
2nd Barrier (instrum)
(instrum)
PSS
HIPS
LOGIC
Topside PSHH
Choke
SDV Gas
PSHH PSHH PSHH
Riser
ESDV
Subsea
Pipeline
Liquids
HIPS FAILURE
6.84 E-04
5.48E -06
CCF
CCF of
CCF of
Human
of PS HIPS failure
From inlet
manifold
DS301 1st Stage DS351
separator
EC301 A/B
SDV
SDV SDV LV1/2 LV1/2 SDV SDV
3506
SDV 3007 3002 3005 3508 3508 3507
3008 SDV
•PSHH3028 3505
SDV •LSHH3026
3003 EC301 DS302 Start-up in 2 phase
2nd stage
Separator
IG401 / DA 401 DS303
ESD2
ADVANTAGES:
• Environment friendly (no release to atmosphere)
DISADVANTAGES:
• Difficulty of controlling risks:
− Reliability calculations cannot take into account all factors (Human
factors & construction errors)
− Must be closely monitored from project to start-up
• Stringent testing and maintenance requirements for operation
Effects
FiFi Deluge HVAC CO2
Alarm ESD1 Pump activated Shut Release ESD2 ESD3
Causes starts Down
FD x x x x x
GD x x x x
SD x x x x
H2SD x
REQUIREMENT:
• Offshore (mandatory), onshore (recommended)
CAUSES:
• Manual activation (PBs)
ACTIONS:
• ESD-1 of all fire zones
− Complete shutdown of all fire zones
Does not stop the diesel fire pumps if these have already started)
− Emergency depressurization (mandatory offshore, optional onshore) of all
fire zones
• Complete de-energization of the installation, including battery powered
systems (except NAVAIDS, emergency lighting, emergency telecom, PAGA)
CAUSES:
• ESD-0
• Manual activation (PBs)
• Gas Detection
• Fire Detection (in process / Hydrocarbon handling areas)
• UPS batteries Low voltage
ACTIONS:
• Complete shutdown of the fire zone: close all ESDVs
• Emergency depressurization (mandatory offshore, optional
onshore) of the fire zone
• ESD-1-F activates fire fighting means in the fire zone
CAUSES:
• ESD-1
• Manual activation (PBs)
• Major process faults
• Flare drum LSHH
• Instrument air PSLL
• Fuel gas PSLL if used to prevent air ingress in flare
• Loss of normal electrical power supply
ACTIONS:
• Shut down all the HC processing equipment, transfer or utility units
• Close SDVs
• Shut down motors
• Shut down some non HC associated equipment (e.g. chemical treatment)
CAUSES:
• ESD-1 of the fire zone
• ESD-2 of the unit
• Manual activation (PBs / local panel)
• FD or GD inside enclosed packages (e.g. gas turbines, gas engines)
• Equipment trip (when not handled by package)
ACTIONS:
• Shuts down package (e.g. compressor)
• Shuts down associated electrical / fired equipment
• Close SDVs
Depressurisation Time:
Initiation of EDP:
• Offshore: automatic upon ESD1
• Onshore: manual or automatic, always in case of ESD1
Interruption:
• Normally, EDP continues till atmospheric pressure is reached, and
BDV’s are locally reset
• EDP remote interruption can however be considered:
− One Push-Button in the control room for each fire zone
− Remote closure of all BDV’s of the fire zone
− Does not stop the other ESD sequences: ESDV’s close, motor shut-
down, electrical shut-off,
ACTIONS
FIRE DETECTION
Outdoors ESD-1 + Activate Fi Fi
Machinery enclosure ESD-3 + Activate Fi Fi + stop HVAC +
close dampers
SMOKE DETECTION
Inside buildings Stop HVAC + close dampers +
Inside technical rooms extinguishing agent release (if any)
PURPOSE
• To provide a highly reliable means of closing the ESDVs and opening
the BDVs
• To avoid common modes of failure in electronic devices and in
control software
HOW?
• Simple, non programmable, hardwired system
• Same push buttons for the USS and ESD
• To de-energise relevant 24V DC, air, hydraulic controls
NOT MANDATORY
• Not for simple installations (wellhead platforms), or if it can be